BOISE PROJECT BOARD OF CONTROL
(FORMERLY BOISE U.S. RECLAMATION PROJECT)
OPERATING AGENCY FOR 187,000
ACRES FOR THE FOLLOWING
IRRIGATION DISTRICTS
2485 OVERLAND ROAD � �! i""t •'^ '' " '"---�
BOISE, IDAHO 83705-3155
iy
CITY CLERKS OFFICE
13 November 2024
RE: Apex Zenith
E Lake Hazel and South Meridian Rd, Meridian
Boise-Kuna Irrigation District
New York Irrigation District
Rawson Canal 259+90
Sec. 06, T2N, R1E, BM.
Nick Napoli:
H-2204-0052 AZ, RZ, MDA
NAMPA-MERIDIAN
DISTRICT
BOISE-KUNA DISTRICT
WILDER DISTRICT
NEW YORK DISTRICT
BIG BEND DISTRICT
BK-146
N(-229-001-00, 001-01, 001-02
TEL:(208) 344-1141
FAX:(208)344-1437
The United States' Rawson Canal lies within the boundary of the above -mentioned location. The
easement for this can and lateral is held in the name of the United States through the Bureau of
Reclamation under the authority of the Act of August 30, 1890. (26 Stat. 3910 43 U.S.C. 945) if
approved.
The Boise Project Board of Control is contracted to operate and maintain this canal. We assert this
Federal easement of 40 feet both directions of the Rawson Canal centerline. Whereas this area is
for the operation and maintenance of our facility, no activity should hinder our ability to do so.
The Boise Project does not approve landscaping (gravel only) within its easements, as this will
certainly increase the cost of maintenance. The easement must remain a flat drivable surface. All
public roadways must be outside of this easement. Easement must remain a flat drivable surface.
No variances will be granted.
Fencing, gates, pathways and pressurized irrigation lines (as may be required) must be constructed
just off the lateral easement, to ensure public safety and prevent encroachments. No variances will
be granted.
The construction of any roadway crossings must be conducted only during the non -irrigation
season when the lateral is dewatered. In any case no work shall take place within the easement
before the proper crossing agreements have been secured through the Bureau of Reclamation and
the Boise Project Board of Control.
If you have any further questions or comments regarding this matter, please do not hesitate to
contact me at (208) 344-1141.
Sincerely,
omas Rittthaler
Assistant Project Manager, BPBC
for/tr
cc: Kevin Reeves Watermaster, Div. 2 BPBC
Alicia Flavel Secretary — Treasurer, BKID
Terri Hasson Secretary — Treasurer, NYID
File
Project facilities and/or easements that parallel and are within and/or intended to be within road
right-of-ways due to any development of this property must be relocated outside of road right-of-
ways.
Utilities planning to cross any project facility must do so in accordance with the master policies
now held between the Bureau of Reclamation and most of the utilities. In any case no work shall
take place within the easement before proper crossing agreements have been secured through both
the Bureau of Reclamation and the Boise Project Board of Control.
Crossing agreements must be secured and signed by all parties prior to March 1st of each year. A
time schedule for the construction to be done during the non -irrigation season must be approved
by Boise Project prior to any activity within Project easements. No construction will be allowed
within the easement boundaries of the Boise Project Board of Control facilities after March 1st of
each year. However, on a case -by -case basis, overhead utilities and utilities boring underneath a
Project facility may be allowed after March lst if reviewed and approved by the Boise Project.
Storm Drainage and/or Street Runoff must be retained on site.
NO DISCHARGE into the live irrigation system is permitted.
Per Idaho Statutes, Title 42, local irrigation/drainage ditches that cross this property, to serve
neighboring properties, must remain unobstructed and protected by an appropriate easement by
the landowner, developer and contractors.
T 7hereas this property lies ivithin the Boise -Kona and Neiv York Irrigation Districts it is important
that representatives of this development contact these offices as soon cis possible to discuss the
pressure system prior to any costly design work If applicable the irrigation systein will have to
be built to specific specifications as set by the District / Project.
YVr•itten confirmation froin the Boise -Kura and New York Irrigation Districts and the City of
Meridian is required as to ivho will olvn and operate the irrigation system.
If the districts are to oivn and operate this Pressurized irrigation systent, Boise Project Board of
Control will require a set of plans be sent to An Money, Civil Survey Consultants, Inc. at 1400
E. Watertoiver Street, Meridian, Idaho 83642-3513 for his review, comments and aapprovaaL
This development is subject to Idaho Code 31-3805, in accordance, this office is requesting a Rill -
size hard copy of the irrigation and drainage plans.
Wording on the preliminary and final recorded plat needs to state that any proposed and/or future
usage of the Boise Project Board of Control facilities are subject to Idaho Statutes, Title 42-1209.
Whereas this development is in its preliminary stages, Boise Project Board of Control reserves
the right to require changes when our easements and/or facilities are affected by unknown factors
even during the approved construction phase.