08 June 2022
City Clerk's Office
33 E Broadway Avenue
Meridian ID, 83642
RE: Vertex Sub #1 and #2 FP-2022-0016, FP-2022-0015
Lake Hazel Rd West of Eagle Rd.
New York Irrigation District NY-216-001-00
Farr Lateral 103+60, 121+60
Sec. 05, 2N, lE.
Alan Tiefenbach:
OPERATING AGENCY FOR 167,000
ACRES FOR THE FOLLOWING
IRRIGATION DISTRICTS
NAMPA-MERIDIAN DISTRICT
BOISE-KUNA DISTRICT
WILDER DISTRICT
NEW YORK DISTRICT
BIG BEND DISTRICT
TEL: (208) 344-1141
FAX: (208) 344-1437
RECEIVED
JUN 13 2022
CITY OFC M 9101
CITY CLERKS OFFICE
Boise Project approves of the plans for Vertex #1 and #2 subdivisions, stamped and dated
5/10/2022 by Lachlin C Kinsella P.E., with the following highlights being noted. No
exceptions will be given on these highlighted items.
The United States' Farr Lateral lies within the boundary of the above -mentioned location.
The easement for this canal is held in the name of the United States through the Bureau
of Reclamation under the authority of the Act of August 30, 1890. (26 Stat. 391 43
U.S.C. 945)
The Boise Project Board of Control is contracted to operate and maintain this lateral. We
assert the federal easement 30 feet south and west and 25 feet north and east of the lateral's
centerline. Whereas this area is for the operation and maintenance of our facility, no
activity should hinder our ability to do so.
The Boise Project does not approve landscaping including trees and/or shrubs (other than
grass or gravel) within its easements, as this will certainly increase our cost of
maintenance. All fences/pathways must be .lust off the edge of all Boise Project
easements. Easements must be left a flat drivable surface.
Parking lots, curbing, light poles, signs, etc. and the placing of asphalt and/or cement
over Project facility easements must be approved by Boise Project Board of Control prior
to construction.
Project facilities and/or easements that parallel, and are within and/or intended to be
within road right -of --ways due to any development of this property must be relocated
outside of road right -of --ways. The easements of Boise Project facilities will remain the
same unless agreed upon and/or approved with written permission from Boise Project
Board of Control.
The construction of any roadway crossings must be conducted only during the AL Ix
season when the canal is dewatered. In any case no work shall take place
within the easement before the proper crossing agreements have been secured through the
Bureau of Reclamation and the Boise Project Board of Control.
Utilities planning to cross any project facility must do so in accordance with the master
policies now held between the Bureau of Reclamation and most of the utilities. In any
case, no work shall take place within the easement before proper crossing agreements
have been secured through both the Bureau of Reclamation and the Boise Project Board
of Control.
Crossing agreements must be secured and signed by all parties prior to March lst of each
year. A time schedule for the construction to be done during the non -irrigation season
must be approved by Boise Project prior to any activity within Project easements. No
construction will be allowed within the easement boundaries of the Boise Project Board
of Control facilities after March 15`h of each year. However, on a case -by -case basis,
overhead utilities and utilities boring underneath a Project facility may be allowed after
March 15' if reviewed and approved by the Boise Project.
The piping and relocation of any Lateral, Canal and/or Drain must be reviewed and
approved by the Project and is (to include all appurtenant boxes and/or structures) and
must be warranted by the landowner for a period of (5) five -years. The Warrantee
Agreement must be secured prior to ANY disturbance of that facility. A relocation
agreement must also be procured through the Bureau of Reclamation prior to any
construction within the above -mentioned easement.
Boise Project Board of Control must approve any requests and/or relocation of delivery
points prior to construction.
Storm Drainage and/or Street Runoff must be retained on site.
NO DISCHARGE into any live irrigation system is permitted.
Per Idaho Statutes, Title 42, local irrigation/drainage ditches and pressurized
irrigation lines that cross this property, in order to serve nei�hborin� properties,
must remain unobstructed and protected by an appropriate easement by the
landowner, developer and contractors.
This development is subject to Idaho Code 31-3805, in accordance, this office is
requesting afull-size copy of the irrigation and drainage plans.
Whereas this property lies within New York Irrigation District it is important that
representatives of this development contact the NYID office as soon as possible to
Is
scuss a pressure system prior to any costly design work. If applicable, the
irrigation system will have to be built to specific specifications as set by the District /
Project.
Boise Project Board of Control must receive a written response from the New York
Irrigation District as to who will own and operate the pressure irrigation system
prior to review and approval of an irrigation plan by Boise Project Board of
Control.
Wording on the preliminary and final recorded plat needs to state that any proposed
and/or firture usage of the Boise Project Board of Control facilities are subject to Idaho
Statues, Title 42-1209.
Future preliminary and final plats must call out the Project easements and the plats must
also note, which lots have surface irrigation water rights and which lots do not.
Whereas this development is in its preliminai� stakes, Boise Project Board of
Control reserves the right to review plans and require changes when our easements
and/or facilities are affected by unknown factors, even during the construction
phase. .
If you have any further questions
hesitate to contact me at (208) 344-1
Ritthaler
Assistant Project Manager, BPBC
for/tr