HomeMy WebLinkAboutGraycliff Estates No. 2 FP-2022-0005 V1Rev. 02.11.22
Reviewer: Kim Warren / Pathways Project Manager
Planner Assigned: Sonya Allen
Project Name: Graycliff Estates No. 2 File No: FP-2022-0005 Date:
2/22/2022
The following will be required for development of the proposed project:
CONDITIONS OF APPROVAL - PATHWAYS
1. The project developer shall design and construct multi-use pathways consistent with the
location and specifications set forth in the Meridian Pathways Master Plan Map and Master
Pathways Plan Document Chapter 3). Any proposed adjustments to pathway alignment shall
be coordinated through the Pathways Project Manager.
2. Prior to submittal of the final plat for City Engineer signature, the applicant shall submit a
public access easement for a detached 10’ multi-use pathway (concrete sidewalk) paralleling
W. Harris Street for the length of the constructed roadway, this phase. Submit easement
document to the Planning Division for Council approval and subsequent recordation. The
easement shall be a minimum of 14’ wide (10’ pathway + 2’ shoulder each side).
If 10’ sidewalk is located entirely within the public ROW, no easement is required. Or if
partially located within, dedicate enough easement behind the ROW to allow for a 10’
sidewalk plus 2’ shoulder.
Use standard City template for public access easement. Submit all easement documents
online through Citizen’s Access Portal.
3. Construct multi-use pathways per paving section based on existing site conditions as
recommended by project civil engineer in accord with UDC 11-3A-8 and 11-3B-12. Prior to
occupancy, city engineer signature on the final plat or final approval the applicant’s
engineer shall provide written documentation that the pathway segment was constructed per
the recommended specifications.
4. The owner (or representative association) of the property affected by each public access
easement shall have an ongoing obligation to maintain the multi-use pathway.
5. 6’ high open vision fencing shall be installed between pathways and (live) water irrigation
canals and laterals as detailed in the Meridian Pathways Master Plan, Chapter 3, page 3-5.
All other fence details per UDC 11-3A-7.
6. Project developer shall be responsible for obtaining agreements and permission(s) as required
for constructing within the Northwest Pipeline Easement.