1D1A `� ^'' PREAPPLICATION MEETING
D A�i t3
Type of Review Requested
Pre-Application Request File number: P REAP P-2022-0179
Assigned Planner: Sonya Allen
Scheduled Date: 11/01/2022 Scheduled Time: 2:00 PM
Applicant Information
Name: MANDIE BROZO, CSHQA
Address: 200 BROAD STREET 83702
Phone. Email: mandie.brozo@cshqa.com
Additional Attendee(s)
Name: Nicholas Sommariva Business Name: Cortland
Address: 3424 Peachtree Road NE Suite 300 Atlanta, GA 30326
Phone: 5052641653 Email: nick.sommariva@cortland.com
Name: George Rees Business Name: Cortland
Address: 3424 Peachtree Road NE Suite 300 Atlanta, GA 30326
Phone: 4042859227 Email: george.rees@cortland.com
Name: Michael Slavin Business Name: High Desert Development Linder Village, LLC
Address: 2537 W State St. Suite 110 Boise, ID 83702
Phone. Email: michael@accomplice.group
Name: Joe Huarte Business Name: High Desert Development Linder Village, LLC
Address: 2537 W State St. Suite 110 Boise, ID 83702
Phone. Email: joehuarte@gmail.com
Subject Property Information
Location/street address: 907 W CHINDEN BLVD
Assessor's parcel number R5262501200
(s):
Township, range, section: 4N1W25
Project Description
Project/Application Name: Orchard Park Multi-family
Description of Work: Orchard Park Multi Family and Mixed Use Development
33 E Broadway Avenue, Suite 102 • Meridian, Idaho 83642
Phone: (208)884-5533 • Facsimile: (208)888-6854 • Website: www.meridaincity.org
1
Application Information
APPLICATION TYPES
Conditional Use Permit -CUP: CHECKED
Design Review - DR: CHECKED
MEETING TYPE
Do you plan to attend this preapplication meeting in person or In Person
virtually via Microsoft Teams?:
MULTI-FAMILY
Number of 1 Bedroom Units: 265
Number of 2-3 Bedroom Units: 265
Number of 4+ Bedroom Units: 0
Number of Units Containing 1,200+ sq. ft.: 42
Number of Units Containing 500 sq. ft. or Less: 0
Number of Units Containing 500-1,200 sq. ft.: 488
Total Number of Units: 530
PROJECT INFORMATION
A neighborhood meeting is good for 3 months and is required prior CHECKED
to application submittal:
Elevations Date (MM/DD/YYYY): TBD
Gross Density: 39 units/acre
Gross Floor Area Proposed: 812,000 SF
I acknowledge pre-app notes are good for 4 months: CHECKED
I acknowledge that a Site Plan will be uploaded in the attachment CHECKED
section:
In Reclaimed Water Buffer: No
Irrigation District: Settler's Irrigation District and North Slough
Lateral Users Association
Landscape Plan Date (MM/DD/YYYY): 10/7/22
Minimum Square Footage of Ground Floor Area for Multi-Story 650 sf
Units:
Minimum Square Footage of Living Area (Excluding Garage): 630
Number of Compact Parking Spaces Provided: 97
Number of Residential Units: 530
Number of Standard Parking Spaces Provided: 873
Percentage of Site Devoted to Building: 34
Percentage of Site Devoted to Landscaping: 46
Percentage of Site Devoted to Paving: 20
Primary Irrigation Source: Settler's Irrigation District and North Slough
Lateral Users Association
Proposed Building Height: 35'-65'
Secondary Irrigation Source: Settler's Irrigation District and North Slough
Lateral Users Association
33 E Broadway Avenue, Suite 102 • Meridian, Idaho 83642
Phone: (208)884-5533 • Facsimile: (208)888-6854 • Website: www.meridaincity.org
2
Site Plan Date (MM/DD/YYYY): 10/7/22
Square Footage of Landscaped Areas to be Irrigated by City Water 274500 sf
Connection:
Who will own and Maintain the Pressurized Irrigation System in this developer
Development:
PROPERTY INFORMATION
Current Land Use: vacant
Total Acreage: 13.663
QUALIFYING OPEN SPACE
10' Parkway Along Arterials: CHECKED
Acres of Qualified Open Space: 3+ acres
Arterial Street Buffer(s): CHECKED
Collector Street Buffer(s): CHECKED
Community Garden: CHECKED
Open Grassy Area (min. 50' x 100'): CHECKED
Parkways: CHECKED
Percentage of Qualified Open Space: 20
Plaza(s): CHECKED
QUALIFYING SITE AMENITIES
Additional 5% Open Space: CHECKED
Clubhouse: CHECKED
Dog Owner Facilities: CHECKED
Enclosed Bike Storage: CHECKED
Fitness Facilities: CHECKED
Neighborhood Business Center: CHECKED
Open Grassy Area (min. 50' x 100') - Multi-Family: CHECKED
Pedestrian or Bicycle Circulation System: CHECKED
Picnic Area: CHECKED
Public Art: CHECKED
Swimming Pool: CHECKED
Walking Trails: CHECKED
TYPE OF USE PROPOSED
Commercial: CHECKED
Multi-Family: CHECKED
Office: CHECKED
ZONING DISTRICT(S)
C-C: CHECKED
33 E Broadway Avenue, Suite 102 • Meridian, Idaho 83642
Phone: (208)884-5533 • Facsimile: (208)888-6854 • Website: www.meridaincity.org
3
Review Type Reviewer Review Notes
Addressing Plan Review Notes Mercedes Amador -Each commercial building will have a unique address and
each suite will have a number assigned.
-The clubhouse/pool house will be assigned the primary
address and each multi family building will be assigned a
letter identifier.
Land Development Plan Review Steve O'Brien We strongly encourage you phase the development plans to
Notes accommodate phased Certificate of Occupancy for the
buildings, The City requires all site development is
completed prior to the issuance of Certificate of Occupancy.
In order to phase occupancy on the multiple buildings, It is
recommended that you submit the projects Civil Plans for
review the following way:
•A master utility plan showing the entire site and phase lines
• Utility plans for each phase with a unique project name for
each AutoCAD of the entire site including phase lines
• Multiple Buildings Memo with signature.
To be considered complete a project must have:
•All final inspections (water, sewer, street lights, and
reclaimed water—as applicable), passed
• Final inspection letters submitted from the Civil Engineer
(Pressure Irrigation, Private Drainage, and Well
Abandonment—as applicable),
• Record drawings submitted and approved through Public
Works, 30 days prior to CO task list compellation.
• Warranty surety in place for all water and sewer mains,
• Documentation that permanent street signs and/or
apartment directional signs were installed
• Non-life safety items such as landscaping and amenities
maybe be excluded on a case by case basis with planning
approval and appropriate sureties in place.
If site development plans DO NOT show phasing, it indicates
that all development improvements must all be completed
prior to any Certificate of Occupancy to be issued for any
building within the site. There cannot be any leasing of any
building or apartments prior to the Project completion and
CO issued.
Information Note to CEPE: Record Drawings must be
submitted 30 days prior to CO
Legal Review Notes Kurt Starman Will require an amendment to the existing development
agreement.
MFD Plan Review Notes Joe Bongiorno Good access and wayfinding signs will be important. Fire
sprinklers for sure in the courtyard areas as we can't get to
them. Two story max in that area as well as we cant get a
ladder truck in there. How tall is the parking structure?
33 E Broadway Avenue, Suite 102 • Meridian, Idaho 83642
Phone: (208)884-5533 • Facsimile: (208)888-6854 • Website:www.meridaincity.org
4
MPD Plan Review Notes Shawn Harper We need to see a fire access plan for the collective buildings
and the 5-story MF/retail/parking portions. Any buildings over
30 ft. in height requires aerial fire apparatus access and
these roadways (min. 26 ft. wide) need to be within certain
distances to the building.
All buildings require fire riser rooms constructed with one-
hour construction with an exterior door.
Fire sprinkler FDCs (Fire Dept. Connections) shall be located
within 100 ft. to a fire hydrant.
Planning Review Notes Sonya Allen *An amendment to the concept plan included in the existing
DA (Inst.#2021-102392) is required to change the
development plan for this site. Also update the Use Area
Plan & Pedestrian Circulation Plan.
* Comply with the dimensional standards of the C-C zoning
district, including height. (A CUP may be needed for the
height; see UDC 11-2113-3.)
* MFR requires a CUP in the C-C zoning district and is
subject to the specific use standards listed in UDC 11-4-3-
27.
*A vertically integrated residential project is principally
permitted in the C-C district, subject to the specific use
standards listed in UDC 11-4-3-41. Must comply with the
standards in effect at the time of application submittal -there
is currently a UDC text amendment in process to change the
existing standards (ZOA-2022-0001).
*All structures must comply with the design standards in the
Architectural Standards Manual; or, request a design
standard exception.
Wastewater Plan Review Notes Vicki Ly • Proposed flow is 48,800 gpd greater than the master plan.
Capacity is available at this time but the City makes no
guarantee that capacity will be available at the time
application submittal.
• Ensure no permanent structures (trees, bushes, buildings,
carports, trash receptacle walls, fences, infiltration trenches,
light poles, etc.) are built within the utility easement.
• Ensure no sewer services cross infiltration trenches
Water Plan Review Notes Tyson Glock • For the multi-family there are three existing stubs that must
be looped through the site. There is one from the west, east,
and southeast corner(off of Orchard Park Dr). Current layout
does not allow connection to the east or from southeast
corner of the site. These connections are required.