OB COM Infrastrucure Response V1L I1E IDIA� —
APPROVED
DATE 09/06/22
FILE NUMBER: FP-2D22-.11
22
Seth Oaks
City of Meridian
Building & Planning Dept
33 E Broadway Ave, Suite 102
Meridian, ID
RE: Outer Banks Infrastructure QLPE Plan Review
J•U•R ENGINEERS, INC.
®LNE a GAPPING
LANGDON GATEWAY
GROUP INC.
J-U-e FAMILY OF COMPANIES
We have received the plan review comments for the Outer Banks Infrastructure project and have incorporated
them into the revised plan set. The intent of this letter is to serve as a response letter to the plan review
comments.
C-202
Waterline shifted over 2-ft to allow 25-ft separation from seepage bed.
C-207
We coordinated with City staff to allow 10-ft separation for this connection point. The existing stubs as
constructed make the 10-ft separation a bit tight while trying to accommodate other infrastructure
improvements.
C-208
Added non -potable crossing note.
Waterline shifted a bit to accommodate 10-ft.
Please do not hesitate to contact me with any additional questions or concerns.
Sincerely,
Darral S. Moore, P.E.
J-U-B ENGINEERS, Inc.