SUBJECT: ADDISON CIRCLE SUBDIVISION STREET FINISH CENTERLINE
ELEVATION STATEMENT
City of Meridian
We are in receipt of a geo-technical engineering report from Atlas dated February 22„
2024.
The report from Atlas indicates that seasonal high groundwater is anticipated to
remain at depth of greater than 9-feet below ground surface.
2 test pits were dug on the project site.The following identifies the relevant
elevations from the report and construction plans:
Existing ground Elevation Groundwater Elevation
Test Pit 1 2540 2535
The lowest design elevation of the Roadway is 2540.15.
Based on the above information the finish centerline elevations are set a minimum
of three feet above the highest established normal groundwater elevation
Sincerely,
PROSE
Joseph D.Canning,PE.
CEO Centurion Engineers, Inc.