HomeMy WebLinkAboutGrayson Sub A&Z- Pathway Conditions 220311 V1Rev. 02.11.22
Reviewer: Kim Warren / Pathways Project Manager
Planner Assigned: Joseph Dodson
Project Name: Grayson Subdivision AZ,PP File No: H-2022-0014 Date: 3/11/2022
The following will be required for development of the proposed project:
CONDITIONS OF APPROVAL - PATHWAYS
1. The project developer shall design and construct multi-use pathways consistent with the
location and specifications set forth in the Meridian Pathways Master Plan Map and Master
Pathways Plan Document Chapter 3). Any proposed adjustments to pathway alignment shall
be coordinated through the Pathways Project Manager.
2. Prior to submittal of the final plat for City Engineer signature, the applicant shall submit a
public access easement for a detached multi-use pathway parallel to Amity Road to the
Planning Division for Council approval and subsequent recordation. The easement shall be a
minimum of 14’ wide (10’ pathway + 2’ shoulder each side).
Use standard City template for public access easement. Submit all easement documents
online through Citizen’s Access Portal.
3. Construct multi-use pathways per paving section based on existing site conditions as
recommended by project civil engineer in accord with UDC 11-3A-8 and 11-3B-12. Prior to
occupancy, city engineer signature on the final plat the applicant’s engineer shall provide
written documentation that the pathway segment was constructed per the recommended
specifications.
4. The owner (or representative association) of the property affected by each public access
easement shall have an ongoing obligation to maintain the multi-use pathway.