HomeMy WebLinkAboutLetter from Dave McKinnon
RECEIVED
APR 26 2006
City Of Meridian
City Clerk Office
Date: April 25, 2006
To:
Mayor and City Council
Re:
Final Plat Staff Report for The Reserve Subdivision
Dear Mayor and Council,
We have received and reviewed a copy of the staff report that has been prepared for the
Reserve Subdivision and have prepared a written response below as requested. The
response will follow the body of the report, with comments as needed for clarification; a
"no comment" response indicates agreement with the comments or conditions.
Application and Summary Location:
No comment.
Site Specific Comments:
1-2.
3.
4.
No comment.
The requested notes and revisions will be added to the face of the plat.
The Landscape plan will be revised and requested. Three copies ofthe
revised plan will be submitted to the Planning Department upon
completion.
5-7. No comment.
8. The previously installed pressure sewer mains will not be needed in the
very near future, a connection to the gravity line in Saguaro Canyon has
already been constructed and the temporary lift station is no longer
needed.
A vacation request for the existing pressurized sewer easement has been
submitted to the City of Meridian for approval.
We will revised the construction drawings to reflect the water lines, and
accompanying easement, to install a water line from the West as proposed
in the Preliminary drawings.
11-16. No comment.
17. Clarification: If the turn-round is not used as a driveway to a garage, a 20'
setback from the turnaround will not be required.
18-20. No comment.
10.
9.
General Requirements
1-14. No Comment
With the above noted changes and comments we are in agreement with the staff
report and ask for your approval of the Final Plat for the Reserve Subdivision. If
you have any questions please contact me at 353-2515 or via e-mail at
dm ckinnon@congergroup.com.
Sincerely,
Dave McKinnon
CMG