HomeMy WebLinkAbout2025 Meridian Prioritization Request Form - Combined2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
1 Linder Rd, Overland Rd /
Franklin Rd 2022-2024 2024-2025 2026-2027
Widen Linder Rd to 5 lanes and construct a new 4-lane
I-84 overpass, including curb, gutter, sidewalk, and bike
lanes in accordance with the 2016 CIP. Project would
be a joint project between ACHD and ITD.
Project programmed to be constructed in 2026-2027.Linder Rd, Overland Rd / Franklin Rd Roads & Intersections Y
2 Locust Grove Rd, Fairview Ave
/ Ustick Rd 2028-2029 TBD TBD
Widen Locust Grove Rd to 3, 4 or 5 lanes with curb,
gutter and pedestrian/bike facilities. Consider
enhanced crossing at Chateau Dr.
Project programmed to be designed in 2028-2029.Locust Grove Corridor B: Locust Grove Rd, Fairview
Ave / Ustick Rd Roads & Intersections Y
3 Fairview Ave and Locust Grove
Rd 2020-2023 2024 2029 Widen intersection. Project programmed to be constructed in 2029.Fairview Ave and Locust Grove Rd Roads & Intersections Y
4 Victory Rd, Locust Grove Rd /
Eagle Rd 2027-2028 TBD TBD
Widen Victory Rd to 3 lanes. Include preferential bike
and pedestrian infrastructure.Project programmed to be designed in 2027-2028.Victory Corridor A: Victory Rd, Locust Grove Rd /
Eagle Rd Roads & Intersections Y
5 Ustick Rd, Ten Mile Rd / Linder
Rd 2022-2023 2025 2026
Widen Ustick Rd to 5 lanes with curb, gutter,and
pedestrian/bike facilities. Project programmed to be constructed in 2026.Ustick Corridor A: Ustick Rd, Ten Mile Rd / Linder Rd Roads & Intersections Y
6 Amity Rd and Locust Grove Rd 2023-2024 2029-2030 TBD
Construct interim signalized intersection with
preservation for future widening to accommodate 5-
lane roadways in all directions.
Project programmed to be constructed in future.Amity Corridor A: Amity Rd and Locust Grove Rd Roads & Intersections Y
7 Locust Grove Rd, Amity Rd /
Victory Rd NP NP NP
Widen Locust Grove Rd to a minimum 3 lanes, with
preservation for up to 5 lanes, with curb, gutter and
pedestrian/bike facilities. Include pedestrian crossings
at Palermo and Wrightwood.
Escalated project costs have resulted in some projects being
deferred.Locust Grove Rd, Amity Rd / Victory Rd Roads & Intersections N
8 Victory Rd, Meridian Rd /
Locust Grove Rd 2027-2028 TBD TBD
Widen Victory Rd to 3 lanes. Include preferential bike
and pedestrian infrastructure. Complete sidewalk/MUP
on the south side of Victory Rd adjacent to County
outparcel.
Project programmed to be designed in 2027-2028.Victory Corridor A: Victory Rd, SH 69 (Meridian Rd) /
Locust Grove Rd Roads & Intersections Y
9 Ten Mile Rd / Cherry Ln 2028-2029 TBD TBD
Widen intersection. Intersection improvements to
include dual left turn lanes.Project programmed to be designed in 2028-2029.Cherry Ln and Ten Mile Rd Roads & Intersections Y
10 Ustick Rd and Venable Ln NP NP NP Install full signal or roundabout.
Scoped in 2023. To be evaluated and prioritized for possible
inclusion into future IFYWP updates.Ustick Rd and Venable Ln Roads & Intersections N
11 Eagle Rd / Overland Rd NP NP NP
Widen intersection. Intersection improvements to
include dual left turn lanes.
Escalated project costs have resulted in some projects being
deferred.SH-69 (Meridian Rd) and Overland Rd Roads & Intersections N
12 Locust Grove Rd, Ustick Rd /
McMillan Rd 2028-2029 TBD TBD
Widen Locust Grove Rd to 3, 4 or 5 lanes; preserve for
5 lanes, with curb, gutter, and pedestrian/bike
facilities. Project should include an enhanced crossing
(pedestrian hybrid beacon) on Locust Grove Road at
Heritage Park Street; access for Meridian Technical
Charter High School.
Project programmed to be designed in 2028-2029.Locust Grove Corridor A: Locust Grove Rd, Ustick Rd /
McMillan Rd Roads & Intersections Y
13 McMillan Rd, Meridian Rd /
Locust Grove Rd NP NP NP
Widen McMillan Rd up to 5-lanes with curb, gutter,
sidewalk, and bike/pedestrian facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.McMillan Rd, SH 69 (Meridian Rd) / Locust Grove Rd Roads & Intersections N
14 McMillan Rd, Linder Rd /
Meridian Rd NP NP NP
Widen McMillan Rd up to 5-lanes with curb, gutter,
sidewalk, and bike/pedestrian facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.McMillan Rd, Linder Rd / SH 69 (Meridian Rd)Roads & Intersections N
2025 Meridian Prioritization Request Form
2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
15 Meridian Rd, Ustick Rd /
McMillan Rd 2027-2028 TBD TBD
Widen Meridian Rd to 3, 4 or 5 lanes; preserve for 5
lanes, with curb, gutter, and pedestrian/bike facilities.
Project should include an enhanced pedestrian
crossing of Meridian Rd at/near Settlers Park entrance
and Sundance Subdivision micropath.
Project programmed to be designed in 2027-2028.Meridian Corridor A: Meridian Rd, Ustick Rd /
McMillan Rd Roads & Intersections Y
16 Linder Rd, Cherry Ln / Ustick
Rd 2028-2029 TBD TBD
Widen Linder Rd to include curb, gutter and
pedestrian/bike facilities. Include preferential bike and
pedestrian infrastructure with wayfinding signage.
Project programmed to be designed in 2028-2029.
Concept Study in 2022-2024.Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Roads & Intersections Y
17 Amity Rd, Meridian Rd / Locust
Grove Rd 2023-2024 2029-2030 TBD
Widen Amity Rd to minimum 3 lanes with preservation
for up to 5 lanes. Include preferential bike and
pedestrian infrastructure for Mary McPherson
elementary school.
Programmed for design in FY2023-2024.Amity Corridor A: Amity Rd, SH 69 (Meridian Rd) /
Locust Grove Rd Roads & Intersections Y
18 Cherry Ln and Black Cat Rd NP NP NP
Widen intersection. Address transition from bike-lane
to/from MUP.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Cherry Ln and Black Cat Rd Roads & Intersections N
19 Black Cat, Franklin to Cherry 2029-2030 TBD TBD
Widen Black Cat Rd with curb, gutter and
pedestrian/bike facilities. An interim help could be
improvements north of Franklin to the RR tracks near
COMPASS school.
Project programmed for design in 2029-2030.Black Cat Rd, Franklin Rd / Cherry Ln Roads & Intersections Y
20 Cherry Ln and McDermott Rd NP NP NP Widen intersection.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Cherry Ln and McDermott Rd Roads & Intersections N
21 Cherry Ln, Black Cat Rd /
McDermott Rd NP NP NP
Widen Cherry Ln with curb, gutter, sidewalk, and
bike/pedestrian facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Cherry Ln, McDermott Rd / Black Cat Rd Roads & Intersections N
22 Ustick Rd and Black Cat Rd 2022-2024 2024 2025 Widen intersection. Project programmed to be constructed in 2025.Ustick Corridor A: Ustick Rd and Black Cat Rd Roads & Intersections Y
23 Ustick, Black Cat to Ten Mile 2022-2023 2024 2025
Widen Ustick Rd to 5 lanes with curb, gutter,and
pedestrian/bike facilities. Project programmed to be constructed in 2025.Ustick Corridor A: Ustick Rd, Black Cat Rd / Ten Mile
Rd Roads & Intersections Y
24 Fairview Ave, SH 55 (Eagle Rd)
/ Cloverdale Rd NP NP NP
Widen Fairview Ave with curb, gutter, sidewalk, and
bike/pedestrian facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Fairview Ave, SH 55 (Eagle Rd) / Cloverdale Rd Roads & Intersections N
25 Fairview Ave, Meridian Rd /
Locust Grove Rd NP NP NP
Widen Fairview Ave with curb, gutter, sidewalk, and
bike/pedestrian facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Fairview Ave, Meridian Rd / Locust Grove Rd Roads & Intersections N
26 Ten Mile Rd, Amity Rd / Victory
Rd NP NP NP
Widen Ten Mile Rd with curb, gutter, sidewalk, and
bike/pedestrian facilities.
Defer. Operating at a LOS D or better. Reevaluate as conditions
change.Ten Mile Rd, Amity Rd / Victory Rd Roads & Intersections N
27 Linder, Pine / Cherry 2028-2029 Future Future
Widen Linder Rd to include curb, gutter and
pedestrian/bike facilities. Include preferential bike and
pedestrian infrastructure with wayfinding signage
(several nearby and directly adjacent schools).
Project programmed to be designed in 2028-2029.
Move to programmed list.Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Roads & Intersections Y
28 McMillan Rd and Star Rd NP NP NP Widen intersection.
Defer. Operating at a LOS D or better. Reevaluate as conditions
change.McMillan Rd and Star Rd Roads & Intersections N
29 Amity Rd and Linder Rd NP NP NP Widen intersection.
Defer. Operating at a LOS D or better. Reevaluate as conditions
change.Amity Rd and Linder Rd Roads & Intersections N
30 Amity Rd and Black Cat Rd NP NP NP Widen intersection.
Defer. Operating at a LOS D or better. Reevaluate as conditions
change.Amity Rd and Black Cat Rd Roads & Intersections N
31 Cherry Ln and Linder Rd NP NP NP Widen intersection.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Cherry Ln and Linder Rd Roads & Intersections N
32 Pine, Linder to Meridian NP NP NP
Widen the entire segment to 3-travel lanes with curb,
gutter, sidewalks and/or multi-use or mixed-use
bikeway.
Project would require the removal of on-street parking for existing
homes. To be evaluated and prioritized for possible inclusion into
future IFYWP updates.
Pine Ave, Linder Rd / Meridian Rd Roads & Intersections N
33 Meridian Rd, McMillan Rd /
Chinden Blvd 2027-2028 TBD TBD
Widen Meridian Rd to 3, 4 or 5 lanes; preserve for 5
lanes, with curb, gutter, and pedestrian/bike facilities. Project programmed to be designed in 2027-2028.Meridian Corridor A: Meridian Rd, McMillan Rd / US
20/26 (Chinden Blvd)Roads & Intersections Y
2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
34
Fairview Ave Corridor
Management, Linder Rd /
Orchard St
NP NP NP
Improve safety and traffic operations along Fairview
Ave in accordance with the Fairview Avenue Corridor
Management Strategy. Project may include bicycle and
pedestrian facilities and other access management
treatments.
Project to be implemented through development. ACHD and
Meridian to coordinate implementation as development
applications are processed.
Fairview Ave Corridor Management, Linder Rd /
Orchard St Roads & Intersections N
35 Lake Hazel Rd and Eagle Rd 2019-2022 2022-2023 2025 Widen and signalize intersection.Project programmed to be constructed in 2025.Lake Hazel Rd and Eagle Rd Roads & Intersections Y
36 Ten Mile Rd and Chateau Dr NP NP NP Improve intersection.
Does not currently meet warrants. ACHD to reevaluate as
development occurs in the area.Ten Mile Rd and Chateau Dr Roads & Intersections N
37 Victory, Linder to Meridian NP NP NP
Widen Victory Rd to 3 lanes with curb, gutter and
pedestrian/bike facilities.
Escalated project costs have resulted in some projects being
deferred.
Victory Corridor E: Victory Rd, Linder Rd / Meridian
Rd Roads & Intersections N
38 Franklin Rd, McDermott Rd /
Black Cat Rd 2024-2025 2028-2029 TBD
Widen Franklin Rd to 5 lanes with curb, gutter and
pedestrian/bike facilities.Project programmed to be constructed in future.Franklin Corridor A: Franklin Rd, McDermott Rd /
Black Cat Rd Roads & Intersections Y
39 Linder Rd, Chinden Blvd (US
20/26) / SH 44 (State St) 2027 TBD TBD
Widen Linder Rd. with bike and pedestrian facilities as
this is one of only a few river crossings in the County
and connects to nearby Eagle Island State Park. Part of
City's envisioned pathway network.
Project programmed to be designed in 2027.Linder Corridor A: Linder Rd, Chinden Blvd (US 20/26)
/ SH 44 (State St) - South Phase Roads & Intersections Y
40 Fairview Ave, Locust Grove Rd
/ SH 55 (Eagle Rd)2020-2024 TBD 2029
Widen Fairview Ave to 7 lanes with curb, gutter
pedestrian/bike facilities.Project programmed to be constructed in 2029.Fairview Ave, Locust Grove Rd / SH 55 (Eagle Rd)Roads & Intersections Y
41 McMillan Rd and Black Cat Rd 2021-2023 2028 2029 Widen intersection. Project programmed to be constructed in 2029.McMillan Rd and Black Cat Rd Roundabout Roads & Intersections Y
42 Meridian/Overland Signal NP NP NP
Improve intersection operation. This may mean adding
additional lanes.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.SH-69 (Meridian Rd) and Overland Rd Roads & Intersections N
43 Franklin Rd and McDermott Rd 2024-2025 2027-2028 TBD
Widen intersection. Coordinate design with ITD and
the SH-16 improvements.Project programmed to be constructed in future.Franklin Corridor A: Franklin Rd and McDermott Rd Roads & Intersections Y
44 McMillan Rd and McDermott
Rd NP NP NP Widen intersection.
Defer. Operating at a LOS D or better. Reevaluate as conditions
change.McMillan Rd and McDermott Rd Roads & Intersections N
45 McMillan, Black Cat to Ten
Mile NP NP NP Widen with curb, gutter, and pedestrian/bike facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.McMillan Rd, Black Cat Rd / Ten Mile Rd Roads & Intersections N
46 Ustick Rd and McDermott Rd 2024-2025 2026 2027 Widen intersection. Project programmed to be constructed in 2027.Ustick Corridor B: Ustick Rd and McDermott Rd Roads & Intersections Y
47 Victory Rd and Linder Rd NP NP NP Widen intersection.
Escalated project costs have resulted in some projects being
deferred.Victory Corridor E: Victory Rd and Linder Rd Roads & Intersections N
48 Ustick Rd and Star Rd NP NP NP Widen intersection.
Escalated project costs have resulted in some projects being
deferred.Ustick Rd and Star Rd Roads & Intersections N
49
Locust Grove Rd, McMillan Rd
/ Chinden
Blvd (US 20/26)
NP NP NP
Widen Locust Grove Rd to 3, 4 or 5 lanes; preserve for
5 lanes, with curb, gutter, and pedestrian/bike
facilities.
Escalated project costs have resulted in some projects being
deferred.
Locust Grove Rd, McMillan Rd / US 20/26 (Chinden
Blvd)Roads & Intersections N
50 Ustick Rd, McDermott Rd /
Black Cat Rd 2024-2025 2026 2027
Widen Ustick Rd to 5 lanes with curb, gutter and
pedestrian/bike facilities.Project programmed to be constructed in 2027.Ustick Corridor B: Ustick Rd, Owyhee Storm Ave /
Black Cat Rd Roads & Intersections Y
51 Eagle Rd / Fairview Ave NP NP NP
Improve intersection operation. This may mean adding
additional lanes or a grade-separated roadway. Request to be shared with our Traffic division. Reponse pending.Eagle Rd and Fairview Ave Roads & Intersections N
52 Lake Hazel / Discovery Park NP NP NP
Improve intersection/entry into City Park. The
improvements could be a signal, roundabout, or other,
but should include provisions for pedestrians/bicyclists.
Request to be shared with our Traffic division. Reponse pending.Lake Hazel Rd and Discovery Park Roads & Intersections N
2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
53 Amity, Eagle to Cloverdale 2026-2027 TBD TBD
Widen Amity Rd to 5 lanes with curb, gutter and
pedestrian/bike facilities. Include enhanced pedestrian
crossing at Ten Mile Creek pathway crossing and install
pedestrian/bike improvements on Amity Rd near the
YMCA and City Park so there are no gaps.
Project programmed to be designed in 2026-2027.Amity Corridor B: Amity Rd, Eagle Rd / Cloverdale Rd Roads & Intersections Y
54 Amity, Locust Grove to Eagle NP NP NP
Widen Amity Rd to 5 lanes with curb, gutter and
pedestrian/bike facilities. Include enhanced pedestiran
crossing at Ten Mile Creek pathway crossing.
Escalated project costs have resulted in some projects being
deferred.
Amity Corridor D: Amity Rd, Locust Grove Rd / Eagle
Rd Roads & Intersections N
55 Victory, Ten Mile to Linder NP NP NP Widen with curb, gutter, and pedestrian/bike facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Victory Rd, Ten Mile Rd / Linder Rd Roads & Intersections N
56 Black Cat, Cherry to Ustick NP NP NP Widen with curb, gutter, and pedestrian/bike facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Black Cat Rd, Cherry Ln / Ustick Rd Roads & Intersections N
57 Black Cat, Ustick to McMillan NP NP NP Widen with curb, gutter, and pedestrian/bike facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Black Cat Rd, Ustick Rd / McMillan Rd Roads & Intersections N
58 Black Cat, McMillan to Chinden NP NP NP Widen with curb, gutter, and pedestrian/bike facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Black Cat Rd, McMillan Rd / Chinden Blvd (US 20/26)Roads & Intersections N
59 McMillan, Ten Mile to Linder NP NP NP
Widen with curb, gutter, and pedestrian/bike facilities.
Project should include an enhanced pedestrian
crossing and curb ramps on McMillan Rd at Pantine
Way, near Hunter Elementary.
Project scoped in 2022. To be evaluated and prioritized for
possible inclusion into future IFYWP updates.McMillan Rd, Ten Mile Rd / Linder Rd Roads & Intersections N
60 Eagle, Lake Hazel to Amity 2021-2023 2023-2024 2025
Widen Eagle Rd to 5 lanes with curb, gutter, and
pedestrian/bike facilities. Project programmed to be constructed in 2025.Eagle Rd, Lake Hazel Rd / Amity Rd Roads & Intersections Y
61 Lake Hazel, Eagle / Cloverdale 2022-2023 2024 2027
Corridor improvement project which includes widening
to two (2) to five (5) lanes and constructing enhanced
pedestrian and bike facilities on both sides of roadway.
Roads & Intersections Y
62 Locust Grove, Lake Hazel to
Amity NP NP NP
Widen Locust Grove Rd up to 5 lanes with curb, gutter,
and pedestrian/bike facilities.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Locust Grove Rd, Lake Hazel Rd / Amity Rd Roads & Intersections N
63 Victory Rd, Eagle Rd /
Cloverdale Rd 2028-2029 Future Future
Corridor improvement project which includes widening
from two (2) to five (5) lanes and constructing
enhanced pedestrian and bike facilities on both sides
of the roadway.
Victory Corridor C: Victory Rd, Eagle Rd / Cloverdale
Rd Roads & Intersections Y
64 Locust Grove and McMillan NP NP NP Improve intersection.
Please provide additional information regarding type of request
and/or improvements needed. McMillan Rd and Locust Grove Rd Roads & Intersections N
65 Meridian and McMillan NP NP NP Improve intersection.
Please provide additional information regarding type of request
and/or improvements needed.
Locust Grove Rd, McMillan Rd / US 20/26 (Chinden
Blvd)Roads & Intersections N
66 Linder and McMillan NP NP NP Improve intersection.
Please provide additional information regarding type of request
and/or improvements needed. McMillan Rd and Linder Rd Roads & Intersections N
67 Ten Mile and McMillan NP NP NP Improve intersection.
Please provide additional information regarding type of request
and/or improvements needed. McMillan Rd and Ten Mile Rd Roads & Intersections N
2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
1
Stoddard Rd, Victory Rd /
Overland Rd (Stoddard Rd,
Victory Rd / Kodiak Dr)
2023 2027 TBD
Reconstruct Stoddard Rd, between Victory Rd and
Overland Rd to 3-lanes, 7' attached sidewalks and bike
lanes. Project includes bridge #2085 and an enhanced
pedestrian crossing (pedestrian hybrid beacon) at
Victory and Stoddard (CM214-27). Bike lanes may be
replaced by a pathway per the Bike Master Plan
Update.
Project programmed to be constructed in future.South Meridian Improvements A: Stoddard Rd,
Victory Rd / Overland Rd Community Programs Y
2 East 03rd St, Franklin Rd /
Carlton Ave (Phase 1)2025-2026 2027 TBD
Construct streetscape improvements, including curb,
gutter, sidewalk, and improved UPRR crossing, from
Franklin Rd to Carlton Ave in accordance with the
Downtown Meridian Neighborhood Plan.
Project programmed to be designed in 2025-2026.Meridian Downtown Improvements A: East 03rd St,
Franklin Rd / Carlton St Community Programs Y
3 Black Cat Rd Railroad Crossing,
625' N/O Aviator St
Reconfigure the railroad crossing to remove stop signs
and replace them with an alternative to keep traffic
flowing, while also maintaining safety.
Community Programs
4 McMillan Rd, Ten Mile Rd /
Linder Rd 2029-2030 TBD TBD
City requests detached concrete sidewalk with curbing
between Goddard Creek Way and Wild Goose Way.
City requests a pedestrian crossing across McMillan
near Hunter Elementary (near Palatine Way). See
Priority #18 below; please construct concurrently.
Project programmed to be designed in 2029-2030.North Meridian Improvements B: McMillan Rd,
Goddard Creek Way / Wild Goose Way Community Programs Y
5 Main St and King Street
Pedestrian Crossing N/A TBD 2026
Install an enhanced pedestrian crossing of Main St at
King Street. Main Street northbound has 3 lanes and
creates a safety concern.
Project to be completed through RPI initiative.Main St and King St Pedestrian Crossing Community Programs N
6 Bower St, Meridian Rd / E.
03rd St 2029-2030 TBD TBD
Complete sidewalks and add wayfinding signage on
Bower St, between Meridian Rd and E. 03rd St.Project programmed to be designed in FY2029-2030. North Meridian Improvements B: Bower St, Meridian
Rd / East 03rd St Community Programs Y
7 Pine Ave and W. 1st St
Pedestrian Crossing NP NP NP
Install an enhanced pedestrian crossing (rectangular
rapid flashing beacon) on Pine Ave at W 01st St to
improve access to Meridian Elementary School.
Escalated project costs have resulted in some projects being
deferred.Pine Ave and West 01st St Pedestrian Crossing Community Programs N
8 W 7th St, Cedarburg Dr to
Washington St.2022-2023 2024 2025
Install sidewalk to fix gap on NW 7th St. This gap
prevents connection from the sidewalk from the south
and east from connecting to the micro-path at
Meridian Middle School/8th St.
Included in the Meridian Downtown Pavement and Pedestrian
Improvements (2025) project.
Move to programmed list.
Meridian Downtown Pavement and Pedestrian
Improvements (2025)Community Programs Y
9 McMillan Rd, Locust Grove Rd
/ Red Horse Way 2026 2028 2029
Complete sidewalk gap on the north side of McMillan
Rd, between Locust Grove Rd and Red Horse Way.Project programmed to be constructed in 2029.McMillan Rd, Meridian Rd / Locust Grove Rd Community Programs Y
10 Locust Grove Rd and Palermo
Dr Pedestrian Signal 2022-2023 2024 2028
Install an enhanced pedestrian signal and lighting on
the north side of Palermo Dr at Locust Grove Rd.Project programmed to be constructed in 2028.South Meridian Improvements A: Locust Grove Rd
and Palermo Dr Pedestrian Crossing Community Programs Y
11 Locust Grove Road, Leighfield
Drive to Star Lane 2028-2029 TBD TBD
Connect gap from existing sidewalk on west side of
Locust Grove Rd, along with improving narrow
sidewalk on east side of roadway newar Leighfield Dr
and Star Dr; east side of Locust Grove Rd to connect
with an existing path to the school near Paradise Ln
and Grand Canyon Dr; and install an enhanced crossing
(PHB) on Locust Grove Rd at Heritage Park St, near
Meridian Technical Charter High School. These
improvements are needed sooner than what is planned
with the roadway project.
Project programmed to be designed in 2028-2029. Locust Grove Corridor A: Locust Grove Rd, Ustick Rd /
McMillan Rd Community Programs Y
2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
12 E. 3rd, Carlton to Fairview NP NP NP
Extend roadway and construct streetscape
improvements, including curb, gutter, sidewalk, and
improved UPRR crossing, from Carlton Ave to Fairview
Ave in accordance with several downtown plans and
studies.
Extension to be completed through development. Duplicate
request. Recommend combining with other request.East 03rd St, Carlton St / Fairview Ave (Phase 2)Community Programs N
13 Ustick-Cherry Bikeway, Black
Cat Road / Chateau Drive NP NP NP
Install bike facilities. Several (likely 5) segments
needed. City requests ACHD's assistance in prioritizing
and scoping corridor connections (likely east to west.)
Scoped in 2024. To be evaluated and prioritized for possible
inclusion into future IFYWP updates.Ustick-Cherry Bikeway, Black Cat Rd / Hickory Way Community Programs N
14 Linder Rd, Washington St /
Maple St 2028-2029 TBD TBD
Include preferential bike and pedestrian infrastructre
near Meridian High School. Complete sidewalk on the
west side of Linder Rd, between Washington St and
Maple St. These improvements are needed sooner than
what is planned with the roadway project .
Project programmed to be designed in 2026. Concept Study in
2022-2024.Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Community Programs Y
15 Cherry Ln, Linder Rd / Meridian
Rd NP NP NP
Install bike facilities along Cherry Ln from Linder Rd to
Meridian Rd
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Cherry Ln Bikeway, Linder Rd / Meridian Rd Community Programs N
16 Linder Road, Maple Avenue /
Cherry Lane 2028-2030 TBD TBD
Include preferential bike and pedestrian infrastructure
for existing schools and City park. These improvements
are needed sooner than what is planned with the
roadway project.
Project programmed to be designed in 2026. Concept Study in
2022-2024. Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Community Programs Y
17
Ten Mile-Linder Bikeway,
Linder Road / Chinden
Boulevard
NP NP NP Install bike facilities, signing and pavement markings.
Scoped in 2020. To be evaluated and prioritized for possible
inclusion into future IFYWP updates.Ten Mile-Linder Bikeway, W 08th St / Chinden Blvd Community Programs N
18 McMillan-Ustick Bikeway, Cool
River Avenue / Eagle Road NP NP NP Install bike facilities.
Scoped in 2020. To be evaluated and prioritized for possible
inclusion into future IFYWP updates.
McMillan-Ustick Bikeway (Phase 3), Linder Rd / Eagle
Rd)Community Programs N
19
Broadway Ave / Idaho Ave
Extension, East
06th St / Locust Grove Rd
NP NP NP
Extend roadway from its current terminus at NE 6th St
to Stonehenge Way/ Commercial Dr and construct
streetscape improvements, including curb, gutter,
sidewalk/MUP.
Defer. To be considered as properties redevelopment.Broadway Ave / Idaho Ave Extension, 06th St / Locust
Grove Rd Community Programs N
20 W Park Creek Dr, Crosswalk at
N Deer Creek Ln NP NP NP Install enhanced crossing with hawk signal or RRFB
To be evaluated and prioritized for possible inclusion into future
IFYWP updates. Project Scoped as part of Black Cat-Ten Mile
Bikeway in FY2023 Scoping Effort.
North Meridian Improvements C: Park Creek Dr and
Deer Creek Ln Pedestrian Crossing Community Programs N
21 Fairview Terrace to Chief
Joseph NP NP NP
Pedestrian connection (sidewalk) between Barbara Dr
in Fairview Terrace Park to E. Willowbrook Dr and Chief
Joseph Elementary on Chateau Drive. Need right-of-
way.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Chief Joseph Elementary Pedestrian Improvements Community Programs N
22 Locust Grove-Eagle Bikeway,
Pine Avenue / McMillan Road NP NP NP
Install bike facilities. Several (likely 3) segments
needed. City requests ACHD's assistance in prioritizing
and scoping corridor connections (likely south to
north.)
Scoped in 2020. To be evaluated and prioritized for possible
inclusion into future IFYWP updates.Locust Grove-Eagle Bikeway, Pine Ave / Chinden Blvd Community Programs N
23
Linder-Meridian Bikeway,
Cherry Lane / Chinden
Boulevard
NP NP NP Install bike facilities.
Escalated project costs have resulted in some projects being
deferred.
North Meridian Improvements C: Linder-Meridian
Bikeway, Pine Ave / Temple Dr Community Programs N
24 Nola Rd, south of Pine Ave
(Middle School)N/A N/A 2025
Construct pedestrian/bicycle faciliteis on Nola Rd from
Pine Ave to Crossroads Middle School/RR Tracks. See
Priority #19 below; construct concurrently.
Project added to Safe Sidewalk Program (2025). To be constructed
in 2025.
Move to programmed list.
Nola Rd and Crossroads Middle School Pedestrian
Crossing Community Programs N
25 McDermott Road, Ustick Road
to McMillan Road NP NP NP
Install pedestrian/bike facilities on the west side of
McDermott Rd connecting to infrastructure on Ustick
Rd and McMillan Rd for connectivity to Owyhee High
School.
Escalated project costs have resulted in some projects being
deferred.
McDermott Rd Pedestrian Facilities, Ustick Rd /
McMillan Rd Community Programs N
2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
26 Stockenham Enhanced Cross-
walks NP NP NP
Remove mid-block cross-walk by Hillsdale Elementary
School and add enhanced cross-walks at Lachlan and
near Rockhampton/Hill Park St. Update school zone
signs and flashers.
Scoped in 2020 - Deferred/Consider keeping central mid-block
pedestrian crossing. Moving crossings would put students into
parking lot. To be reviewed with WASD. To be evaluated and
prioritized for possible inclusion into future IFYWP updates.
Hillsdale Elementary Pedestrian Crossings and School
Zone Community Programs N
27
Central Meridian Bikeway, Blue
Heron Street / Chinden
Boulevard
N/A N/A 2029
Install bike facilities along the Central Meridian
Bikeway from Blue Heron Street to Chinden Boulevard. Project programmed to be constructed in 2029.Bikeway Signage (2029) Community Programs N
28 Taormina Drive at Maesaia
Way NP NP NP
Install sidewalk to fix gap on south side of Taormina Dr
near Maesaia Way.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Taormina Dr, Maesaia Way / W/O Stromboli Pl Community Programs N
29 Chinden-McMillan Bikeway,
Ten Mile Road / Sedona Drive N/A N/A 2029
Install bike facilities along the Chinden-McMillan
Bikeway from Ten Mile Road to Sedona Drive. Note:
Most of the stretch already is built or has an
alternative pathway; Locust grove to City Limits still
needed.
Project programmed to be constructed in 2029.Bikeway Signage (2029) Community Programs N
30 Woodbridge Neighborhood
Bike Study NP NP NP
Study the connectivity and bikeability of the
Woodbridge neighborhood, between Locust Grove Rd
and Eagle Rd, north of I-84.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Woodbridge Neighborhood Bike Study Community Programs N
31 Watertower St at Rebound
School NP NP NP
Install a painted crosswalk on Watertower St at
Rebound School.
ACHD Traffic Engineering does not recommend installation.
Crossing activity is caused by parent drop off.
Watertower St and Rebound School Pedestrian
Crossing Community Programs N
32
Hollandale-Targee Bikeway,
Locust Grove Road / Eagle
Road
2026-2027 2028 TBD
Install signage and pavement markings along
Hollandale-TargeeBikeway from Locust Grove Rd to
Eagle Rd.
Project programmed to be designed in 2026-2027. Southwest Boise Improvements B: Hollandale-Targee
Bikeway, Locust Grove Rd / Entertainment Ave Community Programs Y
33 St. Ignatius School Pedestrian
Signal NP NP NP Install pedestrian signal on Meridian Rd at Producer Dr.
Project scoped in 2019. To be evaluated and prioritized for
possible inclusion into future IFYWP updates.Meridian Rd and Producer Dr Pedestrian Crossing Community Programs N
34 McMillan Rd and Palatine Way
Pedestrian Crossing 2026 2027 TBD
Install an enhanced pedestrian crossing and curb
ramps on McMillan Rd at Palantine Way. See Priority
#5 above; please construct concurrently.
Project programmed to be designed in 2026.North Meridian Improvements A: McMillan Rd and
Palatine Way Pedestrian Crossing Community Programs Y
35 West 02nd St, UPRR /
Broadway Ave NP NP NP
Complete sidewalk on both sides of West 02nd St,
between the Union Pacific Railroad and Broadway Ave
to address parking concerns in this area.
Sidewalk scoped "No Go" in 2015. Agencies to coordinate if other
solutions identified.West 02nd, UPRR / Broadway Ave Community Programs N
36 Broadway Ave, West 07th St /
West 04th St NP NP NP
Complete sidewalks on the south side of Broadway
Ave, between West 07th St and West 04th St.
Escalated project costs have resulted in some projects being
deferred.
Meridian Downtown Improvements C: Broadway
Ave, West 08th St / West 04th St Community Programs N
37 Nola Rd and Crossroads Middle
School Pedestrian Crossing NP NP NP
Install a painted crosswalk on Nola Rd at Crossroads
Middle School. See Priority #12 above; construct
concurrently.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.
Nola Rd and Crossroads Middle School Pedestrian
Crossing Community Programs N
38 East 2 1/2 St, Carlton Ave /
Fairview Ave 2025-2026 2027 TBD
Install sidewalk on the west and/or east side of 2 1/2
St, south of Fairview Ave near Cole Valley Christian
School.
Project programmed to be designed in 2025-2026.Meridian Downtown Improvements A: East 2 1/2 St,
Carlton Ave / Fairview Ave Community Programs Y
39 Gondola-Malta Bikeway, Black
Cat Road / Goddard Creek Way NP NP NP Install bike facilities.
Scoped in 2023 - Deferred/waiting for development to complete
roadway network for connectivity. To be evaluated and prioritized
for possible inclusion into future IFYWP updates.
Gondola-Malta Bikeway, W/O Black Cat Rd /
Goddard Creek Way Community Programs N
40
Locust Grove Rd and
Woodbridge Dr Pedestrian
Crossing
NP NP NP
Install an enhanced pedestrian crossing of Locust
Grove Rd at Woodbridge Dr or Watertower St.
Escalated project costs have resulted in some projects being
deferred.
Meridian Downtown Improvements C: Locust Grove
Rd and Woodbridge Dr Pedestrian Crossing Community Programs N
2025
City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded
41 Montague Way, Amity Road /
Santo Stefano Drive NP NP NP
Install sidewalk on east side of Montague Way from
Amity Rd to Santo Stefano Dr.
Montague Way is a collector and roadway improvements to be
completed through redevelopment.Montague Way, Amity Rd / Santo Stefano Dr Community Programs N
42 Black Cat-Ten Mile Bikeway,
Cherry Lane / Ustick Road NP NP NP
Install bike facilities along the Black Cat-Ten Mike
Bikeway.
Scoped in 2023. To be evaluated and prioritized for possible
inclusion into future IFYWP updates.
Black Cat-Ten Mile Bikeway (Phase 1), Cherry Ln /
Ustick Rd Community Programs N
43 Locust Grove, Pine to Franklin
MUP NP NP NP
Install multi-use pathway, between Pine Ave and
Franklin Rd. This would connect the pathway on Pine
Ave, west of Locust Grove Rd to Franklin Rd, where the
pathway then resumes along the Five Mile Creek. This
would replace some existing sidewalk with a multiuse
pathway.
To be evaluated and prioritized for possible inclusion into future
IFYWP updates.Locust Grove Rd, Pine Ave / Franklin Rd Pathway Community Programs N
44 American Fork (Kodiak)/Linder NP NP NP
Signalize intersection. Near Victory Middle School and
bus stops.Request to be shared with our Traffic division. Reponse pending.Linder Rd and Kodiak Dr Pedestrian Crossing Community Programs N
45 Eagle/Fairview Future
Install pedestrian refuge islands on Fairview legs
Paint bike ladders on east and west legs prior to the
right turn lanes
Community Programs N
46 8th/Cherry Future Evaluate the need for directional ramps Community Programs N
47 Linder/Pine Future Add bike medians for turn movements Community Programs N
Removed N Naomi Ave, Ustick to
Ponderosa NP NP NP
Install 20mph school zone signs. Should this be an
enhanced crossing or 20mph or both?Request to be shared with our Traffic division. Reponse pending.Ponderosa Elementary (School Zone Signage)Community Programs