Loading...
OB COM Infrastrucure Response V1L I1E IDIA� — APPROVED DATE 09/06/22 FILE NUMBER: FP-2D22-.11 22 Seth Oaks City of Meridian Building & Planning Dept 33 E Broadway Ave, Suite 102 Meridian, ID RE: Outer Banks Infrastructure QLPE Plan Review J•U•R ENGINEERS, INC. ®LNE a GAPPING LANGDON GATEWAY GROUP INC. J-U-e FAMILY OF COMPANIES We have received the plan review comments for the Outer Banks Infrastructure project and have incorporated them into the revised plan set. The intent of this letter is to serve as a response letter to the plan review comments. C-202 Waterline shifted over 2-ft to allow 25-ft separation from seepage bed. C-207 We coordinated with City staff to allow 10-ft separation for this connection point. The existing stubs as constructed make the 10-ft separation a bit tight while trying to accommodate other infrastructure improvements. C-208 Added non -potable crossing note. Waterline shifted a bit to accommodate 10-ft. Please do not hesitate to contact me with any additional questions or concerns. Sincerely, Darral S. Moore, P.E. J-U-B ENGINEERS, Inc. 1