HomeMy WebLinkAbout2024-08-05 AgendaPacket-Transportation Commission Meeting
TRANSPORTATION COMMISSION MEETING
City Council Chambers, 33 East Broadway Avenue Meridian, Idaho
Monday, August 05, 2024 at 3:30 PM
All materials presented at public meetings become property of the City of Meridian. Anyone desiring accommodation
for disabilities should contact the City Clerk's Office at 208-888-4433 at least 48 hours prior to the public meeting.
Agenda
VIRTUAL MEETING INSTRUCTIONS
To join the meeting online: https://us02web.zoom.us/j/81095276712
Or join by phone: 1-253-215-8782
Webinar ID: 810 9527 6712
ROLL-CALL ATTENDANCE
_____ David Ballard _____ John Wasson, Ex-Officio - ACHD
_____ Zachary Shoemaker _____ Lila Klopfenstein, Ex-Officio - COMPASS
_____ Ryan Lancaster _____ Miranda Carson, Ex-Officio - WASD
_____ Walter Steed _____ Alissa Taysom, Ex-Officio - VRT
_____ Tracy Hopkins _____ Justin Price, Ex-Officio - ITD
_____ Stephen Lewis _____ Sgt. Tara Smith - Police
_____ Jared Smith _____ Tishra Murray - Legal
_____ Tom LeClaire _____ Hether Hill – Community Development
_____ Hoyoon Song _____ Caleb Hood – Community Development
ADOPTION OF AGENDA [ACTION ITEM]
APPROVAL OF MINUTES [ACTION ITEM]
1. Approval of Minutes - July 1, 2024
OLD BUSINESS [ACTION ITEM]
2. Transportation Project Updates
3. Draft 2025-2029 IFYWP Update
NEW BUSINESS [ACTION ITEM]
1
4. Lost Rapids/Bird Park
5. September Off-Site Meeting
6. Ex-Officio Updates
7. Staff Communications
FUTURE MEETING TOPICS
8. Franklin, McDermott to Black Cat Project Update
9. VRT Ridership Update
10. ACHD Master Street Map Changes – Arterial Corridor Preservation (Cherry Lane)
11. Capital Investments Citizens Advisory Committee (CICAC) Update
NEXT MEETING (OFF-SITE) - SEPTEMBER 19, 2024
ADJOURNMENT
2
Meeting Minutes
Meridian Transportation Commission
Monday, July 1, 2024
Council Chambers – Meridian City Hall 33 East Broadway Ave., Meridian, Idaho
Roll Call
MEMBERS
☒David Ballard ☒Walter Steed ☒Zach Shoemaker
☒Hoyoon Song ☒Stephen Lewis ☒Tracy Hopkins
☒Jared Smith ☒Tom LeClaire ☐Ryan Lancaster
EX-OFFICIO
☒John Wasson (ACHD) ☒Lila Klopfenstein (COMPASS) ☒Miranda Carson (WASD)
☒Alissa Taysom (VRT) ☒Justin Price (ITD)
OTHERS PRESENT
☒Cpl. Trevor Weitzel (Police) ☒ Tishra Murray (Legal) ☒Caleb Hood (Comm. Dev.)
☒Hether Hill (Comm. Dev.)
Adoption of the Agenda
No changes were made to the agenda by staff or commissioners. Motion to approve by
Commissioner Song, 2nd by Commissioner Ballard. All ayes
Approval of Minutes
1. June 3, 2024
Commissioner Ballard had one question/point of clarification which Ms. Hill addressed. Motion
to approve by Commissioner Hopkins, 2nd by Commissioner Song- all ayes; passes.
Old Business Items
2. Transportation Projects Update – Hether Hill
Ms. Hill began on Page 6 of the packet and recommended the Commission review the updates
provided in bolded text through page 13. Ms. Hill noted there were no significant updates month
over month, with the exception of Ustick – Owhyee Storm to Black Cat project and noted ACHD
staff were present to provide an update during agenda item number 5 . There were no further
questions or comments from the Commission.
3. ACHD Master Street Map Changes: Arterial Corridor Preservation – Caleb Hood
Mr. Hood provided an update and overview of the letter sent to ACHD (included in the packet).
The ACHD Commission approved the proposed changes to the MSM on June 26 th and are
reflected in ACHD’s online mapping tools. Fairview/Cherry right-of-way preservation will be
revisited later this year.
3
Item 1.
4. Linder Road Concept Study – Hether Hill
Ms. Hill provided an update on the recommendation the Transportation Commission (TC)
provided to City Council on the Linder Road Concept Study. ACHD presented to City Council on
June 18th and Council chose Concept #2 (of the options previously presented to the TC). Concept
#2 is the standard 5-lane road without roundabouts. There were no further questions or
comments from the Commission.
New Business Items [ACTION ITEM]
5. Ustick, Owhyee Storm to Black Cat Project Update - Seth Jarsky (ACHD)
Mr. Jarsky provided an update via presentation of the Ustick, Owhyee Storm to Black Cat project,
including community survey results. Discussion ensued following the presentation.
6. Ex-Officio Updates
Lila Klopfenstein – The Transportation Improvement Program (TIP) public comment period is
open July 1st through July 31st, with an open house scheduled for July 15th. Information will be
emailed out to the TC and is available on the COMPASS website.
Miranda Carson – Durham School Services will begin servicing West Ada School District (WASD)
beginning in Fall of 2024 for a 5-year contract. WASD is hosting an on-site hiring and family fun
day on July 3rd.
Alissa Taysom – Valley Regional Transit (VRT) service changes were launched June 3rd, however,
ridership numbers are not yet available. Ridership numbers for Route 24 may be available by the
next TC meeting.
Justin Price – ITD kicked off planning for a public meeting(s) for Eagle Road. Additional details
were not available, however, more information on the public meetings (anticipated for late
August) will be provided soon.
7. September Workshop
Ms. Hill reminded the Commission of the holiday in September and requested any
recommendations/ideas be submitted so a field trip for the Commission could be scheduled.
8. Staff Communications
Staff Communications began on page 15 of the packet, which primarily concerned an intersection
in the Baraya Subdivision. In addition to what was published in the packet, Ms. Hill informed the
Commission that a $500,000 budget request for FY25 was presented to City Council for
implementation of pedestrian and intersection improvement projects identified in the Meridian
Intersection and Pedestrian Safety Task Force Report developed in 2023. Ms. Hill noted additional
scoping and evaluation is needed to implement projects and would take place once and if funding
is secured. Mr. Hood also added that ITD is seeking feedback on the Idaho Transportation
Investment Program (ITIP) with a public comment period of July 1st through July 31st.
FUTURE MEETING TOPICS
9. Lost Rapids/Bird Park
4
Item 1.
10. Franklin, McDermott to Black Cat Project Update
11. Meridian Intersection Pedestrian Safety (MIPS) Task Force Update
12. Master Street Map Update
13. VRT Ridership Update
Next Meeting Date: August 5, 2024
Adjournment; 4:25pm – Motion by Commissioner Song, 2nd by Commissioner Hopkins - all ayes.
(AUDIO RECORDING AVAILABLE UPON REQUEST)
APPROVED:
_______________________ _______________
WALTER STEED, CHAIR DATE
ATTEST:
________________________ _______________
CHRIS JOHNSON (City Clerk) DATE
5
Item 1.
MEMO TO CITY COUNCIL AND
TRANSPORTATION COMMISSION
From: Hether Hill, Coordination Planner Meeting Date: August 5, 2024
Topic: Transportation Project Updates
Below is a summary/update on some of the transportation and roadway City Staff has been involved
with recently. This is not an exhaustive list, but rather highlights some of the more important activities
that have recently transpired (or are about to occur) in the tr ansportation realm. Staff will be at the
Transportation Commission meeting to discuss some of these topics in more detail. Please feel free to
contact staff should you have any comments, concerns, or questions on any of these projects. New
information is in bold.
KEY ACHD PROJECTS
ACHD Integrated Five-Year Work Program: The 2024-2028 IFYWP Draft can be found here:
https://engage.achdidaho.org/integrated-five-year-work-plan-ifywp The City’s request for priority
projects to be included in the 2025 -2029 IFYWP were sent to ACHD by the Mayor on March 14th. It is
anticipated that the Initial Draft of the 2025-2029 IFYWP will be released on July 10th. Public/partner
comment period on the 2025-2029 IFWYP Draft will be July 11th through August 14th, with adoption
planned for September 25th.
Amity Rd and Locust Grove Rd & Amity Road, Meridian to Locust Grove: These projects were
presented to the ACHD Commission on September 13th to discuss the projects status, questions and
concerns from the public, and the letters the City has submitted. Project future is currently unknown
with indefinite pause pending new direction from the ACHD Commission. Project Website:
https://engage.achdidaho.org/amity-road-and-locust-grove-road-intersection
City Staff Contact: Brian McClure, Community Development
Eagle Road, Lake Hazel to Amity: Landscaping within the roundabout at Taconic will be included in the
Cost Share Permit. 95% design is complete. Widen Eagle to 5 lan es with curb, gutter, sidewalk and a
multi-use pathway. Includes a multi-lane roundabout at Eagle Rd and Taconic Dr. On 90-day
construction bid list for June 2024 with notice to proceed in September. Project website:
https://engage.achdidaho.org/eagle-road-lake-hazel-road-to-amity-road.City Staff Contact: Brian
McClure, Community Development
6
Item 2.
Fairview, Jericho Road to Eagle & Locust Grove/Fairview Signal: Widen intersection to 9 lanes on
Fairview and 7 lanes on Locust Grove. Widen Fairview to 7 lanes with curb, gutter, sidewalk and Level 3
bike facility. Currently in ROW phase; construction is expected to start 2029. This project is
exceptionally complex with multiple curbs, materials, and elevations. Z-crossing just west of
Fairview/Webb in design. Here is a link to the project website: https://engage.achdidaho.org/fairview-
avenue-jericho-road-to-eagle-road
City Staff Contact: Caleb Hood, Community Development
Franklin, McDermott to Black Cat: Widening Franklin Rd to 5 lanes between McDermott Rd and Black
Cat Rd, and improving the intersection of Franklin Rd and McDermott Rd. The Franklin Rd and
McDermott Rd intersection is a joint project with Nampa Highway District No. 1. City/ACHD
partnership on landscaping in the medians/buffers and future location for a “Welcome to Meridian”
sign being considered. Stormwater swales envisioned behind curb. 30% design complete with project
team meeting on November 20th. Design in FY24-25, Right of Way in FY28-29, notice to proceed
scheduled for future. Posted speed to be 35 MPH but no design elements contemplated to support.
Here is a link to the project website: https://engage.achdidaho.org/franklin-road-mcdermott-road-
to-black-cat-road?utm_campaign=&utm_medium=email&utm_source=govDelivery
City Staff Contact: Brian McClure, Community Development
Lake Hazel and Eagle Signal: The design includes significant grade changes of the existing intersection
and will integrate large retaining walls. Widen and signalize intersection to 4/5 lanes on Eagle and 3/4
lanes on Lake Hazel with multiuse pathway connections. Project will be constructed as part of Eagle
Road, Lake Hazel to Amity widening. On 90-day construction bid list for June 2024 with notice to
proceed in September. Project website: https://engage.achdidaho.org/lake-hazel-and-eagle-
intersection.
City Staff Contact: Brian McClure, Community Development
Lake Hazel Road, Locust Grove Road to Meridian Road: Brighton owns multiple parcels of land between
S Apex Avenue and S Meridian Road. Per their requirements from the City of Meridian they are
required to complete a significant utility upgrade that will require the roadway be reconstructed. ACHD
Commission has approved a Cooperative Development Agreement for the reconstruction and widening
of E Lake Hazel Road between S Apex Avenue and S Meridian Road to 5 -lanes, with 10-foot wide
concrete multi-use pathways on both sides of the road. Lake Hazel is currently closed in this section for
related improvements.
Lake Hazel Road, Eagle to Cloverdale: Widen Lake Hazel Rd to five 11’ lanes with curb gutter and 10’
detached multiuse path on both sides. Bridge improvement included to remove and replace the
existing bridge over the Ten Mile Creek. Project will include swales adjacent to the roadway. Design is
complete. Design 2022-2023; ROW; 2024; Construction 2027. City to cost share on continuous lighting
within Meridian City limits (not Boise). Project Website:
https://engage.achdidaho.org/lake_hazel_eagle_cloverdale.
City Staff Contact: Brian McClure, Community Development
7
Item 2.
Linder, Overland to Franklin (Overpass of I-84): Widen Linder Rd to 5 lanes with a bicycle and
pedestrian facility from Overland Rd to Franklin Rd. Project includes a new I-84 overpass,
improvements to the Overland and Franklin intersections, and connection of W Verbena Dr across
Linder. The City is funding design; design is complete. ROW is programmed at ACHD for 2024-2025 and
construction is programmed for 2026-2027 in the IFYWP. https://engage.achdidaho.org/linder-road-
overpass-franklin-road-to-overland-road The City has been awarded $4.3M from ITD towards
completion of this project. The City and ACHD have entered into an agreement to spend the Strategic
Initiative Funds in 2025.
City Staff Contact: Caleb Hood, Community Development
Linder, Ustick to Pine (concept): The project team met to review concepts. Also, the ACHD Pedestrian
Advisory Group (PAG), ACHD Commissioners, and City staff did an onsite review of the existing
conditions on this stretch of road. In all concepts impacts to some properties would have left
substandard conditions for parking and exacerbated backout parking concerns for all users. Based on
the feedback from the project team and PAG, ACHD is working with consultants to develop new
concepts. New concepts discussed include 3 and 5-lane designs with shared roads, roundabout
couplets for improved safety/access with turning restrictions, and enhanced speed mitigation features
to promote school and park access. A traditional 5-lane design with the most property acquisitions is
also being considered. The Transportation Commission recommended a 5-lane option to Council. On
June 18th, 2024 City Council gave general support for a traditional 5-lane option. A support letter to
ACHD is forthcoming. Project Website: https://engage.achdidaho.org/linder-road-pine-avenue-to-
ustick-road.
City Staff Contact: Brian McClure, Community Development
McMillan/Black Cat Roundabout: Multi-lane roundabout with truck apron, curb, gutter, and 10-foot-
wide multi-use pathways. Crosswalk at each leg with two stage pedestrian crossings and rectangular
rapid flashing beacons (RRFBs) at each pedestrian crossing. City is partnering with ACHD on Tier 1
landscape improvements in the RAB (conduit for now, landscape in the future), splitter islands and 4 -
foot buffer areas. 99% designed. Construction is planned for 2029 in the draft IFYWP.
https://engage.achdidaho.org/mcmillan-and-black-cat-intersection
City Staff Contact: Caleb Hood, Community Development
Star Road Bridges: Replace two bridges over the Five Mile Creek and Five Mile Feeder. Bridge width will
support future widening to 5-lanes and a type 3 bike facility (MUP). This project is substantially
completed.
Ustick, Ten Mile to Linder: Widen Ustick Rd to 5 lanes with curb, gutter, center medians, and multi-use
pathway from Ten Mile Rd to Linder Rd. Right-of-way is scheduled for 2025 in the adopted IFYWP and
construction is planned for 2026. Median landscaping is being explored by the project team. Concept
includes pedestrian bridge crossing over Five Mile Creek with a signalized crossing at Ustick. Design will
include multiuse pathways. A retaining wall will be necessary along Five Mile Creek. No
sidewalk/pathways along Five Mile creek where retaining wall to be located; connection will rely on
City pathway on north side of creek (in Bridgetower).
https://engage.achdidaho.org/ustick_ten_mile_linder
City Staff Contact: Caleb Hood, Community Development
8
Item 2.
Ustick, Black Cat to Ten Mile: Widen to 5-lanes with center medians. Signalized crossing at Naomi
(location of new ACHD maintenance facility, south of City wastewater facility). The ACHD consultant
has submitted 99% PS&E and documents required for ROW acquisition. ROW acquisition taking the
next several months; CN in FY25. On 90-day construction bid list for September 2024.
https://engage.achdidaho.org/ustick_black_cat_ten_mile
City Staff Contact: Caleb Hood, Community Development
Ustick, Owyhee Storm to Black Cat: Widen to two lanes in each direction, with a center turn lane and
median islands where the center turn lane is not needed for access. Project includes 10 -foot wide
multi-use pathways on each side, curb and gutter. ROW planned for 2026; construction 2027 in the
current IFYWP. Project cost is estimated at $11M. https://engage.achdidaho.org/ustick-road-owyhee-
storm-avenue-to-black-cat-road
City Staff Contact: Caleb Hood, Community Development
ACHD CAPITAL MAINTENANCE
Residential Capital Maintenance includes conducting field reconnaissance and collecting survey data to
determine an improvement strategy for deteriorated/non -compliant facilities such as: pavement,
drainage, pipes, sidewalks, ramps. ACHD aims for bringing the segments up to Complete Streets
standards where possible. Existing non-compliant pedestrian ramp and driveway access points located
along each roadway segment will be identified to be upgraded to meet ADA compliance. Reasonable
attempts will be made to improve each pedestrian ramp as directional, not diagonal.
Meridian Downtown Pavement and Pedestrian Improvements (2024): Formerly named: “FY2022
Residential Capital Maintenance”. The project goal is to rehabilitate pavement and add pedestrian
improvements including sidewalk and bulb-outs. Segments include: W 3rd St, W Pine to north end; E
Broadway Ave, E 3rd to E 6th; W Cherry Ave, NW 4th St to Meridian Rd; W Idaho Ave, W 8th St to N
Meridian Rd; W Maple Ave, W 1st St to N Meridian Rd; W 2nd St, W Cherry Ave to W Cherry Ln; NW 4th
S, W Broadway Ave to Maple Ave. https://engage.achdidaho.org/2022-residential-capital-maintenance
Segments E Washington Ave, NW 7th to Meridian Rd; NW 7th St, W Washington St to middle school
micro-path (currently adding sidewalk, no pavement rehab, could change); and W 6th St, W
Washington St to W Carlton Ave are also part of this project, bu t have a separate web page:
https://engage.achdidaho.org/washington-street-and-6th-street City Staff Contact: Caleb Hood,
Community Development
Residential Pavement and Pedestrian Improvements (2026): Segments included: 1st St W, south end to
Franklin Road; Rose Circle; Country Terrace Way S, south end to Overland Road; Blossom Pl, south end
to W McGlinchey Ave; McGlinchey Ave, Blossom Pl to NW 8th St; Interlachen Ct, west end to
Interlachen Way; Laurel Ct, south end to Verbena Dr; Tobago Ct. E., west end to SE 5 th Way; Larkspur
Ct, south end to Verbena Dr; Lilac St, south end to Waltman St; Lavender Ct, south end to Verbena Dr;
Sugar Creek, south end to Sugar Creek Dr; Lawndale Dr, McGlinchey Ave to Crestmont Dr; Cruser Dr,
west end to Five Mile Rd; and Francine Pl S, Victory Rd to S Francine Ln. ACHD project number: 521060.
Project team meeting held April 12th.
City Staff Contact: Hether Hill, Community Development
9
Item 2.
ITD PROJECTS (Updated by ITD Staff April 2024)
ChindenWest Corridor: This project will result in 4 travel lanes (two in each direction). Widening will
take place to the south of the existing alignment and be constructed to accommodate future widening
to 6 travel lanes (three in each direction) with high-capacity intersections at roads with river crossings.
Project website: US-20/26 ChindenWest | ITD Projects (idaho.gov)
Star Road to ID-16: Improvements include re-aligning and reconstructing US-20/26, constructing
pathways, and relocating nearby irrigation infrastructure. Anticipated completion in spring
2024. Crews are currently finishing the final stage of the Phyliss Canal Bridge. Final paving and
completion of the bridge should be early summer 2024. (Key No. 20367) Re-aligning and reconstructing
US-20/26, constructing pathways, and relocating nearby irrigation infrastructure. Anticipated
completion by end of April 2024. Minor punch list items will remain through early Summer.
ITD Project Manager: JD Lewelling, JD.Lewelling@itd.idaho.gov
Middleton Road to Star Road: Final design for east and west sections were completed in September
and October 2023, respectively. PS&E is scheduled for May 2024 for the east package and for October
2024 for the west package. Construction expected to start in either Fall of 2024 or Spring of 2025
depending upon right-of-way acquisition. Project website:
https://chindenwest.com/middletontostar/. Final design for east and west sections were completed
in September and October 2023, respectively. PS&E is scheduled for mid to late 2024 for both the east
(Key No. 24310) and west (Key No. 24309) packages. Construction expected to start in fall of 2025
depending upon right-of-way acquisition. Construction funding has yet to be identified.
City Staff Contact: Caleb Hood, Community Development
ITD Project Manager: Jeff Nettleton, jeff.nettleton@itd.idaho.gov
Idaho Highway 16 extension, I-84 to U.S. 20/26
Crews continue building new ramps to connect US-20/26 and SH-16 and will continue through spring of
2024. The new bridge over Five Mile Creek is complete. A new pedestrian bridge over Five Mile Creek
east of McDermott Road is complete. The north abutment of the McMillan Overpass will be under
construction this winter. Construction on the US 20/26 and SH 16 interchange should start this
summer. Construction on several irrigation structures such as the Purdam Drain, & Husky Drain will
continue throughout this winter. Foundation work is also starting on bridges over Ten Mile Creek. On
the south end of the project, work is continuing on the center pier of the new I -84 interchange and
ramps between Franklin Road and I-84. Construction is anticipated to be complete 2025 and will
include: Approximately 4.5 miles of highway between U.S. 20/26 and I -84; an interchange at I-84;
signalized intersections at Franklin Road and Ustick Road; reconstruction of the U.S. 20/26 intersection;
overpasses at Cherry Lane, McMillan Road, and the railroad; and minor adjustments to local roads near
SH-16. Project website: itdprojects.idaho.gov/pages/sh16corridor Construction underway on the new I-
84 interchange between Garrity and Ten Mile and widening Franklin Road. The south portion of
Franklin Road widening has recently been concrete paved. The north portion of Franklin Road will be
paved in the next month. Asphalt paving to complete the ramps will begin in the coming weeks.
Contract completion date is Fall 2024. See staff communications for link to video update.
ITD Project Manager: Jeff Ryan, Jeff.Ryan@itd.idaho.gov
Ustick to Chinden: North ramps at US-20/26 will reach completion in early June 2024. McMillan
overpass has approach slabs and concrete railing being worked on. Local Ersatz road construction
10
Item 2.
continues now that Meridian’s water line is installed. Plan to close and build t he new McDermott &
Ustick Intersection May through June 2024. Plan to close and build the McDermott & McMillan
Intersection July through August 2024. Contract completion date is Fall 2025.
ITD Project Manager: Dan Gorley, Dan.Gorley@itd.idaho.gov
Franklin to Ustick: MSE walls started for Cherry Lane overpass. Construction continues on two
bridges over Ten Mile Creek for SH-16 and for Quasi Place road. Construction of railroad bridge will
start soon. Contract completion date is Fall 2025.
ITD Project Manager: Dan Gorley, Dan.Gorley@itd.idaho.gov
Interstate 84 Eastbound Auxiliary Lane, Meridian Interchange to Eagle Interchange : Design is
anticipated to be complete spring 2024. Construction timeline is dependent on funding availability.
This project will add a second on-ramp lane eastbound at Meridian Interchange, an auxiliary (fifth) lane
between Meridian Interchange to Eagle Interchange, and a second off -ramp lane at Eagle Interchange:
Design is anticipated to be complete in spring 2024. A virtual public open house was held February 13 -
28, 2024. Construction timeline is dependent on funding availability. This project will add a second on -
ramp lane eastbound at Meridian Interchange, an auxiliary (fifth) lane between Meridian Interchange
to Eagle Interchange, and a second off-ramp lane at Eagle Interchange.
https://itdprojects.org/projects/i-84-meridian-interchange-to-eagle-interchange-auxiliary-lane/
ITD Project Manager: Mark Wasdahl, Mark.Wasdahl@itd.idaho.gov
FY24 Surface Treatments US 20/26 & SH 44: Sealcoat approximately 107 lane miles of US 20/26 and
SH-44 this summer. This will improve ride quality and extend the pavement lifespan. Project will start
no later than June 14, 2024. A typical sealcoat uses oil heated to 150-185F, but this time we will heat it
to 275-325F. In addition to the increase in oil temperature, the aggregate is also heated and pre -coated
with oil. This new technology makes it possible to do all the work at nighttime, thus greatly reducing
the impact to the traveling public. Sealcoat approximately 107 lane miles of US 20/26 and SH-44 this
summer. This will improve ride quality and extend the pavement lifespan. Project will start no later
than June 14, 2024. A typical sealcoat uses oil heated to 150 -185F, but this time we will heat it to 275-
325F. In addition to the increase in oil temperature, the aggregate is also heated and pre-coated with
oil. This new technology makes it possible to do all the work at nighttime, thus greatly reducing the
impact to the traveling public.
ITD Project Manager: Walter Olin, Walter.Olin@itd.idaho.gov
SH-55 Eagle Road Safety Review: An inter-agency team was assembled to discuss a safety review of
Eagle Road, I-84 to SH-44. The safety review, which included a speed study, was completed at the end
of February 2023. ITD has presented to City Council several times, the last time was on September 5,
2023. ITD shared what was found in the safety review and showed what sign and striping
improvements were made as a result. They also shared that the speed study showed that no change
to the enforceable speed limits on Eagle Rd were recommended. ITD recognizes the city’s concerns
regarding the daily congestion on Eagle Rd and proposed implementing advisory speed limit signage
with flashing beacons. These would be activated during the busiest times of the day. The purpose
would be to alert the public of times when congestion is most likely. After the presentation there were
concerns from the mayor and at least one council member due to advisory speeds not being
enforceable. ITD and the city continue to engage to find the best solution for the traveling public on
Eagle Rd. An additional inter-agency team with law enforcement, the city, ITD, and other agencies will
11
Item 2.
be put together in the coming months to continue discussions. While different agencies may have
different goals, the main goal we all agree on is keeping the public safe and ensuring drivers can get to
where they need to go as efficiently and safely as possible. An inter-agency team was assembled to
discuss a safety review of Eagle Road, I-84 to SH-44. The safety review, which included a speed study,
was completed at the end of February 2023. ITD has presented to City Council several times, the last
time was on September 5, 2023. ITD shared what was found in the safety review and showed what sign
and striping improvements were made as a result. They also shared that the speed study showed that
no change to the enforceable speed limits on Eagle Rd were recommended. ITD recognizes the city’s
concerns regarding the daily congestion on Eagle Rd and proposed implementing advisory speed lim it
signage with flashing beacons. These would be activated during the busiest times of the day. The
purpose would be to alert the public of times when congestion is most likely. After the presentation
there were concerns from the mayor and at least one council member due to advisory speeds not
being enforceable. ITD and the city continue to engage to find the best solution for the traveling public
on Eagle Rd. An additional inter-agency team with law enforcement, the city, ITD, and other agencies
will be put together in the coming months to continue discussions. While different agencies may have
different goals, the main goal we all agree on is keeping the public safe and ensuring drivers can get to
where they need to go as efficiently and safely as possible.
ITD Contact: Justin Price, Justin.Price@itd.idaho.gov
I-84 Mobility Improvement Study: This study will determine whether additional auxiliary lanes and
other improvements are needed to smooth merge hesitations, achieve better traffic distribution, and
achieve lane balance for the 11-mile section of Interstate 84 between the Garrity Interchange in
Nampa and the I-84/I-184 Wye Interchange in Boise. Existing traffic counts will be collected, future
traffic counts will be developed, existing conditions will be reviewed along with all previous
environmental and operational studies, traffic will be modeled, an origin-destination study will be
conducted and a phasing plan and future NEPA action will be recom mended. A data collection plan is
currently being developed, ITD resources are being allocated for that data collection and a Request for
Proposals will be advertised within 60 days.
ITD Project Manager: Mark Wasdahl, Mark.Wasdahl@itd.idaho.gov
SH-69 Traffic Study: This study will identify roadway improvements necessary to accommodate traffic
through 2050. Currently, the long-range traffic forecast is being re-evaluated. Technical meetings with
cities of Kuna and Meridian are anticipated for June 2024.
ITD Project Manager: Mark Wasdahl, Mark.Wasdahl@itd.idaho.gov
PATHWAYS (Updated by City Parks Staff April 2024)
Nine Mile Creek, Linder to Meridian: In initiating the land trade, parks staff discovered a strip of
easement belonging to Nampa and Meridian Irrigation District that can accommodate the pathway,
rendering a land trade unnecessary. The current (funded) project phase will run from NW 3rd Stre et
along the Ninemile Creek as far as approximately 8th Street. In April, staff received approval to
request additional funding from LHTAC for construction of this segment, as costs have risen
significantly since funds were originally allocated. Staff is currently working with an engineering
consultant, with plans expected to be complete in 2025, and project construction in 26/27. A future
City project (not yet funded) proposes to extend the Rail With Trail Pathway west as far as Linder Road.
12
Item 2.
Five Mile Creek Pathway: This project, which includes 2/3 of a mile of newly paved pathway along the
south bank of the Fivemile Creek, and a pedestrian bridge crossing of the Ninemile Creek, is now
complete. It connects 3 miles of existing pathway in northwest Meridian with more than 4 miles of
existing pathway to the east, allowing for approximately 8 miles of continuous multi-use pathway
through Meridian, primarily along the Fivemile Creek.
OTHER PROJECTS
MDC, Downtown Parking Efforts: MDC is working on an update to Destination Downtown. Part of this
is parking analysis. The MDC consultant is wrapping-up the Parking Management Strategies &
Implementation Guide. MDC and City Staff met in late January to discuss next steps.
13
Item 2.
1
Hether Hill
From:John Wasson <jwasson@achdidaho.org>
Sent:Tuesday, July 2, 2024 11:22 AM
To:Hether Hill
Subject:Lost Rapids crosswalk
External Sender - Please use caution with links or attachments.
Heather,
I apparently missed this invesƟgaƟon being completed in late May. This is for the requested crosswalk on Lost Rapids:
Received results of pedestrian study.
700-900: 15 pedestrians crossing Lost Rapids, 8 of these were kids at 8:35 prior to bus arrival.
1100-100: 7 pedestrians crossing Lost Rapids
400-800: 10 pedestrians crossing Lost Rapids, extensive on street parking in the bike lane
There is moderate pedestrian usage but none close to the 20 in one hour range that we look for. There are plenty of
gaps at this locaƟon and I do not see a huge factor that would lend to striping a crosswalk at this Ɵme. Recommend no
acƟon. JMH
While there is some observed pedestrian acƟvity, this locaƟon does not meet the minimum threshold to be considered
for marked crosswalk installaƟon at this Ɵme. As land uses change, we can reconsider installaƟon.
Approved. (JES)
John
John Wasson
Assistant Traffic Engineer | Traffic Engineering
Ada County Highway District (ACHD)
3775 Adams Street, Garden City, Idaho 83714
Phone: (208)387-6151
www.achdidaho.org
Connect with us on social! @achdidaho
14
Item 4.
MEMO TO TRANSPORTATION COMMISSION
Agenda Topic on the Transportation Commission Agenda
From: Hether Hill Meeting Date: August 5, 2024
Topic: Staff Communications
Below are summaries of relevant correspondences received by City Staff since the last TC meeting.
From: Les and Amelia Carson <lesandam@pacbell.net>
Sent: Tuesday, July 30, 2024 3:51 PM
To: Robert Simison <rsimison@meridiancity.org>
Subject: Traffic issues!
External Sender - Please use caution with links or attachments.
Hello Mayor Simison,
My husband and I live in Spurwing Greens near the intersection of Chinden & Ten Mile. As I understand it, when
Rock Harbor church was being built, they were given a right-turn-only exit onto Chinden. Apparently, when
Costco was approved (at a most ridiculous location), that exit was taken from the church and given to Costco. I
guess only a certain number are allowed within a certain distance of an intersection and Costco has more
“bang”!
Short story long, Rock Harbor church now uses the Spurwing Greens exit. Sundays are an unbelievable mess at
our entrance! Now, the traffic seems to be moving to other days as well and with the church expansion, no
telling what we’ll be faced with. This picture was taken Monday at 1:11pm. I did not make it out on the first
green light and barely did on the second.
15
Item 7.
This is horrible. The paper reported that Costco increased the traffic at the near intersection by approximately
17,000 cars daily so this just adds to our predicament. Now, it looks like there’s an application to add over 300
condos at Black Cat and Chinden they they estimate will increase cars by over 5,000 cars per day. In addition, if
In & Out is approved for the location near Costco, you’re looking at a disaster waiting to happen.
Please PLEASE do not let this happen.
I’m now finished with my rant and truly hope you’ll seriously consider all that I’ve said and will pass it on to the
planning commission and anyone who’ll listen to the voice of the people. Thank you kindly.
Amelia Carson
Sent from my iPhone
From: Andrew Marini
Sent: Thursday, June 27, 2024 1:07 PM
To: planning@meridiancity.org
Cc: Jeffrey Hall <jhall@nwcommercialgroup.com>; Terri Benson <tbenson@adacounty.id.gov>; Niki Benyakhlef
<Niki.Benyakhlef@itd.idaho.gov>
Subject: Request: W/E Corporate Dr./South Progress Ave. Intersection
Good Afternoon, Meridian P&Z Team,
Hi, I’m Andrew Marini, the Manager of the Ada County Sheriff’s Office - Driver’s Licensing Office at 736 S.
Progress Ave. I'm writing to you about the new construction of the Mister Car Wash at 675 S. Progress Ave.,
Meridian 83642. I'm concerned about the T-intersection of W/E Corporate Dr. and S. Progress Ave. (screenshots
below). Currently, there is only a stop sign for northbound S. Progress Ave. traffic to make an LT or RT onto
Corporate Drive. This intersection has some blind spots, and I’ve witnessed and experienced near misses with
westbound & eastbound Corporate drive traffic. The stop sign & line are recessed back to accommodate a
pedestrian x-walk, further reducing Corporate drive traffic visibility. The developer for Mister Car Wash has
removed the temporary fencing and bushes for the corner which also posed visibility/blind spot concerns. I
anticipate an increase in trips and usage of these roadways due to the new construction. I believe that the
installation of a three-way stop at this intersection is a necessary measure to significantly improve safety and
manage stacking on S Progress Ave. during peak hours.
If this has yet to be considered, I would like to formally request that the City look into modifying this
intersection. Our shared goal of ensuring safety on our roadways makes this a crucial issue. Please let me know
what I need to do to get this looked at. Thank you so much, and I look forward to hearing from you soon!
Andrew
16
Item 7.
Andrew Marini
Licensing Manager
Administrative Services Bureau
Boise: 400 N Benjamin Ln #101, Boise, ID
83704
Meridian: 736 S Progress Ave, Meridian, ID
83642
O: (208) 577-3036
M: (208) 859-8335 (Primary)
amarini@adacounty.id.gov
17
Item 7.
From: Tara Smith <tsmith@meridiancity.org>
Sent: Wednesday, June 5, 2024 10:42 AM
To: Josh Jones <jjonesmthome@gmail.com>
Cc: Trevor Weitzel <tweitzel@meridiancity.org>; Caleb Hood <chood@meridiancity.org>
Subject: RE: Baraya Subdivision
Good morning Josh,
I apologize for the delay in responding. I’m going to be out of the office for several weeks for a surgery, and
have a lot of things needing to get ready for my absence. I do remember communicating with your wife on this
issue. I’m aware ACHD conducted a speed and volume study in April of last year on S. Baraya, but that it did not
meet the criteria for traffic calming measures at that time. I have reached out to my contact at ACHD again
recently to gain some insight into the issue from their perspective but have not heard back yet. However, I
know ACHD does, at times, work with neighborhoods to install calming measures even when criteria is not met,
via resident petitions.
What I believe to be part of the issue is the placement of the stop sign itself. S. Baraya is the main drag through
there, while Balance Rock ends at a T intersection at this time. Typically, at a T intersection, the road that is
ending is required to stop/yield to the street that continues. When they add to the subdivision in the future, I’m
certain the plan is to extend Balance Rock on to the west, as evidenced by the spur road, but for now, the issue
could be motorists are disregarding the sign because they don’t believe they should have to stop. I see this in
other areas of my job as well…if the average citizen doesn’t understand or see the relevance in a law, they don’t
tend to follow it. So one of the questions I posed to my ACHD contact is why isn’t the stop sign on Balance Rock
instead? My best guess is they were likely trying to slow down straight through traffic on S. Baraya, or they were
complying with the City codes that govern the length a neighborhood street can be without a curve or stop
sign. It all goes to controlling speed, however, I’m a far cry from a traffic engineer.
I know this is a frustrating situation for you and it may take a collaboration of efforts to find a solution, but in the
meantime, for my part, I have assigned an officer to pay that intersection some attention. He was out there
yesterday morning for about an hour and will visit it as time allows to see if we can curb some of the
issue. However, enforcement is very temporary as you well know, because we simply cannot be there all the
time. Since I will be out of the office after tomorrow, I have included my Corporal, Trevor Weitzel, on this email
so he is in the loop and can be your contact if something else comes up.
Thank you!
Tara Smith | Traffic Sergeant
Meridian Police Department
1401 E. Watertower St., Meridian, Idaho 83642
Phone: 208-846-7397 | Fax: 208-846-7366
All e-mail messages sent to or received by City of Meridian e-mail accounts are subject to the Idaho law, in
regards to both release and retention, and may be released upon request, unless exempt from disclosure by law.
From: Josh Jones <jjonesmthome@gmail.com>
Sent: Sunday, June 2, 2024 8:29 PM
To: Tara Smith <tsmith@meridiancity.org>
Subject: Baraya Subdivision
External Sender - Please use caution with links or attachments.
18
Item 7.
Ma'am,
My name is Josh Jones, and I am reaching out regarding a traffic issue at the corner of Baraya St and W Balance
Rock Dr. My wife, Hannah Jones, has previously emailed you concerning the frequent violations at this stop sign.
The problem has escalated, and now it’s a daily occurrence, posing a significant risk, especially with many
children playing in our neighborhood.
Several residents, including myself, are in discussions with the city about installing speed bumps at stop signs to
enhance safety. However, in the meantime, we are urgently requesting the presence of an officer at this
intersection occasionally to enforce the stop sign.
I have numerous videos documenting these violations—approximately 100 currently, with at least 15 more
recorded daily. I am willing to share these videos if it helps address the issue and improve safety.
We understand that there are larger issues to handle, but your support in this matter would be greatly
appreciated by our entire community.
Thank you for your attention to this urgent safety concern.
Sincerely,
Josh Jones
From: Chelssie Oates <chelssieh23@gmail.com>
Sent: Thursday, June 13, 2024 5:57 PM
To: Caleb Hood <chood@meridiancity.org>; Trevor Weitzel <tweitzel@meridiancity.org>
Subject: Baraya subdivision stop sign issue
External Sender - Please use caution with links or attachments.
Dwar officer,
I hope this email finds you well. My name is Chelssie, and I serve as the Vice President of the HOA Board for our
subdivision. I'm reaching out to you regarding an issue brought to my attention by one of our homeowners,
concerning instances of stop sign violations in our community.
I understand that you've been working closely with them to address these concerns, and as a board member,
I'm keen to discuss potential solutions with you. Recently, I've been in communication with AcHD, and they've
indicated limitations in implementing changes to the current traffic control measures, including stop signs,
speed bumps, painted lines, and even the possibility of installing a four-way stop sign.
Before I proceed with formal correspondence to AcHD, outlining our desired revisions, they've advised us to
have a representative assess the site in question. Hence, I'd appreciate the opportunity to converse with you
beforehand to ensure alignment in our approach.
If convenient, could you please reach out to me via phone or email at your earliest convenience? Your insights
and expertise would be invaluable in navigating this matter effectively.
Thank you for your attention to this matter.
Warm regards,
Chelssie
Cell: 208-921-0844
19
Item 7.