HomeMy WebLinkAbout2025 Meridian Prioritization Request Form - Combined2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 1 Linder Rd, Overland Rd / Franklin Rd 2022-2024 2024-2025 2026-2027 Widen Linder Rd to 5 lanes and construct a new 4-lane I-84 overpass, including curb, gutter, sidewalk, and bike lanes in accordance with the 2016 CIP. Project would be a joint project between ACHD and ITD. Project programmed to be constructed in 2026-2027.Linder Rd, Overland Rd / Franklin Rd Roads & Intersections Y 2 Locust Grove Rd, Fairview Ave / Ustick Rd 2028-2029 TBD TBD Widen Locust Grove Rd to 3, 4 or 5 lanes with curb, gutter and pedestrian/bike facilities. Consider enhanced crossing at Chateau Dr. Project programmed to be designed in 2028-2029.Locust Grove Corridor B: Locust Grove Rd, Fairview Ave / Ustick Rd Roads & Intersections Y 3 Fairview Ave and Locust Grove Rd 2020-2023 2024 2029 Widen intersection. Project programmed to be constructed in 2029.Fairview Ave and Locust Grove Rd Roads & Intersections Y 4 Victory Rd, Locust Grove Rd / Eagle Rd 2027-2028 TBD TBD Widen Victory Rd to 3 lanes. Include preferential bike and pedestrian infrastructure.Project programmed to be designed in 2027-2028.Victory Corridor A: Victory Rd, Locust Grove Rd / Eagle Rd Roads & Intersections Y 5 Ustick Rd, Ten Mile Rd / Linder Rd 2022-2023 2025 2026 Widen Ustick Rd to 5 lanes with curb, gutter,and pedestrian/bike facilities. Project programmed to be constructed in 2026.Ustick Corridor A: Ustick Rd, Ten Mile Rd / Linder Rd Roads & Intersections Y 6 Amity Rd and Locust Grove Rd 2023-2024 2029-2030 TBD Construct interim signalized intersection with preservation for future widening to accommodate 5- lane roadways in all directions. Project programmed to be constructed in future.Amity Corridor A: Amity Rd and Locust Grove Rd Roads & Intersections Y 7 Locust Grove Rd, Amity Rd / Victory Rd NP NP NP Widen Locust Grove Rd to a minimum 3 lanes, with preservation for up to 5 lanes, with curb, gutter and pedestrian/bike facilities. Include pedestrian crossings at Palermo and Wrightwood. Escalated project costs have resulted in some projects being deferred.Locust Grove Rd, Amity Rd / Victory Rd Roads & Intersections N 8 Victory Rd, Meridian Rd / Locust Grove Rd 2027-2028 TBD TBD Widen Victory Rd to 3 lanes. Include preferential bike and pedestrian infrastructure. Complete sidewalk/MUP on the south side of Victory Rd adjacent to County outparcel. Project programmed to be designed in 2027-2028.Victory Corridor A: Victory Rd, SH 69 (Meridian Rd) / Locust Grove Rd Roads & Intersections Y 9 Ten Mile Rd / Cherry Ln 2028-2029 TBD TBD Widen intersection. Intersection improvements to include dual left turn lanes.Project programmed to be designed in 2028-2029.Cherry Ln and Ten Mile Rd Roads & Intersections Y 10 Ustick Rd and Venable Ln NP NP NP Install full signal or roundabout. Scoped in 2023. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Ustick Rd and Venable Ln Roads & Intersections N 11 Eagle Rd / Overland Rd NP NP NP Widen intersection. Intersection improvements to include dual left turn lanes. Escalated project costs have resulted in some projects being deferred.SH-69 (Meridian Rd) and Overland Rd Roads & Intersections N 12 Locust Grove Rd, Ustick Rd / McMillan Rd 2028-2029 TBD TBD Widen Locust Grove Rd to 3, 4 or 5 lanes; preserve for 5 lanes, with curb, gutter, and pedestrian/bike facilities. Project should include an enhanced crossing (pedestrian hybrid beacon) on Locust Grove Road at Heritage Park Street; access for Meridian Technical Charter High School. Project programmed to be designed in 2028-2029.Locust Grove Corridor A: Locust Grove Rd, Ustick Rd / McMillan Rd Roads & Intersections Y 13 McMillan Rd, Meridian Rd / Locust Grove Rd NP NP NP Widen McMillan Rd up to 5-lanes with curb, gutter, sidewalk, and bike/pedestrian facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.McMillan Rd, SH 69 (Meridian Rd) / Locust Grove Rd Roads & Intersections N 14 McMillan Rd, Linder Rd / Meridian Rd NP NP NP Widen McMillan Rd up to 5-lanes with curb, gutter, sidewalk, and bike/pedestrian facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.McMillan Rd, Linder Rd / SH 69 (Meridian Rd)Roads & Intersections N 2025 Meridian Prioritization Request Form 2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 15 Meridian Rd, Ustick Rd / McMillan Rd 2027-2028 TBD TBD Widen Meridian Rd to 3, 4 or 5 lanes; preserve for 5 lanes, with curb, gutter, and pedestrian/bike facilities. Project should include an enhanced pedestrian crossing of Meridian Rd at/near Settlers Park entrance and Sundance Subdivision micropath. Project programmed to be designed in 2027-2028.Meridian Corridor A: Meridian Rd, Ustick Rd / McMillan Rd Roads & Intersections Y 16 Linder Rd, Cherry Ln / Ustick Rd 2028-2029 TBD TBD Widen Linder Rd to include curb, gutter and pedestrian/bike facilities. Include preferential bike and pedestrian infrastructure with wayfinding signage. Project programmed to be designed in 2028-2029. Concept Study in 2022-2024.Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Roads & Intersections Y 17 Amity Rd, Meridian Rd / Locust Grove Rd 2023-2024 2029-2030 TBD Widen Amity Rd to minimum 3 lanes with preservation for up to 5 lanes. Include preferential bike and pedestrian infrastructure for Mary McPherson elementary school. Programmed for design in FY2023-2024.Amity Corridor A: Amity Rd, SH 69 (Meridian Rd) / Locust Grove Rd Roads & Intersections Y 18 Cherry Ln and Black Cat Rd NP NP NP Widen intersection. Address transition from bike-lane to/from MUP. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Cherry Ln and Black Cat Rd Roads & Intersections N 19 Black Cat, Franklin to Cherry 2029-2030 TBD TBD Widen Black Cat Rd with curb, gutter and pedestrian/bike facilities. An interim help could be improvements north of Franklin to the RR tracks near COMPASS school. Project programmed for design in 2029-2030.Black Cat Rd, Franklin Rd / Cherry Ln Roads & Intersections Y 20 Cherry Ln and McDermott Rd NP NP NP Widen intersection. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Cherry Ln and McDermott Rd Roads & Intersections N 21 Cherry Ln, Black Cat Rd / McDermott Rd NP NP NP Widen Cherry Ln with curb, gutter, sidewalk, and bike/pedestrian facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Cherry Ln, McDermott Rd / Black Cat Rd Roads & Intersections N 22 Ustick Rd and Black Cat Rd 2022-2024 2024 2025 Widen intersection. Project programmed to be constructed in 2025.Ustick Corridor A: Ustick Rd and Black Cat Rd Roads & Intersections Y 23 Ustick, Black Cat to Ten Mile 2022-2023 2024 2025 Widen Ustick Rd to 5 lanes with curb, gutter,and pedestrian/bike facilities. Project programmed to be constructed in 2025.Ustick Corridor A: Ustick Rd, Black Cat Rd / Ten Mile Rd Roads & Intersections Y 24 Fairview Ave, SH 55 (Eagle Rd) / Cloverdale Rd NP NP NP Widen Fairview Ave with curb, gutter, sidewalk, and bike/pedestrian facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Fairview Ave, SH 55 (Eagle Rd) / Cloverdale Rd Roads & Intersections N 25 Fairview Ave, Meridian Rd / Locust Grove Rd NP NP NP Widen Fairview Ave with curb, gutter, sidewalk, and bike/pedestrian facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Fairview Ave, Meridian Rd / Locust Grove Rd Roads & Intersections N 26 Ten Mile Rd, Amity Rd / Victory Rd NP NP NP Widen Ten Mile Rd with curb, gutter, sidewalk, and bike/pedestrian facilities. Defer. Operating at a LOS D or better. Reevaluate as conditions change.Ten Mile Rd, Amity Rd / Victory Rd Roads & Intersections N 27 Linder, Pine / Cherry 2028-2029 Future Future Widen Linder Rd to include curb, gutter and pedestrian/bike facilities. Include preferential bike and pedestrian infrastructure with wayfinding signage (several nearby and directly adjacent schools). Project programmed to be designed in 2028-2029. Move to programmed list.Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Roads & Intersections Y 28 McMillan Rd and Star Rd NP NP NP Widen intersection. Defer. Operating at a LOS D or better. Reevaluate as conditions change.McMillan Rd and Star Rd Roads & Intersections N 29 Amity Rd and Linder Rd NP NP NP Widen intersection. Defer. Operating at a LOS D or better. Reevaluate as conditions change.Amity Rd and Linder Rd Roads & Intersections N 30 Amity Rd and Black Cat Rd NP NP NP Widen intersection. Defer. Operating at a LOS D or better. Reevaluate as conditions change.Amity Rd and Black Cat Rd Roads & Intersections N 31 Cherry Ln and Linder Rd NP NP NP Widen intersection. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Cherry Ln and Linder Rd Roads & Intersections N 32 Pine, Linder to Meridian NP NP NP Widen the entire segment to 3-travel lanes with curb, gutter, sidewalks and/or multi-use or mixed-use bikeway. Project would require the removal of on-street parking for existing homes. To be evaluated and prioritized for possible inclusion into future IFYWP updates. Pine Ave, Linder Rd / Meridian Rd Roads & Intersections N 33 Meridian Rd, McMillan Rd / Chinden Blvd 2027-2028 TBD TBD Widen Meridian Rd to 3, 4 or 5 lanes; preserve for 5 lanes, with curb, gutter, and pedestrian/bike facilities. Project programmed to be designed in 2027-2028.Meridian Corridor A: Meridian Rd, McMillan Rd / US 20/26 (Chinden Blvd)Roads & Intersections Y 2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 34 Fairview Ave Corridor Management, Linder Rd / Orchard St NP NP NP Improve safety and traffic operations along Fairview Ave in accordance with the Fairview Avenue Corridor Management Strategy. Project may include bicycle and pedestrian facilities and other access management treatments. Project to be implemented through development. ACHD and Meridian to coordinate implementation as development applications are processed. Fairview Ave Corridor Management, Linder Rd / Orchard St Roads & Intersections N 35 Lake Hazel Rd and Eagle Rd 2019-2022 2022-2023 2025 Widen and signalize intersection.Project programmed to be constructed in 2025.Lake Hazel Rd and Eagle Rd Roads & Intersections Y 36 Ten Mile Rd and Chateau Dr NP NP NP Improve intersection. Does not currently meet warrants. ACHD to reevaluate as development occurs in the area.Ten Mile Rd and Chateau Dr Roads & Intersections N 37 Victory, Linder to Meridian NP NP NP Widen Victory Rd to 3 lanes with curb, gutter and pedestrian/bike facilities. Escalated project costs have resulted in some projects being deferred. Victory Corridor E: Victory Rd, Linder Rd / Meridian Rd Roads & Intersections N 38 Franklin Rd, McDermott Rd / Black Cat Rd 2024-2025 2028-2029 TBD Widen Franklin Rd to 5 lanes with curb, gutter and pedestrian/bike facilities.Project programmed to be constructed in future.Franklin Corridor A: Franklin Rd, McDermott Rd / Black Cat Rd Roads & Intersections Y 39 Linder Rd, Chinden Blvd (US 20/26) / SH 44 (State St) 2027 TBD TBD Widen Linder Rd. with bike and pedestrian facilities as this is one of only a few river crossings in the County and connects to nearby Eagle Island State Park. Part of City's envisioned pathway network. Project programmed to be designed in 2027.Linder Corridor A: Linder Rd, Chinden Blvd (US 20/26) / SH 44 (State St) - South Phase Roads & Intersections Y 40 Fairview Ave, Locust Grove Rd / SH 55 (Eagle Rd)2020-2024 TBD 2029 Widen Fairview Ave to 7 lanes with curb, gutter pedestrian/bike facilities.Project programmed to be constructed in 2029.Fairview Ave, Locust Grove Rd / SH 55 (Eagle Rd)Roads & Intersections Y 41 McMillan Rd and Black Cat Rd 2021-2023 2028 2029 Widen intersection. Project programmed to be constructed in 2029.McMillan Rd and Black Cat Rd Roundabout Roads & Intersections Y 42 Meridian/Overland Signal NP NP NP Improve intersection operation. This may mean adding additional lanes. To be evaluated and prioritized for possible inclusion into future IFYWP updates.SH-69 (Meridian Rd) and Overland Rd Roads & Intersections N 43 Franklin Rd and McDermott Rd 2024-2025 2027-2028 TBD Widen intersection. Coordinate design with ITD and the SH-16 improvements.Project programmed to be constructed in future.Franklin Corridor A: Franklin Rd and McDermott Rd Roads & Intersections Y 44 McMillan Rd and McDermott Rd NP NP NP Widen intersection. Defer. Operating at a LOS D or better. Reevaluate as conditions change.McMillan Rd and McDermott Rd Roads & Intersections N 45 McMillan, Black Cat to Ten Mile NP NP NP Widen with curb, gutter, and pedestrian/bike facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.McMillan Rd, Black Cat Rd / Ten Mile Rd Roads & Intersections N 46 Ustick Rd and McDermott Rd 2024-2025 2026 2027 Widen intersection. Project programmed to be constructed in 2027.Ustick Corridor B: Ustick Rd and McDermott Rd Roads & Intersections Y 47 Victory Rd and Linder Rd NP NP NP Widen intersection. Escalated project costs have resulted in some projects being deferred.Victory Corridor E: Victory Rd and Linder Rd Roads & Intersections N 48 Ustick Rd and Star Rd NP NP NP Widen intersection. Escalated project costs have resulted in some projects being deferred.Ustick Rd and Star Rd Roads & Intersections N 49 Locust Grove Rd, McMillan Rd / Chinden Blvd (US 20/26) NP NP NP Widen Locust Grove Rd to 3, 4 or 5 lanes; preserve for 5 lanes, with curb, gutter, and pedestrian/bike facilities. Escalated project costs have resulted in some projects being deferred. Locust Grove Rd, McMillan Rd / US 20/26 (Chinden Blvd)Roads & Intersections N 50 Ustick Rd, McDermott Rd / Black Cat Rd 2024-2025 2026 2027 Widen Ustick Rd to 5 lanes with curb, gutter and pedestrian/bike facilities.Project programmed to be constructed in 2027.Ustick Corridor B: Ustick Rd, Owyhee Storm Ave / Black Cat Rd Roads & Intersections Y 51 Eagle Rd / Fairview Ave NP NP NP Improve intersection operation. This may mean adding additional lanes or a grade-separated roadway. Request to be shared with our Traffic division. Reponse pending.Eagle Rd and Fairview Ave Roads & Intersections N 52 Lake Hazel / Discovery Park NP NP NP Improve intersection/entry into City Park. The improvements could be a signal, roundabout, or other, but should include provisions for pedestrians/bicyclists. Request to be shared with our Traffic division. Reponse pending.Lake Hazel Rd and Discovery Park Roads & Intersections N 2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 53 Amity, Eagle to Cloverdale 2026-2027 TBD TBD Widen Amity Rd to 5 lanes with curb, gutter and pedestrian/bike facilities. Include enhanced pedestrian crossing at Ten Mile Creek pathway crossing and install pedestrian/bike improvements on Amity Rd near the YMCA and City Park so there are no gaps. Project programmed to be designed in 2026-2027.Amity Corridor B: Amity Rd, Eagle Rd / Cloverdale Rd Roads & Intersections Y 54 Amity, Locust Grove to Eagle NP NP NP Widen Amity Rd to 5 lanes with curb, gutter and pedestrian/bike facilities. Include enhanced pedestiran crossing at Ten Mile Creek pathway crossing. Escalated project costs have resulted in some projects being deferred. Amity Corridor D: Amity Rd, Locust Grove Rd / Eagle Rd Roads & Intersections N 55 Victory, Ten Mile to Linder NP NP NP Widen with curb, gutter, and pedestrian/bike facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Victory Rd, Ten Mile Rd / Linder Rd Roads & Intersections N 56 Black Cat, Cherry to Ustick NP NP NP Widen with curb, gutter, and pedestrian/bike facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Black Cat Rd, Cherry Ln / Ustick Rd Roads & Intersections N 57 Black Cat, Ustick to McMillan NP NP NP Widen with curb, gutter, and pedestrian/bike facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Black Cat Rd, Ustick Rd / McMillan Rd Roads & Intersections N 58 Black Cat, McMillan to Chinden NP NP NP Widen with curb, gutter, and pedestrian/bike facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Black Cat Rd, McMillan Rd / Chinden Blvd (US 20/26)Roads & Intersections N 59 McMillan, Ten Mile to Linder NP NP NP Widen with curb, gutter, and pedestrian/bike facilities. Project should include an enhanced pedestrian crossing and curb ramps on McMillan Rd at Pantine Way, near Hunter Elementary. Project scoped in 2022. To be evaluated and prioritized for possible inclusion into future IFYWP updates.McMillan Rd, Ten Mile Rd / Linder Rd Roads & Intersections N 60 Eagle, Lake Hazel to Amity 2021-2023 2023-2024 2025 Widen Eagle Rd to 5 lanes with curb, gutter, and pedestrian/bike facilities. Project programmed to be constructed in 2025.Eagle Rd, Lake Hazel Rd / Amity Rd Roads & Intersections Y 61 Lake Hazel, Eagle / Cloverdale 2022-2023 2024 2027 Corridor improvement project which includes widening to two (2) to five (5) lanes and constructing enhanced pedestrian and bike facilities on both sides of roadway. Roads & Intersections Y 62 Locust Grove, Lake Hazel to Amity NP NP NP Widen Locust Grove Rd up to 5 lanes with curb, gutter, and pedestrian/bike facilities. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Locust Grove Rd, Lake Hazel Rd / Amity Rd Roads & Intersections N 63 Victory Rd, Eagle Rd / Cloverdale Rd 2028-2029 Future Future Corridor improvement project which includes widening from two (2) to five (5) lanes and constructing enhanced pedestrian and bike facilities on both sides of the roadway. Victory Corridor C: Victory Rd, Eagle Rd / Cloverdale Rd Roads & Intersections Y 64 Locust Grove and McMillan NP NP NP Improve intersection. Please provide additional information regarding type of request and/or improvements needed. McMillan Rd and Locust Grove Rd Roads & Intersections N 65 Meridian and McMillan NP NP NP Improve intersection. Please provide additional information regarding type of request and/or improvements needed. Locust Grove Rd, McMillan Rd / US 20/26 (Chinden Blvd)Roads & Intersections N 66 Linder and McMillan NP NP NP Improve intersection. Please provide additional information regarding type of request and/or improvements needed. McMillan Rd and Linder Rd Roads & Intersections N 67 Ten Mile and McMillan NP NP NP Improve intersection. Please provide additional information regarding type of request and/or improvements needed. McMillan Rd and Ten Mile Rd Roads & Intersections N 2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 1 Stoddard Rd, Victory Rd / Overland Rd (Stoddard Rd, Victory Rd / Kodiak Dr) 2023 2027 TBD Reconstruct Stoddard Rd, between Victory Rd and Overland Rd to 3-lanes, 7' attached sidewalks and bike lanes. Project includes bridge #2085 and an enhanced pedestrian crossing (pedestrian hybrid beacon) at Victory and Stoddard (CM214-27). Bike lanes may be replaced by a pathway per the Bike Master Plan Update. Project programmed to be constructed in future.South Meridian Improvements A: Stoddard Rd, Victory Rd / Overland Rd Community Programs Y 2 East 03rd St, Franklin Rd / Carlton Ave (Phase 1)2025-2026 2027 TBD Construct streetscape improvements, including curb, gutter, sidewalk, and improved UPRR crossing, from Franklin Rd to Carlton Ave in accordance with the Downtown Meridian Neighborhood Plan. Project programmed to be designed in 2025-2026.Meridian Downtown Improvements A: East 03rd St, Franklin Rd / Carlton St Community Programs Y 3 Black Cat Rd Railroad Crossing, 625' N/O Aviator St Reconfigure the railroad crossing to remove stop signs and replace them with an alternative to keep traffic flowing, while also maintaining safety. Community Programs 4 McMillan Rd, Ten Mile Rd / Linder Rd 2029-2030 TBD TBD City requests detached concrete sidewalk with curbing between Goddard Creek Way and Wild Goose Way. City requests a pedestrian crossing across McMillan near Hunter Elementary (near Palatine Way). See Priority #18 below; please construct concurrently. Project programmed to be designed in 2029-2030.North Meridian Improvements B: McMillan Rd, Goddard Creek Way / Wild Goose Way Community Programs Y 5 Main St and King Street Pedestrian Crossing N/A TBD 2026 Install an enhanced pedestrian crossing of Main St at King Street. Main Street northbound has 3 lanes and creates a safety concern. Project to be completed through RPI initiative.Main St and King St Pedestrian Crossing Community Programs N 6 Bower St, Meridian Rd / E. 03rd St 2029-2030 TBD TBD Complete sidewalks and add wayfinding signage on Bower St, between Meridian Rd and E. 03rd St.Project programmed to be designed in FY2029-2030. North Meridian Improvements B: Bower St, Meridian Rd / East 03rd St Community Programs Y 7 Pine Ave and W. 1st St Pedestrian Crossing NP NP NP Install an enhanced pedestrian crossing (rectangular rapid flashing beacon) on Pine Ave at W 01st St to improve access to Meridian Elementary School. Escalated project costs have resulted in some projects being deferred.Pine Ave and West 01st St Pedestrian Crossing Community Programs N 8 W 7th St, Cedarburg Dr to Washington St.2022-2023 2024 2025 Install sidewalk to fix gap on NW 7th St. This gap prevents connection from the sidewalk from the south and east from connecting to the micro-path at Meridian Middle School/8th St. Included in the Meridian Downtown Pavement and Pedestrian Improvements (2025) project. Move to programmed list. Meridian Downtown Pavement and Pedestrian Improvements (2025)Community Programs Y 9 McMillan Rd, Locust Grove Rd / Red Horse Way 2026 2028 2029 Complete sidewalk gap on the north side of McMillan Rd, between Locust Grove Rd and Red Horse Way.Project programmed to be constructed in 2029.McMillan Rd, Meridian Rd / Locust Grove Rd Community Programs Y 10 Locust Grove Rd and Palermo Dr Pedestrian Signal 2022-2023 2024 2028 Install an enhanced pedestrian signal and lighting on the north side of Palermo Dr at Locust Grove Rd.Project programmed to be constructed in 2028.South Meridian Improvements A: Locust Grove Rd and Palermo Dr Pedestrian Crossing Community Programs Y 11 Locust Grove Road, Leighfield Drive to Star Lane 2028-2029 TBD TBD Connect gap from existing sidewalk on west side of Locust Grove Rd, along with improving narrow sidewalk on east side of roadway newar Leighfield Dr and Star Dr; east side of Locust Grove Rd to connect with an existing path to the school near Paradise Ln and Grand Canyon Dr; and install an enhanced crossing (PHB) on Locust Grove Rd at Heritage Park St, near Meridian Technical Charter High School. These improvements are needed sooner than what is planned with the roadway project. Project programmed to be designed in 2028-2029. Locust Grove Corridor A: Locust Grove Rd, Ustick Rd / McMillan Rd Community Programs Y 2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 12 E. 3rd, Carlton to Fairview NP NP NP Extend roadway and construct streetscape improvements, including curb, gutter, sidewalk, and improved UPRR crossing, from Carlton Ave to Fairview Ave in accordance with several downtown plans and studies. Extension to be completed through development. Duplicate request. Recommend combining with other request.East 03rd St, Carlton St / Fairview Ave (Phase 2)Community Programs N 13 Ustick-Cherry Bikeway, Black Cat Road / Chateau Drive NP NP NP Install bike facilities. Several (likely 5) segments needed. City requests ACHD's assistance in prioritizing and scoping corridor connections (likely east to west.) Scoped in 2024. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Ustick-Cherry Bikeway, Black Cat Rd / Hickory Way Community Programs N 14 Linder Rd, Washington St / Maple St 2028-2029 TBD TBD Include preferential bike and pedestrian infrastructre near Meridian High School. Complete sidewalk on the west side of Linder Rd, between Washington St and Maple St. These improvements are needed sooner than what is planned with the roadway project . Project programmed to be designed in 2026. Concept Study in 2022-2024.Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Community Programs Y 15 Cherry Ln, Linder Rd / Meridian Rd NP NP NP Install bike facilities along Cherry Ln from Linder Rd to Meridian Rd To be evaluated and prioritized for possible inclusion into future IFYWP updates.Cherry Ln Bikeway, Linder Rd / Meridian Rd Community Programs N 16 Linder Road, Maple Avenue / Cherry Lane 2028-2030 TBD TBD Include preferential bike and pedestrian infrastructure for existing schools and City park. These improvements are needed sooner than what is planned with the roadway project. Project programmed to be designed in 2026. Concept Study in 2022-2024. Linder Corridor B: Linder Rd, Pine Ave / Ustick Rd Community Programs Y 17 Ten Mile-Linder Bikeway, Linder Road / Chinden Boulevard NP NP NP Install bike facilities, signing and pavement markings. Scoped in 2020. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Ten Mile-Linder Bikeway, W 08th St / Chinden Blvd Community Programs N 18 McMillan-Ustick Bikeway, Cool River Avenue / Eagle Road NP NP NP Install bike facilities. Scoped in 2020. To be evaluated and prioritized for possible inclusion into future IFYWP updates. McMillan-Ustick Bikeway (Phase 3), Linder Rd / Eagle Rd)Community Programs N 19 Broadway Ave / Idaho Ave Extension, East 06th St / Locust Grove Rd NP NP NP Extend roadway from its current terminus at NE 6th St to Stonehenge Way/ Commercial Dr and construct streetscape improvements, including curb, gutter, sidewalk/MUP. Defer. To be considered as properties redevelopment.Broadway Ave / Idaho Ave Extension, 06th St / Locust Grove Rd Community Programs N 20 W Park Creek Dr, Crosswalk at N Deer Creek Ln NP NP NP Install enhanced crossing with hawk signal or RRFB To be evaluated and prioritized for possible inclusion into future IFYWP updates. Project Scoped as part of Black Cat-Ten Mile Bikeway in FY2023 Scoping Effort. North Meridian Improvements C: Park Creek Dr and Deer Creek Ln Pedestrian Crossing Community Programs N 21 Fairview Terrace to Chief Joseph NP NP NP Pedestrian connection (sidewalk) between Barbara Dr in Fairview Terrace Park to E. Willowbrook Dr and Chief Joseph Elementary on Chateau Drive. Need right-of- way. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Chief Joseph Elementary Pedestrian Improvements Community Programs N 22 Locust Grove-Eagle Bikeway, Pine Avenue / McMillan Road NP NP NP Install bike facilities. Several (likely 3) segments needed. City requests ACHD's assistance in prioritizing and scoping corridor connections (likely south to north.) Scoped in 2020. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Locust Grove-Eagle Bikeway, Pine Ave / Chinden Blvd Community Programs N 23 Linder-Meridian Bikeway, Cherry Lane / Chinden Boulevard NP NP NP Install bike facilities. Escalated project costs have resulted in some projects being deferred. North Meridian Improvements C: Linder-Meridian Bikeway, Pine Ave / Temple Dr Community Programs N 24 Nola Rd, south of Pine Ave (Middle School)N/A N/A 2025 Construct pedestrian/bicycle faciliteis on Nola Rd from Pine Ave to Crossroads Middle School/RR Tracks. See Priority #19 below; construct concurrently. Project added to Safe Sidewalk Program (2025). To be constructed in 2025. Move to programmed list. Nola Rd and Crossroads Middle School Pedestrian Crossing Community Programs N 25 McDermott Road, Ustick Road to McMillan Road NP NP NP Install pedestrian/bike facilities on the west side of McDermott Rd connecting to infrastructure on Ustick Rd and McMillan Rd for connectivity to Owyhee High School. Escalated project costs have resulted in some projects being deferred. McDermott Rd Pedestrian Facilities, Ustick Rd / McMillan Rd Community Programs N 2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 26 Stockenham Enhanced Cross- walks NP NP NP Remove mid-block cross-walk by Hillsdale Elementary School and add enhanced cross-walks at Lachlan and near Rockhampton/Hill Park St. Update school zone signs and flashers. Scoped in 2020 - Deferred/Consider keeping central mid-block pedestrian crossing. Moving crossings would put students into parking lot. To be reviewed with WASD. To be evaluated and prioritized for possible inclusion into future IFYWP updates. Hillsdale Elementary Pedestrian Crossings and School Zone Community Programs N 27 Central Meridian Bikeway, Blue Heron Street / Chinden Boulevard N/A N/A 2029 Install bike facilities along the Central Meridian Bikeway from Blue Heron Street to Chinden Boulevard. Project programmed to be constructed in 2029.Bikeway Signage (2029) Community Programs N 28 Taormina Drive at Maesaia Way NP NP NP Install sidewalk to fix gap on south side of Taormina Dr near Maesaia Way. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Taormina Dr, Maesaia Way / W/O Stromboli Pl Community Programs N 29 Chinden-McMillan Bikeway, Ten Mile Road / Sedona Drive N/A N/A 2029 Install bike facilities along the Chinden-McMillan Bikeway from Ten Mile Road to Sedona Drive. Note: Most of the stretch already is built or has an alternative pathway; Locust grove to City Limits still needed. Project programmed to be constructed in 2029.Bikeway Signage (2029) Community Programs N 30 Woodbridge Neighborhood Bike Study NP NP NP Study the connectivity and bikeability of the Woodbridge neighborhood, between Locust Grove Rd and Eagle Rd, north of I-84. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Woodbridge Neighborhood Bike Study Community Programs N 31 Watertower St at Rebound School NP NP NP Install a painted crosswalk on Watertower St at Rebound School. ACHD Traffic Engineering does not recommend installation. Crossing activity is caused by parent drop off. Watertower St and Rebound School Pedestrian Crossing Community Programs N 32 Hollandale-Targee Bikeway, Locust Grove Road / Eagle Road 2026-2027 2028 TBD Install signage and pavement markings along Hollandale-TargeeBikeway from Locust Grove Rd to Eagle Rd. Project programmed to be designed in 2026-2027. Southwest Boise Improvements B: Hollandale-Targee Bikeway, Locust Grove Rd / Entertainment Ave Community Programs Y 33 St. Ignatius School Pedestrian Signal NP NP NP Install pedestrian signal on Meridian Rd at Producer Dr. Project scoped in 2019. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Meridian Rd and Producer Dr Pedestrian Crossing Community Programs N 34 McMillan Rd and Palatine Way Pedestrian Crossing 2026 2027 TBD Install an enhanced pedestrian crossing and curb ramps on McMillan Rd at Palantine Way. See Priority #5 above; please construct concurrently. Project programmed to be designed in 2026.North Meridian Improvements A: McMillan Rd and Palatine Way Pedestrian Crossing Community Programs Y 35 West 02nd St, UPRR / Broadway Ave NP NP NP Complete sidewalk on both sides of West 02nd St, between the Union Pacific Railroad and Broadway Ave to address parking concerns in this area. Sidewalk scoped "No Go" in 2015. Agencies to coordinate if other solutions identified.West 02nd, UPRR / Broadway Ave Community Programs N 36 Broadway Ave, West 07th St / West 04th St NP NP NP Complete sidewalks on the south side of Broadway Ave, between West 07th St and West 04th St. Escalated project costs have resulted in some projects being deferred. Meridian Downtown Improvements C: Broadway Ave, West 08th St / West 04th St Community Programs N 37 Nola Rd and Crossroads Middle School Pedestrian Crossing NP NP NP Install a painted crosswalk on Nola Rd at Crossroads Middle School. See Priority #12 above; construct concurrently. To be evaluated and prioritized for possible inclusion into future IFYWP updates. Nola Rd and Crossroads Middle School Pedestrian Crossing Community Programs N 38 East 2 1/2 St, Carlton Ave / Fairview Ave 2025-2026 2027 TBD Install sidewalk on the west and/or east side of 2 1/2 St, south of Fairview Ave near Cole Valley Christian School. Project programmed to be designed in 2025-2026.Meridian Downtown Improvements A: East 2 1/2 St, Carlton Ave / Fairview Ave Community Programs Y 39 Gondola-Malta Bikeway, Black Cat Road / Goddard Creek Way NP NP NP Install bike facilities. Scoped in 2023 - Deferred/waiting for development to complete roadway network for connectivity. To be evaluated and prioritized for possible inclusion into future IFYWP updates. Gondola-Malta Bikeway, W/O Black Cat Rd / Goddard Creek Way Community Programs N 40 Locust Grove Rd and Woodbridge Dr Pedestrian Crossing NP NP NP Install an enhanced pedestrian crossing of Locust Grove Rd at Woodbridge Dr or Watertower St. Escalated project costs have resulted in some projects being deferred. Meridian Downtown Improvements C: Locust Grove Rd and Woodbridge Dr Pedestrian Crossing Community Programs N 2025 City Priority Agency Project Name Design YR ROW YR Const YR Agency Project Description ACHD Update ACHD Implementation Project Name Program Funded 41 Montague Way, Amity Road / Santo Stefano Drive NP NP NP Install sidewalk on east side of Montague Way from Amity Rd to Santo Stefano Dr. Montague Way is a collector and roadway improvements to be completed through redevelopment.Montague Way, Amity Rd / Santo Stefano Dr Community Programs N 42 Black Cat-Ten Mile Bikeway, Cherry Lane / Ustick Road NP NP NP Install bike facilities along the Black Cat-Ten Mike Bikeway. Scoped in 2023. To be evaluated and prioritized for possible inclusion into future IFYWP updates. Black Cat-Ten Mile Bikeway (Phase 1), Cherry Ln / Ustick Rd Community Programs N 43 Locust Grove, Pine to Franklin MUP NP NP NP Install multi-use pathway, between Pine Ave and Franklin Rd. This would connect the pathway on Pine Ave, west of Locust Grove Rd to Franklin Rd, where the pathway then resumes along the Five Mile Creek. This would replace some existing sidewalk with a multiuse pathway. To be evaluated and prioritized for possible inclusion into future IFYWP updates.Locust Grove Rd, Pine Ave / Franklin Rd Pathway Community Programs N 44 American Fork (Kodiak)/Linder NP NP NP Signalize intersection. Near Victory Middle School and bus stops.Request to be shared with our Traffic division. Reponse pending.Linder Rd and Kodiak Dr Pedestrian Crossing Community Programs N 45 Eagle/Fairview Future Install pedestrian refuge islands on Fairview legs Paint bike ladders on east and west legs prior to the right turn lanes Community Programs N 46 8th/Cherry Future Evaluate the need for directional ramps Community Programs N 47 Linder/Pine Future Add bike medians for turn movements Community Programs N Removed N Naomi Ave, Ustick to Ponderosa NP NP NP Install 20mph school zone signs. Should this be an enhanced crossing or 20mph or both?Request to be shared with our Traffic division. Reponse pending.Ponderosa Elementary (School Zone Signage)Community Programs