HomeMy WebLinkAboutQ & A with Ted Brandvold V1O
IDANO
APPROVED
DATf. 03/09/22
f IIF NUMBER! A-2022-0031
Follow Up Flag:
Flag Status:
n
Ted Brandvold <tbrandvold@meridiancity.org>
Monday, January 24, 2022 4:18 PM
Kindi Moosman
RE: Scheels All Sports at Ten Mile Crossing
Follow up
Completed
Kindi,
Please see responses in red below. Let me know if you have any additional questions.
Thank you,
Ted
Ted Brandvold I Commercial Project Manager
City of Meridian I Community Development Department
33 E. Broadway Ave.
Meridian, Idaho 83642
Phone: (208) 887-2211, Ext. 1322
Cell: (208) 807-8151
Built for Business, Designed for Living
www.meridicincity.org
All e-mail messages sent to or received by City of Meridian e-mail accounts are subject to the Idaho law,
in regards to both release and retention, and may be released upon request unless exempt from disclosure by law.
From: Kindi Moosman <kindi.moosman@horrocks.com>
Sent: Monday, January 24, 2022 1:02 PM
To: Ted Brandvold <tbrandvold@meridiancity.org>
Subject: RE: Scheels All Sports at Ten Mile Crossing
External Sender - Please use caution with links or attachments.
Hi Ted,
I just wanted to follow up on the below items. I agree that it's a good idea to have these questions and answers in
writing.
Thanks so much! I appreciate you!
Kindi Moosman
Planner
F IORROCKS
2775 W Navigator Dr., Suite 210
Meridian, ID 83642
Direct 208-895-2520, Ext. 543
1
CUEIDR IAy
APPROVED
DATE 03/09/22
FIEF NUMBER:^-2D22-1
man
Sent: Wednesday, January 19, 2022 5:11 PM
To: Ted Brandvold <tbrandvoldl@meridiancitv.ore>
Subject: Scheels All Sports at Ten Mile Crossing
Hi Ted,
Thanks for the call! As discussed, here's an outline of the questions I had regarding the Scheels project:
• Bus Stops — Are there any requirements to add or improve any bus stops?
The bus stops currently in place with satisfy the proposed project's needs.
• CZC Application Requirement of a "Recorded Plat": Will I run into any issues if I upload the existing preliminary
plat and record of survey while KM Engineering completes the final plat which is in progress but won't record
until after we hope to have a building permit?
The recorded Development Agreement allows CZC submittal of the proposed project prior to map recordation.
While it is not recommended to delay recordation of the plat, the project may also proceed through building
permit submittal, and construction. Please note: Certificate of Occupancy will not be issued until the Final Plat is
recorded.
• Is there an overall percentage of landscape required for the site, outside of the Design Guidelines outlined in the
Ten Mile Crossing agreement?
There are no additional landscape requirements beyond those required by the Development's Design
Guidelines.
• Are EV Charging Stations (cars) required? If so, what are the requirements?
EV Charging Stations are not required, but are also not prohibited.
• Are there any requirements surrounding shopping cart corrals, such as spacing, size, look, etc.?
Shopping cart corrals requirements are determined by the developer to suit their needs.
• We discussed that only a CZC would be needed and that the design review would be done by Brighton. I will plan
on uploading their written approval, but can you please verify that this means the Design Review Checklist is not
required for the city submittal?
The Project's Design Review is performed by the Development's Design Review Committee. City of Meridian CZC
review and approval is required for the approval of the proposed zoning use. Please provide a copy of the
Development's Design Review Committee's approval with your submittal for CZC approval.
Thank you so much!
Kindi Moosman
Planner
HORRO K
�N I
E N G I N E E R S
2775 W Navigator Dr., Suite 210
Meridian, ID 83642
Direct 208-895-2520, Ext. 543
Mobile 435-669-4579
Email kindi.moosman@horrocks.com
Web vww. horrocks. corn
E IDI� Il