HomeMy WebLinkAboutPZ - Applicant's Response to Staff Report 11-17 GIVENS PURSLEYLLP
Attorneys and Counselors at Law
601 W.Bannock Street Gary G.Allen Don Z.Gray Deborah E.Nelson
PO Box 2720 Charlie S.Baser Paul G.Hawkins Samuel F.Parry
Boise,ID 83701 Christopher J.Beeson Brian J.Holleran Randall A.Peterman
Telephone:208-388-1200 Jason J.Blakley Kersti H.Kennedy Blake W.Ringer
Facsimile:208-388-1300 Clint R.Bolinder Elizabeth A.Koeckeritz Michael O.Roe
Jeff W.Bower Neal A.Koskella Danielle M.Strollo
www.givenspursley.com Preston N.Carter Michael P.Lawrence Robert B.White
Chynna K.Castoro Franklin G.Lee Michael V.Woodhouse
Jeremy C.Chou David R.Lombardi
Michael C.Creamer Lars E.Lundberg
Charlotte V.Cunnington Kimberly D.Maloney William C.Cole(Of Counsel)
Joshua C.Dickinson Kenneth R.McClure
Amber N.Dina Alex P.McLaughlin
Bradley J.Dixon Melodie A.McQuade Kenneth L.Pursley(1940-2015)
Thomas E.Dvorak Christopher H.Meyer James A.McClure(1924-2011)
Rebecca M.Fitz L.Edward Miller Raymond D.Givens(1917-2008(
Morgan D.Goodin Judson B.Montgomery
November 17, 2022
Via email to sallen@meridiancity.org
Meridian Planning Division
c/o Sonya Allen
33 E Broadway Ave., Suite 102
Meridian, Idaho 83642
RE: Applicant's Response to Staff Report for Sessions Parkway(H-2022-0046)
Dear Planning and Zoning Commissioners:
Givens Pursley represents the applicant on the above commercial development project. Our
development team has reviewed the Staff Report and thanks planning staff for their support of the
Project and recommendation of approval. We agree with all but four of planning staff s
recommended conditions related to site plan design.
Property Background
The application proposes a development agreement modification and a preliminary plat for
five commercial lots comprising the Session Parkway Subdivision, accessible via State
Highway 55. This a small 5.32-acre infill project, owned by the developer of the adjacent Village
Apartments. The property is ideally situated for commercial use because it has frontage along one
of the City's key commercial corridors, State Highway 55.
Concept Plans
The applicant has proposed two conceptual site plans — both concept plans depict a fuel
sales facility and a drive-through establishment fronting Highway 55. The first site plan proposes
three commercial pads on the eastern border of the property(Exhibit 1.0 in the Staff Report). The
second site plan replaces the three commercial pads with a hotel use (Exhibit 2.0 in the Staff
Report).
Response to Proposed Site Plan Conditions
Applicant has worked with planning staff over the past several months to revise the concept
plans to accommodate planning staff requests. In addition to the revisions made to date, planning
staff has proposed several additional conditions regarding site plan layout that cannot be
accommodated by the project based on the site constraints and anticipated uses. The applicant
seeks your approval of the project with the removal of 4 proposed conditions in Section VIII.A.La
of the Staff Report for the following reasons:
Proposed Condition 1. Depict non-retail commercial, office or civic uses for a minimum of 50%
of the development area on Exhibit EX1.0,unless Commission or Council find this isn't applicable
because this property is part of a larger MU-R designated area. This doesn't apply if the property
develops with the hotel as proposed in exhibit EX2.0.
Applicant Response. The Comprehensive Plan for the MU-R designation encourages a mix of uses
for development within the MU-R designation. One of the MU-R goals is that "retail uses should
comprise a maximum of 50%of the mixed use development area." Given the size of the property,
5.32 acres, and due to the location of the property within a much greater MU-R designated area,
the MU-R comprehensive plan considerations regarding a maximum for retail commercial should
not apply to this small infill project. The overall MU-R area, which includes the area east of
Highway 55 between Ustick Road and Fairview Avenue comprises approximately 150 acres.
Within this area there is a robust mix of uses. Two multi family residential developments abut the
Project on its east and south-east sides. The Project is bounded by retail and professional service
uses on its north and south boundaries. To the west, across Highway 55, is undeveloped property
and a detached single-family residential development. Kleiner Park, a regional city park, is
114 mile to the southeast. Given the mix of uses in the immediate vicinity, we request removal of
any condition requiring a specific percentage of uses within the Project area.
Proposed Condition. Specific details for the integrated plaza/open areas shall be provided with the
first certificate of zoning compliance. The applicant can relocate open space/plaza areas depicted
on the plan with director approval once specific tenants are known.
Applicant Response. We request that the plaza area/open space remain where depicted on the
concept site plans, clustered along the southern boundary of the property. For this property
clustering along the southern boundary makes the most sense because it facilitates connection with
the surrounding multi family residential located to the east and southeast and to Kleiner Park. See
Figure I below. We have focused on pedestrian connectivity with these neighboring residential
projects in designing the concept plans, and the plaza area and open space in this corridor
enhances that connectivity and usability. Further, when looking at the surrounding residential
development in the immediate MU-R area, the location of the proposed plaza area is centrally
located for future users of the Sessions Parkway commercial area.
Proposed Condition. On concept plan 1, labeled as EXI.0, some or all of the buildings along the
eastern boundary should be rotated and/or relocated and a shared plaza area/green space added to
a more central location within the development for better integration, including a central pathway
connection to the open space and front pad sites.
I I • I /I I' I / I/' 'I / I • I • I I
I I • • I • I I I' I/ / I/I '/ I • / I I'
I I / I I ' I / I / /I I I I • I I I • I I I
E
ft Jm Oft raw
� I j 1111 Wr�.7' r!I.. ice, 1i�
911 r r 1
PON
ram. -= --�+' �,� � � •�"�"a
MCI t
ZEN
�1111111 Ir■IIY�1 ' ��
,
i � -
■ r 11 :-r :11 ,-7
Irr ill�11111111111■ 1�111
VW
l • •
f
Proposed Condition. If the site develops consistent with concept plan 2, labeled as EX2.0, the
applicant shall construct a 5-foot sidewalk on the east boundary and provide a decorative crosswalk
across the drive aisle of the multi-family portion of the development (SWC of the Village
Apartment)to enhance pedestrian connectivity.
Applicant Response. We request that the sidewalk remain as depicted on the concept plan. This
location provides good connectivity between the adjacent parcels to the north and south.As shown
above in Figure 1, the adjacent multi family development to the east(also owned by the applicant)
already provides significant connectivity to and through that multi family development, making a
pathway along the eastern boundary redundant for the residents of the multi family development.
A pathway located directly adjacent to the hotel is preferred for hotel guest's access to the
multitude of shopping and recreation sites within the immediate vicinity. We agree to provide a
decorative crosswalk in the southeast portion of the site as requested by staff.
Idaho Transportation Department Conceptual Approval
Attached is recent correspondence from the Idaho Transportation Department with our
project traffic engineer at Kittelson and Associates reiterating ITD's support for the project's
proposed Highway 55 access location.
Conclusion
Thank you for the opportunity to respond to Staff comments. We look forward to your
support and approval of the Sessions Parkway subdivision.
Sincerely,
$fl-
Jeff Bower
ITD Correspondence
Sarah Arjona eSarah.Arjona@itd.idaho.gcv> Andy Daleiden;Stephanie Hopkins;Regan Hansen - 5/12/2022
RE:[EXTERNAL]Sessions Parkway&Village Apartments TIS V
Andy, 0
I believe the previous email was further confirmation on the ITD's acceptance of the concept and proposed approach location.If you need a formal letter from ITD
then I believe we can accommodate that however we cannot say the approach is approved or permitted since we have not reviewed civil drawings or approved a
permit.Please let me know if the email was not sufficient for the City.
Thank you,
Sarah A) ona
Development Services Coordinator
ITD District 3
(208)334-8338