MEMO TO CITY COUNCIL
Request to Include Topic on the City Council Agenda
From: Keith Watts, Procurement Division Meeting Date: August 10, 2021
Presenter: Consent- Clint Dolsby Estimated Time: Consent
Topic: Equipment Purchase Agreement for Sidestream Phosphorus Recovery Equipment
with Centrisys/CNP for the Not-To-Exceed amount of$2,139,000.00
Recommended Council Action:
Approval of agreement and authorize the Procurement Manager to sign the agreement and
corresponding purchase order.
Background:
This agreement is the result of the Sole Source approved by Council July 28, 2020. This agreement
is the culmination of joint negotiations by the Public Works, Legal and Procurement departments.
Item#18.
Mayor Tammy de Weerd
ID"' IAN�- City Council Members:
Joe Borton
' D A H O Treg Bernt
Public Milam
Luke Cavener
Works Department Ty Palmer
Anne Little Roberts
TO: Mayor Robert Simison
Members of the City Council
FROM: Clint Dolsby, P.E.
Assistant City Engineer
DATE: July 22, 2021
SUBJECT: APPROVAL OF THE PURCHASE AGREEMENT FOR THE SUPPLY OF
SIDESTREAM PHOSPHORUS RECOVERY EQUIPMENT FOR THE
WASTEWATER RESOURCE RECOVERY FACILITY—SIDESTREAM
PHOSPHORUS RECOVERY PROJECT WITH CENTRISYS/CNP FOR A
NOT TO EXCEED AMOUNT OF$2,139,000.00
I. RECOMMENDED ACTION
A. Move to:
1. Approve the Purchase Agreement for the Supply of Sidestream Phosphorus
Recovery Equipment with Centrisys/CNP for the Wastewater Resource
> Recovery Facility — Sidestream Phosphorus Recovery, for a not-to-exceed
cost of$2,139,000.00.
2. Authorize the Procurement Manager to sign the purchase agreement.
Il. DEPARTMENT CONTACT PERSONS
Clint Dolsby PE, Assistant City Engineer 489-0341
Warren Stewart PE, City Engineer 489-0350
Dale Bolthouse, Director of Public Works 985-1257
Ill. DESCRIPTION
A. Background
This project is the next step in initiating sidestream nutrient recovery at the
Wastewater Resource Recovery Facility (WRRF). This is a follow up to the
phosphorus recovery pilot project that was completed in the fall of 2009 and was
Page I of 3 Page 521
Item#18.
included in the WRRF facility plan in 2012. To control the formation of struvite
in the solids stream at the WRRF, Public Works is considering several steps.
This project will provide a struvite production facility as an additional step for
struvite control and has the added benefit of phosphorus and nitrogen removal
from the centrate flow stream.
Fluid from dewatering operations contributes a substantial nutrient load to the
treatment process. This load increases the secondary treatment costs and reduces
the plant effluent quality. The City has experienced nuisance struvite issues in
solid and sidestream processes that have caused significant pipe clogging and
pump issues, and continue to limit the potential for liquid stream phosphorus
removal until effective sidestream treatment is implemented. Sidestream
phosphorus recovery will help meet future effluent phosphorus limits by
eliminating the majority of the recycle loadings.
B. Proposed Project
Centrisys/CNP will provide the sidestream phosphorus recovery equipment for
this project. This agreement will allow Centrisys/CNP the ability to prepare
submittals and manufacture and deliver the equipment to the wastewater resource
recovery facility.
IV. IMPACT
A. Strategic Impact:
This project meets our mission requirements to identify and prioritize work to
anticipate, plan and provide public services and facilities that support the needs of
our growing community, ensure modern, reliable facilities while maintaining
financial stewardship and maintaining the ability to meet the changing permit
limit requirements.
B. Service/Delivery Impact:
Increased nutrient recovery at the WRRF will support departmental objectives to
develop and employ strategies that comply with current and pending National
Pollutant Discharge Elimination System Permit(NPDES).
C. Fiscal Impact:
Project Costs
WRRF Sidestream Phosphorus Recovery Preliminary Design $123,048.00
WRRF Sidestream Phosphorus Recovery Final Design $545,210.00
WRRF Sidestream Phosphorus Recovery Geotech Investigation $11,819.62
WRRF Sidestream Phosphorus Recovery Survey $10,000.00
WRRF Sidestream Phosphorus Recovery Equipment $2,139,000.00
Total Cost $2,829,077.62
Page 2 of 3 Page 522
Item#18.
Project Funding
FY 2020 Sidestream Phosphorus Recovery(3590-96182) $550,000.00
FY 2021 Sidestream Phosphorus Recovery(3590-96182) $5,450,000.00
Total Funding $6,000,000.00
VI. TIME CONSTRAINTS
Council's approval will allow this project to proceed and the outcome will lower the
plant effluent phosphorus concentration, help protect the dewatering equipment from
struvite formation and lower the secondary treatment costs.
VIl. LIST OF ATTACHMENTS
A. Agreement for the supply of Sidestream Phosphorus Recovery Equipment
Project 10036.e
Department Approval: _ 7 z 2
Galt
Page 3 of 3 Page 523
City Of Meridian
Detailed Statement of Revenues and Expenditures - Rev and Exp Report - Keith
60 - Enterprise Fund
3590 - WW Construction Projects
From 10/1/2020 Through 9/30/2021
Percent of
Budget with Current Year Budget Budget
Amendments Actual Remaining Remaining
Capital Outlay
96182 Sidestream Phosphorus
Recovery
5,450,000.04 0.00 5,450,000.04 100.00%
10036 OSTARA Study 430,635.17 602.50 430,032.67 99.86%
10036.a Sidestream Phosphorus 0.00 10,274.69 (10,274.69) 0.00%
Removal Project - Design
10036.d Sidestream Phosphorus 0.00 545,210.00 (545,210.00) 0.00%
Final Design
Total Capital Outlay 5,880,635.21 556,087.19 5,324,548.02 90.54,
TOTAL EXPENDITURES 5,880,635.21 556,087.19 5,324,548.02 90.54%
Date: 7/26/21 06:50:06 PM Page: 1
AGREEMENT FOR THE SUPPLY OF
SIDESTREAM PHOSPHORUS RECOVERY EQUIPMENT
PROJECT #10036.e
THIS AGREEMENT FOR EQUIPMENT / SUPPLIES PROCUREMENT is made
this 31d day of Au ust, 2021 , and entered into by and between the City of Meridian, a
municipal corporation organized under the laws of the State of Idaho, hereinafter
referred to as "CITY", 33 East Broadway Avenue, Meridian, Idaho 83642, and
Centrisys/CNP, hereinafter referred to as "SUPPLIER", whose business address is
9586 58t" Place, Kenosha, WI 83144.
INTRODUCTION
Whereas, the City has a need for SIDESTREAM PHOSPHORUS
RECOVERY EQUIPMENT ; and
WHEREAS, the SUPPLIER is specially trained, experienced and
competent to provide and has agreed to provide such equipment;
NOW, THEREFORE, in consideration of the mutual promises, covenants,
terms and conditions hereinafter contained, the parties agree as follows:
TERMS AND CONDITIONS
1 . Equipment / Supply Specifications & Requirements:
1 .1 SUPPLIER shall supply the equipment, supplies and services to the
City upon execution of this Agreement and receipt of the City's written notice
to proceed, all items, and comply in all respects, as specified in the
Technical Specifications titled " Wastewater Resource Recovery Facility
(WRRF) Side Stream Treatment Project— Reactor Procurement Submittal",
Plans titled "Meridian Wastewater Facility Meridian, Idaho", and Budgetary
Proposal #06638 dated June 18, 2021 , which by this reference are
incorporated herein.
1 .2 The SUPPLIER shall provide all equipment and services under this
Agreement consistent with the requirements and standards established by
applicable federal, state and city laws, ordinances, regulations and
resolutions and the UCC. The SUPPLIER represents and warrants that it
will perform its work in accordance with generally accepted industry
standards and practices for the profession or professions that are used in
performance of this Agreement and that are in effect at the time of
performance of this Agreement.
2. Consideration
2.1 The SUPPLIER shall be compensated on a Fixed Price basis as
provided in Attachment B "Payment Schedule" attached hereto and by
reference made a part hereof, for the Not-To-Exceed amount of
$2,139,000.00 F.O.B. the City of Meridian Wastewater Resource Recovery
Facility located at 3401. N. Ten Mile Rd, Meridian, ID 83646.
2.2 The SUPPLIER shall provide the City with a detailed invoice upon
delivery of all equipment and supplies, which the City will pay within 30 days
of receipt of a correct invoice and approval by the City Project Manager.
The City will not withhold any Federal or State income taxes or Social
Security Tax from any payment made by City to SUPPLIER under the terms
and conditions of this Agreement. Payment of all taxes and other
assessments on such sums is the sole responsibility of SUPPLIER.
2.3 Except as expressly provided in this Agreement, SUPPLIER shall not
be entitled to receive from the City any additional consideration,
compensation, salary, wages, or other type of remuneration for services
rendered under this Agreement., including , but not limited to, meals,
lodging, transportation, drawings, renderings or mockups. Specifically,
SUPPLIER shall not be entitled by virtue of this Agreement to consideration
in the form of overtime, health insurance benefits, retirement benefits, paid
holidays or other paid leaves of absence of any type or kind whatsoever.
3. Term:
3.1 This agreement shall become effective upon execution by both
parties, and shall expire upon (a) completion of the agreed upon work, or
(b) unless sooner terminated as provided below or unless some other
method or time of termination is listed in Attachment A.
3.2 Should SUPPLIER default in the performance of this Agreement or
materially breach any of its provisions, City, at City's option, may terminate
this Agreement by giving written notification to SUPPLIER.
3.3 Should City fail to pay SUPPLIER all or any part of the compensation
set forth in Attachment B of this Agreement on the date due, SUPPLIER, at
the SUPPLIER's option, may terminate this Agreement if the failure is not
remedied by the City within thirty (30) days from the date payment is due.
4. Liquidated Damages:
Each Milestone listed in the Milestone / Payment Schedule below shall be
accomplished in the timeframe listed. All days shall be calculated as
Calendar Days. Supplier shall be liable to the City for any delay beyond
each milestone time period in the amount of $500 (five hundred dollars) per
calendar day. Such payment shall be construed to be liquidated damages
by the supplier in lieu of any claim or damage because of such delay and
not be construed as a penalty.
5. Termination:
If, through any cause, SUPPLIER, its officers, employees, or agents fails to
fulfill in a timely and proper manner its obligations under this Agreement,
violates any of the covenants, agreements, or stipulations of this
Agreement, falsifies any record or document required to be prepared under
this agreement, engages in fraud, dishonesty, or any other act of
misconduct in the performance of this contract, or if the City Council
determines that termination of this Agreement is in the best interest of CITY,
the CITY shall thereupon have the right to terminate this Agreement by
giving written notice to SUPPLIER of such termination and specifying the
effective date thereof at least fifteen (15) days before the effective date of
such termination.
Notwithstanding the above, SUPPLIER shall not be relieved of liability to
the CITY for damages sustained by the CITY by virtue of any breach of this
Agreement by SUPPLIER, and the CITY may withhold any payments to
SUPPLIER for the purposes of set-off until such time as the exact amount
of damages due the CITY from SUPPLIER is determined. This provision
shall survive the termination of this agreement and shall not relieve
SUPPLIER of its liability to the CITY for damages.
6. Independent SUPPLIER:
6.1 In all matters pertaining to this agreement, SUPPLIER shall be acting
as an independent SUPPLIER, and neither SUPPLIER nor any officer,
employee or agent of SUPPLIER will be deemed an employee of CITY.
Except as expressly provided in Attachment A, SUPPLIER has no authority
or responsibility to exercise any rights or power vested in the City and
therefore has no authority to bind or incur any obligation on behalf of the
City. The selection and designation of the personnel of the CITY in the
performance of this agreement shall be made by the CITY.
6.2 SUPPLIER, its agents, officers, and employees are and at all times
during the term of this Agreement shall represent and conduct themselves
as independent SUPPLIERs and not as employees of the City.
6.3 SUPPLIER shall determine the method, details and means of
performing the work and services to be provided by SUPPLIER under this
Agreement. SUPPLIER shall be responsible to City only for the
requirements and results specified in this Agreement and, except as
expressly provided in this Agreement, shall not be subjected to City's control
with respect to the physical action or activities of SUPPLIER in fulfillment of
this Agreement. If in the performance of this Agreement any third persons
are employed by SUPPLIER, such persons shall be entirely and exclusively
under the direction and supervision and control of the SUPPLIER.
7. Indemnification and Insurance:
7.1 SUPPLIER shall indemnify and save and hold harmless CITY from
and for any and all losses, claims, actions, judgments for damages, or injury
to persons or property and losses and expenses and other costs including
litigation costs and attorney's fees, arising out of, resulting from, or in
connection with the performance of this Agreement by the SUPPLIER, its
servants, agents, officers, employees, guests, and business invitees, and
not caused by or arising out of the tortuous conduct of CITY or its
employees. SUPPLIER shall maintain, and specifically agrees that it will
maintain, throughout the term of this Agreement, liability insurance, in which
the CITY shall be named an additional insured in the minimum amounts as
follow: General Liability One Million Dollars ($1 ,000,000) per incident or
occurrence, Professional Liability One Million Dollars ($1 ,000,000) per
incident or occurrence, Automobile Liability Insurance One Million Dollars
($1 ,000,000) per incident or occurrence and Workers' Compensation
Insurance, in the statutory limits as required by law.. The limits of insurance
shall not be deemed a limitation of the covenants to indemnify and save and
hold harmless CITY, and if CITY becomes liable for an amount in excess of
the insurance limits, herein provided, SUPPLIER covenants and agrees to
indemnify and save and hold harmless CITY from and for all such losses,
claims, actions, or judgments for damages or injury to persons or property
and other costs, including litigation costs and attorneys' fees, arising out of,
resulting from , or in connection with the performance of this Agreement by
the SUPPLIER or SUPPLIER's officers, employs, agents, representatives
or sub-SUPPLIERs and resulting in or attributable to personal injury, death,
or damage or destruction to tangible or intangible property, including use of.
SUPPLIER shall provide CITY with a Certificate of Insurance, or other proof
of insurance evidencing SUPPLIER'S compliance with the requirements of
this paragraph and file such proof of insurance with the CITY at least ten
(10) days prior to the date SUPPLIER begins performance of it's obligations
under this Agreement. In the event the insurance minimums are changed,
SUPPLIER shall immediately submit proof of compliance with the changed
limits. Evidence of all insurance shall be submitted to the City Purchasing
Agent with a copy to Meridian City Accounting, 33 East Broadway Avenue,
Meridian, Idaho 83642.
7.2 Any deductibles, self-insured retention, or named insureds must be
declared in writing and approved by the City. At the option of the City, either:
the insurer shall reduce or eliminate such deductibles, self-insured
retentions or named insureds; or the SUPPLIER shall provide a bond, cash
or letter of credit guaranteeing payment of losses and related investigations,
claim administration and defense expenses.
7.3 To the extent of the indemnity in this contract, SUPPLIER's
Insurance coverage shall be primary insurance regarding the City's elected
officers, officials, employees and volunteers. Any insurance or self-
insurance maintained by the City or the City's elected officers, officials,
employees and volunteers shall be excess of the SUPPLIER's insurance
and shall not contribute with SUPPLIER's insurance except as to the extent
of City's negligence.
7.4 The SUPPLIER's insurance shall apply separately to each insured
against whom claim is made or suit is brought, except with respect to the
limits of the insurer's liability.
7.5 All insurance coverages for Suppliers subs shall be subject to all of
the insurance and indemnity requirements stated herein.
7.6 The limits of insurance described herein shall not limit the liability of
the Supplier and Supplier's agents, representatives, employees or
subcontractors.
7.7 The limits of insurance described herein shall not limit the liability of
the Contractor and Contractor's agents, representatives, employees or
subcontractors.
8. Bonds: Payment and Performance Bonds are required.
9. Warranty: In addition to any warranty required in the specifications, all
equipment, coatings, valves, controls, and other components provided
under this agreement shall be guaranteed for two (2) years against defects
in workmanship and materials from the successful startup of equipment or
30 months after delivery, whichever comes first. ALL WARRANTY
REPAIRS MUST USE NEW PARTS.
10. Notices: Any and all notices required to be given by either of the parties
hereto, unless otherwise stated in this agreement, shall be in writing and be
deemed communicated when mailed in the United States mail, certified,
return receipt requested, addressed as follows:
City of Meridian
Procurement Manager
33 E. Broadway Avenue
Meridian, Idaho 83642
Ph. (208) 489-0417
Email: kwatts@meridiancity.org
Centrisys CNP
Attn: Jerod Swanson, Sales Manager
9586 58t" Place
Kenosha, WI 53144
Ph. (612) 401-2006
e-mail: jerod.swanson@centris
Either party may change their address for the purpose of this paragraph by
giving written notice of such change to the other in the manner herein
provided.
11 . Attorney Fees: Should any litigation be commenced between the parties
hereto concerning this Agreement, the prevailing party shall be entitled, in
addition to any other relief as may be granted, to court costs and reasonable
attorneys' fees as determined by a Court of competent jurisdiction. This
provision shall be deemed to be a separate contract between the parties
and shall survive any default, termination or forfeiture of this Agreement.
12. Time is of the Essence: The parties hereto acknowledge and agree that
time is strictly of the essence with respect to each and every term, condition
and provision hereof, and that the failure to timely perform any of the
obligations hereunder shall constitute a breach of, and a default under, this
Agreement by the party so failing to perform.
13. Assignment: It is expressly agreed and understood by the parties hereto,
that SUPPLIER shall not have the right to assign, transfer, hypothecate or
sell any of its rights under this Agreement except upon the prior express
written consent of CITY.
14. Discrimination Prohibited: In performing the Work required herein,
SUPPLIER shall not unlawfully discriminate in violation of any federal, state
or local law, rule or regulation against any person on the basis of race, color,
religion, sex, national origin or ancestry, age or disability.
15. Reports and Information:
15.1 At such times and in such forms as the CITY may require, there shall
be furnished to the CITY such statements, records, reports, data and
information as the CITY may request pertaining to matters covered by this
Agreement.
15.2 SUPPLIER shall maintain all writings, documents and records
prepared or compiled in connection with the performance of this Agreement
for a minimum of four (4) years from the termination or completion of this or
Agreement. This includes any handwriting, typewriting, printing, photo
static, photographic and every other means of recording upon any tangible
thing, any form of communication or representation including letters, words,
pictures, sounds or symbols or any combination thereof.
16. Audits and Inspections: At any time during normal business hours and
as often as the CITY may deem necessary, there shall be made available
to the CITY for examination all of SUPPLIER'S records with respect to all
matters covered by this Agreement. SUPPLIER shall permit the CITY to
audit, examine, and make excerpts or transcripts from such records, and to
make audits of all contracts, invoices, materials, payrolls, records of
personnel, conditions of employment and other data relating to all matters
covered by this Agreement.
17. Publication, Reproduction and Use of Material: No material produced
in whole or in part under this Agreement shall be subject to copyright in the
United States or in any other country. The CITY shall have unrestricted
authority to publish, disclose and otherwise use, in whole or in part, any
reports, data or other materials prepared under this Agreement.
18. Compliance with Laws: In performing the scope of work required
hereunder, SUPPLIER shall comply with all applicable laws, ordinances,
and codes of Federal, State, and local governments.
19. Changes: The CITY may, from time to time, request changes in the Scope
of Work to be performed hereunder. Such changes, including any increase
or decrease in the amount of SUPPLIER'S compensation, which are
mutually agreed upon by and between the CITY and SUPPLIER, shall be
incorporated in written amendments which shall be executed with the same
formalities as this Agreement.
20. Construction and Severability: If any part of this Agreement is held to be
invalid or unenforceable, such holding will not affect the validity or
enforceability of any other part of this Agreement so long as the remainder
of the Agreement is reasonably capable of completion.
21 . Waiver of Default: Waiver of default by either party to this Agreement shall
not be deemed to be waiver of any subsequent default. Waiver or breach
of any provision of this Agreement shall not be deemed to be a waiver of
any other or subsequent breach, and shall not be construed to be a
modification of the terms of this Agreement unless this Agreement is
modified as provided above.
22. Advice of Attorney: Each party warrants and represents that in executing
this Agreement. It has received independent legal advice from its attorney's
or the opportunity to seek such advice.
23. Entire Agreement: This Agreement contains the entire agreement of the
parties and supersedes any and all other agreements or understandings,
oral of written, whether previous to the execution hereof or
contemporaneous herewith.
24. Order of Precedence: The order or precedence shall be this Agreement,
the Technical Specifications, I.C. Drawings, and the suppliers proposal
#06638 dated June 18, 2021 .
25. Applicable Law: This Agreement shall be governed by and construed and
enforced in accordance with the laws of the State of Idaho, and the
ordinances of the City of Meridian.
26. Approval Required: This Agreement shall not become effective or binding
until approved by the City of Meridian.
CITY OF MERIDIAN CENTRISYS CNP
BY: BY:
Keith Watts, Procurement Manager
Dated: 8-10-2021 Dated: 07/20/2021
Approved by City Council: 8-10-2021
Attachment A
SCOPE OF WORK
• TECHNICAL SPECIFICATIONS by Carollo Engineers, Inc.
dated 3/26/2021 (416 pages)
• Instrumentation Drawings by Mountain Waterworks, Inc.
dated January 2021 (23 pages)
Attachment B
MILESTONE / PAYMENT SCHEDULE
Total and complete compensation for this Agreement shall not exceed $1 ,808.000. This
price includes the optional 10,000-gallon MgCl storage tank and galvanized steel
reactor platforms and handrails
MILESTONE DATES/PRICING SCHEDULE
DATE
DESCRIPTION (Dependenton AMOUNT
Council Approval
1 . Contract Execution Upon Notice-To- $213,900.00
Proceed
2. Receipt of Submittals 70 days from $0.00
NTP
3. Upon Approval of Shop Drawings Upon Approval $213,900.00
of Submittals"
4 Upon Receipt and Approval of Operation & $213,900.00
Maintenance Manuals
40 Weeks from
Approval of
5. Upon Receipt of Equipment Submittals - $1,283,400.00
Upon Receipt of
Equipment*
Net 30 of Start
6. Upon Start Up & Commissioning Up and $213,900.00
Commissioning
CONTRACT TOTAL....................... $2,139,000.00
ALL PAYMENTS WILL BE MADE NET 30 OF RECEIPT OF INVOICE, WHICH
SHALL NOT BE ISSUED PRIOR TO ACHIEVEMENT OF THE MILESTONE
Payment will be made no later than 30 days from receipt of submittals
** LD's will begin at 40 weeks from Approval of Submittals, Payment shall not take
place prior to receipt of equipment
CITY OF MERIDIAN, IDAHO
WASTEWATER RESOURCE RECOVERY FACILITY (WRRF)
SIDE STREAM TREATMENT PROJECT
CAROLLO PROJECT NO. 11700A.10
TECHNICAL SPECIFICATIONS
REACTOR PROCUREMENT SUBMITTAL
NOT FOR CONSTRUCTION
VOLUME 1 OF 1
MARCH 2O21
This document is released for the
purpose of information exchange
review and planning only under
the authority of
Timothy R. Tekippe,
March 2021,
State of Idaho
PE License No. 8572.
It is not to be used for bidding,
permit, or construction purposes.
400'- C0493'" *"FAWA40
12592 WEST EXPLORER DRIVE, SUITE 200 BOISE, IDAHO 83713 P.208.376.2288 F.208.37
pw:ll Carol I o/Documents/Clientll D/Meridian111700A 10IS pecifications/Pre-Purchasel00_00_01
CITY OF MERIDIAN, IDAHO
WASTEWATER RESOURCE RECOVERY FACILITY (WRRF)
SIDE STREAM TREATMENT PROJECT
TABLE OF CONTENTS
VOLUME 1 OF 1
DIVISION 01 - GENERAL REQUIREMENTS
SECTION NO. TITLE
01_11_00 SUMMARY OF WORK
01_33_00 SUBMITTAL PROCEDURES
01_75_17 COMMISSIONING
01_78_23 OPERATION AND MAINTENANCE DATA
01_78_36 WARRANTIES AND BONDS
01_81_01 PROJECT DESIGN CRITERIA
DIVISION 05 - METALS
SECTION NO. TITLE
05_12_00 STRUCTURAL STEEL
DIVISION 26 - ELECTRICAL
SECTION NO. TITLE
26_05_00 COMMON WORK RESULTS FOR ELECTRICAL
26_05_09 LOW VOLTAGE MOTORS UP TO 500 HORSEPOWER
26 05 18 600-VOLT OR LESS WIRES AND CABLES
26 05 21 LOW VOLTAGE WIRE CONNECTIONS
26 05 26 GROUNDING AND BONDING
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 28 01 LOW VOLTAGE MOLDED CASE CIRCUIT BREAKERS
DIVISION 40 - PROCESS INTERCONNECTIONS
SECTION NO. TITLE
40_05_57.23 ELECTRIC ACTUATORS
40_05_65.01 GATE, GLOVE, AND ANGLE VALVES
40_61_00 COMMON WORK RESULTS FOR PROCESS CONTROL AND
INSTRUMENTATION SYSTEMS
40_61_05 PACKAGED CONTROL SYSTEM
40 64 01 CONTROL SYSTEMS: PROGRAMMABLE LOGIC CONTROLLERS
40 71 15 FLOW MEASUREMENT: MAGNETIC FLOWMETERS
40 71 76 FLOW MEASUREMENT: THERMAL MASS
40_72_24 LEVEL MEASUREMENT: RADAR PULSE TIME OF FLIGHT (PTOF)
40_72_36 LEVEL MEASUREMENT CAPACITANCE
40 72 76 LEVEL MEASUREMENT: SWITCHES
40 73 13 PRESSURE/VACUUM MEASUREMENT: GAUGES
40 73 23 PRESSURE/VACUUM MEASUREMENT: DIRECT
40 73 64 PRESSURE/VACUUM MEASUREMENT: INSTRUMENT VALVES
40 74 66 TEMPERATURE MEASUREMENT: TEMPERATURE SWITCH
Table of Contents
00 01 10-1 1170OA10
pw://Carollo/Documents/Client/IDlMeridianl11700A10ISpecificationsl00_00_02(IDS50) March 2021 - DRAFT
40 75 13 ANALYZERS: PH
40 80 01 COMMISSIONING FOR INSTRUMENTATION AND CONTROLS
DIVISION 43 - PROCESS GAS AND LIQUID HANDLING,
PURIFICATION, AND STORAGE EQUIPMENT
SECTION NO. TITLE
43 11 33 ROTARY-LOBE BLOWERS
43 23 57.10 PROGRESSING CAVITY PUMPS
43 33 20.01 LIQUID CHEMICAL DIAPHRAGM-TYPE METERING PUMP
43 41 43 POLYETHYLENE TANKS
DIVISION 46 -WATER AND WASTEWATER EQUIPMENT
SECTION NO. TITLE
46_05_10 COMMON WORK RESULTS FOR MECHANICAL EQUIPMENT
46_05_94 MECHANICAL EQUIPMENT TESTING
46_63_83 PHOSPHORUS PRECIPITATION SYSTEM REACTOR
46_63_83.01 PHOSPHORUS PRECIPITATION SYSTEM
Table of Contents
00 01 10-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10ISpecificationsl00_00_02(IDS50) March 2021 - DRAFT
SECTION 01_11_00
SUMMARY OF WORK
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Detailed description of the Work for the Supply of Phosphorous
Precipitation System Reactors and related equipment.
1.02 THE WORK
A. The Work consists of supply of equipment for the Phosphorous Precipitation
System as described in Section 46 63 83, including submittals, equipment,
programming, start-up, and commissioning services, spare parts, and coordination
with the Contractor during installation. Phosphorous Precipitation System will be
installed by Contractor.
1.03 LOCATION OF PROJECT
A. The Work is located at the Meridian Wastewater Resource Recovery Facility, 3401
N. Ten Mile Road, Meridian, ID 83646.
1.04 RESPONSIBLE PARTIES
A. The following defines the responsible parties associates with the Project:
1. Owner: City of Meridian, Idaho.
2. Contractor: The future building contractor will be determined pending bidding
by Owner. However, for the purposes of these pre-purchase specifications,
"Contractor" shall mean the same as "Supplier".
3. Engineer: Carollo Engineers, Inc.
4. Supplier: CNP Technology Water and Biosolids Corp.
PART2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
END OF SECTION
March 2021 - DRAFT 01 11 00-1 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_11_00(IDS50)
SECTION 01_33_00
SUBMITTAL PROCEDURES
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Requirements and procedures for submittals.
1.02 DEFINITIONS
A. Certificates: Describe certificates that document affirmations by the Contractor or
other entity that the work is in accordance with the Contract Documents.
B. Extra stock materials: Describe extra stock materials to be provided for the Owner's
use in facility operation and maintenance.
C. Maintenance material submittals: Use this article to categorize maintenance
materials submittals requiring no Engineer action other than confirmation of receipt
under an explanatory heading.
D. Manufacturer's instructions: Instructions, stipulations, directions, and
recommendations issued in printed form by the manufacturer of a product
addressing handling, installation, erection, and application of the product;
manufacturer's instructions are not prepared especially for the Work.
E. Product data: Product data usually consists of manufacturers' printed data sheets or
catalog pages illustrating the products to be incorporated into the project.
F. Samples: Samples are full-size actual products intended to illustrate the products to
be incorporated into the project. Sample submittals are often necessary for such
characteristics as colors, textures, and other appearance issues.
G. Spare parts: Describe spare parts necessary for the Owner's use in facility
operation and maintenance; identify the type and quantity here, but include the
actual characteristics of the spare parts in Product as part of the specification of the
product.
H. Shop drawings: Shop drawings are prepared specifically for the project to illustrate
details, dimensions, and other data necessary for satisfactory fabrication or
construction that are not shown in the contract documents. Shop drawings could
include graphic line-type drawings, single-line diagrams, or schedules and lists of
products and their application.
I. Submittals: Submittals are samples, product data, shop drawings, and others that
demonstrate how Contractor intends to conform with the Contract Documents.
J. Tools: Tools are generally defined as items such as special wrenches, gauges,
circuit setters, and other similar devices required for the proper operation or
maintenance of a system that would not normally be in the Owner's tool kit.
March 2021 - DRAFT 01 33 00-1 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_33_00(IDS50)
1.03 GENERAL INSTRUCTIONS
A. Provide submittals that are specified or reasonably required for construction,
operation, and maintenance of the Work.
B. Provide submittal information from only 1 manufacturer for a specified product,
unless otherwise approved by Engineer.
C. Where multiple submittals are required, provide a separate submittal for each
specification section.
1. In order to expedite construction, the Contractor may make more than
1 submittal per specification section, but a single submittal may not cover more
than 1 specification section:
2. The only exception to this requirement is when 1 specification section covers
the requirements for a component of equipment specified in another section.
D. For example, circuit breakers are a component of switchgear. The switchgear
submittal must also contain data for the associated circuit breakers, even though
they are covered in a different specification section.
E. Edit all submittals so that the submittal specifically applies to only the equipment
furnished. Neatly cross out all extraneous text, options, models, etc., that do not
apply to the equipment being furnished, so that the information remaining is only
applicable to the equipment being furnished.
F. Prepare submittals in the English language. Do not include information in other
languages.
G. Present measurements in customary American units (feet, inches, pounds, etc.).
H. Show dimensions, construction details, wiring diagrams, controls, manufacturers,
catalog numbers, and all other pertinent details.
I. Indicate project designated equipment tag numbers from P&IDs for submittal of
devices, equipment, and assemblies.
J. Submittals shall be provided in electronic media format:
1. General: Provide all information In PC-compatible format using Windows°
operating system.
2. Text: Provide text documents and manufacturer's literature using current
version of Adobe'Acrobat° (i.e., PDF extension).
3. Graphics: Provide all graphic submittals (drawings, diagrams) utilizing current
version of Adobe'Acrobat' (i.e., PDF extension).
4. Supplier using other software shall be required to provide conclusive evidence
of 100 percent data transfer compatibility that is an equal to PDF format.
1.04 SUBMITTAL ORGANIZATION
A. Fully indexed electronic submittal with a tabbed divider for every component.
B. Sequentially number pages within the tabbed sections:
1. Submittals that are not fully indexed and tabbed with sequentially numbered
pages, or are otherwise unacceptable, will be returned without review.
March 2021 - DRAFT 01 33 00-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_33_00(IDS50)
C. Organize submittals in exactly the same order as the items are referenced, listed,
and/or organized in the specification section.
D. For submittals that cover multiple devices used in different areas under the same
specification section, the submittal for the individual devices must list the area
where the device is used.
E. Consolidate electronic format submittals with multiples pages into a single file.
1.05 SUBMITTAL COVER SHEETS
A. Submittal Transmittal Form is provided in Appendix A of this Section.
1. Contractor submittal transmittal form is acceptable provided that it includes
information, statements, and certifications comparable to the Submittal
Transmittal Form.
2. Submittal Number Field: Required submittal numbering format (unless other
format approved by Owner and Engineer): Section number-sequential number-
resubmittal number:
a. Example: 03_20_00-002-1:
1) "03_20_00" indicates the affected specification is Section 03_20_00.
2) "002" indicates the second submittal under this Section.
3) "1" indicates the first resubmittal of the Submittal.
b. Contractor may add a separate numbering scheme for Contractor's
internal use. However, all correspondence with Engineer must include the
required submittal numbering.
3. "From" Field: Provide name and address of company responsible for
preparation of submittal. This could be General Contractor, subcontractor,
supplier, manufacturer, etc.
4. "General Contractor Reviewer" Field: Verify that the General Contractor has
reviewed the submittal by signature.
B. Contractor sign and date submittals indicating review and approval:
1. Signature indicates Contractor certifies that they have satisfied submittal
review responsibilities and constitutes Contractor's written approval of
submittal. Contractor shall note that the submittal complies with the
Specification Section.
C. Attachments:
1. Specification section deviations:
a. Provide a list of all numbered deviations, with reference to Specification
Section and pertinent paragraph, with a clear explanation and reason for
the deviation.
2. Drawings deviations:
a. Provide a list of all numbered deviations, with reference to specific
Drawing, with a clear explanation and reason for the deviation. Provide
field dimensions and relationship to adjacent or critical features of the
Work or materials.
D. Contractor: Prepare submittal information in sufficient detail to show compliance
with specified requirements.
1. Determine and verify quantities, field dimensions, product dimensions,
specified design and performance criteria, materials, catalog numbers, and
similar data.
March 2021 - DRAFT 01_33_00-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
2. Coordinate submittal with other submittals and with the requirements of the
Contract Documents.
3. Check, verify, and revise submittals as necessary to bring them into
conformance with Contract Documents and actual field conditions.
1.06 SUBMITTAL CONTENT
A. Shop Drawings:
1. Contractor to field verify elevation, coordinates, and pipe material for pipe tie-in
prior to the submittal of shop drawings to Owner and Engineer.
2. Details:
a. Fabrication drawings: drawn to scale and dimensioned.
b. Front, side, and, rear elevations, and top and bottom views, showing all
dimensions.
c. Locations of conduit entrances and access plates.
d. Component layout and identification.
e. Weight.
f. Finish.
g. Temperature limitations, as applicable.
h. Nameplate information.
B. Product Information:
1. Product Data:
a. Details:
1) Supplier name and address.
2) Subcontractor name and address.
b. Include:
1) Catalog cuts.
2) Bulletins.
3) Brochures.
4) Manufacturer's Certificate of Compliance: signed by product
manufacturer along with supporting reference data, affidavits, and
tests, as appropriate.
5) Manufacturer's printed recommendations for installation of
equipment.
6) Quality photocopies of applicable pages from manufacturer's
documents.
2. Completely fill out a Motor Data Sheet, as specified in Section 26_05_09, for
every motor furnished:
a. Submit 1 copy of the Motor Data Sheet to the Engineer for review as part
of the associated equipment submittal.
3. Samples:
a. Details:
1) Submit labeled samples.
2) Samples will not be returned.
3) Provide samples from manufacturer's standard colors, materials,
products, or equipment lines.
4. Minor or incidental products and equipment schedules:
a. Details:
1) Shop Drawings of minor or incidental fabricated products will not be
required, unless requested.
March 2021 - DRAFT 01_33_00-4 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
2) Submit tabulated lists of minor or incidental products showing the
names of the manufacturers and catalog numbers, with Product Data
and Samples as required to determine acceptability.
C. Design calculations:
1. Details:
a. Defined in technical sections.
b. For equipment and materials designed and manufactured by a supplier
and not the Engineer, calculations are required to be submitted by
supplier.
c. Calculations must bear the original seal and signature of a Professional
Engineer licensed in the state where the project is located and who
provided responsible charge for the design.
D. Qualifications Statements:
1. Details:
a. Defined in technical sections.
b. Licensing documentation.
c. Certification documentation.
d. Education documentation.
E. Quality assurance/control submittals:
1. Mill test reports:
a. Details:
1) Submit certified copies of factory and mill test reports.
2) Do not incorporate Products in the Work which have not passed
testing and inspection satisfactorily.
2. Test reports:
a. Details:
1) Include the following information:
a) A description of the test.
b) List of equipment used.
c) Name of the person conducting the test.
d) Date and time the test was conducted.
e) Ambient temperature and weather conditions.
f) All raw data collected.
g) Calculated results.
h) Clear statement if the test passed or failed the requirements
stated in Contract Documents.
i) Signature of the person responsible for the test.
3. Factory Acceptance Test:
a. Details: Include complete test procedure and all forms to be used during
test.
4. Certificates:
a. Details: Defined in technical sections.
5. Manufacturers' field reports:
a. Details: Manufacturer's Certificate of installation and functionality
compliance.
6. Field samples:
a. Details: Defined in technical sections.
7. Test plans:
a. Details: Defined in technical sections.
March 2021 - DRAFT 01_33_00-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
Item#18.
1.07 SUBMITTAL PROCEDURE
A. Contractor: Send submittal to Engineer.
1. Delivery: Deliver submittals to Engineer.
2. Timeliness: Schedule and make submissions in accordance with the
requirements of the individual specification sections and in such a sequence
as to cause no delay in Work.
B. Engineer: Review submittal and provide response.
1. Review description:
a. Engineer will be entitled to rely upon the accuracy or completeness of
designs, calculations, or certifications made by licensed professionals
accompanying a particular submittal whether or not a stamp or seal is
required by Contract Documents or Laws and Regulations.
b. Engineer's review of submittals shall not release Contractor from
Contractor's responsibility for performance of requirements of Contract
Documents. Neither shall Engineer's review release Contractor from
fulfilling purpose of installation nor from Contractor's liability to replace
defective work.
c. Engineer's review of shop drawings, samples, or test procedures will be
only for conformance with design concepts and for compliance with
information given in Contract Documents.
d. Engineer's review does not extend to:
1) Accuracy of dimensions, quantities, or performance of equipment
and systems designed by Contractor.
2) Contractor's means, methods, techniques, sequences, or procedures
except when specified, indicated on the Drawings, or required by
Contract Documents.
3) Safety precautions or programs related to safety which shall remain
the sole responsibility of the Contractor.
e. Engineer can Approve or Not Approve any exception at their sole
discretion.
2. Review timeframe:
a. Except as may be provided in technical specifications, a submittal will be
returned within 10 workdays.
b. When a submittal cannot be returned within the specified period, Engineer
will, within a reasonable time after receipt of the submittal, give notice of
the date by which that submittal will be returned.
3. Schedule delays:
a. No adjustment of Contract Times or Contract Price will be allowed due to
Engineer's review of submittals, unless all of the following criteria are met:
1) Engineer has failed to review and return first submission within the
agreed upon time frame.
2) Contractor demonstrates that delay in progress of Work is directly
attributable to Engineer's failure to return submittal within time
indicated and accepted by Engineer.
4. Review responses: 1 copy of submittal will be returned to Contractor with one
of the following reviewer's response.
a. Approved:
1) No Exceptions:
a) There are no notations or comments on the submittal and the
Contractor may release the equipment for production.
March 2021 - DRAFT 01_33_00-6 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
Item#18.
2) Make Corrections Noted - See Comments:
a) The Contractor may proceed with the work, however, all
notations and comments must be incorporated into the final
product.
b) Resubmittal not required.
3) Make Corrections Noted - Confirm:
a) The Contractor may proceed with the work, however, all
notations and comments must be incorporated into the final
product.
b) Submit confirmation specifically addressing each notation or
comment to the Engineer within 15 calendar days of the date of
the Engineer's transmittal requiring the confirmation.
b. Not approved:
1) Correct and Resubmit:
a) Contractor may not proceed with the work described in the
submittal.
b) Contractor assumes responsibility for proceeding without
approval.
c) Resubmittal of complete submittal package is required within
15 calendar days of the date of the Engineer's submittal review
response.
2) Rejected - See Remarks:
a) Contractor may not proceed with the work described in the
submittal.
b) The submittal does not meet the intent of the Contract
Documents. Resubmittal of complete submittal package is
required with materials, equipment, methods, etc. that meet the
requirements of the Contract Documents.
c. Receipt Acknowledged: Filed for Record:
1) This is used in acknowledging receipt of informational submittals that
address means and methods of construction such as schedules and
work plans, conformance test reports, health and safety plans, etc.
C. Contractor: Prepare resubmittal, if applicable.
1. Clearly identify each correction or change made.
2. Include a response in writing to each of the Engineer's comments or questions
for submittal packages that are resubmitted in the order that the comments or
questions were presented throughout the submittal.
a. Acceptable responses to Engineer's comments are listed below:
1) "Incorporated" Engineer's comment or change is accepted and
appropriate changes are made.
2) "Response" Engineer's comment not incorporated. Explain why
comment is not accepted or requested change is not made. Explain
how requirement will be satisfied in lieu of comment or change
requested by Engineer.
b. Reviews and resubmittals:
1) Suppliers shall provide resubmittals which include responses to all
submittal review comments separately and at a level of detail
commensurate with each comment.
2) Supplier responses shall indicate how the supplier resolved the issue
pertaining to each review comment. Responses such as
"acknowledged" or "noted" are not acceptable.
March 2021 - DRAFT 01_33_00-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
Item#18.
3) Resubmittals which do not comply with this requirement may be
rejected and returned without review.
4) Contractor shall be allowed no extensions of any kind to any part of
their contract due to the rejection of non-compliant submittals.
5) Submittal review comments not addressed by the Contractor in
resubmittals shall continue to apply whether restated or not in
subsequent reviews until adequately addressed by the Contractor to
the satisfaction of the reviewing and approving authority.
c. Any resubmittal that does not contain responses to the Engineer's
previous comments shall be returned for Revision and Resubmittal.
No further review by the Engineer will be performed until a response for
previous comments has been received.
3. Resubmittal timeframe:
a. Contractor shall provide resubmittal within 15 days.
b. When a resubmittal cannot be returned within the specified period,
Contractor shall notify Engineer in writing.
1.08 SUPPLIER'S PROFESSIONAL ENGINEER (P.E.) CERTIFICATION FORM
A. Submit a completed Supplier's P.E. Certification Form, provided in this Section, to
comply with technical sections requirement for a professional engineer's certification
for design of the anchor bolts from an engineer licensed in the state the project is
located.
PART PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
END OF SECTION
March 2021 - DRAFT 01_33_00-8 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
Item#18.
APPENDIX A
CONTRACTOR SUBMITTAL TRANSMITTAL FORM
March 2021 - DRAFT 0 33 00-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
DOCUMENT 01 33 00
CONTRACTOR SUBMITTAL TRANSMITTAL FORM
Owner: Date:
Contractor: Project No.:
Project Name: Submittal Number:
Submittal Title:
To:
From:
Specification No. and Subject of Submittal / Equipment Supplier
Spec##: Subject:
Authored By: Date Submitted:
Submittal Response
Check Either (A) or(B):
❑ (A) We have verified that the equipment or material contained in this submittal meets all
the requirements specified in the project manual or shown on the contract drawings
with no exceptions.
❑ (B) We have verified that the equipment or material contained in this submittal meets all
the requirements specified in the project manual or shown on the contract drawings
except for the following deviations (list deviations):
Certification Statement: By this submittal, I hereby represent that I have determined and verified all
field measurements, field construction criteria, materials, dimensions, catalog numbers and similar
data, and I have checked and coordinated each item with other applicable approved shop drawings
and all Contract requirements.
General Contractor's Reviewer's Signature:
Printed Name:
In the event, Contractor believes the Submittal response does or will cause a change to the
requirements of the Contract, Contractor shall immediately give written notice stating that Contractor
considers the response to be a Change Order.
Firm: Signature: Date Returned:
PM/CM Office Use
Date Received GC to PM/CM:
Date Received PM/CM to Reviewer:
Date Received Reviewer to PM/CM:
Date Sent PM/CM to GC:
March 2021 - DRAFT 01 33 00-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_33_00(IDS50)
Item#18.
APPENDIX B
SUPPLIER'S P.E. CERTIFICATION FORM
March 2021 - DRAFT 01 33 00-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_33_00(IDS50)
Item#18.
DOCUMENT 01 33 00
SUPPLIER'S P.E. CERTIFICATION FORM
Owner: Date:
Contractor: Registration State:
Project Name: Project No.:
Responsibilities:
Spec Section:
Statement of Certification
The undersigned hereby certifies that he/she is a professional engineer registered in the State of
and that he/she has been employed by
The undersigned further certifies that he/she has performed the said design in conformance with all
applicable local, state, and federal codes, rules, and regulations; and, that his/her signature and
P.E. stamp have been affixed to all calculation and drawings used in, and resulting from, the design.
The undersigned hereby agrees to make all original design drawings and calculations available to:
(Name of Owner, or Owner's representative within 7 days of receiving a written request
by the Owner.)
Prof. Engineer
Signature: Date:
Printed Name: Company Name:
Contractor's
Signature: Date:
Printed Name:
March 2021 - DRAFT 01 33 00-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_33_00(IDS50)
Item#18.
SECTION 01_75_17
COMMISSIONING
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Requirements for each Commissioning phase of the
equipment/system.
B. Related sections:
1. Section 01_78_23 - Operation and Maintenance Data.
2. Section 40_80_01 - Testing, Calibration, and Commissioning.
1.02 DEFINITIONS
A. Clean Water Facility Testing —Testing of complete facility utilizing clean water for
purposes of confirming extended equipment/system operation prior to Process
Start-up Phase.
B. Commissioning —The process of planning, testing, and process start-up of the
installation for compliance with contract requirements and demonstrating, through
documented verification, that the project has successfully met the Contractual
requirements. It includes training the Owner's staff to operate the facility.
C. Commissioning Phases—The work activities of facility commissioning are grouped
into the phases defined in the table below.
Commissioning
Planning Testing and Training Process Start-Up
Phase Phase Phase
Owner Training Plan and Source Testing Process Start-up
Schedule
Subsystem Testing Plan Owner Training Process Operational
Period
Clean Water Facility Installation Testing
Testing Plan
Functional Testing
Clean Water Facility
Testing
Closeout Documentation
D. Component—A basic building block of equipment, subsystems, and systems that
requires installation or functional testing but does not have an electrical connection
or internal electronics. (Examples: filter effluent piping and manual isolation valves).
March 2021 - DRAFT 01 75 17-1 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
E. Device —A basic building block of equipment, subsystems, and systems that
requires installation or functional testing and does have an electrical connection or
internal electronics. (Examples: filter level transmitter or water pump pressure
transmitter).
F. Equipment—An assembly of component(s) and devices(s) that requires installation
or functional testing. (Examples: Pump, motor, VFD, Ozone Generator, UV
Disinfection System, etc.).
G. Facility—A grouping of process areas, systems, subsystems, equipment,
components, and devices (Examples: treatment plant, pump station, etc.).
H. Functional Testing —Testing performed on a completed subsystem to demonstrate
that equipment/system meets manufacturers' calibration and adjustment
requirements and other requirements as specified. Functional testing includes
operating equipment/system manually in local, manually in remote (or remote
manual), and automatically in remote (in remote auto).
I. Installation Testing —Testing to demonstrate that subsystem component (piping,
power, networks, devices, etc.) is ready and meets the project requirements in
advance of functional testing. Installation testing also includes manufacturers'
certification of installation and other requirements as specified to prepare
equipment/system for Functional Testing. Also referred to as Field Acceptance
Testing.
J. Instrumentation and Controls Fine-Tuning — Improving the performance of the
Instrumentation Process Control system by operating for an extended time period.
K. Manufacturer's Certificate of Source Testing —When applicable, the form is used
during Source Testing for the manufacturer to confirm that the applicable source
tests have been performed and results conform to the Contract Documents. The
form is provided at the end of this Section.
L. Manufacturer's Certificate of Installation and Functionality Compliance —The form is
used during Installation Testing and Functional Testing. It is submitted at the end of
Functional Testing to confirm that the equipment/system is installed in conformance
with the Contract Documents and that it meets the Functional Testing requirements
defined in the Contract Documents. The form is provided at the end of this Section.
M. Process Area —A grouping of systems, subsystems, equipment, components, and
devices that divide a facility into functional areas. (Examples: Filter Process Area or
Chemical Area).
N. Process Operational Period —A period of time after completion of the process
start-up set aside for final Operational Testing to verify facility performance meets
the Contract Document requirements. This period may specifically limit other
construction activities.
O. Process Start-up Phase - Operating the facility to verify performance meets the
Contract Document requirements.
P. Process Start-Up —Activities conducted after the testing and training phase that are
necessary to place systems or process areas into operational service.
March 2021 - DRAFT 01 75 17-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
Q. Product—A system, subsystem, or component.
R. Subsystem —A building block of systems made up from a grouping of components,
devices, and equipment that perform a definable function. (Examples: Filter No. 1
Backwash Subsystem, Sedimentation Basin No. 1 Hoseless Sludge Removal
Subsystem).
S. System —A grouping of subsystems, equipment, components, and devices that
perform a definable function. (Examples: Filter No. 1, Sedimentation Basin).
1.03 COMMISSIONING COORDINATION (CC)
A. Contractor, Supplier, Owner and Resident Engineer shall coordinate to provide
commissioning coordination for the Project.
1.04 SERVICES OF MANUFACTURER'S REPRESENTATIVES
A. Qualification of manufacturer's representative as specified in the Contract
Documents technical Sections include the following:
1. Authorized representative of the manufacturer, factory trained and
experienced in the technical applications, installation, operation, and
maintenance of respective equipment/system with full authority by the
equipment/system manufacturer to issue the certifications required of the
manufacturer.
2. Competent, experienced technical representatives of equipment/system
manufacturer for assembly, installation, testing guidance, and training.
3. Additional qualifications may be specified in the individual Sections.
4. Submit qualifications of the manufacturer's representative no later than
30 days in advance of required observations.
5. Representative subject to approval by Owner and Engineer.
6. No substitute representatives will be allowed until written approval by Owner
and Engineer has been obtained.
B. Completion of manufacturer on-site services: Engineer approval required.
C. Manufacturer is responsible for determining the time required to perform the
specified services.
1. Minimum times specified in the Contract Documents are estimates.
2. No additional costs associated with performing the required services will be
approved.
3. Manufacturer required to schedule services in accordance with the
Contractor's project schedule up to and including making multiple trips to
project site when there are separate milestones associated with installation of
each occurrence of manufacturer's equipment.
D. Manufacturer's on-site services as specified in the Contract Documents include the
following:
1. Assistance during Commissioning Phase and Process Start-Up Phase.
2. Upon request, provide daily copies of manufacturer's representatives' field
notes and data to Engineer.
3. Other requirements as specified in the Contract Documents.
March 2021 - DRAFT 01 75 17-3 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
1.05 PLANNING PHASE
A. Overview of Planning Phase:
1. Defines approach and timing for Commissioning.
B. Owner training plan and schedule:
1. Training outcomes:
a. Owner's operations, maintenance, and engineering staff have the
information needed to safely operate, maintain, and repair the
equipment/systems provided under this Contract.
2. Training objectives:
a. To instruct personnel in the operation and maintenance of the
equipment/system. Instruction shall include step-by-step troubleshooting
procedures with all necessary test equipment/system.
b. To instruct personnel in the removal, inspection, and cleaning of
equipment/system as needed.
c. Training tailored to the skills and job classifications of the staff attending
the classes (e.g., plant superintendent, treatment plant operator,
maintenance technician, electrician, etc.).
d. Provide supporting documentation, such as vendor operation and
maintenance manuals.
3. Training schedule:
a. Schedule Owner's staff training within the constraints of their workloads.
Those who will participate in this training have existing full-time work
assignments, and training is an additional assigned work task, therefore,
scheduling is imperative. Operator training shall occur between 7:00 a.m.
and 3:30 p.m., Monday through Friday. Maintenance staff training shall
occur between 7:00 a.m. and 4:30 p.m. Monday through Thursday.
4. Training plan:
a. Coordinate and arrange for manufacturer's representatives to provide
both classroom-based learning and field (hands-on) training, based on
training module content and stated learning objectives.
b. Conduct classroom training at location designated by Owner.
c. Scope and sequence:
1) Plan and schedule training in the correct sequence to provide
prerequisite knowledge and skills to trainees.
a) Describe recommended procedures to check/test
equipment/system following a corrective maintenance repair.
5. Training scheduling coordination:
a. Complete Owner training no sooner than 21 calendar days prior to start of
process start-up of each system.
6. Meetings:
a. Commissioning progress meetings will be held between Owner,
Contractor, Supplier and Resident Engineer throughout construction, to
plan, scope, coordinate, and schedule future activities, resolve problems,
etc.:
1) Frequency: Monthly minimum. Increase frequency as needed based
on complexity and quantity of commissioning activities.
7. Training sessions:
a. Provide training sessions for equipment/system as specified in the
individual equipment/system Section.
March 2021 - DRAFT 01 75 17-4 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
b. Submit Commissioning Schedule not less than 30 calendar days prior to
planned initial commissioning of each subsystem or system.
8. Schedule requirements:
a. With input from Supplier, building contractor shall provide detailed
schedule of commissioning activities including durations and sequencing
requirements:
1) Identify the following activities:
a) Testing and Training Phase:
(1) Source Testing.
(2) Owner Training.
(3) Installation Testing.
(4) Functional Testing.
(5) Clean Water Facility Testing.
(6) Closeout Documentation.
b) Process Start-Up Phase:
(1) Process Start-Up.
(2) Process Operational Period.
(3) Instrumentation and Controls Fine-Tuning.
b. Schedule manufacturer's services to avoid conflict with other on-site
testing or other manufacturers' on-site services.
c. Verify that conditions necessary to allow successful testing have been met
before scheduling services.
C. Subsystem testing plans (by Supplier):
1. Provide separate testing plans for each individual subsystem and system that
include the following:
a. Approach to testing including procedures, schedule, and recirculation
requirements.
b. Test objective: Demonstrate subsystem meets the design requirements as
specified in the technical Sections.
c. Test descriptions, forms, temporary systems (pumps, piping, etc.),
shutdown requirements for existing systems, test forms, test logs, witness
forms, and checklists to be used to control and document the required
tests.
d. Test forms: Include, but not limited to, the following information:
1) Tag and name of equipment/system to be tested.
2) Test date.
3) Names of persons conducting the test.
4) Names of persons witnessing the test, where applicable.
5) Test data.
6) Applicable project requirements.
7) Check offs for each completed test or test step.
8) Place for signature of person conducting tests and for the witnessing
person, as applicable.
e. Define start-up sequencing of unit processes:
1) Include testing of alarms, interlocks, permissives, control circuits,
capacities, speeds, flows, pressures, vibrations, sound levels, and
other parameters.
2) Provide detailed test procedures setting forth step-by-step
descriptions of the procedures for systematic testing of
equipment/system.
March 2021 - DRAFT 01 75 17-5 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
3) Demonstrate proper rotation, alignment, speed, flow, pressure,
vibration, sound level, adjustments, and calibration:
a) Perform initial checks in the presence of and with the assistance
of the manufacturer's representative.
4) Demonstrate proper operation of each control loop function including
mechanical, electrical, alarms, local and remote controls,
instrumentation, and other equipment/system functions:
a) Generate signals with test equipment/system to simulate
operating conditions in each control mode.
2. Engineer approval of test plan is required prior to performing test:
a. Revise and update test plans based on review comments, actual
progress, or to accommodate changes in the sequence of activities.
b. Submit test reports for each phase of testing for each equipment/system.
c. Engineer approval of preceding test reports is required prior to start of
next test.
d. Tests will be rescheduled if test plan is not approved by the required
deadline.
3. Contractor is responsible to reproduce and distribute final test procedures.
D. Clean Water Facility Testing Plan (by building contractor, with input from Supplier):
1. Submit a Clean Water Facility Testing Plan equivalent to the requirements of
the subsystem test plans a minimum of 30 calendar days prior to Clean Water
Facility Testing. Clean water may be non-potable plant water if acceptable to
Owner.
1.06 TESTING AND TRAINING PHASE
A. Overview of Testing And Training Phase:
1. General:
a. Include specified Source Testing, Owner Training, Installation Testing,
Functional Testing, Clean Water Facility Testing, and Closeout
Documentation required by this Section and the technical Sections.
2. Contractor responsibilities:
a. Prior to testing, verify equipment protective devices and safety devices
have been installed, calibrated, and tested.
b. Acceptable tests: Demonstrate the equipment/system performance meets
the requirements stated in the Contract Documents:
1) When the equipment/system fails to meet the specified requirements,
perform additional, more detailed, testing to determine the cause,
correct, repair, or replace the causative components and repeat the
testing that revealed the deficiency.
B. Source testing:
1. Also referred to as factory testing or factory acceptance testing (FAT).
2. Test components, devices, and equipment/system for proper performance at
point of manufacture or assembly as specified in the technical Sections.
3. Notify the Engineer in writing when the equipment/system is ready for source
inspection and testing.
4. Source Test Plan:
a. As specified in this Section and other technical Sections.
b. Source testing requirements as specified in technical Sections:
1) Non-witnessed: Provide Manufacturer's Certificate of Source Testing.
March 2021 - DRAFT 01 75 17-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
2) Witnessed: 1 Owner's representative and 1 Engineer's
representative present during testing, unless otherwise specified, and
provide Manufacturer's Certificate of Source Testing.
c. Prepared by Contractor as a result of discussions and planning emerging
from regularly conducted commissioning meetings for source tests as
specified in the Contract Documents.
d. Provide the following items for each Source Test (unless determined by
Contractor, Owner and Engineer that level of equipment complexity does
not warrant all of the following source test plan elements; source plan
requirements tailored to level of equipment complexity):
1) Purpose and goals of the test.
2) Identification of each item of equipment/system, including system
designation, location, tag number, control loop identifier, etc.
3) Description of the pass/fail criteria that will be used.
4) Listing of pertinent reference documents (Contract Documents and
industry standards or Sections applicable to the testing).
5) Complete description, including drawings or photographs, of test
stands and/or test apparatus.
6) Credentials of test personnel.
7) Descriptions of test equipment to be used, product information, and
all appropriate calibration records for the test equipment.
8) Test set-up procedures.
9) Detailed step-by-step test procedures:
a) The level of detail shall be sufficient for the Resident Engineer
and Contractor to be able to follow the steps and develop
confidence that the tests were being performed as planned.
b) All steps are significant, and all steps shall be included in the
procedures.
10) Sample data logs and data recording forms.
11) Sample computations or analyses with the results in the same format
as the final report to demonstrate how data collected will be used to
generate final results:
a) Complete disclosure of the calculation methodologies.
b) Include a sample for each type of computation required for the
test and analysis of the results.
12) Detailed outline of the Source Test report.
13) Sample test reports.
e. Submit Source Test Plan and forms as specified in the technical Sections:
1) Submit a copy of the Source Test Plan at least 21 days before any
scheduled test date.
2) Engineer approval of Source Test Plan required prior to beginning
source testing.
3) Schedule the testing after approval of the test procedures submittal.
f. Indicate the desired dates for source inspection and testing.
1) Notify the Engineer of the scheduled tests a minimum of 15 days
before the date of the test.
5. Test results:
a. Prepare and submit test results with collected data attached.
6. Owner is responsible for costs associated with Owner's representatives
witnessing Source Tests, if required by the equipment specification.
7. Contractor is responsible for providing fuel, chemicals, and other consumables
needed for Source Testing.
March 2021 - DRAFT 01 75 17-7 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
C. Owner training:
1. Training instruction format:
a. The training for operations and maintenance personnel shall be provided
as one entity.
b. Instructors shall apply adult education best practices, emphasizing learner
participation and activity.
c. Training delivery may include problem solving, question/answer, hands-on
instruction, practice, evaluation/feedback tools, and lecture.
d. Visual aids and hands-on practice sessions must support training
objectives.
e. Lecturing should be less than 30 percent of class time.
f. Conduct hands-on instruction according to the following descriptions:
1) Present hands-on demonstrations of at least the following tasks:
a) Proper start-up, shutdown, and normal and alternative operating
strategies.
b) Common corrective maintenance repairs for each group.
c) Describe recommended procedures to check/test
equipment/system following a corrective maintenance repair.
2) Use tools and equipment provided by manufacturer to conduct the
demonstrations:
a) Submit requests for supplemental assistance and facilities with
the Contractor's proposed lesson plans.
3) Contractor remains responsible for equipment disassembly or
assembly during hands-on training situations involving equipment
disassembly or assembly by Owner's personnel:
a) Provide written certification of proper equipment/system
operation to Engineer after completion of hands-on training.
2. Class agenda:
a. Include the following information in the agenda:
1) Instructor name.
2) Listing of subjects to be discussed.
3) Time estimated for each subject.
4) Allocation of time for Owner staff to ask questions and discuss the
subject matter.
5) List of documentation to be used or provided to support training.
b. Owner may request that particular subjects be emphasized and the
agenda be adjusted to accommodate these requests.
c. Distribute copies of the agenda to each student at the beginning of each
training class.
3. Number of students:
a. Estimated maximum class size: 15 persons:
1) Owner will determine the actual number of students.
2) Engineer will provide an estimated headcount 1 week prior to the
class, so that the instructor can provide the correct number of training
aids for students.
4. Instructor qualifications:
a. Provide instructors completely knowledgeable in the equipment/system for
which they are training.
b. Provide instructor's technical preparation and instructional technology
skills and experience.
March 2021 - DRAFT 01 75 17-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
c. Sales representatives are not qualified instructors unless they possess the
detailed operating and maintenance knowledge required for proper class
instruction.
d. If, in the opinion of the Owner, an appropriately knowledgeable person did
not provide the scheduled training, such training shall be rescheduled and
repeated with a suitable instructor.
5. Training aids:
a. Instructors are encouraged to use audio-visual devices, P&IDs, models,
charts, and so forth to increase the transfer of knowledge.
b. Owner shall provide such equipment (televisions, video recorder/player,
computer, projectors, screens, easels, etc.)for each class.
c. Instructor is responsible for confirming with Engineer and Owner in
advance of each class that the classroom will be appropriate for the types
of audiovisual equipment to be employed.
6. Classroom documentation:
a. Trainees will keep training materials and documentation after the session.
b. Operations and maintenance manuals, as specified in technical Sections:
1) Provide a minimum of 2 copies of final Engineer-approved operations
and maintenance manuals as specified in Section 01_78_23 for use
during the classroom instruction.
2) Owner reserves the right to delay training for a particular equipment
item if the operations and maintenance manuals for that equipment
are incomplete, inaccurate, or otherwise unsuitable for use by the
Owner's staff.
3) No contract extensions or extra costs will be allowed for training
delays due to operations and maintenance manual submittal delays.
4) Owner may waive requirement to have operations and maintenance
manuals provide prior to training.
c. Provide supplemental documentation handouts to support instruction.
d. Training modules:
1) Provide a training module for each equipment category.
2) Divide each training module's instructional content into discrete
lesson plans.
e. Lesson plans:
1) Provide performance-based learning objectives.
2) State learning objectives in terms of what the trainees will be able to
do at the end of the lesson.
3) Define student conditions of performance and criteria for evaluating
instructional success:
a) Provide the following information:
4) Instruction lesson plan outlines for each craft:
a) Provide specific components and procedures.
5) Minimum requirements:
a) Hands-on demonstrations planned for the instructions.
b) Cross-reference training aids.
c) Planned training strategies such as whiteboard work, instructor
questions, and discussion points or other planned classroom or
field strategies.
d) Attach handouts cross-referenced by section or topic in the
lesson plan.
e) Indicate duration of outlined training segments.
March 2021 - DRAFT 01 75 17-9 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17 QDS50)
Item#18.
6) Provide maintenance instruction lesson plans including mechanical,
instrumentation, and electrical aspects:
a) Equipment operation:
(1) Describe equipment's operating (process) function and
system theory.
(2) Describe equipment's fundamental operating principles and
dynamics.
(3) Identify equipment's mechanical, electrical, and electronic
components and features.
(4) Identify support equipment associated with the operation of
subject equipment.
(5) Detail the relationship of each piece of equipment or
component to the subsystems, systems, and process.
(6) Cite hazards associated with the operations, exposure to
chemicals associated with the component, or the waste
stream handled by the component.
(7) Specify appropriate safety precautions, equipment, and
procedures to eliminate, reduce, or overcome hazards.
b) Detailed component description:
(1) Define Preventative Maintenance (PM) inspection
procedures required on equipment in operation, spot
potential trouble symptoms (anticipate breakdowns), and
forecast maintenance requirements (predictive
maintenance):
(a) Review preventive maintenance frequency and task
analysis table.
(2) Identify each component function and describe in detail.
(3) Where applicable, group relative components into
subsystems.
(4) Identify and describe in detail equipment safety features,
permissive and controls interlocks.
7) Provide the following information in equipment troubleshooting
lesson plans:
a) Define recommended systematic troubleshooting procedures as
they relate to specific craft problems.
b) Provide component specific troubleshooting checklists as they
relate to specific craft problems.
8) Provide the following information in equipment Corrective
Maintenance (CM) troubleshooting lesson:
a) Describe recommended equipment preparation requirements as
they relate to specific craft problems.
b) Identify and describe the use of any special tools required for
maintenance of the equipment as they relate to specific craft
problems.
c) Describe component removal/installation and
disassembly/assembly procedures for specific craft repairs.
d) Perform at least 2 hands-on demonstrations of common
corrective maintenance repairs:
(1) Additional demonstrations may be required by the Owner.
e) Describe recommended measuring instruments and procedures,
and provide instruction on interpreting alignment measurements,
as appropriate.
March 2021 - DRAFT 01 75 17-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17(IDS50)
Item#18.
7. Class logistics:
a. Delivery time minimum: 4 hours.
b. Delivery time maximum: 8 hours.
c. Schedule specific sessions:
1) Minimum of 30 days in advance to allow Owner staffing
arrangements to take place.
2) At the times requested by the Owner, within the period 7 a.m. to
7 p.m. Monday through Friday:
a) Times scheduled will be at Owner's discretion.
3) Owner approval and confirmation required for session schedules.
4) Provide minimum of 1 session for each class unless otherwise noted.
8. Distribute Training Evaluation Form following each training session:
a. Training Evaluation Form is included in this Section.
b. Return completed Training Evaluation Forms to Owner's designated
training coordinator immediately after session is completed.
c. Revise training sessions judged "Unsatisfactory" by a majority of
attendees:
1) Conduct training sessions again until a satisfactory rating is achieved
at no additional cost to Owner. The Contractor shall be responsible
for all costs associated with repeated training sessions including
costs for trainee time.
9. Submittals:
a. Prior to the training session:
1) Instructor qualifications: 30 calendar days prior to initial training
session.
2) Training course materials: 14 calendar days prior to initial training
session:
a) Training agenda, lesson plan, presentation, and handouts.
b) Other audio-visual aids utilized during each training course.
c) Format: Electronic submission.
b. Post training session:
1) Training course materials: Due 14 calendar days after class
completion:
a) Class attendance sheet.
b) Training agenda, final lesson plan, presentation, and handouts.
c) Other audio-visual aids utilized during each training course.
d) Provide materials for all sessions of the class in a single
transmittal.
e) Format: 2 electronic copies and 3 hard copies organized in
notebooks.
D. Installation testing:
1. Perform subsystem testing according to approved Subsystem Testing Plans.
2. Initiate the Manufacturer's Certificate of Installation and Functionality
Compliance for all equipment:
a. Manufacturer's Certificate of Installation and Functionality Compliance
form is included in this Section.
b. Manufacturer's Certificate of Installation and Functionality Compliance
certifies the equipment meets the following requirements:
1) Has been properly installed, adjusted, aligned, and lubricated.
2) Is free of any stresses imposed by connecting piping or anchor bolts.
3) Is able to be operated as necessary for Functional Testing.
March 2021 - DRAFT 01 75 17-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
c. Form shall be submitted after completion of Functional Testing, as
specified in this Section.
3. Perform mechanical equipment Installation Testing: As specified below and in
individual equipment Sections:
a. Remove rust preventatives and oils applied to protect equipment during
construction.
b. Flush lubrication systems and dispose of flushing oils:
1) Recharge lubrication system with lubricant recommended by
manufacturer.
c. Install and adjust packing, mechanical seals, O-rings, and other seals.
Replace defective seals.
d. Remove temporary supports, bracing, or other foreign objects installed to
prevent damage during shipment, storage, and erection.
e. Check rotating machinery for correct direction of rotation and for freedom
of moving parts before connecting driver.
f. Perform cold alignment and hot alignment to manufacturer's tolerances.
g. Adjust V-belt tension and variable pitch sheaves.
h. Inspect hand and motorized valves for proper adjustment:
1) Tighten packing glands to ensure no leakage, but permit valve stems
to rotate without galling.
2) Verify valve seats are positioned for proper flow direction.
i. Tighten leaking flanges or replace flange gasket:
1) Inspect screwed joints for leakage.
j. Install gratings, safety chains, handrails, shaft guards, and sidewalks prior
to operational testing.
4. Electrical devices and subsystems Installation Testing: As specified in the
technical Sections.
5. Instrumentation devices and subsystems Installation Testing: As specified in
the technical Sections.
E. Functional testing:
1. Perform subsystem testing according to approved Subsystem Testing Plan.
2. Notify the Engineer 5 days prior to when the Work is ready for Functional
Testing:
a. Perform testing in the presence of the Engineer.
3. Determine Functional Testing durations with Owner's input.
a. Durations will vary depending on the availability of water for testing.
b. Target minimum Functional Test duration: 8 hours:
1) Identify equipment/system that cannot be tested for a minimum of
8 hours as specified in technical Sections.
4. Perform Functional Testing as specified in technical Sections.
a. Perform Functional Testing in addition to the other tests specified in the
technical Sections.
b. Perform Functional Testing to demonstrate that the component equipment
functions as an entire system in accordance with the design requirements.
c. Perform Functional Testing to demonstrate that the unit process has
operated in a manner necessary to demonstrate equipment/system
functions manually in local, manually in remote (or remote manual), and
automatically in remote (in remote auto).
d. Repair or replace parts that operate improperly and retest.
e. Submit testing results as specified in the technical Sections to the Owner
and Engineer for approval of Functional Testing results.
March 2021 - DRAFT 01 75 17-12 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
5. Provide completed Manufacturer's Certificate of Installation and Functionality
Compliance forms for all equipment:
a. Manufacturer's Certificate of Installation and Functionality Compliance
form is included in this Section.
b. Manufacturer's Certificate of Installation and Functionality Compliance
certifies the equipment/system meets the following requirements:
1) Is suitable for satisfactory full-time operation under full-load
conditions.
2) Operates within the allowable limits for vibration and noise.
3) Electrical and instrumentation requirements:
a) Electrical equipment, instrumentation, and control panels are
properly installed, calibrated, and functioning.
b) Electrical Installation Testing is complete, and test results have
been approved by the Engineer:
(1) Noted deficiencies have been corrected.
(2) Relays, circuit breakers, and other protective devices are
set.
c) Control logic for start-up, shutdown, sequencing, interlocks,
control, and emergency shutdown has been tested and is
properly functioning.
d) Motor control is calibrated and tested.
F. Clean Water Facility Testing:
1. Utilize non-potable plant water.
2. Do not begin Clean Water Facility Testing until Engineer has approved
submittals for Functional Testing requirements.
3. Test entire facility with recirculating water supply at the design flow for the
largest single process or system train to ensure proper complete facility
(equipment/system) hydraulic performance.
4. Perform testing in the presence of the Engineer unless such presence is
expressly waived in writing.
5. The purpose of Clean Water Facility Testing is to confirm extended
equipment/system operation prior to process start-up:
a. Testing shall occur for a minimum of 3 days with all systems operational
to the extent possible.
G. Closeout documentation:
1. Submittals:
a. Provide records generated during Commissioning Phase of Project:
1) Required documents include but are not limited to:
a) Training documentation.
b) Manufacturer's Certificate of Source Testing.
c) Manufacturer's Certificate of Installation and Functionality
Compliance.
d) Daily logs of equipment/system testing identifying tests
conducted and outcome.
e) Test forms and documentation.
f) Functional Testing results.
g) Logs of time spent by manufacturer's representatives performing
services on the job site.
h) Equipment lubrication records.
i) Electrical phase, voltage, and amperage measurements.
March 2021 - DRAFT 01 75 17-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
j) Insulation resistance measurements.
k) Bearing temperature measurements.
1.07 PROCESS START-UP PHASE
A. Overview of Process Start-Up Phase:
1. Operating the facility to verify performance meets the Contract Document
requirements.
B. Process Start-Up:
1. Perform process start-up in the presence of the Engineer.
2. Pre-start-up activities:
a. Commissioning Documentation and Data Review.
b. Start-Up Go/No-Go Decision Criteria.
c. Building and Fire Inspection Compliance Check.
d. Process Start-Up Sequence Review:
1) Submit a Process Start-Up plan for review by Engineer.
2) Include the following:
a) Pre-start-up activities.
b) Process Start-Up.
c) Process Operational Period.
e. Description of Temporary Testing Arrangement, if applicable.
f. Final Process Start-Up Forms and Documentations.
g. Final Operational Testing Plan.
3. Control loop tuning (by Supplier):
a. Perform control loop tuning during system testing with water to the extent
possible.
4. Process area start-ups:
a. Process start-up individual process areas comprised of multiple
interdependent systems where possible and beneficial to reduce
complexity and risk of complete facility testing.
b. Process area test flows may be limited by upstream and downstream
process constraints (i.e., tank and basin volumes) and/or localized
recirculation capabilities.
5. Facility-wide process start-up:
a. Upon approved completion of pre-start-up activities, perform entire facility
process start-up:
1) Supplier shall complete control loop tuning during this phase of
process start-up.
2) Continue process start-up operations until facility meets or exceeds
the Contract requirements.
b. Process control systems testing:
1) Test complete system instrumentation, controls and PLC, HMI, and
LOI programming for the facility.
c. Remaining equipment/system tests:
1) Conduct remaining specified equipment/system performance tests
that could not be performed during the Testing and Training Phase
due to inter-system and/or treatment process dependencies.
C. Process Operational Period:
1. Prior to beginning the Process Operational Period:
March 2021 - DRAFT 01 75 17-14 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/01_75_17(IDS50)
Item#18.
a. Conformance with treatment standards is required prior to Operational
Testing, if applicable.
b. Correct any outstanding punchlist items that are related to process
operation prior to the Operational Testing.
2. Duration: 10 calendar days.
3. Engineer will be present for process operational period unless such presence
is expressly waived in writing.
4. Prove facility conformance with Contract Document requirements.
5. Contractor to provide:
a. Specified start-up materials and operating supplies.
b. Necessary craft of labor assistance, in the event of an emergency
equipment failure requiring immediate attention (emergency is defined as
a failure of function which precludes the further operation of a critical
segment of or the whole of the Work) with a response time of not more
than 4 hours from the time of notification.
c. Manufacturer's authorized representative to supervise placing
equipment/systems in operation and provide guidance during Operational
Testing per applicable Section.
d. Necessary manufacturer's representatives and operating supplies for
retesting systems that fail to pass the initial Operational Testing due to
deficiencies in products of workmanship at no additional cost to the
Owner.
e. List of 24-hour"on-call" representative supervisory persons who will
monitor the Operational Testing and serve as liaison for the Engineer and
Owner.
6. Owner will provide:
a. Operations personnel for duration of test.
b. Initial purchase of chemicals for Operational Period testing, meeting the
anticipated chemical use stated in the Specifications. Supplier to provide
any additional chemical required as a result of failed or delayed testing, at
no additional cost to Owner.
7. Prior to date of Substantial Completion of Installation, the following
construction coordination shall occur:
a. Owner staff will operate the completed Project construction.
b. Entire system shall continuously meet performance requirements and
shall operate without fault, failure, or defect for a continuous period.
c. Individual equipment/system failures that are corrected within 24 hours
and do not prevent the entire project from continuously satisfying the
established operational requirements shall not require the consecutive
day test to be restarted unless the failure recurs.
d. Restart the consecutive test period for any of the following conditions:
1) Any failure of the complete Project construction to meet operational
requirements.
2) When malfunctions or deficiencies cause shutdown or partial
operation of the facility, or results in failure of the complete Project
construction to meet operational requirements.
3) Any individual equipment/system failure that meets any of the
following conditions:
a) Requires more than 24 hours to correct, unless otherwise
specified in Section 40_80_01.
b) Recurs within the 24-hour correction period requiring further
correction.
March 2021 - DRAFT 01 75 17-15 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
4) Immediately correct defects in material, workmanship, or
equipment/system which became evident during Operational Testing.
PART PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
March 2021 - DRAFT 01 75 17-16 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
MANUFACTURER'S CERTIFICATE OF SOURCE TESTING
OWNER EQPT/SYSTEM
PROJECT NAME EQPT TAG NO.
PROJECT NO. EQPT SERIAL NO.
SPECIFICATION NO.
SPECIFICATION TITLE
Comments:
I hereby certify Source Testing has been performed on the above-referenced equipment/system
as defined in the Contract Documents, and results conform to the Contract Document
requirements. Testing data is attached.
Date of Execution: 20
Manufacturer:
Manufacturer's Authorized Representative Name (print):
(Authorized Signature)
If applicable, Witness Name (print):
(Witness Signature)
March 2021 - DRAFT 01 75 17-17 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
MANUFACTURER'S CERTIFICATE OF
INSTALLATION AND FUNCTIONALITY COMPLIANCE
OWNER EQPT/SYSTEM
PROJECT NAME EQPT TAG NO.
PROJECT NO. EQPT SERIAL NO.
SPECIFICATION NO.
SPECIFICATION TITLE
I hereby certify that the above-referenced equipment/system has been: (Check Applicable)
❑ Installed in accordance with manufacturer's recommendations.
❑ Inspected, checked, and adjusted.
❑ Serviced with proper initial lubricants.
❑ Electrical/instrumentation and mechanical connections meet quality and
safety standards.
❑ All applicable safety equipment has been properly installed.
❑ Functionally tested.
❑ System has been performance tested, and meets or exceeds specified
performance requirements.
NOTES:
Attach test results with collected data and test report.
Attach written certification report prepared by and signed by the electrical and/or
instrumentation subcontractor.
Comments:
I, the undersigned manufacturer's representative, hereby certify that I am (i) a duly authorized
representative of the manufacturer, (ii) empowered by the manufacturer to inspect, approve,
and operate this equipment/system, and (iii) authorized to make recommendations required to
ensure that the equipment/system furnished by the manufacturer is complete and operational,
except as may be otherwise indicated herein. I further certify that all information contained
herein is true and accurate.
Date: 20
Manufacturer:
Manufacturer's Authorized Representative Name (print):
By Manufacturer's Authorized Representative:
(Authorized Signature)
March 2021 - DRAFT 01 75 17-18 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
COMMISSIONING
TRAINING EVALUATION FORM
EQUIPMENT/SYSTEM ITEM:
VENDOR/MANUFACTURER:
DATE: NAME OF REPRESENTATIVE:
1. Was representative prepared? Acceptable Unacceptable or N/A
2. Was an overview description presented? Acceptable Unacceptable or N/A
3. Were specific details presented for system Acceptable Unacceptable or N/A
components?
4. Were alarm and shutdown conditions Acceptable Unacceptable or N/A
clearly presented?
5. Were step-by-step procedures for starting, Acceptable Unacceptable or N/A
stopping, and troubleshooting presented?
6. Were routine/preventative maintenance Acceptable Unacceptable or N/A
items clearly identified?
7. Was the lubrication schedule (if any) Acceptable Unacceptable or N/A
discussed?
8. Was the representative able to answer all Acceptable Unacceptable or N/A
questions?
9. Did the representative agree to research Acceptable Unacceptable or N/A
and answer unanswered questions?
10. Comments:
11. Overall Rating: Satisfactory Unsatisfactory
Note:
Sessions judged "Unsatisfactory" by a majority of attendees shall be revised and conducted
again until a satisfactory rating is achieved.
March 2021 - DRAFT 01 75 17-19 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_75_17(IDS50)
Item#18.
COMMISSIONING ROLES AND RESPONSIBILITIES MATRIX
NO. TASK OWNER CONTRACTOR ENGINEER
Testing and Training Phase
Source Testing
1 Source Testing Witness Lead Witness,
Review
Installation Testing
2 Electrical Conductor Testing No Action Lead Witness
3 Electrical Field Acceptance Tests No Action Lead Witness
4 Instrument Field Calibration No Action Lead Witness
5 Network Installation Testing Witness Lead Witness
6 Loop Testing Witness Lead Witness
7 Pressure Testing No Action Lead Witness
8 Leak Testing No Action Lead Witness
9 Holiday Testing No Action Lead Witness
10 HVAC Testing No Action Lead Witness
11 Motor Electrical Testing No Action Lead Witness
Functional Testing
12 Network Operational Testing Witness Lead Review
13 Preliminary Run Testing Local/Manual Control Witness Lead Review
14 PCIS Functional Demonstration Testing Witness Lead Review
- Local/Auto Control Testing
- Remote/Manual Contact Testing
-Alarm Testing
-Control Loop Testing
15 Subsystem Start-Up and Testing Witness Lead Review
16 Equipment/System Start-Up and Testing Witness Lead Review
17 HVAC Start-Up and Testing Witness Lead Review
18 Corrosion Control Start-Up and Testing Witness Lead Review
19 Wide Area Network Communications Testing Support Lead Witness
20 Manufacturer's Certificate of Installation and No Action Lead Witness,
Functionality Compliance Review
Clean Water Facility Testing
21 Test Water Management Plan Finalization Support Lead Review
22 Clean Water Facility Testing Witness Lead Witness,
Review
March 2021 - DRAFT 01 75 17-20 11700A1
pwalCarollolDocumentslClient/IDIMeridian/11700A101Specifcations/Pre-Purchasel01_75_17(I1DS50)
Item#18.
NO. TASK OWNER CONTRACTOR ENGINEER
Process Start-Up Phase
Process Start-Up
23 Commissioning Documentation and Data Review Review Lead Review
24 Start-Up Go/No-Go Decision Criteria Lead Support Review
25 Building and Fire Inspection Compliance Check No Action Lead Witness
26 HVAC Functionality Check No Action Lead Witness
27 Start-Up Sequence Review Support Lead Review
28 Temporary Testing Arrangement Finalization Support Lead Support
29 Start-Up Forms Finalization Support Lead Support
30 Operation Testing Plan Finalization Review Support Lead
31 Test Water Management Plan Finalization Support Lead Review
32 System Testing Support Lead Witness
33 Control Loop Tuning Support Lead Witness
34 Process Area Start-Ups Lead Support Witness
35 Facility-Wide Start-Up Lead Support Witness
36 Process Control Systems Testing Support Lead Witness
38 HVAC Final Testing,Adjust, and Balancing Witness Lead Witness,
Review
Process Operational Period
39 Operational Testing Support Lead Witness
40 Final Testing Reports Support Lead Review
41 Water Quality Testing and Documentation Support Lead Review
Instrumentation and Controls Reliability Phase
Instrumentation and Controls Reliability Period
42 As specified in Section 40_80_01
Legend:
Lead: Primarily responsible for organization, coordination, and execution of task work product or result.
Support: Assist the lead with organization, coordination, and execution of task work product or result.
Witness: Observe and document completion of task work product or result.
Review: As necessary to accept task work product result.
No Action: Limited or no involvement.
Notes: Responsibilities can be modified via coordination between Owner, Contractor, and Engineer.
Responsibilities are project specific.
March 2021 - DRAFT 01 75 17-21 11700A1
pwalCarollolDocumentslClient/IDIMeridian/11700A101Specifcations/Pre-Purchasel01_75_17(IDS50)
Item#18.
SECTION 01_78_23
OPERATION AND MAINTENANCE DATA
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Preparation and submittal of Operation and Maintenance
Manuals.
B. Related sections:
1. Section 46_05_94 - Mechanical Equipment Testing.
1.02 SUBMITTALS
A. Submit Operation and Maintenance Manuals before field quality control testing and
before training of each piece of equipment or system.
B. Submit manuals for each piece of equipment or system:
1. Submit Manuals electronically until all comments from Owner and Engineer
have been incorporated. Indicate section and tab divisions on electronic
Manuals.
2. Provide one (1) hard copy and one (1) electronic copy in .pdf format of final
manuals.
3. Make manuals available at project site for use by construction personnel and
Owner.
4. Make additions and revisions to the Manuals in accordance with Owner's
review comments.
1.03 OPERATION AND MAINTENANCE MANUALS
A. Preparation:
1. Provide Operations and Maintenance Manuals in 3-ring binders with rigid
covers. Utilize numbered tab sheets to organize information.
2. Provide original and clear text on reproducible non-colored paper.
3. Provide all dimensions in English units.
4. Coordinate with Contractor to define Operations and Maintenance Manual
compliance with Owner's Computer Maintenance Management System
(CMMS).
B. Contents of Operation and Maintenance Manuals:
1. Cover page: Equipment name, equipment tag number, project name, Owner's
name, appropriate date. Manufacturer's name, address, phone number, and
email address. Local Representative's name, address, phone number, and
email address. Contractor's name, address, phone number, and email
address. Spare Parts Supplier name, address, phone number, and email
address.
2. Table of Contents: General description of information provided within each tab
section.
March 2021 - DRAFT 01_78_23-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_78_23(IDS50)
Item#18.
3. Equipment Summary Form: Completed form in the format shown in
Appendix A. The manufacturer's standard form will not be acceptable.
4. Instrumentation Data Sheet.
5. Information from submittal that specifically applies to that equipment
— i.e., pump curves, shop drawing with final dimensions.
6. Lubrication information: Required lubricants and lubrication schedules.
7. Control diagrams:
a. Internal and connection wiring, including logic diagrams, wiring diagrams
for control panels, ladder logic for computer-based systems, and
connections between existing systems and new additions, and
adjustments such as calibrations and set points for relays, and control or
alarm contact settings.
b. Complete set of control schematics.
8. Programming: Copies of all Contractor furnished programming.
9. Start-up procedures: Recommendations for installation, adjustment,
calibration, and troubleshooting.
10. Operating procedures:
a. Step-by-step procedures for starting, operating, and stopping equipment
under specified modes of operation.
b. Include safety precautions and emergency operating shutdown
instructions.
11. Preventative maintenance procedures: Recommended steps and schedules
for maintaining equipment.
12. Overhaul instructions: Directions for disassembly, inspection, repair, and
reassembly of the equipment; safety precautions; and recommended
tolerances, critical bolt torques, and special tools that are required.
13. Parts list:
a. Complete parts list for all equipment being provided.
Catalog data for all products or equipment furnished including generic title
and identification number of each component part of equipment:
1) Include bearing manufacturer, model and ball or roller pass
frequencies for every bearing.
14. Spare parts list: Recommended number of parts to be stored at the site and
special storage precautions.
15. Drawings:
a. Exploded view or plan and section views with detailed callouts.
b. Provide electrical and instrumentation schematic record drawings.
16. Source (factory) quality control test results: Provide copies of factory test
reports as specified in Section 46_05_94 or the equipment section.
17. Field quality control test results: After field-testing is completed, insert field test
reports as specified in Section 46_05_94 or the equipment section.
18. Control Description and Final Start-Up checklist, plus any tests completed by
the manufacturer.
19. Certificate of proper installation.
PART PRODUCTS
Not Used.
March 2021 - DRAFT 01_78_23-2 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_78_23(IDS50)
Item#18.
PART 3 EXECUTION
Not Used.
END OF SECTION
March 2021 - DRAFT 0 78 23-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_78_23(IDS50)
Item#18.
APPENDIX A
EQUIPMENT SUMMARY FORM
1. EQUIPMENT ITEM
2. EQUIPMENT P&ID TAG NUMBER(S)
(maps equipment number)
3. LOCATION OF EQUIPMENT
4. Make, Model, Serial No.
5. NAMEPLATE DATA
Manufacturer
Horsepower
Amperage
Voltage
Service Factor (S.F.)
Speed
ENC Type
Capacity
Other
6. MANUFACTURER'S LOCAL REPRESENTATIVE
Manufacturer
Name
Address
Telephone Number
7. MAINTENANCE REQUIREMENTS (include page number inside O&M)
8. LUBRICANT LIST (include page number inside O&M)
9. SPARE PARTS (recommendations) (include page number inside O&M)
10. COMMENTS
March 2021 - DRAFT 0 78 23-4 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_78_23(IDS50)
Item#18.
SECTION 01_78_36
WARRANTIES AND BONDS
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Warranty and bonds requirements.
1.02 SUBMITTALS
A. For each item of material or equipment furnished under the Contract:
1. Submit form of manufacturer's warranty prior to fabrication and shipment of the
item from the manufacturer's facility.
2. Submit form of manufacturer's special warranty when specified.
B. Provide consolidated warranties and bonds within 15 calendar days of Substantial
Completion:
1. Contents:
a. Organize warranty and bond documents:
1) Include Table of Contents organized by specification Section number
and the name of the product or work item.
b. Include each required warranty and bond in proper form, with full
information, are certified manufacturer as required, and are properly
executed by Contractor, or subcontractor, supplier, or manufacturer.
c. Provide name, address, phone number, and point of contact of
manufacturer, supplier, and installer, as applicable.
2. Hardcopy format:
a. Submit 2 copies.
b. Assemble in 3 D-side ring binders with durable cover.
c. Identify each binder on the front and spine with typed or printed title
"Warranties and Bonds"; Project Name or Title, and the Name Address
and Telephone Number of the Contractor.
3. Electronic copy in PDF format:
a. Submit 1 copy.
1.03 OWNER'S RIGHTS
A. Owner reserves the right to reject warranties.
B. Owner reserves the right to refuse to accept Work for the project if the required
warranties have not been provided.
1.04 RELATIONSHIP TO GENERAL WARRANTY AND CORRECTION PERIOD
A. Warranties specified for materials and equipment shall be in addition to, and run
concurrent with, both Contractor's general warranty and the correction period
requirements.
March 2021 - DRAFT 01_78_36-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_78_36(IDS50)
Item#18.
B. Disclaimers and limitations in specific materials and equipment warranties do not
limit Contractor's general warranty, nor does such affect or limit Contractor's
performance obligations under the correction period.
1.05 MANUFACTURER'S WARRANTY MINIMUM REQUIREMENTS
A. Written warranty issued by item's manufacturer.
B. Project-specific information, properly executed by product manufacturer, and
expressly states that its provisions are for the benefit of the Owner.
C. Covers all costs associated with the correction of the defect, including but not
limited to removal of defective parts, new parts, labor, and shipping:
1. When correcting warranted Work that has failed, remove and replace other
Work that had been damaged as a result of such failure or that must be
removed and replaced to provide access for correction of warranted Work.
D. Provides a timely response to correct the defect:
1. Manufacturer shall provide, in a timely fashion, temporary equipment as
necessary to replace warranted items requiring repair or replacement, when
warranted items are in use and are critical to the treatment process, as defined
by Owner.
2. In the case that Owner has to provide temporary equipment to replace function
of warranted item requiring repair or replacement, manufacturer shall
reimburse Owner for such costs associated with the temporary equipment.
E. Warranty commence running on the date of final completion:
1. For items of Work for which acceptance is delayed beyond Date of Final
Completion, submit warranty within 10 calendar days after acceptance, listing
date of acceptance as beginning of warranty period.
F. Duration of Warranty: 2 years.
1.06 MANUFACTURER'S SPECIAL WARRANTY
A. Manufacturer's special warranty is a written warranty published by the manufacturer
which includes the requirements specified in the Section where the item is specified:
1. Includes Project-specific information and requirements, properly executed by
product manufacturer, and expressly states that its provisions are for the
benefit of the Owner. Technical sections indicate Project-specific requirements
that differ from the minimum warranty requirements for that item:
a. Examples include extending the duration of manufacturer's warranty or to
provide increased rights to Owner.
2. Manufacturer's warranties commence on the date that the Project is certified
by Engineer as finally complete.
1.07 WARRANTY WORK
A. Contractor's responsibilities:
1. Manufacturer's disclaimers and limitations on product warranties do not relieve
the Contractor of the warranty on the work that incorporates the product, nor
does it relieve suppliers, manufacturers, and subcontractors required to
countersign special warranties with Contractor.
March 2021 - DRAFT 01_78_36-2 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_78_36(IDS50)
Item#18.
B. Replacement cost:
1. Upon determination that work covered by warranty has failed, replace or
rebuild the work to an acceptable condition complying with requirement of the
Contract Documents:
a. Contractor is responsible for the cost of replacing or rebuilding defective
work regardless of whether Owner has benefited from the use of the work
through a portion of its anticipated useful service life.
C. Related damages and losses:
1. When correcting warranted work that has failed, remove and replace other
work that has been damaged as a result of such failure or that must be
removed and replaced to provide access for correction of warranted work.
D. Owner's recourse:
1. Written warranties are in addition to implied warranties, and shall not limit the
duties, obligations, rights, and remedies otherwise available under the law, nor
shall warranty periods be interpreted as limitation on time in which Owner can
enforce such other duties, obligations, rights, or remedies.
E. Reinstatement of warranty:
1. When work covered by a warranty has failed and has been corrected by
replacement or rebuilding, reinstate the warranty by written endorsement:
a. The reinstated warranty shall be equal to the original warranty with an
equitable adjustment for depreciation.
1.08 IMPLIED WARRANTIES
A. Warranty of title and intellectual rights:
1. Except as may be otherwise indicated in the Contract Documents, implied
warranty of title required by Laws and Regulations is applicable to the Work
and to materials and equipment incorporated therein.
2. Provisions on intellectual rights, including patent fees and royalties, are in the
General Conditions, as may be modified by the Supplementary Conditions.
B. Implied warranties: Duration in accordance with Laws and Regulations.
1.09 BONDS
A. Bond requirements as specified in the Agreement between Owner and Supplier.
PART PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
END OF SECTION
March 2021 - DRAFT 01_78_36-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_78_36(IDS50)
Item#18.
SECTION 01_81_01
PROJECT DESIGN CRITERIA
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Criteria for use in selection of equipment and appurtenances specified in
subsequent Sections of these Specifications, or on the Drawings.
2. Criteria for design of tanks and other equipment fabricated off site and shipped
to the Work for installation.
3. Criteria for use in design of anchors for connecting process, mechanical and
electrical equipment and appurtenances to supporting structures.
B. The criteria included in this Section are general criteria that apply throughout the
Work unless more restrictive or more stringent criteria are indicted on the Drawings
or in technical Specifications. See Drawings and Specifications for additional criteria
relevant to specific locations, materials and equipment.
C. Related sections:
1. Section 46_63_83.01 - Phosphorous Precipitation System.
1.02 REFERENCES
A. American Society of Civil Engineers (ASCE):
1. 7-10 - Minimum Design Loads for Buildings and Other Structures (ASCE 7).
B. ASHRAE, Incorporated (ASHRAE).
C. International Code Council (ICC):
1. International Building Code (IBC).
2. International Energy Conservation Code (IECC).
3. International Fire Code (IFC).
4. International Fuel Gas Code (IFGC).
5. International Mechanical Code (IMC).
D. Sheet Metal and Air Conditioning Contractor's National Association (SMACNA):
1. Seismic Restraint Manual: Guidelines for Mechanical Systems,
3rd edition - 2008.
1.03 SUBMITTALS
A. Design of supports and anchorage for structures:
1. Shop drawings and calculations:
a. Complete shop drawings and calculations.
b. Calculations shall be signed and sealed by a Professional Engineer
licensed in the State of Idaho.
March 2021 - DRAFT 01 81 01-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_81_01(IDS50)
Item#18.
2. Seismic design calculations:
a. Where seismic design calculations are specified in this Specification, such
requirements will be waived for structures or equipment determined to be
in Seismic Design Category A.
3. Wind design calculations:
a. Where wind design calculations are specified in this Specification, such
requirements will be waived for structures or equipment located inside
other structures.
1.04 PROJECT DESIGN CRITERIA - SITE INFORMATION
A. Location:
1. Address: 3401 North Ten Mile Road, Meridian, ID 83646.
2. Site coordinates (approximate): Latitude 43.637829 N; Longitude -
116.437424W.
B. Elevation:
1. Operating elevation for equipment: 2,551 feet above mean sea level
(approximate).
1.05 PROJECT DESIGN CRITERIA - REGULATORY REQUIREMENTS
A. Building Codes:
1. Building Code:
a. International Building Code (IBC), 2015.
2. Electrical code:
a. National Electrical Code (NEC), 2017.
3. Energy code:
a. International Energy Conservation Code (IECC), 2015.
4. Fire code:
a. Idaho Fire Code (IFC), 2015.
5. Fuel gas code:
a. International Fuel Gas Code (IFGC), 2012.
6. Mechanical code:
a. International Mechanical Code (IMC), 2012.
7. Plumbing code:
a. 2017 Idaho State Plumbing Code.
1.06 PROJECT DESIGN CRITERIA - OPERATING ENVIRONMENT
A. Equipment and materials for the Work shall be suitable for performance in a
wastewater treatment plant environment, and under conditions specified in the
following paragraphs:
1. See technical specifications for each type of equipment for additional
requirements.
1.07 PROJECT DESIGN CRITERIA - STRUCTURAL
A. Scope:
1. These paragraphs provide criteria for structural design of submittal items such
as stairs and platforms, equipment, equipment supports and bracing, and
attachment or anchorage of such items to building and non-building structures.
March 2021 - DRAFT 01 81 01-2 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_81_01(IDS50)
Item#18.
2. Design criteria for individual structures are indicated on the General Structural
Notes Drawing and the Contract Drawings for each structure.
3. Specifications for manufactured or prefabricated structures may include design
criteria in addition to the items in this Section.
B. Design in accordance with requirements of the following:
1. The building code specified in this section.
2. ASCE 7-10.
3. Specific project requirements listed in the following paragraphs.
C. Structure description and risk category.
1. Determine importance factors, develop design loads, and provide detailing in
accordance with the provisions of ASCE 7 based on structure description, risk
category indicated in Table 3:
Table 3: Project Structures - Risk Categories(')
Description Risk Category(')
Side Stream Treatment Building III
Phosphorus Precipitation System Reactors III
Other equipment and project components not specifically III
listed
Notes:
(1) Categories are based on and for use with ASCE 7 unless otherwise noted.
D. Groundwater design criteria:
1. Design groundwater elevation: Approximately 3 feet below grade. (See project
geotechnical report for groundwater elevations at specific boring locations.)
E. Flood design criteria:
1. FEMA Flood Insurance Rate Map Zone X— "Other Flood Areas".
(Map No. 16001 C0139 H, Panel 139 of 875.)
F. Wind design criteria (for structures and for equipment located outdoors or under
open canopies):
1. Basic wind speed:
a. Velocity = 120 miles per hour (33 feet, 3-second gust).
2. Exposure category: C.
3. Topographic factor, KZt: 1.0.
4. Wind pressure for design of"components and cladding":
a. Calculated per building code based on criteria in this Section.
b. Use maximum pressure on any wall for all components at the building.
c. Includes pressure for design of doors, windows, siding panels and other
elements.
G. Seismic design criteria:
1. Design spectral response acceleration, 5 percent damped:
a. Short period, SS = 0.290g.
b. One second period, S, = 0.106g.
March 2021 - DRAFT 01 81 01-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_81_01(IDS50)
Item#18.
2. Seismic Design Category:
a. As indicated on the Drawings for each structure (by area) and in Table 4.
Table 4: Project Structures - Seismic Design Categories
Structures and Buildings Seismic Design
(by Drawing Area Number) Category(')
Structures founded on Site Class D soils('):
NA All Buildings and Equipment included in the Work C
Notes:
(1) Categories are based on and for use with ASCE 7 unless otherwise noted.
3. Mechanical and electrical equipment, including equipment supports and
anchorage to structures or foundations, and including associated distribution
systems such as piping, ductwork, conduits, cable trays, bus ducts, etc.:
a. Design in accordance with the provisions of ASCE 7-10, Chapter 13,
except as modified herein.
b. Seismic design category B exemptions:
1) Exemptions in ASCE 7, paragraph 13.1.4 for anchoring and bracing
of mechanical, and electrical components in Seismic Design
Category B are permitted for this Work.
c. Component amplification factor (ap) and component response modification
factor (Rp): In accordance with ASCE 7, Table 13.6-1.
d. Overstrength factor for anchorage to concrete (0.): In accordance with
ASCE 7, Table 13.6-1.
e. Component importance factor, Ip: In accordance with the provisions of
ASCE 7, Chapter 13 unless otherwise specified in Table 5 of this Section.
Table 5: Mechanical and electrical equipment, Component importance factor, Ip
Component Description Ip
Electrical Equipment and appurtenances provided and 1.5
installed under Divisions 26 and 40.
Mechanical (HVAC) Equipment and appurtenances provided and 1.0
installed under Division 40.
Process Equipment and appurtenances provided and 1.0
installed under Divisions 43 and 46.
f. "Statement of seismic qualification" or"special seismic certification":
1) Requirements are based on the Seismic Design Category (SDC) of
the facility where the equipment is installed.
4. Tanks, including pre-fabricated tank structures, tank supports, and anchorage
to structures or foundations:
a. Consider impulsive and convective "sloshing" effects.
b. Component response modification factor for impulsive effects, RI: In
accordance with ASCE 7, Table 15.4-2.
c. Component response modification factor for convective effects, R, = 1.0.
March 2021 - DRAFT 01 81 01-4 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_81_01(IDS50)
Item#18.
d. Component importance factor, le: Determine in accordance with ASCE 7,
Section 15.4.1.1.
e. Seismic design category ("SDC"):
1) See Table 4 of this Section.
H. Snow design criteria for structures and for equipment located outdoors):
1. Ground snow load: pg = 20 pounds per square foot.
2. Exposure factor, minimum: C.= 1.0 (partially exposed).
3. Thermal factor, minimum: Ct = 1.0 (all structures except structures kept just
above freezing and cold, ventilated roofs, unheated and open air structures,
structures kept below freezing, and continuously heated greenhouses).
4. Importance factor, minimum: Based on risk category of the structure where the
equipment is located.
5. Minimum snow load, pm = 25 pounds per square foot.
I. Atmospheric icing design criteria (for structures and for equipment located
outdoors):
1. Equivalent radial/nominal uniform ice thickness: 0.25 inch /40 miles per hour
wind.
2. Ice density for calculating ice weight, minimum: 56 pounds per cubic foot.
3. Importance factor, minimum: Based on risk category of the structure adjacent
to the equipment.
PART PRODUCTS
2.01 GENERAL
A. Equipment and materials for the project shall be suitable for the following
conditions:
1. Wastewater treatment plant conditions.
2. Site, environmental and structural loading conditions as specified in this
Section.
3. Specific conditions listed in the relevant sections of the Contract Documents
for the equipment and products under consideration.
B. Anchoring and fastening: See the following Sections for materials and installation
requirements.
PART 3 EXECUTION
3.01 GENERAL
A. Design in accordance with the requirements of the building code and the references
and project-specific design criteria listed in this Section.
B. In the event of conflicts between design criteria, the more restrictive or severe shall
govern.
March 2021 - DRAFT 01 81 01-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_81_01(IDS50)
Item#18.
3.02 DESIGN OF SUPPORTS AND ANCHORAGE FOR EQUIPMENT AND TANKS.
A. General:
1. Anchor bolts used to resist seismic loads and wind forces shall have a
standard hex bolt head.
a. Do not use anchor bolts fabricated from rod stock with an L or J shape.
b. Do not use post-installed anchors (including concrete anchors, sleeve
anchors, flush shells, chemical anchors, powder actuated fasteners, or
other types of anchor) unless indicated on the Drawings or accepted in
writing by the Engineer.
2. Anchor bolt and fastener calculations:
a. Design for ductile failure (anchor bolt yield).
b. Anchor bolts and fasteners embedded cast into plastic concrete or
installed into cured concrete:
1) Design based on a minimum specified 28-day concrete compressive
strength of 4,000 pounds per square inch (f'c = 4,000 psi).
B. Seismic loads:
1. Do not use friction to resist sliding resulting from seismic forces. Resist such
forces only by direct application of loads to fasteners as bearing, shear,
tension, or compression force(s).
2. Do not use more than 60 percent of the weight of the mechanical and electrical
equipment for designing anchors for resisting overturning due to seismic
forces.
3. For tanks and equipment with varying weight based on the volume of material
contained, design anchorage to accommodate both filled and empty
conditions:
a. Do not use more than 60 percent of the weight of the tank for resisting
overturning due to seismic forces.
C. Wind loads:
1. Design load combinations shall be as specified in ASCE 7.
2. For tanks and equipment with varying weight based on volume of material
contained, evaluate anchorage considering both filled and empty conditions.
END OF SECTION
March 2021 - DRAFT 01 81 01-6 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel01_81_01(IDS50)
Item#18.
SECTION 05_12_00
STRUCTURAL STEEL
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Structural steel shapes and plate.
2. Fasteners:
a. All thread rods.
b. Assembly bolts.
c. High strength bolts.
d. Powder actuated fasteners.
3. Isolation sleeves and washers.
4. Thread coating.
5. Welding.
1.02 REFERENCES
A. American Institute of Steel Construction (AISC):
1. 303-05 - Code of Standard Practice for Steel Buildings and Bridges.
2. 360-05 - Specification for Structural Steel Buildings.
B. American Iron and Steel Institute (AISI):
1. Steel and stainless steel alloys ("types") as indicated.
C. American National Standards Institute (ANSI):
1. B212-15 - Cutting Tools - Carbide-tipped Masonry Drills and Blanks for
Carbide-tipped Masonry Drills.
D. ASTM International (ASTM):
1. A6 - Standard Specification for General Requirements for Rolled Structural
Steel Bars, Plates, Shapes and Sheet Piling.
2. A36 - Standard Specification for Carbon Structural Steel.
3. A53 - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-
Coated, Welded, and Seamless.
4. A108 - Standard Specification for Steel Bars, Carbon and Alloy, Cold Finished.
5. A123 - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron
and Steel Products.
6. A153 - Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware.
7. A193 - Standard Specification for Alloy Steel and Stainless Steel Bolting
Materials for High-Temperature or High Pressure Service and Other Special
Purpose Applications.
8. A240 - Standard Specification for Chromium and Chromium-Nickel Stainless
Steel Plate, Sheet, and Strip for Pressure Vessels and for General
Applications.
9. A276 - Standard Specification for Stainless Steel Bars and Shapes.
March 2021 - DRAFT 05 12 00-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_00(IDS50)
Item#18.
10. A307 - Standard Specification for Carbon Steel Bolts and Studs, 60,000 psi
Tensile Strength.
11. A325 - Standard Specification for Structural Bolts, Steel, Heat Treated,
120/105 ksi Minimum Tensile Strength.
12. A380 - Standard Practice for Cleaning, Descaling, and Passivation of Stainless
Steel Parts, Equipment, and Systems.
13. A489 - Standard Specification for Carbon Steel Lifting Eyes.
14. A490 - Standard Specification for Structural Bolts, Alloy Steel, Heat Treated,
150 ksi Minimum Tensile Strength.
15. A496 - Standard Specification for Steel Wire, Deformed, for Concrete
Reinforcement.
16. A500 - Standard Specification for Cold-Formed Welded and Seamless Carbon
Steel Structural Tubing in Rounds and Shapes.
17. A501 - Standard Specification for Hot-Formed Welded and Seamless Carbon
Steel Structural Tubing.
18. A992 - Standard Specification for Structural Steel Shapes.
19. B633 - Standard Specification for Aluminum-Alloy Rolled Tread Plate.
20. E94 - Standard Guide for Radiographic Examination.
21. E164 - Standard Practice for Contact Ultrasonic Testing of Weldments.
22. E165 - Standard Practice for Liquid Penetrant Examination for General
Industry.
23. E709 - Standard Guide for Magnetic Particle Testing.
24. E1032 - Standard Test Method for Radiographic Examination of Weldments.
25. F436 - Standard Specification for Hardened Steel Washers.
26. F593 - Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and
Studs.
27. F959 - Standard Specification for Compressible-Washer-Type Direct Tension
Indicators for Use with Structural Fasteners.
28. F1554 - Standard Specification for Anchor Bolts, Steel, 36, 55 and 105-ksi
Yield Strength.
E. American Welding Society (AWS):
1. A 5.1 - Specification for Carbon Steel Electrodes for Shielded Metal Arc
Welding.
2. A 5.17 - Specification for Carbon Steel Electrodes and Fluxes for Submerged
Arc Welding.
3. A 5.20 - Specification for Carbon Steel Electrodes for Flux Cored Arc Welding.
4. D 1.1 - Structural Welding Code - Steel.
5. D 1.6 - Structural Welding Code - Stainless Steel.
6. D 10.4 - Recommended Practices for Welding Austenitic Chromium-Nickel
Stainless Steel Piping and Tubing.
F. International Code Council Evaluation Service, Inc. (ICC-ES):
1. AC01 - Acceptance Criteria for Expansion Anchors in Masonry Elements.
2. AC58 - Acceptance Criteria for Adhesive Anchors in Masonry Elements.
3. AC193 - Acceptance Criteria for Mechanical Anchors in Concrete Elements.
4. AC308 - Acceptance Criteria for Post-Installed Adhesive Anchors in Concrete
Elements.
G. Occupational Safety and Health Administration (OSHA):
1. Code of Federal Regulations, Title 29 - Labor, Chapter XVI I.
a. Part 1926 - Safety and Health Regulations for Construction.
March 2021 - DRAFT 05 12 00-2 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_00(IDS50)
Item#18.
H. Research Council on Structural Connections (RCSC)
(c/o American Institute of Steel Construction):
1. Specification for Structural Joints Using ASTM A325 or A490 Bolts.
I. Steel Structures Painting Council (SSPC):
1. SP1 - Solvent Cleaning.
2. SP7 - Brush-off Blast Cleaning.
3. SP10 - Near White Abrasive Blasting.
4. SP11 - Power Tool Cleaning to Bare Metal.
1.03 DEFINITIONS
A. All thread rod: Straight steel rod continuously threaded from end to end.
B. Anchor bolt: Straight steel rod embedded in concrete and having one integrally
forged headed end and one threaded end. Installed with headed end cast into
concrete with embedment as indicated on the Drawings or specified, leaving
threaded end projecting clear of concrete face as required for the connection to be
made.
C. Anchor rod: Straight steel rod embedded in concrete and having threads on each
end. Fit threaded end to be embedded in concrete with nuts or plates as indicated
on the Drawings and providing embedment as indicated on the Drawings or
specified. Leave threaded end projecting clear of the concrete face as required for
the connection to be made.
D. Cast-in anchor: Fastener or assembly installed in position before placing plastic
concrete or installing masonry units and grout around the anchor.
E. Passivation: Removal of exogenous iron or iron compounds from the surface of a
stainless steel by means of a chemical dissolution resulting from treatment with an
acid solution that removes the surface contamination but does not significantly
affect the stainless steel itself.
F. Wet and moist locations: When used with reference to anchors and fasteners,
locations that are subject to deterioration and corrosion. Includes:
1. Liquid-containing structures:
a. Locations at or below the maximum operating liquid surface elevation.
b. Locations above the maximum operating liquid surface elevation and:
1) below the top of the walls containing the liquid; and
2) at the underside of a structure (including roofs, slabs, beams or
walkways) spanning over the liquid.
2. Bases of pumps and equipment that handles liquids.
3. Indoor locations exposed to moisture or splashing during normal operations.
1.04 SUBMITTALS
A. General: Submit in accordance with Section 01 33 00.
B. Quality control submittals:
1. Fabricator shall submit evidence of AISC Quality Certification.
2. Submit shop drawings of members to be fabricated before starting their
fabrication.
March 2021 - DRAFT 05 12 00-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_00(IDS50)
Item#18.
C. Test reports:
1. Certified copies of mill tests and analyses made in accordance with applicable
ASTM standards or reports from a recognized commercial laboratory,
including chemical and tensile properties of each shipment of structural steel
or part thereof having common properties.
2. For each type of post-installed anchor to be included in the Work, current
International Code Council ES Report (ICC-ES) demonstrating conformance to
the Acceptance Criteria (AC) indicated for that anchor.
1.05 QUALITY ASSURANCE
A. Qualifications:
1. The fabricator shall participate in the AISC Quality Certification Program and
shall be designated an AISC-Certified Plant, Category STD at the time of bid.
2. Perform welding of structural metals with welders who have current American
Welding Society certificate for the type of welding to be performed.
3. Notify Engineer at least 24 hours minimum before starting shop or field
welding.
4. Engineer may check materials, equipment, and qualifications of welders:
a. Remove welders performing unsatisfactory Work, or require
re-qualification.
5. In addition to specified Quality Control testing by the Contractor, Engineer may
request that Contractor's testing laboratory use gamma ray, magnetic particle,
dye penetrant, trepanning, or other aids to visual inspection to examine any
part of welds or all welds.
6. Contractor shall bear costs of retests on defective welds.
7. Contractor shall also bear costs in connection with qualifying welders.
B. Regulatory requirements:
1. Conform to OSHA requirements for steel erection.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Packing and shipping: Deliver structural steel free from mill scale, rust, and pitting.
B. Storage and protection: Until erection and painting, protect from weather items not
galvanized or protected by a shop coat of paint.
PART2 PRODUCTS
2.01 MATERIALS
A. Unless otherwise specified or indicated on the Drawings, materials shall conform to
the following:
March 2021 - DRAFT 05 12 00-4 11700A10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_00(IDS50)
Item#18.
Table 05 12 00-A: Steel materials
Class, Grade, Type,
Item ASTM Standard or Alloy Number
Steel
Plate, bars, rolled shapes, and A 36 --
miscellaneous items (except W and
WT shapes)
Rolled W and WT shapes A 36 or A 992 Grade 50
Tubing, cold-formed A 500 --
Tubing, hot-formed A 501 --
Round HSS A 500 Grade B
Steel pipe A 53 Grade B
Stainless steel
Plate, sheet, and strip A 240 Type 316*
Bars and shapes A 276 Type 316*
* Use Type 316L if material will be welded.
2.02 FASTENERS
A. General: Furnish threaded fasteners, except high strength bolts, with flat washers,
and self-locking nuts, or lock washers and nuts:
1. Bolt heads and nuts: Hex-type.
2. Bolts, nuts, and washers: Of domestic manufacture.
B. Materials:
1. Provide stainless steel or galvanized steel fasteners based on exposure
conditions listed in the following paragraphs:
2. Stainless steel: For use at the following locations, unless otherwise noted:
a. At locations indicated on the Drawings.
b. At "wet and moist locations" as defined herein, unless otherwise noted.
c. For connecting aluminum or stainless steel to concrete or masonry.
3. Galvanized:
a. For use at all locations not requiring stainless steel.
b. Where bolts, including anchor bolts, nuts, washers, and similar fasteners
are specified to be galvanized, galvanize in accordance with ASTM A153.
C. All thread rods (includes all thread rods epoxy bonded into concrete as specified in
Section 03_21_17 and as indicated on the Drawings:
1. Description.
2. Materials:
a. Stainless steel: Type 316 stainless steel conforming to ASTM F593.
b. Galvanized: ASTM A36 galvanized in accordance with ASTM A123.
D. Assembly bolts:
1. Description: Bolts, nuts, and washers for connections in wood or fiberglass-
reinforced plastic baffles, collectors, and other field-assembled construction.
March 2021 - DRAFT 05 12 00-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_00(IDS50) Page 594
Item#18.
2. Materials:
a. Stainless steel: Type 316 stainless steel in accordance with ASTM F593.
Galvanized: ASTM A307.
E. High strength bolts:
1. Description: Steel bolts, nuts and washers for steel-to-steel connections
between structural steel framing members.
2. Acceptance criteria:
a. Conform to the requirements of ASTM A325 or ASTM A490, as indicated
on the Drawings.
b. At pre-tensioned and slip-critical joints, provide:
1) Direct-tension-indicator washers conforming to the requirements of
ASTM F959.
2) Flat washers conforming to ASTM F436 behind the element being
turned for tightening.
3. Materials:
a. Hot-dip galvanized.
b. Carbon steel.
F. Powder actuated fasteners:
1. Do not use unless directed by the Engineer.
2.03 ISOLATING SLEEVES AND WASHERS
A. Manufacturers: One of the following or equal:
1. Central Plastics Company, Shawnee, Oklahoma.
2. Corrosion Control Products, PSI Inc., Gardena, CA.
B. Sleeves: Mylar, 1/32 inch thick, 4,000 volts per mil dielectric strength, of proper size
to fit bolts and extending halfway into both steel washers:
1. One sleeve required for each bolt.
C. Washers: The inside diameter of all washer shall fit over the isolating sleeve and
both the steel and isolating washers shall have the same inside diameter and
outside diameter:
1. Proper size to fit bolts. Two insulating washers are required for each bolt.
2. Two 1/8-inch thick steel washers for each bolt.
3. G3 phenolic:
a. Thickness: 1/8 inch.
b. Base material: Glass.
c. Resin: Phenolic.
d. Water absorption: 2 percent.
e. Hardness (Rockwell): 100.
f. Dielectric strength: 450 volts per mil.
g. Compression strength: 50,000 pounds per square inch.
h. Tensile strength: 20,000 pounds per square inch.
i. Maximum operating temperature: 350 degrees Fahrenheit.
2.04 GALVANIZED SURFACE REPAIR
A. Manufacturers: One of the following or equal:
1. Galvinox.
2. Galvo-Weld.
March 2021 - DRAFT 05 12 00-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/05_12_00(IDS50) Page 595
Item#18.
2.05 THREAD COATING
A. Manufacturers: One of the following or equal:
1. Never Seez Compound Corporation, Never-Seez.
2. Oil Research, Inc., WLR No. 111.
2.06 SUPPLEMENTARY PARTS
A. Furnish as required for complete structural steel erection, whether or not such parts
and Work are specified or indicated on the Drawings.
2.07 FABRICATION
A. Shop assembly:
1. Fabricate structural steel in conformance with AISC 303 and AISC 360 unless
otherwise specified or modified by applicable regulatory requirements.
2. Where anchors, connections, or other details of structural steel are not
specifically indicated on the Drawings or specified, their material, size and
form shall be equivalent in quality and workmanship to items specified.
3. Round off sharp and hazardous projections and grind smooth.
4. Take measurements necessary to properly fit work in the field. Take
responsibility for and be governed by the measurements and proper working
out of all the details.
5. Take responsibility for correct fitting of all work.
B. Stainless steel shapes and assemblies:
1. For structural members such as W shapes, S shapes, channels, angles, and
similar rolled shapes not available in quantity, size, and type of stainless steel
specified or indicated on the Drawings:
a. Make full penetration welds between pieces of plate to attain same or
higher section modulus and moment of inertia as members indicated on
the Drawings.
b. Fabricate shapes using laser-fused full penetration joints. Fabricate
shapes from dual grade stainless steel. Fabricate beams and channels to
ASTM A6 tolerances:
1) Manufacturers: One of the following, or equal:
a) Stainless Structurals, LLC; Jacksonville FL.
2. Cleaning and passivation:
a. Following shop fabrication of stainless steel members, clean and
passivate fabrications.
b. Finish requirements: Remove free iron, heat tint oxides, weld scale and
other impurities, and obtain a passive finished surface.
c. Provide quality control testing to verify effectiveness of cleaning agents
and procedures and to confirm that finished surfaces are clean and
passivated:
1) Conduct sample runs using test specimens with proposed cleaning
agents and procedures as required to avoid adverse effects on
surface finishes and base materials.
March 2021 - DRAFT 05 12 00-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_00(IDS50) Page 596
Item#18.
d. Pre-clean, chemically descale (pickle), and final clean fabrications in
accordance with the requirements of ASTM A380 to remove deposited
contaminants before shipping:
1) Passivation by citric acid treatment is not allowed:
a) If degreasing is required before cleaning to remove scale or iron
oxide, cleaning (pickling) treatments with citric acid are
permissible; however, these treatments shall be followed by
inorganic cleaners such as nitric-hydrofluoric acid.
2) Provide acid descaling (pickling) in accordance with Table Al.1 of
Annex Al of ASTM A380
3) After pickling, final cleaning of stainless steel shall conform to Part II
of Table A2.1 of Annex A2 of ASTM A380.
e. Inspect after cleaning using methods specified for"gross inspection" in
ASTM A380.
f. Improperly or poorly cleaned and passivated materials shall not be
shipped and will not be accepted at the site.
C. Galvanizing:
1. Where galvanizing is required, hot-dip galvanize structural steel after
fabrication in accordance with ASTM Al23:
a. Do not electro-galvanize or mechanically-galvanize unless specified or
accepted by Engineer.
b. Re-straighten galvanized items that bend or twist during galvanizing.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verification of conditions: Examine Work in place to verify that it is satisfactory to
receive the Work of this Section. If unsatisfactory conditions exist, do not begin this
Work until such conditions have been corrected.
3.02 ERECTION
A. General:
1. Fabricate structural and foundry items to true dimensions without warp or twist.
2. Form welded closures neatly, and grind off smooth where weld material
interferes with fit or is unsightly.
3. Install structural items accurately and securely, true to level, plumb, in correct
alignment and grade, with all parts bearing or fitting structure or equipment for
which intended.
4. Do not re-drill, re-shape, force out of alignment, or force fit fabricated items.
5. Place anchor bolts or other anchoring devices accurately and make surfaces
that bear against structural items smooth and level.
6. Rigidly support and brace structural items needing special alignment to
preserve straight, level, even, and smooth lines. Keep structural items braced
until concrete, grout, or dry pack mortar has hardened for 48 hours minimum.
7. Erect structural steel in conformance with AISC 303 and AISC 360 unless
otherwise specified or modified by applicable regulatory requirements.
8. Where anchors, connections, and other details of structural steel erection are
not specifically indicated on the Drawings or specified, form, locate, and attach
with equivalent in quality and workmanship to items specified.
March 2021 - DRAFT 05 12 00-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/05_12_00(IDS50) Page 597
Item#18.
B. Round off sharp or hazardous projections and grind smooth. Bolting:
1. General:
a. Install bolts, to project 2 threads minimum, but 1/2 inch maximum beyond
nut.
2. High-strength steel bolting:
a. Connections with high strength bolts shall conform to RCSC Specification
for Structural Joints Using ASTM A325 or A 490 Bolts.
b. Consider connections with high strength bolts to be snug-tightened joints
unless pre-tensioned joints or slip-critical joints are indicated on the
Drawings.
c. Snug-tightened connections:
1) Furnish hardened flat washers at joints with sloping faces or with
slotted holes as required by RCSC.
d. Pre-tensioned and slip-critical connections:
1) Furnish hardened flat washer:
a) Under element (nut or bolt head) being turned during tightening.
b) On outer plies for short slotted holes.
2) Furnish direct-tension-indicator washer. Verify adequate tightening of
bolts at pre-tensioned and slip critical connections by means of
tension indicator washers placed as indicated in ASTM F959,
Figure 1.
3) At slip-critical connections, provide uncoated faying surfaces as
specified by RCSC.
C. Welding - general:
1. Make welds full penetration type, unless otherwise indicated on the Drawings.
2. Remove backing bars and weld tabs after completion of weld. Repair defective
welds observed after removal of backing bars and weld tabs.
3. Obtain Engineer's acceptance of welds in repaired or field-modified work.
D. Welding stainless steel:
1. General: Field welding of stainless steel not allowed. Comply with AWS D1.6:
a. Perform with electrodes and techniques in accordance with AWS D10.4.
2. Passivation of welded surfaces:
a. Provide cleaning, pickling, and passivating as specified under Part 2
Fabrication.
E. Welding carbon steel:
1. General: Comply with AWS D1.1:
a. Weld ASTM A36 and A992 structural steel, ASTM A500 and A 501
structural tubing, and ASTM A53 pipe with E70XX electrodes conforming
to AWS A5.1; F7X-EXXX electrodes conforming to AWS A5.17: E7XT-X
electrodes conforming to AWS A5.20:
1) Field repair cut or otherwise damaged galvanized surfaces to
equivalent original condition using a galvanized surface repair.
F. Interface with other products:
1. Where steel fasteners come in contact with aluminum or other dissimilar
metals, bolt with stainless steel bolts and separate or isolate from dissimilar
metals with isolating sleeves and washers:
a. Prior to installing nuts, coat threads of stainless steel fasteners with thread
coating to prevent galling of threads.
March 2021 - DRAFT 05 12 00-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_00(IDS50) Page 598
Item#18.
3.03 PRIMING AND COATING
A. General:
1. Paint or coat steel items as specified in Section 09_96_01.
3.04 FASTENERS: CAST-IN AND POST-INSTALLED
A. General:
1. Install bolts, to project 2 threads minimum, but 1/2 inch maximum beyond nut.
2. Tightening requirements:
a. Unless otherwise specified, tighten bolts to the "snug-tight" condition,
defined as tightness attained by a few impacts of an impact wrench or the
full effort of a man using an ordinary spud wrench.
B. All thread rods - epoxy bonded in concrete:
1. Install as specified in Section 03_21_17 and as indicated on the Drawings.
C. Powder actuated fasteners:
1. Use powder actuated fasteners only for applications indicated on the Drawings
or specified.
3.05 FIELD QUALITY CONTROL
A. Provide Contractor quality control as specified in Section 01_45_00.
B. Field tests and inspections:
1. High-strength bolting:
a. Confirm use of specified bolts and nuts.
b. Snug-tightened connections:
1) Confirm use of washers as required by RCSC for sloping surfaces at
joints and for slotted holes.
2) Confirm that all plies of the connected elements have been brought
into firm contact by the tightened connections.
c. For pre-tensioned and slip-critical connections, perform testing in the
presence of the Engineer.
d. Pre-tensioned connections:
1) Prior to pre-tensioning, confirm that the appropriate feeler gage is
accepted in at least half the spaces between protrusions of the
direct-tension indicator, and that the protrusions are properly oriented
away from the work.
2) If feeler is accepted in fewer than half the spaces, remove direct-
tension indicator and replace before tightening.
3) After pre-tensioning, confirm that the at least half the spaces
between protrusions refuse entry of the feeler gage.
e. Slip-critical connections:
1) Before assembly, confirm that faying surfaces (planes of contact
between any 2 plies within the joint, including those of filler plates
and finger shims) are free of mill scale and coatings in areas within
1 inch of the edge of any hole and between all holes in the bolt
pattern.
2) Test for entry of feeler gage into protrusions of direct tension
indicators before and after tightening, as specified for pre-tensioned
connections.
March 2021 - DRAFT 05 12 00-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/05_12_00(IDS50) Page 599
Item#18.
f. Test results:
1) Submit records of testing to Engineer within 24 hours after testing.
2. Welding — Field welds:
a. Perform testing in the presence of the Engineer.
b. Visual observation:
1) Examine all welds in accordance with AWS D1.1. Quality of welds
and standards for acceptance shall be in accordance with AWS D1.1,
Section 6.9.
c. Radiographic testing:
1) Conform to AWS D 1.1, Section 6.12, and ASTM E94, and
ASTM E1032 as applicable.
2) Provide radiographic testing of welds as specified in the following
paragraphs:
a) Complete joint penetration groove welds with weld thickness of
3/4 inch or less: 10 percent of welds.
b) Complete joint penetration groove welds with weld thickness
from 3/4 inch to 1 1/2 inches: 50 percent of welds.
c) Complete joint penetration groove welds with weld thickness
greater than 1 1/2 inches: All welds.
d. Ultrasonic testing:
1) Conform to AWS D1.1, Section 13 and ASTM E164 as applicable.
2) Provide ultrasonic testing of welds as specified in the following
paragraphs:
a) Complete joint penetration groove welds not accessible for
radiographic testing, when accepted by the Contractor's
Engineer.
b) Frequency of testing shall be as specified for radiographic
testing.
e. Magnetic particle inspection:
1) Conform to ASTM E709.
2) Provide magnetic particle testing of welds as specified in the
following paragraphs:
a) Complete joint penetration groove welds of tee and corner joints:
20 percent of welds.
b) Partial joint penetration groove welds: 10 percent of welds.
c) Fillet welds: 10 percent of welds
f. Liquid penetrant inspection:
1) Conform to ASTM E165.
2) Provide for detecting discontinuities that are open to the surface.
g. Test results:
1) Submit records of testing to Engineer within 24 hours after testing.
3.06 FIELD QUALITY ASSURANCE
A. Provide Owner quality assurance as specified in Section 014500.
B. Special tests and inspections: As required by Section 01_45_24.
C. Field inspections:
1. Required inspections:
a. Observe construction for conformance to the Contract Documents and the
accepted Shop Drawings.
March 2021 - DRAFT 05_1200-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel05_12_0_0(IDS50) Page 600
Item#18.
b. Make observations of items in the following tables at frequencies not less
than that indicated in the tables.
2. Records of inspections:
a. Provide record of each inspection.
b. Submit copies to Engineer upon request.
3.07 NON-CONFORMING WORK
A. Remove and replace damaged and non-conforming work to the satisfaction of the
Engineer:
1. Bolting:
a. Snug-tightened connections: Provide additional tightening.
b. Pre-tensioned and slip-critical connections: Remove bolts. Replace with
new bolts and direct-tension indicators, and re-tighten.
c. Re-inspect and re-test all repaired or corrected bolts.
2. Welding:
a. Repair non-conforming welds in accordance with AWS D1.1,
Section 5.26.
b. Re-inspect and re-test all repaired or corrected welds.
END OF SECTION
March 2021 - DRAFT 05 12 00-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/05_12_00(IDS50) Page 601
Item#18.
SECTION 26_05_00
COMMON WORK RESULTS FOR ELECTRICALGENERAL
1.01 SUMMARY
A. Section includes:
1. General requirements applicable to all Electrical Work.
2. General requirements for electrical submittals.
B. Related sections:
1. Section 01 14 00 - Work Restrictions.
2. Section 01 33 00 - Submittal Procedures.
3. Section 01 35 21 - Selective Alterations and Demolition.
4. Section 01_45_00 - Quality Control.
5. Section 01_60_00 - Product Requirements.
6. Section 01_75_17 - Commissioning.
7. Section 01 77 00 - Closeout Procedures.
8. Section 01_78_23 - Operation and Maintenance Data.
9. Section 01_81_01 - Project Design Criteria.
10. Section 26 05 02 - Hazardous Classified Area Construction.
11. Section 26 05 33 - Conduits.
12. Section 26_05_53 - Identification for Electrical Systems.
13. Section 26_08_50 - Field Electrical Acceptance Tests.
C. Interfaces to equipment, instruments, and other components:
1. The Drawings, Specifications, and overall design are based on preliminary
information furnished by various equipment manufacturers, which identify a
minimum scope of supply from the manufacturers. This information pertains to,
but is not limited to, instruments, control devices, electrical equipment,
packaged mechanical systems, and control equipment provided with
mechanical systems.
2. Provide all material and labor needed to install the actual equipment furnished,
and include all costs to add any additional conduit, wiring, terminals, or other
electrical hardware to the Work, which may be necessary to make a complete,
functional installation based on the actual equipment furnished:
a. Make all changes necessary to meet the manufacturer's wiring
requirements.
3. Review the complete set of Drawings and Specifications in order to ensure
that all items related to the electrical power and control systems are
completely accounted for. Include any such items that appear on the Drawings
or in the Specifications from another discipline in the scope of Work:
a. If a conflict between Drawings and Specifications is discovered, refer
conflict to the Engineer as soon as possible for resolution.
D. All electrical equipment and systems for the entire Project must comply with the
requirements of the Electrical Specifications, whether referenced in the individual
Equipment Specifications or not:
1. The requirements of the Electrical Specifications apply to all Electrical Work
specified in other sections.
2. Inform all vendors supplying electrical equipment or systems of the
requirements of the Electrical Specifications.
March 2021 - DRAFT 26 05 00-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_00(IDS50) Page 602
Item#18.
3. Owner is not responsible for any additional costs due to the failure of
Contractor to notify all subcontractors and suppliers of the Electrical
Specifications requirements.
E. Contract Documents:
1. General:
a. The Drawings and Specifications are complementary and are to be used
together in order to fully describe the Work.
2. Specifications:
a. The General and Supplementary Conditions of the Contract Documents
govern the Work.
b. These requirements are in addition to all General Requirements.
3. Contract Drawings:
a. The Electrical Drawings show desired locations, arrangements, and
components of the Electrical Work in a diagrammatic manner.
b. Locations of equipment, control devices, instruments, boxes, panels, etc.
are approximate only; exercise professional judgment in executing the
Work to ensure the best possible installation:
1) The equipment locations and dimensions indicated on the Drawings
are approximate. Use the shop drawings to determine the proper
layout, foundation, and pad requirements, etc. for final installation.
Coordinate with all subcontractors to ensure that all electrical
equipment is compatible with other equipment and space
requirements. Make changes required to accommodate differences
in equipment dimensions.
2) The Contractor has the freedom to select any of the named
manufacturers identified in the individual specification sections;
however, the Engineer has designed the spatial equipment layout
based upon a single manufacturer and has not confirmed that every
named manufacturer's equipment fits in the allotted space. It is the
Contractor's responsibility to ensure that the equipment being
furnished fits within the defined space.
c. Installation details:
1) The Contract Drawings include typical installation details the
Contractor is to use to complete the Electrical Work. For cases where
a typical detail does not apply, develop installation details that may
be necessary for completing the Work, and submit these details for
review by the Engineer.
2) Not all typical installation details are referenced within the Drawing
set. Apply and use typical details where appropriate.
1.02 REFERENCES
A. Code compliance:
1. The publications are referred to in the text by the basic designation only. The
latest edition accepted by the Authority Having Jurisdiction of referenced
publications in effect at the time of the bid governs.
2. The standards listed are hereby incorporated into this Section:
a. American National Standards Institute (ANSI).
b. American Society of Civil Engineers (ASCE):
1) ASCE 7 - Minimum Design Loads for Buildings and Other Structures.
c. ASTM International (ASTM).
March 2021 - DRAFT 26 05 00-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_00(IDS50) Page 603
Item#18.
d. Illuminating Engineering Society (IES).
e. Institute of Electrical and Electronics Engineers (IEEE).
f. Insulated Cable Engineers Association (ICEA).
g. International Code Council (ICC):
1) International Code Council Evaluation Service (ICC-ES):
a) AC 156 -Acceptance Criteria for Seismic Certification by Shake
Table Testing of Non-Structural Components (ICC-ES AC 156).
h. International Society of Automation (ISA).
i. National Electrical Manufacturers Association (NEMA):
1) 250 - Enclosures for Electrical Equipment (1000 V Maximum).
j. National Fire Protection Association (NFPA):
1) 70 - National Electrical Code (NEC).
k. National Institute of Standards and Technology (NIST).
I. Underwriters' Laboratories, Inc. (UL).
1.03 DEFINITIONS
A. Definitions of terms and other electrical and instrumentation considerations as set
forth by:
1. IEEE.
2. N ETA.
3. IES.
4. 1 SA.
5. NEC.
6. NEMA.
7. NFPA.
8. NIST.
B. Specific definitions:
1. FAT: Factory acceptance test.
2. LCP: Local control panel: Operator interface panel that may contain an HMI,
pilot type control devices, operator interface devices, control relays, etc. and
does not contain a PLC or RIO.
3. PLC Cabinet: An enclosure containing the PLC.
4. PCIS: Process control and instrumentation system.
5. Space: That portion of the switchgear, motor control center, panelboard,
switchboard or control panel that does not physically contain a device but is
capable of accepting a device with no modifications to the equipment, i.e.,
provide all standoffs, bus, and hardware, as part of the space.
6. Spare: That portion of the switchgear, motor control center, panelboard,
switchboard or control panel that physically contains a device with no load
connections to be made.
7. VCP: Vendor control panel: Control panels that are furnished with particular
equipment by a vendor other than the ICSC. These panels may contain PLCs,
RIO, OIT, HMI, etc.
8. Unequipped space: That portion of the switchgear, motor control center,
panelboard, switchboard or control panel that does not physically contain a
device, standoff, bus, hardware, or other equipment.
March 2021 - DRAFT 26 05 00-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_00(IDS50) Page 604
Item#18.
1.04 SYSTEM DESCRIPTION
A. General requirements:
1. The Work includes everything necessary for and incidental to executing and
completing the Electrical Work indicated on the Drawings and specified in the
Specifications and reasonably inferable there from:
a. The Electrical Drawings are schematic in nature; use the Structural,
Architectural, Mechanical, and Civil Drawings for all dimensions and
scaling purposes.
2. It is the intent of these Specifications that the entire electrical power,
instrumentation, and control system be complete and operable. Provide all
necessary material and labor for the complete system from source of power to
final utilization equipment, including all connections, testing, calibration of
equipment furnished by others as well as equipment furnished by the
Contractor, whether or not specifically mentioned but which are necessary for
successful operation.
3. Provide all Electrical Work, including conduit, field wiring, and connections by
the electrical subcontractor under the provisions of the Electrical Specifications
for all aspects of the Work.
4. Coordinate all aspects of the Work with the electrical subcontractor and other
subcontractors before bidding in order to ensure that all costs associated with
a complete installation are included. The Owner is not responsible for any
change orders due to lack of coordination of the Work between the Contractor,
the electrical subcontractor, the other subcontractors or suppliers.
5. Demolition:
a. Where demolition is specified or indicated on the Drawings, disconnect all
associated electrical equipment and render the equipment safe.
b. Remove and dispose of all conduit, wire, electrical equipment, controls,
etc. associated with the items and/or areas to be demolished as indicated
on the Drawings unless otherwise indicated.
c. Salvage electrical equipment as specified in Section 01_35_21.
d. For each piece of equipment to be removed, remove all ancillary
components (e.g. instruments, solenoid valves, disconnect switches, etc.).
e. Conduit:
1) Where conduit removal, other than associated with equipment to be
removed, is indicated on the Drawings:
a) Remove exposed conduit to the point of encasement or burial.
b) Cut conduit flush and plug or cap encased or buried conduit.
2) Where conduits are to remain in place and removal is not indicated
on the Drawings:
a) Cap conduit open ends.
b) Re-label empty conduits as spare.
f. Remove all wire back to the source for all conduits to be removed or
abandoned in place.
g. Provide new nameplates for modified electrical distribution equipment,
motor control centers etc. to identify equipment and circuits that are no
longer used as spares.
h. Provide new typewritten schedules for all modified panelboards.
6. Portions of this Project involve installation in existing facilities and interfaces to
existing circuits, power systems, controls, and equipment:
a. Perform and document comprehensive and detailed field investigations of
existing conditions (circuits, power systems, controls, equipment, etc.)
March 2021 - DRAFT 26 05 00-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_00(IDS50) Page 605
Item#18.
before starting any Work. Determine all information necessary to
document, interface with, modify, upgrade, or replace existing circuits,
power systems, controls, and equipment.
b. Provide and document interface with, modifications to, upgrades, or
replacement of existing circuits, power systems, controls, and equipment.
7. Provide all trenching, forming, rebar, concrete, back filling, hard surface
removal and replacement, for all items associated with the Electrical Work and
installation:
a. As specified in the Contract Documents.
B. New System"
1. Provide new circuit breakers, cable, and conduits as shown on the contract
documents to facilitate power and SCADA monitoring/Control connections
between existing power generator and control equipment and new side-stream
Phosphorous Precipitation System Reactor equipment.
C. Operating facility:
1. Meridian Water Resource Recovery Facility (WRRF) is an operating facility.
Portions of this facility must remain fully functional throughout the entire
construction period. In consideration of this requirement, comply with the
following guidelines:
a. All outages must be of minimal duration and fully coordinated and agreed
to by the Owner. Adjust the construction schedule to meet the
requirements of the Owner. All changes in schedule and any needs to
reschedule are included in the Work.
b. As weather and water demand conditions dictate, re-adjust the
construction schedule to meet the demands placed upon Owner by its
users.
c. Coordinate the construction and power renovation, bear all costs, so that
all existing facilities can continue operation throughout construction.
2. According to individual circumstances and in compliance with the Drawings,
extend or replace conduit and cable connections from existing locations.
3. The standards of documentation, instrument tagging, cable and conductor
ferruling, terminal identification and labeling that apply to the new installation
apply equally to the existing installation which forms part of the modified
system.
1.05 SUBMITTALS
A. Furnish submittals as specified in Section 01_33_00 and this Section.
B. General:
1. Instruct all equipment suppliers of submittals and operation and maintenance
manuals of the requirements in this Section.
2. Furnish the submittals required by each section in the Electrical Specifications.
3. Adhere to the wiring numbering scheme specified in Section 26_05_53
throughout the Project:
a. Uniquely number each wire.
b. Wire numbers must appear on all Equipment Drawings.
4. Use equipment and instrument tags, as indicated on the Drawings, for all
submittals.
March 2021 - DRAFT 26 05 00-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_00(IDS50) Page 606
Item#18.
C. Seismic requirements:
1. Provide electrical equipment with construction and anchorage to supporting
structures designed to resist site seismic loads based on the seismic design
criteria in Section 01 81 01.
D. Operation and maintenance manuals:
1. As specified in Section 01_78_23.
2. Furnish the Engineer with a complete set of written operation and maintenance
manuals 8 weeks before Functional Acceptance Testing.
E. Record Documents:
1. Furnish as specified in Section 01_77_00.
2. Provide Record Documents of all Electrical Drawings.
3. Record Drawing requirements:
a. Update Record Drawings weekly.
b. Record Drawings must be fully updated as a condition of the monthly
progress payments.
c. Submit Record Drawings upon completion of the Work for final review.
d. Clearly and neatly show all changes including the following:
1) All existing pipe, conduit, wire, instruments or other structures
encountered or uncovered during construction.
4. Shop drawings:
a. Upon completion of the Work, update all shop drawings to indicate the
final as-built configuration of the systems:
1) Provide as-built shop drawings for all electrical equipment on 11-inch
by 17-inch paper:
a) Size all drawings to be readable and legible on 11-17 inch
media.
2) Provide electronic copies of these documents on CD-ROM or DVD
disks in PDF format.
5. Review and corrections:
a. Correct any record documents or other documents found to be
incomplete, not accurate, of poor quality, or containing errors.
b. Promptly correct and re-submit record documents returned for correction.
F. Test reports:
1. As specified in Section 01_33_00.
2. Include the following:
a. A description of the test.
b. List of equipment used.
c. Name of the person conducting the test.
d. Date and time the test was conducted.
e. All raw data collected.
f. Calculated results.
g. Each report signed by the person responsible for the test.
3. Additional requirements for field acceptance test reports are specified in
Sections 01 75 17 and 26 08 50.
March 2021 - DRAFT 26 05 00-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_00(IDS50) Page 607
Item#18.
G. Calculations:
1. Where required by specific Electrical Specifications:
a. Because these calculations are being provided by a registered
professional engineer, they will be reviewed for form, format, and content
but will not be reviewed for accuracy and calculation means.
1.06 QUALITY ASSURANCE
A. Furnish all equipment listed by and bearing the label of UL or of an independent
testing laboratory acceptable to the Engineer and the Authority Having Jurisdiction.
1.07 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 01_60_00.
1.08 PROJECT OR SITE CONDITIONS
A. Site conditions:
1. Provide an electrical, instrumentation and control system, including all
equipment, raceways, and any other components required for a complete
installation that meets the environmental conditions for the Site as specified in
the General Requirements and below.
2. Seismic load resistance:
a. Provide electrical equipment with construction and anchorage to
supporting structures designed to resist site seismic loads as specified in
Section 01 81 01.
3. Wind load resistance:
a. Provide electrical equipment with construction and anchorage to
supporting structures designed to resist site wind loads as specified in
Section 01 81 01.
4. Altitude, temperature and humidity:
a. As specified in Section 01_81_01.
b. Provide all electrical components and equipment fully rated for continuous
operation at this altitude, with no additional derating factors applied.
c. Provide additional temperature conditioning equipment to maintain all
equipment in non-conditioned spaces subject to these ambient
temperatures, with a band of 10 degrees Fahrenheit above the minimum
operating temperature and 10 degrees Fahrenheit below maximum
operating temperature, as determined by the equipment manufacturer's
guidelines:
1) Provide all power conduits wiring for these devices (e.g. heaters,
fans, etc.) whether indicated on the Drawings or not.
5. Outdoor installations:
a. Provide electrical, instrumentation and control equipment suitable for
operation in the ambient conditions where the equipment is located.
b. Provide heating, cooling, and dehumidifying devices incorporated into and
included with electrical equipment, instrumentation and control panels to
maintain the enclosures within the rated environmental operating ranges
as specified in this Section for the equipment:
1) Provide all wiring necessary to power these devices.
March 2021 - DRAFT 26 05 00-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_00(IDS50) Page 608
Item#18.
B. Provide enclosures for electrical, instrumentation and control equipment, regardless
of supplier or subcontractor furnishing the equipment, that meet the requirements
outlined in NEMA Standard 250 for the following types of enclosures:
1. NEMA Type 1: Intended for indoor use, primarily to provide a degree of
protection from accidental contact with energized parts or equipment.
2. NEMA Type 4: Intended for indoor or outdoor use, primarily to protect
equipment from exposure to windblown dust and rain, splashing or hose
directed water, ice formation and freezing.
3. NEMA Type 4X: Made from corrosion resistant materials and are intended for
indoor or outdoor use, primarily to protect equipment from exposure to
windblown dust and rain, splashing or hose directed water, ice formation and
freezing, and corrosion. Provide specific materials as specified or indicated on
the Drawings.
4. NEMA Type 12: Intended for indoor use, primarily to provide a degree of
protection from dust, falling dirt and dripping non-corrosive liquids.
5. NEMA Type 6: Rated for submergence.
6. NEMA Type 6P: Rated for prolonged submergence.
7. NEMA Type 7: Intended for installation in locations where explosive or
combustible gas or vapors may be present (Class I Division 1 or Class I
Division 2) meeting the requirements outlined in Section 26_05_02.
8. NEMA Type 8: Intended for installation in either indoor or outdoor locations
where explosive or combustible gas or vapors may be present (Class I
Division 1 or Class I Division 2) and the equipment is oil-immersed, meeting
the requirements outlined in Section 26_05_02 - Hazardous Classified Area
Construction.
C. Plant area Electrical Work requirements:
1. Provide all Electrical Work in accordance with the following table, unless
otherwise specifically indicated on the Drawings:
ENVIRONMENT
W = WET
D = DAMP
NEMA C = CLEAN/DRY
ENCLOSURE EXPOSED X = CORROSIVE SUPPORT
PLANT AREA TYPE CONDUIT TYPE H = HAZARDOUS MATERIALS
Electrical Room 1, 12 GRC C GALV STL
Side Stream Building 4 PCS W SST
Digester Building 7 PCS H SST
Outdoors 4X SS PCs W SST
Reactor Tank*
* Refer to Section 26_05_02 Hazardous Areas for description of the Class I Division 2 space
around the Reactor Tank.
2. Modify exposed conduit runs as specified in Section 26_05_33.
1.09 SEQUENCING (NOT USED)
March 2021 - DRAFT 26 05 00-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_00(IDS50) Page 609
Item#18.
1.10 SCHEDULING
A. General:
1. Testing requirements are specified in Section 01_75_17, 26_08_50, and other
sections.
2. Work restrictions and other scheduling requirements are specified in
Section 011400.
3. Commissioning requirements as specified in Section 01_75_17.
1.11 WARRANTY
A. Provide additional warranty as specified in the individual Electrical Specifications.
1.12 SYSTEM START-UP
A. Replace or modify equipment, software, and materials that do not achieve design
requirements after installation in order to attain compliance with the design
requirements:
1. Following replacement or modification, retest the system and perform
additional testing to place the complete system in satisfactory operation and
obtain compliance acceptance from the Engineer.
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 MAINTENANCE
A. Before Substantial Completion, perform all maintenance activities required by any
sections of the Specifications including any calibrations, final adjustments,
component replacements or other routine service required before placing equipment
or systems in service.
B. Furnish all spare parts as required by other sections of the Specifications.
PART PRODUCTS
2.01 MANUFACTURERS
A. Provide similar items of same manufacturer throughout the electrical and
instrumentation portion of the Project.
B. Allowable manufacturers are specified in individual Electrical Specifications.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS
A. Furnish all materials under this Contract that are new, free from defects, and
standard products produced by manufacturers regularly engaged in the production
of these products and that bear all approvals and labels as required by the
Specifications.
B. Stainless steel:
March 2021 - DRAFT 26 05 00-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_00(IDS50) Page 610
Item#18.
1. Where stainless steel is indicated or used for any portion of the Electrical
Work, provide a non-magnetic, corrosion-resistant alloy, ANSI Type 316, satin
finish.
2. Provide exposed screws of the same alloys.
3. Provide finished material free of any burrs or sharp edges.
4. Use only stainless steel hardware, when chemically compatible, in all areas
that are or could be in contact with corrosive chemicals.
5. Use stainless steel hardware, when chemically compatible, in all chemical
areas or areas requiring NEMA Type 4X construction.
6. Do not use stainless steel in any area containing chlorine, gas or solution,
chlorine products or ferric chloride.
2.04 MANUFACTURED UNITS (NOT USED)
2.05 EQUIPMENT (NOT USED)
2.06 COMPONENTS (NOT USED)
2.07 ACCESSORIES (NOT USED)
2.08 MIXES (NOT USED)
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
2.11 SOURCE QUALITY CONTROL
A. Provide all equipment that is new, free from defects, and standard products
produced by manufacturers regularly engaged in the production of these products.
PART 3 EXECUTION
3.01 EXAMINATION
A. It is the electrical subcontractor's responsibility to be fully familiar with the existing
conditions and local requirements and regulations.
B. Review the site conditions and examine all shop drawings for the various items of
equipment in order to determine exact routing and final terminations for all wiring
and cables.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. Equipment locations shown on Electrical Drawings may change due to variations in
equipment size or minor changes made by others during construction:
1. Verify all dimensions indicated on the Drawings:
a. Actual field conditions govern all final installed locations, distances, and
levels.
March 2021 - DRAFT 26 05 00-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_00(IDS50) Page 611
Item#18.
2. Review all Contract Documents and approved equipment shop drawings and
coordinate Work as necessary to adjust to all conditions that arise due to such
changes.
3. Make minor changes in location of equipment before rough in, as directed by
the Owner or Engineer.
4. Provide a complete electrical system:
a. Install all extra conduits, cables, and interfaces as may be necessary to
provide a complete and operating electrical system.
B. Install the equipment in accordance with the accepted installation instructions and
anchorage details to meet the seismic and wind load requirements at the Project
site.
C. Cutting and patching:
1. Perform all cutting, patching, channeling, core drilling, and fitting required for
the Electrical Work, except as otherwise directed:
a. Secure the permission of the Engineer before performing any operation
likely to affect the strength of a structural member such as drilling, cutting
or piercing:
1) Before cutting, channeling, or core drilling any surface, ensure that
no penetration of any other systems will be made:
a) Verify that area is clear and free of conduits, cables, piping,
ductwork, post-tensioning cables, etc.
b) Use tone-locate system or X-ray to ensure that area is clear of
obstructions.
b. Review the complete Drawing set to ensure that there are no conflicts or
coordination problems before cutting, channeling, or core drilling any
surface.
2. Perform all patching to the same quality and appearance as the original work.
Employ the proper tradesmen to secure the desired results. Seal around all
conduits, wires, and cables penetrating walls, ceilings, and floors in all
locations with a fire stop material, typically:
a. 3M: CP 25WB+: Caulk.
b. 3M: Fire Barrier: Putty.
3. Use the installation details indicated on the Drawings as a guide for acceptable
sealing methods.
D. Install all conduits and equipment in such a manner as to avoid all obstructions and
to preserve headroom and keep openings and passageways clear:
1. Install all conduits and equipment in accordance with working space
requirements in accordance with the NEC.
a. This includes any panel, disconnect switch or other equipment that can be
energized while open exposing live parts regardless of whether it is likely
to require examination or has serviceable parts.
2. Where the Drawings do not show dimensions for locating equipment, install
equipment in the approximate locations indicated on the Drawings.
a. Adjust equipment locations as necessary to avoid any obstruction or
interferences.
3. Where an obstruction interferes with equipment operation or safe access,
relocate the equipment.
March 2021 - DRAFT 26 05 00-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_00(IDS50) Page 612
Item#18.
4. Where the Drawings do not indicate the exact mounting and/or supporting
method to be used, use materials and methods similar to the mounting details
indicated on the Drawings.
E. Earthwork and concrete:
1. Install all trenching, shoring, concrete, backfilling, grading and resurfacing
associated with the Electrical Work:
a. Requirements as specified in the Contract Documents.
F. Roof penetrations:
1. Seal conduit penetrations in accordance with roofing manufacturer's
instructions.
G. Terminations:
1. Provide and terminate all conductors required to interconnect power, controls,
instruments, panels, and all other equipment.
H. Miscellaneous installation requirements:
1. In case of interference between electrical equipment indicated on the
Drawings and the other equipment, notify the Engineer.
2. Location of manholes and pullboxes indicated on the Drawings are
approximate. Coordinate exact location of manholes and pullboxes with
Mechanical and Civil Work.
3. Provide additional manholes or pullboxes to those shown where they are
required to make a workable installation.
4. Circuits of different service voltage:
a. Voltage and service levels:
1) Medium voltage: greater than 1.0 kV.
2) Low voltage: 120 V to 480 V.
3) Instrumentation: Less than 50 VDC.
I. Labeling:
1. Provide all nameplates and labels as specified in Section 26_05_53.
J. Equipment tie-downs:
1. Anchor all instruments, control panels, and equipment by methods that comply
with seismic and wind bracing criteria, which apply to the Site.
2. All control panels, VCPs, LCPs, RTUs, PCMs, etc., must be permanently
mounted and tied down to structures in accordance with the Project seismic
criteria.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. As specified in Section 01_75_17.
March 2021 - DRAFT 26 05 00-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_00(IDS50) Page 613
Item#18.
B. For Owner and Engineer witnessed FAT:
1. Contractor is responsible for the Owner's and Engineer's costs associated with
FAT as specified in Section 01_75_17.
C. Owner training:
1. As specified in Section 01_75_17 and in this Section.
3.08 FIELD QUALITY CONTROL
A. Inspection:
1. Allow for inspection of electrical system installation as specified in
Section 014500.
2. Provide any assistance necessary to support inspection activities.
3. Engineer inspections may include, but are not limited to, the following:
a. Inspect equipment and materials for physical damage.
b. Inspect installation for compliance with the Drawings and Specifications.
c. Inspect installation for obstructions and adequate clearances around
equipment.
d. Inspect equipment installation for proper leveling, alignment, anchorage,
and assembly.
e. Inspect equipment nameplate data to verify compliance with design
requirements.
f. Inspect raceway installation for quality workmanship and adequate
support.
g. Inspect cable terminations.
4. Inspection activities conducted during construction do not satisfy inspection or
testing requirements specified in Section 26_08_50.
B. Field acceptance testing (Functional Testing):
1. Notify the Engineer when the Electrical Work is ready for field acceptance
testing.
2. Perform the field acceptance tests as specified in Section 26_08_50.
3. Record results of the required tests along with the date of test:
a. Use conduit identification numbers to indicate portion of circuit tested.
C. Workmanship:
1. Leave wiring in panels, manholes, boxes, and other locations neat, clean, and
organized:
a. Neatly coil and label spare wiring lengths.
b. Shorten, re-terminate, and re-label excessive used as well as spare wire
and cable lengths, as determined by the Engineer.
3.09 ADJUSTING (NOT USED)
3.10 CLEANING
A. As specified in Section 01_77_00.
B. Remove all foreign material and restore all damaged finishes to the satisfaction of
the Engineer and Owner.
March 2021 - DRAFT 26 05 00-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_00(IDS50) Page 614
Item#18.
C. Clean and vacuum all enclosures to remove all metal filings, surplus insulation and
any visible dirt, dust or other matter before energization of the equipment or system
start-up:
1. Use of compressors or air blowers for cleaning is not acceptable.
D. Clean and re-lamp all new and existing luminaries that were used in the areas
affected by the construction, and return all used lamps to the Owner.
E. As specified in other sections of the Contract Documents.
3.11 PROTECTION
A. Protect all Work from damage or degradation until Substantial Completion.
B. Maintain all surfaces to be painted in a clean and smooth condition.
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 26 05 00-14 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_00(IDS50) Page 615
Item#18.
SECTION 26_05_09
LOW VOLTAGE MOTORS UP TO 500 HORSEPOWER
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Low voltage motors up to 500 horsepower (hp).
1.02 REFERENCES
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. American Bearing Manufacturers Association (ABMA):
1. 9 - Load Ratings and Fatigue Life for Ball Bearings.
2. 11 - Load Ratings and Fatigue Life for Roller Bearings.
C. American Petroleum Institute (API):
1. 670 - Vibration, Axial Position, and Bearing Temperature Monitoring Systems.
D. ASTM International (ASTM).
1. 13117 - Standard Practice for Operating Salt Spray (Fog) Apparatus.
E. Institute of Electrical and Electronic Engineers (IEEE):
1. 43 - IEEE Recommended Practice for Testing Insulation Resistance of
Rotating Machinery.
2. 112 - IEEE Standard Test Procedure for Polyphase Induction Motors and
Generators.
3. 841 - IEEE Standard for Petroleum and Chemical Industry-Premium-
Efficiency, Severe Duty, Totally Enclosed Fan-Cooled (TEFC) Squirrel Cage
Induction Motors - Up to and Including 370 kW (500 hp).
F. National Electrical Manufacturers' Association (NEMA):
1. MG-1 - Motors and Generators.
2. MG-2 - Safety Standard for Construction and Guide for Selection, Installation,
and Use of Electric Motors and Generators.
G. Underwriters Laboratories Inc. (UL):
1. 674 - Electric Motors and Generators for Use in Division 1 Hazardous
(Classified) Locations.
1.03 DEFINITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
March 2021 - DRAFT 26 05 09-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 616
Item#18.
1.04 SYSTEM DESCRIPTION
A. Furnish and install electric motors and accessories as specified in this Section and
the Sections specifying driven equipment to provide a complete and operable
installation.
1.05 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 - Submittal Procedures and
26 05 00 - Common Work Results for Electrical.
B. Submit completed motor data sheets for each motor supplied:
1. Conform to data sheet in the appendix of this Section.
2. Manufacturer's or other data sheets are not acceptable.
C. Product data:
1. Descriptive bulletins.
2. Machine tag and loop number as indicated on the Drawings and in the
specification section number of the driven machine.
3. Complete electrical data.
4. Torque, current, and power factor versus speed curves:
a. At 100 percent rated voltage for all full voltage started and VFD-driven
motors.
b. For motors on reduced voltage start at 70, 80, 90, and 100 percent rated
voltage.
5. Additional data for motors installed in classified areas:
a. Temperature code.
b. Hazardous area approval indicating Class, Division, and Group:
1) For motors driven by variable frequency drives, provide
manufacturer's certification that the motor is suitable for operation in
the hazardous area when driven by a variable frequency drive.
6. Accessories data:
a. Power factor correction capacitors:
1) Size in KVAR, for all motors not connected to variable frequency
drives.
b. Motor winding heaters:
1) Voltage.
2) Watts.
c. Winding temperature detectors:
1) Type.
2) Rating.
d. Moisture detectors.
7. Mechanical data:
a. Bearing design and bearing life calculations.
b. Resonant frequencies for all VFD-driven motors 50 hp or greater.
D. Shop drawings:
1. Motor weight.
2. Frame size.
3. Conduit box(es), size(s), and location(s).
4. Outline drawings with dimensions.
5. Installation details for the project seismic criteria.
March 2021 - DRAFT 26 05 09-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 617
Item#18.
E. Test reports:
1. Factory test reports with test reference standard identified.
F. Certification:
1. When motors are driven by variable speed drive systems, submit certification
that selected motor:
a. Is capable of satisfactory performance under the intended load.
b. Meets the requirements of the latest edition of NEMA MG-1 Part 31.
G. Calculations:
1. Where site conditions specified in Section 260500 - Common Work Results
for Electrical exceed manufacturer's ratings, provide derating calculations for
each motor.
1.06 QUALITY ASSURANCE
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.07 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.08 PROJECT OR SITE CONDITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING (NOT USED)
1.11 WARRANTY
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.12 SYSTEM START-UP
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.13 OWNER'S INSTRUCTION (NOT USED)
1.14 MAINTENANCE (NOT USED)
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. US Motors.
2. General Electric.
3. Reliance.
4. Toshiba.
5. Baldor.
March 2021 - DRAFT 26 05 09-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 618
Item#18.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS (NOT USED)
2.04 MANUFACTURED UNITS (NOT USED)
2.05 EQUIPMENT
A. 3-phase induction motors - general:
1. Voltage:
a. All motors 1/2 hp and larger shall be rated 460 V, 3-phase unless
otherwise indicated on the Drawings.
b. Dual voltage motors rated 230/460 V, 3-phase are acceptable provided all
leads are brought to the conduit box.
2. Motors driving identical machines shall be identical.
3. All motors greater than 1 hp and up to 500 hp shall meet the "NEMA Premium
Efficiency" percent listed in NEMA MG-1.
4. Horsepower as indicated on the Drawings:
a. Horsepower ratings indicated on the Drawings are based on vendor's
estimates. Provide motors sized for the load of the actual equipment
furnished without operating in the service factor.
5. Service factor:
a. 1.15 service factor on sine wave power.
b. 1.0 when driven by VFD.
6. Torque:
a. Provide motors that develop sufficient torque for acceleration to full speed
at voltage 10 percent less than motor nameplate rating.
b. When started using reduced voltage starters:
1) Provide motors that develop sufficient torque for acceleration to full
speed.
c. NEMA Design B except where driven load characteristics require other
than normal starting torque:
1) In no case shall starting torque or breakdown torque be less than the
values specified in NEMA MG-1.
7. Enclosures:
a. As specified in the individual equipment Specifications or in this Section.
b. Totally enclosed fan cooled:
1) Cast iron conduit box.
2) Tapped drain holes with Type 316 stainless steel plugs for frames
286 and smaller, and automatic breather and drain devices for
frames 324 and larger.
c. Explosion-proof:
1) Tapped drain holes with corrosion resistant plugs for frames 286 and
smaller and automatic breather and drain devices for frames 324 and
larger.
d. Lifting devices: All motors weighing 265 pounds (120 kilograms) or more
shall have suitable lifting devices for installation and removal.
8. Manufactured with cast iron frames in accordance with NEMA MG-1 or
manufacturer's standard material for the specified rating.
March 2021 - DRAFT 26 05 09-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 619
Item#18.
9. Nameplates:
a. Provide all motors with a permanent, stainless steel nameplate indelibly
stamped or engraved with:
1) NEMA standard motor data.
a) Indicate compliance with NEMA MG-1 Part 31 for inverter duty
motors.
2) AFBMA bearing numbers and lubrication instructions.
10. Hardware:
a. Type 316 stainless steel.
11. Conduit boxes:
a. Cast iron or stamped steel.
b. Split from top to bottom.
c. Provide gaskets at the following interfaces:
1) Frames and conduit boxes.
2) Conduit boxes and box covers.
d. Rotatable through 360 degrees in 90-degree increments.
1) Where available based on the size of the conduit box.
e. Exceeding the dimensions defined in NEMA MG-1.
f. Provide grounding lugs inside conduit boxes for motor frame grounding.
12. Motor bearings:
a. Antifriction.
b. Regreasable and initially filled with grease for horizontal motors and
vertical motors per manufacturer's standard design.
c. Bearings and lubrication suitable for ambient temperature and
temperature rise.
d. Suitable for intended application and have ABMA L-10 rating life of
60,000 hours or more.
e. Fit bearings with easily accessible grease supply, flush, drain, and relief
fittings using extension tubes where necessary.
f. Where specified in the equipment Specifications, provide split-sleeve type
hydrodynamic radial bearings. Provide a bearing isolator to protect
bearings from contaminants.
13. Insulation systems:
a. Motors installed in ambient temperatures 40 degrees Celsius or less:
1) Provide Class F insulation.
2) Design temperature rise consistent with Class B insulation.
3) Rated to operate at an ambient temperature of 40 degrees Celsius at
the altitude where the motor will be installed.
b. Motors installed in ambient temperatures between 40 degrees Celsius
and 50 degrees Celsius:
1) Provide Class F insulation.
2) Design temperature rise consistent with Class B insulation.
3) Rated to operate at an ambient temperature of 50 degrees Celsius at
the altitude where the motor will be installed.
c. Motors installed in ambient temperatures between 50 degrees Celsius
and 65 degrees Celsius:
1) Provide Class H insulation.
2) Design temperature rise consistent with Class F insulation.
3) Rated to operate at an ambient temperature of 65 degrees Celsius at
the altitude where the motors will be installed.
March 2021 - DRAFT 26 05 09-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 620
Item#18.
14. Motor leads:
a. Insulated leads with non-wicking, non-hydroscopic material. Class F
insulation.
15. Noise:
a. Maximum operating noise level in accordance with NEMA MG-1.
B. Motors driven by variable frequency drives:
1. Compatible with the variable frequency drives specified.
2. Inverter duty rated and labeled.
3. Meet the requirements of NEMA MG-1 Part 31.
4. Winding insulation meets the requirements of NEMA MG-1 Part 31.4.4.2.
5. Capable of running continuously at 1/10th of full speed, with no harmful effects
or overheating.
6. All motors except explosion proof motors:
a. Shaft grounding ring:
1) Provide a shaft grounding ring for each VFD-driven motor.
2) Aluminum frame and internal components.
3) Conductive microfiber brushes.
4) Maintenance free design.
5) Aegis Bearing Protection ring as manufactured by Electro Static
Technology or equal.
C. Motors installed in hazardous locations:
1. Class I, Division 1 or Class II, Division 1 areas:
a. Enclosures:
1) Explosion proof for 3-phase motors.
2) UL listed in conformance with UL-674.
3) UL approval with nameplate and serial number.
2. Other hazardous areas:
a. Enclosures:
1) TEFC for motors in Class I, Division 2 areas.
2) Vertical motors as specified in this Section.
3) Hazardous area and temperature code approval stamped on
nameplate.
3. Single-phase motors: Explosion proof motor enclosure.
D. Single-phase motors:
1. Capacitor start type rated for operation at 115 volts, 60 hertz, unless otherwise
specified or as indicated on the Drawings.
2. Totally enclosed fan cooled (TEFC) motors manufactured in accordance with
NEMA MG 1.
3. Ball bearings: Sealed.
4. 1/2 hp or less fan motors:
a. Split-phase or shaded pole type when standard for the equipment.
b. Open type when suitably protected from moisture, dripping water, and lint
accumulation.
5. Wound rotor or commutator type single-phase motors only when their specific
characteristics are necessary for application and their use is acceptable to the
Engineer.
6. Integral overload protection.
2.06 COMPONENTS (NOT USED)
March 2021 - DRAFT 26 05 09-6 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 621
Item#18.
2.07 ACCESSORIES
A. Motor winding heaters:
1. Provide all 3-phase motors with belted or cartridge space heaters mounted
within the motor enclosure.
2. Space heater rating shall be 120 volts, single-phase, unless otherwise
indicated on the P&IDs.
3. Power leads for heaters wired into conduit box.
4. Installed within motor enclosure adjacent to core iron.
B. Winding temperature detectors:
1. Provide factory installed winding temperature detector with leads terminating in
the conduit box:
a. Where required by the driven equipment Specification or as indicated on
the Drawings.
b. RTD type, 2 per phase, 100-ohm platinum.
2. Temperature switches with normally closed contacts as indicated on the
P&IDs.
2.08 MIXES (NOT USED)
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
2.11 SOURCE QUALITY CONTROL (NOT USED)
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Install motors in accordance with manufacturer's instructions.
C. Install shaft grounding ring on VFD-driven motors in accordance with the
manufacturer's instructions.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING AND PROCESS START-UP
A. As specified in Section 01_75_17 - Commissioning.
March 2021 - DRAFT 26 05 09-7 1170
pwalCarollolDocumentslClientllDlMeridianl11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 622
Item#18.
B. Factory testing:
1. Motors less than 250 hp:
a. Perform manufacturer's standard production tests including but not limited
to:
1) No load current.
2) High potential test.
3) Winding resistance.
b. Furnish copies of standard test reports on prototype or identical units.
3.08 FIELD QUALITY CONTROL
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Before start-up, perform insulation resistance test on each motor furnished or
installed on this project:
1. Windings energized to 1,000 volts DC for 1 minute.
2. Resistance measured at the end of the test, recorded, and submitted to the
Engineer for review.
3. Inform the Engineer of any unusual or unacceptable test results.
4. This test is in addition to the acceptance tests in Section 26_08_50 - Field
Electrical Acceptance Tests.
3.09 ADJUSTING (NOT USED)
3.10 CLEANING (NOT USED)
3.11 PROTECTION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
END OF SECTION
March 2021 - DRAFT 26 05 09-8 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 623
Item#18.
MOTOR DATA SHEET
MOTOR/EQUIPMENT TAG MOTOR NUMBER
SPECIFICATION NUMBER OF DRIVEN MACHINE
MOTOR NAMEPLATE DATA
MANUFACTURER MODEL/SERIES MODEL NO.
FRAME ENCLOSURE NEMA DESIGN
HP SERVICE FACTOR RPM
INSULATION CLASS VOLTS FULL LOAD AMPS
AMBIENT TEMP PHASE NO LOAD AMPS
DESIGN TEMP HERTZ LOCK ROTOR AMPS
INRUSH CODE LETTER
100% LOAD 75% LOAD 50% LOAD
GUARANTEED MINIMUM EFFICIENCIES:
GUARANTEED MINIMUM POWER FACTOR:
MAXIMUM SIZE OF POWER FACTOR CORRECTION CAPACITOR: KVAR
ACCESSORIES
MOTOR WINDING HEATER VOLTS WATTS
WINDING THERMAL PROTECTION
WINDING TEMP SWITCHES(YES/NO)
RTD:
TYPE QUANTITY PER PHASE #OF WIRES
NOMINAL RESISTANCE NOMINAL TEMP COEFFICIENT
RECOMMENDED DEGREES RECOMMENDED DEGREES
ALARM CELSIUS TRIP CELSIUS
SPECIAL APPLICATIONS
INVERTER DUTY"(YES/NO) PART WINDING (YES/NO) WYE-DELTA(YES/NO)
2 SPEED, 1 WINDING (YES/NO) 2 SPEED, 2 WINDING (YES/NO)
AREA CLASSIFICATION:
CLASS DIVISION GROUP TEMP CODE
Conforms to NEMA MG-1 Part 31.
March 2021 - DRAFT 26 05 09-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_09(IDS50) Page 624
Item#18.
Page 625
Item#18.
SECTION 26_05_18
600-VOLT OR LESS WIRES AND CABLES
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. 600 volt class or less wire and cable.
1.02 REFERENCES
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. ASTM International (ASTM):
1. B3 - Standard Specification for Soft or Annealed Copper Wire.
2. B8 - Standard Specification for Concentric-Lay-Stranded Copper Conductors,
Hard, Medium-Hard, or Soft.
C. CSA International (CSA).
D. Insulated Cable Engineers Association (ICEA):
1. NEMA WC 70/ICEA S-95-658-1999 - Standard for Power Cables Rated 2000
Volts or Less for the Distribution of Electrical Energy.
2. NEMA WC 57/ICEA S-73-532 - Standard for Control, Thermocouple
Extension, and Instrumentation Cables.
E. National Fire Protection Association (NFPA):
1. 72 - National Fire Alarm and Signaling Code.
2. 101 - Life Safety Code.
F. Telecommunications Industry Association/Electronics Industry Association
(TIA/EIA):
1. 568-C.2 - Balanced Twisted-Pair Telecommunication Cabling and
Components Standard.
2. 569-B — Commercial Building Standards for Telecommunications Pathways
and Spaces.
3. 1005 — Industrial Cabling Standard.
G. Underwriter's Laboratories Inc., (UL):
1. 44 - Thermoset-Insulated Wires and Cables.
2. 1277 - Standard for Electrical Power and Control Tray Cables with Optional
Optical-Fiber Members.
3. 1424 - Standard for Cables for Power-Limited Fire-Alarm Circuits.
4. 1569 - Standard for Metal-Clad Cables.
5. 2196 - Standard for Fire Test for Circuit Integrity of Fire-Resistive Power,
Instrumentation, Control, and Data Cables.
6. 2225 - Standard for Cables and Cable-Fittings for Use in Hazardous
(Classified) Locations.
March 2021 - DRAFT 26 05 18-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 626
Item#18.
1.03 DEFINITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Specific definitions and abbreviations:
1. AWG: American wire gauge.
2. BCCS: Bare copper-covered steel.
3. CPE: Chlorinated polyethylene.
4. FEP: Fluorinated ethylene propylene.
5. FHDPE: Foam high-density polyethylene.
6. FPE: Foam polyethylene.
7. OD: Outside diameter.
8. PVC: Polyvinyl chloride.
9. XHHW: Cross-linked high heat water resistant insulated wire.
C. Definitions of terms and other electrical considerations as set forth in the:
1. ASTM.
2. ICEA.
1.04 SYSTEM DESCRIPTION
A. Furnish and install the complete wire and cable system.
1.05 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 - Submittal Procedures and
26 05 00 - Common Work Results for Electrical.
B. Product data:
1. Manufacturer of wire and cable.
2. Insulation:
a. Type.
b. Voltage class.
3. AWG size.
4. Conductor material.
5. Pulling compounds.
C. Shop drawings:
1. Show splice locations.
a. For each proposed splice location provide written justification describing
why the splice is necessary.
D. Test reports:
1. Submit test reports for meg-ohm tests.
E. Calculations:
1. Submit cable pulling calculations to the Engineer for review and comment for
all cables that will be installed using mechanical pulling equipment. Show that
the maximum cable tension and sidewall pressure will not exceed
manufacturer recommended values:
a. Provide a table showing the manufacturer's recommended maximum
cable tension and sidewall pressure for each cable type and size included
in the calculations.
March 2021 - DRAFT 26 05 18-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 627
Item#18.
b. Submit the calculations to the Engineer a minimum of 2 weeks before
conduit installation.
1.06 QUALITY ASSURANCE
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. All wires and cables shall be UL listed and labeled.
1.07 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.08 PROJECT OR SITE CONDITIONS (NOT USED)
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING (NOT USED)
1.11 WARRANTY
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.12 SYSTEM START-UP
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.13 OWNERS INSTRUCTIONS (NOT USED)
1.14 MAINTENANCE (NOT USED)
PART2 PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. 600 volt class wire and cable:
a. General Cable.
b. Okonite Co.
c. Southwire Co.
d. Service Wire.
2. 600 volt VFD cable:
a. General Cable.
b. Southwire Co.
c. Service Wire.
3. Instrumentation class wire and cable:
a. Alpha Wire Co.
b. Belden CDT.
c. General Cable.
d. Okonite Co.
e. Rockbestos Surprenant Cable Corp.
March 2021 - DRAFT 26 05 18-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 628
Item#18.
4. Network cables:
a. General Cable.
b. Belden.
c. CommScope.
5. Fire alarm wire and cable:
a. West Penn Wire.
b. Olympic Wire and Cable.
c. Rockbestos Surprenant Cable Corp.
d. Draka, Lifeline.
6. Tray cables:
a. General Cable.
b. Southwire Co.
c. Okonite Co.
d. Service Wire.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS
A. Conductors:
1. Copper in accordance with ASTM B3.
2.04 MANUFACTURED UNITS
A. General:
1. Provide new wires and cables manufactured within 1 year of the date of
delivery to the Site.
2. Permanently mark each wire and cable with the following at 24-inch intervals:
a. AWG size.
b. Voltage rating.
c. Insulation type.
d. UL symbol.
e. Month and year of manufacture.
f. Manufacturer's name.
3. Identify and mark wire and cable as specified in Section 26_05_53 -
Identification for Electrical Systems:
a. Use integral color insulation for#2 AWG and smaller wire.
b. Wrap colored tape around cable larger than #2 AWG.
B. 600 volt class wire and cable:
1. Provide AWG or kcmil sizes as indicated on the Drawings or in the Conduit
Schedules:
a. When not indicated on the Drawings, size wire as follows:
1) In accordance with the NEC:
a) Use 75 degree Celsius ampacity ratings.
b) Ampacity rating after all derating factors, equal to or greater than
rating of the overcurrent device.
2) Provide #12 AWG minimum for power conductors.
3) Provide #14 AWG minimum for control conductors.
2. Provide Class B stranding in accordance with ASTM B8:
a. Provide Class C stranding where extra flexibility is required.
March 2021 - DRAFT 26 05 18-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 629
Item#18.
3. Insulation:
a. XHHW-2.
b. 90 degree Celsius rating.
4. Multiconductor cables:
a. Number and size of conductors as indicated on the Drawings or in the
Conduit Schedules.
b. Individual conductors with XHHW-2 insulation.
c. Overall PVC jacket.
d. Tray cable rated.
e. Color-coding for control wire in accordance with ICEA Method 1, E-2 in
accordance with NEMA WC 57/ICEA S-73-532.
f. Ground conductor: Bare:
1) Sized in accordance with NEC.
C. 600 volt VFD cables:
1. Conductor:
a. Provide Class B stranding in accordance with ASTM B8.
2. Insulation:
a. Cross-linked Polyethylene.
b. 90 degree Celsius rating.
c. UL 44 Type RHH/RHW-2 or XHHW-2.
3. Ground:
a. Provide Class B stranding in accordance with ASTM B8.
b. 3 symmetrically placed bare copper conductors in direct contact with
shield.
4. Metallic shield:
a. Overall 5 mil bare copper tape shield with 50 percent overlap.
5. Outer jacket:
a. UL 1277 Type PVC.
6. Cable tray rated, UL Type TC-ER.
D. Instrumentation class cable:
1. Type TC.
2. Suitable for use in wet locations.
3. Voltage rating: 600 volts.
4. Temperature rating:
a. 90 degree Celsius rating in dry locations.
b. 75 degree Celsius rating in wet locations.
5. Conductors:
a. Insulation:
1) Flame-retardant PVC, 15 mils nominal thickness, with nylon jacket
4 mils nominal thickness.
b. #16 AWG stranded and tinned.
c. Color code: ICEA Method 1:
1) Pair: Black and white.
2) Triad: Black, white and red.
3) Multiple pairs or triads:
a) Color-coded and numbered.
6. Drain wire:
a. #18 AWG.
b. Stranded, tinned.
March 2021 - DRAFT 26 05 18-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 630
Item#18.
7. Jacket:
a. Flame retardant, moisture and sunlight resistant PVC.
b. Ripcord laid longitudinally under jacket to facilitate removal.
8. Shielding:
a. Individual pair/triad:
1) Minimum 1.35-mil double-faced aluminum foil-polyester tape
overlapped to provide 100 percent coverage.
b. Multiple pair or triad shielding:
1) Group shield: Minimum 1.35-mil double-faced aluminum foil-
polyester tape overlapped to provide 100 percent coverage.
2) Completely isolate group shields from each other.
3) Cable shield: 2.35 mils double-faced aluminum and synthetic
polymer backed tape overlapped to provide 100 percent coverage.
c. All shielding to be in contact with the drain wire.
E. Network cables:
1. Category 5e:
a. General:
1) Provide Cat 5e cables meeting the standards set by TIA/EIA-568-C.2
and verified by third-party testing laboratory.
b. Conductors:
1) #24 AWG solid bare annealed copper.
c. Insulation:
1) Polyolefin.
2) 4 non-bonded twisted pair cables formed into a cable core.
d. Shielding:
1) SF/FTP.
e. Color code (T568B):
1) Pair 1: White/blue stripe and blue.
2) Pair 2: White/orange stripe and orange.
3) Pair 3: White/green stripe and green.
4) Pair 4: White/brown stripe and brown.
f. Outer jacket:
1) PVC with ripcord.
g. Electrical characteristics
1) Voltage rating: 600VAC.
F. Tray cable:
1. Provide minimum size #1/0 AWG for single wires, for CT use:
a. Listed and identified on its surface as suitable for cable tray use.
2. Provide multi-conductor cable listed and identified on its surface as suitable for
cable tray use, Type TC cable in accordance with the NEC:
a. Provide with an integral white insulated conductor where a neutral is
required.
3. Ambient temperature adjustment in accordance with the NEC.
G. Fire alarm cable:
1. Number of pairs: As indicated on the Drawings or as necessary for the
application.
2. Voltage rating: 300 V minimum.
3. 2-hour fire rating in accordance with UL 2196.
4. Provide fire alarm cable in accordance with the requirements of UL 1424.
March 2021 - DRAFT 26 05 18-6 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 631
Item#18.
5. Provide Type FPLP (power-limited plenum rated)for all cabling within ducts,
plenums, and all spaces used for air handling:
a. Cable must meet NEC standards, and must have adequate fire-resistant
and low smoke-producing characteristics.
6. Provide Type FPLR (power-limited riser rated) for all vertical runs that pass
from floor to floor:
a. FPLR cable must meet NEC standards, and must have fire-resistant
characteristics capable of preventing the carrying of fire from floor to floor.
7. FPL (power-limited general purpose) is only suitable for general-purpose fire
alarm use and shall not be used for risers, ducts, plenums, and in air-handling
spaces:
a. FPL cable must meet NEC standards, and must be listed as resistant to
the spread of fire.
8. Cable substitutions are not permitted unless approved by Engineer.
9. Meets code requirements of NFPA 72 and NFPA 101.
10. Conductor insulation:
a. Low smoke PVC.
b. Minimum 105 degree Celsius rating.
11. Conductor jacket:
a. Low smoke PVC.
b. Ripcord and surface-printed with year of manufacture and cable
description at maximum 24-inch intervals.
c. Minimum 105 degree Celsius rating.
2.05 EQUIPMENT (NOT USED)
2.06 COMPONENTS (NOT USED)
2.07 ACCESSORIES
A. Wire ties:
1. One of the following or equal:
a. T&B, "Ty-Rap" cable ties.
b. Panduit, cable ties.
B. Wire markers:
1. As specified in Section 26_05_53 - Identification for Electrical Systems.
2.08 MIXES (NOT USED)
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
2.11 SOURCE QUALITY CONTROL
A. Assembly and testing of cable shall comply with the applicable requirements of
ICEA S-95-658-1999.
B. Test Type XHHW-2 in accordance with the requirements of UL 44.
March 2021 - DRAFT 26 05 18-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 632
Item#18.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Color-coding:
1. Color-coding shall be consistent throughout the facility.
2. The following color code shall be followed for all 240/120 volt and 208/120 volt
systems:
a. Phase A: Black.
b. Phase B: Red.
c. Phase C: Blue.
d. Single phase system: Black for 1 hot leg, red for the other.
e. Neutral: White.
f. High phase or wild leg: Orange.
g. Equipment ground: Green.
3. The following color code shall be followed for all 480/277 volt systems:
a. Phase A: Brown.
b. Phase B: Orange.
c. Phase C: Yellow.
d. Neutral: Gray.
e. Equipment ground: Green.
4. The following color code shall be followed for all 120 VAC control wiring:
a. Power: Red.
b. Neutral: White.
5. The following color code shall be followed for all general purpose DC control
circuits:
a. Grounded conductors: White with blue stripe.
b. Ungrounded conductors: Blue.
6. Switch legs shall be violet. 3-way switch runners shall be pink.
7. Wires in intrinsically safe circuits shall be light blue.
8. Wire colors shall be implemented in the following methods:
a. Wires manufactured of the desired color.
b. Continuously spiral wrap the first 6 inches of the wire from the termination
point with colored tape:
1) Colored tape shall be wrapped to overlap 1/2 of the width of the tape.
C. Install conductors only after the conduit installation is complete, and all enclosures
have been vacuumed clean, and the affected conduits have been swabbed clean
and dry:
1. Install wires only in approved raceways.
2. Do not install wire:
a. In incomplete conduit runs.
b. Until after the concrete work and plastering is completed.
March 2021 - DRAFT 26 05 18-8 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 633
Item#18.
D. Properly coat wires and cables with pulling compound before pulling into conduits:
1. For all #4 AWG and larger, use an approved wire-pulling lubricant while cable
is being installed in conduit:
a. Ideal Products.
b. Polywater Products.
c. 3M Products.
d. Greenlee Products.
e. Or equal as recommended by cable manufacturer.
f. Do not use oil, grease, or similar substances.
E. Cable pulling:
1. Prevent mechanical damage to conductors during installation.
2. For cables #1 AWG and smaller, install cables by hand.
3. For cables larger than #1 AWG, power pulling winches may be used if they
have cable tension monitoring equipment.
4. Provide documentation that maximum cable pulling tension was no more than
75 percent of the maximum recommended level as published by the cable
manufacturer. If exceeded, the Engineer may, at his discretion, require
replacement of the cable.
5. Ensure cable pulling crews have all calculations and cable pulling limitations
while pulling cable.
6. Make splices or add a junction box or pullbox where required to prevent cable
pulling tension or sidewall pressure from exceeding 75 percent of
manufacturer's recommendation for the specified cable size:
a. Make splices in manholes or pull boxes only.
b. Leave sufficient slack to make proper connections.
F. Use smooth-rolling sheaves and rollers when pulling cable into cable tray to keep
pulling tension and bending radius within manufacturer's recommendations.
G. Install and terminate all wire in accordance with manufacturer's recommendations.
H. Neatly arrange and lace conductors in all switchboards, panelboards, pull boxes,
and terminal cabinets by means of wire ties:
1. Do not lace wires in gutter or panel channel.
2. Install all wire ties with a flush cutting wire tie installation tool:
a. Use a tool with an adjustable tension setting.
3. Do not leave sharp edges on wire ties.
I. Terminate stranded conductors on equipment box lugs such that all conductor
strands are confined within the lug:
1. Use ring type lugs if box lugs are not available on the equipment.
J. Lighting circuits:
1. Each circuit shall have a dedicated neutral.
K. Splices:
1. Provide continuous circuits from origin to termination whenever possible:
a. Obtain Engineer's approval prior to making any splices.
2. Lighting and receptacle circuit conductors may be spliced without prior
approval from the Engineer.
March 2021 - DRAFT 26 05 18-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 634
Item#18.
3. Where splices are necessary because of extremely long wire or cable lengths
that exceed standard manufactured lengths:
a. Splice box NEMA rating requirements as specified in Section 26_05_00 -
Common Work Results for Electrical.
b. Make splices in labeled junction boxes for power conductors.
c. Make splices for control and instrument conductors in terminal boxes:
1) Provide terminal boards with setscrew pressure connectors, with
spade or ring lug connectors.
4. Power and control conductors routed in common raceways may be spliced in
common junction boxes.
5. Clearly label junction and terminal boxes containing splices with the word
"SPLICE LOCATED WITHIN".
6. Leave sufficient slack at junction boxes and termination boxes to make proper
splices and connections. Do not pull splices into conduits.
7. Install splices with compression type butt splices and insulate using a
heat-shrink sleeve:
a. In NEMA Type 4 or NEMA Type 4X areas, provide heat-shrink sleeves
that are listed for submersible applications.
8. Splices in below grade pull boxes, in any box subject to flooding, and in wet
areas shall be made waterproof using:
a. A heat shrink insulating system listed for submersible applications.
b. Or an epoxy resin splicing kit.
L. Apply wire markers to all wires at each end after being installed in the conduit and
before meg-ohm testing and termination.
M. Instrumentation class cable:
1. Install instrumentation class cables in separate raceway systems from power
cables:
a. Install instrument cable in metallic conduit within non-dedicated manholes
or pull boxes.
b. Install cable without splices between instruments or between field devices
and instrument enclosures or panels.
2. Do not make intermediate terminations, except in designated terminal boxes
as indicated on the Drawings.
3. Shield grounding requirements as specified in Section 26_05_26 - Grounding
and Bonding.
N. Copper Ethernet cables:
1. Comply with TIA/EIA-568-C.2.
2. Pathways:
a. For initial installation, the maximum fill capacity for pathways (i.e. conduit,
raceways, trays, baskets) is 40 percent. The maximum fill capacity of
60 percent is allowed to accommodate future additions after initial
installation.
b. Conduit should be run in the most direct route possible with no more than
two 90 degree bends between pull boxes and serve no more than 3 outlet
boxes.
3. Cable bend radius:
a. Proper cable bend radius control must be maintained throughout the
pathways. The bend radius needs to be at a minimum 10 times the cable
diameter.
March 2021 - DRAFT 26 05 18-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_18(IDS50) Page 635
Item#18.
4. Cable pulling:
a. Provide cable pulling swivel system to prevent winding and tangling of
rope and cables during pull.
b. The maximum pulling tension is not to exceed manufacturer
recommendations. Cable installation should not in any way deform the
cable jacket.
c. Do not install bruised, kinked, scored, deformed, or abraded cable. Do not
splice cable between termination, tap, or junction points. Remove and
discard cable if damaged during installation and replace it with new cable.
5. Cable management:
a. Organize and manage cables for quick and easy moves, adds and
changes.
6. Testing:
a. All cables and termination hardware shall be 100 percent tested for
defects in installation and to verify cabling system performance under
installed conditions according to the requirements of TIA/EIA-568-C.1
Section 11.
1) All pairs of each installed cable shall be verified prior to system
acceptance.
2) Any defect in the cabling system installation including but not limited
to cable, connectors, feed through couplers, patch panels, and
connector blocks shall be repaired or replaced in order to ensure 100
percent useable conductors in all cables installed.
b. All twisted-pair copper cable links shall be tested for compliance to the
requirements in TIA/EIA/568-C.2 for the appropriate Category of cabling
installed.
c. All cables shall be tested in accordance with the contract documents,
TIA/EIA standards, and best industry practice.
d. The field test equipment shall meet the requirements of TIA/EIA-568-C.
The appropriate level III tester shall be used to verify Category 6 cabling.
e. Visually inspect UTP jacket materials for NRTL certification markings.
Inspect cabling terminations in communications equipment rooms for
compliance with color-coding for pin assignments, and inspect cabling
connections for compliance with TIA/EIA-568-C.1.
f. Visually inspect cable placement, cable termination, grounding and
bonding, equipment and labeling of all components.
g. Test UTP copper cabling for DC loop resistance, shorts, opens,
intermittent faults, and polarity between conductors.
1) Test operation of shorting bars in connection blocks.
2) Test cables after termination but not cross-connection.
a) Test instruments shall meet or exceed applicable requirements
in TIA/EIA-568-C.2.
(1) Perform tests with a tester that complies with performance
requirements in "Test Instruments (Normative)" Annex,
complying with measurement accuracy specified in
"Measurement Accuracy (Informative)" Annex.
(2) Use only test cords and adapters that are qualified by test
equipment manufacturer for channel or link test
configuration.
March 2021 - DRAFT 26 05 18-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 636
Item#18.
7. Separation from EMI sources:
a. Comply with TIA/EIA-569-B recommendations for separating unshielded
copper voice and data communication cable from potential EMI sources,
including electrical power lines and equipment.
b. Separation between open communications cables or cables in nonmetallic
raceways and unshielded power conductors and electrical equipment
shall be as follows:
1) Electrical Equipment Rating Less Than 2 kVA: A minimum of
5 inches.
2) Electrical Equipment Rating between 2 and 5 kVA: A minimum of
12 inches.
3) Electrical Equipment Rating More Than 5 kVA: A minimum of
24 inches
c. Separation between communications cables in grounded metallic
raceways and unshielded power lines or electrical equipment shall be as
follows:
1) Electrical Equipment Rating Less Than 2 kVA: A minimum of
2-1/2 inches.
2) Electrical Equipment Rating between 2 and 5 kVA: A minimum of
6 inches.
3) Electrical Equipment Rating More Than 5 kVA: A minimum of
12 inches.
d. Separation between communications cables in grounded metallic
raceways and power lines and electrical equipment located in grounded
metallic conduits or enclosures shall be as follows:
1) Electrical Equipment Rating Less Than 2 kVA: No requirement.
2) Electrical Equipment Rating between 2 and 5 kVA: A minimum of
3 inches.
3) Electrical Equipment Rating More Than 5 kVA: A minimum of
6 inches.
e. Separation between Communications Cables and Electrical Motors and
Transformers, 5 kVA or HP and Larger: A minimum of 48 inches.
O. Multi-conductor cable:
1. Where cable is not routed in conduit with a separate ground conductor, use
1 conductor in the cable as a ground conductor:
a) Use an internal ground conductor, if it is no smaller than as indicated on
the Drawings and in accordance with NEC requirements for equipment
ground conductor size.
b) Where 2 parallel cables are used, and the internal ground conductor in
each cable does not meet NEC requirements for the combined circuit, use
4-conductor cable, with one of the full-sized conductors serving as
ground.
P. Fire alarm cable:
1. Install fire alarm cable in dedicated metallic raceways as indicated on the
Drawings.
Q. Signal cable:
1. Separate and isolate electrical signal cables from sources of electrical noise
and power cables by minimum 12 inches.
March 2021 - DRAFT 26 05 18-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_18(IDS50) Page 637
Item#18.
R. Wiring allowances:
1. Equipment locations may vary slightly from the drawings. Include an allowance
for necessary conductors and terminations for motorized equipment, electrical
outlets, fixtures, communication outlets, instruments, and devices within
10 linear feet of locations indicated on the Drawings.
2. Locations for pull boxes, manholes, and duct banks may vary slightly from the
drawings. Include an allowance for necessary conductors and related
materials to provide conductors to all pull boxes, manholes and duct banks
within 20 linear feet of locations indicated on the Drawings.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. As specified in Section 01_75_17 - Commissioning.
3.08 FIELD QUALITY CONTROL
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Grounding:
1. As specified in Section 26_05_26 - Grounding and Bonding.
3.09 ADJUSTING (NOT USED)
3.10 CLEANING (NOT USED)
3.11 PROTECTION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 26 05 18-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_18(IDS50) Page 638
Item#18.
SECTION 26_05_21
LOW VOLTAGE WIRE CONNECTIONS
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Wire connecting devices.
2. Terminations.
3. Splices.
1.02 REFERENCES
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. ASTM International (ASTM):
1. D3005 - Standard Specification for Low-Temperature Resistant Vinyl Chloride
Plastic Pressure-Sensitive Electrical Insulating Tape.
C. CSA International (CSA):
1. C22.2 - No.197-M1983 (R2208) - PVC Insulating Tape.
D. Underwriters Laboratories, Inc. (UL):
1. 510 - Standard for Polyvinyl Chloride, Polyethylene, and Rubber Insulating
Tape.
1.03 DEFINITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.04 SYSTEM DESCRIPTION
A. Provide a complete system of wiring connectors, terminators, fittings, etc. for a
complete wiring system suitable for the cables and conductors used.
1.05 SUBMITTALS
A. Furnish submittals as specified in Sections 013300 - Submittal Procedures and
26 05 00 - Common Work Results for Electrical.
B. Product data:
1. Catalog cut sheets.
2. Installation instructions.
1.06 QUALITY ASSURANCE
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. All materials shall be UL listed.
March 2021 - DRAFT 26 05 21-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_21(IDS50) Page 640
Item#18.
1.07 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.08 PROJECT OR SITE CONDITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING (NOT USED)
1.11 WARRANTY
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.12 SYSTEM START-UP
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 MAINTENANCE (NOT USED)
PART PRODUCTS
2.01 MANUFACTURERS
A. Manufacturers for each type of technology are specified with the equipment in this
Section.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS (NOT USED)
2.04 MANUFACTURED UNITS (NOT USED)
2.05 EQUIPMENT
A. Control connections:
1. Use insulated ring type wire terminators for connections to all screw terminals:
a. With chamfered/funneled terminal barrel entry.
b. Deep internal serrations.
c. Long barrel design to reduce electrical resistance and increased
insulator-barrel surface area to ensure that the insulator remains in
contact with the barrel.
d. Electroplated-tin copper conductor.
e. Manufacturers: The following or equal:
1) Thomas and Betts, Stakon.
2. For process equipment connections work from manufacturer's drawings.
March 2021 - DRAFT 26 05 21-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_21(IDS50) Page 641
Item#18.
B. Joints, splices, taps, and connections:
1. 600-volt conductors:
a. Use solderless connectors.
b. Use only plated copper alloy connectors or lugs:
1) Aluminum connectors or lugs are not acceptable for copper
conductors.
c. Under those specific conditions where aluminum conductors have been
allowed or are specified then the connectors for aluminum conductors
shall be specifically designed for that purpose.
d. For wire Number 10 AWG and smaller use compression splice caps, with
insulating caps:
1) Manufacturers: The following or equal:
a) Buchanan, 2006S or 2011 S, with 2007 or 2014 insulating caps.
e. For wire Number 8 AWG and larger, use heavy duty copper compression
connectors:
1) Manufacturers: One of the following or equal:
a) Burndy.
b) Thomas and Betts.
f. Heat shrink tubing:
1) Suitable for indoors, outdoors, overhead, direct burial or submerged
applications.
2) Minimum shrink ratio: 4 to 1.
3) Continuous operating temperature: -55 degrees Celsius to
110 degrees Celsius.
4) Internally applied adhesive sealant.
5) Cross-linked polyolefin:
a) Manufacturers: One of the following or equal:
(1) 3M, ITCSN.
(2) Thomas & Betts, Shrink-Kon.
2. Instrumentation class cable splices:
a. Suitable for indoor, outdoors, weather exposed, direct buried, or
submersed applications.
b. Utilizing an epoxy, polyurethane, and re-enterable compounds.
c. For use with shielded or unshielded plastic- and rubber-jacketed, signal,
control, and power cables rated up to 1 kilovolt.
d. Two-part mold body with tongue and groove seams and built in spacer
webbing.
e. Manufacturers: The following or equal:
1) 3M, Scotchcast 72-N.
C. Insulating tape:
1. General purpose insulating tape:
a. Minimum 7 mil vinyl tape.
b. Suitable for application in an ambient of-18 degrees Celsius
(0 degrees Fahrenheit).
c. Operating range up to 105 degrees Celsius (220 degrees Fahrenheit).
d. Flame retardant, hot- and cold- weather resistant, UV resistant.
e. For use as a primary insulation for wire cable splices up to 600 VAC.
f. Meeting and complying with:
1) ASTM D3005 Type I.
2) UL 510.
3) CSA C22.2.
March 2021 - DRAFT 26 05 21-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_21(IDS50) Page 642
Item#18.
g. Manufacturers: The following or equal:
1) 3M, Scotch Number Super 33+.
2. General-purpose color-coding tape:
a. Minimum 7 mil vinyl tape.
b. Suitable for application on PVC and polyethylene jacketed cables.
c. For use indoors and outdoors in weather protected enclosures.
d. Available with the following colors:
1) Red.
2) Yellow.
3) Blue.
4) Brown.
5) Gray.
6) White.
7) Green.
8) Orange.
9) Violet.
e. For use as phase identification, marking, insulating, and harnessing.
f. Meeting and complying with:
1) UL 510.
2) CSA C22.2.
g. Manufacturers: The following or equal:
1) 3M, Scotch Number 35.
2.06 COMPONENTS (NOT USED)
2.07 ACCESSORIES (NOT USED)
2.08 MIXES (NOT USED)
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
2.11 SOURCE QUALITY CONTROL (NOT USED)
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Load connections:
1. Connect loads to the circuits as indicated. Color-code all branch circuits as
specified in Section 26_05_18 - 600-Volt or Less Wires and Cables.
C. Zero to 600-volt systems:
1. Make all connections with the proper tool and die as specified by the device
manufacturer.
March 2021 - DRAFT 26 05 21-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_21(IDS50) Page 643
Item#18.
2. Use only tooling and dies manufactured by the device manufacturer.
3. Insulate all connections and splices with Scotch 33+ tape and Scotchfill, or
pre-molded plastic covers, or heat shrink tubing and caps.
4. Number all power and control wires before termination.
D. Motor connections (600 volts and below):
1. Terminate all leads and wires with compression type ring lugs.
2. Terminations on all motor leads, including leads that are connected together to
accommodate the motor voltage, and the machine wires entering the motor
terminal box from the power source, shall have ring type compression lugs.
3. Cover bolted connectors with a heat shrinkable, cross-linked polyolefin
material formed as a single opening boot:
a. In damp and wet locations, use a complete kit containing mastic that shall
seal out moisture and contamination.
b. Shrink cap with low heat as recommended by manufacturer.
4. Wire markers shall be readable after boot installation.
5. Manufacturers: The following or equal:
a. Raychem, MCK.
b. Elastimold.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. As specified in Section 01_75_17 - Commissioning.
3.08 FIELD QUALITY CONTROL
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
3.09 ADJUSTING (NOT USED)
3.10 CLEANING (NOT USED)
3.11 PROTECTION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 26 05 21-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_21(IDS50) Page 644
Item#18.
SECTION 26_05_26
GROUNDING AND BONDING
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Grounding materials and requirements.
1.02 REFERENCES
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. ASTM International (ASTM):
1. B3 - Standard Specification for Soft or Annealed Copper Wire.
2. B8 - Standard Specification for Concentric-Lay-Stranded Copper Conductors,
Hard, Medium-Hard, or Soft.
3. B33 — Standard Specification for Tin-Coated Soft or Annealed Copper Wire for
Electrical Purposes.
C. Institute of Electrical and Electronics Engineers (IEEE):
1. 81 - IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and
Earth Surface Potentials of a Grounding System.
D. Underwriters Laboratories, Inc. (UL):
1. 467 - Ground and Bonding Equipment.
1.03 DEFINITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 013300 - Submittal Procedures and
26 05 00 - Common Work Results for Electrical.
B. Product data:
1. Catalog cut sheets.
1.05 QUALITY ASSURANCE
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. All grounding components and materials shall be UL listed and labeled.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.07 PROJECT/SITE CONDITIONS (NOT USED)
March 2021 - DRAFT 26 05 26-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_26(IDS50) Page 646
Item#18.
1.08 SEQUENCING (NOT USED)
1.09 SCHEDULING (NOT USED)
1.10 WARRANTY
A. As specified in Section 26_05_00 - Common Work Results for Electrical
1.11 SYSTEM START-UP
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.12 OWNER'S INSTRUCTIONS (NOT USED)
1.13 MAINTENANCE (NOT USED)
PART PRODUCTS
2.01 MANUFACTURERS
A. Compression connectors: One of the following or equal:
1. Erico.
2. Harger.
3. Burndy.
4. Thomas & Betts.
B. Exothermic connectors: One of the following or equal:
1. Erico.
2. Harger.
3. Burndy.
4. Thomas & Betts.
C. Ground rods: One of the following or equal:
1. Erico.
2. Harger.
3. Nehring
4. Thomas & Betts.
D. Ground cable: One of the following or equal:
1. Erico.
2. Harger
3. Nehring.
4. Southwire.
E. Precast ground well boxes: One of the following or equal:
1. Brooks Products, 3-RT Valve Box.
2. Christy Concrete Products, G12 Valve Box.
2.02 SYSTEM DESCRIPTION
A. Ground equipment and raceway systems so that the completed installation
conforms to all applicable code requirements.
March 2021 - DRAFT 26 05 26-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_26(IDS50) Page 647
Item#18.
B. Provide a complete electrical grounding system as indicated on the Drawings and
as specified including but not limited to:
1. Grounding electrodes.
2. Bonding jumpers.
3. Ground connections.
C. Provide bonding jumpers and wire, grounding bushings, clamps and appurtenances
required for complete grounding system to bond equipment and raceways to
equipment grounding conductors.
D. The ground system resistance (electrode to ground) of the completed installation,
as determined by tests specified in Section 26_08_50 - Field Electrical Acceptance
Tests, shall be:
1. 5 ohms or less for industrial systems.
2. 1 ohm or less for electrical buildings.
2.03 EXISTING PRODUCTS (NOT USED)
2.04 MATERIALS
A. Ground rod:
1. Minimum: 3/4-inch diameter, 10 feet long.
2. Uniform 10 mil covering of electrolytic copper metallically bonded to a rigid
steel core:
a. The copper-to-steel bond shall be corrosion resistant.
3. In accordance with UL 467.
4. Sectional type joined by threaded copper alloy couplings.
5. Fit the top of the rod with a threaded coupling and steel-driving stud.
B. Ground cable:
1. Requirements:
a. Soft drawn (annealed).
b. Concentric lay, coarse stranded in accordance with ASTM B8.
c. Bare copper in accordance with ASTM B3.
d. Bare tinned-copper in accordance with ASTM B33.
2. Size is as indicated on the Drawings, but not less than required by the NEC.
Use the following type of wire unless otherwise indicated on the Drawings:
a. Size #6 AWG and smaller; solid conductor.
b. Size #4 AWG and larger; stranded conductor.
C. Compression connectors:
1. Manufactured of high copper alloy specifically for the particular grounding
application.
2. Suitable for direct burial in earth and concrete.
3. Identifying compression die number inscription to be impressed on
compression fitting.
4. Barrels prefilled and sealed with oxide-inhibiting and anti-seizing compound.
D. Exothermic welds:
1. Current carrying capacity equal to that of the conductor.
2. Permanent molecular bond that cannot loosen or corrode over time.
3. Will not deteriorate with age.
4. Use low emission welds for indoor installations.
March 2021 - DRAFT 26 05 26-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_26(IDS50) Page 648
Item#18.
E. Equipment grounding conductors:
1. Conductors shall be the same type and insulation as the load circuit
conductors:
a. Use 600-volt insulation for the equipment grounding conductors for
medium voltage systems.
2. Minimum size in accordance with the NEC.
F. Grounding electrode conductors:
1. Minimum size in accordance with the NEC.
G. Main bonding jumpers and bonding jumpers:
1. Minimum size in accordance with the NEC.
2.05 MANUFACTURED UNITS (NOT USED)
2.06 EQUIPMENT (NOT USED)
2.07 COMPONENTS (NOT USED)
2.08 ACCESSORIES
A. Precast ground well boxes:
1. Minimum 10 inch interior diameter.
2. Traffic-rated cast iron cover.
3. Permanent "GROUND" marking on cover.
2.09 MIXES (NOT USED)
2.10 FABRICATION (NOT USED)
2.11 FINISHES (NOT USED)
2.12 SOURCE QUALITY CONTROL (NOT USED)
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Provide a separate, green insulated, grounding conductor in each raceway
independent of raceway material:
1. Multi-conductor power and control cables shall include an integral green
insulated grounding conductor.
2. Provide a separate grounding conductor in each individual raceway for parallel
feeders.
March 2021 - DRAFT 26 05 26-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_26(IDS50) Page 649
Item#18.
C. Provide a separate grounding conductor for each motor and connect at motor
terminal box. Do not use bolts securing motor box to frame or cover for grounding
connectors:
1. When grounding motors driven by variable frequency drives (VFD) comply with
the requirements of the VFD manufacturer.
D. Provide a grounding type bushing with lug for connection of grounding conductor for
conduits that originate from each motor control center section, switchboard, or
panelboard:
1. Individually bond these raceways to the ground bus in the equipment.
E. Provide grounding type bushings with lugs for connection of grounding conductor at
both ends of metallic conduit runs. Bond ground bushings to the grounding system.
F. Provide a green insulated wire-grounding jumper from the ground screw to a box
grounding screw and, for grounding type devices, to equipment grounding
conductor.
G. Interconnect the secondary switchgear, switchboard, or panelboard neutral bus to
the ground bus in the secondary switchgear, switchboard, or panelboard
compartment, only at service entrance point or after a transformer.
H. Duct bank ground system:
1. Provide a bare copper grounding conductor the entire length of each duct
bank, embedded in the concrete of the duct bank as indicated on the Drawings
and specified in the Specifications.
2. Bond duct bank ground conductors together where duct banks join, merge,
intersect, or split.
I. Grounding at service (600 V or Less):
1. Connect the neutral to ground only at one point within the enclosure of the first
disconnecting means on the load side of the service transformer.
J. Ground connections:
1. All connections to the ground grid system, the duct bank grounding system,
equipment, ground rods, etc., shall be made using compression type
grounding connectors or exothermic welds as indicated on the Drawings, UL
listed, and labeled for the application.
2. Make ground connections in accordance with the manufacturer's instructions.
3. Do not conceal or cover any ground connections until the Engineer or
authorized representative has established and provided written confirmation
that every grounding connection is as indicated on the Drawings and specified
in the Specifications.
K. Grounding electrode system:
1. Ground ring:
a. Provide all trenching and materials necessary to install the ground ring as
indicated on the Drawings.
b. Ground ring conductor shall be in direct contact with the earth, or where
embedded, concrete, of the size as indicated on the Drawings.
c. Minimum burial depth 36 inches or as indicated on the Drawings.
d. Re-compact disturbed soils to original density in 6-inch lifts.
March 2021 - DRAFT 26 05 26-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_26(IDS50) Page 650
Item#18.
2. Ground rods:
a. Locations as indicated on the Drawings.
b. Length of rods forming an individual ground array shall be equal in length.
c. Drive ground rods and install grounding conductors before construction of
concrete slabs and duct banks.
d. Install all ground rods, coupled, to result in an overall length of 20 foot
each.
3. Metal underground water pipe:
a. Bond metal underground domestic water pipe to grounding electrode
system.
4. Metal frame of building or structure:
a. Bond metal frame of building or structure to grounding electrode system.
5. Extend grounding conductors through concrete to accessible points for
grounding equipment and electrical enclosures.
6. Where grounding conductors are not concrete-encased or direct buried, install
in Schedule 40 PVC conduit for protection.
7. Install grounding system at each structure where switchgear, motor control
centers, switchboards, panelboards, panels, or other electrical equipment are
installed.
L. Shield grounding:
1. Analog signal cables shields shall only be grounded at a single point in the
loop. Unless otherwise noted, ground signal cable shields at control panel.
2. For communication and data line signal cable shields and drain wires should
be grounded at both ends of the cable run.
3. Insulate the shielding and exposed drain wire for each signal cable with heat-
shrink tubing.
4. Terminate the signal cable shield on a dedicated grounding terminal block.
M. Where indicated on the Drawings, install ground rods in precast ground wells.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. As specified in Section 01_75_17 - Commissioning.
3.08 FIELD QUALITY CONTROL
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Measure grounding electrode system resistance to ground in accordance with
IEEE 81.
March 2021 - DRAFT 26 05 26-6 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_26(IDS50) Page 651
Item#18.
3.09 ADJUSTING
A. Under the direction of the Engineer, add additional parallel connected ground rods
and/or deeper driven rods until the ground resistance measurement meets the
specified resistance requirements:
1. Use of salts, water, or compounds to attain the specified ground resistance is
not acceptable.
3.10 CLEANING (NOT USED)
3.11 PROTECTION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 26 05 26-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_26(IDS50) Page 652
Item#18.
SECTION 26_05_53
IDENTIFICATION FOR ELECTRICAL SYSTEMS
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Identification of electrical equipment, devices, and components.
2. Material, manufacturing, and installation requirements for identification
devices.
B. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 01 75 17 - Commissioning.
3. Section 26 05 00 - Common Work Results for Electrical.
4. Section 26 05 33 - Conduits.
5. Section 26 06 01 - Conduit Schedule.
1.02 REFERENCES
A. As specified in Section 26_05_00.
B. Occupational Safety and Health Administration (OSHA).
1.03 DEFINITIONS
A. As specified in Section 26_05_00.
1.04 SYSTEM DESCRIPTION
A. Nameplates:
1. Provide a nameplate for each piece of electrical equipment and devices,
control panel and control panel components in accordance with Owner
Standard.
2. Provide all nameplates of identical style, color, and material throughout the
facility.
3. Device nameplates information:
a. Designations as indicated on the Drawings and identified on the Process
and Instrumentation Drawings.
b. All nameplates shall be reviewed and approved by Owner.
B. Wire numbers:
1. Coordinate the wire numbering system with all vendors of equipment so that
every field wire has a unique number associated with it for the entire system:
a. Wire numbers shall correspond to the wire numbers on the control
drawings or the panel and circuit numbers for receptacles and lighting.
b. Wire numbers shall correspond to the documented drawings of the control
panel.
March 2021 - DRAFT 26 05 53-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_53(IDS50) Page 654
Item#18.
c. Internal panel wires on a common terminal shall have the same wire
number.
d. Multi-conductor cables shall be assigned a cable number that shall be
attached to the cable at intermediate pull boxes and stub-up locations
beneath freestanding equipment. All multi-conductor and instrumentation
cables shall be identified at pull points as described above:
1) Label armored multi-conductor cable using the conduit number as
indicated on the Drawings, following the requirements for conduit
markers in Section 26 05 33.
2. Provide the following wiring numbering schemes throughout the project for
field wires between process control module, (PLC), vendor control panels,
(VCP), motor control centers, (MCC), field starters, field instruments, etc.
(ORIGIN LOC.)-(ORIGIN TERM.)/(DEST. LOC.)-(DEST. TERM.)
OR
(ORIGIN LOC.)-(ORIGIN TERM.)
(DEST. LOC.)-(DEST. TERM.)
Where:
ORIGIN LOC. = Designation for originating panel or device
ORIGIN TERM. = Terminal designation at originating panel or device
DEST. LOC. = Designation for destination panel or device
DEST. TERM. = Terminal designation at destination panel or device or PLC
1/0 address at destination panel:
a. Identify equipment and field instruments as the origin.
b. PLCs are always identified as the destination.
c. Location is the panel designation for VCP, LCP, or PLC. For connections
to MCCs, location is the specific starter tag and loop number. Location is
the tag and loop number for motor starters, field instruments and
equipment. Any hyphen in the panel designation or tag and loop number
shall be omitted.
d. Terminal designation is the actual number on the terminal block where the
conductor terminates at field devices and vendor control panels. For multi-
conductor cables, all terminal numbers shall be shown, separated by
commas.
e. Terminal designations at motor leads shall be the motor manufacturer's
standard terminal designation (e.g. T1, T2, T3, etc.).
f. Refer to final loop drawings provided by Owner for wire labeling.
1.05 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 26_05_00.
March 2021 - DRAFT 26 05 53-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_53(IDS50) Page 655
Item#18.
B. Product data:
1. Nameplates:
a. Color.
b. Size:
1) Outside dimensions.
2) Lettering.
c. Material.
d. Mounting means.
2. Nameplate schedule:
a. Show exact wording for each nameplate.
b. Include nameplate and letter sizes.
3. Wire numbers:
a. Manufacturer's catalog data for wire labels and label printer.
C. Record documents:
1. Update the conduit schedule to reflect the exact quantity of wire numbers
including spares and destination points for all wires.
1.06 QUALITY ASSURANCE (NOT USED)
1.07 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 26_05_00.
1.08 PROJECT SITE CONDITIONS (NOT USED)
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING (NOT USED)
1.11 WARRANTY
A. As specified in Section 26_05_00.
1.12 SYSTEM START-UP
A. As specified in Section 26_05_00.
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 MAINTENANCE (NOT USED)
PART PRODUCTS
2.01 MANUFACTURERS
A. Nameplates and signs:
1. One of the following or equal:
a. Brady, Identoline deteactable warning tapes for underground installations,
Brady fiberglass or phenolic plastic for area signs.
b. Seton.
March 2021 - DRAFT 26 05 53-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_53(IDS50) Page 656
Item#18.
B. Conductor and cable markers:
1. Heat-shrinkable tubing:
a. One of the following or equal:
1) Raychem.
2) Brady.
3) Thomas & Betts.
4) Kroy.
2. Marker printer:
a. The following or equal:
1) Brady.
3. Pre-printed slip-on sleeve markers:
a. The following or equal:
1) Grafoplast.
2) Engineer knows of no equal.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS
A. Nameplates:
1. Fabricated from white-center and blue face laminated plastic engraving stock:
a. 3/32-inch thick material.
b. Two-ply.
c. With chamfered edges.
d. Block style engraved characters of adequate size to be read easily from a
distance of 6 feet:
1) No characters smaller than 1/8-inch in height.
B. Signs:
1. Automatic equipment and high voltage signs:
a. Suitable for exterior use.
b. In accordance with OSHA regulations.
C. Conduit and raceway markers:
1. Stainless Steel.
2.04 MANUFACTURED UNITS (NOT USED)
2.05 EQUIPMENT (NOT USED)
2.06 COMPONENTS (NOT USED)
2.07 ACCESSORIES (NOT USED)
2.08 MIXES (NOT USED)
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
March 2021 - DRAFT 26 05 53-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_05_53(IDS50) Page 657
Item#18.
2.11 SOURCE QUALITY CONTROL
A. Nameplates:
1. Provide all nameplates for control panel operator devices (e.g. pushbuttons,
selector switches, pilot lights, etc.):
a. Same material and same color and appearance as the device
nameplates, in order to achieve an aesthetically consistent and
coordinated system.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 26_05_00.
B. Nameplates:
1. Attach nameplates to equipment with rivets, bolts or sheet metal screws,
approved waterproof epoxy-based cement or install in metal holders welded to
the equipment.
2. On NEMA Type 4, NEMA Type 4X, or NEMA Type 7 enclosures, use epoxy-
based cement to attach nameplates.
3. Nameplates shall be aligned and level or plumb to within 1/64 inch over the
entire length:
a. Misaligned or crooked nameplates shall be remounted, or provide new
enclosures at the discretion of the Engineer.
C. Conductor and cable markers:
1. Apply all conductor and cable markers before termination.
2. Heat-shrinkable tubing:
a. Tubing shall be shrunk using a heat gun that produces low temperature
heated air.
b. Tubing shall be tight on the wire after it has been heated.
c. Characters shall face the open panel and shall read from left to right or
top to bottom.
d. Markers shall be aligned and be in an unobstructed view.
D. Conduit markers:
1. Furnish and install conduit markers for every conduit in the electrical system
that is identified in the conduit schedule or part of the process system:
a. Conduit markings shall match the conduit schedule.
2. Mark conduits at the following locations:
a. All conduits routing below grade.
b. All conduits that cannot be traced visually.
3. Mark conduits after the conduits have been fully painted.
4. Position conduit markers so that they are easily read from the floor.
March 2021 - DRAFT 26 05 53-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_53(IDS50) Page 658
Item#18.
5. Attach tags with Type 316 stainless steel wires.
6. Mark conduits before construction review by Engineer for punch list purposes.
7. Label intrinsically safe conduits in accordance with the requirements of the
NEC.
E. Signs and labeling:
1. Furnish and install permanent warning signs at mechanical equipment that
may be started automatically or from remote locations:
a. Fasten warning signs with round head stainless steel screws or bolts.
b. Locate and mount in a manner to be clearly legible to operations
personnel.
2. Furnish and install permanent and conspicuous warning signs on equipment
(front and back), doorways to equipment rooms, pull boxes, manholes, etc.,
where the voltage exceeds 600 volts.
3. Furnish and install warning signs on equipment that has more than one source
of power.
a. Warning signs to identify every panel and circuit number of the
disconnecting means of all external power sources.
4. Place warning signs on equipment that has 120 VAC control voltage source
used for interlocking.
a. Identify panel and circuit number or conductor tag for control voltage
source disconnecting means.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. As specified in Section 01_75_17.
3.08 FIELD QUALITY CONTROL
A. Replace any nameplates, signs, conductor markers, cable markers, or raceway
labels that in the sole opinion of the Engineer do not meet the Engineer's aesthetic
requirements.
3.09 ADJUSTING (NOT USED)
3.10 CLEANING (NOT USED)
3.11 PROTECTION (NOT USED)
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 26 05 53-6 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_05_53(IDS50) Page 659
Item#18.
SECTION 26_28_01
LOW VOLTAGE MOLDED CASE CIRCUIT BREAKERS
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Low voltage molded case circuit breakers.
1.02 REFERENCES
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. National Electrical Manufacturers Association (NEMA):
1. AB 3. - Molded Case Circuit Breakers and Their Application.
C. Underwriter's Laboratories (UL):
1. 489 - Molded-Case Circuit Breakers, Molded-Case Switches, and Circuit-
Breaker Enclosures.
2. 943 - Ground Fault Circuit Interrupters.
1.03 DEFINITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. In accordance with UL 489.
1.04 SYSTEM DESCRIPTION
A. Molded case thermal magnetic or motor circuit protector type circuit breakers as
indicated on the Drawings and connected to form a completed system.
1.05 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 - Submittal Procedures and
26 05 00 - Common Work Results for Electrical.
B. Product data:
1. Catalog cut sheets.
2. Manufacturer's time-current curves for all molded case circuit breakers
furnished.
1.06 QUALITY ASSURANCE
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
B. Low voltage molded case circuit breakers shall be UL listed and labeled.
March 2021 - DRAFT 26 28 01-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_28_01(IDS50) Page 660
Item#18.
1.07 DELIVERY, STORAGE AND HANDLING
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.08 PROJECT OR SITE CONDITIONS
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING (NOT USED)
1.11 WARRANTY
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.12 SYSTEM START-UP
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 MAINTENANCE (NOT USED)
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. Eaton.
2. General Electric Co.
3. Schneider Electric.
4. ABB.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS (NOT USED)
2.04 MANUFACTURED UNITS
A. General:
1. Conforming to UL 489.
2. Operating mechanism:
a. Quick-make, quick-break, non-welding silver alloy contacts.
b. Common Trip, Open and Close for multi-pole breakers such that all poles
open and close simultaneously.
c. Mechanically trip free from the handle.
d. Trip indicating handle - automatically assumes a position midway between
the manual ON and OFF positions to clearly indicate the circuit breaker
has tripped.
e. Lockable in the "OFF" position.
March 2021 - DRAFT 26 28 01-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_28_01(IDS50) Page 661
Item#18.
3. Arc extinction:
a. In arc chutes.
4. Voltage and current ratings:
a. Minimum ratings as indicated on the Drawings.
b. Minimum frame size 100A.
5. Interrupting ratings:
a. Minimum ratings as indicated on the Drawings.
b. Not less than the rating of the assembly (panelboard, switchboard, motor
control center, etc.).
B. Motor circuit protectors:
1. Instantaneous only circuit breaker as part of a listed combination motor
controller.
2. Each pole continuously adjustable in a linear scale with `LO' and `HI' settings
factory calibrated.
2.05 EQUIPMENT (NOT USED)
2.06 COMPONENTS
A. Terminals:
1. Line and load terminals suitable for the conductor type, size, and number of
conductors in accordance with UL 489.
B. Case:
1. Molded polyester glass reinforced.
2. Ratings clearly marked.
C. Trip units:
1. Provide thermal magnetic or solid-state trip units as indicated on the Drawings.
2. Thermal magnetic:
a. Instantaneous short circuit protection.
b. Inverse time delay overload.
c. Ambient or enclosure compensated by means of a bimetallic element.
3. Solid state:
a. With the following settings as indicated on the Drawings:
1) Adjustable long time current setting.
2) Adjustable long time delay.
3) Adjustable short time pickup.
4) Adjustable short time delay.
5) Adjustable instantaneous pickup.
6) Adjustable ground fault pickup as indicated on the Drawings.
7) Adjustable ground fault delay as indicated on the Drawings.
D. Provide ground fault trip devices as indicated on the Drawings.
E. Molded case circuit breakers for use in panelboards:
1. Bolt-on type:
a. Plug-in type breakers are not acceptable.
2. Ground fault trip devices as indicated on the Drawings.
March 2021 - DRAFT 26 28 01-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_28_01(IDS50) Page 662
Item#18.
2.07 ACCESSORIES
A. Lockable handle:
1. Provide assembly to lock operating handle in `OPEN' position.
2. Where a molded case circuit breaker is located in a dedicated enclosure,
provide a lockable handle. Reference the Electrical Specifications for
additional locking requirements associated with other mounting installations.
2.08 MIXES (NOT USED)
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
2.11 SOURCE QUALITY CONTROL
A. Test breakers in accordance with:
1. U L 489.
2. Manufacturer's standard testing procedures.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. Install breakers to correspond to the accepted shop drawings.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. As specified in Section 01_75_17 - Commissioning.
3.08 FIELD QUALITY CONTROL
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
3.09 ADJUSTING
A. Adjust trip settings in accordance with Protective Device Coordination Study as
accepted by the Engineer and in accordance with manufacturer's
recommendations.
B. Adjust motor circuit protectors in accordance with NEC and the manufacturer's
recommendation based on the nameplate values of the installed motor.
March 2021 - DRAFT 26 28 01-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/26_28_01(IDS50) Page 663
Item#18.
3.10 CLEANING (NOT USED)
3.11 PROTECTION
A. As specified in Section 26_05_00 - Common Work Results for Electrical.
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 26 28 01-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel26_28_01(IDS50) Page 664
Item#18.
SECTION 40_05_57.23
ELECTRIC ACTUATORS
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Electric motor-driven actuators for gate valves as identified in the
actuator schedule.
B. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 46_05_10 - Common Work Results for Mechanical Equipment.
1.02 REFERENCES
A. American Water Works Association (AWWA):
1. C540 - AWWA Standard for Power-Actuating Devices for Valves and Slide
Gates.
B. National Electrical Manufacturers Association (NEMA):
1. 250 - Enclosures for Electrical Equipment (1000 V Maximum).
1.03 DEFINITIONS
A. NEMA:
1. Type 4X enclosure in accordance with NEMA 250.
1.04 SUBMITTALS
A. Submit as specified in Sections 01_33_00 and 46_05_10.
B. Provide a complete list/schedule of all actuators being provided with their
associated tag names as indicated on the design Drawings and/or Specifications,
service process area and the size of the valve they are actuating.
C. Clearly identify any exceptions in terms of quantities and/or quality of actuator(s)
being submitted.
D. Product data:
1. Electrical ratings:
a. Voltage and number of phases.
b. Starting and running current.
c. Voltage levels and source for control and status.
2. Description of integral control interface.
3. Environmental ratings, including NEMA enclosure rating and submergence
capabilities.
4. Gear ratios for both manual and motorized actuation.
5. Opening and closing directions.
6. Allowable starts per hour.
March 2021 40 05 57.23 1099
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_05_57.23(IDS50)0) Page 666
Item#18.
7. List of all included options and accessories.
8. Full travel times.
9. Gearbox data including gear ratio, and gearbox efficiency.
10. Affidavit in accordance with AWWA C540.
E. Shop drawings:
1. Wiring diagrams:
a. Include all options and expansion cards furnished with each actuator.
2. Dimensioned drawings of each valve and actuator combination.
3. Dimensioned drawings of each valve gearbox.
4. Electric motor data.
F. Calculations: Submit the following for each valve/gate size and class signed by
Professional Engineer:
1. Operating torque calculations.
2. Maximum torque calculations for seating and unseating.
3. Maximum operating torque at starting and normal operation.
G. Test reports:
1. Factory test report and certificate.
2. Each actuator must be performance tested with a simulated load at the factory
and individual test certificates and detailed test reports shall be provided:
a. The test equipment used should simulate a typical valve load.
H. Manufacturer's instructions:
1. Include manufacturer's instructions, description of system operation, start-up
data, and troubleshooting checklist.
I. Operations and maintenance data:
1. Include manufacturer's literature; cleaning procedures, replacement part lists,
wiring diagrams, and repair data.
2. Include a list of all configurable parameters, and the final values for each.
3. List of recommended spare parts.
4. List of special tools necessary for proper operation and/or maintenance.
5. Exploded view drawings that illustrate all assemblies, sub-assemblies, and
components.
6. Routine test procedures for all electronic and electrical circuits.
7. Troubleshooting chart covering the complete valve and controls/electrical
power systems, showing description of trouble, probable cause, and
suggested remedy.
8. Certified factory and field-test results.
1.05 QUALITY ASSURANCE
A. Obtain required information from the valve/gate supplier, including but not limited to:
1. Interface to gate or valve.
2. Operating range (In degrees).
3. Quarter turn or multi-turn.
4. Required turns for full travel on multi-turn applications.
5. Direction of rotation for opening and closing.
6. Maximum and normal torque requirements.
7. Additional sizing requirements indicated in this Section.
March 2021 40 05 57.23-2 109921310
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_05_57.23(IDS50) Page 667
Item#18.
B. All motorized, intelligent actuators shall be the product of a single manufacturer for
all valve and gate applications on this project, regardless of gate or valve type,
manufacturer, or supplier.
1.06 SPARE PARTS
A. Provide the following spare parts (minimum 10 percent of total number of actuators
of each model type furnished, but not less than 1 for each model of actuator
furnished):
1. Stem nut.
2. Worm shaft subassembly.
3. Drive sleeve subassembly.
4. Complete actuator seal kit.
5. Actuator gearbox oil (sufficient quantity to fill 4 gearboxes).
6. Encoder.
7. Control module.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or Engineer approved equal:
B. Acceptable manufacturers for lines 4 inch and larger:
1. One of following or equal:
a. Rotork Controls Inc.:
1) IQ3 (Multi-turn).
2.02 CHARACTERISTICS FOR ACTUATORS ON LINES 4 INCHES AND LARGER
A. Provide actuators complete and operable with all components and accessories
required for operation.
B. Power supply:
1. Voltage and phases as indicated in the Schedule.
2. Valve or gate motion independent of power supply phase rotation.
3. Provide an internal backup power source to maintain settings and track valve
position when main power is off.
4. The actuators shall incorporate all major components such as the motor,
starter, local controls, terminals etc. housed within a self-contained, sealed
enclosure.
C. Size actuator to move gates or valves from full open to closed position within the
time indicated in the Schedule:
1. If an operating time is not indicated on the Schedule, size the actuator to move
gates or valves at minimum 12 inches per minute under maximum load.
Measure rate of closure for valves at maximum diameter of disc, plug, or ball.
2. Size actuators so that gear boxes are not required where possible.
March 2021 40 05 57.23 1099
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_05_57.23(IDS50)0) Page 668
Item#18.
D. Control interface:
1. Configuration:
a. Provide a non-intrusive, non-contacting interface for configuring all input
and output settings, control values, ranges, torque switch settings, valve
positions switch settings, and options:
1) Configurable from a hand-held configuring tool or input devices on
the actuator.
2. Local interface, integral to actuator:
a. Non-intrusive, non-contacting selector switches:
1) LOCAL-STOP-REMOTE:
a) Motor actuator operation is prevented with the switch in STOP.
2) OPEN-CLOSE:
a) Controls the valve when LOCAL-STOP-REMOTE is in LOCAL.
b) Spring return to center.
c) Configurable between maintained (actuator runs until end of
travel, high torque, or a LOCAL-STOP-REMOTE is switched to
STOP) and momentary (actuator stops when lever is released).
b. Local display:
1) Valve fully open and fully closed indicators.
2) Numerical display showing actual valve or gate position in percent of
travel.
3. Control inputs:
a. Capable of using 120 VAC or 24 VDC inputs.
b. Controls the valve when LOCAL-STOP-REMOTE is in REMOTE.
c. Isolated inputs capable of operating from external control voltage source
or internal power supply:
1) Furnish 120 VAC and 24 VDC control power supplies within the
actuator.
d. Provide the following inputs:
1) OPEN.
2) CLOSE.
3) STOP.
e. OPEN and CLOSE inputs configurable between maintained (actuator runs
until end of travel, high torque, or a STOP input) and momentary (actuator
stops when command is removed).
4. Status outputs:
a. Monitor relay output: Dry contact, normally closed, opens when actuator is
not in REMOTE or in the event of any internal fault or alarm condition.
b. Dry contact outputs configured for the functions indicated on the
Drawings. Provide the following outputs for all actuators:
1) Fully closed.
2) Fully open.
3) LOCAL-STOP-REMOTE in REMOTE position.
c. Capable of being configured for the following additional functions:
1) Communications failure.
2) Valve opening or closing.
3) Valve moving (continuous or pulsing).
4) Motor tripped on torque in mid-travel.
5) Open or close interlock active.
6) ESD active.
March 2021 40 05 57.23-4 109921310
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_05_57.23(IDS50) Page 669
Item#18.
7) Motor tripped on torque in mid-travel.
8) Motor tripped on torque going open.
9) Motor tripped on torque going closed.
10) Pre-set torque exceeded.
11) Valve jammed.
12) Lost main power phase.
13) Control supply lost.
14) Internal failure detected.
d. All output contacts rated for 5 amps, 120 VAC and 24 VDC.
5. Analog input when modulating duty:
a. Provide a 4-20 milliampere analog input for analog modulating valves
when indicated on the Drawings.
b. Modulate valve to maintain position based on analog input value.
c. Maximum input impedance 250 ohms.
6. Analog outputs when modulating duty:
a. Provide an isolated 4-20 milliampere analog outputs when indicated on
the Drawings:
1) Loop power sourced from the actuator power supply.
2) Capable of driving into a load up to 500 ohms.
3) Output proportional to process value(s) indicated on the Drawings.
4) Valve or gate position.
5) Operating torque.
E. Features:
1. Time delay on reversal: Incorporate time delay between stopping actuator and
starting in opposite direction to limit excessive current, torque, and heating
from instantaneous reversal.
2. Data logging:
a. Store diagnostic data and reference data:
1) Store reference data (recorded during commissioning) and data from
last operation.
3. Provide display of logged data on the actuator, or provisions to download to a
personal computer.
F. Materials:
1. Construct motorized actuators of materials suitable for the environment in
which the valve or gate is to be installed.
G. Components:
1. Motors:
2. Specifically designed for valve actuator service with high starting torque, totally
enclosed non-ventilated construction.
3. Torque ratings equal to or greater than that required for valve seating and
dynamic torques with a 25 percent factor of safety:
a. Design requirements for rubber-seated AWWA butterfly valves:
1) Design actuators for maximum gate or valve operating torque, in
accordance with and using safety factors required in AWWA C504
and AWWA C540:
a) Valve actuator torque requirement for open-close service: Not
less than the required valve-seating and dynamic torques under
design operating conditions in accordance with AWWA C504.
March 2021 40 05 57.23 1099
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_05_57.23(IDS50)0) Page 670
Item#18.
b) Valve actuator torque requirement for modulating service: Not
less than twice the required valve dynamic torque under design
operating conditions in accordance with AWWA C504.
b. Design requirements for slide gates, gate valves, knife gate valves, globe
valves, and diaphragm valves:
1) Design valves and actuators for maximum operating torque, in
accordance with and using safety factors required in AWWA C540.
2) Design for the maximum torque and thrust running load over the full
cycle.
3) Maximum torque or thrust rating: The actuator stall torque or
maximum thrust output shall not exceed the torque or thrust
capability of the valve or gate, as determined by the valve or gate
manufacturer.
4. Capable of being removed and replaced without draining the actuator gear
case.
5. Motor bearings shall be amply proportioned of the anti-friction type and
permanently lubricated.
6. Rated for operating under the following conditions without exceeding
temperature limits with ambient temperature of 40 degrees Celsius:
a. Continuous operation for 15 minutes or twice the open-to-close operating
time (whichever is greater) at normal operating torque or 33 percent of
maximum torque (whichever is greater).
b. 60 starts per hour for open/close service or 1,200 starts per hour for
modulating service.
7. Provide the following motor protection features:
a. Jammed valve (no valve motion detected through a time delay).
b. High motor temperature (sensed by an embedded thermostats).
c. High torque.
d. Single phasing protection.
H. Enclosures:
1. Actuator housing ratings as indicated in the Schedule.
2. Stainless steel external fasteners.
3. Provide 'O' ring seals for each of the following areas:
a. Between the terminal compartment and the internal electrical elements.
b. Between the mechanical and electrical portions to protect from the ingress
of oil, and to protect the mechanical components of oil from dust and
moisture when the electrical terminal is open.
4. Provide the following minimum enclosure ratings:
a. NEMA Type 4X enclosure for general applications.
I. Position sensing:
1. Electronic and adjustable using a solid-state encoder wheel:
a. Mechanical limit switches and potentiometers are not acceptable.
2. Capable of retaining position and monitoring valve or gate motion when valve
is manually actuated and when main power is not present.
3. Valve range and position switch outputs field adjustable.
J. Torque sensing:
1. Torque shutdown setting: 40 percent to 100 percent rated torque:
a. Adjustable in 1 percent increments.
2. Torque display: 0 to 100 percent-rated torque.
March 2021 40 05 57.23-6 10992B10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_05_57.23(IDS50) Page 671
Item#18.
3. Capable of interrupting control circuit during both opening and closing and
when valve torque overload occurs.
4. Electrical or electronic torque sensing.
5. Independent of variations in frequency, voltage, or temperature.
6. Provide a temporary inhibit of the torque sensing system during unseating or
during starting in mid-travel against high inertia loads.
7. Provide visible verification of torque switch status without any housing
disassembly.
K. Manual actuators:
1. Hand wheel for manual operation:
a. Maximum 80-pound pull on rim when operating gate or valve under
maximum load.
b. Provide pull chain when motorized actuator is located more than 6 feet
above floor surface:
1) Chain shall be of sufficient length to reach approximately 4 feet
above the operating level.
2) Where the chain obstructs an aisle or walkway, provide holdback or
other means to ensure chain does not create a nuisance or hazard to
operating personnel.
2. Declutch lever: Padlockable, capable of mechanically disengaging motor and
related gearing and freeing hand wheel for manual operation.
L. Gearing: Hardened alloy steel spur or helical gears and self-locking, alloy bronze
worm gear set:
1. Accurately cut to assure minimum backlash.
M. Bearings:
1. Anti-friction bearing with caged balls or rollers throughout.
2. Sealed-for-life type thrust bearings housed in a separate thrust base.
N. Drive bushing:
1. Easily detachable for machining to suit the valve stem or gearbox input shaft.
2. Positioned in a detachable base of the actuator.
O. Lubrication:
1. Provide totally enclosed actuator gearing with oil filled gear case suitable for
operation at any angle.
2. Suitable for standard SAE80EP gear oil.
3. Actuators requiring special or exotic lubricants are not acceptable.
2.03 ACCESSORIES
A. Software:
1. Provide software communications to the valve actuator and handheld setting
tool using Bluetooth wireless communications:
a. Provide all accessories and drivers required for operation and
communications with a standard personal computer running Microsoft
Windows.
March 2021 40 05 57.23 1099
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_05_57.23(IDS50)0) Page 672
Item#18.
B. Setting tool:
1. If required for setting or configuring the actuator, provide a hand-held setting
tool.
a. Furnish 1 setting tool for every 10 actuators.
C. Termination module cover:
1. For actuators on a valve network provide a means to keep the valve network in
service, in the event where the actuator must be removed.
2. Provide sunshades for all outdoor installations of remote control stations that
use a LCD or similar screen. Regular pushbutton, sector switches, and pilot
light control stations will not require a sunshade.
2.04 SOURCE QUALITY CONTROL
A. Factory test:
1. Test each actuator in the factory, and submit an individual test certificate for
each actuator.
2. Perform a high potential test and record the following information:
a. Test voltage.
3. Simulate a maximum and typical valve loads and record the following
information:
a. Current and power factor at maximum and set torque values.
b. Torque as measured by the actuator.
c. Actuator output speed or operating time.
4. Performance testing: Conduct performance test for each actuator simulating
valve operating torque from full-open to full-close and from full-close to
full-open. The following information shall be recorded during each performance
test:
a. Torque at maximum torque setting.
b. Current at maximum torque setting.
c. Test voltage and frequency.
d. Actuator output speed and operating time for full-open to full-close.
e. Amperage draw on motors at breakaway and under normal operation.
B. Field verify characteristics prior to sizing motor actuator.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install actuators in accordance with manufacturer's instructions.
3.02 MOTORIZED ACTUATOR SCHEDULE
A. Provide all actuators indicated on the Drawings:
1. Major process actuators are listed in the Intelligent Actuator Schedule in this
section.
2. The schedule does not include all number and types of actuators required for
the Project.
March 2021 40 05 57.23-8 10992B10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_05_57.23(IDS50) Page 673
Item#18.
B. Abbreviations relating to type:
1. BFV = Butterfly Valve.
2. BV = Ball Valve.
3. PV = Plug Valve.
4. SG = Slide Gate.
5. KGV = Knife Gate Valve.
C. Abbreviations relating to actuator type:
1. O/C = Open and Close Service.
2. MOD = Modulating Service.
D. Abbreviations relating to controls:
1. PA = Profibus PA.
2. DP = Profibus DP.
3. DN = DeviceNet.
4. FF = Foundation Fieldbus H1.
5. MB = Modbus RTU (RS-485).
6. NET = Manufacturer's proprietary network.
7. A = Analog (4-20 mA) control, modulating duty.
8. D = Discrete control, modulating duty.
9. D-O/C = Discrete Open/Close.
END OF SECTION
March 2021 40 05 57.23 1099
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_05_57.23(IDS50)0) Page 674
Item#18.
INTELLIGENT ACTUATOR SCHEDULE
Actuator NEMA Voltage/ Open
Item Reference DWG Type Size Type Rating Phase/Hz Notes Time Controls
Struvite Pump Suction Knife N07, N08 KGV 6" O/C 4 480/3/60 120 s D-O/C
Gate Valves
Struvite to Sludge Storage N07, N08 SKGV 6" O/C 4 480/3/60 120 s D-O/C
Knife Gate Valves
March 2021 40_05_57.23-10 1099
pwalCarollolDocumentslClientllDlMeritlianl11700A101SpecificationslPre-Purchase140_05_57.23(IDS50) Page 675
Item#18.
SECTION 40_05_65.01
GATE, VALVES
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Gate, valves.
B. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 01 75 17 - Commissioning.
3. Section 01 78 36 - Warranties and Bonds.
1.02 REFERENCES
A. ASTM International (ASTM):
1. B98 - Standard Specification for Copper-Silicon Alloy Rod, Bar, and Shapes.
1.03 SUBMITTALS
A. Submit as specified in Section 01_33_00.
1.04 WARRANTY
A. Provide warranty as specified in Section 01_78_36.
B. Interior epoxy coatings: Affidavit of compliance attesting that epoxy coatings applied
to interior surfaces of valves comply in accordance with all provisions of
AWWA C550.
PART2 PRODUCTS
2.01 GATE VALVES
A. Knife gate valves:
1. Manufacturers: One of the following or equal:
a. DeZurick SPX, KGL.
b. ITT Fabri-Valve, C37.
2. Design:
a. Size and configuration: Indicated on the Drawings.
b. Suitable for service under pressures equal to and less than 150 pounds
per square inch gauge.
c. Full round port, metal seated, raised face design.
d. Flanged wafer design drilled and tapped to ASME Class 125/150
standard.
e. Rounded gate with beveled edge, finish-ground to 32 RMS, maximum, on
both sides.
f. Body to incorporate guides and jams to assist in seating.
March 2021 40 05 65.01 1099
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_05_65.01(IDS50)0) Page 676
Item#18.
g. Materials:
1) Body: Cast or ductile iron or cast steel, with Type 316 stainless steel
lining or cast Type 316 stainless steel.
2) Wetted components (including gate): Type 316 stainless steel.
3) Yoke sleeve: Acid resisting bronze or aluminum bronze.
4) Packing: PTFE.
h. Outside screw and yoke (OS&Y) with handwheel operator.
PART 3 EXECUTION
3.01 COMMISSIONING
A. As specified in Section 01_75_17.
END OF SECTION
March 2021 40 05 65.01-2 109921310
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_05_65.01(IDS50) Page 677
Item#18.
SECTION 40_61_00
COMMON WORK RESULTS FOR
PROCESS CONTROL AND INSTRUMENTATION SYSTEMS
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. General requirements applicable to all Process Control and Instrumentation
Work.
2. General requirements for process control and instrumentation submittals.
3. As specified in this Section, some PLC programming and SCADA/HMI
software configuration will be provided by the Owner, hereinafter referred to as
the Owner or Programmer.
B. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 01_60_00 - Product Requirements.
3. Section 01_75_17 - Commissioning.
4. Section 01 77 00 - Closeout Procedures.
5. Section 01_78_23 - Operation and Maintenance Data.
6. Section 01_81_01 - Project Design Criteria.
7. Section 26 05 00 - Common Work Results for Electrical.
8. Section 26_05_53 - Identification for Electrical Systems.
9. Section 40_80_01 - Testing, Calibration, and Commissioning.
10. Section 46_63_83.01 - Phosphorus Precipitation System.
C. Interfaces to equipment, instruments, and other components:
1. Drawings, Specifications, and overall design are based on preliminary
information furnished by various equipment manufacturers, which identify a
minimum scope of supply from the manufacturers. This information pertains to,
but is not limited to, instruments, control devices, electrical equipment,
packaged mechanical systems, and control equipment provided with
mechanical systems.
2. Provide all material and labor needed to install the actual equipment furnished,
include all costs to add any additional instruments, wiring, control system
inputs/outputs, controls, interlocks, electrical hardware etc., which may be
necessary to make a complete, functional installation based on the actual
equipment furnished:
a. Make all changes necessary to meet the manufacturer's wiring
requirements.
3. Review the complete set of Drawings and Specifications in order to ensure
that all items related to the instrumentation and control systems are completely
accounted for. Include any items indicated on the Drawings or in Specifications
from another discipline in the scope of Work:
a. If a conflict between Drawings and Specifications is discovered, refer
conflict to the Engineer as soon as possible for resolution.
March 2021 - DRAFT 40 61 00-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 678
Item#18.
D. All instrumentation, and control equipment and systems for the entire project to
comply with the requirements specified in the Instrumentation and Control
Specifications, whether referenced in the individual Equipment Specifications or not:
1. The requirements of the Instrumentation and Control Specifications apply to all
Instrumentation and Control Work specified in other Specifications, including
HVAC controls, packaged mechanical systems, LCPs, VCPs, etc.
2. Inform all vendors supplying instrumentation, control systems, panels, and/or
equipment of the requirements of the Instrumentation and Control
Specifications.
3. The Owner is not responsible for any additional costs due to the failure of the
Contractor to notify all subcontractors and suppliers of the Instrumentation and
Control Specifications' requirements.
E. Contract Documents:
1. General:
a. The Drawings and Specifications are complementary and are to be used
together in order to fully describe the Work.
2. Contract Drawings:
a. The Instrumentation and Control Drawings show in a diagrammatic
manner, the desired locations, and arrangements of the components of
the Instrumentation Work. Follow the Drawings as closely as possible, use
professional judgment and coordinate with the other trades to secure the
best possible installation, use the entire Drawing set for construction
purposes.
b. Locations of equipment, control devices, instruments, boxes, panels, etc.
are approximate only, exercise professional judgment in executing the
Work to ensure the best possible installation:
1) The equipment locations and dimensions indicated on the Drawings
and elevations are approximate. Use the shop drawings to determine
the proper layout, foundation, and pad requirements, etc. for final
installation. Coordinate with all subcontractors to ensure that all
instrumentation and control equipment is compatible with other
equipment and space requirements. Make changes required to
accommodate differences in equipment dimensions.
2) The Contractor has the freedom to select any of the named
manufacturers as identified in the individual Specifications; however,
the Engineer has designed the spatial equipment layout based upon
a single manufacturer and has not confirmed that every named
manufacturer's equipment fits in the allotted space. It is the
Contractor's responsibility to ensure that the equipment being
furnished fits within the defined space.
c. Installation details:
1) The Contract Drawings include installation details showing means
and methods for installing instrumentation and control equipment.
For cases where typical details are not provided or compatible with
an installed location, develop installation details that are necessary
for completing the Work, and submit these details for review by the
Engineer.
d. Loop Diagrams:
1) Loop diagrams are provided by the Owner.
March 2021 - DRAFT 40 61 00-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 679
Item#18.
1.02 REFERENCES
A. Code compliance:
1. The following codes and standards are hereby incorporated into this Section:
a. American National Standards Institute (ANSI).
b. American Petroleum Institute (API):
1) RP 550 - Manual on Installation of Refinery Instruments and Control
Systems; Part II-Process Stream Analyzers; Section 5-Oxygen
Analyzers.
2) RP 551 - Process Measurement Instrumentation.
c. International Organization for Standardization (ISO):
1) 9001 - Quality Management Systems - Requirements.
d. International Society of Automation (ISA):
1) 5.1 - Instrumentation Symbols and Identification.
2) 5.4 - Instrument Loop Diagrams.
3) 20 - Specification Forms for Process Measurement and Control
Instruments, Primary Elements, and Control Valves.
e. National Electrical Manufacturers Association (NEMA):
1) 250 - Enclosures for Electrical Equipment (1000 V Maximum).
f. National Fire Protection Association (NFPA).
g. National Institute of Standards and Technology (NIST).
h. Underwriters Laboratories, Inc. (UL):
1) 508 - Standard of Safety for Industrial Control Equipment.
2) 508A- Standard of Safety for Industrial Control Panels.
1.03 DEFINITIONS
A. Definitions of terms and other electrical and instrumentation considerations in
accordance with:
1. Factory Mutual (FM).
2. International Electrotechnical Commission (IEC).
3. Institute of Electrical and Electronics Engineers (IEEE).
4. International Society of Automation (ISA).
5. International Organization for Standardization (ISO).
6. National Electrical Code (NEC).
7. National Electrical Manufacturers Association (NEMA).
8. InterNational Electrical Testing Association (NETA).
9. National Fire Protection Association (NFPA).
10. National Institute of Standards and Technology (NIST).
11. Underwriters Laboratories (UL).
B. Specific definitions:
1. Control circuit: Any circuit operating at 120 volts alternating current (VAC) or
direct current (VDC) or less, whose principal purpose is the conveyance of
information (including performing logic) and not the conveyance of energy for
the operation of an electrically powered device.
2. Panel: An instrument support system that may be a flat surface, a partial
enclosure, or a complete enclosure for instruments and other devices used in
process control systems.
3. Power circuit: Any circuit operating at 90 volts (AC or DC) or more, whose
principal purpose is the conveyance of energy for the operation of an
electrically powered device.
March 2021 - DRAFT 40 61 00-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 680
Item#18.
4. Signal circuit: Any circuit operating at less than 50 VAC or VDC, which
conveys analog information or digital communications information.
5. Digital bus: A communication network, such as PROFIBUS, Foundation
Fieldbus, or DeviceNet, allowing instruments and devices to transmit data,
control functions and diagnostic information.
6. 2-Wire transmitter (loop powered): A transmitter that derives its operating
power supply from the signal transmission circuit and requires no separate
power supply connections. As used in this Section, 2-wire transmitter refers to
a transmitter that provides a signal such as 4 to 20 mA 24VDC regulation of a
signal in a series circuit with an external 24 VDC driving potential:
a. Fieldbus communications signal or both.
7. Powered transmitters: A transmitter that requires a separate power source
(120 VAC, 240 VAC, etc.) in order for the transmitter to develop its signal. As
used in this Section, the produced signal may be a 4 to 20 mA 24VDC signal,
a digital bus communications signal or both.
8. Modifications: Changing, extending, interfacing to, removing, or altering an
existing circuit.
C. NEMA:
1. Type 1 enclosure in accordance with NEMA 250.
2. Type 3R enclosure in accordance with NEMA 250.
3. Type 4 enclosure in accordance with NEMA 250.
4. Type 4X enclosure in accordance with NEMA 250.
5. Type 7 enclosure in accordance with NEMA 250.
6. Type 12 enclosure in accordance with NEMA 250.
D. Acronym definitions:
1. DPDT: Double-pole, double-throw.
2. ES: Enterprise system: Computer based communications or data sharing
system utilized for non-process control functions such as E-mail, sharing files,
creating documents, etc.
3. FAT: Factory acceptance test also known as Source Test.
4. HART: Highway addressable remote transducer.
5. HOA: Hand-Off-Auto control function. In the Hand mode, equipment is started
or stopped, valves are opened or closed based upon hardwired control circuits
completely independent of the PLC with minimum interlocks and permissive
conditions. In the Auto mode, equipment is started or stopped and valves are
opened or closed through a control algorithm within the PLC software. In the
Off mode, the equipment is prohibited from responding from the PLC control.
6. HMI: Human machine interface is a software application that presents
information to an operator or user about the state of a process, and to accept
and implement the operators control instructions. Typically information is
displayed in a graphical format.
7. 1/0: Input/Output.
8. IP: Internet protocol or ingress protection.
9. LCP: Local control panel: Operator interface panel that may contain an HMI,
pilot type control devices, operator interface devices, control relays, etc. and
does not contain a PLC or RIO.
10. LAN: Local area network: A control or communications network that is limited
to the physical boundaries of the facility.
March 2021 - DRAFT 40 61 00-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 681
Item#18.
11. NJB: Network junction box. An enclosure that contains multiple access points
to various networks within the facility. Networks could be Ethernet, Ethernet/IP,
Fieldbus, RIO, etc.
12. P&ID: Process and instrumentation diagram.
13. PC: Personal computer.
14. PCIS: Process control and instrumentation system: Includes the entire
instrumentation system, the entire control system, and all of the Work specified
in the Instrumentation and Control Specifications and depicted on the
Instrumentation Drawings. This includes all the PCS and instruments and
networking components as well as the various servers, workstations, thin
clients, etc.
15. PCS: Process Control System: A general name for the computerized system
that gathers and processes data from equipment and sensors and applies
operational controls to the process equipment. It includes the PLCs and/or
RIOs, LOIs, HMIs, both LCPs, VCPs and all data management systems
accessible to staff.
16. PLC: Programmable logic controller.
17. RIO: Remote 1/0 device for the PLC consisting of remote 1/0 racks, or remote
1/0 blocks.
18. RTU: Remote telemetry unit: A controller typically consisting of a PLC, and a
means for remote communications. The remote communications devices
typically are radios, modems, etc.
19. SCADA: Supervisory control and data acquisition system: A general name for
the computerized system that gathers and processes data from sensors and
equipment located outside of the facility, such as wells, lift stations, metering
stations etc.
20. SPDT: Single-pole, double-throw.
21. SPST: Single-pole, single-throw.
22. UPS: Uninterruptible power supply.
23. VCP: Vendor control panel: Control panels that are furnished with particular
equipment by a vendor other than the Owner or Contractor. These panels may
contain PLCs, RIO, LOI, HMI, etc.
24. WAN: Wide area network: A control or communications network that extends
beyond the physical boundaries of the facility.
1.04 SYSTEM DESCRIPTION
A. General requirements:
1. The Work includes everything necessary for and incidental to executing and
completing the instrumentation and control system work indicated on the
Drawings and specified in the Specifications and reasonably inferable there
from including but not limited to:
a. Preparing hardware submittals for field instrumentation.
b. Prepare the test plan, the training plan, and the spare parts submittals.
c. Procure all hardware.
d. Fabricate panels.
e. Perform bench calibration and verify calibration after installation.
f. Oversee, document, and certify loop testing.
g. Oversee, document, and certify system.
h. Installation Testing.
i. Oversee and document Functional Testing.
March 2021 - DRAFT 40 61 00-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 682
Item#18.
j. Conduct the Process Operational Period and the Instrumentation and
Controls Process Performance Testing.
k. Prepare operation and maintenance manuals.
I. Conduct training classes.
m. Provide Record Documents.
n. Resolve signal, power, or functional incompatibilities between the PCS
and interfacing devices.
o. Perform all required corrective and preventative maintenance.
2. It is the intent of these Specifications that the entire electrical power,
instrumentation, and control system be complete and operable. Provide all
necessary material and labor for the complete system from source of power to
final utilization equipment, including all connections, testing, calibration of all
equipment furnished by others, as well as equipment furnished by the
Contractor, whether or not specifically mentioned but which are necessary for
successful operation.
B. Operating facility:
1. Portions of this existing facility must remain fully functional throughout the
entire construction period. In consideration of this requirement, comply with the
following guidelines:
a. All outages must be of minimal duration and fully coordinated and agreed
to by the Owner. Adjust the construction to meet the requirements of the
Owner.
b. As weather and facility demand conditions dictate, re-adjust the
construction schedule to meet the demands placed upon Owner by its
users.
c. Where portions of the Work are in existing facilities and require interface
to existing circuits, power systems, controls and equipment, perform
comprehensive and detailed field investigations of existing conditions.
Determine all information necessary to document, interface with, modify,
upgrade, or replace existing circuits, power systems, controls, and
equipment.
2. According to individual circumstances and in compliance with the Drawings,
extend or replace conduit and cable connections from existing locations.
3. Where shown or specified, replace existing field instruments with new.
4. The Contractor is responsible for the integrity and measurement accuracy of
all loops. However, any defect found in existing equipment is the responsibility
of the Owner.
5. The standards of documentation, instrument tagging, cable and conductor
termination, terminal identification and labeling that apply to the new
installation apply equally to the existing installation.
1.05 SUBMITTALS
A. Furnish submittals as specified in Section 01_33_00 and this Section.
B. General:
1. Instruct all equipment suppliers of submittals and operation and maintenance
manuals of the requirements in this Section.
2. Furnish the submittals required by each section in the Instrumentation
Specifications.
March 2021 - DRAFT 40 61 00-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 683
Item#18.
3. Adhere to the wiring numbering scheme specified in Section 26_05_53
throughout the Project:
a. Uniquely number each wire.
b. Wire numbers must appear on all Equipment Drawings.
4. Use equipment and instrument tags, as indicated on the Drawings, for all
submittals.
C. Submittal preparation:
1. In these Contract Documents, some items of Work are represented
schematically, and are designated for the most part by numbers, as derived
from criteria in ISA-5.1:
a. Employ the nomenclature and numbers designated in this Section and
indicated on the Drawings exclusively throughout shop drawings, data
sheets, and similar submittals.
b. Replace any other symbols, designations, and nomenclature unique to a
manufacturer's, suppliers, or subcontractor's standard methods with those
identified in this Section and indicated on the Drawings.
D. Specific submittal requirements:
1. Product data:
a. Submitted for non-custom manufactured material listed in this and other
sections and shown on shop drawings.
b. Include:
1) Catalog cuts.
2) Bulletins.
3) Brochures.
4) Quality photocopies of applicable pages from these documents.
5) Identify on the data sheets the Project name, applicable specification
section, and paragraph.
6) Identify model number and options for the actual equipment being
furnished.
7) Neatly cross out options that do not apply or equipment not intended
to be supplied.
c. Use equipment and instrument tags as depicted on the P&IDs for all
submittals.
d. Adhere to wiring numbering scheme outlined in Section 26_05_53
throughout the Project:
1) Uniquely number each wire per the Specifications.
e. Wire numbers must appear on all Equipment Drawings.
2. Detailed sequence of operation for all equipment or systems.
3. Operation and maintenance manuals:
a. As specified in Section 01_78_23.
4. Project Record documents:
a. Furnish as specified in Section 01_77_00.
5. Commissioning and Process Start-up Submittals:
a. Inform the Owner and or Engineer of the day, date, and time for a
scheduled test at least 15 calendar days before the test takes place to
allow the Owner and or Engineer sufficient time to plan travel to the test
site.
b. General testing submittal requirements are specified in this Section.
March 2021 - DRAFT 40 61 00-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 684
Item#18.
c. Test Procedure Submittals:
1) Submit the proposed procedures to be followed during tests of the
PCS and its components in 2 parts:
a) Preliminary Submittal: Outline of the specific proposed tests and
examples of proposed forms and checklists.
b) Detailed Submittal: After successful review of the Preliminary
Submittal, submit the proposed detailed test procedures, forms,
and checklists. Include a statement of test objectives with the
test procedures.
d. Provide certified and witnessed test and calibration checklists for each of
the following tests:
1) Source Testing:
a) Also called Factory Acceptance Tests (FAT):
b) Submit completed Manufacturer's Certificate of Source Testing
as specified in Section 01_75_17.
2) Functional Testing:
a) Loop Validation Tests:
(1) Loop Validation Certifications:
(a) Complete field device loop tests have been
successfully completed for all individual instruments,
all separate analog control networks, all valves, all
VCPs, all motors, all local operator interface panels, all
motor control centers, etc.
b) Calibration, adjustment, and test details for all components and
systems.
c) Programming.
d) Submit completed Manufacturer's Certificate of Installation and
Functionality Compliance as specified in Section 01_75_17.
3) Process Operational Period.
6. Test reports:
a. As specified in Section 01_33_00.
1.06 QUALITY ASSURANCE
A. Manufacture instruments at facilities certified to the quality standards of ISO 9001.
B. Furnish all equipment listed by and bearing the label of UL or of an independent
testing laboratory acceptable to the Engineer and the Authority Having Jurisdiction.
1.07 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 01_60_00.
B. Special instructions:
1. Securely attach special instructions for proper field handling, storage, and
installation to each piece of equipment before packaging and shipment.
C. Tagging:
1. Tag each component and/or instrument to identify its location, instrument tag
number, and function in the system.
2. Firmly attach a permanent tag indelibly machine marked with the instrument
tag number, as given in the tabulation, on each piece of equipment constituting
the PCS.
March 2021 - DRAFT 40 61 00-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 685
Item#18.
3. Tag instruments immediately upon receipt in the field.
4. Prominently display identification on the outside of the package.
5. Utilize the Tag and Loop Number identifications shown on the P&IDs.
D. Delivery and inspection:
1. Deliver products in undamaged condition, in manufacturer's original container
or packaging with identifying labels intact and legible. Include date of
manufacture on label.
1.08 PROJECT OR SITE CONDITIONS
A. Site conditions:
1. Provide a PCS, including all equipment, raceways, and any other components
required for a complete installation that meets the environmental conditions for
the Site as specified in the General Requirements and below.
2. Seismic classification:
a. Provide all equipment and construction techniques suitable for the seismic
requirements for the site, as specified in Section 01_81_01.
3. Wind:
a. Provide all equipment and construction techniques suitable for the site
wind loading criteria, as specified in Section 01_81_01.
4. Altitude, temperature and humidity:
a. Provide all equipment and instrumentation fully rated for continuous
operation at this altitude, temperature and humidity conditions with no
additional derating factors applied.
b. Provide additional temperature conditioning equipment to maintain all
equipment and instrumentation in non-conditioned spaces or outdoors
subject to these ambient temperatures 10 degrees Fahrenheit above the
minimum operating temperature and 10 degrees Fahrenheit below
maximum operating temperature as determined by the equipment
manufacturer's guidelines:
1) Provide all power wiring for these devices (e.g., heaters, fans, etc.),
whether or not indicated on the Drawings.
5. Area classifications:
a. Furnish enclosures that match the area classifications as specified in
Section 26 05 00.
6. Site security:
a. Abide by all security and safety rules concerning the Work on the Site.
1.09 SEQUENCING
A. General:
1. As specified in Section 01_75_17.
B. General Field Start-up and testing procedures:
1. As specified in Section 01_75_17.
C. Installation testing:
1. As specified in Section 01_75_17.
2. Commence after acceptance of all training, wire test, calibration tests, and
loop validation tests, and all inspections have demonstrated that the PCIS
complies with all Contract requirements.
March 2021 - DRAFT 40 61 00-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 686
Item#18.
3. Acceptance of the PCIS Installation testing must be provided in writing by the
Owner before the performance testing may begin.
D. Functional testing:
1. Representatives from each of the following groups shall be in attendance
during the functional Testing: Programmer, strain press supplier, and
centrifuge supplier. Commence after acceptance of all training, wire test,
calibration tests, and loop validation tests, and all inspections have
demonstrated that the PCIS complies with all Contract requirements.
2. Loop validation test.
3. As specified in Section 40_80_01.
a. Coordinate the scheduling of tests a minimum of 21 days before the
estimated completion date of installation and wiring of the PCIS.
b. Complete loop validation testing a minimum of 5 days before the pre-
commissioning phase of the project.
c. Loop validation certifications:
1) After the field device loop tests have been successfully completed as
specified in Section 40_80_01 for all individual instruments, all
separate analog control networks, all valves, all VCPs, all motors, all
local operator interface panels, all motor control centers, etc., submit
a certified copy of all test forms signed by the Contractor, Vendor,
and the Owner's representative with test data entered, together with
a clear and unequivocal statement that all instrumentation, including
all control and signal wiring, has been successfully calibrated,
inspected, and tested.
a) Acceptance of the PCIS Installation Testing must be provided in
writing by the Engineer before the Process Operational Period
may begin.
E. Provide all special tools and spare parts, as specified in the Maintenance paragraph
of this Section, before Process Operational Period commences, suitably wrapped
and identified.
F. Process Operational Period:
1. Upon completion of the Process Operational Period, conduct an
Instrumentation and Controls Process Performance Test as a condition for
Project final completion.
1.10 SCHEDULING (NOT USED)
1.11 WARRANTY (NOT USED)
1.12 SYSTEM PROCESS START-UP
A. Replace or modify equipment, software, and materials that do not achieve design
requirements after installation in order to attain compliance with the design
requirements:
1. Following replacement or modification, retest the system and perform
additional testing to place the complete system in satisfactory operation and
obtain compliance acceptance from the Engineer.
March 2021 - DRAFT 40 61 00-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 687
Item#18.
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 MAINTENANCE
A. Before Substantial Completion, perform all maintenance activities required by the
Contract Documents including any calibrations, final adjustments, component
replacements or other routine service required before placing equipment or systems
in service.
B. Furnish all spare parts as required by the Contract Documents.
C. Provide additional spare parts specified in other sections of the Instrumentation and
Control Specifications.
D. Submit all special tools and spare parts, suitably wrapped and identified, before
Process Operational Period commences.
PART PRODUCTS
2.01 MANUFACTURERS
A. Provide similar items from a single manufacturer throughout the PCIS portion of the
Project.
B. Allowable manufacturers are specified in individual instrument and equipment
specifications.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS
A. Furnish all materials under this Contract that are new, free from defects, and
standard products produced by manufacturers regularly engaged in the production
of these devices and that bear all approvals and labels as required by the
Specifications.
B. Provide materials complying with the applicable industrial standard as specified in
the Contract Documents.
2.04 MANUFACTURED UNITS (NOT USED)
2.05 EQUIPMENT (NOT USED)
2.06 COMPONENTS
A. Furnish all meters, instruments, and other components that are the most recent field
proven models marketed by their manufacturers at the time of submittal of the shop
drawings unless otherwise specified to match existing equipment.
March 2021 - DRAFT 40 61 00-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 688
Item#18.
B. Signal transmission:
1. Analog signals:
a. Furnish analog measurements and control signals that vary in direct linear
proportion to the measured variable, unless otherwise indicated.
b. Furnish electrical analog signals outside control panels that are 4 to
20 milliamperes 24 VDC, except as indicated.
c. Analog signals within enclosures may be 1 to 5 VDC.
d. Electrically or optically isolate all analog signals from other signals.
e. Furnish regulated analog signals that are not affected by changes in
supply voltage or load resistance within the unit's rating.
f. Maintain the total 4 to 20 milliamperes loop impedance to 10 percent
below the published value at the loop operating voltage.
g. Where necessary, reduce loop impedance by providing current-to-current
(1/1) isolation amplifiers for signal re-transmission.
2. Discrete input Signals:
a. As indicated in the controller hardware specification.
3. Discrete output signals:
a. Dry contacts or TRIAC outputs (with express written approval by the
Engineer) as needed to coordinate with the field device.
b. Provide external terminal block mounted fuse for all discrete outputs.
c. Provide interposing relays as needed for discrete outputs for voltage
and/or current compatibilities.
d. Provide interposing relays as required for functionality of the control
circuit.
4. Signal Performance and Design Criteria:
a. Stability:
1) After Control have taken corrective action, oscillation of the final
control element shall not exceed 2 cycles per minute or a magnitude
of motion of 0.5 percent of full travel.
b. Response:
1) Any change in setpoint or controlled variable shall produce a
corrective change in position of the final control element and
stabilized within 30 seconds.
c. Agreement:
1) Setpoint indication of controlled variable and measured indication of
controlled variable shall agree within 3 percent of full scale over a 6:1
operating range.
d. Repeatability:
1) For any repeated magnitude of control signal, from either an
increasing or decreasing direction, the final control element shall take
a repeated position within 0.5 percent of full travel regardless of force
required to position the final element.
e. Sensitivity:
1) Controls shall respond to a setpoint deviations and measured
variable deviations within 1.0 percent of full scale.
f. Performance:
1) All instruments and control devices shall perform in accordance with
the manufacturers' specifications.
C. Discrete circuit configuration:
1. Configure discrete control circuits to fail safe, on loss of continuity or loss of
power.
March 2021 - DRAFT 40 61 00-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 689
Item#18.
2. Alarm contacts: Fail to the alarm condition.
3. Control contacts fail to the inoperative condition unless otherwise indicated on
the Drawings.
D. Grounding:
1. Provide control panels with a signal ground bus, isolated from the power
ground bus:
a. Provide multiple panels in one location with a common point for signal
ground bus connection to ground.
2. Ground single point ground shields and measurement loops at the source
panel external terminals, unless otherwise noted, by bonding to the control
panel signal ground bus.
3. Provide isolating amplifiers within control panels for field equipment
possessing a grounded input or output, except when the panel circuit is
galvanically isolated.
2.07 ACCESSORIES
A. Nameplates:
1. Provide a nameplate for each controller, instrument transducer, instrument
power supply, solenoid, or any other control device located either in the field or
within panels.
2. All nameplates shall be of identical style, color, and material throughout the
facility.
3. Device nameplates shall include:
a. Designations as indicated on the Drawings and identified on the Process
and Instrumentation Drawings.
1) Device tag and loop number ID.
2) PLC ID.
3) Power information (e.g. MCP440, 120VAC).
b. White lettering on a blue background, laminated plastic.
4. All instruments shall be equipped with Type 316 stainless steel nameplate with
the instrument tag stamped in 3/8-inch letters and connected to the instrument
using Type 316 stainless steel wire.
2.08 MIXES (NOT USED)
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
2.11 SOURCE QUALITY CONTROL
A. Provide all equipment that is new, free from defects, and standard products
produced by manufacturers regularly engaged in the production of these products
that bear all approvals and labels as required by the Specifications.
March 2021 - DRAFT 40 61 00-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 690
Item#18.
PART 3 EXECUTION
3.01 EXAMINATION
A. Provide a complete instrumentation and control system:
1. Install all extra conduits, cables, and interfaces as may be necessary to
provide a complete and operating electrical, and process control and
instrumentation system.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. Equipment locations indicated on the Drawings may change due to variations in
equipment size or minor changes made by others during construction:
1. Verify all dimensions as indicated on the Drawings:
a. Actual field conditions govern all final installed locations, distances, and
levels.
2. Review all information indicated on the Drawings, including architectural,
structural, mechanical, instrumentation, and the accepted electrical,
instrumentation, and mechanical shop drawings, and coordinate Work as
necessary to adjust to all conditions that arise due to such changes.
3. Make minor changes in location of equipment before rough in, as directed by
the Owner or Engineer.
B. Perform all related Electrical Work in accordance with the applicable sections of the
Electrical Specifications.
C. The PCIS configurations are diagrammatic:
1. The locations of equipment are approximate unless dimensioned.
2. Where Project conditions require, make reasonable changes in locations and
arrangements.
D. Field instruments installation:
1. Install field instruments as specified in the Contract Documents, API RP 550
and RP 551, and the manufacturer's instructions.
2. Mount field instruments so that they can be easily read, readily approached,
and easily serviced, and so they do not restrict access to mechanical
equipment:
a. Mount field instruments on a pipe stand or local panel, if they are not
directly mounted, unless otherwise indicated on the Drawings.
b. Provide sun shields for all field electronic instruments exposed to direct
sunlight.
3. Make connections from rigid conduit systems to field instruments with PVC
coated flexible conduit:
a. Type of flexible conduit required for the area classification:
1) Area classification as specified in Section 26_05_00.
b. Maximum length of 18 inches.
4. Connect field instruments with cable as specified in the Electrical
Specifications, except when the manufacturer requires the use of special
cable, or otherwise specified in this Section:
a. Special cable applications shall be in accordance with the NEC.
March 2021 - DRAFT 40 61 00-14 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 691
Item#18.
5. Verify the correctness of each installation:
a. Polarity of electric power and signal connections.
b. Ensure all process connections are free of leaks.
E. Conduit, cables, and field wiring:
1. Provide all PCS equipment cables, and process LAN communication networks
under the Instrumentation and Control Specifications.
2. Provide terminations and wire identification as specified in the Electrical
Specifications.
3. Protect all wiring from sharp edges and corners.
4. Provide all conduits, fittings, boxes, etc. in accordance with all the
requirements of the Electrical Specifications.
F. Equipment tie-downs:
1. Anchor all instruments, control panels, and equipment by methods that comply
with seismic and wind bracing requirements, which apply to the Site.
2. All control panels, VCPs, LCPs, RTUs, PCMs, etc., shall be permanently
mounted and tied down to structures.
G. Existing instrumentation:
1. Clean, recondition and re-calibrate each existing instrument to be reused,
removed, or reinstalled using an authorized service facility of the instrument
manufacturer.
2. Provide certification of this Work before reinstallation of each instrument.
H. Instrument tagging:
1. As specified in Section 26_05_53.
2. Provide all field-mounted instruments with nameplates:
a. Nameplates engraved with the instrument's full tag number as indicated
on the Drawings:
1) Affix tags with stainless steel wire fasteners.
3. Provide all back of panel instruments with nameplates:
a. Engraved with the instrument's full tag number as indicated on the
Drawings:
4. Provide all front of panel instruments with a nameplate:
a. Engraving to include the following:
1) Instrument's full tag number
2) Service description.
b. Nameplates:
1) Secure nameplates to the panel with adhesive.
I. Cable and conductor termination:
1. Terminate all cables and conductors on terminal blocks.
2. Terminal block enclosures:
a. Suitable for the area classification as specified in Section 26_05_00.
J. Surge protection:
1. Provide outdoor field instrument loops with voltage surge protection units
installed on the instruments.
2. Individually fuse each 4 to 20 milliamperes direct current loop with a
1/16 ampere fuse between power supplies and receiver surge protectors.
March 2021 - DRAFT 40 61 00-15 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 692
Item#18.
3. Provide voltage surge protection for 4 wire transmitters and analyzers:
a. Protect both power source and signal loop.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. As specified in Section 01_75_17.
B. Owner Training:
1. Demonstration requirements are specified in Section 40_80_01.
2. General:
a. Provide system maintenance and operator training courses for all the
instrumentation and control equipment and systems furnished, as
described below.
1) All training described below shall be provided by the Contractor.
2) Training for phosphorous recovery system in accordance with
Section 46 63 83.01.
b. Tailor training classes to the specific needs of the class participants:
1) Develop separate courses for operators, maintenance staff, and
supervisors:
a) The specific categories and number of personnel in each
category are identified below.
2) Furnish training courses that are a combination of classroom and
hands-on training:
3) Present the minimum number of sessions, specified in
Table 40 61_00-3.10-T1, for each course in order to satisfy class
size restrictions and limitations scheduling Owner staff.
4) Furnish additional sessions if required to accommodate the total
number of personnel identified for each course.
c. Instructor qualifications:
1) Highly qualified training instructors for technical training with
demonstrated expertise in not only control system functionality but
also professional training techniques:
a) Instructor qualifications are subject to the approval of the
Engineer.
Table 1
Minimum Personnel
Course Length (Estimated Minimum
(hours per Number Number
Course Title session) of Students) of Sessions
Instrument Training 2 10 1
March 2021 - DRAFT 40 61 00-16 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 693
Item#18.
3. Training course requirements:
a. System overview training:
1) Coordinate training courses that give the Owner's supervisory level
personnel an overview of all elements of the PCIS system that focus
on the overall functional aspect of elements of the control system and
provide an understanding of the interaction of the various
components.
b. Instrumentation training:
1) Furnish training covering all instruments and control panels.
2) Furnish the specified quantity of training, allocated to cover new
instruments and hardwired controls as specified in this Section and
specifically determined in the accepted training plan.
3) Train maintenance staff in the use, cleaning, calibration,
maintenance, and troubleshooting of all the instruments furnished
within this Project.
4) Furnish training on the operation of new hardwired controls.
3.08 FIELD QUALITY CONTROL
A. Inspection:
1. Allow for inspection of PCIS installation.
2. Provide any assistance necessary to support inspection activities.
3. Engineer inspections may include, but are not limited to, the following:
a. Inspect equipment and materials for physical damage.
b. Inspect installation for compliance with Drawings and Specifications.
c. Inspect installation for obstructions and adequate clearances around
equipment.
d. Inspect equipment installation for proper leveling, alignment, anchorage,
and assembly.
e. Inspect equipment nameplate data to verify compliance with design
requirements.
f. Inspect cable terminations.
g. Inspect/witness instrument calibrations/verifications.
4. Inspection activities conducted during construction do not satisfy inspection
requirements specified in Section 40_80_01.
B. Instrument Installation Inspection:
1. Provide any assistance necessary to support inspection activities.
2. Inspections may include, but are not limited to, the following:
a. Inspect equipment and materials for physical damage.
b. Inspect the installed arrangement, lay lengths, orientation, piping
obstructions, etc., that could affect the instruments accuracy or
repeatability.
c. Inspect installation for compliance with Drawings and Specifications.
d. Inspect installation for obstructions and adequate clearances around
equipment.
e. Inspect equipment installation for proper leveling, alignment, anchorage,
and assembly.
f. Inspect equipment nameplate data to verify compliance with design
requirements.
g. Inspect cable terminations.
h. Inspect/witness instrument calibrations/verifications.
March 2021 - DRAFT 40 61 00-17 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 694
Item#18.
3. Inspection activities conducted during construction do not satisfy inspection
requirements specified in Section 40 80 01.
4. Field acceptance testing: (Functional Testing) is specified in
Section 40 80 01.
C. Installation supervision:
1. Ensure that the entire PCIS is installed in a proper and satisfactory manner. At
a minimum, the Contractor shall provide the following services:
a. Installation resources:
1) Coordinate with the Contractor regarding installation requirements of
the Contract Documents.
b. Provide technical assistance to installation personnel by telephone:
1) Furnish installation personnel with at least one copy of the accepted
submittals, including all installation details.
c. Periodic inspections during the construction period.
d. A complete check of the completed installation to ensure that it is in
conformance with the requirements of the equipment manufacturer and
the Contract Documents.
e. Field verify accuracy and calibration of all instruments.
3.09 ADJUSTING
A. Control valves:
1. Stroke all control valves, cylinders, drives and connecting linkages from the
control system as well as local control devices and adjust to verify proper
control action, hand switch action, limit switch settings, torque settings, remote
control actions, and remote feedback of valve status and position.
2. Check control valve actions and positioner settings with the valves in place to
ensure that no changes have occurred since the bench calibration.
B. Make all revisions necessary to the control system software, as directed by the
Engineer.
1. It is understood that the Contractor knows and agrees that changes will be
required in the control system software during the Source Testing, Functional
Testing, Process Operational Period, Process Start-up, and during the Project
Correction Period.
3.10 CLEANING
A. As specified in Section 01_77_00.
B. Vacuum clean all control panels and enclosures before process start-up and again
after final completion of the project.
C. Clean all panel surfaces.
D. Return to new condition any scratches and/or defects.
E. Wipe all instrument faces and enclosures clean.
F. Leave wiring in panels, manholes, boxes, and other locations in a neat, clean, and
organized manner:
1. Neatly coil and label all spare wiring lengths.
March 2021 - DRAFT 40 61 00-18 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_00(IDS50) Page 695
Item#18.
2. Shorten, re-terminate, and re-label excessive spare wire and cable lengths, as
determined by the Engineer.
G. As specified in other sections of the Contract Documents.
3.11 PROTECTION
A. Protect all Work from damage or degradation until date of Substantial Completion.
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 40 61 00-19 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_00(IDS50) Page 696
Item#18.
SECTION 40_61_05
PACKAGED CONTROL SYSTEM
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. General requirements for a Master Control Panel (MCP) designed to monitor
and control all skids and ancillary equipment furnished for each skid, local
control panels at each skid, local control panels for other furnished equipment,
and field instruments required for a complete package control system.
1.02 REFERENCES
A. Code compliance:
1. As specified in Section 014100 - Regulatory Requirements:
a. The publications are referred to in the text by basic designation only. The
latest edition accepted by the Authority Having Jurisdiction of referenced
publications in effect at the time of Bid governs.
2. The following codes and standards are hereby incorporated into these
Specifications:
a. Institute of Electrical and Electronics Engineers:
1) C62.41.1 - IEEE Guide on the Surge Environment in Low-Voltage
(1000V and less) AC Power Circuits.
b. International Society of Automation (ISA):
1) 5.4 - Instrument Loop Diagrams.
2) 20 - Specification Forms for Process Measurement and Control
Instruments, Primary Elements, and Control Valves.
c. National Electrical Manufacturer's Association (NEMA):
1) 250 - Enclosures for Electrical Equipment (1,000 Volts Maximum).
d. National Fire Protection Association (NFPA).
e. Underwriters Laboratories Inc. (UL):
1) 508C - Power Conversion Equipment.
2) 489 - Molded-Case Circuit Breakers, Molded-Case Switches, and
Circuit-Breaker Enclosures.
3) 913 - Standard for Intrinsically Safe Apparatus and Associated
Apparatus for Use in Class I, II, III, Division 1, Hazardous (Classified)
Locations.
4) 1283 - Standard for Electromagnetic Interference Filters.
5) 1449 - Transient Voltage Surge Suppressors.
1.03 DEFINITIONS
A. Definitions of terms and other electrical and instrumentation considerations as set
forth in the:
1. Factory Mutual or FM Global (FM).
2. Institute of Electrical and Electronic Engineers (IEEE).
3. InterNational Electrical Testing Association (NETA).
4. International Electrotechnical Commission (IEC).
March 2021 - DRAFT 40 61 05-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 698
Item#18.
5. International Organization for Standardization (ISO).
6. International Society of Automation (ISA).
7. National Electrical Code (NEC).
8. National Fire Protection Association (NFPA).
9. National Institute of Standards and Technology (NIST).
10. Underwriter Laboratories (UL).
B. NEMA:
1. Type 1 enclosure in accordance with NEMA 250.
2. Type 3R enclosure in accordance with NEMA 250.
3. Type 4 enclosure in accordance with NEMA 250.
4. Type 4X enclosure in accordance with NEMA 250.
5. Type 6 enclosure in accordance with NEMA 250.
6. Type 6P enclosure in accordance with NEMA 250.
7. Type 12 enclosure in accordance with NEMA 250.
C. Specific definitions:
1. Control circuit: Any circuit operating at 120 volts alternating current (AC) or
direct current (DC) or less, whose principal purpose is the conveyance of
information (including performing logic) and not the conveyance of energy for
the operation of an electrically powered device.
2. Panel: An instrument support system that may be either a flat surface, a partial
enclosure, or a complete enclosure for instruments and other devices used in
process control systems. Unless otherwise specified or clearly indicated by the
context, the term "panel" in these Contract Documents is interpreted as a
general term, which includes flat surfaces, enclosures, cabinets, and consoles.
3. Power circuit: Any circuit operating at 90 volts (AC or DC) or more, whose
principal purpose is the conveyance of energy for the operation of an
electrically powered device.
4. Signal circuit: Any circuit operating at less than 50 volts AC or DC, which
conveys analog information or digital communications information.
5. Digital Bus: A communication network, such as Profibus, Foundation Fieldbus,
or DeviceNet, allowing instruments and devices to transmit data, control
functions, and diagnostic information.
6. 2-Wire transmitter (loop powered): A transmitter that derives its operating
power supply from the signal transmission circuit and requires no separate
power supply connections. As used in this Section, 2-wire transmitter refers to
a transmitter that provides 4 to 20 mA current regulation of a signal in a series
circuit with an external 24 VDC driving potential:
a. Field Bus Communications signal or both.
7. Powered transmitters: A transmitter that requires a separate power source
(120 VAC, 240 VAC, etc.) in order for the transmitter to develop its signal. As
used in this Section, the produced signal may either be a 4 to 20 mA current
signal, a Digital Bus communications signal or both.
8. Hardwired control: Control circuitry that does not utilize software to initiate
functionality.
9. Hardwired interlocks: A safety or protective feature that will interrupt operation
of the equipment in all operating modes with no required operator intervention.
10. Software interlocks: A safety or protective feature that will interrupt operation
of the equipment when the RTU has control.
11. The term "panel" in this Section is interchangeable with the term "enclosure".
March 2021 - DRAFT 40 61 05-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 699
Item#18.
D. Acronym definitions:
1. CCS: The PCS central computer system (CCS) consisting of computers and
software. The personal computer-based hardware and software system that
includes the operator interface, data storage, data retrieval, archiving,
alarming, historian, reports, trending, and other higher level control system
software and functions.
2. DPDT: Double-pole, double-throw.
3. ES: Enterprise system: Computer based communications or data sharing
system utilized for non-process control functions such as E-mail, sharing files,
creating documents, etc.
4. FAT: Factory acceptance test also known as Source Test.
5. HART: Highway addressable remote transducer.
6. HOA: Hand-Off-Auto control function that is totally PLC based. In the Hand
mode, equipment is started or stopped, valves are opened or closed through
operator direction under the control of the PLC software. In the Auto mode,
equipment is started or stopped and valves are opened or closed through a
control algorithm within the PLC software. In the Off mode, the equipment is
prohibited from responding from the PLC control.
7. HMI: Human machine interface is a software application that presents
information to an operator or user about the state of a process, and to accept
and implement the operators control instructions. Typically information is
displayed in a graphical format.
8. ICSC: Instrumentation and control system contractor: Subcontractor who
specializes in the design, construction, fabrication, software development,
installation, testing, and commissioning of industrial instrumentation and
control systems.
9. IJB: Instrument junction boxes: A panel designed with cord sets to easily
remove, replace, or relocate instrument signals.
10. I/O: Input/Output.
11. IP: Internet protocol or ingress protection.
12. LCP: Local control panel: Operator interface panel that may contain an HMI,
pilot type control devices, operator interface devices, control relays, etc. and
does not contain a PLC or RIO.
13. LAN: Local area network: A control or communications network that is limited
to the physical boundaries of the facility.
14. LOI: Local Operator Interface is an operator interface device consisting of an
alphanumeric or graphic display with operator input functionality. The LOI is
typically a flat panel type of display mounted on the front of an enclosure with
either a touch screen or tactile button interface.
15. LOR: Local-Off-Remote control function. In the Remote mode, equipment is
started or stopped, and valves are opened or closed through the PLC based
upon the selection of the HOA. In the Local mode, equipment is started or
stopped, valves are opened or closed based upon hardwired control circuits
completely independent of the PLC with minimum interlocks and permissive
conditions. In the Off mode, the equipment is prohibited from responding to
any control commands.
16. NJB: Network junction box. An enclosure that contains multiple access points
to various networks within the facility. Networks could be Ethernet, Ethernet/IP,
Fieldbus, RIO, etc.
17. P&ID: Process and instrumentation diagram.
18. PC: Personal computer.
March 2021 - DRAFT 40 61 05-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 700
Item#18.
19. PCIS: Process control and instrumentation system: Includes the entire
instrumentation system, the entire control system, and all of the Work specified
in the Instrumentation and Control Specifications and depicted on the
Instrumentation Drawings.
20. PCM: Process control module: An enclosure containing any of the following
devices: PLC, RTU, or RIO.
21. PCS: Process Control System: A general name for the computerized system
that gathers and processes data from equipment and sensors and applies
operational controls to the process equipment. It includes the PLCs and/or
RIOs, LOIs, HMIs, both LCPs, VCPs and all data management systems
accessible to staff.
22. PJB: Power junction box: An enclosure with terminal blocks that distribute
power to multiple instruments.
23. PLC: Programmable logic controller.
24. RIO: Remote 1/0 device for the PLC consisting of remote 1/0 racks, or remote
1/0 blocks.
25. RTU: Remote telemetry unit: A controller typically consisting of a PLC, and a
means for remote communications. The remote communications devices
typically are radios, modems, etc.
26. SCADA: Supervisory control and data acquisition system: A general name for
the computerized system that gathers and processes data from sensors and
equipment located outside of the facility, such as wells, lift stations, metering
stations etc.
27. SPD: Surge protection device.
28. SPDT: Single-pole, double-throw.
29. SPST: Single-pole, single-throw.
30. UPS: Uninterruptible power supply.
31. VCP: Vendor control panel: Control panels that are furnished with particular
equipment by a vendor other than the ICSC. These panels may contain PLCs,
RIO, LOI, HMI, etc.
32. WAN: Wide area network: A control or communications network that extends
beyond the physical boundaries of the facility.
1.04 SYSTEM DESCRIPTION
A. Master control panel (MCP):
1. PLC processor, power supply, 1/0 backplanes, 1/0 modules, and
communications modules sized for connected 1/0 and required spares.
2. LOI on the face of the MCP enclosure for monitoring and control of the
package control system shall be 10" Panelview Plus 7 (with FactoryTalk
software).
3. Ethernet communication equipment to provide communications with plant PCS
system.
4. Uninterruptable power supply.
5. The MCP shall exercise control over all aspects of the package control
system.
6. All PLC and LOI programming required for fully functional package control
system.
B. Other control panels:
1. Provide each reactor system with a control panel.
2. Provide other control panels at the supplier's discretion.
March 2021 - DRAFT 40 61 05-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 701
Item#18.
3. 1/0 modules and equipment necessary to interface with the MCP.
4. Additional LOls on individual unit skid local control panels at the supplier's
discretion.
C. Contractor shall be responsible for installation of loose Field instruments (provided
by the vendor) that are not mounted on the process skid for process and equipment
monitoring.
1.05 SUBMITTALS
A. General:
1. Submit as specified in Section 01_33_00 - Submittal Procedures.
2. Furnish submittals that are fully indexed with a tabbed divider for every
component.
3. Sequentially number pages within the tabbed sections. Submittals and
Operations and Maintenance manuals that are not fully indexed and tabbed
with sequentially numbered pages, or are otherwise unacceptable, will be
returned without review.
4. Edit all submittals and operation and maintenance manuals so that the
submittal specifically applies to only the equipment furnished. Neatly cross out
all extraneous text, options, models, etc. that do not apply to the equipment
being furnished, so that the information remaining is only applicable to the
equipment being furnished.
B. Pre-bid information:
1. The Electrical and Instrumentation Drawings have been prepared based on
information provided by potential equipment suppliers and existing installations
of similar equipment. Suppliers of packaged systems shall provide sufficient
information to the Contractor to allow an adequate estimate of the Electrical
and Instrumentation Work associated with the installation of the packaged
system.
2. To the extent practical, packaged systems shall be factory assembled and
wired. Information on packing splits and other anticipated field wiring
requirements shall be provided to the Contractor prior to the bid.
3. The Contractor shall be responsible to obtain the necessary information to
accurately estimate the electrical connections to the packaged system
equipment.
C. Product data:
1. General:
a. Submitted for non-custom manufactured material specified in this and
other sections and indicated on shop drawings.
b. Furnish sufficient information to evaluate the suitability of the proposed
material or equipment for the intended use, and for compliance with these
Specifications.
c. Include:
1) Catalog cuts.
2) Bulletins.
3) Brochures.
4) Quality photocopies of applicable pages from these documents.
5) Identify on the data sheets the project name, applicable specification
section, and paragraph.
March 2021 - DRAFT 40 61 05-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 702
Item#18.
6) Identify model number and options for the actual equipment being
furnished.
d. Legibly cross out options that do not apply or equipment not intended to
be supplied.
2. Material and equipment schedules:
a. Furnish a complete schedule and/or matrix of all materials, equipment,
apparatus, and instruments that are proposed:
1) Include sizes, names of manufacturers, catalog numbers, and such
other information required to identify the items.
3. Instrument data sheets:
a. Furnish fully completed data sheets, both electronically in Microsoft Word
or Excel and in hard copy, for each instrument and component according
to ISA 20. Include the following information on the data sheet:
1) Component functional description specified in this Section and
indicated on the Drawings.
2) Manufacturers model number or other product designation.
3) Tag number specified in this Section and indicated on the Drawings.
4) System or loop of which the component is a part.
5) Location or assembly at which the component is to be installed.
6) Input and output characteristics.
7) Scale range with units and multiplier.
8) Requirements for electric supply.
9) Requirements for air supply.
10) Power consumption.
11) Response timing.
12) Materials of construction and of component parts that are in contact
with, or otherwise exposed to, process media, and or corrosive
ambient air.
13) Special requirements or features, such as specifications for ambient
operating conditions.
14) Features and options that are furnished.
D. Shop drawings:
1. General:
a. Show all interfaces between any of the following: instruments, vendor
control panels, motor control centers, motor starters, variable speed
drives, control valves, flowmeters, chemical feeders and other equipment
related to the control work provided.
2. Shop drawing requirements:
a. Front, side, and, rear elevations, and top and bottom views, showing all
dimensions.
b. Locations of conduit entrances and access plates.
c. Component layout and identification.
d. Schematic and wiring diagrams with wire numbers and terminal
identification.
e. Connection diagrams, terminal diagrams, internal wiring diagrams,
conductor size, etc.
f. Anchoring method and leveling criteria, including manufacturer's
recommendations for the seismic specified in Section 01_81_02 - Seismic
Design Criteria and wind conditions specified in Section 01_81_04 - Wind
Design Criteria.
g. Weight.
March 2021 - DRAFT 40 61 05-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 703
Item#18.
h. Finish.
i. Nameplates with legends:
1) Temperature limitations, as applicable.
3. Loop drawings:
a. Submit loop drawings for every analog, discrete, signal and control circuit:
1) Provide a loop drawing submittal that completely defines and
documents the contents of each monitoring, alarming, interlock, and
control loop for supplier provided equipment.
b. Show every instrument and 1/0 point on at least one loop diagram.
c. Provide a complete index in the front of each bound volume:
1) Index the loop drawings by systems or process areas.
d. Provide drawings showing definitive diagrams for every instrumentation
loop system:
1) Show and identify each component of each loop or system using
requirements and symbols from ISA S5.4 as amended by the
Contract Drawings, as defined by the most recent revision in ISA.
2) Furnish a separate drawing sheet for each system or loop diagram.
e. In addition to the ISA S5.4 requirements, show the following details:
1) Functional name of each loop.
2) Reference name, drawing, and loop diagram numbers for any signal
continuing off the loop diagram sheet.
3) Show all terminal numbers, regardless of the entity providing the
equipment.
4) MCC panel, circuit, and breaker numbers for all power feeds to the
loops and instrumentation.
5) Designation of and, if appropriate, terminal assignments associated
with, every manhole, pull-box, junction box, conduit, and panel
through which the loop circuits pass.
6) If a circuit is continued on another drawing show the name and
number of the continuation drawing on the loop drawing. Provide
complete references to all continuation drawings.
f. The Contractor shall be responsible for reviewing existing plant as-built
information for the generation of drawings that include existing plant
control equipment. Where as-built information is not available, accurate
information shall be collected through site surveys.
4. Control panel drawings:
a. Layout drawings:
1) Submit panel, enclosure, console, furniture, and cabinet layout
drawings for all items provided.
2) As a minimum, include the following information:
a) To scale front, side, and plan views.
b) Dimensions.
c) Interior and exterior arrangements.
d) Mounting information, including conduit entrance location.
e) Finish data.
f) Tag number and functional name of items mounted in and on
each panel, console, and cabinet.
g) Nameplate legend including text, letter size, and colors.
b. Wiring and piping diagrams:
1) Submit panel wiring and piping diagrams for every panel that
contains wiring and/or piping.
March 2021 - DRAFT 40 61 05-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 704
Item#18.
2) Include the following information:
a) Name of panel.
b) Wiring and piping sizes and types.
c) Terminal strip numbers.
d) Wire tags and labels.
e) Functional name and manufacturer's designation for items to
which wiring and piping are connected.
f) Electrical control schematics in accordance with ANSI
standards.
c. Calculations:
1) Provide installation details based on calculated shear and tension
forces:
a) Calculations shall be signed and sealed by a Professional
Engineer licensed in the state where the cabinets and panels
will be installed.
2) For assembled enclosures and other equipment with a weight of
200 pounds or more, provide calculations for:
a) Weight including panel internal components.
b) Seismic forces and overturning moments.
c) Shear and tension forces in connections.
3) Cooling calculations, to include but not limited to:
a) Highest expected ambient temperature for the enclosure's
location
b) Internal heat load.
c) Exposure to direct sunlight.
d) Dimensions of the enclosure in inches.
e) Maximum desired temperature inside the enclosure.
d. Seismic panel construction:
1) Seismic anchorage: Provide seismic design calculations and
installation details for anchorage of all panels, enclosures, consoles,
etc. to meet seismic requirements as specified in Section 01_81_02
- Seismic Design Criteria:
a) Stamped by a Professional Engineer registered in the state
where the Project is being constructed.
2) For floor mounted free standing panels weighing 200 pounds or more
(assembled, including contents), submit calculations, data sheets,
and other information to substantiate that panel, base, and framing
meet minimum design strength requirements and seismic
requirements at the project site. Calculations shall be signed and
sealed by a Professional Engineer.
5. Schematic diagrams:
a. Submit schematic diagrams for all electrical equipment in ladder diagram
format.
b. Include device and field connection terminal numbers on all schematic
diagrams.
E. Process control and LOI software submittal:
1. A complete listing of the PLC system point 1/0 database:
a. Include for each data point, relevant parameters such as range, contact
orientation, limits, incremental limits, 1/0 card byte, 1/0 hardware address,
and PLC assignment.
b. Organize on a site-by-site basis, separate by point type.
March 2021 - DRAFT 40 61 05-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 705
Item#18.
c. In addition to the active 1/0 points, list the implemented spare 1/0 points
and the available 1/0 points remaining on each card, as well as other
defined future points specified or shown.
2. Preliminary LOI screens, including pop-ups, trends, and alarm screens.
Provide electronic and hard copy.
3. Final LOI screens for use by the ICSC in developing graphic screens for
Meridian WWRF PCS system. Provide electronic and hard copy.
4. Provide a complete, documented listing of all PLC codes.
F. Testing:
1. For each test specified in this Section, prepare and submit complete test
plans, test procedures, test forms, test binders, and test reports, and other
submittals, as specified below.
2. Submit manufacturer's certifications and manufacturer's field reports where
required.
3. Submit Test plans, procedures, forms, and binders for approval by the
Engineer before scheduling or performing tests.
4. Additional test form and test procedure requirements are specified with
individual test requirements.
1.06 QUALITY ASSURANCE
A. Furnish all equipment listed by and bearing the label of the UL or of an independent
testing laboratory acceptable to the Engineer and the authority having jurisdiction.
1.07 DELIVERY, STORAGE, AND HANDLING
A. Shipping precautions:
1. After completion of shop assembly and successful Source Testing, pack all
equipment, cabinets, panels, and consoles in protective crates and enclose in
heavy duty polyethylene envelopes or secured sheeting to provide complete
protection from damage, dust, and moisture.
2. Place dehumidifiers when required, inside the polyethylene coverings.
3. Skid-mount the equipment for final transport.
4. Provide lifting rings for moving without removing protective covering.
5. Display boxed weight on shipping tags together with instructions for unloading,
transporting, storing, and handling at the job site.
B. Tagging:
1. Tag each component and/or instrument to identify its location, instrument tag
number, and function in the system.
2. Firmly attach a permanent tag indelibly machine marked with the instrument
tag number, as given in the tabulation, on each piece of equipment provided
as part of this Section.
3. Tag instruments immediately upon receipt in the field.
4. Prominently display identification on the outside of the package.
1.08 PROJECT OR SITE CONDITIONS
A. Provide instruments suitable for the installed site conditions including, but not
limited to, material compatibility, site altitude, site seismic conditions, humidity, and
process and ambient temperatures.
March 2021 - DRAFT 40 61 05-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 706
Item#18.
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING
A. The supplier shall schedule a coordination meeting with the Owner, ICSC, and
Engineer.
1. The meeting shall take place before installation of control systems equipment.
2. The supplier shall bring sample LOI graphic screens, including pop-up, trends,
and alarm screens.
3. Sample LOI graphic screens shall be reviewed and discussed.
4. Discuss Ethernet communications between the MCP and connected devices
provided by others.
5. Data transfer between the MCP and connected devices shall be discussed,
including PLC data register addresses.
1.11 WARRANTY (NOT USED)
1.12 SYSTEM STARTUP (NOT USED)
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 COMMISSIONING (NOT USED)
1.15 MAINTENANCE
A. If the PLC hardware provided for the MCP and local control panels is not the same
type as the WWRF PLC system hardware, the supplier shall provide the following
spare PLC hardware for the PLC equipment in the MCPs and LCPs.
1. 1 spare CPU for every type of CPU in the system.
2. 1 spare I/O modules for every type of I/O module in the system.
3. 1 spare power supplies for every power supply in the system.
4. 1 spare network and/or communications card for every network or
communications card in the system.
5. 1 spare remote adaptor for every remote adaptor in the system.
B. Provide one spare fuse for every fuse furnished on the Project (100% spare fuses
for each panel).
PART PRODUCTS
2.01 GENERAL
A. Signal transmission:
1. Analog signals:
a. Furnish analog measurements and control signals that vary in direct linear
proportion to the measured variable, unless otherwise indicated.
b. Furnish electrical analog signals outside control panels that are 4 to
20 mA 24 VDC, except as indicated.
c. Analog signals within enclosures may be 1 to 5 VDC.
d. Electrically or optically isolate all analog signals from other signals.
e. All pneumatic signals: 3 to 15 psig.
March 2021 - DRAFT 40 61 05-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 707
Item#18.
f. Discrete input signal: 24 VDC or 120 VAC according to the supplier's
discretion.
g. Discrete output signals:
1) Output type according to the supplier's discretion.
2) Provide external terminal block mounted fuse with blown fuse
indication for all discrete outputs.
3) Interposing relays:
a) Provide interposing relays as required.
h. Furnish regulated analog signals that are not affected by changes in
supply voltage or load resistance within the unit's rating.
i. Maintain the total 4 to 20 mA loop impedance to 10 percent below the
published value at the loop operating voltage.
j. Where necessary, reduce loop impedance by providing current-to-current
(1/1) isolation amplifiers for signal re-transmission.
B. Discrete circuit configuration:
1. Configure discrete control circuits to fail safe, on loss of continuity or loss of
power.
2. Alarm contacts: Fail to the alarm condition.
3. Control contacts fail to the inoperative condition unless otherwise indicated on
the Drawings.
C. Grounding:
1. Provide control panels with a signal ground bus, isolated from the power
ground bus:
a. Provide multiple panels in one location with a common point for signal
ground bus connection to ground.
2. Single-point ground shields and measurement loops at the source panel
external terminals, unless otherwise noted, by bonding to the control panel
signal ground bus.
3. Provide isolating amplifiers within control panels for field equipment
possessing a grounded input or output, except when the panel circuit is
galvanically isolated.
2.02 CONTROL PANEL
A. General:
1. PLC processor, power supply, 1/0 backplanes, and modules sized for
connected 1/0 and required spares.
2. An LOI shall be provided on the face of the MCP enclosure for monitoring and
control of the system. Additional HMIs may be provided on individual units
local control panels at the supplier's discretion.
3. The MCP shall exercise control over all aspects of the system. Each unit shall
be equipped with a control panel containing 1/0 modules and necessary
interface with the MCP.
4. Ethernet communication equipment to provide communications with plant PCS
system.
5. The MCP shall continuously monitor all operating parameters, and shall
respond to alarms and emergency conditions by shutting down or activating
system components. The MCP shall indicate alarm conditions locally at the
LOI, and remotely for monitoring by the WWRF PCS system.
6. The MCP shall be integrated into the overall WWRF PCS system via Ethernet.
March 2021 - DRAFT 40 61 05-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 708
Item#18.
7. The MCP shall be capable of sending and receiving equipment status signals,
analog data and alarms, and receiving both discrete and analog control signals
from the WWRF PCS system via Ethernet.
8. The WWRF PCS system (provided by the ICSC)will be configured to store
data for the system for reports and alarm generation. System manufacturer
shall provide information on register addresses on all data, which are to be
transmitted. The data register shall be contiguous for each data type.
9. Uninterruptible power supply.
10. All PLC and LOI programming required for fully functional package control
system.
2.03 PROGRAMMABLE LOGIC CONTROLLERS (PLC) HARDWARE
A. PLC hardware shall be:
1. Per specification Section 40_64_01 Control Systems: Programmable Logic
Controllers.
B. General:
1. Install all communications modules in the PLC backplane.
C. Installed spare requirements:
1. 1/0 points:
a. 25 percent spare capacity for each type of 1/0 signal at the MCP.
b. 25 percent spare capacity for each type of 1/0 signal at the local control
panels.
c. Wire all spare 1/0 points to field terminal blocks in the corresponding
panel.
d. Space shall be available in the MCP to support the future addition of
50percent additional spare 1/0.
2. PLC backplane capacity:
a. At the MCP, 25 percent or 3 spare backplane slots, whichever is greater.
b. At the local control panels, 1 spare backplane slot.
3. PLC memory:
a. 50 percent spare memory.
2.04 UNINTERRUPTIBLE POWER SUPPLY (UPS)
A. General:
1. Provide UPS at MCP.
2. Provide UPS power at LCPs, either via UPS in the MCP, or via separate UPS
mounted in each LCP.
3. The minimum VA rating of the UPS shall be greater than or equal to 1.5 times
the connected load or 700 VA, whichever is greater.
4. The battery shall be sized to provide minimum 15 minutes runtime at full load.
5. Provide calculations showing run time and VA loading of the UPS.
B. Double-conversion true-online UPS: One of the following or equal:
1. Free-standing UPS, 700-3,000 VA:
a. Vertiv, Liebert GXT 4.
b. Eaton Corp., Powerware 9130.
2. Free-Standing UPS, above 3 kVA:
a. Vertiv, Liebert.
March 2021 - DRAFT 40 61 05-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 709
Item#18.
C. Provide manual maintenance bypass switch:
1. 700 to 3,000 VA units: One of the following or equal:
a. Vertiv, Liebert Micropod 2U.
b. Eaton Corp.: Powerware HotSwap.
2. Above 3,000 VA units: By manufacturer of UPS, with connections matched for
operation with UPS.
2.05 HUMAN MACHINE INTERFACE (LOI) HARDWARE
A. General:
1. NEMA Type 4X, or 12 rated, depending upon the environmental are the
cabinet is located.
2. LOI shall communicate directly with PLC processor via dedicated
communication cable.
3. Provide color touch-screen type display.
B. LOI: One of the following or equal:
1. Allen-Bradley, PanelView Plus 7 Standard (2711 P-T10C22D8S, 10.4-inch
version).
2.06 PLC AND LOI PROGRAMMING
A. General:
1. The PLC programming software system shall be manufactured by the PLC
hardware manufacturer.
2. Provide one licensed copy of PLC programming software to the Owner.
3. The LOI programming software system shall be manufactured by LOI
hardware manufacturer.
4. Provide one licensed copy of LOI programming software to the Owner.
B. PLC programming software: One of the following or equal:
1. Rockwell Automation SoftwareRSLogix 5000.
C. LOI programming software: One of the following or equal:
1. Rockwell Automation, Studio 5000.
D. Coordination with plant control system:
1. Coordinate with the ICSC to determine the requirements for data transfer
between the packaged system controls and the plant process control system.
2. Supplier shall program MCP to aggregate the data into contiguous registers for
efficient transfer to the plant process control system.
3. Minimum data transfer shall be as indicated in the control strategies. Supplier
shall supplement the 1/0 requirements with setpoints and virtual 1/0 required to
implement the control strategies as specified in this Section.
4. Unless otherwise stated, the packaged control system shall provide data to the
plant control system with data in engineering units.
5. In addition to the supplier provided equipment, the following systems shall be
monitored and controlled by supplier provided PLCs as indicated on the P&IDs
and in the control strategies.
March 2021 - DRAFT 40 61 05-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 710
Item#18.
E. General programming requirements:
1. Use variable names or aliases derived from tag and loop identification on the
P&IDs for all process values.
2. Program slew rates for all setpoints to limit the effect of updated setpoints on
the process:
a. Provide for control setpoints and manual speed and position selections.
b. Store new setpoints in one register, and gradually ramp the actual
setpoint register at the slew rate until it reaches the new value.
c. Provide operator access to change slew rates through the controls
system.
3. Saved setpoints:
a. Provide an operator selection to save all setpoint values.
b. Provide an operator selection to restore all setpoints to the last saved
value.
4. Calculated values:
a. Program calculations such that division by zero errors cannot occur.
b. Prevent calculations from generating values that exceed the limits of the
equipment or data type structures (integers) internal to the PLC.
c. Configure counting functions (start counts and operation counts) to allow
a minimum of 10,000 counts and to rollover to zero at an even decimal
interval (1 followed by 4 or more zeros).
5. Timers:
a. Provide programmable settling and proving timers in all control sequences
for starting and stopping of equipment to allow the process to settle down
before proceeding with any additional control functions.
6. PLC status:
a. Furnish all information that depicts the status of all enclosures containing
PLC or 1/0 in the control system, including but not limited to the following:
1) PLC cabinet over-temperatures from high temperature switch.
2) Intrusion status on all enclosures equipped with intrusion switches.
3) AC power failure.
4) DC power supply failure.
5) UPS failure signal.
7. PLC system communication status:
a. Furnish a minimum of 1 screen to display all communication errors and
status within the control system network:
1) Communication between PCS and PLC.
2) PLC to RIO.
3) Digital bus network status.
4) Display status of each node, and summary of failures over the past
60 minutes.
b. Generate a communications alarm if any communication fault is detected.
c. In the event of communications loss:
1) Continue normal operation at each PLC with last known shared
values.
F. Common control functions:
1. Incorporate common control functions into all control loops and devices and
into the control programming, whether or not specifically specified in the
specific control descriptions or elsewhere in the Contract Documents.
2. Alarms:
a. Generate alarms within the PLC logic.
March 2021 - DRAFT 40 61 05-14 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 711
Item#18.
b. Indicate alarms at PCS and the LOI. Enable acknowledgement from either
the PCS or the LOI.
c. Once the alarm is acknowledged by an operator, display alarm conditions
in a steady state (not flashing) while the alarm condition is still present:
1) Use interlocks and proving timers to prevent alarms from operating
due to power loss, except for loss of power alarms.
3. Where run time accumulation is required, integrate accumulated run time to
the nearest 0.1 hours whenever the running status input indicates that the
equipment is running:
a. Display total run time in hours.
4. For all monitored analog values:
a. Maintain trends in PCS.
b. Totalize flows:
1) Display totals on the HMI and LOI.
5. Analog data processing:
a. Engineering units conversion:
1) Use engineering units for all analog point values. Convert analog
inputs to engineering units.
b. Analog magnitude checking:
1) Provide clamps to prevent operator-entered values (setpoints, etc.)
that fall outside acceptable limits.
6. Tank and vessel levels:
a. Display all tank and vessel levels as both a level (typically in feet) and a
volume (typically in gallons):
1) Some individual displays may be only level or volume, when agreed
to by the Owner and Engineer during the submittal phase.
b. Monitor rate of change of volume on all tanks and vessel:
1) Establish the maximum rate at which the volume should decrease (all
pumps or feeders operating at maximum output). Generate an alarm
whenever the volume decreases faster than this rate.
7. 1/0 filtering and processing:
a. Analog input filtering:
1) Provide RTU programming for each analog input to implement an
adjustable first order filter, for the purpose of smoothing out spikes
and other noise for analog transmitter input signals. By default, shall
configure analog inputs with no filtering affect.
2) Monitor analog input signal quality:
a) Over range: The input value is above the normal range (typically
over 21 mA).
b) Under range: The input value is below the normal range
(typically under 3 mA, indicating a probable broken connection).
c) Generate alarms for over or under range inputs.
d) Do not use over- or under-range values for control or calculation
purposes:
(1) Where a second instrument is provided to monitor the same
condition (a redundant instrument, or additional instruments
furnished for averaging or different operating modes), and
has a valid signal, use that input for control.
(2) Otherwise, hold all outputs affected by the signal at their
last values before the signal went out of range.
March 2021 - DRAFT 40 61 05-15 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 712
Item#18.
3) Digital input filtering (proving timer):
a) Provide an adjustable time delay function (0-10 seconds) on
discrete input for the purpose of de-bouncing. By default,
discrete inputs shall be configured with de-bounce timers set to
zero seconds.
8. LOI/HMI HAND-OFF-AUTO:
a. Where indicated, provide HAND-OFF-AUTO and START-STOP
selections accessed from an LOI or HMI for operators with sufficient
security, to provide the following operating modes:
1) AUTO: The normal, automatic control mode of the strategy which
allows full PLC control in response to process conditions and
programmed sequences.
2) HAND: Enables Manual control where control decisions are made by
an operator through the START-STOP, OPEN/CLOSE, or other
selections as indicated.
3) OFF: Automated control is disabled and PLC calls for all associated
equipment to stop and valves to close or go to their identified safe
state.
9. Display the current status of all operator selections (HAND/AUTO,
START/STOP, etc.) on the LOI and HMI.
10. Motor control:
a. Display current REMOTE status on the screens.
b. Monitor the device's running status:
1) Display the current status (running or stopped) on the screens.
2.07 PANELS, ENCLOSURES, AND PANEL COMPONENTS
A. General:
1. Provide instruments and other components performing similar functions of the
same type, model, or class, and from one manufacturer.
2. It shall be the responsibility of the supplier to design and size all panels.
3. Design panels to fit in the space as indicated on the Drawings.
B. Requirements:
1. Each panel will be fed by a 480-volt 3-phase AC power circuit or as otherwise
indicated on the Drawings. Panel designs shall include control power
transformers, power supplies and distribution components required to derive
all necessary control voltages.
2. Panel enclosure ratings shall conform to the area classifications as specified in
Section 26 05 00 - Common Work Results for Electrical.
3. Design cabinets for the environmental conditions described in
Section 46_05_10 - Common Work Results for Mechanical Equipment.
4. Unless otherwise indicated on the Drawings, instruments provided as part of
the packaged system shall be powered from supplier provided control
cabinets.
C. Panels/enclosures:
1. Manufacturers: One of the following or equal:
a. Rittal.
b. Hoffman Engineering.
c. Saginaw Control & Engineering.
March 2021 - DRAFT 40 61 05-16 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 713
Item#18.
2. Panel assembly:
a. General guidelines for panel fabrication include:
1) Continuous welds ground smooth.
2) Exposed surfaces free of burrs and sharp edges.
3) Base formed of heavy channel iron, either galvanized or powder
coated, minimum 1/2-inch holes at 12-inch spacing to accommodate
anchoring of freestanding enclosures to floor.
b. Provide stiffeners for back mounting panels in enclosures larger than
4 feet. In addition, secure the panels in place by collar studs welded to the
enclosure.
3. In addition to the requirements specified above, the following requirements for
NEMA Type 4X stainless steel enclosures apply:
a. Minimum 14-gauge, Type 304 stainless steel.
b. Captive stainless steel cover screws threaded into sealed wells.
c. Finish: Unpainted, brushed finish.
d. Specifically designed for use with flange-mounted disconnect handles
where required or as indicated on the Drawings.
4. General wiring requirements:
a. Wiring methods: Wiring methods and materials for panels shall be in
accordance with the NEC requirements for general purpose (no open
wiring) unless otherwise specified.
b. Install all components in accordance with the manufacturer's instructions
included in the listing and labeling.
c. Where the electrical power supply voltage to the control panel is more
than 120 VAC, provide the panel with a control power transformer and
flange mounted disconnect.
1) Mechanically interlock the disconnect switch with the control
enclosure doors so that no door can be opened unless the power is
disconnected. Reactivate power once all doors are closed.
2) Disconnect shall remove power from all power and control circuits,
except for externally wetted signal and control signals. Externally
powered circuits shall be grouped together, labeled, and provided
with finger safe barriers.
d. Control panels supplied with 120 VAC:
1) Provide an internal breaker with the line side terminals covered by a
barrier.
2) Provide a nameplate prominently positioned on the control panel
identifying the location of the power source and a warning statement
requiring the source to be disconnected before opening the door to
the enclosure.
e. Provide a nameplate on the cover of the control panel identifying all
sources of power supply and foreign voltages within the control panel.
f. Provide transformers, protective devices, and power supplies required to
convert the supply voltage to the needed utilization voltage.
g. Provide surge protection device on input supply power.
h. Provide nonmetallic ducts for routing and organization of conductors and
cables:
1) Provide separate ducts for signal and low voltage wiring from power
and 120 VAC control wiring.
i. Provide 1/2-A fuse for each 4-20 mA circuit.
j. Provide 5-A fuse for each discrete input loop.
March 2021 - DRAFT 40 61 05-17 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 714
Item#18.
k. Conductors and cables shall be run from terminal to terminal without
splice or joints. Exceptions:
1) Factory applied connectors molded onto cables shall be permitted.
Such connectors shall not be considered as splices or joints.
I. The control panel shall be the source of power for all 120 VAC devices
interconnected with the control panel including, but not limited to:
1) Solenoid valves.
2) Instruments mounted both in the control panel and remotely
connected to the control panel.
D. Thermal management:
1. Provide heating, cooling, and dehumidifying devices in order to maintain all
instrumentation and control devices to within an acceptable range.
2. Provide enclosure temperature sensor:
a. Manufacturers: One of the following or equal:
1) Omega, EWS Series.
2) TCS Basys Controls, TS Series.
E. Panel meters:
1. Digital:
a. Self-contained instruments that display process signals directly in
engineering units.
b. Manufacturers: The following or equal:
1) Red Lion.
2) Action Instruments Visipak.
2. Digital bar graph meter:
a. Self-contained instruments that display process signals directly in
engineering units, both in decimal format and as a bar graph display.
b. Suitable for panel mounting.
c. Provisions for field adjustable scaling and/or offset.
d. Accuracy shall be within 1 least significant digit.
e. Manufacturers: One of the following or equal:
1) Ametek Dixson.
2) Yokogawa.
3) Weschler Instruments.
F. Pilot devices:
1. General:
a. Provide operator pushbuttons, switches, and pilot lights, from a single
manufacturer.
b. Size:
1) 30.5 millimeters.
c. Heavy duty.
d. Pushbuttons:
1) Contacts rated:
a) NEMA Type A600.
2) Furnish 1 spare normally open and normally closed contact with each
switch.
e. Selector switches:
1) Contacts rated:
a) NEMA Type A600.
b) Knob type.
March 2021 - DRAFT 40 61 05-18 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 715
Item#18.
2) Furnish 1 spare normally open contact and normally closed contact
with each switch.
3) Provisions for locking in the OFF position where lockout provisions
are indicated on the Drawings.
f. Pilot lights:
1) Type:
a) LED for interior installations.
2) Push to test.
3) Lamp color:
a) On/Running/Start: Green.
b) Off/Stop: Red.
c) Power: White.
d) Alarm: Amber.
e) Status or normal condition: White.
f) Opened: Green.
g) Closed: Red.
h) Failure: Red.
2. Indoor and outdoor areas:
a. NEMA Type 4/13.
b. Manufacturers: One of the following or equal:
1) Allen-Bradley, Type 800T.
2) Square D, Class 9001 Type K.
3) General Electric, Type CR104P.
4) IDEC TWTD Series.
3. Corrosive areas:
a. NEMA Type 4X.
b. Corrosion resistant.
c. Exterior parts of high impact strength fiberglass reinforced polyester or
multiple-layer epoxy coated zinc.
d. Manufacturers: One of the following or equal:
1) Cutler Hammer, Type E34.
2) Square D, Class 9001 Type SK.
3) Allen-Bradley, Type 800H.
4) IDEC TWTD Series.
4. Hazardous (Classified) Areas/Class I Division 2:
a. NEMA Type 4X.
b. Corrosion resistant.
c. Exterior parts of high impact strength fiberglass reinforced polyester or
multiple-layer epoxy-coated zinc:
1) All contacts contained within a hermetically sealed chamber:
a) Pushbuttons.
b) Selector switches.
c) Push-to-test contacts on pilot lights.
2) UL listed and labeled for Class I Division 2 areas.
d. Manufacturers: One of the following or equal:
1) Cutler Hammer, Type E34.
2) Allen-Bradley, Type 800H.
G. Signal isolators and converters:
1. Furnish signal isolators that provide complete isolation of input, output, and
power input:
a. Minimum isolation level: 1.5 kV AC/50 Hz for at least 1 minute.
March 2021 - DRAFT 40 61 05-19 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 716
Item#18.
b. Adjustable span and zero.
c. Accuracy: Within 1.0 percent of span.
d. Ambient temperature range: -20 degrees Celsius to +65 degrees Celsius.
2. Manufacturers: One of the following or equal:
a. Phoenix Contact, MCR Series.
b. Acromag, 1500, 600T, 800T, Flat Pack or ACR Series.
c. Action Instruments, Q500 Series or Ultra SlimPakll.
d. AGM Electronics, Model TA-4000.
H. Relays:
1. General:
a. For all types of 120 VAC relays, provide transient surge protection across
the coil of each relay.
b. For all types of 24 VDC relays, provide a free-wheeling diode across the
coil of each relay.
2. General purpose:
a. NEMA A300 rated for standard relays and NEMA B300 for latching.
b. Plug-in type.
c. LED indication for relay energized.
d. Touch safe design: All connection terminals to be protected against
accidental touch.
e. Provide additional (slave/interposing) relays when the following occurs:
1) The number or type of contacts shown exceeds the contact capacity
of the specified relays.
2) Higher contact rating is required in order to interface with starter
circuits or other equipment.
f. DIN rail mounting on 35-mm rail.
g. Ice Cube type relays shall be provided with retainer clips to secure relay in
socket.
h. Manufacturers: One of the following or equal:
1) Phoenix Contact, PLC series.
2) Potter and Brumfield, Type KRP or KUP.
3) IDEC, R* series. (* = H, J, R, S, U).
4) Allen-Bradley, Type 700 HC Series.
5) Schneider Electric, Type K.
3. Time delay:
a. Provide time delay relays to control contact transition time.
b. NEMA A300 rated.
c. Minimum timing range: 0.1 seconds to 10 minutes.
d. Manufacturers: One of the following or equal:
1) IDEC RTE Series.
2) Agastat, Type Series 7000 (pneumatic).
3) Allen-Bradley, Type 700_HR.
I. Terminal blocks:
1. Din rail mounting on 35-mm rail.
2. Suitable for specified AWG wire.
3. Rated for 30 amperes at 600 volts.
4. Screw terminal type.
5. Finger safe protection for all terminals for conductors.
6. Construction: Polyamide insulation material capable of withstanding
temperature extremes from - 40 degrees Celsius to 105 degrees Celsius.
March 2021 - DRAFT 40 61 05-20 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 717
Item#18.
7. Terminals: Plainly identified to correspond with markings on the diagrams:
a. Permanent machine printed terminal identification.
8. Identify terminals suitable for use with more than 1 conductor.
9. Provide minimum 10 percent spare terminals.
10. Manufacturers: One of the following or equal:
a. Phoenix Contact, UT4 Series.
b. Allen-Bradley Series 1492.
11. Fuses (holders) and circuit breakers:
a. Fuse holders:
1) Modular type:
a) DIN rail mounting on 35-mm rail.
b) Touch safe design: All connection terminals to be protected
against accidental touch.
c) Incorporates blown fuse indicator.
d) UL 489 rated, as applicable.
2) Provide nameplate identifying each fuse:
a) As specified in Section 26_05_53 - Identification for Electrical
Systems.
3) Manufacturers: One of the following or equal:
a) Phoenix Contact.
b) Allen-Bradley, 1492-FB Series B.
J. Surge protection devices (SPD):
1. 120 VAC control panel power SPD:
a. Provide SPD for panel 120 VAC power entrances:
1) Non-faulting and non-interrupting design.
2) Provide line to neutral and neutral to ground surge protection.
b. Provide surge protection at secondary of main circuit breaker:
1) Surge protection is not required for 120 VAC circuits that are only
used for panel lights and receptacles.
2) For panels receiving power at 480 VAC, provide surge protection on
the 120 VAC control power transformer secondary.
c. DIN rail mounting.
d. Attach wiring to the SPD by means of a screw-type cable-clamping
terminal block:
1) Gastight connections.
2) Visual status indication of MOV status on the input and output
circuits.
3) Dry contact rated for remote status indication.
e. Approvals:
1) Tested in accordance with IEC 61643-11.
2) Tested in accordance with UL 1283.
3) Tested in accordance with UL 1449.
4) Surge protection minimum requirements: Withstand a minimum
10-kA test current of an 8/20 has waveform in accordance with
IEEE C62.41.1 Category C Area.
f. Manufacturers: One of the following or equal:
1) Phoenix Contact, Type SFP Filter.
2) ASCO, Model 277.
2. 24 VDC control panel power SPD:
a. Provide SPD for 24VDC power circuits.
b. Provide surge protection at DC power supply output.
March 2021 - DRAFT 40 61 05-21 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 718
Item#18.
c. DIN rail mounting.
d. Attach wiring to the SPD by means of a screw-type cable clamping
terminal block:
1) Optical status indicator.
2) Dry contact rated for remote status indication.
e. Approvals:
1) Tested in accordance with IEC 61643-11.
f. Manufacturers: One of the following or equal:
1) Phoenix Contact, Plugtrab PLT-SEC-T3-24-FM-UT.
3. Panel mounted control, signal, and data line SPD:
a. General:
1) This section applies to SPD located in a control panel, field panel,
network junction box, or marshalling panel.
2) Approvals:
a) Tested in accordance with IEC 61643-21.
b) Tested in accordance with UL 497B.
3) SPD shall consist of 2 parts:
a) Base module:
(1) DIN rail mounting.
(a) Grounded to DIN rail via mounting rail foot.
b) Plug protection module:
(1) Replacing a plug shall not require the removal of any wires
nor interrupt the signal.
4) Provide indirect shield ground style SPD unless otherwise noted.
5) Provide ability to locally identify and indicate SPD health.
6) SPD shall be provided with controller module with dry contact for
remote status monitoring of SPD device health.
7) SPD modules shall be compatible with signal, communication bus
type, data type, or control power being protected.
8) Provide dedicated SPD for each signal, communication bus type, or
data line being protected.
b. Manufacturers: One of the following or equal:
1) Phoenix Contact, Plugtrab PT-IQ Series.
2) Dehn, Blitzductor XTU Series.
4. Copper Ethernet SPD:
a. Protects network equipment from lightning or other surge events.
b. Suitable for Gigabit networks.
c. Compatible with shielded Cat 6 cabling with shielded RJ-45 ports.
d. Compliant with PoE standards IEEE 802.3af and 802.3at.
e. Nominal discharge surge current: 10 kA.
f. Approvals:
1) Tested in accordance with IEC 61643-21.
2) Tested in accordance with UL 497B.
g. Manufacturers: One of the following or equal:
1) Phoenix Contact, DT-LAN-CAT6+.
2) Weidmuller, VDATA CAT6.
3) Eaton/MTL, ZoneBarrier.
March 2021 - DRAFT 40 61 05-22 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 719
Item#18.
5. Field device mounted SPD:
a. Conduit entry mounting.
1) Provide parallel or through wiring configurations as required by the
application.
a) Use parallel wiring configuration if there is an available cable
gland at the device.
b) Use through wiring configuration if there is no available cable
gland at the device.
2) Provide Screw connections compatible with field device.
b. NEMA 4X stainless steel material housing.
c. Approvals:
1) Tested in accordance with IEC 61643-21.
d. 4-wire field device:
1) Module shall provide simultaneous protection of signal cable,
communication bus, or data line, and power supply line.
a) Maximum continuous voltage:
(1) DC:
(a) Signal: 32 VDC.
(b) Power supply: 255 VDC.
(2) AC:
(a) Signal: 22.6 VAC.
(b) Power supply: 255 VAC.
2) Manufacturers: The following, engineer knows of no equal:
a) Endress+Hauser, HAW569-CB2C.
e. 2-wire or 3-wire field device:
1) Module shall provide protection for the signal cable, communication
bus or data line.
2) Manufacturers: One of the following or equal:
a) Endress+Hauser, HAW569 Series.
b) Phoenix Contact, Surgetrab S-PT Series.
c) Eaton/MTL, TP Series.
K. Power supplies:
1. Design power supply systems so that either the primary or backup supply can
be removed, repaired, and returned to service without disrupting the system
operation.
2. Convert 120 VAC to 24 volt DC or other DC voltages required.
3. Provide power supplies configured as fully redundant units consisting of
2 power supplies connected with an automatic switchover unit with alarm
contacts monitored by the PLC.
4. Sized to provide 40 percent excess rated capacity.
5. UL 508C listed to allow full rated output without de-rating.
6. Provide fuse or short-circuit protection.
7. Provide a minimum of 1 set of dry contacts configured to change state on
failure for monitoring and signaling purposes.
8. Output regulation: Within 0.05 percent for a 10 percent line change or a
50 percent load change:
a. With remote voltage sensing.
9. Operating temperature range: 0 degrees Celsius to 50 degrees Celsius.
10. Touch safe design: All connection terminals to be protected against accidental
touch.
March 2021 - DRAFT 40 61 05-23 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 720
Item#18.
11. Manufacturers: One of the following or equal:
a. Phoenix Contact Quint Power Supply with SFB technology.
1) Phoenix Contact Quint- O-ring redundancy module.
b. IDEC PSSR Series:
1) With redundancy Diode.
c. Sola.
d. PULS.
L. Intrinsic safety barriers:
1. Transformer isolated barrier:
a. Containing a transformer to provide complete:
1) Isolation between the safe and hazardous areas for loop powered
devices.
2) 3-way isolation between the safe area, hazardous area and power
supply powered devices.
b. Resistor for current limitation.
c. Fuses for short circuit protection.
d. Provide barriers with pluggable connectors that are coded for easy
replacement.
e. Transmission error shall be less than or equal to 0.1 percent of full scale.
f. DIN rail mounted on 35-mm DIN rail.
g. Approvals:
1) FM.
2) UL 913.
2. Manufacturers: One of the following or equal:
a. Phoenix Contact, ME Series.
b. Pepperl + Fuchs.
M. Limit switches:
1. NEMA 4X.
2. AC contact rating 120 V, 10 A.
3. DC contact rating 125 V, 0.4 A.
4. DeviceNet compatible as indicated on the Drawings.
5. Provide robust actuation mechanism not prone to degradation.
6. Provide complete actuator mechanism with all required hardware.
7. Allows for contact opening even during contact weld condition.
8. UL approved.
9. Operating temperature range: -18 degrees to +110 degrees Celsius
(0 degrees to 230 degrees Fahrenheit).
10. Manufacturers: One of the following or equal:
a. Allen-Bradley, 802 Series.
b. Honeywell HDLS Series.
c. Omron D4 Series.
d. Eaton, E47, E49, E50.
e. ABB.
N. Provide a folding shelf for enclosures that contain programmable controllers. The
shelf shall be mounted on the inside surface of the door, capable of supporting a
laptop computer.
March 2021 - DRAFT 40 61 05-24 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 721
Item#18.
O. Protection:
1. Provide disconnecting, short-circuit, and overcurrent protection for all control
panels.
2. Provide a separate protective device for each 120 VAC powered electrical
device.
a. Each 120 VAC control loop and instrument shall have an individual circuit
breaker within its respective control panel and clearly identified for
function.
b. Each 120 VAC and 24 VDC PLC output shall have its own individual fuse
external of the 1/0 card with blown fuse indication:
1) Size external fuse to open before any 1/0 card mounted fuses.
3. Provide dedicated single-pole circuit breakers, one for the panel luminaire(s),
and one for the panel receptacle(s):
a. 15 amperes, 120 VAC.
P. Conductors and cables:
1. Power and control wiring:
a. Materials: Stranded, soft annealed copper.
b. Insulation: 600 volts Type MTW.
c. Minimum sizes:
1) Primary power distribution: 12 AWG.
2) Secondary power distribution: 14 AWG.
3) Control: 16 AWG.
d. Color:
1) AC power (line and load): BLACK.
2) AC power (neutral): WHITE.
3) AC control: RED.
4) AC control: ORANGE for foreign voltages.
5) DC power and control (ungrounded): BLUE.
6) DC power and control (grounded): WHITE with BLUE stripe.
7) Ground: GREEN.
2. Signal cables:
a. Materials: Stranded, soft annealed copper.
b. Insulation: 600 V, PVC outer jacket, 16 AWG paired triad overall
aluminum shield (tape), with copper drain wire.
c. Color:
1) 2 conductor:
a) Positive (+): BLACK.
b) Negative (-): WHITE and RED.
2) 3 Conductor:
a) Positive (+): BLACK.
b) Negative (-): RED.
c) Signal: WHITE.
d. Insulate the foil shielding and exposed drain wire for each signal cable
with heat shrink tubing.
Q. Receptacles:
1. Provide one duplex receptacle located every 4 feet of enclosure width, spaced
evenly along the back mounting panels.
2. GFCI, 125-volt, single-phase, 15-ampere style plug.
3. Provide circuit breaker or fuse to limit receptacle draw to 5 amperes.
March 2021 - DRAFT 40 61 05-25 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 722
Item#18.
R. Grounding:
1. Provide the following:
a. Grounding strap between enclosure doors and the enclosure.
b. Equipment grounding conductor terminals.
c. Provide equipment ground bus with lugs for connection of all equipment
grounding wires.
d. Bond multi-section panels together with an equipment grounding
conductor or an equivalent grounding bus.
2. Identify equipment grounding conductor terminals with the word "GROUND,"
the letters "GND," the letter "G," or the color green.
3. Signal (24 VDC) grounding: Terminate each drain wire of a signal (shielded)
cable to a unique grounding terminal block, or common ground bus at the end
of the cable as shown on the Loop Drawings.
4. Ensure the continuity of the equipment grounding system by effective
connections through conductors or structural members
5. Design so that removing a device does not interrupt the continuity of the
equipment grounding circuit.
6. Provide an equipment-grounding terminal for each incoming power circuit, in
the vicinity of the phase conductor terminal.
7. Size ground wires in accordance with NEC and UL Standards, unless noted
otherwise.
8. Connect all exposed, noncurrent-carrying conductive parts, devices, and
equipment to the equipment-grounding circuit.
9. Connect the door stud on the enclosures to an equipment-grounding terminal
within the enclosure using an equipment-bonding jumper.
10. Bond together all remote and local control panels, processor racks, and
conductive enclosures of power supplies and connect to the equipment-
grounding circuit to provide a common ground reference.
2.08 FIELD INSTRUMENTS
A. General:
1. Instrument housing shall be rated NEMA Type 4X.
2. Wetted materials shall be compatible with process fluid and manufacturer's
recommendations for the intended service.
3. For analog field instruments, provide local LCD display.
4. Provide sunshades for all transmitters located outdoors.
5. Provide all hardware for instrument mounting.
6. Factory calibrate each instrument at a facility that is traceable to the NIST.
7. Analog instrument outputs:
a. Isolated 4-20 mA DC with HART communication protocol.
2.09 ACCESSORIES (NOT USED)
2.10 CONTROL SYSTEM SOURCE TEST
A. Source Test - General:
1. Right of observation: The Owner retains the right to observe all Source test
activities including any and all subsystem preparation, pretests,
troubleshooting, retests, warm-up, and software modification and/or update.
2. The Owner reserves the right to test any specified function, whether or not
explicitly stated in the test submittal.
March 2021 - DRAFT 40 61 05-26 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 723
Item#18.
3. Costs for repeating testing: The supplier shall pay for Engineer's and other
Owner's representatives' travel, subsistence for witnessing the repetition of
failed tests.
4. Correction of deficiencies: Any deficiencies observed during the test shall be
corrected and retested before completion of the test.
5. Any changes and/or corrections shall be noted on the test forms. Engineer
shall witness the revisions and/or corrections prior to leaving the test site.
6. If the corrections and/or revisions are too extensive to be made while the
Engineer is scheduled to be at the Source test site, the Source Test shall be,
at the Engineer's sole discretion, considered failed, and the test shall be
restarted at a later date. All costs for the re-test shall be borne by the supplier.
B. Testing simulation:
1. The Source shall make use of hardware simulators that contain switches, pilot
lights, variable analog signal generators, and analog signal level displays,
which shall be connected to the 1/0 points of the PLCs and controllers
provided. All inputs and outputs shall be simulated and proper control and
system operation shall be validated.
C. Panel inspections:
1. The Engineer to inspect each control panel for completeness, workmanship, fit
and finish, and compliance with the Contract Documents and the approved
shop drawings.
2. Inspection to include, as a minimum: Layout, mounting, wire and data cable
routing, wire tags, power supply, components and wiring, 1/0 components
layout (including terminals, wiring and relays), device layout on doors and front
panels, and proper ventilation operation.
D. 1/0 test:
1. Verify that 1/0 is properly wired to field terminals and is properly mapped into
the PLC and operator displays.
2. Test forms to include, but not be limited to:
a. PLC and panel number.
b. 1/0 type.
c. 1/0 tag name.
d. Panel terminal block numbers.
e. Rack/slot/number of 1/0 point.
f. Check-off for correct response for each 1/0 point.
g. Space for comments.
h. Initials of individual performing test.
i. Date test was performed.
j. Witness' signature lines.
E. Control logic test:
1. The purpose of this test is to verify that all software functions and logic work as
specified, along with any hardwired logic or functions in the tested control
panels.
March 2021 - DRAFT 40 61 05-27 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 724
Item#18.
2. Testing requirements:
a. Demonstrate each function described in the general and specific control
description. Demonstrate in detail how each function operates under a
variety of operating scenarios. Test to verify the application of each
general control strategy function to each specific control strategy or loop
description.
b. Demonstrate the proper operation of the programming and configuration
for each control strategy or loop description. Test each strategy or loop
description on a sentence-by-sentence and function-by-function basis.
Loops with similar or identical logic must each be tested individually.
3. Test forms:
a. Include the fully revised and approved for the loop being tested.
b. Identify the cause and effect as each 1/0 point is toggled through the
simulator. Check boxes shall be provided to track proper and/or improper
operation of the loop.
c. Any deficiencies or operational changes shall be noted on the forms for
correction and documentation:
d. Include signature and date lines.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. Field instruments installation:
1. Install field instruments as specified in the Contract Documents and in
accordance with API 550 and 551 and the manufacturer's instructions.
2. Mount field instruments so that they can be easily read, readily approached,
and easily serviced, and so they do not restrict access to mechanical
equipment:
a. Mount field instruments on a pipe stand or local panel, if they are not
directly mounted.
3. Make connections from rigid conduit systems to field instruments with PVC
coated flexible conduit:
a. Type of flexible conduit required for the area classification.
b. Maximum length of 18 inches.
4. Connect field instruments with cable as specified in the Electrical
Specifications, except when the manufacturer requires the use of special
cable, or otherwise specified in this Section:
a. Special cable applications shall be in accordance with the NEC.
5. Verify the correctness of each installation:
a. Polarity of electric power and signal connections.
b. Ensure all process connections are free of leaks.
B. Process sensing lines and air tubing:
1. Install individual tubes parallel and/or perpendicular to and near the surfaces
from which they are supported.
2. Provide supports for rigid tubing at intervals of not more than 3 feet.
March 2021 - DRAFT 40 61 05-28 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 725
Item#18.
3. Slope horizontal runs of instrument tubing at a minimum of 1/1 6-inch per foot
to allow for draining of any condensate.
4. Bends:
a. Use proper tool.
b. Make bends for parallel lines symmetrical.
c. Make bends without deforming or thinning the walls of the tubing.
5. Square-cut and clean all ends of tubing before being inserted in the fittings.
6. Provide bulkhead fittings at all panels requiring pipe and/or tubing entries.
7. Use stainless steel tubing for all piping hard piped from the air header, unless
otherwise indicated on the Drawings or not compatible with the fluids or
atmosphere in the area:
a. Use flexible connections only on moving equipment and under the
constraint that the length shall be less than 1.5 times maximum travel of
the equipment.
C. Equipment tie-downs:
1. Anchor all instruments, control panels, and equipment by methods that comply
with seismic and wind bracing requirements, which apply to the site.
2. All control panels, VCPs, LCPs, RTUs, PCMs, etc., shall be permanently
mounted and tied down to structures.
D. Instrument tagging:
1. Provide all field-mounted instruments with nameplates:
a. Nameplates engraved with the instrument's full tag number as indicated
on the Drawings:
1) Affix tags with stainless steel wire fasteners.
2. Provide all back of panel instruments with nameplates:
a. Engraved with the instrument's full tag number.
3. Provide all front of panel instruments with a nameplate:
a. Engraving to include the following:
1) Instrument's full tag number.
2) Service description.
b. Nameplates:
1) Secure nameplates to the panel with stainless steel screws.
2) Use an approved adhesive if screws would violate the NEMA or other
ratings of the enclosure.
E. Cable and conductor termination:
1. Terminate all cables and conductors on terminal blocks.
2. Terminal block enclosures:
a. Suitable for the area classification.
F. Surge protection:
1. Provide outdoor field instrument loops with voltage surge protection units
installed on the instruments.
2. Individually fuse each 4-20 mA DC loop with a 1/16-ampere fuse between
power supplies and receiver surge protectors.
3. Provide voltage surge protection for 4-wire transmitters and analyzers:
a. Protect both power source and signal loop.
March 2021 - DRAFT 40 61 05-29 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 726
Item#18.
G. Control panel installation:
1. Install enclosures so that their surfaces are plumb and level within 1/8-inch
over the entire surface of the panel; anchor securely to wall and structural
supports at each corner, minimum. Direct attachment to drywall is not
permitted.
2. Provide floor stand kits for wall-mount enclosures larger than 48 inches high.
3. Provide a full-size equipment-grounding conductor in accordance with NEC
included with the power feeder. Terminate to the incoming power circuit-
grounding terminal.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 FIELD QUALITY CONTROL
A. General:
1. Failure testing:
a. In addition to demonstrating correct operation of all specified features,
demonstrate how the system reacts and recovers from abnormal
conditions including, but not limited to:
1) Equipment failure.
2) Operator error.
3) Communications sub-system error.
4) Power failure.
5) Process equipment failure.
6) High system loading conditions.
B. Loop check/validation:
1. Check all control loops under simulated operating conditions.
2. Provide "end-to-end" tests:
a. Test PLC/controller inputs and outputs from field device to all operator
displays and pilot devices.
C. Pre-commissioning (functional) test:
1. General:
a. Commence pre-commissioning tests after completion of all loop
check/validation tests:
1) Pre-commissioning to demonstrate proper operation of all systems
with process equipment operating over full operating ranges under
conditions as closely resembling actual operating conditions as
possible.
2. Control logic operational validation:
a. The purpose of control logic validation is to field test the operation of the
complete control system, including all parts of the system, all control
panels (including vendor control panels), all control circuits, all control
stations, all monitored/controlled equipment, and final control elements.
March 2021 - DRAFT 40 61 05-30 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 727
Item#18.
3. Loop tuning:
a. Optimally tune all electronic control stations and software control logic
incorporating proportional, integral, or derivative control. Apply control
signal disturbances at various process variable levels and adjusting the
gain, reset, or rate settings as required to achieve proper response.
4. Pre-commissioning validation sheets:
a. Document each pre-commissioning test on an approved test form.
b. Document loop tuning with a report for each loop, including 2-pen chart
recordings showing the responses to step disturbance at a minimum of
3 setpoints or process rates approved by the Engineer. Show tuning
parameters on the charts, along with time, date, and sign-off by supplier
and Engineer.
5. Pre-commissioning certification:
a. Document via a certified report the completion of all pre-commissioning
and test activities:
1) Including all test forms with test data entered, submitted to the
Engineer with a clear and unequivocal statement that all pre-
commissioning test requirements have been satisfied.
D. Performance/reliability/operational tests:
1. After successful completion of the pre-commissioning test as accepted by the
Engineer and Owner, the performance test can proceed.
E. The performance test may be performed concurrently with the 7-day operational
test specified in Section 01_75_17 - Commissioning.
3.08 ADJUSTING
A. Control valves:
1. Stroke all control valves, cylinders, drives and connecting linkages from the
control system as well as local control devices and adjust to verify proper
control action, hand switch action, limit switch settings, torque settings, remote
control actions, and remote feedback of valve status and position.
2. Check control valve actions and positioner settings with the valves in place to
ensure that no changes have occurred since the bench calibration.
3.09 CLEANING
A. Vacuum clean all control panels and enclosures before start-up and again after final
completion of the project.
B. Clean all panel surfaces.
C. Return to new condition any scratches and/or defects.
D. Wipe all instrument faces and enclosures clean.
E. Leave wiring in panels, manholes, boxes, and other locations in a neat, clean, and
organized manner:
1. Neatly coil and label all spare wiring lengths.
2. Shorten, re-terminate, and re-label excessive spare wire and cable lengths, as
determined by the Engineer.
March 2021 - DRAFT 40 61 05-31 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 728
Item#18.
3.10 DEMONSTRATION AND TRAINING
A. Training:
1. Provide system maintenance and operator training courses for all the
instrumentation, control systems furnished.
2. Training course requirements:
a. Operator training:
1) Operator's training shall include:
a) Control system overview: Architecture, equipment functions,
software components, etc.
b) Display navigation, overview, and types of displays.
c) Process and equipment monitoring and control: Basic principles
and operation.
d) Logging ON and OFF the system and description of the security
and access system.
e) Alarm subsystem.
f) Trending: Provide a thorough session on how to use all trending
functions.
b. PLC hardware training:
1) Furnish training on PLC hardware and on related components,
including battery backup equipment, UPSs, LOI hardware, control
circuits, and analog circuits.
2) Furnish training on PLC hardware principles, product features, proper
installation, operation, troubleshooting, and maintenance.
3) PLC training may be provided by manufacturer's certified trainers.
c. PLC software training:
1) Furnish training on PLC software:
a) Training covers the programming conventions, new
standardized software modules, specific control strategy
programs, and documentation created for the work performed
under this Contract.
d. LOI hardware and software training:
1) Provide the following:
a) Overview of hardware and firmware, including starting, stopping,
and PLC interface.
b) Configuration of tag database.
c) Creating, editing, and saving display screens.
d) Troubleshooting.
e. Instrumentation training:
1) Furnish training covering all instruments and control panels.
2) Train maintenance staff in the use, cleaning, calibration,
maintenance, and troubleshooting of all the instruments furnished
within this project.
3) Furnish training on the operation of new hardwired controls.
3.11 PROTECTION
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
March 2021 - DRAFT 40 61 05-32 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_61_05(IDS50) Page 729
Item#18.
B. Fully protect all instruments after installation and before commissioning. The
Contractor shall replace any instruments damaged before commissioning:
1. The sole party responsible for determining the corrective measures is the
Engineer.
3.12 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Furnish all instruments identified on the Contract Drawings or in the Contract
Specifications. If an instrument is shown on one of these documents, it shall be
considered to be shown on all.
B. Produce completed Instrument data sheets for all instruments required under this
Contract:
1. Submit all instrument data sheets for review.
2. Furnish instrument data sheets in both hard copy and electronic format.
C. The instrument data sheets are included as a guideline for the supply of
instruments. The data sheets are not complete; some information needed to order
and specify the required instruments is not included.
D. The P&IDs are intended as a guideline for the supply of instruments. Some
information needed to order and specify the required instruments is not included.
END OF SECTION
March 2021 - DRAFT 40 61 05-33 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_61_05(IDS50) Page 730
Item#18.
SECTION 40_64_01
CONTROL SYSTEMS: PROGRAMMABLE LOGIC CONTROLLERS
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Programmable logic controller (PLC) based control systems hardware.
2. Development software to be used with the specified PLC hardware.
1.02 REFERENCES
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Institute of Electrical and Electronics Engineers (IEEE).
1.03 DEFINITIONS
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Specific definitions:
1. CPU: Central processing unit.
2. 1/0: Input/Output.
C. Specific definitions:
1. Development operating software: The software provided by the PLC
manufacturer for use in programming the PLC.
2. Application software: The software that is programmed specifically for the
Project.
1.04 SYSTEM DESCRIPTION
A. Provide all PLC hardware as indicated on the Drawings and as specified in this
Section.
1.05 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 - Submittal Procedures and
40 61 00 - Common Work Results for Process Control and Instrumentation
Systems.
B. Product data:
1. CPU:
a. Processor type.
b. Processor speed.
c. Memory.
d. Internal processor battery backup time.
March 2021 - DRAFT 40 64 01-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 732
Item#18.
2. 1/0 modules:
a. Type.
b. Standard wiring diagram.
C. Calculations:
1. Submit calculations or documented estimate to verify that memory
requirements of this Section are met, including spare requirements. If possible,
use PLC manufacturer's calculation or estimating worksheet.
2. Submit calculations to verify that spare 1/0 requirements of this Section are
met.
3. Submit calculations to verify that PLC power supply requirements of this
Section are met.
D. Product data:
1. Programming languages.
2. Operating system requirements.
E. Control logic:
1. Fully annotated copy of programmed PLC logic.
2. Cross-referenced index of all PLC registers or points.
F. Provide application software for the specific Project process requirements:
1. Fully annotated copy of programmed PLC logic in its native format.
2. Cross-referenced index of all PLC registers or points.
1.06 QUALITY ASSURANCE
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Provide PLC hardware manufactured at facilities certified to the quality standards of
ISO 9001.
C. Additional requirements:
1. Provide PLC system components by a single manufacturer:
a. Third-party communication modules may be used only for communication
or network media functions not provided by the PLC manufacturer.
2. Use PLC manufacturer approved hardware, such as cable, mounting
hardware, connectors, enclosures, racks, communication cable, splitters,
terminators, and taps.
3. All PLC hardware, CPUs, 1/0 devices, and communication devices shall be
new, free from defects, and produced by manufacturers regularly engaged in
the manufacture of these products.
1.07 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.08 PROJECT OR SITE CONDITIONS
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
March 2021 - DRAFT 40 64 01-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_64_01(IDS50) Page 733
Item#18.
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING (NOT USED)
1.11 WARRANTY
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.12 SYSTEM START-UP (NOT USED)
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 COMMISSIONING (NOT USED)
1.15 MAINTENANCE
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. In addition to the spare parts requirements specified in Section 406100
- Common Work Results for Process Control and Instrumentation Systems, furnish
the following:
1. CPU: 1 spare for each type of CPU in the system.
2. 1/0 cards: 3 spares for each type of 1/0 card in the system.
3. Power supplies: 2 spares for every power supply in the system.
4. Network/communications cards: 1 spare for every network or communications
card in the system.
5. Remote adapter: 1 spare for every remote adaptor in the system.
6. Chassis: 1 spare for each chassis size in the system.
7. Communication cable: 1 spare for each type of cable used in the system.
C. Installed spare requirements:
1. 1/0 points:
a. Provide total of 25 percent spare 1/0 capacity for each type of 1/0 at every
PLC and remote inputs and outputs (RIO).
b. Wire all spare 1/0 points to field terminal blocks in the same enclosure the
PLC resides in.
2. PLC backplane capacity:
a. Provide 25-percent or 3 spare backplane slots, whichever is greater, in all
racks containing 1/0.
3. PLC memory:
a. Provide 50-percent spare program volatile memory.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. Rockwell Automation, ControlLogix:
a. CPU; 1756-L82E
b. Ethernet Communications module; 1756-EN2TR.
March 2021 - DRAFT 40 64 01-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 734
Item#18.
c. Discrete Input Module; 1756-IA161
d. Discrete Output Module; 1756-OA161
e. Analog Input Module; 1756-IF16H
f. Analog Output Module; 1756-OF81
9.
B. The PLC programming software system shall be manufactured by PLC hardware
manufacturer:
1. Rockwell Software:
a. RSLogix 5000.
b. Studio 5000.
2.02 EXISTING PRODUCTS (NOT USED)
2.03 MATERIALS (NOT USED)
2.04 MANUFACTURED UNITS
A. Programmable logic controller:
1. Construction:
a. Furnish plug-in modular system.
b. Provide PLCs capable of operating in a hostile industrial environment
without fans, air conditioning, or electrical filtering:
1) Temperature: 0 to 60 degrees Celsius.
2) RFI: 80 to 1,000 MHz.
3) Vibration: 10 to 500 hertz.
4) Humidity: 0 to 95 percent.
c. Provide internal power supplies designed to protect against overvoltage
and frequency distortion characteristics frequently encountered with the
local power utility.
d. Design the PLC system to function as a standalone unit that performs all
of the control functions described in this Section completely independent
from the functions of the HMI system PC-based operator interfaces:
1) Failure of the HMI system shall not impact data acquisition, control,
scaling, alarm checking, or communication functions of the PLC.
2. CPU:
a. Configure each CPU so that it contains all the software relays, timers,
counters, number storage registers, shift registers, sequencers, arithmetic
capability, and comparators necessary to perform the specified control
functions.
b. Capable of interfacing with all discrete inputs, analog inputs, discrete
outputs, analog outputs, and communication cards to meet the specified
requirements.
c. Capable of supporting and implementing closed-loop floating-point math
and PID control that is directly integrated into the CPU control program.
3. Memory:
a. Non-volatile memory: On-board complementary
metal-oxide-semiconductor (CMOS), electrically erasable programmable
read-only memory (EEPROM), PCMCIA, compact flash card, or SD card.
March 2021 - DRAFT 40 64 01-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_64_01(IDS50) Page 735
Item#18.
b. Supply with sufficient memory to implement the specified control functions
plus a reserve capacity as specified with the requirements of this Section:
1) Reserve capacity:
a) Totally free from any system use.
2) Programmed in a multi-mode configuration with multiple series or
parallel contacts, function blocks, counters, timers, and arithmetic
functions.
4. Programming:
a. Provide a system where processors are programmed by:
1) Portable laptop computer both locally and via the PLC control
network.
5. PLC power supply:
a. Input: 120 VAC.
b. Mounted in the PLC housing or as indicated on the Drawings.
c. Sized to power all modules mounted in that housing including an average
module load for any empty housing slots plus 50 percent above that total.
6. PLC input/output, 1/0 modules:
a. General:
1) Compatible with all of the PLCs being furnished under the contract
and by the same manufacturer as the PLCs.
2) Provide 1/0 modules that:
a) Isolate in accordance with IEEE Surge Withstand Standards and
NEMA Noise Immunity Standards.
b) Provide A/D and D/A converters with optically or galvanically
isolated inputs and outputs.
c) Accept dual-ended inputs.
3) The use of common grounds between 1/0 points is not acceptable.
4) Provide modules that are removable without having to disconnect
wiring terminals:
a) Utilize a swing-arm or plug-in wiring connector.
5) Provide at each PLC the 1/0 modules for the following:
a) Designated future 1/0 points contained in the 1/0 Lists and/or
shown on the P&IDs, control schematics, or described in the
control strategies.
b) Installed spare capacity in accordance with the requirements of
this Section.
c) Wire all spares provided to the field terminal strip.
6) Condition, filter, and check input signals for instrument limit
conditions.
7) Filter, scale, and linearize the raw signal into an engineering-units-
based measurement.
8) Alarm measurements for high, low, rate-of-change limits, and alarm
trends.
9) Provide external fuses mounted on the field connection terminal
block for all discrete input, discrete output, and analog input 1/0
points.
10) When multiple cards of the same 1/0 type are provided and parallel
equipment, instrumentation, or redundant processes exist, distribute
1/0 among cards to ensure that a single card failure will not render an
entire process unavailable.
March 2021 - DRAFT 40 64 01-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 736
Item#18.
b. Discrete input modules:
1) Defined as contact closure inputs from devices external to the input
module.
2) Provide inputs that are optically isolated from low-energy
common-mode transients to 1,500 volts peak from users wiring or
other 1/0 modules.
3) Individually isolated inputs.
4) With LEDs to indicate status of each discrete input.
1) Input voltage: 120VAC.
2) Provide input module points that are individually fused with
blown-fuse indicator lights, mounted external of the module on the
output terminal strip:
a) Coordinate external fuse size with the protection located on the
module, so that the external fuse opens first under a fault
condition.
c. Discrete output modules:
1) Defined as contact closure outputs for ON/OFF operation of devices
external to the output module:
a) Triac outputs may be used, with the permission of the Engineer.
Care must be used in applying this type of module to ensure that
the leakage current through the output device does not falsely
signal or indicate an output condition.
2) Optically isolated from inductively generated, normal mode and
low-energy common-mode transients to 1,500 volts peak.
3) LEDs to indicate status of each output point.
4) Output voltage: 120VAC.
5) Individually isolated outputs.
d. Analog input modules:
1) Signal type: Provide 4-20 mA for most applications; other levels are
acceptable to interface to vendor control panels.
2) Analog-to-digital conversion: Minimum 12-bit precision with the digital
result entered into the processor.
3) The analog-to-digital conversion updated with each scan of the
processor.
4) Individually isolated each input.
5) Coordinate the size of the external fuse with the protection located on
the module, so that the external fuse opens first under a fault
condition.
e. Analog output modules:
1) Signal type: Provide 4-20 mA for most applications; other levels are
acceptable to interface to vendor control panels.
2) Individual isolated output points each rated for loads of up to
1,000 ohms.
7. Communications modules:
a. Remote 1/0 adapter module:
1) For any PLC location requiring more than 1 housing (backplane) to
mount all of the 1/0 modules or that is identified as a RIO, provide an
appropriate communications modules for communication with the
secondary housing(s).
2) Install the communications modules in the PLC backplane and the
RIO backplane.
March 2021 - DRAFT 40 64 01-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_64_01(IDS50) Page 737
Item#18.
3) Provide communications modules that support all available types of
1/0 modules required.
4) Provide all network taps, connectors, termination resistors, drop
cables, and trunk cables necessary for remote 1/0 communications.
5) Complete diagnostic LEDs.
b. Network communications modules:
1) General:
a) Install communications modules in the PLC backplane and
install external ethernet switch to handle building traffic.
2) Ethernet:
a) Ports: 2-RJ-45.
b) Communication rate: 100 Mbit/s.
c) Allen-Bradley ControlLogix - 1756-EN2TR.
3) Provide all network taps, connectors, termination resistors, drop
cables, and trunk cables necessary for remote 1/0 communications.
8. PLC backplane housing:
a. Mount the PLC power supply, CPU, communications module, and 1/0
modules in a suitable standard PLC backplane or housing.
b. Provide spare slots in each PLC and RIO location in accordance with the
requirements of this Section.
c. Provide a blank slot filler module for each spare slot.
B. PLC programming software:
1. Furnish operating software capable of monitoring and/or controlling the PLCs
via the PLC data network:
a. Contain diagnostics to collect troubleshooting and performance data and
display it in easy to understand graphs and tables.
b. Monitor devices at each drop on the PLC data network for proper
communications.
c. Provide the ability to program all PLCs on the PLC data network from the
Engineer's console.
2. PLC programming laptop/desktop operating system:
a. Microsoft Windows 10.
3. The PLC programming software shall be suitable for the PLCs specified
above.
4. PLC programming software for all programming, monitoring, searching, and
editing:
a. Usable both on-line, while connected to the PLC, and off-line.
b. The operating software shall display multiple series and parallel contacts,
coils, timers, counters, and mathematical function blocks.
c. Capable of disabling/forcing all inputs, outputs, and coils to simulate the
elements of the ladder logic; forced elements shall be identifiable by
means of color change.
d. Include a search capability to locate any address or element and its
program location.
e. Display at the EC, PLC status information, such as faults and
communication errors and amount of memory remaining.
5. The PLC programming software shall support the following programming
languages:
a. Ladder Diagram.
b. Function Block Diagram.
c. Structured Text.
March 2021 - DRAFT 40 64 01-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 738
Item#18.
d. Instruction List.
6. Generate a PLC program printout, which is fully documented, through the PLC
programming software:
a. Fully documented program listings include, as a minimum, appropriate
rungs, address, and coils shown with comments to clarify to a reader what
that segment of the program accomplishes on an individual line-by-line
basis.
b. Include a sufficient embedded comment for every rung of the program
explaining the control function accomplished in said rung.
c. Use a mnemonic associated with each contact, coil, etc. that describes its
function.
d. Utilize the tag and loop identification as contained in the P&IDs:
1) If additional internal coils, timers, etc. are used for a loop, they shall
contain the loop number.
e. Provide a cross-reference report of program addresses.
7. Software functions automatically without operator intervention, except as
required to establish file names and similar information:
a. Furnish the operating system software that is the standard uncorrupted
product of the PLC manufacturer with the following minimum functions:
1) Respond to demands from a program request.
2) Dynamic allocation of the resources available in the PLC. These
resources include main memory usage, computation time, peripheral
usage, and I/O channel usage.
3) Allotment of system resources based on task priority levels such that
a logical allocation of resources and suitable response times are
ensured.
4) Queuing of requests in order of priority if one or more requested
resources are unavailable.
5) Resolution of contending requests for the same resource in
accordance with priority.
6) Service requests for execution of one program by another.
7) Transfer data between programs as requested.
8) Management of all information transfers to and from peripheral
devices.
9) Control and recovery from all program fault conditions.
10) Diagnose and report real-time hardware device errors.
8. Program execution:
a. Application software - program execution scheduled on a priority basis:
1) A multilevel priority interrupt structure is required.
2) Enter into a list of pending programs a program interrupted by a
higher priority program:
a) Resume its execution once it becomes the currently highest
priority program.
3) Schedule periodic programs.
4) Base the allocation of resources to a time-scheduled program on its
relative priority and the availability of resources.
March 2021 - DRAFT 40 64 01-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_64_01(IDS50) Page 739
Item#18.
9. Start-up and restart:
a. Provide software that initializes and brings a PLC or any
microprocessor-based hardware unit from an inactive condition to a state
of operational readiness.
b. Initialization:
1) Determination of system status before start-up of initializing operating
system software and initializing application software.
2) Loading of all memory-resident software, initializing timers, counters,
and queues, and initialization of all dynamic database values.
10. Shutdown:
a. Where possible, provide orderly shutdown capability for shutdowns
resulting from equipment failure, including other PLC processor failures,
primary power failure, or a manually entered shutdown command.
b. Upon loss of primary power, a high-priority hardware interrupt initiates
software for an immediate, orderly shutdown.
c. Hardware is quickly and automatically commanded to a secure state in
response to shutdown command or malfunction.
d. Alarm PLC failure at the operator interface level.
11. Diagnostics:
a. Furnish diagnostic programs with the PLC software package to detect and
isolate hardware problems and assist maintenance personnel in
discovering the causes for system failures.
b. Use the manufacturer's standard diagnostic routines as much as possible.
c. Furnish diagnostic software and test programs for each significant
component in the control system.
d. As a minimum, provide diagnostic routines to test for power supply,
central processing unit, memory, communications, and 1/0 bus failures.
12. Calendar/time program:
a. The calendar/time program to update the second, minute, hour, day,
month, and year and transfer accurate time and date information to all
system-level and application software.
b. Variations in the number of days in each month and in leap years must be
handled automatically by the program.
c. The operator must be able to set or correct the time and date from any
operator interface, only at the highest security level.
13. Algorithms:
a. Implementation of algorithms for the determinations of control actions and
special calculations involving analog and discrete data.
b. Algorithms must be capable of outputting positional or incremental control
outputs or providing the product of calculations.
c. Algorithms must include alarm checks where appropriate.
d. Provide, as a minimum, the following types of algorithms:
1) Performs functions such as summing several variables, raising to a
power, roots, dividing, multiplying, and subtracting.
2) A switch algorithm, which reads the current and value from its input
address and stores it as the value of its output address. 2 types of
switches shall be accommodated: 2 outputs with 1 input and 1 output
with 2 inputs.
3) A 3-mode proportional-integral-derivative, PID, controller algorithm,
with each of the 3 modes independently adjustable, supports both
direct and reverse-acting modes.
4) Lead, lag, dead time, and ratio compensators.
March 2021 - DRAFT 40 64 01-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 740
Item#18.
5) Integration and totalization of analog process variables.
14. Furnish a comprehensive database for the analog inputs, calculated values,
control modules, and outputs:
a. In addition, provide spare database points for future expansion.
15. One integrated database can be utilized for all types of analog points or
separate databases for each type; in either case, the database for each point
must include all specified aspects.
16. All portions of the database must be available for use by the display, report,
and other specified software modules.
17. All of the data fields and functions specified below must be part of the point
definition database at the operator interface. Provide the capability to define
new database points through the point display specified below as well as
modifying defined points through these displays. This point definition and
modification must include all of the features and functions defined below. The
analog database software must support the following functions and attributes:
a. Analog input signal types:
1) Provide software at the remote terminal units (RTUs) and PLCs to
read variable voltage/current signals and pulse duration/frequency
type analog input signals.
b. Input accuracy:
1) Inputs must be read with an accuracy of within 0.05-percent full-scale
or better.
2) Data conversion errors must be less than 0.05-percent full-scale.
3) Pulse accumulation error less than or equal to 1 count of actual input
count at a scan rate of once per minute.
4) Maintain for a minimum of 1 year the system accuracy stated above
without adjustments.
c. Blocking:
1) Provide mechanisms to inhibit or block the scanning and/or
processing of any analog input through the operator interface.
2) For any input so blocked, the operator may manually enter a value to
be used as the input value.
d. Filtering:
1) For each analog input, provide a first order lag digital filter with an
adjustable filter factor.
e. Linearizing:
1) Where analog inputs require square root extraction or other
linearization, provide a mechanism to condition the filtered data
before the process of scaling and zero suppression takes place.
f. Calculated values:
1) Provide means to allow for pseudo-inputs calculated by algebraic
and/or Boolean expressions utilizing real inputs, other calculated
values, constants, etc.
2) These values must be handled the same as real inputs in terms of
record-keeping, alarming, etc.
g. Scaling and zero suppression:
1) Provide a conversion program to convert input values into
engineering units in a floating-point format.
h. Alarms:
1) Provide an alarm program to check all analog variables against
high-high, high, low, and low-low alarm limits.
March 2021 - DRAFT 40 64 01-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_64_01(IDS50) Page 741
Item#18.
2) When an analog value exceeds a set limit, it must be reported as an
alarm based on individually set priority level for each alarm point.
3) Provide an adjustable hysteresis band in order to prevent excessive
alarms when a variable is hovering around an alarm limit.
4) Must be possible to inhibit alarms based on external events, e.g.,
lock-out low pump flow alarm when the pump is off.
i. Averages:
1) Provide a program to calculate and store hourly, daily, and monthly
averages of analog variables.
2) Continuously compute averages, e.g., the average for the current
period to the present point in time must be stored in memory and
available for use in displays, etc.
3) Update hourly averages each minute or at the polling interval for the
selected variable.
4) Update daily averages at least once each hour and calculate using
the results of the hourly averages.
5) Update monthly averages at least once each day and calculate using
the results of the daily averages.
6) At the end of each averaging period, store the average values for the
period on the hard disk for historical record-keeping and reset the
present period average register to the present value of the variable.
7) The active database must include the present period average and
previous period average for each variable and averaging period.
j. Totals:
1) Provide a program to calculate and store hourly, daily, and monthly
totalization of analog variables.
2) Assign a scaling factor to each variable to convert to the appropriate
units based on a 1-minute totalizing interval.
3) Assign a separate factor for each totalizing interval.
4) Variables for which totalization is inappropriate must have scaling
factors of zero.
5) At the end of each totalizing period, store the totalized values for the
period on the hard disk for historical record-keeping and reset the
present period totalization register to zero.
6) The active database must include the present period total and
previous period total for each variable and totalizing period.
k. Engineering units:
1) Provide software to allow the system and the operator to convert all
the measured analog variables to any desired engineering units.
2) The operator must be able to view displays and generate reports of
any measured variable in one or more engineering units such as flow
in gpm, mgd, cfs, and acre-feet per day.
3) Pre-program the conversion of the engineering units, and, if not
pre-programmed, the operator must be able to program new
engineering unit conversions by using simple methods, e.g.,
multiplication of the database attributes by a constant.
4) The programming method must be at a level and compatible with the
specified training of the operator and the Owner's personnel.
5) New conversions must not require the services of a special
programmer and/or special, high-level, programming training.
March 2021 - DRAFT 40_64_01-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 742
Item#18.
I. Control modules:
1) For each control function configured, whether processed at the RTU,
PLC, or operator interface, maintain a file of necessary data including
input values, setpoints, constants, intermediate calculated values,
output value and limit clamps, etc.
2) Input and output assignments, setpoints, and constants must be
adjustable by the operator through the operator interface.
3) Provide control algorithms for manual control with output values
adjustable by the operator.
m. Analog outputs:
1) Analog outputs must be maintained as part of the database.
2) These outputs must be adjustable manually by the operator through
the operator interface or through automatic control algorithms.
18. Some of the above functions may be better accomplished in the data
acquisition and graphic display software package; it is the responsibility of the
ICSC to optimize the location of the various functions between all software
packages.
C. General control functions:
1. Analog control functions:
a. PID, lead/lag, signal select, alarm, limit, delay, and time base.
b. Furnish the control system complete with a library of
mathematical/calculation software to support averaging, weighted
average, addition, subtraction, multiplication, division, square root
extraction, exponential, AND, OR, NAND, NOR, XOR, and NXOR
functions.
c. All math utilities must be linkable to process data points or manual inputs
via control block configuration.
d. By linking control blocks to data points, the math library must support
system unit conversion and calculation requirements.
2. Discrete control functions:
a. AND, OR, NOT, EXCLUSIVE OR, comparators, delays, and time base.
3. Software support:
a. Retain in firmware all control and logic functions at each RTU and PLC
and in RAM at the operator interface.
b. Call each function as required by the configured controls to perform the
intended function.
4. Control and status discrepancies:
a. Generate a discrepancy/fail alarm for any pump, valve, or final control
element if a discrepancy exists between a system or operator command
and the device status.
1) For example, the system commands to start (call), and the pump fails
to start (run status report back), within predetermined
operator-programmable time delay (time disagree), then a
discrepancy (fail) alarm shall be generated.
b. Involuntary change in the device's status must also generate an alarm:
1) For example, a pump starts when not commanded to do so, or a
pump shuts down while running even though it still has a command
to run.
c. Each command, status, and alarm must cause the color of the symbol to
change.
March 2021 - DRAFT 40 64 01-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_64_01(IDS50) Page 743
Item#18.
d. Because many discrete final control elements have a cycle time in excess
of the scan interval, provide each control output with an associated delay
period selected to be longer than the operating period of the control
element:
1) Delay periods for each final control element must be adjustable at the
operator interface.
2) List all time delays in the final documentation.
5. Some of the above functions may be better accomplished in the data
acquisition and graphic display software package; it is the responsibility of the
ICSC to optimize the location of the various functions between all software
packages.
D. Control configuration:
1. Provide software to allow control strategies to be developed, and their
operation initiated through the operator interface.
2. Provide standardized control point displays for defining the control functions
including the function type, input/output addresses, setpoints, tuning
constants, etc.
3. Provide a mechanism to link separate control functions together into an
integrated control strategy.
4. Provide a mechanism to download operational/control setpoints developed at
any operator interface to any PLC or RTU for operational implementation.
5. Provide a mechanism to define and implement operational/control setpoints
locally at the PLC or RTU, and to upload them to the operator interface for
operational record-keeping.
6. Perform control configurations on-line at the operator interface; the PLC or
RTU may be taken off-line when being configured or downloaded.
E. Remote inputs and outputs (RIOs):
1. Compatible with all of the PLCs being furnished under this Contract, shall be
by the same manufacturer as the PLCs, and, as a minimum, include:
a. Power supply.
b. Rack.
c. Backplane.
d. Communications module.
e. 1/0 modules.
f. Enclosure.
2. Provide all cables and software needed for a complete and operational RIO
system as specified in the Contract Documents.
3. Provide a group of pre-assigned diagnostic registers to report RIO system
faults to the driver PLC.
4. The control system must continue operation should a fault occur on a single
RIO drop:
a. Upon clearing the fault, restart communications to that drop automatically.
2.05 EQUIPMENT (NOT USED)
2.06 COMPONENTS (NOT USED)
2.07 ACCESSORIES (NOT USED)
2.08 MIXES (NOT USED)
March 2021 - DRAFT 40_64_01-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 744
Item#18.
2.09 FABRICATION (NOT USED)
2.10 FINISHES (NOT USED)
2.11 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Utilize personnel to accomplish or supervise the physical installation of all elements,
components, accessories, or assemblies:
1. Employ installers who are skilled and experienced in the installation and
connection of all elements, components, accessories, and assemblies.
C. All components of the control system including all data network cables are the
installation responsibility of the ICSC unless specifically noted otherwise.
D. General:
1. The control system logic program shall reside at the PLC level.
E. Use the tag and loop identifications found on the P&IDs for all tags used and/or
assigned as part of the application software work provided by the ICSC.
F. Program the PLC logic using the following language(s):
1. Ladder Diagram.
2. Function Block Diagram.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION
A. Provide a minimum of 4 CD/DVD copies of the following:
1. Application software:
a. Finalized fully annotated copy of programmed PLC logic in its native
format.
b. Cross-referenced index of all PLC registers or points.
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
March 2021 - DRAFT 40 64 01-14 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_64_01(IDS50) Page 745
Item#18.
3.07 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.08 ADJUSTING (NOT USED)
3.09 CLEANING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.10 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Tailor training specifically for this Project that reflects the entire control system
installation and configuration.
C. Perform training by pre-approved and qualified representatives of the ICSC and/or
manufacturer of the PLC hardware and programming software:
1. A representative of the ICSC may perform the PLC hardware training only if
the representative has completed the manufacturer's training course for the
PLC hardware.
2. A representative of the ICSC may perform the PLC programming software
training only if the representative has completed the manufacturer's training
course for the PLC programming software.
3.11 PROTECTION
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.12 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 40_64_01-15 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_64_01(IDS50) Page 746
Item#18.
SECTION 40_71_15
FLOW MEASUREMENT: MAGNETIC FLOWMETERS
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Full-body magnetic flowmeters.
B. Provide all instruments identified in the Contract Drawings.
C. Related sections:
1. Section 01 33 00 - Submittal Procedures
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
1.02 REFERENCES
A. As specified in Section 40_61_00.
B. International Organization for Standardization (ISO):
1. 9000 - Quality management systems -- Fundamentals and vocabulary.
2. 17025 - General requirements for the competence of testing and calibration
laboratories.
C. National Institute of Standards and Technology (NIST).
D. NSF International (NSF).
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. A template for the data sheet is included in the specification. System Supplier shall
complete data sheet based on system design.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials, etc.
March 2021 - DRAFT 40_71_15-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_15(IDS50) Page 748
Item#18.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
1.07 PROJECT OR SITE CONDITIONS
A. As specified in Section 40_61_00.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. As specified in Section 40_61_00.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. Endress+Hauser:
a. W 400 for most locations, Promag H100 fine chemical lines less than 1-
inch diameter.
b. Badger ModMAG M-Series
2.02 MANUFACTURED UNITS
A. Magnetic flowmeter:
1. General:
a. Magnetic flowmeters obtain the flow velocity by measuring the changes of
induced voltage of the conductive fluid passing across a controlled
magnetic field.
b. Complete zero stability shall be an inherent characteristic of the flowmeter
system.
c. Include for each magnetic flow metering system:
1) A metering tube with electrodes (sensor).
2) Signal cable.
3) Transmitter integral or remote as indicated on the instrument data
sheets.
4) Foowmeter grounding rings.
March 2021 - DRAFT 40 71 15-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_71_15(IDS50) Page 749
Item#18.
2. Performance requirements:
a. Accuracy:
1) 0.25 percent of flow rate from 10 to 100 percent of full-scale for
velocities ranging between 1.9 to 10 feet per second.
b. Repeatability:
1) 0.25 percent of rate.
3. Element:
a. Metering tube:
1) Constructed of carbon steel or Type 304 stainless steel (unless
specifically noted otherwise in the instrument data sheets) with
flanged connections to match with piping material.
2) Liner material in conformance with:
a) Manufacturer's recommendations for the intended service.
3) Electrodes type and material in conformance with:
a) Manufacturer's recommendations for the intended service.
b) Utilize a minimum of 2, self-cleaning electrodes.
4) Meter terminal housing NEMA Type 4X unless specifically noted
otherwise in the instrument data sheets.
5) Meter coating consisting of epoxy painted finish.
6) Components:
a) 2 grounding rings:
(1) Which are in conformance with the manufacturer's bore and
material recommendation for the meter's intended service.
(2) Designed to protect and shield from abrasion of the liner's
edge interface at the meter's end.
4. Transmitter:
a. Power supply:
1) As indicated in the data sheets. Universal 100-240 VAC.
2) Power consumption: 60 VA maximum.
b. Outputs:
1) As noted in the instrument data sheets.
2) For all instruments with 4 to 20 mA HART or digital bus protocol,
provide a Device Type Manager (DTM) certification by FDT group.
c. Microprocessor-based signal converter/transmitter.
d. Utilize DC pulse technique to drive flux-producing coils.
e. Contain a 6-digit display for flow rate, percent of span, and totalizer.
f. Operator keypad interface.
g. Integral zero return to provide consistent zero output signals in response
to an external dry contact closure.
h. Integral low flow cut-off zero return.
i. Programmable parameters including:
1) Meter size.
2) Full-scale flow rate.
3) Magnetic field frequency.
4) Time constant.
j. Data retention for a minimum of 5 years without auxiliary main or battery
power.
k. Self-diagnostics and automatic data checking.
I. Protected terminals and fuses in a separate compartment which isolates
field connection from electronics.
m. Ambient operating temperature limits of-5 to 140 degrees Fahrenheit (-20
to 60 degrees Celsius).
March 2021 - DRAFT 40_71_15-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_15(IDS50) Page 750
Item#18.
n. The transmitter should retain all setup parameters and accumulated
measurements internally in non-volatile memory in the event of power
failure.
o. Device failure modes, self-monitoring characteristics and remedy
diagnosis shall follow NAMUR standards NE 43 and NE 107.
2.03 ACCESSORIES
A. Stainless steel tag labeled as specified in the Contract Documents.
B. Provide sunshades for all transmitters located outdoors.
C. Provide galvanic isolation gaskets, nylon/TeflonT" flange bolt insulation bushings
and nylon washers on all meters installed on pipes with cathodic protection.
D. Furnish 1 spool piece for every size of magnetic flow tube being provided.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00.
B. Factory calibrate each flow metering system at a facility that is traceable to the
NIST. ISO-17025 accredited test facility with certified accuracy traceable to NIST.
C. Evidence of accreditation shall originate from a national verification agency such as
A2 LA.
D. A real-time computer generated printout of the actual calibration date indication
actual velocities and as read values of the flow tube:
1. Flow calibration report of the manufacturers flow lab calibration procedure
shall be shipped with the meter system.
2. Minimum calibration shall be a 3-point calibration including 1, 3, and 10 feet
per second velocities for every meter and transmitter system.
3. Manufacturer shall archive all calibration reports for future reference.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00.
B. For instruments located outdoors or where instrument elements and transmitters
are separated by conduit located outside the building envelope, provide surge
protection devices at the transmitters.
March 2021 - DRAFT 40 71 15-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_71_15(IDS50) Page 751
Item#18.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
B. Provide manufacturer's services to perform installation inspection.
3.05 ADJUSTING
A. Field verification:
1. Verify factory calibration of all instruments in accordance with the
manufacturer's instructions.
2. The transmitter and sensor to include a method to verify flow meter
performance to the original manufacturer specifications.
3. Verification should be traceable to factory calibration using a third party,
attested onboard system pursuant to ISO standards.
4. The verification report should be compliant to common quality systems such
as ISO 9000 to prove reliability of the meter specified accuracy.
5. Return factory calibrated devices to the factory if they do not meet the field
verification requirements for calibration.
3.06 CLEANING
A. As specified in Section 40_61_00.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
B. Demonstrate performance of all instruments to the Engineer before commissioning.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES
A. Instrument Data Sheets included in this Section.
B. The provided information does not necessarily include all required instruments.
C. Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications,
or both.
END OF SECTION
March 2021 - DRAFT 40_71_15-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_15(IDS50) Page 752
Item#18.
A/E: Carollo Engineers MAGNETIC INSTRUMENT DATA
FLOWMETERS SHEETS
Spec.No. Rev.
Contractor: No By Date Revision 40 71 15
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Reg. P.O.
Location: Meridian,ID
BOM No.: By Chk App
File:
1 Instrument Tag No. F680
2 Service
3 P&ID PI-SSD-06
4 C Line Size/Schedule
5 O Line Material
6 N Connection Type/
Pressure Rating
7 N Connection Materials
8 Tube Size
E 9 Tube Material
L 10 Liner Material
E 11 M Electrode Type Mfg Standard
M 12 E Electrode Material
E 13 T Meter Casing
N 14 E Power Spply I Phase 120 VAC 1P
T 15 R Grounding Type&Matl. Grounding Rings
16 Enclosure Class NEMA 4X
17 Other
18 Fluid
19 F Max Flow
20 L Min Velocity
21 U Min Flow Norm Flow
22 1 Min Temp Max Temp
23 D Min Press Max Press
24 Vacuum Possibility
25 Conductivity
T 26 Function
R 27 Mounting Remote Remote
A 28 Enclosure Class NEMA 4X NEMA 4X
N 29 Length Signal Cable
S 30 Type Span Adjustment
M 31 Power Supply
1 32 Transmitter Output 4-20 mA HART 4-20 mA HART
RelayOut uts Form C Form C
T 33 Accuracy 0.25% 0.25%
T 34 Calibrated Range
E 35 Empty Pipe Detection
R 36 Bi-Directional Flow
37 Display Scale Size Range
381 Alarm Contact No. Form
391 Manufacturer
401 Element Meter Model No.
411 Transmitter(Inst.)Model No.
Notes:
March 2021 - DRAFT 40 71 15-6 1170OA10
pwalCarollolDocumentslClientllDlMeridian/11700A10/Specifications/Pre-Purchase/40_71_15(IDS50) Page 753
Item#18.
A/E: Carollo Engineers MAGNETIC INSTRUMENT DATA
FLOWMETERS SHEETS
Spec.No. Rev.
Contractor: No By Date I Revision 40 71 15
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Reg. P.O.
Location: Meridian,ID
BOM No.: By Chk TAPP
File:
1 Instrument Tag No. SSPRIFIT0502
2 Service SSPRIFIT0501
3 P&ID N12 N12
4 C Line Size/Schedule
5 O Line Material
6 N Connection Type/
Pressure Rating
7 N Connection Materials
8 Tube Size
E 9 Tube Material
L 10 Liner Material
E 11 M Electrode Type Mfg Standard Mfg Standard
M 12 E Electrode Material
E 13 T Meter Casing
N 14 E Power Spply I Phase 120 VAC 1P 120 VACT I
T 15 R Grounding Type&Mad.
16 Enclosure Class NEMA 4X NEMA 4X
17 Other
18 Fluid
19 F Max Flow
20 L Min Velocity
21 U Min Flow I Norm Flow
22 1 Min Temp Max Temp
23 D Min Press Max Press
24 Vacuum Possibility
25 Conductivity
T 26 Function
R 27 Mounting Integral Integral
A 28 Enclosure Class NEMA 4X NEMA 4X
N 29 Length Signal Cable
S 30 Type Span Adjustment
M 31 Power Supply
I 32 Transmitter Output 4-20 mA HART 4-20 mA HART
Relay Outputs Form C Form C
T 33 Accuracy 0.25% 0.25%
T 34 Calibrated Range
E 35 Empty Pipe Detection
R 36 Bi-Directional Flow
37 Display Scale Size Range
38 Alarm Contact No. Form
39 Manufacturer
40 Element Meter Model No.
411 Transmitter(Inst.)Model No.
Notes:
March 2021 - DRAFT 40 71 15-7 1170
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_71_15(IDS50) Page 754
Item#18.
A/E: Carollo Engineers MAGNETIC INSTRUMENT DATA
FLOWMETERS SHEETS
Spec.No. Rev.
Contractor: No By Date Revision 40 71 15
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Reg. P.O.
Location: Meridian,ID
BOM No.: By Chk App
File:
1 Instrument Tag No. F331
2 Service
3 P&ID PI-NFD-06
4 C Line Size/Schedule
5 O Line Material
6 N Connection Type/
Pressure Rating
7 N Connection Materials
8 Tube Size
E 9 Tube Material
L 10 Liner Material
E 11 M Electrode Type Mfg Standard
M 12 E Electrode Material
E 13 T Meter Casing
N 14 E Power Spply I Phase 120 VAC 1 P
T 15 R Grounding Type&Mad.
16 Enclosure Class NEMA 4X
17 Other
18 Fluid
19 F Max Flow
20 L Min Velocity
21 U Min Flow I Norm Flow
22 I Min Temp Max Temp
23 D Min Press Max Press
24 Vacuum Possibility
25 Conductivity
T 26 Function
R 27 Mounting Integral
A 28 Enclosure Class NEMA 4X
N 29 Length Signal Cable
S 30 Type Span Adjustment
M 31 Power Supply
I 32 Transmitter Output 4-20 mA HART
Relay Outputs Form C
T 33 Accuracy 0.25%
T 34 Calibrated Range
E 35 Empty Pipe Detection
R 36 Bi-Directional Flow
37 Display Scale Size Range
38 Alarm Contact No. Form
39 Manufacturer
401 Element Meter Model No.
411 Transmitter Inst. Model No.
Notes:
January 2021 - DRAFT 40_71_15 1170
pw://Carollo/Documents/Client/ID/Meridian/11700A101SpecificationslPre-Purchase/40_71_15(IDS50)0) Page 755
Item#18.
SECTION 40_71_76
FLOW MEASUREMENT: THERMAL MASS
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Thermal mass flow measurement.
B. Provide all instruments identified in the Contract Documents.
1.02 REFERENCES
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.03 DEFINITIONS
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Specific definitions:
1. Surface mount technology: The practice and method of attaching leaded and
non-leaded electrical components to the surface of a conductive pattern that
does not utilize leads in feed-through holes. This technology reduces power
requirements for the thermal flow instruments.
2. Retract mechanism: A device that holds the sensor probe in place for the flow
measurement. This device also includes a mechanism that enables the plant
maintenance staff to remove the probe easily for cleaning and other
maintenance needed. This device also enables the plant maintenance staff to
re-insert the sensor probe back into its original position without leakage for
measurement service again.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 - Submittal Procedures and
40 61 00 - Common Work Results for Process Control and Instrumentation
Systems.
B. Design calculations:
1. Flow modeling.
C. Provide complete documentation covering the traceability of all calibration
instruments.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
March 2021 - DRAFT 40 71 76-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_76(IDS50) Page 757
Item#18.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
D. Provide instruments manufactured at facilities certified to the quality standards of
ISO 9001.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.07 PROJECT OR SITE CONDITIONS
A. Project environmental conditions as specified in Section 40_61_00 - Common Work
Results for Process Control and Instrumentation Systems:
1. Provide instruments suitable for the installed site conditions including, but not
limited to, material compatibility, site altitude, site seismic conditions, humidity,
and process and ambient temperatures.
1.08 WARRANTY
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.09 MAINTENANCE
A. Furnish all parts, materials, fluids, etc. necessary for operation, maintenance, and
calibration purposes throughout the warranty period. Deliver all of these supplies
before project substantial completion.
PART PRODUCTS
2.01 MANUFACTURERS
A. Thermal mass flowmeters:
1. Dry gas measurement:
a. Insertion mounting:
1) One of the following or equal:
a) Fluid Components International (FCI°), Model No. ST100.
b) Kurz Instruments, Inc., Model No. 454FTB series.
c) Sierra Instruments, Inc., Model No. 640S.
March 2021 - DRAFT 40 71 76-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_76(IDS50) Page 758
Item#18.
b. Inline mounting with integral flow conditioning:
1) One of the following or equal:
a) Kurz instrument, Inc., Model 534FTB.
b) Fluid Components International (FCI°), Model ST100L.
2. Wet gas measurement (insertion mounting):
a. One of the following or equal:
1) Kurz Instruments, Inc.:
a) Single point: Model No. 454FTB-WGF series.
b) Multipoint: K-Bar 2000B series and Mass Flow Computer.
b. Fluid Components International LLC (FCI°), Model No. ST50 with thermal
dispersion flow element, remote transmitter, and a balance retract
mechanism for the probe sensor.
2.02 MANUFACTURED UNITS
A. Thermal mass flowmeter for dry gas measurement:
1. General:
a. Thermal mass flowmeters measure airflow, industrial, and process gas
mass flows by detecting the heat transfer from a heated RTD sensor
referenced to the temperature of the ambient gas stream sensor.
b. The electronic circuitry shall either maintain a constant differential
temperature between the gas temperature and the heated element or a
constant power.
c. The electronic circuitry shall deliver a linear signal 4 to 20 mA DC output
proportional to the process fluid flow.
2. Performance requirements:
a. Accuracy:
1) 1.5 percent of full scale for velocities over 2 feet per second.
b. Repeatability:
1) 0.5 percent of full scale.
3. Element:
a. Sensor with terminal enclosure.
b. Mounting:
1) For insertion mounting:
a) Utilize a sensor with 3/4-inch male NPT process connection.
2) For inline mounting:
a) Utilize a sensor with Class 150 ANSI flanged connection.
c. No overheat at zero flow.
4. Transmitter:
a. Microprocessor-based.
b. Enclosure: NEMA Type 4X.
c. Power supply:
1) 120 VAC.
2) Power consumption: 50 VA maximum.
d. Outputs:
1) Isolated 4 to 20 mA DC with HART communication protocol.
e. Alphanumeric display for flow rate.
f. Ambient operating temperature limits: 0 to 150 degrees Fahrenheit.
5. Components:
a. Signal cable between insertion probe and transmitter:
1) Abrasive-resistant, polyurethane jacket.
March 2021 - DRAFT 40 71 76-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_76(IDS50) Page 759
Item#18.
2) Sensor cable permanently bonded to sensor.
3) Provide enough length of cable to allow removal and inspection of
insertion element.
B. Thermal mass flowmeter for wet gas measurement:
1. General:
a. Thermal mass flowmeters measure airflow, industrial, and process gas
mass flows by detecting the heat transfer from a heated RTD sensor
referenced to the temperature of the ambient gas stream sensor.
b. The electronic circuitry shall either maintain a constant differential
temperature between the gas temperature and the heated element or a
constant power.
c. The electronic circuitry shall deliver a linear signal proportional to the
process fluid flow.
2. Performance requirements:
a. Accuracy:
1) 1.5 percent of full scale for velocities over 2 feet per second.
b. Repeatability:
1) 0.5 percent of full scale.
3. Element:
a. Sensor with terminal enclosure.
b. Utilize a sensor with 3/4-inch male NPT process connection.
c. No overheat at zero flow.
4. Transmitter:
a. Microprocessor-based.
b. Enclosure: NEMA Type 4X.
c. Power supply:
1) 120 VAC.
2) Power consumption: 50 VA maximum.
d. Outputs:
1) Isolated 4 to 20 mA DC with HART communication protocol.
e. Alphanumeric display for flow rate.
f. Ambient operating temperature limits: 0 to 150 degrees Fahrenheit.
5. Components:
a. Signal cable between insertion probe and transmitter:
1) Abrasive-resistant, polyurethane jacket.
2) Sensor cable permanently bonded to sensor.
3) Provide enough length of cable to allow removal and inspection of
insertion element.
2.03 ACCESSORIES
A. Software (if available as either a standard or an option) for fully validation on
instrument performances.
B. Provide sunshade for outdoor installations.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
March 2021 - DRAFT 40 71 76-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_76(IDS50) Page 760
Item#18.
B. Factory calibrate each instrument with a minimum 3-point calibration or according to
Manufacturer's standard at a facility that is traceable to the NIST:
1. Submit calibration data sheets to the Engineer at least 30 days before
shipment of the instruments to the project site.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine the installation location for the instrument and verify that the instrument will
work properly when installed:
1. Notify the Engineer promptly if any installation condition does not meet the
instrument manufacturer's recommendations or specifications.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Install digester gas flowmeters 45 degrees below the horizontal to prevent
condensation from building up on the tip.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Provide manufacturer's services to perform installation inspection services.
3.05 ADJUSTING
A. As specified in Section 40_80_01 - Commissioning for Instrumentation and
Controls.
3.06 CLEANING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.08 PROTECTION
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
March 2021 - DRAFT 40 71 76-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_76(IDS50) Page 761
Item#18.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications,
or both.
END OF SECTION
March 2021 - DRAFT 40 71 76-6 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_71_76(IDS50) Page 762
Item#18.
A/E: Carollo Engineers THERMAL MASS
FLOWMETERS
Spec. No. Rev.
Contractor: N By Dat Revisio 40 71 76
o e n — —
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Req. P.O.
Location: Meridian, ID
BOM No.: By Chk App
File:
1 Instrument Tag No. SSPR1 FIT0010- SSPR1 FIT0020
2 Service
3 P&ID N07 N08
4 C Line Size/Schedule 8 INCH 8 INCH
5 O Line Material
6 N Connection Type
7 N Connection Materials
8 Type Spool Piece: Insertion:
X
E 9 P Probe Material
1 Probe Insertion
L 0 R Length
E 1 O Enclosure Class
M 1 B Balance Retract
2 Mech.
E 3 E Other
N 4 Other
T 5 Other
1 Fluid AIR AIR
6
1 F Max Flow Units SCFM SCFM
7
1 L Max Velocity Units
8
9 U Flow Min Flow
2 1 Max Min
0 Temp Temp
2 D Max Min I
1 Press Press
2 Other
2
2 Other
3
T 2 Function
R 5 Mounting REMOTE REMOTE
A 6 Enclosure Class NEMA 4X NEMA 4X I
N 2 Length Signal Cable
S 8 Type Span Adjustment Mfr. Std.
March 2021 - DRAFT 40 71 76-7 1170
pwalCarollolDocumentslClientllDlMeridianl11700A101SpecificationslPre-Purchasel40_7176(IDS50) Page 763
Item#18.
SECTION 40_72_24
LEVEL MEASUREMENT: RADAR PULSE TIME OF FLIGHT (PTOF)
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Non-contact radar (PTOF) level instruments.
B. Provide all instruments identified in the Contract Documents.
C. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
1.02 REFERENCES
A. As specified in Section 40_61_00.
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
B. Specific definitions:
1. PTOF: Pulse Time of Flight.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. A template for the data sheet is included in the specification. System Supplier shall
complete the data sheet based on system design.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials, etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
March 2021 - DRAFT 40 72 24-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_24(IDS50) Page 765
Item#18.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
1.07 PROJECT OR SITE CONDITIONS
A. As specified in Section 40_61_00.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. As specified in Section 40_61_00.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following:
1. Endress+Hauser, Micropilot FMR20.
2.02 MANUFACTURED UNITS
A. Pulse Time of Flight:
1. General:
a. Instrument emits radar pulses via a transmitter, with a frequency range of
6.3 GHz to 26 GHz.
b. The pulses reflect from the surface being measured and are received
back at the instrument via a sensor.
c. The instrument measures the pulse travel time between the transmitter,
surface, and receiver to calculate the level.
d. Safety:
1) Shall not generate frequency waves with power levels hazardous to
humans.
2. Performance requirements:
a. Accuracy:
1) 0.1-inch.
3. Element:
a. Level element must conform to the process material compatibility as
indicated on the Instrument Data Sheets or the Instrument Index.
b. Connections:
1) Process: Tank mounted.
2) The design shall be such that product condensation on the antenna
shall not affect the performance of the gauge. It shall be possible to
choose between either parabolic-, cone-, rod-shaped antennas.
4. Display:
a. E&H RIA15.
b. Power supply:
1) 24 VDC - 2-wire loop powered.
2) Power consumption: 15 VA maximum.
March 2021 - DRAFT 40 72 24-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_72_24(IDS50) Page 766
Item#18.
c. Backlit digital display for level or volume.
d. Protected terminals and fuses in a separate compartment, which isolates
field connection from electronics.
1) Indication: Local - 5-digit display.
e. Enclosure rating: NEMA Type 4X.
f. Electrical connection: 1/2-inch male NPT.
2.03 ACCESSORIES
A. Software: Provide Windows based PC software for configuration and echo mapping.
B. Provide sun shield for outdoor installations.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00.
B. Factory calibrate each level transmitter at a facility that is traceable to NIST.
C. Provide complete documentation covering the traceability of all calibration
instruments.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00.
B. Coordinate the installation with all trades to ensure that the mechanical system has
all necessary appurtenances including weld-o-lets, valves, etc. for proper
installation of instruments.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
3.05 ADJUSTING
A. Verify factory calibration of all instruments in accordance with the manufacturer's
instructions:
1. Return factory calibrated devices to the factory if they do not meet the field
verification requirements for calibration.
3.06 CLEANING
A. As specified in Section 40_61_00.
March 2021 - DRAFT 40 72 24-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_24(IDS50) Page 767
Item#18.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
B. Demonstrate performance of all instruments to the Engineer before commissioning.
C. Furnish 2 hours of Owner training.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications
or both.
END OF SECTION
March 2021 - DRAFT 40 72 24-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_72_24(IDS50) Page 768
Item#18.
A/E: Carollo Engineers RADAR PTOF LEVEL
INSTRUMENTS
Spec.No. Rev.
Contractor: N B Date Revision 40 72 24
o —
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Reg. P.O.
Location: Meridian,ID
BOM No.: By Chk App
File:
G 1 Instrument Tag SSPRlLIT0501
Number
E 2 Service MGCL Tank
N 3 P&ID N11
4 Other
5 Type Pulse Time of Flight
(PTOF)
P 6 Housing Material PVDF
R 7 Measurement Range By Vendor
O 8 Op.Temp.Range
B 9 Manufacturer E+H
E 10 Model FMR20
11 Model Number
12 Antenna Style Probe
13 Other
14 Other
15 Other
16 Other
17 Type Pulse Time of Flight
(PTOF)
T 18 Operating Mode
R 19 Enclosure NEMA 4X
A 20 Mounting Remote—Near Fill
N 21 Temperature Range Connection
S 22 Voltage Requirements
M 23 Power Loop Powered 24 VDC
1 24 Accuracy f 0.25inches
T 25 Calibrated Range
T 26 Display Multi Character LCD
E 27 Output 4-20 mA HART
R 28 Calibration
29 Status Relay
30 Manufacturer E+H
31 Model No.
32 Damping
33 Elect.Entry
34 Other
O 35
P 36
T 37
S 38
Notes:
March 2021 - DRAFT 40 72 24-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_24(IDS50) Page 769
Item#18.
SECTION 40_72_36
LEVEL MEASUREMENT: CAPACITANCE
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Level measurement devices using the principle of admittance/capacitance for
level measurement.
2. For discrete measurement of liquid, slurry and granular levels.
3. For analog measurement of liquid, slurry and granular levels.
B. Provide all instruments identified in the Contract Documents.
1.02 REFERENCES
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.03 DEFINITIONS
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 - Submittal Procedures and
40 61 00 - Common Work Results for Process Control and Instrumentation
Systems.
B. Provide complete documentation covering the traceability of all calibration
instruments.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials, etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
March 2021 -DRAFT 40 72 36-1 117
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_36(IDS50) Page 771
Item#18.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
D. Manufacture instrument facilities certified to the quality standards of ISO Standard
9001 — Quality Systems — Model for Quality Assurance in Design/Development,
Production, Installation and Servicing.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.07 PROJECT OR SITE CONDITIONS
A. Project environmental conditions as specified in Section 40_61_00 - Common Work
Results for Process Control and Instrumentation Systems:
1. Provide instruments suitable for the installed site conditions including, but not
limited to, material compatibility, site altitude, site seismic conditions, humidity,
and process and ambient temperatures.
1.08 WARRANTY
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
1.09 MAINTENANCE
A. Furnish all parts, materials, fluids, etc., necessary for operation, maintenance, and
calibration purposes throughout the warranty period. Deliver all of these supplies
before project substantial completion.
PART PRODUCTS
2.01 MANUFACTURERS
A. Continuous RF admittance/capacitance level:
1. One of the following or equal:
a. Drexelbrook, Universal Lite 509-15 Series.
b. Delta Controls, Model TS173.
c. Endress + Hauser, Liquicap Level Transmitter, Models FM151/52.
d. Magnetrol Kotron 805.
2.02 MANUFACTURED UNITS
A. RF admittance/capacitance level measurement:
1. General:
a. RF signal enables a very small current flow from the sensor to reference
ground. A change in RF admittance indicates presence or absence of the
measured material. Transmitter circuitry enables the instrument to ignore
the effect of buildup of material coating on the sensing element.
March 2021 -DRAFT 40 72 36-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_72_36(IDS50) Page 772
Item#18.
b. Single-point level switch sensing level of liquid, slurries, or granular
materials.
c. Sensing interface between 2 liquids with significantly different dielectric
constants (1 liquid must be non-conductive).
2. Performance requirements:
a. Accuracy:
1) Within 0.25-inch.
b. Repeatability:
1) Within 0.1-inch.
3. Element:
a. Rigid probe or flexible cable with weight for large container liquid
applications.
b. Probe and insulation material must conform to measured material
chemical compatibility as indicated on the instrument data sheet or the
instrument index.
4. Transmitter:
a. Power supply:
1) 24 VDC.
2) Power consumption: 15 VA maximum.
b. Outputs:
1) Isolated 4 to 20 milliamperes DC with HART communication protocol.
c. Enclosure: NEMA Type 4X.
d. Operating temperature range from -28 to 155 degrees Fahrenheit.
2.03 ACCESSORIES
A. Provide sunshades for outdoor installations.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
B. Factory calibrate each instrument with a minimum 3-point calibration or according to
Manufacturer's standard at a facility that is traceable to the NIST:
1. Submit calibration data sheets to the Engineer at least 30 days before
shipment of the instruments to the project site.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine the installation location for the instrument and verify that the instrument will
work properly when installed:
1. Notify the Engineer promptly if any installation condition does not meet the
instrument manufacturer's recommendations or specifications.
March 2021 -DRAFT 40 72 36-3 117
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_36(IDS50) Page 773
Item#18.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.05 ADJUSTING
A. As specified in Section 40_80_01 - Commissioning for Instrumentation and
Controls.
3.06 CLEANING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.08 PROTECTION
A. As specified in Section 40_61_00 - Common Work Results for Process Control and
Instrumentation Systems.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications,
or both.
END OF SECTION
March 2021 -DRAFT 40 72 36-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridianl11700A101SpecificationslPre-Purchasel40_72_36(IDS50) Page 774
Item#18.
SECTION 40_72_76
LEVEL MEASUREMENT: SWITCHES
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Displacement float level switch.
2. Tuning fork level switch.
B. Provide all instruments identified in the Contract Documents.
C. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
3. Section 40 72 76 - Level Measurement: Switches.
4. Section 40_80_01 - Testing, Calibration, and Commissioning.
1.02 REFERENCES
A. As specified in Section 40_61_00.
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. Provide complete documentation covering the traceability of all calibration
instruments.
C. A template for the data sheet is included in the specification. System Supplier shall
complete data sheet based on system design.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
March 2021 - DRAFT 40 A 76-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_76(IDS50) Page 775
Item#18.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
1.07 PROJECT OR SITE CONDITIONS
A. Project environmental conditions as specified in Section 40 61_00:
1. Provide instruments suitable for the installed site conditions including, but not
limited to, material compatibility, site altitude, site seismic conditions, humidity,
and process and ambient temperatures.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. Furnish all parts, materials, fluids, etc. necessary for operation, maintenance, and
calibration purposes throughout the warranty period. Deliver all of these supplies
before project substantial completion.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. Tuning fork level switch:
a. E+H, Liquiphant.
b. Drexelbrook, TF-100 Series.
2. Displacement float level switch:
a. Gems Sensors and Controls, Series LS-3.
b. B/W, Unifloat.
3. Ball float level switch:
a. E+H, Liquifloat T FTS20.
b. Evoqua Water Technologies, 9G-EF.
c. ITT Flygt, Model ENM-10.
d. Anchor Scientific Inc., Ecofloat/Solofloat.
2.02 MANUFACTURED UNITS
A. A. Ball float level switch:
1. General:
a. Free hanging, encapsulated body with a switch to determine position of
float.
2. Element:
a. Mechanical switch encapsulated in waterproof floating ball of nominal
diameter, supported by flexible PVC cable and jacket or heavy neoprene.
b. The length of the PVC cable shall be, at a minimum, equal to sump depth
plus 5 feet.
March 2021 - DRAFT 40 72 76-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_76(IDS50) Page 776
Item#18.
c. Float: Provide Type 316 stainless steel or polypropylene, maximum
3 inches in diameter.
d. An operating temperature rating: -30 degrees Fahrenheit to +150 degrees
Fahrenheit.
e. Mercury switches are not acceptable.
f. Lead wires: Mounted in flexible waterproof PVC cable from switch to
junction box terminals without splices.
3. Switch:
a. Single pole double throw contacts rated 10 amps resistive at 120 VAC.
b. Provide the number of floats per level system as indicated on the
Drawings.
c. Suspend ball float and adjust for level setpoint as required.
4. Components:
a. Floats shall include Type 316 stainless steel clamp and brackets and 1/4-
inch cable to allow testing of the float without entering the basin or wet
well.
b. Provide strain relief at both ends of the float cable.
B. Tuning fork level switch:
1. General: Tuning fork level switches comprised of a control relay, mechanically
rigid fork, and transmitter housing.
2. Switch: The control relay senses the liquid level by frequency attenuation at
the probe fork when immersed.
a. Power supply:
1) 120 VAC.
2) Power consumption: 10 VA maximum.
b. Outputs:
1) Relay outputs:
a) 1 Form C contact.
b) 5 amperes at 120 VAC.
c) Programmable.
c. Electrical connection: One 1/2-inch NPT conduit entry.
d. Enclosure: NEMA Type 4X.
e. Approvals: Class I, Div 1 - if wired intrinsically safe.
C. Displacement float level switch:
1. General: Float with a permanent magnet encircles a stationary stem. A
hermetically sealed magnetically operated latching reed switch(es) mounted in
the stem:
a. Mercury switches are not acceptable.
2. Lead wires: Mounted in flexible waterproof PVC cable from switch to junction
box terminals without splices.
3. Switch:
a. Single pole single throw (SPST).
4. The number of floats per level system shall be as indicated on the Drawings.
2.03 ACCESSORIES (NOT USED)
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00.
March 2021 - DRAFT 40 A 76-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_76(IDS50) Page 777
Item#18.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine the installation location for the instrument and verify that the instrument will
work properly when installed:
1. Notify the Engineer promptly if any installation condition does not meet the
instrument manufacturer's recommendations or specifications.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
3.05 ADJUSTING
A. As specified in Section 40_80_01.
3.06 CLEANING
A. As specified in Section 40_61_00.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be as indicated on the Drawings, as specified in the
Specifications or both.
END OF SECTION
March 2021 - DRAFT 40 72 76-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_72_76(IDS50) Page 778
Item#18.
A/E: Carollo Engineers LEVEL SWITCHES
Spec.No. Rev.
Contractor: No By Date Revision 40 72 76
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Reg. P.O.
Location: Meridian,ID
BOM No.: By Chk. App.
File:
1 Type Conductance: Capacitance: Tun*n Fork:X Ball Float: Displacement:X
2 Setting Field Set: Facto Set:X
G 3 Dead Band Fixed:X Ad': I Other:
E 4 Material
N 5 Dimensions Field Set:
E 6 Mounting Flange:X Threaded: Other:
R 7 Operating Pressure/Tem erature
A 8 Connection MFR STD:X Other:
L 9 Manufacturer
10 Other
11 Other
S 12 Type Mechanical:X Reed: Other:
W 13 Quantity Single:X Dual: Other:
I 14 Form SPST: SPDT:X DPDT: Other:
T 15 Rating: Amps Volts Hertz
C 16 Load Inductive: Non-Inductive:X
H 17 Other
18 Other
Rev. Tag Number Model No. Setpoint P&ID Service Notes
SSPRI ISH0105
and 0205 Foam Detection Tuning Fork
SSPRILSH0500 MGCL Tank Leak Tuning Fork
Detection
SSPRILSH0502 MGCL Tank Displacement
Level High Float
Notes: Refer to Section 40_72_76 for additional level switch requirements.
March 2021 - DRAFT 40 72 76-5 1170
pw://Carollo/Documents/ClienUlD/Meridian/11700A10/Specifications/Pre-Purchase140_72_76(IDS50) Page 779
Item#18.
SECTION 40_73_13
PRESSURE/VACUUM MEASUREMENT: GAUGES
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Pressure/vacuum gauges.
B. Provide all instruments specified in the Contract Documents.
C. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
1.02 REFERENCES
A. As specified in Section 40_61_00.
B. American Society of Mechanical Engineers (ASME):
1. 1340.100 - Pressure Gauges and Gauge Attachments.
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. Additional requirements:
1. Product data:
a. Accessories such as diaphragm seals, valve manifold, snubbers, and
pulsation dampeners.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials, etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
March 2021 - DRAFT 40_73_13-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_13(IDS50) Page 781
Item#18.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
1.07 PROJECT OR SITE CONDITIONS
A. As specified in Section 40_61_00.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. As specified in Section 40_61_00.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. Ashcroft:
a. Maximum pressure less than 10 pounds per square inch: Model 1188.
b. Maximum pressure less than 200 pounds per square inch:
1) Model 1279.
2.02 MANUFACTURED UNITS
A. General:
1. Pressure gauge assembly shall include pressure-sensing element, gauge
case, and dial mechanism.
B. Performance requirements:
1. Pressure range:
a. As specified in the Contract Documents.
2. Accuracy:
a. Grade 2A, as defined by ASME B40.100.
b. Within 1.0 percent of span after friction errors are eliminated by tapping or
vibration.
c. Maximum allowable friction inaccuracy: Within 1.0 percent of span.
3. Element:
a. Where the maximum pressure is less than 10 pounds per square inch,
provide socket and bellows; for all other pressure ranges, employ a
Bourdon®tube.
b. Socket tips for bellows and Bourdon®tube:
1) Materials: Type 316 stainless steel.
c. Overpressure: Minimum 130 percent of maximum range pressure without
damage to gauge or sensing element.
d. Wetted materials: Type 316 stainless steel.
March 2021 - DRAFT 40 73 13-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_73_13(IDS50) Page 782
Item#18.
4. Dial gauge:
a. Dial size: 4-1/2 inches.
b. Dial case material:
1) Maximum pressure less than 10 pounds per square inch:
a) Stainless steel.
2) Maximum pressure greater than or equal to 10 pounds per square
inch:
a) Stainless steel.
c. Provide safety gauge with safety blow out through the back or top of the
unit.
d. Dial face: Gasketed shatterproof glass or polycarbonate.
e. Provide gauge locks on all pressure gauges directly connected to sanitary
seals.
f. Provide gauge locks where possible.
g. Connection and mounting:
1) Direct mounted and suitable for outdoor installation.
2) 1/2-inch NPT.
3) Connection material: Stainless steel.
h. Pointer: Externally adjustable.
2.03 ACCESSORIES
A. Pulsation dampeners and snubbers:
1. Provide pulsation dampener or snubber with each pressure gauge installed on
discharge of positive displacement type pump.
2. Provide piston-type snubber if pressure spikes will exceed 130 percent of
gauge maximum range.
3. Materials: Type 316 stainless steel.
4. Mount pulsation dampener or snubber integrally to the pressure gauge.
5. Connection: 1/2-inch NPT.
6. Provide sanitary seals as specified in the Contract Documents.
7. Provide means for gauge isolation as specified in the Contract Documents.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00.
B. Factory calibrate each pressure gauge at a facility that is traceable to the NIST.
C. Provide complete documentation covering the traceability of all calibration
instruments.
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
March 2021 - DRAFT 40_73_13-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_13(IDS50) Page 783
Item#18.
3.03 INSTALLATION
A. As specified in Section 40_61_00.
B. Coordinate the installation with all trades to ensure that the mechanical system has
all necessary appurtenances including weld-o-lets, valves, etc. for proper
installation of instruments.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
3.05 ADJUSTING
A. Verify factory calibration of all instruments in accordance with the manufacturer's
instructions:
1. Return factory calibrated devices to the factory if they do not meet the field
verification requirements for calibration.
3.06 CLEANING
A. As specified in Section 40_61_00.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications
or both.
END OF SECTION
March 2021 - DRAFT 40 73 13-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_73_13(IDS50) Page 784
Item#18.
A/E: Carollo Engineers PRESSURE
GAUGES
Spec. Rev.
No.
Contractor: No By Date Revision 40 73 13
Project: Side Stream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Req. P.O.
Location: Meridian, ID
BOM No.: By Chk App
File:
1 Type Direct Rd .:4 Receiver: Other:
2 Mounting Surface: Local: Flush:
3 Dial Diameter:4.5" Color:
4 Case Cast Iron: Aluminum: Phenolic: Polished Other:
SS
5 Ring Screwed: Hinged: Slip: Std: Other:
6 Blowout Protection None: Disc: Front: Other: Mfr. Std.
7 Lens Glass: Plastic:
8 Options Siphon: N/A Material:
9 Other Snubber:
10 Other Pressure Limit Valve: N/A
11 Other Movement Damping: N/A
12 Nominal Accuracy Required
13 Pressure Element Bourdon®: Bellows: Other:
14 Element Material Bronze: Steel: Type SS: 316 Other:
15 Socket Material Bronze: Steel: SS: 316 Other:
16 Connection '/4 in.: /2 in.: Bottom: Other:
17 Movement Dampened: Standard:4 Other:
18 Diaphragm Seal Mfr.: Wetted Part Mat'I: Type:
19 Other Other MatT Fill Fluid: Model:
20 Manufacturer
21 Model No.
Rev Tag Number Range P&ID Service Notes
SSPR1 P10301 N09 AIR FBV
SSPR1 P10302 N09 AIR FBV
SSPR1 P10401 N10 AIR FBV
SSPR1 P10402 N10 AIR FBV
Notes:
Refer to Section 40 73 64- Pressure/Vacuum Measurement: Instrument Valves for additional instrument valve
requirements.
March 2021 - DRAFT 40_73_13-5 1170
pwalCarollolDocumentslClientllDlMeridianl11700A101SpecificationslPre-Purchase140_73_13(IDS50) Page 785
Item#18.
SECTION 40_73_23
PRESSURE/VACUUM MEASUREMENT: DIRECT
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Pressure transmitters and indicators.
B. Provide all instruments identified in the Contract Documents.
C. Related sections:
1. Sections 01 33 00 - Submittal Procedures.
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
3. Section 40 73 64 - Pressure/Vacuum Measurement: Instrument Valves.
4. Section 40_80_01 - Commissioning for Instrumentation and Controls.
1.02 REFERENCES
A. As specified in Section 40_61_00.
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
B. Specific definitions:
1. Lower range value (LRV): Lowest pressure that the pressure transmitter is
capable of measuring.
2. Upper range value (URV): Highest pressure that the pressure transmitter is
capable of measuring.
3. Calibrated range: The range that the pressure transmitter is configured to
measure. The low end of the calibrated range must be greater than the LRV of
the transmitter. The high end of the calibrated range must be less than or
equal to the URV. The calibrated range corresponds to the flow signal sent
from the transmitter.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. Provide complete documentation covering the traceability of all calibration
instruments.
C. A template for the data sheet is included in the specification. System Supplier shall
complete data sheet based on system design.
March 2021 - DRAFT 40_73_23-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_23(IDS50) Page 787
Item#18.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
D. Provide instruments manufactured at facilities certified to the quality standards of
ISO 9001.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
1.07 PROJECT OR SITE CONDITIONS
A. As specified in Section 40_61_00.
B. Project environmental conditions as specified in Section 40 61_00:
1. Provide instruments suitable for the installed site conditions including, but not
limited to, material compatibility, site altitude, site seismic conditions, humidity,
and process and ambient temperatures.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. Furnish all parts, materials, fluids, etc. necessary for operation, maintenance, and
calibration purposes throughout the warranty period. Deliver all of these supplies
before project substantial completion.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following:
1. Endress & Hauser, Cerabar S Series.
2. Emerson, Rosemount 3051 S Series.
March 2021 - DRAFT 40 73 23-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_73_23(IDS50) Page 788
Item#18.
2.02 MANUFACTURED UNITS
A. Pressure transmitters - direct:
1. General:
a. Pressure transmitter assembly shall include a diaphragm type pressure
transducer and microprocessor based transmitter for measurement of
gauge, vacuum, or absolute pressure.
2. Performance requirements:
a. Maximum ratio of total instrument range to calibrated span: 10 to 1.
b. Accuracy:
1) Reference accuracy: Plus or minus 0.075 percent of calibrated span,
including effects of hysteresis, nonlinearity, and repeatability.
2) Total performance accuracy: Plus or minus 0.30 percent of calibrated
span, including reference accuracy effects, static pressure and
ambient temperature effects.
3) Stability: Plus or minus 0.15 percent of upper range limit over
5 years.
3. Element:
a. Diaphragm type transducer integral to pressure transmitter.
b. Diaphragm material: Stainless steel or ceramic.
c. Process material compatibility:
1) Verify all material compatibilities with the instrument manufacturer.
d. Process connection: As specified in the Instrument Data Sheets.
4. Transmitter:
a. Power supply:
1) 24 VDC - 2 wire loop powered.
2) Power consumption: 3 VA maximum.
b. Outputs:
1) Isolated 4-20mA DC with HART communication protocol.
c. Provided with electronic microprocessor.
d. Adjustments: Adjustable electronic zero and span, with elevated or
suppressed zero as required by application. Adjustment shall be possible
without mechanical fulcrum points or handheld configurator.
e. Local display:
1) 5-digit LCD.
2) Scaled in engineering units.
f. Remote or Integral as specified in data sheet. Remote mount transmitters
only as shown on the plan drawings to provide maintenance staff access.
g. Enclosure:
1) NEMA Type 4X or NEMA 7 based on the defined classified space.
h. Over range protection: To maximum process line pressure.
i. Conduit: 1/2-inch male NPT.
5. Components:
a. Transmitter mounting:
1) As specified in the Instrument Data Sheets.
2) Provide all necessary hardware for transmitter mounting.
March 2021 - DRAFT 40_73_23-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_23(IDS50) Page 789
Item#18.
2.03 ACCESSORIES
A. Provide valve manifolds as specified in Section 40 73_64:
1. Mount valve manifold integrally to the transmitter.
2. Valve manifold and transmitter shall be assembled by Manufacturer and
shipped as an assembly.
3. Provide remote or integral diaphragm seals as shown in the Typical Details.
B. Provide sunshades for outdoor installations if in direct sunlight.
C. Provide stainless steel tags for each instrument. Tags shall be labeled as specified
in the Contract Documents.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00.
B. Factory calibrate each instrument with a minimum 3-point calibration or according to
Manufacturer's standard at a facility that is traceable to the NIST:
1. Submit calibration data sheets to the Engineer at least 30 days before
shipment of the instruments to the project site.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine the installation location for the instrument and verify that the instrument will
work properly when installed:
1. Notify the Engineer promptly if any installation condition does not meet the
instrument manufacturer's recommendations or specifications.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00.
B. Coordinate the installation with all trades to ensure that the mechanical system has
all necessary appurtenances including weld-o-lets, valves, etc. for proper
installation of instruments.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
3.05 ADJUSTING
A. As specified in Section 40_80_01.
3.06 CLEANING
A. As specified in Section 40_61_00.
March 2021 - DRAFT 40 73 23-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_73_23(IDS50) Page 790
Item#18.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications,
or both.
END OF SECTION
March 2021 - DRAFT 40_73_23-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_23(IDS50) Page 791
Item#18.
A/E: Carollo Engineers PRESSURE
TRANSMITTERS
Spec. No. Rev.
Contractor: No By Date I Revision 40_73_23
Project: Side Stream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Req. P.O.
Location: Meridian, ID
BOM No.: By Chk App
File:
1 Instrument Tag No. SSPR1 LIT0104 SSPR1 LIT0204
GENERAL 2 Service Water Water
3 P&ID N07 N08
4 Pressure
SERVICE 5 Process Temperature 35-70 deg F 35-70 deg F
6 1 Ambient Temperature
7 Manufacture
8 Model No.
9 Pressure Transmitter Type Remote Mount Remote Mount
TRANSMITTER 10 Calibrated Span
11 Accuracy
12 Adjustable Range
13 Output Signal 4-20 mA 4-20 mA
14 Body Rating
15 Process Flange Type Threaded Threaded
16 Drain/Vent None None
17 Process Flange MNPT MNPT
18 Adapters
BODY 19 Wetted O-Ring
20 Housing
21 Bolts
22 Mounting Brackets
23 Conduit Entry Size
ELEMENT 24 Isolating Diaphragm Flanged Flanged
25 Fill Fluid Silicone Silicone
26 Certification/Approval
Type
27 Meter
OPTIONS 28 Zero Span &Adjustment
29 Surge Protection
30 1 Custom Configuration
31 Manufacturer
MANIFOLD 32 Model Number
33 Manifold Style Reference Details
34 Manifold Type Block and Bleed
Notes:
Provide tank level measurement instrument including direct mount flanged diaphragm seal with pressure element,
remote mount transmitter, interconnecting cable between diaphragm seal assembly and transmitter.
March 2021 - DRAFT 40 73 23-6 1170OA10
pwalCarollolDocumentslClientllDlMeridianl11700A101SpecificationslPre-Purchase140_73_23(IDS50) Page 792
Item#18.
SECTION 40_73_64
PRESSURE/VACUUM MEASUREMENT: INSTRUMENT VALVES
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Valve manifolds and instrument valves.
B. Provide all valves identified in the Contract Documents.
C. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
3. Section 40_80_01 - Commissioning for Instrumentation and Controls.
1.02 REFERENCES
A. As specified in Section 40_61_00.
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. Additional requirements:
1. Product data:
a. Valve type.
b. Body material.
c. Size.
d. Options.
2. Shop drawings:
a. Mounting details for all manifold valves.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the valves are
compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials, etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
March 2021 - DRAFT 40_73_64-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_64(IDS50) Page 793
Item#18.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
C. Notify the Engineer if any installation condition does not meet the valve
manufacturer's recommendations or specifications.
D. Provide valves manufactured at facilities certified to the quality standards of
ISO 9001.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
B. Protect valve manifolds and protective coatings from damage during handling and
installation. Repair coating where damaged.
1.07 PROJECT OR SITE CONDITIONS
A. Project environmental conditions as specified in Section 40_61_00:
1. Provide valves suitable for the installed site conditions including, but not
limited to, material compatibility, process, and ambient temperatures.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. As specified in Section 40_61_00.
B. Furnish all parts, materials, fluids, etc. necessary for operation, maintenance, and
calibration purposes throughout the warranty period. Deliver all of these supplies
before project substantial completion.
PART PRODUCTS
2.01 MANUFACTURERS
A. Valve manifold:
1. One of the following or equal:
a. Anderson Greenwood.
b. Hex Valve.
c. Noshok.
d. Emerson, Rosemount.
e. Endress & Hauser
B. Block and bleed valve:
1. One of the following or equal:
a. Anderson Greenwood.
b. Hex Valve.
March 2021 - DRAFT 40 73 64-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_73_64(IDS50) Page 794
Item#18.
C. Gauge valve:
1. One of the following or equal:
a. Anderson Greenwood.
b. Hex Valve.
D. Level sensor isolation valve:
1. One of the following or equal:
a. Indu-Tech, Level Sensor Isolation Valve.
b. DeZURIK, Level Sensor Isolation Valve.
c. Tyco, Rovalve Isolation Knife Gate Valve.
2.02 MANUFACTURED UNITS
A. Valve manifolds:
1. General:
a. Provide 2-valve, 3-valve, blowdown type 5-valve, or metering type 5-valve
manifolds as indicated on the Drawings.
b. Valve manifolds shall have one piece bonnet with a metal to metal seal to
the valve body below the bonnet threads.
2. Requirements:
a. Bonnet lock pin to prevent accidental loosening.
b. Gas leak tested metal-to-metal hard seat design for hard seat valves.
c. Gas leak tested soft seat design with replaceable seat for soft seat valves.
d. Manifold valves shall have straight through portion for bi-directional flow
and easy roddable cleaning.
e. Manifold valves shall allow for direct or remote instrument mounting.
f. Shall be able to withstand pressures up to 6,000 psi for soft seat valves
and 10,000 psi for hard seat valves at maximum 200 degrees Fahrenheit.
g. Materials of construction:
1) Body material: Type 316 stainless steel.
2) O-Ring: Teflon.
h. 2-Valve manifolds:
1) 1 isolation valve and 1 drain/vent and calibration valve.
i. 3-Valve manifolds:
1) 2 isolation valves and 1 equalizing valve for differential pressure
applications.
2) Plugged vent connections used for vent/drain or calibration.
j. Blowdown 5-valve manifold:
1) 2 isolation valves, 1 equalizing valve, 2 blowdown valves for
differential pressure applications.
k. Metering 5-valve manifold:
1) 2 isolation valves, 2 equalizing valves, 1 vent/drain and calibration
valve for differential pressure applications.
B. Block and bleed valves:
1. General:
a. Valve shall provide process isolation and venting/draining capabilities.
b. Gas leak tested metal-to-metal hard seat design for hard seat valves.
c. Gas leak tested soft seat design with replaceable seat for soft seat valves.
d. Valve shall not be used with fluids with high solids content, such as raw
wastewater or sludge.
March 2021 - DRAFT 40_73_64-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_64(IDS50) Page 795
Item#18.
2. Requirements:
a. Materials of construction:
1) Body material: Type 316 stainless steel.
2) O-Ring: Teflon.
C. Gauge valves:
1. General:
a. Valve shall provide process isolation from pressure instrument.
b. Gas leak tested, metal-to-metal hard seat design for hard seat valves.
c. Gas leak tested soft seat design with replaceable seat for soft seat valves.
2. Requirements:
a. Materials of construction:
1) Body material: Type 316 stainless steel.
2) O-Ring: Teflon.
D. Level sensor isolation valves:
1. General:
a. Valve shall provide process isolation from level diaphragm.
b. Gas leak tested, metal-to-metal hard seat design for hard seat valves.
c. Gas leak tested soft seat design with replaceable seat for soft seat valves.
2. Requirements:
a. Materials of construction:
1) Body material: Type 316 stainless steel.
2) Flange diameter size: 3 inches.
2.03 ACCESSORIES
A. Provide tube fitting, female NPT, or pipe butt weld connections if necessary.
B. Provide stainless steel concentric or eccentric pipe nipples when necessary.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine the installation location and verify it will work properly when installed.
1. Notify the Engineer promptly if any installation condition does not meet the
manufacturer's recommendations or specifications.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00.
B. Coordinate the installation with all trades to ensure that the mechanical system has
all necessary appurtenances including weld-o-lets, valves, etc. for proper installation
of all valves.
March 2021 - DRAFT 40 73 64-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_73_64(IDS50) Page 796
Item#18.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
3.05 ADJUSTING
A. As specified in Section 40_80_01.
3.06 CLEANING
A. As specified in Section 40_61_00.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
B. Demonstrate performance of all valves to the Engineer before commissioning.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES (NOT USED)
END OF SECTION
March 2021 - DRAFT 4 73 64-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_73_64(IDS50) Page 797
Item#18.
SECTION 40_74_66
TEMPERATURE MEASUREMENT: TEMPERATURE SWITCH
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Temperature switch instruments.
B. Provide all instruments identified in the Contract Documents.
C. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
3. Section 40_80_01 - Commissioning for Instrumentation and Controls.
1.02 REFERENCES
A. As specified in Section 40_61_00.
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. Provide complete documentation covering the traceability of all calibration
instruments.
C. A template for the data sheet is included in the specification. System Supplier shall
complete data sheet based on system design.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials, etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
March 2021 - DRAFT 40 74 66-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_74_66(IDS50) Page 799
Item#18.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
D. Provide instruments manufactured at facilities certified to the quality standards of
ISO 9001.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
1.07 PROJECT OR SITE CONDITIONS
A. Project environmental conditions as specified in Section 40 61_00:
1. Provide instruments suitable for the installed site conditions including, but not
limited to, material compatibility, site altitude, site seismic conditions, humidity,
and process and ambient temperatures.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. Furnish all parts, materials, fluids, etc. necessary for operation, maintenance, and
calibration purposes throughout the warranty period. Deliver all of these supplies
before project substantial completion.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. Ashcroft, B Series.
2.02 MANUFACTURED UNITS
A. Temperature switches:
1. General:
a. Temperature switch shall be bulb type with snap-action switch element.
2. Performance requirements:
a. Temperature range: As indicated in the data sheets or the P&IDs.
b. Accuracy:
1) Within 2.0 percent of range.
c. Repeatability:
1) Within 2.0 percent of range.
3. Element:
a. Sensing element material: Stainless steel.
b. Sensing element shall not require ambient temperature compensation.
c. Switch elements:
1) Snap acting.
March 2021 - DRAFT 40 74 66-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_74_66(IDS50) Page 800
Item#18.
4. Transmitter:
a. Setpoint:
1) Dual.
2) Activate switch at setpoint on increasing temperature for high
temperature alarm applications and on decreasing temperature for
low temperature alarm applications.
b. Fixed deadband.
c. Manual reset type.
d. Enclosure: Epoxy coated NEMA Type 4X.
e. Switch mounting:
1) Local mount directly to process.
2) Process connection: 1/2-inch NPT.
3) Provide all necessary hardware for temperature switch mounting.
f. Outputs:
1) Relay outputs:
a) Form C contact: 1.
b) Rated at 10A, 125/250VAC.
2.03 ACCESSORIES
A. Thermowell:
1. Unless otherwise noted, provide thermowell with each temperature switch.
2. Process connection: As indicated in the Data sheets.
3. Thermowell material: As Indicated in the Datasheets.
4. Stem style: As indicated in the Data sheets.
5. Immersion depth:
a. Minimum 3 inches or 10 times the diameter of thermowell, whichever is
larger.
b. Where pipe diameter is inadequate for appropriate immersion depth,
install thermowell in an elbow on the axis of the pipe.
B. Provide sunshades for outdoor installations.
2.04 SOURCE-QUALITY-CONTROL
A. As specified in Section 40_61_00.
B. Factory calibrate each instrument with a minimum 3-point calibration or according to
Manufacturer's standard at a facility that is traceable to the NIST:
1. Submit calibration data sheets to the Engineer at least 30 days before
shipment of the instruments to the project site.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine the installation location for the instrument and verify that the instrument will
work properly when installed.
1. Notify the Engineer promptly if any installation condition does not meet the
instrument manufacturer's recommendations or specifications.
3.02 PREPARATION (NOT USED)
March 2021 - DRAFT 40 74 66-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_74_66(IDS50) Page 801
Item#18.
3.03 INSTALLATION
A. As specified in Section 40_61_00.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
3.05 ADJUSTING
A. As specified in Section 40_80_01.
3.06 CLEANING
A. As specified in Section 40_61_00.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications
or both.
END OF SECTION
March 2021 - DRAFT 40 74 66-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_74_66(IDS50) Page 802
Item#18.
A/E: Carollo Engineers TEMPERATURE
SWITCHES
Spec.No. Rev.
Contractor: No By Date Revision 40 74 66
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Reg. P.O.
Location: Meridian,ID
BOM No.: B Chk A
File:
1 Type
D 2 Setting Set in Field:Facto Set:X Internal:External:Dial:
E 3 Dead Band Fixed:X Ad'.:Min.:Other:
V 4 Wetted Material
I 5 Connection MFR STD:X Bottom:Back:
C 6 Mounting Local:X Surface:Flush:Thermowell: Remote:
E 7 Thermowell Type Straight:Tapered: Stepped:
8 Thermowell Material Stainless Steel:X Other:
9 Thermowell Insertion Length
10 Process Connection 1/2-inch Thread:X 3/4-inch Thread:Flange:Weld Mount:
11 Other
12 Ty e Mercury: Snap:X Other:
13 Quantity Single:X Dual:Other:
S 14 Form SPST: SPDT:X DPDT:Other
W 15 Rating: Amps I Volts Hertz 10 120 60
1 16 Other
T 17 Load Inductive:Non-Inductive:
C 18 Enclosure General Purpose:Weatherproof.X None:Explosion roof:
H 19 Enclosure Class NEMA 4X
20 Conduit Connection MFR STD:Other
21 Accuracy
22 Other
23 Manufacturer
24 Model No.
Rev Tag Number Adj.Range SP Process Signal SP IOp. P&ID Service Notes
SSPRITSH0304 N09 Blower FBV
Discharge
SSPRITSH0404 N10 Blower
Discharge
Notes:To be provided with blower package.
t
March 2021 - DRAFT 40 74 66-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_74_66(IDS50) Page 803
Item#18.
SECTION 40_75_13
ANALYZERS: PH
PART1 GENERAL
1.01 SUMMARY
A. Section includes:
1. pH instruments.
B. Provide all instruments identified in the Contract Documents.
C. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
3. Section 40_80_01 - Commissioning for Instrumentation and Controls.
1.02 REFERENCES
A. As specified in Section 40_61_00.
B. CSA International (CSA).
1.03 DEFINITIONS
A. As specified in Section 40_61_00.
1.04 SUBMITTALS
A. Furnish submittals as specified in Sections 01_33_00 and 40_61_00.
B. Provide complete documentation covering the traceability of all calibration
instruments.
C. A template for the data sheet is included in the specification. System Supplier shall
complete data sheet based on system design.
1.05 QUALITY ASSURANCE
A. As specified in Section 40_61_00.
B. Examine the complete set of Contract Documents and verify that the instruments
are compatible with the installed conditions including:
1. Process conditions: Fluids, pressures, temperatures, flows, materials, etc.
2. Physical conditions:
a. Installation and mounting requirements.
b. Location within the process.
c. Accessories: Verify that all required accessories are provided and are
compatible with the process conditions and physical installation.
March 2021 - DRAFT 40_75_13-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_75_13(IDS50) Page 805
Item#18.
C. Notify the Engineer if any installation condition does not meet the instrument
manufacturer's recommendations or specifications.
D. Provide instruments manufactured at facilities certified to the quality standards of
ISO 9001.
1.06 DELIVERY, STORAGE, AND HANDLING
A. As specified in Section 40_61_00.
1.07 PROJECT OR SITE CONDITIONS
A. Project environmental conditions as specified in Section 40 61_00.
1. Provide instruments suitable for the installed site conditions including, but not
limited to, material compatibility, site altitude, site seismic conditions, humidity,
and process and ambient temperatures.
1.08 WARRANTY
A. As specified in Section 40_61_00.
1.09 MAINTENANCE
A. Furnish all parts, materials, fluids, etc. necessary for operation, maintenance, and
calibration purposes throughout the warranty period. Deliver all of these supplies
before project substantial completion.
PART PRODUCTS
2.01 MANUFACTURERS
A. One of the following or equal:
1. HACH:
a. Sensor model DPD1 P1.
b. Transmitter model SC200.
2.02 MANUFACTURED UNITS
A. pH analyzers:
1. General:
a. pH measurement shall use the potentiometric measurement method
utilizing a glass electrode. The pH sensitive glass membrane surface
reacts to the acid content of the solution with a specific voltage, which is
measured relative to a reference electrode.
2. Performance requirements:
a. Accuracy: Within 0.01 pH.
b. Stability: Within 0.01 pH/month.
c. Repeatability: Within 0.01 pH.
3. Element:
a. Sensor material:
1) Glass pH sensor housed in a molded reinforced polypropylene body
threaded as recommended by manufacturer.
March 2021 - DRAFT 40 75 13-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_75_13(IDS50) Page 806
Item#18.
2) Built in temperature sensor.
3) The reference electrode junction shall be capable of maintaining
steady reference signal by resisting plugging in dirty applications.
b. pH measuring range: 2 to 12 pH.
c. Temperature measuring range: 0 to 70 degrees Celsius.
d. Operating temperature range: 0 to 80 degrees Celsius.
e. Operating pressure range: 0 to 87 pounds per square inch.
4. Transmitter:
a. Power supply:
1) 120 VAC.
2) Power consumption: 73 VA maximum.
b. Outputs:
1) Two isolated 4 to 20 milliamperes DC with HART communication
protocol.
a) Proportional to pH and temperature.
c. Display:
1) Backlit LCD digital display.
d. Measurement ranges: 0 to 14 pH.
e. Temperature: 0 to 50 degrees Celsius.
f. Displayed resolution: Within 0.01 pH.
g. Ambient conditions:
1) Operable from 0 to 50 degrees Celsius.
2) Relative humidity 0 to 95 percent.
h. Mechanical:
1) Enclosure rating:
a) NEMA Type 4X (IP65).
2) Mounting:
a) Panel mount suitable for mounting in an enclosure that includes
gasket to maintain weather rating of the panel.
b) Surface mount enclosures, include self-tapping screws.
c) Pipe mounting accessories shall be included for mounting
enclosures to a 2-inch pipe.
3) Provide all mounting hardware for proper installation and servicing of
the sensor assembly.
i. Electrical certification: NRTL certified to UL and CSA standards, and CE
approved.
5. Components:
a. Sensor cable:
1) Shall be provided with watertight sensor-to-cable connector that
prevents cable twisting and eliminates rewiring when replacing the
sensor.
2) Cable length: As required to connect sensor to transmitter plus
10 percent.
2.03 ACCESSORIES
A. Sensor:
1. Process assemblies:
a. Provide threaded DN flange.
b. Provide 1-inch FNPT CVPC Pipe for probe connection.
c. Coordinate detailed connection with between tank and instrument
manufacturer.
March 2021 - DRAFT 40_75_13-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_75_13(IDS50) Page 807
Item#18.
B. Transmitter:
1. DAT module.
2. Flat gasket.
3. Stainless steel tag:
a. Marking specified on Instrument Data Sheets.
C. Preamplifier:
1. Use Manufacturer recommended preamplifier on coaxial cable runs longer
than 15 feet. Review the contractor drawings and verify the need for a
preamplifier.
D. NEMA 4X enclosure with viewing window as defined on the Drawings.
2.04 SOURCE QUALITY CONTROL
A. As specified in Section 40_61_00.
B. Factory calibrate each instrument with a minimum 3-point calibration or according to
Manufacturer's standard at a facility that is traceable to the NIST:
1. Submit calibration data sheets to the Engineer at least 30 days before
shipment of the instruments to the project site.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine the installation location for the instrument and verify that the instrument will
work properly when installed.
1. Notify the Engineer promptly if any installation condition does not meet the
instrument manufacturer's recommendations or specifications.
3.02 PREPARATION (NOT USED)
3.03 INSTALLATION
A. As specified in Section 40_61_00.
3.04 FIELD QUALITY CONTROL
A. As specified in Section 40_61_00.
B. Provide manufacturer's services to perform installation inspection, start-up and
calibration/verification.
3.05 ADJUSTING
A. As specified in Section 40_80_01.
3.06 CLEANING
A. As specified in Section 40_61_00.
March 2021 - DRAFT 40 75 13-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_75_13(IDS50) Page 808
Item#18.
3.07 DEMONSTRATION AND TRAINING
A. As specified in Section 40_61_00.
3.08 PROTECTION
A. As specified in Section 40_61_00.
3.09 SCHEDULES
A. The provided information does not necessarily include all required instruments.
Provide all instruments identified in the Contract Documents:
1. Instruments may be indicated on the Drawings, specified in the Specifications
or both.
END OF SECTION
March 2021 - DRAFT 40_75_13-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_75_13(IDS50) Page 809
Item#18.
A/E: pH
ANALYZERS
Spec.No. Rev.
Contractor: No By Date Revision 40 75 13
Project: Sidestream Treatment Project Contract Date
Customer: City of Meridian
Plant: WRRF Re P.O.
Location: Meridian,ID
BOM No.: By Chk App
File:
G 1 Ta No. I Element Transmitter SSPRIAIT0102/0202
E 2 Service One per Reactor Tank
N 3 P&ID N05/N06
4 Type
5 Body Style
6 Enclosure
E 7 Electrodes
L 8 Ambient Conditions
E 9 Connection
M 10 Sample Flow Required
E 11 pH easuring Range
N 12 Temperature Measuring Range
T 13 Manufacturer HACH
14 Model No. DPD1P1
15 Length
16 1 Other Built in Temperature Sensor
C 17 Style
A 18 Length
B 19 Model No.
L 20 Pre-Amplifier
E 21 Other
22 Type Control Unit and Display
T 23 Enclosure
R 24 Mounting
A 25
N 26 Power Requirements 115 VAC,60 Hz
S 27 Resolution
M 28 Accuracy
1 29 Calibrated Range
T 30
T 31 Outputs 4-20 mA HART
E 32 Contacts
R 33 Manufacturer HACH
34 Model No. SC200
35 Display
36 Other
37 Other
38 Other
O 38 Cleaning
P 39 Low Flow Cell
T 38 Process Assembly
S 38 Other
39
Notes:
March 2021 - DRAFT 40 75 13-6 1170OA10
pwalCarollolDocumentslClientllDlMeridian/11700A10/Specifications/Pre-Purchase/40_75_13(IDS50) Page 810
Item#18.
SECTION 40_80_01
COMMISSIONING FOR INSTRUMENTATION AND CONTROLS
PART GENERAL
1.01 SUMMARY
A. Section includes:
1. Testing requirements that apply to process control and instrumentation
systems for the entire Project.
B. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 01 75 17 - Commissioning.
3. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
1.02 REFERENCES
A. As specified in Section 40_61_00.
B. Electronics Industries Alliance (EIA).
C. Telecommunications Industry Association (TIA).
1.03 DEFINITIONS
A. As specified in Sections 01_75_17 and 40_61_00.
B. Specific definitions:
1. Complete End-to-End Testing (CEET) - Signals are tested from the field
device through the PLC program, the network, and all the way to the
operator's HMI graphic screens.
2. Loop Validation Tests - Signals are tested from the field device to the PLC.
3. Platform Testing: Testing of the PLC and SCADA/HMI at the manufacturer's
shop to demonstrate the program's functionality based upon specified and
designed control requirements.
1.04 SYSTEM DESCRIPTION (NOT USED)
1.05 SUBMITTALS
A. Furnish submittals as specified in Section 01_33_00.
B. General:
1. Reference additional detailed test submittal scheduling and prerequisite
requirements as specified in the Sequencing article of Section 40_61_00.
March 2021 - DRAFT 40_80_01-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 811
Item#18.
C. Overall test plan:
1. Develop the PCIS system test submittals in consultation and cooperation with
all applicable subcontractors.
2. Develop and submit an overall testing plan for the PCIS. The overall test plan
to be reviewed and approved by the Engineer before detailed test plans,
procedures, and forms will be reviewed.
3. Describe the test phases as they apply specifically to this Project and each
process system.
4. Provide a preliminary testing schedule to show the sequence of tests and
commissioning as they apply to each process system and each PLC.
5. Provide a description of factory tests. Describe what equipment will be
included, what testing equipment will be used, and the simulator that will be
used.
6. Provide examples of proposed forms and checklists.
D. Test procedures:
1. Develop and submit detailed test procedures to show that the integrated
SCADA system hardware and software is fully operational and to the
satisfaction of the Owner.
2. Provide a statement of test objectives for each test.
3. Prepare specific procedures for each process system.
4. Describe sequentially the steps to be followed in verifying the correct operation
of each process system, including all features described in the loop
descriptions, control strategies, and shown in the P&IDs. Implied or generic
test procedures are not acceptable.
5. Specify who will perform the tests, specifically what testing equipment will be
used (including serial numbers and NIST-traceable calibration), and how the
testing equipment will be used.
6. Describe the expected role of the Engineer, as well as any requirements for
assistance from Owner's staff.
7. Provide the forms and checklists to be used.
E. Test forms:
1. Submit completed calibration forms, test forms, and checklists.
a. Test forms shall include the detailed test procedures, or shall include clear
references to separate pages containing the complete test procedure
applicable to each form. If references to procedures are used, the
complete procedure shall be included with each test binder.
b. Every page of each test form shall include project name, date, time, name
of person conducting the test, signature of person conducting the test,
and for witnessed tests, place for signature of person (Engineer and
Owner) witnessing the test.
c. Sample test forms at the end of this Section show the minimum required
content:
1) The sample test forms have not been customized for this Project.
2) Contractor shall develop and submit test forms customized for the
Project and meeting the specified test and submittal requirements.
F. FAT procedure additional minimal requirements:
1. Prepare and submit a FAT procedure which includes:
a. Control system testing block diagram.
b. Estimated test duration.
March 2021 - DRAFT 40 80 01-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 812
Item#18.
G. Details on the simulator construction, components, and operation. Testing binders:
1. Sub-system to be tested, provide and submit a test binder containing all test
procedures and individual test forms for the test. References to other
documents for test procedures and requirements are not acceptable.
2. Fill out in advance headings and all other information known before the test.
3. Include applicable test plan information, as well as a list of all test
prerequisites, test personnel, and equipment.
4. Include or list reference material and provide separately at the time of the test.
5. Record test results and verify that all test requirements and conditions have
been met.
H. Test reports:
1. At the conclusion of each test, submit a complete test report, including all test
results and certifications.
2. Include all completed test binders, forms, and checklists.
3. Submission, review, and acceptance of each test report is required before the
start of the sub-system.
1.06 QUALITY ASSURANCE
A. Test personnel:
1. Furnish qualified technical personnel to perform all calibration, testing, and
verification. The test personnel are required to be familiar with this Project and
the equipment, software, and systems before being assigned to the test
program.
1.07 DELIVERY, STORAGE, AND HANDLING (NOT USED)
1.08 PROJECT OR SITE CONDITIONS (NOT USED)
1.09 SEQUENCING (NOT USED)
1.10 SCHEDULING
A. As specified in Section 40_61_00.
1.11 WARRANTY (NOT USED)
1.12 SYSTEM START-UP (NOT USED)
1.13 OWNER'S INSTRUCTIONS (NOT USED)
1.14 MAINTENANCE (NOT USED)
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.01 EXAMINATION (NOT USED)
3.02 PREPARATION (NOT USED)
March 2021 - DRAFT 40_80_01-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 813
Item#18.
3.03 INSTALLATION
A. As specified in Section 40_61_00.
B. Installation supervision:
1. Provide as specified in Section 40_61_00.
3.04 ERECTION, INSTALLATION, APPLICATION, CONSTRUCTION (NOT USED)
3.05 REPAIR/RESTORATION (NOT USED)
3.06 RE-INSTALLATION (NOT USED)
3.07 COMMISSIONING
A. Commissioning as specified in Section 01_75_17.
B. Testing and training phase:
1. Source testing:
a. Manufacturer services: Provide as specified in the table below.
Source Testing
(Witnessed or
Section Number Section Title Non-Witnessed)
40_67_01 Control Systems - Panels, Enclosures, Witnessed
and Panel Components
40_80_01 Commissioning for Instrumentation and Witnessed
Controls
b. Prerequisite requirements:
1) Engineer approval of the hardware and equipment source testing
submittal, Manufacturer Certificate of Source Testing, is required
before proceeding to Preliminary FAT.
c. Preliminary FAT (Pre-FAT):
1) The purpose of the Pre-FAT is to provide assurance that the
HMI/SCADA system is ready for the full, witnessed FAT, in terms of
both stability and functionality:
a) Debugging of software and troubleshooting of hardware shall
occur during and before the pre-FAT, not during the FAT.
b) Contractor shall fully test the HMI/SCADA system and fix all
deficiencies found before the FAT.
2) Conduct utilizing test procedures approved by Engineer.
3) Owner shall have the right to witness any or all of the Pre-FAT
testing and shall be notified in writing 20 days before the start of the
pre-FAT.
4) Submit a letter, signed by the Contractor's project manager or
company officer, certifying that integrated system hardware and
software has been tested and confirmed to be fully operational and in
compliance with the requirements specified in the Contract
Documents and is fully ready for the full, witnessed FAT:
a) Attach the completed pre-FAT test forms, signed by the
Contractor's staff.
March 2021 - DRAFT 40 80 01-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 814
Item#18.
5) Engineer approval of the pre-FAT submittal is required before
proceeding to FAT.
d. FAT hardware and communications testing:
1) Perform tests to show that the integrated system hardware and
software is fully operational and in compliance with the requirements
specified in the Contract Documents.
2) The complete PCIS system including operator stations, servers,
network equipment, printers, PCMs, PLCs, RTUs, LCPs, CCS,
peripherals, communications equipment, and other HMI/SCADA
equipment, shall be assembled, connected, and software loaded for
a fully functional FAT of the integrated system.
3) Testing simulation:
a) Inputs and outputs shall be simulated and proper control and
system operation shall be validated.
b) FAT shall make use of simulators that contain switches, pilot
lights, variable analog signal generators, and analog signal level
displays, which shall be connected to the 1/0 points within the
HMI/SCADA system:
(1) The use of jumper wires, terminal block mounted pilot
lights, and loose meters to act as or supply the functionality
of a simulator shall not be allowed.
(2) The simulator may consist of a PLC, operating under a
HMI/SCADA software package, or other approved software
that has its 1/0 points wired to PLC's 1/0 points.
(3) Software operating on a PC may then act as the switches,
pilot lights, variable analog signal generators, and analog
signal level displays.
4) Additional source tests are specified in other sections of the
Instrumentation and Control Specifications.
5) Owner shall have the right to witness any or all of the FAT testing
and shall be notified in writing 20 days before the start of the FAT.
6) Verify communications between the hardware and the programmer's
software comply with specified requirements:
a) For systems that contain RTUs or remote communications with
other devices, the complete communications system must be
factory tested, including actual interfacing with telephone
company equipment and/or the actual radios used for radio
based telemetry systems.
7) Panel inspections:
a) Engineer will inspect each control panel for completeness,
workmanship, fit and finish, and compliance with the Contract
Documents and the accepted shop drawings:
(1) Inspection to include, as a minimum: Layout, mounting,
wire and data cable routing, wire tags, power supply,
components and wiring, 1/0 components layout (including
terminals, wiring and relays), device layout on doors and
front panels, and proper ventilation operation.
b) Inspection forms:
(1) Provide panel inspection forms as part of the FAT
procedures submittal.
(2) A sample FAT control panel form has been provided at the
end of this Section.
March 2021 - DRAFT 40_80_01-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 815
Item#18.
8) 1/0 test:
a) Engineer will verify that 1/0 is properly wired to field terminals
and is properly mapped into the PLC and the rest of the SCADA
system, including all operator interface devices.
b) Test methodology:
(1) Discrete inputs:
(a) Apply appropriate input from simulator at panel
terminal, observe input card indicator, observe data
value at each indicated data address, and observe
data received at field wiring terminals or operator
interface screen.
(2) Discrete outputs:
(a) Issue commands from operator interface screen or
PLC, verify output card indicator light, and measure
response at field wiring terminals or multimeter.
(3) Analog inputs:
(a) Apply appropriate analog input signal at panel
terminals on simulator, observe data value at each
indicated data address, and observe data properly
received at field wiring terminals or operator interface
screen.
(b) Check each point at 0 percent, 50 percent, and 100
percent of scale.
(4) Analog outputs:
(a) Enter scaled values in the output buffer file, observe
the output data file value, and measure appropriate
response at field wiring terminals or multimeter.
c) Test forms to include, but not be limited to the following data:
(1) PLC and panel number.
(2) 1/0 type.
(3) 1/0 tag name.
(4) Rack/slot/number of 1/0 point.
(5) Check-off for correct response for each 1/0 point.
(6) Comments field.
(7) Initials of individual performing test.
(8) Date test was performed.
(9) Witness signature lines.
9) System configuration test:
a) Demonstrate and test the setup and configuration of operator
stations, servers, development stations, and peripherals.
b) Demonstrate utility software and functions, such as virus
protection, backup, optical drive burning, network monitoring,
etc.
c) Demonstrate the proper operation of peripheral hardware.
d) Demonstrate general HMI/SCADA functions.
e) Demonstrate proper operation of log-on and other security
access functions.
f) Demonstrate the proper operation of all historical data storage,
trend, display, backup, and report functions.
g) Test automatic fail over of redundant equipment.
h) Demonstrate the proper operation of the alarm display and
acknowledgement functions.
March 2021 - DRAFT 40 80 01-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 816
Item#18.
i) Test forms:
(1) For each test, list the specification page and paragraph of
the function demonstrated, and provide a description of the
function.
(2) List the specific tests and steps to be conducted.
(3) For each function, list all of the different sub-functions or
ways the function can be used, and provide a test check-off
for each:
(a) Include signature and date lines.
10) Engineer approval of the FAT Communication Testing activities is
required before proceeding to FAT Platform Testing.
e. FAT Platform Testing - Control logic test:
1) Verify the PLC, HMI, and SCADA, provides monitoring and control
functionality based upon specified and designed control
requirements.
2) Testing requirements:
a) Demonstrate each function described in the Control Strategies.
b) Demonstrate in detail how each function operates under a
variety of operating scenarios:
(1) Test to verify the application of each general control
strategy function to each specific control strategy or loop
description.
c) Demonstrate the proper operation of the programming and
configuration for each control strategy or loop description.
(1) Test each strategy or loop description on a sentence-by-
sentence and function-by-function basis.
(2) Loops with similar or identical logic must each be tested
individually.
(3) Test the boundaries of each numeric operator input by
entering values outside of the allowable range.
d) Demonstrate the proper operation of all digital communication
links and networks.
(1) Verify each digital communication 1/0 point.
e) Failure testing: Demonstrate how the system responds to and
recovers from abnormal conditions including, but not limited to:
equipment failure, operator error, communications subsystem
error, communications failures, simulated/forced software
lockups, power failure (both utility power and power to HMI
and/or SCADA hardware), process equipment failure, and high
system loading conditions.
3) Test forms:
a) Submit completed test forms for each loop including but not
limited to the fully revised and approved control strategy.
b) Identify the cause and effect as each 1/0 point is toggled through
the simulator:
(1) Identify and track proper and/or improper operation of the
loop.
c) Note any deficiencies or operational changes on the forms for
correction and documentation:
(1) Include signature and date lines.
4) Engineer approval of the FAT submittal is required prior to shipment
of system components.
March 2021 - DRAFT 40_80_01-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 817
Item#18.
2. Owner training:
a. Demonstration requirements are specified in this Section.
Table 1
Minimum
Course Personnel
Length (Estimated Minimum
(hours per Number Number
Course Title session) of Students) of Sessions
System Overview 1 10 1
Operator Training - Basic 2 10 2
Operator Training - Advanced 4 5 2
3. Training course requirements:
a. System overview training:
1) Furnish training courses that give the Owner's supervisory level
personnel and overview of all elements of the PCIS system that
focus on the overall functional aspect of elements of the control
system and provide an understanding of the interaction of the various
components.
2) Furnish a training course that gives the Owner's supervisory level
personnel and overview of the new Contractor-provided elements of
the PCIS system. Focus on the overall functional aspects of each
new elements of the control system, particularly the mechanical
system vendor-provided control packages.
b. Operator training:
1) Furnish training courses that instruct system operators in the efficient
operation of all aspects of the PCIS that include not only the general
operation of the control system but also the operation of specific
system features.
2) Furnish training courses that instruct system operators in the efficient
operation of Contractor-provided aspects of the PCIS that include not
only the general operation of each control system but also the
operation of specific system features.
3) Operator's training shall include the following for each vendor
package and programmable device:
a) Control system overview: Architecture, equipment functions,
software components, etc.
b) Display navigation, overview, and types of displays.
c) Process and equipment monitoring and control: Basic principles
and operation.
d) Logging ON and OFF the system and description of the security
and access system.
e) Alarm subsystem.
f) Trending: Provide a thorough session on how to use all trending
functions.
g) Reports: How to access, print, and review content.
h) Control strategies: Present an average 15-minute review of each
control strategy, including a hands-on demonstration of screens
and operator functions for each.
March 2021 - DRAFT 40 80 01-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 818
Item#18.
i) Instruction on the use of all operational functionality alarm
logging, trending, displays, database, reports, and control
software developed for the Project and incorporated in the
installed PCIS system.
4. Installation testing:
a. Calibration:
1) Performed by Contractor and Vendor.
2) Calibrate and adjust all instruments, devices, valves, and systems, in
conformance with the component manufacturer's instructions and as
specified in these Contract Documents.
3) Replace either individually or within a system, defective elements
that cannot achieve proper calibration or accuracy:
a) Calibration for discrete devices:
(1) Calibrate and adjust devices for reliable operation and to
avoid nuisance tripping.
b) Calibration for ultrasonic and radar level devices:
(1) Provide Echo Transmission and signal quality on level
transmitters including guided and unguided units:
(a) Submit printout of the actual transmission and
parameters.
(2) Adjust mounting, as required, to obtain accurate readings.
(3) Post mounting: Provide any additional calibration required
by manufacturer.
c) Calibrating analog transmitters:
(1) Components having adjustable features are to be set
accurately for the specific conditions and applications of
this installation.
(2) Test and verify that components and/or systems are within
the specified limits of accuracy.
(3) Calibration points:
(a) Calibrate each analog instrument at 0 percent,
25 percent, 50 percent, 75 percent, and 100 percent of
span, using test instruments with accuracies traceable
to N I ST.
(4) Field verify calibration of instruments including units that
have been factory-calibrated to determine whether any of
the calibrations are in need of adjustment.
d) Analyzer calibration:
(1) Calibrate and test each analyzer system as a workable
system after installation. Follow the testing procedures
directed by the manufacturers' technical representatives.
(2) Submit completed instrument calibration sheets for every
field instrument and analyzer.
(3) Calibration tags:
(a) Attach a calibration and testing tag to each instrument,
piece of equipment, or system.
(b) Sign the tag when calibration is complete.
e) Calibration for industrial networking test equipment:
f) Submit calibration documentation.
b. Loop check:
1) Performed by the Contractor.
2) Cabling installed, terminated, and labeled.
March 2021 - DRAFT 40_80_01-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 819
Item#18.
3) Perform continuity check of wiring to each field device through
intermediate devices to field terminals in the cabinet.
4) Complete loop check form for each device.
5) Submit loop check test results before proceeding to the next step.
c. Loop validation tests:
1) Performed by the Contractor and manufacturer's representative,
working together, and witnessed by the Owner or Owner's
representative.
2) Perform tests on the signal from each field device through
intermediate devices to the 1/0 module on the PLC.
a) The PLC may or may not be connected to the network.
3) Engineer approval of the loop validation test submittal is required
before proceeding to CEET.
d. LAN cable post-testing:
1) Performed by Contractor.
2) After installing the cable and connectors, test all cables using the
LAN certification to confirm the installation meets the requirements of
the specification.
3) Provide test documentation that includes the cable number, total
length of cable, a permanent hard copy, as well as a-USB or CD
copy of all traces:
a) After installing connectors:
b) Perform cable end-to-end testing on all installed cables from
both ends of the cable. Test shall include cable system
performance tests and confirm the absence of wiring errors.
c) Submit a signed test report presenting the results of the cable
testing.
d) Repair or replace any portions of the system not meeting
TIA/EIA standards for installed cabling. Repaired sections shall
be retested.
4) Submit final documentation (including traces), using the approved
test form, to the Engineer upon successful completion of the testing.
5) Engineer approval of the LAN cable post-testing submittal is required
before proceeding to CEET.
e. Complete End-to-End Testing (CEET):
1) Performed by Contractor, manufacturer's representative working
together, with assistance from the OWNER or the inspection staff, as
needed:
a) The participants need to be dedicated full-time to CEET.
b) Contractor will be responsible for creating field signals and
verifying proper operation of final control elements.
2) Prerequisites:
a) CEET cannot begin until the successful completion of the
preceding tests:
(1) Calibration.
(2) Loop check.
(3) Loop validation tests.
(4) LAN cable post-testing.
(5) Industrial network testing.
March 2021 - DRAFT 40 80 01-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 820
Item#18.
3) Testing description:
a) This testing is to ensure all 1/0 signals operate to the intent of
the design from the field device to the HMI and all other auxiliary
controls and indicators in the PCS.
b) Connect PLC to the network to test signals from the field device
through the PLC program, the network, and to the operator's
HMI graphic screens. The outputs will be energized for a
duration long enough to verify proper operation of the final
control element.
c) SCADA screens:
(1) Test and record operator commands and signal readouts to
each operator device where there is more than one
operator interface point.
(2) For each signal, perform separate tests for SCADA
computer screens, local operator interface (LOI) screens,
and local control panels.
(3) Retest any loop following any necessary corrections.
4) Check control loops under simulated operating conditions by causing
a range of input signals at the primary control elements and
observing appropriate responses of the respective control and
monitoring elements, final control elements, and the graphic displays
associated with the HMI/SCADA system:
a) Use actual process inputs wherever available.
b) Issue commands from the HMI/SCADA system and verify proper
responses of field devices:
(1) Test SCADA system inputs from field device to SCADA
system operator workstations:
(a) Track responses through trend charts in the
HMI/SCADA system.
(2) Test SCADA system outputs from SCADA operator
workstations to field devices and equipment.
5) Discrete device testing:
a) Exercise each field device providing a discrete input to the
HMI/SCADA system in the field and observe the proper
operation shall be observed at the operator workstation:
(1) Test limit switches, set limits mechanically, and observe
proper operation at the operator workstation.
(2) Exercise starters, relay contacts, switch contacts, and
observe proper operation.
(3) Calibrate and test instruments supplying discrete inputs,
and observe proper operation.
b) Test each device accepting a discrete output signal from the
HMI/SCADA. Perform the appropriate operator action at the
SCADA operator stations (including LOls, if present) and
confirm the proper operation of the field device:
(1) Stroke valves through outputs from the HMI/SCADA
system, and confirm proper directional operation. Confirm
travel limits and any feedback signals to the HMI/SCADA
system.
(2) Exercise motors starters from the HMI/SCADA system and
verify proper operation through direct field observation.
March 2021 - DRAFT 40 80 01-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 821
Item#18.
(3) Exercise solenoids and other field devices from the
HMI/SCADA system and verify proper operation through
direct field observation.
6) Analog device testing:
a) Apply continuously variable up and down analog inputs to verify
the proper operation and setting of discrete devices (signal trips,
etc.).
b) Apply provisional settings on controllers and alarm setpoints.
7) Analog input:
a) Exercise each field device monitoring the analog signal, through
the HMI/SCADA system:
(1) Apply simulated sensor inputs corresponding to 0 percent,
25 percent, 50 percent, 75 percent, and 100 percent of
span for networks that incorporate analog elements, and
monitor the resulting outputs to verify compliance to
accuracy tolerance requirements.
8) Analog output:
a) Exercise each field device requiring an analog command signal,
through the HMI/SCADA system:
(1) Vary the output from the PLC HMI/SCADA system and
measure the end device position, speed, etc. to confirm the
proper operation of the device for the supplied analog
signal.
(2) Manually set the output from the HMI/SCADA screen at
0 percent, 25 percent, 50 percent, 75 percent, and
100 percent and measure the response at the final device
and at any intermediate devices.
9) Submit completed test forms:
a) Discrete instrument input devices:
(1) Switch setting, contact action, and dead band.
(2) Valve position switches:
(a) Response in the PLC as the valve is stroked from the
PLC.
(b) Field observed actual valve position, and valve
indicator position as the valve is stroked from the PLC.
(3) Operator interface switches (control stations and other pilot
devices) and associated response.
(4) Starter and drive auxiliary device contact response.
(5) Response of all other discrete inputs to the PLC.
(6) Test equipment used and associated serial numbers.
b) Discrete output devices:
(1) Observed response of field device to the discrete output
from the PLC.
(2) Observe the proper operation of Open, Close, Start, Stop,
On, Off, etc.
(3) Test equipment used and associated serial numbers.
c) Analog input devices:
(1) Calibration range.
(2) Calibration data: Input, output, and error at each test value.
(3) Analog input associated PLC register address.
(4) Value in PLC register at each test point.
March 2021 - DRAFT 40 80 01-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 822
Item#18.
(5) Value displayed at each operator interface station (local
operator interface displays and SCADA workstations).
(6) Test equipment used and associated serial numbers.
d) Analog output devices:
(1) Calibration range.
(2) Test value at each test point.
(3) Analog output associated PLC register address.
(4) Control variable value at field device at each test point.
(5) Physical device response at each test point:
(a) Response to be actual valve position, or motor speed,
etc.
(6) Test equipment used and associated serial numbers.
10) Failure testing:
a) Demonstrate how the system reacts and recovers from
abnormal conditions including, but not limited to:
(1) Equipment failure.
(2) Communications sub-system error.
(3) Power failure.
(4) Process equipment failure.
(5) High system loading conditions.
11) Engineer approval of the CEET submittals is required before
proceeding to Functional Testing.
5. Functional testing:
a. General:
1) Testing to demonstrate proper operation of systems with process
equipment operating over full operating ranges under conditions as
closely resembling actual operating conditions as possible.
2) Performed by Contractor and manufacturer's representative working
together, with assistance from the Owner or the inspection staff, as
needed.
3) Additional tests are specified in other Instrumentation and Control
Sections.
4) Follow approved detailed test procedures and check lists for
Functional Test activities.
b. Control logic operational validation:
1) The purpose of control logic validation is to field test the operation of
the complete control system, including all parts of the HMI/SCADA
system, all control panels (including vendor control panels), all
control circuits, all control stations, all monitored/controlled
equipment, and final control elements.
2) Demonstrate control functionality shown on the P&IDs, control
schematics, and other drawings, and specified in the loop
descriptions, control strategies, Electrical Specifications, and
Mechanical Equipment Specifications.
3) Test in detail on a function-by-function and sentence-by-sentence
basis.
4) Thoroughly test hardware and software functions:
5) Including all hardwired and software control circuit interlocks and
alarms.
6) Test final control elements, controlled equipment, control panels, and
ancillary equipment under startup, shut down, and steady-state
operating conditions to verify all logic and control is achieved.
March 2021 - DRAFT 40 80 01-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 823
Item#18.
7) Control logic validation tests to include, but not limited to: a repeat of
all control logic tests from the FAT, modified and expanded to include
all field instruments, control panels, circuits, and equipment.
c. Loop tuning:
1) Optimally tune all electronic control stations and software control
logic incorporating proportional, integral, or derivative control. Apply
control signal disturbances at various process variable levels and
adjusting the gain, reset, or rate settings as required to achieve
proper response.
2) Verify the transient stability of final control elements operating over
the full range of operating conditions, by applying control signal
disturbances, monitoring the amplitude and decay rate of control
parameter oscillations and making necessary controller adjustments
as required to eliminate excessive oscillatory amplitudes and decay
rates. As a minimum, achieve 1/4-wave amplitude decay ratio
damping (subsidence ratio of 4) under the full range of operating
conditions.
3) If excessive oscillations or system instability occur, as determined by
the Engineer, continue tuning and parameter adjustments, or develop
and implement any additional control algorithms needed to achieve
satisfactory control loop operation.
4) Functional validation sheets:
a) Document each Functional test on an approved test form.
b) Document loop tuning with a report for each loop, including two-
pen chart recordings showing the responses to step disturbance
at a minimum of 3 setpoints or process rates approved by the
Engineer. Show tuning parameters on the charts, along with
time, date, and sign-off by Contractor and Engineer.
c) Include on the form, functions which can be demonstrated on a
loop-by-loop basis:
(1) Loop number and P&ID number.
(2) Control strategy, or reference to specification tested.
(3) Test procedures: Where applicable, use the FAT function-
by-function, sentence-by-sentence loop test checklist forms
modified to meet the requirements of the Functional test.
Otherwise, create new forms.
d) For functions that cannot be demonstrated on a loop-by-loop
basis (such as overall plant power failure), include on the test
form a listing of the specific steps and tests to be conducted.
Include with each test description the following information:
(1) Specification page and paragraph of function
demonstrated.
(2) Description of function and/or text from specification.
(3) Test procedures: use the FAT loop test checklist forms
modified to meet the specific testing conditions of the
Functional test.
5) Functional certification:
a) Provide Manufacturer's Certificate of Installation and
Functionality Compliance as specified in Section 01_75_17.
(1) Including all test forms with test data entered, submitted to
the Engineer with a clear and unequivocal statement that all
Functional test requirements have been satisfied.
March 2021 - DRAFT 40 80 01-14 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 824
Item#18.
C. Process Start-up Phase:
1. Process Start-up:
a. Manufacturer shall be onsite to support Process Start-up activities and
provide functional changes as required.
2. Process Operation Period:
a. Manufacturer shall be available to support Process Operational Period
and provide functional changes as required.
3. Instrumentation and Controls Fine-Tuning:
a. General:
1) After the Process Operational Period, test PCIS system for additional
60 days as specified in this Section to identify issues and make
corrections, as needed.
2) The performance test is part of the Work that must be completed as
a condition of substantial completion and final completion for the
entire Project.
3) The complete PLC control and HMI/SCADA system must run
continuously for the duration of the performance test.
4) Test and use the entire process control system under standard
operating conditions.
5) Exercise all system functions.
6) Log failure, any system interruption and accompanying component,
subsystem, or program failure including time of occurrence, duration
of each failure, failure classification, and cause:
a) Provide a competently trained technician or programmer on call
for the Project Site during all normal working days and hours
from the start of the performance test until final acceptance of
the system:
(1) Response time to the Project Site: 24 hours or less, for a
major failure.
b. SCADA system testing:
1) Exercise each system function, e.g., status report, alarms, logs, and
displays several times at a minimum, and in a manner that
approximates "normal" system operation.
2) Failure of the HMI/SCADA system during testing shall be considered
as indicating that the programs and operating system do not meet
the requirements of the specifications:
a) Corrective action is required before restarting the performance
test.
3) Only those components, sub-systems, and systems covered in this
Section and supplied under this Contract shall be considered for this
acceptance test. Problems and failures of other systems shall not be
considered as part of this test, except as they display the capabilities
of this system to detect failures.
4) Failures:
a) Classify failures as either major or minor:
(1) Minor failure:
(a) A small and non-critical component failure or software
problem that can be corrected by the Owner's
operators.
(b) Log this occurrence but this is not a reason for
stopping the test and is not grounds for non-
acceptance.
March 2021 - DRAFT 40 80 01-15 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 825
Item#18.
(c) Should the same or similar component failure occur
repeatedly, this may be considered as grounds for
non-acceptance.
(d) Failure of one printer or operator station is considered
a minor failure providing all functions can be provided
by backup equipment, i.e., alternate printers and
operator station, and repairs can be made and
equipment returned to service within 3 working days.
(2) Major failure:
(a) Considered to have occurred when a component,
subsystem, software control, or program fault causes a
halt in or improper operation of the system and/or
when a technician's work is required to make a repair
or to re-initiate operation of the system.
(b) Cause termination of the performance test.
(c) Start a new acceptance test when the causes of a
major failure have been corrected.
(d) A failure is also considered major when failure of any
control system that results in an overflow, underflow,
overdose, or underdose condition occurs.
5) Technician report:
a) Each time a technician is required to respond to a system
malfunction, they must complete a report, which includes details
concerning the nature of the complaint or malfunction and the
resulting repair action required and taken.
b) If a malfunction occurs which clears itself or which the operator
on duty is able to correct, no report is required or logged as
specified above.
c) If a technician has performed work but no report is written, then
a major failure is considered to have occurred.
d) Each report shall be submitted within 24 hours to the Engineer
and the Owner, or its representative.
3.08 FIELD QUALITY CONTROL (NOT USED)
3.09 ADJUSTING (NOT USED)
3.10 CLEANING (NOT USED)
3.11 PROTECTION (NOT USED)
3.12 SCHEDULES
A. Example test forms:
1. Example test forms are attached at the end of this Section. They may be used
as a starting point for the development of Project-specific test forms for this
Project.
2. The example test forms are not intended to be complete or comprehensive.
Edit and supplement the forms to meet the requirements for testing and test
forms specified in this Section and other Contract Documents.
END OF SECTION
March 2021 - DRAFT 40 80 01-16 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 826
Item#18.
FACTORY ACCEPTANCE TEST-CONTROL PANELS
1. GENERAL INSPECTION
A. Structural Inspection
❑ Verify Lifting Lugs Installed
❑ Verity enclosure has lock and lock is functional
❑ Confirm that seismic bracing components are provided per manufacturer's installation instructions
B. Exterior Inspection
❑ Cabinet exterior is clean, scratch, and dent free
❑ Inspect externally for corrosion and damage
❑ Verify enclosure door opens and closes easily
❑ Verify enclosure has a 3-point latch
❑ Verify enclosure has a flange mounted disconnect(where voltages greater than 120 VAC enter the cabinet)
❑ Verify enclosure has the appropriate NEMA rating (1, 1G, 12, 3R,4,4X, etc.)
❑ Verify enclosure is the appropriate size (not grossly larger than design, and will still fit in the plant)
Nameplates
❑ Cabinet has identification nameplate
❑ All door labels are straight, spelled correctly, and match the tagging defined in the Contract
❑ Cabinet has a nameplate that includes the following:
❑ Power source(s) ❑ Integrator's Logo
❑ Circuit ID(s) ❑ Short Circuit KAIC ratings
❑ If labels are screwed to door,silicone was utilized to cover screw holes (Labels screwed to the door of a
NEMA 4/4X panel technically violates the NEMA rating.)
Door Devices
❑ All devices penetrating the outside of panel have gaskets, silicone or both
❑ All door devices are installed (HMIs, Pilot Devices, etc.)
❑ Door mounted equipment is mounted straight and square
❑ All exterior or door mounted equipment present and accounted for, installed and securely fastened
❑ NEMA classification has not been violated due to penetrations
❑ Door mounted equipment has the same NEMA rating as the panel
❑ All door mounted equipment installed at the correct height
❑ All door mounted equipment installed in the correct positions and order(layout of door mounted equipment
is grouped properly and in a logical manner)
❑ Doors with multiple penetrations have adequate bracing (if needed)
❑ Visually check condition of indicators , controllers and annunciators
❑ Check that pilot lights illuminate correctly
❑ Check the Push-To-Test function
❑ Ensure correct pilot light color
Peripheral Devices
❑ Horn/Beacon is installed (where required)
❑ Silence and Reset pushbutton
PROJECT NAME: TEST DATE:
FACILITY NAME: TESTED BY:
PROCESS AREA: COMPANY:
NETWORK ID: PAGE:
WITNESSED BY: SIGNATURE:
March 2021 - DRAFT 40 80 01-17 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 827
Item#18.
FACTORY ACCEPTANCE TEST-CONTROL PANELS
1. GENERAL INSPECTION (continued)
C. Interior Inspection
❑ Cabinet is cleaned of marks and dirt.
❑ Inspect internally for corrosion and damage.
❑ Back panel is clean of marks and dirt.
❑ Interior of panel vacuumed and shall be free of all debris.
❑ Check that the panel roof is clean and clear of foreign materials.
❑ Bottom of panel has been cut out(where bottom entry is required),with angle iron welded around the bottom
perimeter. Re-painting has been performed.
❑ If internal light door limit switch is provided, ensure the light automatically turns"on"when the doors are open.
❑ Check that a document pocket has been provided.
❑ Intrusion alarms(where required).
Interior Labeling
❑ All panel mounted equipment has identification labeling, by using either a Brothers or Phenolic type tags.
❑ Verify that door mounted components are mounted square and symmetrical.
❑ Verify that nameplates are straight, legible, and spelled correctly.
❑ All terminal blocks are identified/labeled with permanent labels including tight end blocks and caps.
❑ All wiring shrink labeled and or phased correctly to the specifications.
❑ All wire labels shrunk completely rotated and aligned alike for easy identification.
❑ All fuses and circuit breakers are labeled with ID and current rating.
❑ System Integrator's label or labels installed on door.
❑ Panel manufacturer model/serial number tag is present.
❑ All required safety/warning tags installed and straight.
❑ Correct UL(typically UL 508)or cUL tag installed and registered and all other associated tags installed and
straight(the UL tag might not be installed in the panel at the factory test. If the panel is modified due to
changes during the factory test or a punch list generated from the factory test, the UL labeling would need
to be re-applied. Some UL shops do not apply the UL label until the panel is released to be shipped.).
Wireways
❑ Plastic wire way covers installed properly.
❑ Plastic wireways have no sharp edges.
❑ No wire Ties inside the wireways.
❑ No sharp edges on wire ties.
❑ Separation:White duct is used for DC voltages, Gray duct is used for AC voltages.
❑ Ensure wiring duct is not over-full, includes provision for 20%more wiring and the cover may easily be
installed. Panduit recommends 50%duct fill, but 40% is a better practice.
PROJECT NAME: TEST DATE:
FACILITY NAME: TESTED BY:
PROCESS AREA: COMPANY:
NETWORK ID: PAGE:
WITNESSED BY: SIGNATURE:
March 2021 - DRAFT 40 80 01-18 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 828
Item#18.
FACTORY ACCEPTANCE TEST-CONTROL PANELS
1. GENERAL INSPECTION (continued)
C. Interior Inspection (continued)
Wiring
❑ Visually check terminals and condition of internal wirings
❑ Verify that the control panel has been assembled and wired as designed
❑ Verify that all components are operational and perform the functions intended
❑ Verify that all components are sized appropriately for the application
❑ Verify that equipment control circuits function as intended
❑ Back of door wiring is labeled and neatly formed
❑ Back panel to door wiring has sufficient bending radius with spiral wrap
❑ Wire connection has been verified wired to correct points within the panel
❑ Individual wires have been given a pull test to verify a good terminal connection
❑ Wire and cable minimum bending radius have not been violated
❑ All equipment installed straight and square to back panel
❑ Wire colors are correct:
❑ Black and White>AC hot and neutral, respectively
❑ Red >AC control signals
❑ Blue> DC power and control (Blue w/White stripe for DC ground)
❑ Yellow> Foreign voltages (those still present when panel power is disconnected)
❑ Green >AC equipment ground
❑ Black>TSP (+)
❑ White>TSP(-)
❑ Analog wiring shields are continuous(connected by a dedicated terminal block for such shields)
❑ Analog shield wires are grounded within the panel,where not otherwise grounded at the transmitter itself
❑ Discrete inputs are separately fused or protected by a circuit breaker on a "per loop"basis
❑ Intrinsic Safety Wiring
❑ Ensure wiring associated with intrinsic safety circuits or intrinsic safety barriers is kept away from all
other wiring by LIL minimum distances or by a physical (grounded metal)barrier preventing non-
intrinsically safe wiring from coming in contact with intrinsically safe circuits or wiring
❑ Verify all spare terminals are installed according to the percentage listed in the specifications
Grounding
❑ Equipped with "Blackburn"or other grounding type lug
❑ Lug is securely fastened to the panel structure
❑ Verify Grounding bar is installed
❑ Verify Isolated ground bar is installed
PROJECT NAME: TEST DATE:
FACILITY NAME: TESTED BY:
PROCESS AREA: COMPANY:
NETWORK ID: PAGE:
WITNESSED BY: SIGNATURE:
March 2021 - DRAFT 40 80 01-19 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 829
Item#18.
FACTORY ACCEPTANCE TEST-CONTROL PANELS
2. POWER TEST
A. AC Power
❑ AC Power is routed correctly within the panel, and is isolated from DC and network wiring.
❑ All fuses are installed and sized properly.
❑ All breakers are installed and sized properly.
❑ 24 VDC Power Supplies are functional.
❑ 24 VDC Power fail contacts are functional.
❑ 24 VDC power supplies are redundant, and have diode modules enabling the hot swap-over between supplies.
❑ 24 VDC supplies are equipped with dry contact failure alarms,wired as PLC inputs to signal failure of any
DC power supply. Such alarm inputs to the PLC have been tested as being functional.
❑ Dedicated receptacle is wired to receive a dedicated AC supply.
❑ Verify continuity for all DC commons,ground and AC neutrals.
❑ Verify that the CP temporary input power is connected correctly and is the correct voltage.
❑ Close the CP main circuit breaker(s).
❑ Verify that voltages at subsequent circuit breakers are correct.
❑ Close circuit breakers.
❑ Verify that power feeding interruptible and uninterruptible power supplies is correct.
❑ Turn on power supplies if they are not already on.
❑ Verify that voltages at distribution terminals are correct.
❑ Energize any remaining hardware such as the PLC.
B. Uninterruptible Power Supply(UPS)
❑ Mounted appropriately within the cabinet, on a dedicated shelf, or rear of a swing-out sub panel.
❑ Is equipped with maintenance bypass switch (or at least plug/receptacle means for bypassing the unit).
❑ Test all UPS alarms(on inverter,failure, battery failure etc.)
❑ Turn off the AC power supply and verify that the UPS will be switched on to supply the designated vital loads in
the control panel.
3. CONTROLS&AUXILIARY DEVICES TEST
❑ Verify all interposing and auxiliary relays are functioning.
❑ Verify panel lights are functioning.
Ventilation and Heating
❑ If ventilation fans are fitted, check the fans operate correctly any associated air filters are clean and not blocked.
❑ Verify components are installed in the correct orientation for proper air flow.
4. HARDWIRED INTERLOCK AND SAFETY TEST
❑ Verify that hardwired interlocks through the control panel as shown on schematic drawings are functioning. For
example, outlet high pressure switch interlock to a pump.
❑ Verify that all hardwired safety devices through the control panel is functioning. For example,the pull cord
emergency stops of conveyors.
PROJECT NAME: TEST DATE:
FACILITY NAME: TESTED BY:
PROCESS AREA: COMPANY:
NETWORK ID: PAGE:
WITNESSED BY: SIGNATURE:
March 2021 - DRAFT 40 80 01-20 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 830
Item#18.
FACTORY ACCEPTANCE TEST-CONTROL PANELS
5. PLC TEST
A. Components
❑ PLC interior High Temperature alarm is installed,wired to the PLC, and is shown to be functional.
❑ Relays have transient suppression across their coils.This is particularly important for DC coil relays,where
diodes in reverse polarity are often used.
❑ TVSS is installed across the main incoming 120 VAC.
PLC and PLC Rack
❑ Verify all cards are securely seated.
❑ Ensure clearance around PLC rack has been met, such that convective heat transfer is not impeded by
devices erroneously mounted in the"no encroachment"area. Confirm with manufacturer clearance
recommendations.
B. PLC 1/0 Test
❑ Furnish 1/0 test forms and test all the listed input and output points as follows:
❑ Discrete Inputs: Simulate a field contact closure by"shorting"across the appropriate terminal blocks.
Observe the transition between a logical "0"and 1"in the PLC software.
❑ Discrete Outputs: Force the output bit to toggle between logical "0"and logical 1"using the PLC software.
Measure contact resistance at the wired terminal blocks using a digital meter selected for the"ohms"
setting.
❑ Analog Inputs: Connect a signal generator to the appropriate terminal blocks. Tailor the connection
depending on whether a 2-wire or 4-wire simulation is required. Modulate the 4-20mA signal. Observe the
associated PLC internal memory register to transition between 0-65535 or if scaled in engineering units,
between 0 and the maximum scaled engineering unit. The latter method is preferred.
❑ Analog Outputs: Force the output register to a value between 0-65535 or 0-100%, if the scaling block can
be manipulated. Observe the measured 4-20mA value increment and decrement using a digital ammeter.
C. Redundant Controllers(where required)Test
❑ Remove Communication cable from primary PLC to verify switching to backup PLC
❑ Remove Communication cable from backup PLC to verify switching back to primary PLC
❑ Remove Power cable from primary PLC to verify switching to backup PLC
❑ Remove Power cable from backup PLC to verify switching back to primary PLC
D. PLC Control Logic Verification
❑ The PLC control strategy is verified by following the Control Logic Verification Form based on the specifications.
Each control strategy will be verified by simulating the process and checking the state or value of PLC outputs.
The results of equipment status and alarms and process instrument values and trends shall also be verified on
the Plant SCADA graphic screens stored in a temporary SCADA computer. Since all PLC input and output wiring
has been verified and some field devices are not available during Factory Acceptance Testing, certain inputs will
be simulated either by means of additional hardware and/or software as described below.
❑ DI states are either simulated by hardwired switches or forced inputs using a programming terminal.
❑ For example,when starters and drives are not provided as part of the contract,jumpers may be installed
from the output call relays to the running confirmation inputs to simulate the running state of the motors.
PROJECT NAME: TEST DATE:
FACILITY NAME: TESTED BY:
PROCESS AREA: COMPANY:
NETWORK ID: PAGE:
WITNESSED BY: SIGNATURE:
March 2021 - DRAFT 40 80 01-21 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 831
Item#18.
FACTORY ACCEPTANCE TEST-CONTROL PANELS
5. PLC TEST(continued)
D. PLC Control Logic Verification (continued)
Typical Fault Logic
❑ If the fault input is high and the disable(if applicable)for the fault is not high and the common disable(if
applicable)is not high begin timing. If any of these conditions changes,stop timing and reset the timer. If
the timer reaches its preset, activate the alarm output. If the fault alarm is a shutdown alarm stop the
associated motor and latch the alarm so that it remains present even if the condition clears.
❑ The fault condition must return to normal and the alarm must be reset for a latched alarm to clear.
Typical Fail to Start Logic
❑ If the motor is called to run (call output high)and no running feedback is received (running input is low)and
the fail to start and common alarm disables (if applicable)are not high start timing. If any of these conditions
changes, stop timing and reset the timer. If the timer reaches its preset, activate the alarm output,stop
calling the motor and latch the alarm.
6. HMI OR OIT TEST
HMI/OIT Functionality
❑ Communication with PLC
❑ Screen Layouts
❑ Screen Navigation
❑ Set Point Entry
❑ Animation
❑ Color Correctness (Green=Run, Red=Off,Amber=Alarm,or the agreed upon convention)
❑ Alarms
❑ Acknowledge and Reset
❑ Security/Access Levels/Passwords
7. NETWORK COMMUNICATION TEST
A. Network Components
❑ Fiber optic cabling terminates in a patch panel
❑ Media converters are installed and functional
❑ Terminating resistors have been installed for trunk/tap topologies or where required
❑ Wire and cable bending limitations have not been violated
B. Networking Functions
❑ Verify data transfer via the network to different PI-Cs as shown on the Network Block Diagrams
❑ Verify network traffic rate and error margin is acceptable
PROJECT NAME: TEST DATE:
FACILITY NAME: TESTED BY:
PROCESS AREA: COMPANY:
NETWORK ID: PAGE:
WITNESSED BY: SIGNATURE:
March 2021 - DRAFT 40 80 01-22 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 832
Item#18.
FACTORY ACCEPTANCE TEST-CONTROL PANELS
8. FAT DOCUMENTATION AND RECORD
Panel Documentation
❑ As-built panel drawings showing actual panel construction and devices arrangement and c/w Bill of
Material.
❑ Panel schematic and interconnection drawings.
❑ P&ID drawings and schematic drawings for the process area controlled by the panel that is to be tested.
❑ I/O list test forms of the process area to be tested.
❑ FAT procedure of the process area to be tested.
❑ Test record forms of the process area to be tested. Forms shall include area for signature of responsible
test personnel.
❑ Hard copy of the PLC application program of the process area to be tested.
❑ Hard copy of the HMI/OIT graphic screens of the process area to be tested.
9. FAT TOOLS AND SOFTWARE
❑ Simulation software if required
❑ Digital volt meter Fluke 87
❑ Process meter Fluke 787
❑ Laptop computer with PLC application program
❑ Temporary SCADA computer with HMI software and applicable graphic screens
❑ Jumper wires
PROJECT NAME: TEST DATE:
FACILITY NAME: TESTED BY:
PROCESS AREA: COMPANY:
NETWORK ID: PAGE:
WITNESSED BY: SIGNATURE:
March 2021 - DRAFT 40 80 01-23 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 833
Item#18.
INSTALLATION AND CERTIFICATION CHECKLIST
DOCUMENTATION
INSTRUMENT LOOP NO.
SERVICE DESCRIPTION
A COPY OF LATEST ISSUE OF THE FOLLOWING DOCUMENTS ARE INCLUDED IN THIS INSTRUMENT INSTALLATION
CERTIFICATION FILE:
❑ INSTRUMENT SPECIFICATION SHEETS(FOR ALL INSTRUMENTS IN THE LOOP)
❑ INSTRUMENT INSTALLATION DETAILS(FOR ALL INSTRUMENTS IN THE LOOP)
❑ INSTRUMENT LOOP WIRING DIAGRAMS
❑ INSTRUMENT INSTALLATION CERTIFICATION CHECKLIST
❑ SIZING CALCULATIONS
❑ INSTRUMENT INSTALLATION SCHEDULE(APPLICABLE PART)
❑ NAMEPLATE SCHEDULE(APPLICABLE PART)
❑ VENDOR LITERATURE CALIBRATION INFORMATION
❑ ❑
INSTRUMENT LOOP IS PART OF EQUIPMENT START-UP/SHUTDOWN INTERLOCKS? No Yes
REMARKS:
CHECKED BY(COMPANY) ACCEPTED BY(COMPANY)
SIGNATURE SIGNATURE
DATE DATE
March 2021 - DRAFT 40 80 01-24 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 834
Item#18.
SWITCHES
INSTALLATION AND CALIBRATION CHECKLIST
INSTRUMENT LOOP NO.
SERVICE DESCRIPTION
CHECK BELOW,WHEN COMPLETED:
❑ BENCH CALIBRATED PER SPECIFICATION SHEET NO.
❑ VERIFIED PER P&ID NO.
❑ CORRESPONDS TO SPECIFICATION SHEET NO.
❑ WIRING CORRECT PER INSTRUMENT LOOP DRAWING NO.
❑ INSTALLATION CORRECT PER DETAIL NO.
❑ ACCESSORIES ARE PRESENT AND PROPERLY INSTALLED
❑ INSTRUMENT IS ACCESSIBLE FOR MAINTENANCE OR REMOVAL
❑ ENGRAVED LAMINATED NAMEPLATE(NO SPELLING ERRORS)PERMANENTLY INSTALLED
❑ ❑
INSTRUMENT LOOP IS PART OF EQUIPMENT START-UP/SHUTDOWN INTERLOCKS? No Yes
FIELD CALIBRATION CHECK
CONTACT FOR CONTACT IS
NO. FUNCTION SIGNAL TO AT SPECIFIED VALUE FOR ACTUAL TRIP POINT WAS
1 ❑ ALARM ❑ INCR ❑ OPEN SET PT= SET PT=
❑ S/D PERM ❑ DECR ❑ CLOSE RESET- RESET=
2 ❑ ALARM ❑ INCR ❑ OPEN SET PT= SET PT=
❑ S/D PERM ❑ DECR ❑ CLOSE RESET- RESET=
3 ❑ ALARM ❑ INCR ❑ OPEN SET PT= SET PT=
❑ S/D PERM ❑ DECR ❑ CLOSE RESET= RESET=
4 ❑ ALARM ❑ INCR ❑ OPEN SET PT= SET PT=
❑ S/D PERM ❑ DECR ❑ CLOSE RESET= RESET=
NOTE:PERM IS ABBREVIATION FOR PERMISSIVE
March 2021 - DRAFT 40 80 01-25 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 835
Item#18.
SWITCHES
INSTALLATION AND CALIBRATION CHECKLIST
REMARKS:
CHECKED BY(COMPANY) ACCEPTED BY(COMPANY)
SIGNATURE SIGNATURE
DATE DATE
March 2021 - DRAFT 40 80 01-26 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 836
Item#18.
TRANSMITTER/CONTROLLER/INDICATOR
INSTALLATION AND CALIBRATION CHECKLIST
INSTRUMENT LOOP IS PART OF EQUIPMENT START-UP/SHUTDOWN INTERLOCKS? No Yes
INSTRUMENT TYPE ❑ TRANSMITTER ❑ CONTROLLER ❑
INDICATOR
❑ OTHER DESCRIPTION
INSTRUMENT TAG NO. SERIAL NO.
SERVICE
DESCRIPTION
BENCH CALIBRATION CHECK
INPUT RANGE= OUTPUT RANGE_
HEAD CORRECTION= ❑ LINEAR
CALIBRATED SPAN= ❑ SQUARE ROOT
%CALIB
SPAN DESIRED VALUE ACTUAL VALUE EXPECTED VALUE ACTUAL VALUE
0
50
100
CHECK BELOW,WHEN COMPLETED:
❑ BENCH CALIBRATED PER SPECIFICATION SHEET NO.
❑ VERIFIED PER P&ID NO.
❑ CORRESPONDS TO SPECIFICATION SHEET NO.
❑ WIRING CORRECT PER INSTRUMENT LOOP DRAWING NO.
❑ INSTALLATION CORRECT PER DETAIL NO.
❑ ACCESSORIES ARE PRESENT AND PROPERLY INSTALLED
❑ INSTRUMENT IS ACCESSIBLE FOR MAINTENANCE OR REMOVAL
❑ ENGRAVED LAMINATED NAMEPLATE(NO SPELLING ERRORS)PERMANENTLY INSTALLED
FIELD CALIBRATION CHECK
INPUT RANGE= OUTPUT RANGE_
%CALIB
SPAN DESIRED VALUE ACTUAL VALUE EXPECTED VALUE ACTUAL VALUE
0
50
100
March 2021 - DRAFT 40 80 01-27 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 837
Item#18.
TRANSMITTER/CONTROLLER/INDICATOR
INSTALLATION AND CALIBRATION CHECKLIST
❑ DIRECT ❑ REVERSE
❑ ACTION VERIFIED AT 50%SPAN
❑ ACTION VERIFIED AT SPAN
CONTROLLER SETTINGS
RESET DERIV. HIGH LOW ELEV. ZERO
SETTING GAIN PB (INTEGRAL) (RATE) LIMIT LIMIT ZERO SUPP
PRE-TUNE
POST-TUNE
PRE-TUNE SETTINGS
DERIVATION
GAIN PB RESET(REPEAT/MIN) RESET(MIN/REPEAT) (MINUTES)
FLOW 1.0 100 10 0.1 N/A
LEVEL 1.0 100 MIN. MAX. N/A
PRESSURE 2.0 50 2.0 0.5 N/A
TEMP. 4.0 25 0.1 10 OFF
REMARKS
CHECKED BY(COMPANY) ACCEPTED BY(COMPANY)
SIGNATURE SIGNATURE
DATE DATE
March 2021 - DRAFT 40 80 01-28 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 838
Item#18.
ANALYZERS
INSTALLATION AND CALIBRATION CHECKLIST
INSTRUMENT LOOP IS PART OF EQUIPMENT START-UP/SHUTDOWN INTERLOCKS? No Yes
TYPE OF INSTRUMENT
INSTRUMENT TAG NO. SERIAL NO.
SERVICE DESCRIPTION
CHECK BELOW, IF TRUE
❑ BENCH CALIBRATED PER SPECIFICATION SHEET NO.
❑ VERIFIED PER P&ID NO.
❑ CORRESPONDS TO SPECIFICATION SHEET NO.
❑ WIRING CORRECT PER INSTRUMENT LOOP DRAWING NO.
❑ INSTALLATION CORRECT PER DETAIL NO.
❑ ACCESSORIES ARE PRESENT AND PROPERLY INSTALLED
❑ INSTRUMENT IS ACCESSIBLE FOR MAINTENANCE OR REMOVAL
❑ ENGRAVED LAMINATED NAMEPLATE(NO SPELLING ERRORS)PERMANENTLY INSTALLED
REMARKS
CHECKED BY(COMPANY) ACCEPTED BY(COMPANY)
SIGNATURE SIGNATURE
DATE DATE
March 2021 - DRAFT 40 80 01-29 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 839
Item#18.
CONTROL VALVES
INSTALLATION AND CALIBRATION CHECKLIST
❑ ❑
INSTRUMENT LOOP IS PART OF EQUIPMENT START-UP/SHUTDOWN INTERLOCKS? No Yes
❑ VALVE TAG NO. SERIAL NO.
❑ TRANSDUCER TAG NO. SERIAL NO.
❑ SOLENOID TAG NO. SERIAL NO.
❑ VOLUME BOOSTER TAG NO. SERIAL NO.
❑ POSITIONER SERIAL NO.
SERVICE DESCRIPTION
TRANSDUCER CHECK
INPUT RANGE= OUTPUT RANGE=
CALIBRATED SPAN= CALIBRATED SPAN=
BENCH
SPAN DESIRED ACTUAL SPAN EXPECTED ACTUAL
0% 0%
50% 50%
100% 100%
FIELD
SPAN DESIRED ACTUAL SPAN EXPECTED ACTUAL
0% 0%
50% 50%
100% 100%
CHECK BELOW, IF TRUE:
❑ BENCH CALIBRATED PER ABOVE
❑ VERIFIED PER P&ID NO.
❑ CORRESPONDS TO SPECIFICATION SHEET
NO.
❑ VALVE SPECIFICATION NO.
❑ TRANSDUCER SPECIFICATION NO.
❑ SOLENOID SPECIFICATION NO.
❑ WIRING CORRECT PER INSTRUMENT LOOP DRAWING NO.
❑ INSTALLATION CORRECT PER INSTRUMENT INSTALLATION DETAILS
❑ VALVE DETAIL NO.
❑ TRANSDUCER DETAIL NO.
❑ SOLENOID DETAIL NO.
March 2021 - DRAFT 40 80 01-30 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/40_80_01(IDS50) Page 840
Item#18.
CONTROL VALVES
INSTALLATION AND CALIBRATION CHECKLIST
❑ ACCESSORIES ARE PRESENT AND PROPERLY INSTALLED
❑ INSTRUMENT IS ACCESSIBLE FOR MAINTENANCE OR REMOVAL
❑ ENGRAVED LAMINATED NAMEPLATE(NO SPELLING ERRORS)PERMANENTLY INSTALLED
VALVE CHECK
FLOW ❑ PROCESS FLOW DIRECTION THROUGH THE VALVE IS CORRECT
CHECK
SAFETY ON LOSS OF AIR VALVE FAILS ON LOSS OF POWER SOLENOID FAILS
CHECK ❑ OPEN ❑ CLOSE ❑ TO VENT ❑ TO VALVE
TRAVEL FULL OPEN AT FULL CLOSED AT MEASURED TRAVEL
CHECK PSI PSI INCHES
SEATING ❑ ON BENCH RESULTS ACTUATOR BENCH SET
CHECK ❑ IN-LINE
POSITIONER CHECK
VALVE FULL OPEN AT PSI TO POSITIONER
VALVE FULL CLOSED AT PSI TO POSITIONER
VOLUME BOOSTER CHECK
BYPASS VALVE(GAIN)ADJUSTING SCREW BACKED OUT TURNS FROM CLOSED TO ENSURE QUICK BUT
STABLE OPERATION TYPICALLY 1-1/2 TO 2 TURNS
REMARKS
CHECKED BY(COMPANY) ACCEPTED BY(COMPANY)
SIGNATURE SIGNATURE
DATE DATE
March 2021 - DRAFT 40 80 01-31 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel40_80_01(IDS50) Page 841
Item#18.
Page 842
Item#18.
SECTION 43_11_33
ROTARY-LOBE BLOWERS
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Rotary-lobe blowers.
B. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 01 75 17 - Commissioning
3. Section 01_78_23 - Operation and Maintenance Data.
4. Section 01 78 36 - Warranties and Bonds.
5. Section 01_81_01 - Project Design Criteria.
6. Section 26_05_09 - Low Voltage Motors up to 500 Horsepower.
7. Section 40_73_13 - Pressure/Vacuum Measurement: Gauges.
8. Section 40 73 23 - Pressure/Vacuum Measurement: Direct.
9. Section 40_80_01 - Commissioning for Instrumentation and Controls.
10. Section 46_05_10 - Common Work Results for Mechanical Equipment.
11. Section 46_05_94 - Mechanical Equipment Testing.
C. Tag numbers:
1. Rotary-lobe Blower 1 SBU681.
2. Rotary-lobe Blower 2 SBU682.
1.02 REFERENCES
A. American Bearing Manufacturers Association (ABMA):
1. 9 - Load Ratings and Fatigue Life for Ball Bearings.
2. 11 - Load Ratings and Fatigue Life for Roller Bearings.
B. American Society of Heating, Refrigerating and Air-Conditioning Engineers
(ASHRAE):
1. 52.1 - Testing for HVAC Air Filtration.
C. American Society of Mechanical Engineers (ASME):
1. B16.1 - Gray Iron Pipe Flanges and Flanged Fittings: Classes 25, 125, and
250.
D. National Electrical Manufacturers Association (NEMA):
1. 250 - Enclosures for Electrical Equipment (1,000 V Maximum).
1.03 SYSTEM DESCRIPTION
A. System components: Aeration blowers, blower panel, and appurtenances.
B. General: Aeration blowers and appurtenances shall include the following items and
supplied by blower manufacturer:
1. Rotary positive displacement blower and motor.
March 2021 - DRAFT 43 11 33-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_1133(IDS50) Page 843
Item#18.
2. Air intake filters.
3. Silencers, inlet, and discharge.
4. Check valves.
5. Relief valves.
6. Flexible pipe connectors.
7. Pressure gauges.
8. Acoustic enclosure.
9. Discharge temperature gauge.
10. Appurtenances as required.
C. Design requirements:
Type of Blower Rotary lobe, positive displacement
Number of blowers 2 (1 per reactor train)
Rated speed 3,514 rpm @ 99% of maximum
Rated inlet air flow at rated speed 255 scfm per machine
SUM
Inlet filter/Silencer pressure loss 0.35 pounds per square inch
Rated discharge pressure 8.0 psig
Rated inlet pressure 13.1 psia
Inlet temperature 93 degree Fahrenheit
Design Relative Humidity 10 %
Minimum Turndown (VFD ONLY) 69 scfm per machine
Brake Horsepower (max) 15 bHp
1. Motor: As specified in Section 26_05_09, except as otherwise specified or
supplemented below:
Power supply 480-volt, 3-phase, 60-hertz
Horsepower 20 HP
Speed, maximum 3,535
Enclosure TEFC
Service factor 1.15
2. Drive: Belt.
3. Noise control:
a. Sound pressure levels radiated from equipment furnished shall not
exceed 73 dBA (mean, A-weighted) at 3 feet (RE 2 x 10-5 N/m2) for free
field condition when unit is in operation at rated flow.
4. Vibration:
a. Maximum acceptable peak vibration velocity (unfiltered) for blower
equipment is 0.45 inches per second.
5. Package flow, pressure, and BHP performance to include pressure loss
through a clean inlet filter/ silencer, pressure loss of the exhaust silencer and
check valve.
March 2021 - DRAFT 43 11 33-2 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_11_33(IDS50) Page 844
Item#18.
6. Package Performance shall be guaranteed to ISO 1217 with a tolerance is
+/- 5% on volume flow and +/- 5% on package horsepower. Manufacturer of
blower must provide data for purchased machine.
7. Sound data shall be from an ISO 2151 method of measurement, in an
ISO 3745 qualified test facility. Sound data shall be compliant with a
Declaration of Conformity assessment standard.
1.04 SUBMITTALS
A. Submit as specified in Section 01_33_00.
B. Product data:
1. As specified in Section 46_05_10.
2. Blower information:
a. Manufacturer.
b. Model.
c. Blower speed in revolutions per minute.
d. Blower site capacity, actual cubic feet per minute (scfm and icfm at site
conditions).
e. Discharge pressure, pounds per square inch absolute.
f. Rated maximum pressure rise of blowers.
g. Horsepower required including loss in V-belt drive.
h. Weight of blower.
i. Weight of motor.
j. Free-field noise level at 3 feet from blower acoustic enclosure.
3. Motor performance and construction data.
4. Construction details of acoustic enclosure.
5. Descriptive brochures and applicable performance and construction data for
each item of auxiliary equipment along with their weights.
6. Test data on equipment performance, vibration, and noise.
7. Certified general arrangement drawings showing materials, details of
construction, dimensions, and connections.
8. List of recommended spare parts broken down into on hand parts and long
term for 2 years operation and 3 to 5 years operation.
9. ISO-1217 Performance Test Results Slip test results are unacceptable as an
alternate. Manufacturer must provide documented results for the purchased
machines. Typical or average data is not acceptable.
C. Shop drawings: As specified in Section 46_05 10:
1. Blower panel device layout and material list.
D. Calculations: As specified in Section 46_05_10.
E. Vendor operation and maintenance manuals: As specified in Section 01_78_23.
F. Commissioning submittals:
1. Provide Manufacturer's Certificate of Source Testing.
2. Provide Manufacturer's Certificate of Installation and Functionality
Compliance.
March 2021 - DRAFT 43 11 33-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_1133(IDS50) Page 845
Item#18.
1.05 ENVIRONMENTAL CONDITIONS
A. Blower shall be suitable for continuous service and outdoor installation.
B. Blower shall be suitable for continuous service at the elevation and other conditions
associated with the facility location: Meridian, ID.
1.06 WARRANTY
A. Provide warranty as specified in Section 01_78_36. All blower equipment supplied
shall be covered by a warranty of 24 months from date of commissioning.
PART PRODUCTS
2.01 AERATION BLOWERS
A. Manufacturers: One of the following or equal:
1. Aerzen Generation 5 Delta Hybrid Rotary Lobe Compressor D10S, or equal.
B. Regardless of manufacturer, the package will be produced by the manufacturer of
the blower stage, to ensure single source responsibility for blower performance and
compatibility of associated accessories. Packagers not permitted to bid.
C. The equipment shall be designed, constructed and installed in accordance with the
best practices and methods and shall operate satisfactorily when installed as shown
on the Drawings.
2.02 MATERIALS
A. General:
1. Aeration blower assembly: Complete with blower, drive, inlet and discharge
silencers, valves, and appurtenances.
2. Blower rating: As specified above.
3. Rotation direction of blower shall match requirements of piping.
B. Blower and drive:
1. General:
a. Blower shall deliver oil-free air.
b. Blower and motor mounting: On common base.
c. Lifting provisions: Lifting eyes on blowers, motors, and base so each
major component or entire unit can be lifted.
d. Piping connections: 125 pound class flanges in accordance with
ASME B16.1.
2. Type: Positive displacement rotary blowers using 2 impellers to pressurize a
trapped volume of air at a controlled rate prior to exposing it to a discharge
pressure.
3. Casing and head plates:
a. Blower casing: 1 piece with separate head plates and end covers.
b. Casing and head plates: Made of close-grained, machined cast iron.
c. End covers and head plates: Reinforced with bosses at penetrations with
cast, machined support feet.
March 2021 - DRAFT 43 11 33-4 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_11_33(IDS50) Page 846
Item#18.
4. Impellers:
a. Material: Ductile iron or cast iron.
b. Design: Straight, 3-lobe, involute type.
c. Balance: Dynamically, by removing metal from impeller body.
d. Operation: Free of rubbing without need for liquid seals or lubrication.
e. Timing: positively by a pair of accurately machined, heat-treated, alloy
steel timing gears.
f. Shafts: Alloy steel forgings, pressed into each end of each impeller and
pinned.
g. Impeller assembly support: Anti-friction type bearings, sized for a
minimum ABMA 9 and 11 L10 life for bearings of 85,000 hours.
5. Lubrication:
a. Positive oil seal: Provided at each bearing.
b. Seal design: Capable of preventing lubricant from leaking into air stream.
c. Vent provisions: Capable of venting impeller side of oil seal to atmosphere
while eliminating possible carryover of lubricant into air stream.
d. Drive-end bearings: Grease or oil lubricated.
e. Timing gears and gear-end bearings: Splash oil lubricated.
f. Blower's shipment: With openings sealed after injection of rust inhibitor.
2.03 APPURTENANCES
A. Inlet filter shall have front access for filter element access. Filter shall provide
99 percent removed efficiency of 5-micron particle size and larger.
B. Inlet Filter/ Silencer:
1. Each package shall be supplied with one combination inlet filter silencer.
2. The inlet filter silencer shall be mounted directly to the inlet flange of the
blower.
3. The filter media efficiency must meet the requirements of ASHRAE 52.2
MERV7 50-70 percent @3-10 microns corresponding to EN779 G4.
4. The silencer portion shall be located upstream of the inlet filter.
5. Filter and silencer performance losses shall be included in the blower
performance calculation.
6. The filter element shall be designed to trap dirt on the inside so that upon
changing, dirt does not fall into the machinery. Filters where dirt accumulates
on the external surface of the filter will not be permitted.
C. Base Frame / Discharge Silencer:
1. Each package shall be supplied with one combination base frame/discharge
silencer.
2. The silencer shall be a chamber type design for maximum sound attenuation
and shall not use fibrous or absorption materials of any kind. Internal
absorption material has been shown to degrade and internally foul diffusers
and will not be permitted.
3. The silencer shall be fabricated of a single shell of pressure vessel quality
steel with continuous welds.
4. The silencer shall be subject to a pressure test for tightness and strength at a
minimum of 1.65 times the maximum blower operating pressure.
5. The silencer shall have a machined inlet connection where the discharge
flange of the blower stage bolts directly to, with no intermediary pieces.
March 2021 - DRAFT 43 11 33-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_1133(IDS50) Page 847
Item#18.
Threaded connection between the compressor stage and the discharge
silencer is subject to leakage and misalignment and will not be permitted.
6. Discharge silencer performance losses shall be included by the blower vendor
in the blower performance calculation.
7. The base frame shall be constructed from welded carbon steel or cast iron that
shall be designed to maintain alignment of the blower internal components and
the drive during operation.
8. The base frame shall be designed to resist distortion while being installed on
vibration isolating mounts.
9. The blower manufacturer shall supply a stainless steel grounding lug fully
welded to the base.
D. Acoustic enclosure:
1. Galvanized sheet-metal sandwich construction.
2. With noise attenuating walls and with ventilation openings ported, ducted,
shielded, and lined with acoustic absorptive material as required to achieve
specified noise levels.
3. Design criteria:
a. As specified in Section 01_81_01.
4. Raintight and dusttight, suitable for outdoor unprotected installation (due to
potential for spray water caused by washdown of other equipment within
facility).
5. With ventilation system designed for not more than 15 degrees Fahrenheit air
temperature rise with aeration blower operating at maximum load.
6. With fan interlocked with blower motor to start when blower starts and to stop
with an adjustable time delay after the blower motor stops.
7. With a weather-protected ventilation air intake filter:
a. Of disposable, dry type, pleated lofted cotton and polyester fiber media
construction, securely bonded to a welded galvanized wire backing, with a
frame of heavy-duty paperboard.
b. Sized for not more than 400 feet per minute face velocity.
c. With ASHRAE Standard 52.1 cleaning efficiency of not less than
25 percent.
d. With thickness not less than 1 inches.
e. With an easily visible and resettable "replace filter" indicator with retained
indication independent of blower on/off status.
8. With removable access panels located for maintenance and inspection access
to the housed equipment, each weighing not more than 40 pounds, or hinged if
weight exceeds 40 pounds.
E. Relief valve: High-capacity, full-nozzle type; 2 inch minimum valve inlet:
1. Manufacturers: The following or equal:
a. Kunkle Valve Co.
F. Check valves:
1. Each package shall be supplied with one check valve that shall be installed on
the discharge line.
2. The check valve shall be of the full-bore low pressure-drop, flapper type
design with a steel body, and steel flap embedded in Silicone with full-contact
seal.
March 2021 - DRAFT 43 11 33-6 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_11_33(IDS50) Page 848
Item#18.
3. The valve shall be removable without disturbing the piping. Pressure losses
produced by the check valve shall be included in the blower performance
calculation.
4. Consisting of following components:
a. Valve body: ASTM A126 cast iron.
b. Disc: ASTM B148-9A, aluminum bronze.
c. Spring: ASTM A276, Type 316 stainless steel.
d. Pins and thrust bearings: ASTM A276 Type 316, stainless steel.
e. Seals, rated for minimum 350 degrees Fahrenheit.
G. Pressure gauges:
1. As specified in Section 40_73_13.
H. Switches:
1. High discharge air temperature switch:
a. With thermowell, suitable for mounting in discharge piping.
b. Adjustable over range of 80 to 300 degrees Fahrenheit or as
recommended by blower manufacturer. Initial setting as recommended by
blower manufacturer.
c. With local indication of temperature.
d. Activation shuts down unit and activates an alarm condition.
2.
I. Other safety devices and controls: As recommended by blower manufacturer.
J. Rubber expansion joints:
1. Provided at discharge flanges of blowers.
2. Suitable for pressures up to 25 pounds per square inch gauge and
temperature up to 392 degrees Fahrenheit.
3. At discharge joints, provided with control rods to restrict axial pipe movement.
4. Manufacturers: The following or equal:
a. General Rubber.
K. Discharge piping and silencer insulation: Insulation inside acoustic enclosure by
blower manufacturer.
L. Supports and bracing: As required to support blower, associated equipment, and
piping, and to prevent excessive or harmful vibration or movement of equipment or
piping.
2.04 CONTROLS
A. Manufacturer shall provide local control panel:
1. Panel shall include emergency stop switch and applicable relays/switches for
high discharge and motor temperature.
B. Mounting position of emergency stop and temperature switches: As recommended
by manufacturer of sensing equipment to provide maximum protection.
2.05 SPARE PARTS AND SPECIAL TOOLS
A. Spare parts: Provide the following:
1. 4 complete sets of ventilation and air intake filters.
March 2021 - DRAFT 43 11 33-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_1133(IDS50) Page 849
Item#18.
2. 2 sets of drive belts:
a. Spare parts shall be properly bound and labeled for easy identification
without opening the packaging.
B. Special tools: Provide the following:
1. 1 set of special tools with equipment when required for normal operation and
maintenance.
PART 3 EXECUTION
3.01 DELIVERY, STORAGE AND HANDLING
A. All equipment shall be completely factory assembled, skid mounted, crated and
delivered to protect against damage during shipment.
B. All exposed flanges shall be covered and sealed with shrink-wrap to prevent the
entrance of moisture. Finished iron or steel surfaces not painted shall be properly
protected to prevent rust and corrosion.
C. All equipment delivered to the site shall be stored as specified in accordance with
the manufacturer's instructions.
3.02 INSTALLATION
A. Install adequate supports and bracing to support blower, associated equipment, and
piping, and to prevent excessive or harmful vibration or movement of equipment or
piping resulting from operation of the system.
B. Mount blower on base plate: Properly align and grout base plate as required for
blower and base for electric motor with sliding rails.
C. Secure silencers with hold-down bolts.
3.03 COMMISSIONING
A. As specified in Sections 01_75_17, 46_05_94, and this Section.
B. Manufacturer services:
1. Provide certificates:
a. Manufacturer's Certificate of Source Testing.
b. Manufacturer's Certificate of Installation and Functionality Compliance.
2. Manufacturer's Representative onsite requirements:
a. Installation and Functional Testing: 1 trip, 1-day minimum.
b. The functional test shall consist of 4 hours of operation of each blower
with vibration, temperature, noise, and pressure readings as well as motor
amp readings taken and recorded at 60-minute intervals.
c. Electrical and Controls: Conduct testing as specified in Section 40_80_01.
3. Training:
a. The Manufacturer shall provide operations and maintenance training to
the plant personnel. The training shall consist of 1 hour of classroom
training using the Operation and Maintenance Manual for reference and
2 hours of hands on training at the blower package.
March 2021 - DRAFT 43 11 33-8 1170OA10
pwa/CarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_11_33(IDS50) Page 850
Item#18.
4. Process operational period:
a. As required by Owner or Contractor.
C. Source testing:
1. Each blower stage shall be factory tested in accordance with ISO 1217
performance test to verify flow and brake horsepower at blower maximum
conditions. A slip test shall not be acceptable, nor is average data for the
manufactured size.
2. The acceptance criteria are +5% tolerance on power and -5% tolerance on
flow regardless of the size of the machine.
3. Blower:
a. Test witnessing: Not witnessed.
b. Conduct Level 1 General Equipment Performance Test.
c. Conduct Level 1 Vibration Test.
d. Conduct Level 1 Noise Test.
4. Electrical and Controls:
a. Conduct testing as specified in Section 40_80_01.
END OF SECTION
March 2021 - DRAFT 43 11 33-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_1133(IDS50) Page 851
Item#18.
SECTION 43_23_57.10
PROGRESSING CAVITY PUMPS
1.01 GENERAL
1.02 SUMMARY
A. Section includes: Rotary, positive displacement, Moineau principal, single screw,
progressing cavity type pumps with drivers, and specified components.
B. Tag numbers: As specified in Pump Schedule.
1.03 REFERENCES
A. American Bearing Manufacturers' Association (ABMA):
1. 9 - Load Ratings and Fatigue Life for Ball Bearings.
2. 11 - Load Ratings and Fatigue Life for Roller Bearings.
B. American Gear Manufacturers Association (ALMA).
C. American Society of Mechanical Engineers (ASME):
1. B16.1 - Gray Iron Pipe Flanges and Flanged Fittings, Class 25, 125, and 250.
2. B16.5 - Pipe Flanges and Flanged Fittings: NPS 1/2 through 24.
D. ASTM International (ASTM):
1. A48 - Standard Specification for Gray Iron Castings.
2. A276 - Standard Specification for Stainless Steel Bars and Shapes.
3. A283 - Specification for Low and Intermediate Tensile Strength Carbon Steel
Plates.
4. A681 - Standard Specification for Tool Steels Alloy.
5. D2240 - Standard Test Method for Rubber Property—Durometer Hardness.
E. Hydraulic Institute (HI):
1. 3.1-3.5 - Rotary Pumps for Nomenclature, Definitions, Application and
Operation.
2. 3.6 - Rotary Pump Tests.
3. 9.1-9.5 - Pumps - General Guidelines for Types, Definitions, Application,
Sound Measurement and Decontamination.
F. National Electrical Manufacturers Association (NEMA).
1.04 DEFINITIONS
A. Pump head (total dynamic head, TDH), flow capacity, pump efficiency, net positive
suction head available (NPSHa), and net positive suction head required (NPSHr):
As defined in HI 3.1-3.5, 3.6, and 9.1-9.5 and as modified in the Specifications.
B. Suction head: Gauge pressure available at pump intake flange or bell in feet of fluid
above atmospheric; average when using multiple suction pressure taps, regardless
of variation in individual taps.
March 2021 - DRAFT 43 23 57.10-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_23_57.10(IDS50) Page 853
Item#18.
1.05 SYSTEM DESCRIPTION
A. Pump type and components:
1. Rotary, positive displacement, Moineau principle, single screw, progressing
cavity type pumps with components.
2. System includes pump, motor or other driver, drive arrangements, seals or
packing, couplings, base plates, guards, supports, anchor bolts, necessary
valves, gauges, taps, lifting eyes, stands, and other items as required for a
complete and operational system.
B. Design requirements:
1. Pump performance characteristics:
a. As specified in the Pump Schedule.
b. Performance tolerances shall be the same as the test tolerances specified
in Section 46 05_94 - Mechanical Equipment Testing.
2. Motor characteristics: As specified in the Pump Schedule.
C. Product requirements as specified in Section 01_60_00 - Product Requirements
and Section 46_05_10 - Common Work Results for Mechanical Equipment.
1.06 SUBMITTALS
A. Submit as specified in Section 01_33_00 - Submittal Procedures.
B. Product data: As specified in Section 46_05_10 - Common Work Results for
Mechanical Equipment:
1. Submit seal water pressure and flow requirements.
C. Shop drawings: As specified in Section 46_05_10 - Common Work Results for
Mechanical Equipment.
D. Calculations: As specified in Section 46_05_10 - Common Work Results for
Mechanical Equipment:
1. Torsional analysis: When scheduled submit as specified in Section 46_05_10 -
Common Work Results for Mechanical Equipment.
E. Vendor operation and maintenance manuals: As specified in Section 01_78_23 -
Operation and Maintenance Data.
F. Commissioning submittals:
1. Provide Manufacturer's Certificate of Source Testing as specified in
Section 01_75_17 - Commissioning.
2. Provide Manufacturer's Certificate of Installation and Functionality Compliance
as specified in Section 01_75_17 - Commissioning.
1.07 WARRANTY
A. As specified in Section 01_78_36 - Warranties and Bonds.
March 2021 - DRAFT 43 23 57.10-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_23_57.10(IDS50) Page 854
Item#18.
PART PRODUCTS
2.01 MANUFACTURERS
A. Pumps: The following, no equal:
1. Netzsch, Inc., Model Series NM.
B. Pumps: One of the following or equal (alternate quotation):
1. Seepex, BN Series.
2. Moyno Industrial Products Division of Robbins & Meyers, Inc., Model Series
EZ Strip.
2.02 MATERIALS
A. General: Materials in the Pump Schedule shall be the type and grade as specified in
this Section.
B. Cast iron: ASTM A48, Class 30 minimum.
C. Buna-N: Synthetic rubber with a minimum Durometer hardness of 70 in accordance
with ASTM D2240 test methods.
D. Tool steel: ASTM A681, with 0.020 inch minimum chrome plating thickness
oversized and finish to Rockwell hardness of not less than C60.
E. Stainless steel: ASTM A276, Type as scheduled.
F. Structural steel: ASTM A283, Grade D.
2.03 PUMP CASINGS
A. Construction: Material as scheduled of sufficient strength, weight, and thickness to
provide accurate alignment, and prevent excessive deflection.
B. Housing cover plates: 2-piece split case housing over stator for access to rotor and
shaft ends without otherwise dismantling the pump.
C. Design Working Pressure: Not less than the maximum of 1.25 the Rated Design
Point head or 1.1 times the maximum discharge pressure at the maximum
revolutions per minute in vendor published information for the specified model.
D. Hydrostatic test: 5-minute hydrostatic test minimum 1.5 times Design Working
Pressure.
E. Suction and discharge piping connections: Flanged in accordance with
ASME 1316.1, Class 125, or ASME 1316.5, Class 150; provide higher pressure class
as required to meet Design Working Pressure.
F. Vent and taps: Provide casings with both 3/4 inch National Pipe Thread high point
vent and low point drain taps.
March 2021 - DRAFT 43 23 57.10-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_23_57.10(IDS50) Page 855
Item#18.
2.04 STATOR AND ROTOR
A. Stages: As scheduled.
B. Materials: As scheduled.
C. Stator removal: Removable for maintenance replacement.
D. Rotation: Clockwise looking from driver, unless otherwise indicated on the
Drawings.
E. Balance: As specified in Section 46_05_10 - Common Work Results for Mechanical
Equipment to meet the vibration criteria as specified in Section 46_05_94 -
Mechanical Equipment Testing.
2.05 DRIVE SHAFTS
A. Type: Solid shaft, rigidly connected to the rotor through a connecting rod and
grease lubricated, gear type U-joint:
1. Pin shaft joints or flexible shafts are not acceptable for other pumps.
2. Shaft turned and polished.
B. Material: As scheduled.
C. Strength: Able to withstand minimum 1.5 times maximum operating torque and
other loads, and of ample strength and stiffness to operate without distortion or
vibration which may reduce pump life at normal speeds as shown in the
manufacturer's literature.
D. Resonant frequency: As specified in Sections 46_05_10 - Common Work Results
for Mechanical Equipment and 46_05_94 - Mechanical Equipment Testing.
E. Shaft connecting rod: Design to limit operating angle to within 1-degree angular
deflection.
F. Shaft connecting rod: Design to limit operating angle to within 1-degree angular
deflection.
2.06 BEARINGS AND BEARING FRAME
A. Materials:
1. Pump bearing frame: As scheduled.
B. Bearing type: Mount shaft in 2 sets of antifriction tapered roller bearings or radial
ball bearings meeting ABMA standards and adequate to withstand radial or axial
thrust forces and complying with following:
1. Inboard set: Single.
2. Outboard set: Dual.
3. Shaft expansion: Make provisions in shaft and bearing mounting to prevent
distortion of shaft due to temperature expansion.
March 2021 - DRAFT 43 23 57.10-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_23_57.10(IDS50) Page 856
Item#18.
C. Bearing lubrication: Grease with external grease fittings or sealed for life:
1. Size sufficiently to safely absorb heat energy normally generated in bearing
under maximum ambient temperature of 60 degrees Celsius.
2. Equip with grease relief pipe, if externally greased.
D. Bearing life: Minimum L10 life of 100,000 hours at rated design point but not less
than 24,000 hours in accordance with ABMA 9 or 11 at bearing design load
imposed by pump shutoff with maximum sized impeller at rated speed.
2.07 SHAFT STUFFING BOX
A. Size: As specified in Section 46_05_10 - Common Work Results for Mechanical
Equipment.
B. Materials: Same as pump casing.
C. Shaft seal type: As scheduled and as specified in Section 46_05_10 - Common
Work Results for Mechanical Equipment.
D. Drain size: Minimum 3/4 inch, with drain line routed to nearest equipment floor
drain.
2.08 COUPLINGS
A. Types: When driver or gear coupled to pump, provide flexible coupling as specified
in Section 46_05_10 - Common Work Results for Mechanical Equipment.
B. Flexible coupling life: Infinite at up to 0.30-degree misalignment angle total or per
disk for disk type at maximum operating loads.
C. Design coupling to withstand a minimum of 1.5 times the maximum operating torque
and other imposed loads.
2.09 SUPPORTS, PEDESTALS, AND BASEPLATES
A. Type: Single piece base plate with drive arrangement as scheduled and as
specified in Section 46_05_10 - Common Work Results for Mechanical Equipment.
B. Materials: Structural steel, hot-dip galvanized after fabrication and coated per
manufacturer recommendation.
C. Pump and driver support strength: Able to withstand minimum 1.5 times maximum
imposed operating loads or imposed seismic loads, whichever is greater.
D. Configuration: Allow easy access to stuffing boxes, bearing frames, suction housing
and couplings; suction flange at least 2 inches above pump foundation; factory
mount pump and driver to baseplate.
E. Motor arrangement:
1. For overhead, piggyback or side motor arrangements: Provide motor base with
slide rails to allow for adequate belt and alignment adjustment of pump and
motor.
March 2021 - DRAFT 43 23 57.10-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_23_57.10(IDS50) Page 857
Item#18.
2. When in-line motor arrangement scheduled:
a. Motor centerline to coincide with pump centerline.
b. Provide gearbox as needed to provide specified pump speed.
3. When piggyback or overhead motor arrangement scheduled:
a. Support motor directly above pump centerline.
b. Mount motor minimum of 6 inches above top of pump on structural frame.
4. When side-mounted motor arrangement scheduled:
a. Mount side-mounted motors adjacent to pump, secured directly to
baseplates.
b. Provide side-mounted motors "left-handed" or right-handed" as indicated
on the Drawings.
F. Anchor bolts: Provide post-installed anchors, per manufacturer's sizing and
recommendation.
2.10 SPEED REDUCERS
A. Gear reducers (when scheduled or required for a pump in this Section):
1. Provide with NEMA C face connection between motor and gearbox.
2. Provide helical reduction gears, rated for AGMA Class 11 service with a
1.5 service factor.
3. Provide oil bath lubricated.
4. As specified in Section 46_05_10 - Common Work Results for Mechanical
Equipment.
B. V-belt drives (when scheduled or required for a pump in this Section):
1. Design to transfer torque of installed driver.
2. Limit speed reduction ratio to 5 to 1.
3. As specified in Section 46_05_10 - Common Work Results for Mechanical
Equipment.
2.11 EQUIPMENT GUARDS
A. Provide equipment safety guards as specified in Section 46_05_10 - Common Work
Results for Mechanical Equipment.
2.12 DRIVERS
A. Horsepower:
1. As scheduled.
2. Listed driver horsepower is the minimum to be supplied.
a. Increase driver horsepower if required to prevent driver overload while
operating at any point of the supplied pump operating head-flow curve
including runout.
b. When scheduled driver is a motor, increase motor horsepower if required
to prevent operation in the service factor.
c. Make all structural, mechanical, and electrical changes required to
accommodate increased horsepower.
B. Motors: Provide motors as specified in Section 26_05_09 - Low Voltage Motors up
to 500 Horsepower and as specified in this Section:
1. Revolutions per minute: As scheduled:
2. Enclosure: As scheduled.
March 2021 - DRAFT 43 23 57.10-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/1170OA10/Specifications/Pre-Purchase/43_23_57.10(IDS50) Page 858
Item#18.
3. Electrical characteristics: As scheduled.
4. Efficiency, service factor, insulation, and other motor characteristics: As
specified in Section 26_05_09 - Low Voltage Motors up to 500 Horsepower.
5. Motor accessories: As specified in Section 26_05_09 - Low Voltage Motors up
to 500 Horsepower and in this Section.
6. Coordinate motors with the variable frequency drive manufacturer to ensure
compatibility between the motor and variable frequency drive:
a. Coordinate pump starting torque requirements to ensure supplied variable
frequency drive provides sufficient starting torque capacity for all
operational conditions, including after extended shutdown periods while in
service pumping process fluids and sludge.
C. Other drivers: As scheduled and as specified in sections listed in the Schedule.
2.13 PUMP ACCESSORIES
A. Provide stator run dry protection for all supplied pumps:
1. Run dry protection shall be provided for the pump stator through the
measurement of temperature at the stator/rotor interface. The temperature run
dry protection shall shut down the pump upon high temperature before stator
damage occurs.
2. As part of the run dry protection package, provide thermistor, thermowell
drilled and tapped into pump stator, explosion proof connection head, and in
relay controller type that can be housed in pump controller.
a. Connection head shall be aluminum.
b. Controller shall display indicating stator temperature and alarm setpoint.
c. Controller shall include fault output for remote monitoring.
d. Controller shall be mounted within NEMA 4X LCP located near pump.
1) LCP shall be provided by Contractor.
3. Provide relay to allow annunciation of a high stator temperature (fail) alarm if
the temperature reaches an adjustable preset temperature. Setpoint for alarm
condition shall be set in the field per Manufacturer's recommendations.
4. Electrical characteristic: 120 volts, single-phase, 60 hertz.
2.14 SPARE PARTS AND SPECIAL TOOLS
A. Spare parts:
1. Pump thrust bearing set.
2. Pump radial bearing set.
3. Stators: 1 every type.
4. Shaft coupling or U-joint: 1 every size and type.
5. Pump rotor: 1 every type.
B. Special tools: Deliver 1 set for each furnished pump type and size needed to
assemble and disassemble pump system.
PART 3 EXECUTION
3.01 COMMISSIONING
A. As specified in Section 01_75_17 - Commissioning and this Section.
March 2021 - DRAFT 43 23 57.10-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_23_57.10(IDS50) Page 859
Item#18.
B. Manufacturer services:
1. Provide certificates:
a. Manufacturer's Certificate of Source Testing.
b. Manufacturer's Certificate of Installation and Functionality Compliance.
2. Manufacturer's Representative onsite requirements:
a. Installation: 1 trip, 1-day minimum.
b. Functional Testing: 1 trips, 1-day minimum each.
3. Training:
a. Maintenance: 4 hours per session, 2 sessions.
b. Operation: 2 hours per session, 2 sessions.
4. Process operational period:
a. As required by Owner or Contractor.
C. Source testing: As specified in Pump Schedule.
D. Functional testing: As specified in Pump Schedule.
3.02 PUMP SCHEDULE
PMP-001,
Tag Numbers PMP-002
General Characteristics
Service Struvite and
Anaerobic Digested
Sludge
Quantity 2
Minimum Pumped Fluid Temperature, degrees Fahrenheit 40
Normal Pumped Fluid Temperature, degrees Fahrenheit 80
Maximum Pumped Fluid Temperature, degrees Fahrenheit 95
Fluid Viscosity, Maximum Centipoise -
Fluid Viscosity, Minimum Centipoise -
Pump Characteristics
Number of Rotor Sealing Stages 1
Bearing Lubrication Grease or Sealed
Shaft Seal Type Gland Packing
Coupling Type Spacer
Speed Control Fixed
Maximum Pump revolutions per minute 175
Minimum Pump revolutions per minute 35
Rated Design Point (At Maximum Revolutions per Minute):
Flow, gallons per minute 100
Head, feet 40
March 2021 - DRAFT 43 23 57.10-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_23_57.10(IDS50) Page 860
Item#18.
PMP-001,
Tag Numbers PMP-002
Other Conditions:
Maximum NPSHr at Every Specified Flow, feet 13
Minimum NPSHa at Every Specified Flow, feet 23
Minimum Suction Static Head, feet 2
Maximum Suction Static Head, feet 40
Pump Materials
Pump Casing Cast Iron
Stator Buna-N
Rotor 316 SST
Shaft 316 SST
Pump Bearing Frame Cast Iron
Driver Characteristics
Driver Type Motor
Drive Arrangement Close Coupled
Non-reverse Ratchets None Required
Minimum Driver Horsepower
Maximum Driver Speed, revolutions per minute 1,800
Motor Characteristics (when motor is driver type)
Inverter Duty Rated No
Motor Voltage/Phases/Hertz 460/3/60
Enclosure Type TEFC
Source Testing
Test Witnessing Not Witnessed
Performance Test Level 1
Vibration Test Level 1
Noise Test Level 1
Functional Testing
Performance Test Level 1
Vibration Test Level None
Noise Test Level None
END OF SECTION
March 2021 - DRAFT 43 23 57.10-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_23_57.10(IDS50) Page 861
Item#18.
SECTION 43_33_20.01
LIQUID CHEMICAL DIAPHRAGM-TYPE METERING PUMPS
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Positive displacement, diaphragm metering pumps; accessories,
drives, and control panel requirements for pumping chemical solutions.
B. Tag numbers:
1. As specified in Pump Schedule.
1.02 REFERENCES
A. International Society of Automation (ISA):
1. ISA5.4 - Instrument Loop Diagrams.
B. National Electrical Code (NEC).
C. National Electrical Manufacturer's Association (NEMA):
1. 250 - Enclosures for Electrical Equipment (1000 V Maximum).
D. NSF International (NSF):
1. 61 - Drinking Water System Components - Health Effects.
1.03 DEFINITIONS
A. NEMA: Type 4X enclosure in accordance with NEMA 250.
1.04 SYSTEM DESCRIPTION
A. General: Provide mechanically actuated, positive displacement, diaphragm type
chemical metering pumps, accessories, and other items required for a complete and
operational system. Each chemical metering pump system shall include, but not be
limited to, the following items, which shall be supplied by the chemical metering
pump manufacturer:
1. Pumps.
2. Motors.
3. Electronic speed and manual stroke controllers.
4. Control panels.
5. Calibration columns.
6. Pulsation dampeners.
7. External pressure relief valves.
8. Diaphragm back pressure valves.
B. Fluid characteristics:
1. Magnesium Chloride:
a. Dry chemical formula: MgC12.
b. Solution concentration: 25 to 35 percent by weight.
March 2021 - DRAFT 43 33 0.0.01 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_33_20.01(IDS50)0) Page 863
Item#18.
c. Solution pH: 4 to 9.
d. Solution specific gravity: 1.24 to 1.34.
2. FLOFOAMTM DM:
a. Dry chemical formula: Polydimethylsiloxane (C2H6OSi)n.
b. Solution pH: 6 to 8 at 1% aqueous solution.
c. Solution specific gravity: 0.9 to 1.2.
C. Design requirements:
1. Pump:
a. Dry self-priming, capable of being run dry without damaging effects to
pump.
2. Motor characteristics:
a. As specified in this Section and in Section 26_05_09 - Low Voltage
Motors up to 500 Horsepower.
3. VFD characteristics: As specified in this Section.
4. Shafting and couplings: Design shafting and couplings to withstand a minimum
of 1.5 times the maximum operating torque or other imposed loads.
5. Supports:
a. Provide pump and driver supported on a common base.
b. Design anchor bolts to withstand a minimum of 1.5 times the maximum
imposed operating loads or 1.0 times the imposed seismic loads,
whichever is greater.
D. Performance requirements:
1. Systems shall deliver the pressures and volumes listed for their respective
services in the Pump Schedule.
E. Product requirements as specified in Section 01_60_00 - Product Requirements
and Section 46_05_10 - Common Work Results for Mechanical Equipment.
1.05 SUBMITTALS
A. Submit as specified in Section 01_33_00 - Submittal Procedures.
B. Product data: As specified in Section 46_05_10 - Common Work Results for
Mechanical Equipment:
1. Design data, test reports, certificates, manufacturer's instructions,
manufacturer's field reports:
a. Chemical feed pumps:
1) For each pump type, submit calibration charts and tables relating
flow rate to stroke length and stroke rate.
2) Submit hydraulic modeling results for each pumping system:
a) Confirm scheduled values or recommend new pressure
setpoints for the backpressure valves and pressure relief valves
listed in the Pump Schedule.
3) Submit calculations for each metering pump showing the suitability of
each pump for the suction and discharge conditions of each
application point:
a) Pump manufacturer shall recommend and size an accumulator
to be piped to the suction side of each metering pump, when
required based on calculations.
March 2021 - DRAFT 43 33 20.01-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_33_20.01(IDS50) Page 864
Item#18.
4) Submit calculations recommending dimensions of pulsation
dampener indicated on the Drawings.
C. Shop drawings: As specified in Section 46_05_10 - Common Work Results for
Mechanical Equipment:
1. Provide a list of parameters, ratings, or other characteristics where the
proposed chemical feed systems deviate from the requirements.
2. Dimensions, including anchor bolt layout, materials of construction, size,
weight, and performance data.
3. Drawings: Provide electrical and instrumentation drawings showing
coordination with electrical control devices operating in conjunction with the
associated feed system.
4. Dimensioned inlet and outlet connections.
5. Current NSF 61 Certification for components to be in contact with associated
chemical or potable water.
6. Provide data showing chemical compatibility and history of service with the
associated chemical for materials in the system.
7. Control panel views showing equipment arrangement, doors, equipment layout
inside the panel and dimensional information.
8. Internal interconnecting wiring diagrams showing terminal strips and external
devices connected to the panel as specified in Section 40_61_00 - Common
Work Results for Process Control and Instrumentation Systems.
9. Loop drawings for analog and discrete signals in accordance with ISA5.4.
10. Complete schematic and diagrams including terminal block and wire
identification numbers and device location symbols consistent with the
Contract Documents.
11. Panel bill of material with detailed description of components and equipment
data sheets.
12. Field cable numbers and terminations.
13. Manufacturer's Representative's qualifications as specified in
Section 01_75_17 - Commissioning.
14. Manufacturer's certificate stating that the materials of construction are
compatible with the pumped fluid.
15. Manufacturer's Certificate of Source Testing as specified in Section 01_75_17
- Commissioning.
16. Manufacturer's Certificate of Installation and Functionality Compliance as
specified in Section 01_75_17 - Commissioning.
17. Calibration curves for each pump relating stroke length and speed to flow rate
shall be supplied.
18. Capacity control shall be 0 to 100 percent with delivery repeatable within plus
or minus 1 percent accuracy over at least a 10 to 1 range.
19. Motor and VFD supplier shall carefully review the intended application of the
VFD and certify in writing that sizes provided are adequate for continuous or
intermittent operations (whichever is the most severe operating condition.
D. Calculations: As specified in Section 46_05_10 - Common Work Results for
Mechanical Equipment.
E. Vendor operation and maintenance manuals: As specified in Section 01_78_23
- Operation and Maintenance Data:
1. Provide information on each piece of equipment, including instrumentation.
March 2021 - DRAFT 43 33 0.0.01 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_33_20.01(IDS50)0) Page 865
Item#18.
2. Provide all safety considerations relating to operations and handling of the
associated chemical.
3. Maintenance data shall include all information and instructions required by
plant personnel to keep equipment properly cleaned, lubricated, and adjusted
so that it functions economically throughout its full design life.
4. Lubrication charts and tables of alternate lubricants.
5. Name, address, and phone number of manufacturer and manufacturer's local
service representative.
F. Commissioning submittals:
1. Provide Certificate of Source Testing as specified in Section 01_75_17
- Commissioning.
2. Provide Manufacturer's Certificate of Installation and Functionality Compliance
as specified in Section 01_75_17 - Commissioning.
1.06 WARRANTY
A. Provide warranty as specified in Section 01_78_36 -Warranties and Bonds.
1.07 DELIVERY, STORAGE AND HANDLING
A. Packing, shipping, handling and unloading:
1. Pack for shipping and outdoor storage at the project site for up to 6 months:
a. Apply temporary corrosion protective coatings to unpainted components
and pack components to protect from the elements.
2. Ship pump and drive completely assembled:
a. VFD shall be shipped unwired to the motor for field wiring.
PART PRODUCTS
2.01 GENERAL
A. A single pump manufacturer shall furnish and coordinate all drives and pump
components specified in this Section, including motors, gears, couplings, supports,
and other specified accessories and appurtenances to ensure compatibility and
integrity of the individual components.
B. The manufacturer of the pumps shall have sole-source responsibility for furnishing
the complete assemblies and meeting the specified performance requirements.
2.02 PUMPS
A. Equipment:
1. Pump:
a. Manufacturers: The following:
1) Prominent Fluid Controls, Inc.
2. Type: Simplex chemical proportioning pumps of the positive displacement
diaphragm type.
March 2021 - DRAFT 43 33 20.01-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_33_20.01(IDS50) Page 866
Item#18.
3. Materials:
a. The metering pumps and their components and accessories shall be
suitable for the following chemical concentrations, as scheduled in this
Section:
1) Magnesium chloride:
a) Wetted parts shall be suitable for use with 25 to 35 percent
magnesium chloride solution.
b) Other non-specified materials are to be manufacturer's standard
for continuous service with 25 to 35 percent magnesium chloride
solution.
b. Diaphragm materials:
1) Flat, composite, mechanically actuated diaphragms shall be VitonTM
EPDM or PTFE faced as pump manufacturer deems suitable for the
pumped liquid, fiber reinforced and bonded to an elastomeric support
with a Type 316 stainless steel backing plate.
c. Other parts in contact with pumped liquid: PTFE, PVC, or other suitable
thermoplastic.
4. Characteristics:
a. Diaphragm simplex chemical proportioning pumps of the positive
displacement, non-loss of motion or flat disc diaphragm type.
b. The diaphragm shall be mechanically actuated.
c. Liquid end:
1) Liquid end shall be sealed by means of an o-ring of material
compatible with the pumped liquid.
2) Liquid end of each metering pump shall be fitted with a system to
detect early stage diaphragm failure. Upon actuation, the leak
detector shall stop the pump, light a locally visible LED and sound a
remote alarm.
5. Components:
a. Electronic speed and manual stroke controllers.
b. Suction and discharge single check valves.
c. Built-in internal or external, adjustable pressure relief valve to relieve
pressure in the event of discharge line stoppage; which shall be factory
set to relieve at 50 pounds per square inch gauge.
d. Hydraulic make-up and air bleed valves.
6. Accessories: As indicated on the Drawings, pumps shall be equipped with:
a. Calibration column in suction piping.
b. Diaphragm backpressure, pulsation dampener, and pressure relief valve
in discharge piping.
7. Tests and inspections:
a. As scheduled in this Section.
8. Verification of performance.
2.03 PUMP GEARBOX DRIVE
A. Pump gearbox shall be constructed of steel and nodular iron and be water resistant
and suitable for outdoor installation:
1. Pump and gearbox housing shall be coated in high-solids epoxy.
B. Gearbox shall be oil bath lubricated.
C. All fasteners shall be Type 316 stainless steel.
March 2021 - DRAFT 43 33 0.0.01 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_33_20.01(IDS50)0) Page 867
Item#18.
2.04 DRIVE AND MOTOR
A. Type:
1. Each chemical metering pump shall be motor-driven through a flexible
coupling, or direct-connected to the pump when manufacturer's standard.
2. Pumps and motors shall be mounted on floor-mountable base plates.
a. Coupler:
1) Manufacturers: One of the following or equal:
a) Dodge, Para-flex.
b) Falk, Type WA.
B. Characteristics:
1. Electric motors shall be as specified in Section 26_05_09 - Low Voltage
Motors up to 500 Horsepower.
2. Motors and motor starters shall be furnished by the pump manufacturer and
shall be coordinated with the requirements of the pumps and the following
characteristics:
Horsepower (minimum) 1/2
Volts/phase/hertz 120/3160
Speed (maximum) 1,800 revolutions per minute
Service factor 1.15
Ambient temperature 50 degrees Centigrade
Maximum temperature rise 40 degrees Centigrade
Enclosure TEFC
Insulation Class B, moisture resistant, inverter duty
Bearings Tapered rollers
Fasteners Type 316 stainless steel
3. The motor shall be a permanent magnet type, having a 90 volt direct current
armature rating, and horsepower not less than the minimum specified rating.
4. Motor shall have a thermostat for high temperature shutdown.
5. The motor brushes shall have tinned leads.
2.05 CONTROLS
A. Provide chemical metering pump control indicated on the Drawings .
B. Each chemical metering pump shall be provided with an automatically controlled,
electronic speed controller to adjust the capacity from 0 to 100 percent while the
pump is operating:
1. Electronic speed controller shall operate with a power source of 120 volts, and
shall automatically control speed of the pump based on a 4-20 mA signal.
2. Electronic controller shall allow pump to be controlled remotely by a signal
originating from the PLC or by a manually controlled external stroke
adjustment wheel located on controller.
March 2021 - DRAFT 43 33 20.01-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_33_20.01(IDS50) Page 868
Item#18.
C. 3. Stroke controller shall include a digital stroke length indicator, calibrated from 0 to
100 percent. Each chemical metering pump shall be provided with a Hand-Off-
Automatic (H-O-A) selector switch:
1. Switch shall have 2 contacts, 1 to be closed in the "hand" position and 1 to be
closed in the "automatic" position.
2. A run-indicator light shall also be provided.
D. Motor starter shall be provided with normally open (dry) contact for remote "run"
indication.
E. Provide separate Local Control Panels (LCP)for the chemical feed systems. LCPs
shall include a single non-regulated 120 volt power source:
1. This power is drawn from the main plant power grid and is not filtered.
2. It is subject to random noise and voltage spikes, and voltage fluctuations of up
to plus or minus 15 percent.
3. The manufacturer shall furnish a complete LCP including, but not limited to,
the following:
a. NEMA Type 4X, Type 316 stainless steel, size as required.
b. Motor starters for each motor.
c. Stroke control drives as required.
d. Switches, push buttons, pilot lights and indicators as required for proper
pump control.
e. Contacts for analog and discrete inputs and outputs as indicated in the
P&ID drawings and Control Descriptions.
f. Instruments, control devices, and other devices as required to perform the
operations indicated in the Control Descriptions and indicated on the
Drawings.
F. Locate panel on or near the chemical metering pumps as indicated on the
Drawings.
2.06 ACCESSORIES
A. Pulsation dampeners:
1. Manufacturers: One of the following or equal:
a. Kemlon Products.
b. Blacoh Fluid Controls, Inc.
c. Pulsafeeder.
2. Pulsation dampeners shall be furnished and installed on each chemical
metering pump's discharge lines.
3. Materials:
a. Pulsation dampeners shall have Hypalon diaphragms and CPVC, PVC,
stainless steel or lined cast iron chamber:
1) Materials shall be compatible with the pumped liquid at the specified
concentration, and suitable for outdoor use and exposure.
4. Characteristics:
a. Pulsation dampeners shall be gas or air charged, single diaphragm type
complete with valved gas/air charge valve connection and pressure gage
graduated from 0 to 200 pounds per square inch.
b. Pulsation dampeners shall allow no more than 6 percent discharge
pressure fluctuation.
5. Dampeners shall be provided with a true-union ball valve for shutoff.
March 2021 - DRAFT 43 33 0.0.01 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_33_20.01(IDS50)0) Page 869
Item#18.
B. Calibration columns:
1. Materials:
a. Materials shall be compatible with the pumped liquid and concentration
specified in this Section, and suitable for outdoor use and exposure.
2. Characteristics:
a. Furnish and install calibration columns, 1 for each chemical metering
pump, on each chemical pump's inlet line as indicated on the Drawings
and specified in this Section:
1) Columns shall be translucent.
b. Provide top cap threaded connection with vent piped to floor to prevent
entry of foreign materials and to direct spillage or overflow.
c. End connections shall be threaded.
d. Capacities and graduations: 2,500 mL at 100 mL increments.
C. Diaphragm backpressure and pressure relief valves:
1. Manufacturers: One of the following or equal:
a. Wallace and Tiernan.
b. Pulsafeeder.
c. Griffco.
d. Milton Roy Co.
2. Materials:
a. Valves shall be of suitable materials for the pumped liquid.
3. Characteristics:
a. Ported to serve as either a backpressure valve or a pressure relief valve.
b. Relief valve shall be plumbed to the nearest chemical drain, or back to the
pump suction on the non-pump side of the pump suction isolation valve, to
avoid spillage.
c. Valves shall be furnished and installed on each chemical metering pump's
discharge lines.
d. Valves shall have an adjustable spring range of 15-50 pounds per square
inch. Valves shall be factory adjusted for the backpressure recommended
by the pump manufacturer.
e. Valves shall produce a back pressure no greater than 10 pounds per
square inch above valve set pressure when metering pumps are operating
at full capacity, pulsating flow.
D. Pressure relief valves:
1. Furnish and install pressure relief valves on each chemical metering pump's
discharge line as indicated on the Drawings.
2. Materials:
a. Wetted materials shall be compatible with the pumped liquid.
3. Characteristics:
a. Valves shall have an adjustable spring range of 25-175 pounds per
square inch. Valves shall be factory adjusted for the relief pressure
recommended by the pump manufacturer.
2.07 NAMEPLATES
A. Each pump, gearbox, and motor shall have, securely affixed in a conspicuous
location, a stainless steel nameplate with raised letters providing the manufacturer's
model, serial number, rating, range, speed and other pertinent data.
March 2021 - DRAFT 43 33 20.01-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_33_20.01(IDS50) Page 870
Item#18.
2.08 SPARE PARTS AND SPECIAL TOOLS
A. Spare parts: Furnish the following spare parts packed and labeled for warehouse
storage:
1. Complete set of inlet and outlet ball check valves (balls, seats and gaskets)
and a diaphragm for each pump.
2. 1 complete spare parts kit for each pump provided.
3. 1 spare parts kit for each size and type of backpressure and pressure relief
valve.
4. An initial supply of all oils, greases, and lubricants required to start operations.
Supply an amount of these materials equivalent to 1 year of continuous
operation for each system.
B. Special tools: Deliver 1 set for each furnished pump type and size needed to
assemble and disassemble pump system.
PART 3 EXECUTION
3.01 COMMISSIONING
A. As specified in Section 01_75_17 - Commissioning and this Section.
B. Manufacturer services:
1. Provide certificates:
a. Manufacturer's Certificate of Source Testing.
b. Manufacturer's Certificate of Installation and Functionality Compliance.
2. Manufacturer's Representative onsite requirements:
a. Installation: 1 trip, 2 day minimum.
b. Functional Testing: 1 trips, 2 day minimum each.
3. Training:
a. Operation and Maintenance: 4 hours per session, 2 sessions.
4. Process operational period:
a. As required by Owner or Contractor.
C. Source testing: As specified in Pump Schedule.
D. Functional testing: As specified in Pump Schedule.
3.02 SCHEDULES
A. Magnesium Chloride Pumps:
Tag Number SSPR1-PMP-0510, 0520
Feed Point Phosphorus Precipitation System Reactor
Service Magnesium Chloride
Pump Type Single Diaphragm
Number of Pumps 2
Named Manufacturer ProMinent
Torsional Analysis Not Required
March 2021 - DRAFT 43 33 0.0.01 1170
pwalCarollolDocumentslClientllDlMeridianl11700A101SpecificationslPre-Purchasel43_33_20.01(IDS50)0) Page 871
Item#18.
Tag Number SSPR1-PM P-0510, 0520
Pump Characteristics
Design Conditions:
Maximum Flow, (gallons per hour) 35
Minimum Flow, (gallons per hour) 4
Normal Flow, (gallons per hour) 10-20
Pump Stroke Length Controller Manual
Maximum Discharge Pressure (psig) 40
Minimum Suction Lift (feet) 10
Relief Valve Setting (psig) Per Mfg.
Pump Materials
Pump Housing/Enclosure Per Mfg.
Liquid End PTFE faced PVC or PVDF
Driver Characteristics
Driver Type Variable Speed Motor
Drive Coupling Close-coupled, Horizontal
Minimum Driver Horsepower 0.5
Maximum Driver Speed (rpm) 1,725
Service Factor 1.15
Voltage/Phases/Hertz 480/3/60
NEMA Enclosure Type TEFC, Severe Duty
Source Testing
Test Witnessing Not Witnessed
Performance Test Level 1
Vibration Test Level None
Noise Test Level None
Functional Testing
Performance Test Level 1
Vibration Test Level None
Noise Test Level None
1. Provide pumps that deliver the maximum capacity, listed in the above table,
when at full speed and maximum stroke length.
B. Flo-Foam Pumps:
March 2021 - DRAFT 43 33 20.01-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridianl11700A101Specifications/Pre-Purchasel43_33_20.01(IDS50) Page 872
Item#18.
Tag Number SSPR1-PM P-0610, 0620
Feed Point Phosphorus Precipitation System Reactor
Service Anti-foaming agent
Pump Type Single Diaphragm
Number of Pumps 2
Named Manufacturer ProMinent
Torsional Analysis Not Required
Pump Characteristics
Design Conditions:
Maximum Flow, (gallons per hour) Per Mfg.
Minimum Flow, (gallons per hour) Per Mfg.
Normal Flow, (gallons per hour) Per Mfg.
Pump Stroke Length Controller Manual
Maximum Discharge Pressure (psig) 40
Minimum Suction Lift (feet) 10
Relief Valve Setting (psig) Per Mfg.
Pump Materials
Pump Housing/Enclosure Per Mfg.
Liquid End PTFE faced PVC or PVDF
Driver Characteristics
Driver Type Variable Speed Motor
Drive Coupling Close-coupled, Horizontal
Minimum Driver Horsepower 0.5
Maximum Driver Speed (rpm) 1,725
Service Factor 1.15
Voltage/Phases/Hertz 480/3/60
NEMA Enclosure Type TEFC, Severe Duty
Source Testing
Test Witnessing Not Witnessed
Performance Test Level 1
Vibration Test Level None
Noise Test Level None
Functional Testing
Performance Test Level 1
March 202 - DRAFT 43 33 20.01 1170
pwalCarollolDocumentslClientllDlMeridianl11700A101SpecificationslPre-Purchasel43_33_20.01(IDS50)50) Page 873
Item#18.
Tag Number SSPR1-PMP-0610, 0620
Vibration Test Level None
Noise Test Level None
1. Provide pumps that deliver the maximum capacity, listed in the above table,
END OF SECTION
March 2021 - DRAFT 43 33 20.01-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_33_20.01(IDS50) Page 874
Item#18.
SECTION 43_41_43
POLYETHYLENE TANKS
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Type 1 and Type 2 polyethylene storage tanks. Type 1 tank shall
be made from crosslinked polyethylene resin and Type 2 shall be made from linear
(non-crosslinked) polyethylene resin. Tank shall be designed with double wall
containment.
B. Related sections:
1. Section 01_81_01 - Project Design Criteria.
1.02 REFERENCES
A. American Society for Mechanical Engineers (ASME):
1. B16.4 - Gray Iron Threaded Fittings.
2. B16.5 - Pipe Flanges and Flanged Fittings: NPS 1/2 through 24.
B. ASTM International (ASTM):
1. D638 - Standard Test Method for Tensile Properties of Plastics.
2. D790 - Standard Test Methods for Flexural Properties of Unreinforced and
Reinforced Plastics and Electrical Insulating Materials.
3. D1505 - Standard Test Method for Density of Plastics by the Density-Gradient
Technique.
4. D1525 - Standard Test Method for Vicat Softening Temperature of Plastics.
5. D1693 - Standard Test Method for Environmental Stress-Cracking of Ethylene
Plastics.
6. D1998 - Standard Specification for Polyethylene Upright Storage Tanks.
7. D2837 - Standard Test Method for Obtaining Hydrostatic Design Basis for
Thermoplastic Pipe Materials or Pressure Design Basis for Thermoplastic Pipe
Products.
C. National Fire Protection Association (NFPA):
1. 30 - Flammable and Combustible Liquid Code.
D. National Electrical Manufacturer's Association (NEMA).
E. Occupational Safety and Health Administration (OSHA):
1. 29 CRF Part 1910 - Occupational Safety and Health Standards.
1.03 DESIGN CRITERIA
A. Tanks: As scheduled.
B. Tank wall thickness: Calculated in accordance with ASTM D1998 using design
specific gravity as scheduled. Note that design specific gravity may be higher than
specific gravity of tank contents.
March 2021 - DRAFT 43 41 43-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_41_43(IDS50) Page 875
Item#18.
C. Design requirements:
1. The minimum required wall thickness of the cylindrical shell at any fluid level
shall be determined by the following equation, but shall not be less than
0.187 inches thick:
T = P x O.D./2 SD = 0.433 x S.G. x H x O.D./2 SD.
T = wall thickness, in.
SD = hydrostatic design stress, psi.
P = pressure (.433 x S.G. x H), psi.
H = fluid head, ft.
S.G. = specific gravity, g/cm^3.
O.D. = outside diameter, in.
D. The hydrostatic design stress shall be determined by multiplying the hydrostatic
design basis, determined by ASTM D2837 using rotationally molded samples, with
a service factor selected for the application:
1. The hydrostatic design stress is 600 pounds per square inch at 73 degrees
Fahrenheit for Type I and Type I I materials.
2. The tank shall have a stratiform (tapered wall thickness) wall.
E. The hydrostatic design stress shall be derated for service above 100 degrees
Fahrenheit and for mechanical loading of the tank.
F. The minimum design specific gravity shall be 1.5.
G. The minimum required wall thickness for the cylinder straight shell must be
sufficient to support its own weight in an upright position without any external
support:
1. Flat areas shall be provided to allow locating large fittings on the cylinder
straight shell.
H. The top head must be integrally molded with the cylinder shell:
1. The minimum thickness of the top head shall be equal to the top of the straight
wall.
2. The top head of tanks with 2,000 or more gallons of capacity shall be designed
to provide a minimum of 1,300 square inches of flat area for fitting locations.
1. Tanks with 2,000 or more gallons of capacity shall have a minimum of 3 lifting lugs
integrally molded into the top head:
1. The lifting lugs shall be designed to allow erection of an empty tank.
J. The tank shall be designed to provide a minimum of 4 tie-down lugs integrally
molded into the top head:
1. The tie-down lugs shall be designed to allow tank retention in wind and
seismic loading situations without tank damage.
K. Tank shell thickness:
1. In accordance with ASTM D1998, Section 6.1.
2. Design tank wall thickness for liquid with specific gravity as specified.
3. Provide adequate thickness at all fittings and connection points for mounting of
fittings to the tank without damage to the tank or causing excessive deflection.
4. Maximum allowable hoop stress used in tank wall thickness calculations per
ASTM D1998 shall be based on test data in accordance with ASTM D2837.
March 2021 - DRAFT 43 41 43-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_41_43(IDS50) Page 876
Item#18.
L. Restraint system:
1. Seismic load restraint system:
a. Seismic design criteria: As specified in Section 01_81_01.
2. Wind load restraint system:
a. Wind design criteria: As specified in Section 01_81_01.
b. If the wind load restraint system includes the use of cables, tensioning
and adjustment devices, such as turnbuckles, shall be used to allow for
easy adjustment of the cables at the time of construction and as required
in the future.
c. The tank shall be designed to provide a minimum of 4 tie-down lugs
integrally molded into the top head:
1) The tie-down lugs shall be designed to allow tank retention in wind
and seismic loading situations without tank damage.
d. The tie down system shall be designed to withstand wind loads specified
in Section 01 81 01:
1) Tie down systems must meet seismic zone requirements per
IBC code.
2) Any anchor bolts shall be provided by the customer per the
instructions and the base plates for the system.
1.04 SUBMITTALS
A. Fabrication drawings for each tank including:
1. Dimensions.
2. Tank wall thickness.
3. Materials of construction.
4. Tank fittings.
5. Tank appurtenances.
6. Tank restraint system.
7. Tank resin and hoop stress data.
B. Chemical compatibility sheet to include:
1. Chemical to be stored.
2. Percentage of chemical.
3. Temperature of chemical.
C. Engineering design calculations of restraint and anchoring system signed by a
registered civil or structural engineer.
D. Installation instructions.
E. Warranty.
F. Certification to certify that each tank is suitable for the specified chemical service,
no degradation within warranty period, including tank fittings and gasket material.
G. Proof of qualification: Provide lists of installation and contact information with same
type of application and chemical used.
H. Color charts for proposed coating systems.
March 2021 - DRAFT 43 41 43-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_41_43(IDS50) Page 877
Item#18.
1.05 WARRANTY
A. Manufacturer warranty against defects:
1. Tank: 5 years full warranty. Prorated warranties are not acceptable.
1.06 QUALITY ASSURANCE
A. Qualification of manufacturer: Manufacturer with experienced personnel, physical
facilities, and management capacity sufficient to produce custom-made rotationally
molded polyethylene tanks of the size, exposure, and chemical services specified
for minimum 5 years with satisfactory performance record.
PART PRODUCTS
2.01 SCOPE OF SUPPLIES
A. Provide all materials, labor, equipment, and hardware to provide all polyethylene
storage tanks with specified fittings and accessories, seismic and wind load restraint
systems, anchor bolts, and flange flexible connectors for complete installation in the
positions and orientations indicated on the Drawings.
2.02 MANUFACTURERS
A. One of the following or equal:
1. Poly Processing Co.
2. Snyder Industries, Inc.
2.03 TANK MATERIALS
A. Type 1 high-density crosslinked polyethylene (XLPE) or Type 2 high-density linear
polyethylene (HDLPE).
B. Resin:
1. Manufacturers: One of the following or equal:
a. PAXON, grade 7204 resin for crosslinkable polyethylene.
b. Exxon, 8660-8661 for high-density linear polyethylene.
C. The material used shall be virgin polyethylene resin as compounded and certified by
the manufacturer:
1. Type 1 tanks shall be made from crosslinked polyethylene resin as
manufactured by ExxonMobil Chemical, or resin of equal physical and
chemical properties.
2. Type II tanks shall be made from high-density linear polyethylene resin as
manufactured by ExxonMobil Chemical, or resin of equal physical and
chemical properties.
3. Resin choice would be based on the specific application, chemical to be stored
and concentration.
March 2021 - DRAFT 43 41 43-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_41_43(IDS50) Page 878
Item#18.
D. Ultra violet stabilizer:
1. The polyethylene resin material shall contain a minimum of a UV 8 stabilizer
as compounded by the resin manufacturer.
2. Pigments may be added but shall not exceed 0.25 percent (dry blended) of the
total weight.
E. Free of holes, blisters, crazing, cracking, delamination, undispersed raw materials,
and any sign of contamination from foreign matter:
1. The finished tank wall shall be free of visual defects such as foreign inclusions,
air bubbles, pinholes, pimples, crazing, cracking, and delaminations.
2. All cut edges where openings are cut into the tanks shall be trimmed smooth.
F. Resin shall meet or exceed the following properties:
1. Mechanical Properties of Type 1 of Tank Material: Current XLPE Resin:
Property ASTM Value
Density (Resin) D1505 0.938-0.946 g/cc
Tensile (Yield Stress 2"/min) D638 3,000 psi
Elongation at Break (2"/min.) D638 >300%
ESCR (100% Igepal, Cond. A, F50) D1693 >1000 hours
ESCR (10% Igepal, Cond. A, F50) D1693 >1000 hours
icat Softening Temperature, D1525 250
Flexural Modulus D790 100,000 psi
2. Mechanical Properties of Type II tank material: Current HDLPE Resin:
Property ASTM Value
Density (Resin) D1505 0.942-0.948 g/cc
Tensile (Yield Stress 2"/min) D638 2,950 psi
Elongation at Break (2"/min.) D638 >1,000%
ESCR (100% Igepal, Cond. A, F50) D1693 550 hours
ESCR (10% Igepal, Cond. A, F50) D1693 48 hours
icat Softening Temperature D1525 235
Flexural Modulus D790 129,000 psi
G. Gel test: This test does not apply to Type II linear resins:
1. Inner portion of tank wall:
a. Not less than 65 percent.
b. ASTM D1998 requirements.
2. Entire wall thickness: Not less than 80 percent.
March 2021 - DRAFT 43 41 43-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_41_43(IDS50) Page 879
Item#18.
H. Restraint system:
1. Metal components, including anchor bolts:
a. Type 316 stainless steel.
b. The Anchor bolts shall be supplied by the tank manufacturer.
c. The drawings and calculations for the seismic system shall be submitted
for review.
2. Concrete anchors or flush shells shall not be used.
2.04 FITTINGS
A. Terminate in socket, threaded, or flanged connections:
1. Flanges: 150 pound ASME B 16.5.
2. Threaded connections: ASME B 16.4.
B. Fittings at upper tank sidewall or top:
1. Compression threaded type, long shank, polyvinyl chloride flanged fittings with
deep cut threads (not injection molded thread) and with dual wide nuts.
2. The bulkhead fittings shall be constructed of PVC, PP, or other specified
material.
3. Gaskets shall be a minimum of 1/4 inch thickness and constructed of
40-50 durometer EPDM, 60-70 durometer Viton or other specified material.
C. Fittings on tank top:
1. Bosses molded into the tank.
2. Fittings shall be vertical.
3. The top head shall be integrally molded with the cylinder shell.
4. The minimum thickness of the top head shall be equal to the top of the straight
wall.
5. The top head of tanks with 2,000 or more gallons of capacity shall be designed
to provide a minimum of 1,300 square inches of flat area for fitting locations.
D. Flanged outlet drain fitting in the lower tank sidewall: Integrally molded into the
bottom knuckle of the tank to allow full drainage of tank contents.
E. Fittings and appurtenances for each tank:
1. 1 minimum 3-inch flanged inlet nozzle entering the tank in the top near the
wall.
2. 1 minimum 2-inch flanged outlet/drain nozzle, integrally molded with tank wall.
3. One 4-inch flanged overflow nozzle.
4. One 4-inch flanged roof nozzle for mounting of tank level sensor.
5. One 4-inch flanged roof nozzle for mounting of tank level switch.
6. One 4-inch flanged roof nozzle for mounting of tank leak detection.
7. One 6-inch flanged roof vent.
8. One 24-inch hinged type manway lid on top of the tank:
a. Manway shall be sealed and shall be constructed of the same material as
tank.
b. Hardware shall be 316 stainless steel.
c. The gaskets shall be per tank manufacturer recommendation for the
chemical stored.
March 2021 - DRAFT 43 41 43-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_41_43(IDS50) Page 880
Item#18.
2.05 ACCESSORIES
A. Tank insulation:
1. Not used
B. Tank electrical heat tracing:
1. Not Used
C. Ladder and platform:
1. Provide a galvanized steel or fiberglass reinforced plastic ladder and landing
platform for each storage tank for access to the top manway.
2. In accordance with OSHA standards.
3. Steel components: Hot-dip galvanized after fabrication.
4. Fasteners: Type 304 stainless steel.
5. Anchor bolts: Type 304 stainless steel.
6. Secure ladder to the tank using special stainless steel or Hastalloy bolts with
polyethylene encapsulated heads.
7. Support ladder directly on the concrete foundation and from the tank wall.
D. Tank vents:
1. Each tank shall be properly vented for the type of material and flow rates
expected.
2. Vents must comply with OSHA Part 1910 normal venting for atmospheric
tanks or other accepted standard, or shall be as large as the filling or
withdrawal connection, whichever is larger but in no case less than 2 inches
nominal inside diameter with screening.
2.06 TANK FABRICATION
A. Rotationally molded construction in accordance with ASTM D1998.
B. Provide for each tank the following shop finishing:
1. Shipping label identifying:
a. Tank tag number.
b. Chemical service.
2. Permanent labels:
a. Identification label.
b. NFPA label specifically coded for the tank contents in accordance with
NFPA 30.
c. Paint or affix label onto the tank wall to be clearly visible from outside the
tank enclosure.
2.07 TESTING
A. Each tank shall be leak tested by the manufacturer prior to shipment by filling with
clean water for a period of at least 4 hours with all fittings installed and blinded:
1. There shall be no measurable drop in liquid surface.
2. Any leaks shall be noted and repaired and the tank shall be re-tested for an
additional 4 hours minimum.
a. Reason for leak and method of repair shall be recorded and submitted to
the Engineer.
3. Any defects or leaks that have not been adequately repaired will be cause for
rejection of the tank.
March 2021 - DRAFT 43 41 43-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_41_43(IDS50) Page 881
Item#18.
PART 3 EXECUTION
3.01 INSTALLATION
A. General:
1. Transportation, handling, storage of the tanks, and installation shall be in
accordance with the manufacturer's printed instructions.
2. Repair any damage to tank components or the insulation due to transportation
or installation.
3. Install piping to tank with sufficient flexibility to allow tank movement of 1 inch
in any direction without damage to piping.
B. All tank fitting attachments shall be equipped with flexible couplers or other
movement provisions provided by the tank customer:
1. The tank will deflect based upon tank loading, chemical temperature and
storage time duration.
2. Tank piping flexible couplers shall be designed to allow 4 percent design
movement.
3. Movement shall be considered to occur both outward in tank radius and
downward in fitting elevation from the neutral tank fitting placement.
3.02 FIELD QUALITY CONTROL
A. Manufacturer's field service (1 day):
1. Inspect the installed tanks for proper installation.
2. Instruct Owner's personnel on operations and maintenance of the tanks.
3.03 SCHEDULE
A. Tank schedule as follows:
Tag Number Magnesium Chloride Storage Tank
Service Magnesium Chloride
at 30% solution
Chemical pH 4 - 9
Chemical 1.24 - 1.34
Specific Gravity
Tank Design Specific Gravity 1.5
Number of Tanks 1
Usable Capacity, each 10,000 gal
Type of Tank Type 2 - Linear HDPE
General Design Flat bottom, dished top,
double wall containment
Installation Vertical
Diameter (feet) 12
Height (feet 20 (max)
March 2021 - DRAFT 43 41 43-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/43_41_43(IDS50) Page 882
Item#18.
Tag Number Magnesium Chloride Storage Tank
External Inlet Nozzle Size - Ground 3
Supported (inches)
External Outlet/Drain Nozzle Size - Ground 2
Supported (inches)
Overflow Nozzle Size (inches) 4
Vent Nozzle Size (inches) 6
Roof Nozzle Size (inches) 4-inch nozzle for mounting
ultrasonic level sensor
Roof Nozzle Size (inches) 4-inch nozzle for mounting level switch
Roof Nozzle Size (inches) 4- inch nozzle for mounting
tank leak detection
Top Manway (inches) 24
Ladder Required
Lifting Lugs Required
Mechanical, float and cable style, plus radar-
style electronic level indicator for main tank
Level Indicator
High level switch for main tank and leak
detection for containment tank, per drawings
Pipe and Conduit Supports Required
END OF SECTION
March 2021 - DRAFT 43 41 43-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel43_41_43(IDS50) Page 883
Item#18.
SECTION 46_05_10
COMMON WORK RESULTS FOR MECHANICAL EQUIPMENT
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Basic design and performance requirements for mechanical
equipment.
B. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 01_60_00 - Product Requirements.
3. Section 01_75_17 - Commissioning.
4. Section 01 77 00 - Closeout Procedures.
5. Section 01_78_23 - Operating and Maintenance Data.
6. Section 01_81_01 - Project Design Criteria.
7. Section 03_60_00 - Grouting.
8. Section 05_05_24 - Mechanical Anchoring and Fastening to Concrete and
Masonry.
9. Section 05 12 00 - Structural Steel.
10. Section 05 14 05 - Structural Aluminum.
11. Section 09_96_01 - High-Performance Coatings.
12. Section 26_05_09 - Low Voltage Motors Up to 500 Horsepower.
13. Section 26_08_50 - Field Electrical Acceptance Tests.
14. Section 40_05_00.01 - Common Work Results for General Piping.
15. Section 40_05_06.55 - Piping Insulation.
16. Section 40_80_01 - Testing, Calibration, and Commissioning.
17. Section 46_05_94 - Mechanical Equipment Testing.
1.02 REFERENCES
A. American Gear Manufacturer's Association (ALMA) Standards:
1. 6001-E08 - Design and Selection of Components for Enclosed Gear Drives.
B. American Bearing Manufactures Association (ABMA) Standards:
1. 9 - Load Ratings and Fatigue Life for Ball Bearings.
2. 11 - Load Ratings and Fatigue Life for Roller Bearings.
C. American Petroleum Institute (API):
1. 682 - Shaft Sealing Systems for Centrifugal and Rotary Pumps.
D. ASTM International (ASTM):
1. A36 - Standard Specification for Carbon Structural Steel.
2. A48 - Standard Specification for Gray Iron Castings.
3. A125 - Standard Specification for Steel Springs, Helical, Heat-Treated.
4. A193 - Standard Specification for Alloy-Steel and Stainless Steel Bolting for
High Temperature or High Pressure Service and Other Special Purpose
Applications.
March 2021 - DRAFT 46 05 10-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 885
Item#18.
5. A194 - Standard Specification for Carbon and Alloy Steel Nuts for Bolts for
High Pressure or High Temperature Service, or Both.
6. A320 - Standard Specification for Alloy-Steel and Stainless Steel Bolting for
Low-Temperature Service.
7. A536 - Standard Specification for Ductile Iron Castings.
8. A653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or
Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.
9. B61 - Standard Specification for Steam or Valve Bronze Castings.
10. B62 - Standard specification for Composition Bronze or Ounce Metal Castings.
11. B505 - Standard Specification for Copper Alloy Continuous Castings.
12. B584 - Standard Specification for Copper Alloy Sand Castings for General
Applications.
13. F593 - Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and
Studs.
14. F594 - Standard Specification for Stainless Steel Nuts.
E. Hydraulic Institute (HI).
F. Occupational Safety and Health Administration (OSHA).
G. Unified Numbering System (UNS).
1.03 DEFINITIONS
A. Special tools: Tools that have been specifically made for use on unit of equipment
for assembly, disassembly, repair, or maintenance.
B. Resonant frequency: That frequency at which a small driving force produces an
ever-larger vibration if no dampening exists.
C. Rotational frequency: The revolutions per unit of time usually expressed as
revolutions per minute.
D. Critical frequency: Same as resonant frequency for the rotating elements or the
installed machine and base.
E. Peak vibration velocity: The root mean square average of the peak velocity of the
vibrational movement times the square root of 2 in inches per second.
F. Rotational speed: Same as rotational frequency.
G. Maximum excitation frequency: The excitation frequency with the highest vibration
velocity of several excitation frequencies that are a function of the design of a
particular machine.
H. Critical speed: Same as critical frequency.
I. Free field noise level: Noise measured without any reflective surfaces (an idealized
situation); sound pressure levels at 3 feet from the source unless specified
otherwise.
J. Operating weight: The weight of unit plus weight of fluids or solids normally
contained in unit during operation.
March 2021 - DRAFT 46 05 10-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 886
Item#18.
1.04 DESIGN REQUIREMENTS
A. General:
1. Product requirements as specified in Section 01_60_00.
2. Project conditions as specified in Section 01 81_01
3. Provisions specified under each technical equipment specification prevail over
and supersede conflicting provisions specified in this Section.
4. Equipment manufacturer's responsibility extends to selection and mounting of
gear drive units, motors or other prime movers, accessories, and auxiliaries
required for proper operation.
5. Vibration considerations:
a. Resonant frequency:
1) For single-speed equipment, ensure there are no natural resonant
frequencies within 25 percent above or below the operating rotational
frequencies or multiples of the operating rotational frequencies that
may be excited by the equipment design.
2) For variable-speed equipment, ensure there are no natural resonant
frequencies within 25 percent above or below the range of operating
frequencies.
b. Design, balance, and align equipment to meet the vibration criteria
specified in Section 460594.
6. Equipment units weighing 50 pounds or more: Provide with lifting lugs or eyes
to allow removal with hoist or other lifting device.
B. Power transmission systems:
1. V-belts, sheaves, shaft couplings, chains, sprockets, mechanical
variable-speed drives, variable frequency drives, gear reducers, open and
enclosed gearing, clutches, brakes, intermediate shafting, intermediate
bearings, and U-joints are to be rated for 24 hour-a-day continuous service or
frequent stops-and-starts intermittent service, whichever is most severe, and
sized with a service factor of 1.5 or greater in accordance with manufacturer
recommendations:
a. Apply service factor to nameplate horsepower and torque of prime source
of power and not to actual equipment loading.
b. Apply service factors in accordance with AGMA 6001-E08, other
applicable AGMA standards, or other applicable referenced standards.
C. Equipment mounting and anchoring:
1. Mount equipment on cast-iron or welded-steel bases with structural steel
support frames:
a. Utilize continuous welds to seal seams and contact edges between steel
members.
b. Grind welds smooth.
2. Provide bases and supports with machined support pads, dowels for alignment
of mating of adjacent items, adequate openings to facilitate grouting, and
openings for electrical conduits.
3. Provide jacking screws in bases and supports for equipment weighing over
1,000 pounds.
March 2021 - DRAFT 46 05 10-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 887
Item#18.
4. Design equipment anchorage, supports, and connections for dead load,
running loads, loads during start-up, seismic load specified in
Section 01_81_01, and other loads as required for proper operation of
equipment.
a. For equipment with an operating weight of 400 pounds or greater and all
equipment that is supported higher than 4 feet above the floor, provide
calculations for:
1) The operating weight and location of the centroid of mass for the
equipment.
2) Forces and overturning moments.
3) Shear and tension forces in equipment anchorages, supports, and
connections.
4) The design of equipment anchorage, supports, and connections
based on calculated shear and tension forces.
5. Anchorage of equipment to concrete or masonry:
a. Perform calculations and determine number, size, type, strength, and
location of anchor bolts or other connections.
b. Unless otherwise indicated on the Drawings, select and provide anchors
from the types specified in Section 05_05_24.
c. Provide bolt sleeves around cast-in anchor bolts for 400 pounds or greater
equipment:
1) Adjust bolts to final location and secure the sleeve.
6. Anchorage of equipment to metal supports:
a. Perform calculations and determine number, size, type, strength, and
location of bolts used to connect equipment to metal supports.
7. Unless otherwise indicated on the Drawings, install equipment supported on
concrete over non-shrink grout pads as specified in this Section.
1.05 SUBMITTALS
A. As specified in Section 01_33_00.
B. Product data:
1. For each item of equipment:
a. Design features.
b. Load capacities.
c. Efficiency ratings.
d. Material designations by UNS alloy number or ASTM Specification and
Grade.
e. Data needed to verify compliance with the Specifications.
f. Catalog data.
g. Nameplate data.
h. Clearly mark submittal information to show specific items, materials, and
accessories or options being furnished.
2. Gear reduction units:
a. Engineering information in accordance with applicable AGMA standards.
b. Gear mesh frequencies.
March 2021 - DRAFT 46 05 10-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 888
Item#18.
C. Shop drawings:
1. Drawings for equipment:
a. Drawings that include cut-away drawings, parts lists, material specification
lists, and other information required to substantiate that proposed
equipment complies with specified requirements.
2. Outline drawings showing equipment, driver, driven equipment, pumps, seal,
motor(s) or other specified drivers, variable frequency drive, shafting, U-joints,
couplings, drive arrangement, gears, base plate or support dimensions, anchor
bolt sizes and locations, bearings, and other furnished components.
3. Installation instructions including leveling and alignment tolerances, grouting,
lubrication requirements, and initial Installation Testing procedures.
4. Wiring, control schematics, control logic diagrams and ladder logic or similar
for computer-based controls.
5. Recommended or normal operating parameters such as temperatures and
pressures.
6. Alarm and shutdown setpoints for all controls furnished.
D. Calculations:
1. Structural:
a. Substantiate equipment base plates, supports, bolts, anchor bolts, and
other connections meet minimum design requirements specified and
seismic design criteria as specified in Section 01_81_01.
2. Mechanical:
a. ABMA 9 or ABMA 11 L10 life for bearings calculation methods for drivers,
pumps, gears, shafts, motors, and other driveline components with
bearings.
b. Substantiate that operating rotational frequencies meet the requirements
of this Section.
c. Torsional analysis of power transmission systems: When torsional
analysis specified in the equipment sections, provide:
1) Sketch of system components identifying physical characteristics
including mass, diameter, thickness, and stiffness.
2) Results of analysis including first and second critical frequencies of
system components and complete system.
d. Calculations shall be signed and stamped by a licensed engineer.
E. Operation and maintenance manuals:
1. As specified in Section 01_78_23.
2. Equipment with bearings:
a. Include manufacturer and model number of every bearing.
b. Include calculated ball pass frequencies of the installed equipment for
both the inner and outer raceways.
F. Commissioning submittals: As specified in Section 01_75_17.
G. Project closeout documents: As specified in Section 01_77_00.
March 2021 - DRAFT 46 05 10-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 889
Item#18.
PART PRODUCTS
2.01 MATERIALS
A. Materials as specified in Section 01_60_00 including special requirements for
materials in contact with drinking water.
B. Ferrous materials:
1. Steel for members used in fabrication of assemblies: ASTM A36.
2. Iron castings: ASTM A48, tough, close-grained gray iron, free from blowholes,
flaws, and other imperfections.
3. Ductile iron castings: ASTM A536, Grade 65-45-12, free from flaws and
imperfections.
4. Galvanized steel sheet: ASTM A653, minimum 0.0635-inch (16-gauge).
5. Expanded metal: ASTM A36, 13-gauge, 1/2-inch flat pattern expanded metal.
6. Stainless steel:
a. As specified in Section 05_12_00.
b. In contact or within 36 inches of water: Type 316 or 316L.
c. Other locations: Type 304 or 304L.
d. Source cleaning and passivation as specified in Section 05_12_00.
C. Non-ferrous materials:
1. Bronze in contact with wastewater: Composition of not more than 2 percent
aluminum nor more than 6 percent zinc; UNS Alloy C83600, C89833, C89520,
C92200, or C93700 in accordance with ASTM B61, B62, B505, or B584, when
not specified otherwise.
2. Aluminum: As specified in Section 05_14_05.
D. Dielectric materials for separation of dissimilar metals:
1. Neoprene, bituminous impregnated felt, heavy bituminous coatings,
nonmetallic separators or washers, or other materials as specified.
E. Non-shrink grout and epoxy non-shrink grout: As specified in Section 03_60_00.
2.02 ANCHORS AND FASTENERS
A. Mechanical anchoring to concrete and masonry:
1. As specified in Section 05_05_24:
a. Type 316 stainless steel.
2. Design as specified in Section 01_81_01.
B. High-strength fasteners:
1. As specified in Section 05_12_00.
C. Flange bolts:
1. As specified in Section 40_05_00.01.
D. Mechanical assembly fasteners, unless otherwise shown on the Drawings:
1. Stainless steel:
a. High-temperature service or high-pressure service:
1) Bolts: ASTM A193, Grade B8 (Type 304) or Grade 138M (Type 316),
Class 1, heavy hex.
2) Nuts: ASTM A194, Grade 8, heavy hex.
March 2021 - DRAFT 46 05 10-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 890
Item#18.
3) Washers: Alloy group matching bolts and nuts.
b. Low-temperature service:
1) Bolts: ASTM A320, Grade B8 (Type 304) or Grade 138M (Type 316),
Class 1, heavy hex.
2) Nuts: ASTM A194, Grade 8 (Type 304) or Grade 138M (Type 316),
heavy hex.
3) Washers: Alloy group matching bolts and nuts.
c. General service:
1) Bolts: ASTM F593, Alloy Group 1 (Type 304) or Alloy Group 2
(Type 316).
2) Nuts: ASTM F594, Alloy Group 1 (Type 304) or Alloy Group 2
(Type 316).
3) Washers: Alloy group matching bolts and nuts.
2.03 SHAFT COUPLINGS
A. General:
1. Type and ratings: Provide non-lubricated type, designed for not less than
50,000 hours of operating life.
2. Sizes: Provide as recommended by manufacturer for specific application,
considering horsepower, speed of rotation, and type of service.
B. Shaft couplings for close-coupled electric-motor-driven equipment:
1. Use for:
a. Equipment 1/2 horsepower or larger.
b. Reversing equipment.
c. Equipment subject to sudden torque reversals or shock loading:
d. Examples:
1) Reciprocating pumps, blowers, and compressors.
2) Conveyor belts.
2. Manufacturers: One of the following or equal:
a. Lovejoy.
b. T.B. Woods.
3. Provide flexible couplings designed to accommodate angular misalignment,
parallel misalignment, and end float.
4. Manufacture flexible component of coupling from synthetic rubber or urethane.
5. Provide service factor of 2.5 for electric motor drives and 3.5 for engine drives.
6. Do not allow metal-to-metal contact between driver and driven equipment.
C. Shaft couplings for direct-connected electric-motor-driven equipment:
1. Use for 1/2 horsepower or larger and subject to normal torque, non-reversing
applications.
2. Manufacturers: One of the following or equal:
a. Rexnord.
b. T.B. Woods.
3. Provide flexible couplings designed to accommodate shock loading, vibration,
and shaft misalignment or offset.
4. Provide flexible connecting element of rubber and reinforcement fibers.
5. Provide service factor of 2.0.
6. Connect stub shafts through collars or round flanges, firmly keyed to their
shafts with neoprene cylinders held to individual flanges by through pins.
March 2021 - DRAFT 46_05_10-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 891
Item#18.
D. Spacer couplings: Where cartridge-type mechanical seals or non-split seals are
specified, provide a spacer-type coupling of sufficient length to remove the seal
without disturbing the driver or driven equipment unless noted otherwise in the
individual equipment specifications.
E. Specialized couplings: Where requirements of equipment dictate specialized
features, supply coupling recommended for service by manufacturer:
1. Includes any engine-driven equipment.
2.04 STUFFING BOX, SEAL CHAMBER, AND SHAFT SEALS
A. General:
1. Unless otherwise noted in the equipment section, provide cartridge-type,
double mechanical shaft seals for pumps.
2. Provide a stuffing box large enough for a double mechanical seal.
3. Where packing is specified, provide stuffing box large enough to receive a
double mechanical seal.
4. For pumps with packing, design packing gland to allow adjustment and
repacking without dismantling pump except to open up packing box.
B. Packing: When specified in the equipment section of the specifications, provide the
following type of packing:
1. Wastewater, water, and sludge applications:
a. Asbestos free.
b. PTFE (Teflon) free.
c. Braided graphite.
d. Manufacturers: One of the following or equal:
1) Chesterton, 1400.
2) John Crane, equivalent product.
C. Mechanical seals: Provide seal types specified in the equipment sections and as
specified.
1. Provide seal types meeting the following requirements:
a. Balanced hydraulically.
b. Spring: Stationary, out of pumping fluid, Hastelloy C; Type Elgiloy or
17-7 PH stainless steel for split seals.
c. O-ring: Viton 747.
d. Gland: Type 316L stainless steel.
e. Set screws: Type 316L stainless steel.
f. Faces: Reaction bonded, silicon carbide.
g. Seal designed to withstand 300 pounds per square inch gauge minimum
differential pressures in either direction; no requirement for seal buffer
pressure to be maintained when pump is not operational even though
process suction head may be present in pump.
2. Cartridge-type double mechanical: Manufacturers:
a. One of the following or equal:
1) Chesterton, S20.
2) John Crane, 5620 Series.
3. Cartridge-type flushless mechanical:
a. Manufacturers: One of the following or equal:
1) Chesterton, 156.
2) John Crane, 5870.
March 2021 - DRAFT 46 05 10-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 892
Item#18.
2.05 GEAR REDUCTION UNITS
A. Type: Helical or herringbone, unless otherwise specified.
B. Design:
1. Made of alloys treated for hardness and for severe service.
2. AGMA Class II service:
a. Use more severe service condition when such is recommended by unit's
manufacturer.
3. Cast-iron housing with gears running in oil.
4. Anti-friction bearings.
5. Thermal horsepower rating based on maximum horsepower rating of prime
mover, not actual load.
6. Manufactured in accordance with applicable AGMA standards.
C. Planetary gear units are not to be used.
2.06 BEARINGS
A. Type: Oil or grease lubricated, ball or roller antifriction type, of standard
manufacture.
B. Oil-lubricated bearings: Provide either pressure lubricating system or separate oil
reservoir splash-type system:
1. Size oil-lubrication systems to safely absorb heat energy generated in
bearings when equipment is operating under normal conditions and with the
temperature 15 degrees Fahrenheit above the maximum design temperature
as specified in Section 01_81_01.
2. Provide an external oil cooler when required to satisfy the specified operating
conditions:
a. Provide air-cooled system if a water-cooling source is not indicated on the
Drawings.
b. Equip oil cooler with a filler pipe and external level gauge.
C. Grease lubricated bearings, except those specified to be factory sealed: Fit with
easily accessible grease supply, flush, drain, and relief fittings.
1. Lubrication lines and fittings:
a. Lines: Minimum 1/4-inch diameter stainless steel tubing.
b. Multiple fitting assemblies: Mount fittings together in easily accessible
location.
c. Use standard hydraulic-type grease supply fittings:
1) Manufacturers: One of the following or equal:
a) Alenite.
b) Zerk.
D. Ratings: Rated in accordance with ABMA 9 or ABMA 11 L10 life for bearings rating
life of not less than 50,000 hours.
2.07 MOTORS
A. As specified in Section 26_05_09.
March 2021 - DRAFT 46 05 10-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 893
Item#18.
2.08 GEAR MOTORS
A. Motors as specified in Section 26_05_09.
B. Helical gearing for parallel shaft drives and worm gearing for right-angle drives.
C. Manufactures: One of the following or equal:
1. Baldor Electric Company.
2. Bodine Electric Company.
2.09 VENDOR CONTROL PANELS
A. As specified in Section 40_61_00.
2.10 EQUIPMENT SUPPORT FRAMES
A. Bolt holes shall not exceed bolt diameter by more than 25 percent, up to a limiting
maximum diameter oversize of 1/4-inch.
2.11 PIPING AND VALVES
A. Piping as specified in Section 40_05_00.01.
B. Valves as specified in Section 40_05_51.01.
2.12 SAFETY EQUIPMENT
A. Safety guards:
1. Provide guards that protect personnel from rotating shafts or components
within 7.5 feet of floors or operating platforms.
2. Requirements:
a. Allow visual inspection of moving parts without removal.
b. Allow access to lubrication fittings.
c. Prevent entrance of rain or dripping water for outdoor locations.
d. Size belt and sheave guards to allow for installation of sheaves 15 percent
larger and addition of 1 belt.
3. Materials:
a. Sheet metal: Carbon steel, 12-gauge minimum thickness, hot-dip
galvanized after fabrication.
b. Fasteners: Type 304 stainless steel.
B. Insulation:
1. Insulate all surfaces with normal operating temperatures above 120 degrees
Fahrenheit when surface is within 7.5 feet height from any operating floor or
level.
2. Insulation thickness such that temperature is below 120 degrees Fahrenheit.
3. Insulation Type 3 and cover Type 5 as specified in Section 40_05_06.55.
C. Warning signs:
1. Provide warning signs in accordance with OSHA requirements for equipment
that starts automatically or remotely.
2. Mount warning signs with stainless steel fasteners at equipment.
March 2021 - DRAFT 46 05 10-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 894
Item#18.
2.13 SPRING VIBRATION ISOLATORS
A. Design requirements:
1. Telescopic top and bottom housing with vertical stabilizers to resist lateral and
vertical forces.
2. Use steel coil springs.
3. Design vibration isolators in accordance with seismic design criteria as
specified in Section 01_81_01.
B. Performance requirements:
1. Minimum spring deflection of 1 inch under static load and capable of limiting
transmissibility to 10 percent maximum at design operating load.
2. Rotary-lobe blowers:
a. Each package shall be supplied with vibration isolating feet with a
minimum efficiency of 80 percent.
b. Blower manufacturer shall be responsible for attenuating noise and
vibration in the blower package such that no special installation base shall
be required, nor shall any additional measures be required to reduce
vibrations from the blower package being transmitted to the base or the
piping.
C. Manufacturers: One of the following or equal:
1. California Dynamics Corporation, Type RJSD.
2. Mason Industries, equivalent product.
D. Materials:
1. Fabricate isolators using welded-steel or shatterproof ductile iron in
accordance with ASTM A536 Grade CS-45-12.
2. Spring steel: ASTM A125.
2.14 NAMEPLATES
A. Fastened to equipment at factory in an accessible and visible location.
B. Stainless steel sheet engraved or stamped with text, holes drilled or punched for
fasteners.
C. Fasteners: Number 4 or larger oval head stainless steel screws or drive pins.
D. Text:
1. Manufacturer's name, equipment model number and serial number, motor
horsepower when appropriate, and identification tag number.
2. Indicate the following additional information as applicable:
a. Maximum and normal rotating speed.
b. Service class per applicable standards.
3. Include for pumps:
a. Rated total dynamic head in feet of fluid.
b. Rated flow in gallons per minute.
c. Impeller, gear, screw, diaphragm, or piston size.
4. Include for gear reduction units:
a. AGMA class of service.
b. Service factor.
c. Input and output speeds.
March 2021 - DRAFT 46 05 10-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 895
Item#18.
2.15 SHOP FINISHES
A. Provide appropriate factory coatings as recommended by manufacturer for service
conditions.
1. Motors and gear reducers: Shop finish paint with manufacturer's standard
coating, unless otherwise specified in the individual equipment specification.
2.16 SPECIAL TOOLS
A. Supply 1 set of special tools as specified in Section 01_60_00.
2.17 SOURCE TESTING
A. Testing requirements unless specified otherwise in the individual equipment
specifications:
1. Mechanical equipment: Level 1 General Equipment Performance Test as
specified in Section 46_05_94.
2. Motors: As specified in Section 26_05_09.
3. Vendor control panels: As specified in Section 40_80_01.
2.18 SHIPPING
A. As specified in Section 01_60_00.
B. Prior to shipment of equipment:
1. Bearings (and similar items):
a. Pack separately or provide other protection during transport.
b. Greased and lubricated.
2. Gear boxes:
a. Oil filled or sprayed with rust preventive protective coating.
3. Fasteners:
a. Inspect for proper torques and tightness.
PART 3 EXECUTION
3.01 DELIVERY, HANDLING, STORAGE, AND PROTECTION
A. As specified in Section 01_60_00.
B. Inspect fasteners for proper torques and tightness.
C. Storage:
1. Bearings:
a. Rotate units at least once per month or more often as recommended by
the manufacturer to protect rotating elements and bearings.
2. Gear boxes:
a. Inspect to verify integrity of protection from rust.
D. Protection:
1. Equipment Log shall include description of rotation performed as part of
maintenance activities.
March 2021 - DRAFT 46 05 10-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 896
Item#18.
3.02 INSTALLATION
A. Field measurements:
1. Prior to shop drawings preparation, take measurements and verify dimensions
indicated on the Drawings.
2. Ensure equipment and ancillary appurtenances fit within available space.
B. Sequencing and scheduling:
1. Equipment anchoring: Obtain anchoring material and templates or setting
drawings from equipment manufacturers in adequate time for anchors to be
cast-in-place.
2. Coordinate details of equipment with other related parts of the Work, including
verification that structures, piping, wiring, and equipment components are
compatible.
C. Metal work embedded in concrete:
1. Accurately place and hold in correct position while concrete is being placed.
2. Clean surface of metal in contact with concrete immediately before concrete is
placed.
D. Concrete surfaces designated to receive non-shrink grout:
1. Heavy sandblast concrete surface in contact with non-shrink grout.
2. Clean concrete surfaces of sandblasting sand, grease, oil, dirt, and other
foreign material that may reduce bond to non-shrink grout.
3. Saturate concrete with water. Concrete shall be saturated surface damp at
time non-shrink grout is placed.
E. Install equipment in accordance with manufacturer's installation instructions and
recommendations.
F. Lubrication lines and fittings:
1. Support and protect lines from source to point of use.
2. Fittings:
a. Bring fittings to outside of equipment in manner such that they are readily
accessible from outside without necessity of removing covers, plates,
housings, or guards.
b. Mount fittings together wherever possible using factory-mounted multiple
fitting assemblies securely mounted, parallel with equipment lines, and
protected from damage.
c. Fittings for underwater bearings: Bring fittings above water surface and
mount on edge of structure above.
G. Alignment of drivers and equipment:
1. Where drive motors or other drivers are connected to driven equipment by
flexible coupling, disconnect coupling halves and align driver and equipment
after complete unit has been leveled on its foundation.
March 2021 - DRAFT 46 05 10-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 897
Item#18.
2. Comply with procedures of appropriate HI, AGMA Standards, alignment
tolerances of equipment manufacturers and the following requirements to bring
components into angular and parallel alignment:
a. Maximum total coupling offset (not the per-plane offset): Not to exceed
0.5 mils per inch of coupling length for spacer couplings based on
coupling length (not dial separation).
b. Utilize jacking screws, wedges, or shims as recommended by the
equipment manufacturer and as specified in the equipment sections.
3. Use reverse-indicator arrangement dial-type or laser-type alignment indicators:
Mount indicators on the driver/coupling flange and equipment/coupling flange.
Alignment instrumentation accuracy shall be sufficient to read angular and
radial misalignment at 10 percent or less of the manufacturer's recommended
acceptable misalignment.
4. Alignment and calculations shall include measurement and allowance for
thermal growth, spacer coupling length, indicator separation, and axial spacing
tolerances of the coupling.
5. When alignment satisfies most stringent tolerance of system components,
grout between base and foundation.
a. Allow minimum 48 hours for grout to harden.
b. After grout hardens, remove jacking screws, tighten anchor bolts and
other connections, and recheck alignment.
c. Correct alignment as required.
6. After functional testing is complete, dowel motor or drivers and driven
equipment:
a. Comply with manufacturer's instructions.
H. Grouting under equipment bases, baseplates, soleplates, and skids:
1. Unless otherwise indicated on the Drawings, grout with non-shrink grout as
specified in Section 036000.
a. Non-shrink epoxy grout required only when indicated on the Drawings.
2. Comply with equipment manufacturer's installation instructions for grouting
spaces, and tolerances for level and vertical and horizontal alignment.
3. Install grout only after:
a. Equipment is leveled and in proper alignment.
b. Piping connections are complete and in alignment with no strain
transmitted to equipment.
4. Do not use leveling nuts on equipment anchors for supporting and leveling
equipment bases, baseplates, soleplates, and skids for grouting.
5. Use jack screws for supporting and leveling equipment bases, baseplates,
soleplates, and skids for grouting following the procedure defined below:
a. Drill and tap equipment base plates, sole plates, and skids for jack
screws.
b. Use suitable number and size of jack screws.
c. End of jack screws shall bear on circular steel plates epoxy bonded to
equipment foundation.
d. Jack screw threads that will be in contact with grout: Wrap with multiple
layers of tape or other material, acceptable to Engineer, to prevent grout
from bonding to threads.
e. Place and cure grout as specified in Section 03_60 00.
f. After grout is cured, remove jack screws and material used to prevent
bonding to grout.
1) Provide jack screws to Owner for future use.
March 2021 - DRAFT 46 05 10-14 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 898
Item#18.
g. Tighten equipment anchors in accordance with equipment manufacturer
requirements.
h. Fill holes where jack screws have been removed with grout.
i. Cure as specified in Section 03_60_00.
6. For equipment bases, baseplates, soleplates, and skids where it is not
practical to use jack screws, use steel wedges and shims.
a. Wrap wedges and shims that contact grout with multiple layers of tape or
other material, acceptable to Engineer, to prevent grout from bonding.
b. Place and cure grout as specified in Section 03_60_00
c. Remove wedges or shims.
d. Tighten equipment anchors to in accordance with equipment
manufacturer requirements.
e. Fill voids where wedges and shims have been removed with grout.
f. Cure as specified in Section 03_60_00.
7. Preparation of equipment bases, baseplates, soleplates, and skids for
grouting:
a. Metal in contact with grout: Grit blast to white metal finish.
b. Clean surfaces of equipment bases, baseplates, soleplates, and skids in
contact with grout of dirt, dust, oil, grease, paint, and other material that
will reduce bond.
8. Preparation of concrete equipment foundation for grouting:
a. Rough concrete surfaces in contact with grout.
b. Concrete contact surface shall be free of dirt, dust, laitance, particles,
loose concrete, or other material or coatings that will reduce bond.
c. Saturate concrete contact surface area with water for minimum of
24 hours prior to grouting.
d. Remove standing water just prior to grout placement, using clean rags or
oil-free compressed air.
9. Forms and header boxes:
a. Build forms for grouting of material with adequate strength to withstand
placement of grouts.
b. Use forms that are rigid and liquid tight. Caulk cracks and joints with an
elastomeric sealant.
c. Line forms with polyethylene film for easy grout release. Forms carefully
waxed with 2 coats of heavy-duty paste wax will also be acceptable.
10. Grout placement requirements:
a. Minimum ambient and substrate temperature: 45 degrees Fahrenheit and
rising:
1) Conform to grout manufacturer's temperature requirements.
b. Pour grout using header box.
c. Keep level of grout in header box above bottom of equipment bases,
baseplates, soleplates, and skids at all times to prevent air entrapment.
d. Grout shall flow continuously from header box to other side of forms
without trapping air or forming voids.
e. Vibrate, rod, or chain grout to facilitate grout flow, consolidate grout, and
remove entrapped air.
f. After grout sets, remove forms and trim grout at 45-degree angle from
bottom edge of equipment bases, baseplates, soleplates, and skids.
g. Cure as specified in Section 03_60_00.
March 2021 - DRAFT 46 05 10-15 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_10(IDS50) Page 899
Item#18.
I. Field welding:
1. Use welding procedures, welders, and welding operators qualified and certified
in accordance with AWS D1.1.
2. Shielded arc welding.
J. Field finishes:
1. Protect motors.
2. Clean equipment.
3. Apply primer and coating systems as specified in Section 09_96_01.
K. Special techniques:
1. Use applicable special tools and equipment, including precision machinist
levels, dial indicators, and gauges as required in equipment installations.
L. Tolerances:
1. Completed equipment installations: Comply with requirements for intended use
and specified vibration and noise tolerances.
M. Warning signs:
1. Mount securely with stainless fasteners at equipment that can be started
automatically or from remote locations.
3.03 FIELD PAINTING
A. Compatible with factory painting.
B. As specified in Section 09_96_01.
3.04 COMMISSIONING
A. As specified in Section 01_75_17.
B. Functional testing requirements unless specified otherwise in the individual
equipment specifications:
1. Mechanical equipment: Level 1 tests as specified in Section 46_05_94.
2. Motors: As specified in Sections 26 05_09 and 26_08_50.
3. Vendor control panels: As specified in Section 40_80_01.
END OF SECTION
March 2021 - DRAFT 46 05 10-16 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_10(IDS50) Page 900
Item#18.
SECTION 46_05_94
MECHANICAL EQUIPMENT TESTING
PART1 GENERAL
1.01 SUMMARY
A. Section includes: Testing of mechanical equipment and systems.
B. Related sections:
1. Section 01 75 17 - Commissioning.
2. Section 26_05_09 - Low Voltage Motors up to 500 Horsepower.
3. Section 40_05_00.09 - Piping Systems Testing.
1.02 REFERENCES
A. American National Standards Institute (ANSI):
1. S1.4 Specification for Sound Level Meters.
B. Hydraulic Institute (HI).
C. National Institute of Standards and Technology (NIST).
1.03 SUBMITTALS
A. Schedule of source (factory) tests, Owner training, installation testing, functional
testing, clean water facility testing, closeout documentation, process start-up and
process operational period as specified in this Section and in Section 01_75_17 and
equipment sections.
B. Test instrumentation calibration data.
C. Operation and maintenance manual:
1. Include motor rotor bar pass frequencies for motors larger than
500 horsepower.
D. Commissioning and Process Start-up Plan: As specified in Section 01_75_17.
E. Test plan as specified in Section 01_75_17 and equipment sections.
F. Test reports as specified in this Section and in Section 01_75_17 and equipment
sections.
G. Coordinate with mechanical equipment testing requirements specified under each
technical equipment specification.
PART2 PRODUCTS
Not Used.
March 2021 - DRAFT 46 05 94-1 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_94(IDS50) Page�901
Item#18.
PART 3 EXECUTION
3.01 GENERAL
A. Commissioning and process start-up of equipment as specified in:
1. This Section.
2. Section 01 75 17.
3. Equipment sections:
a. If testing requirements are not specified, provide Level 1 Tests.
B. Comply with latest version of applicable standards.
C. Test and prepare piping as specified in Section 40_05_00.09.
D. Operation of related existing equipment: Owner will operate related existing
equipment or facilities necessary to accomplish the testing. Schedule and
coordinate testing as required by Section 01_75_17.
E. Provide necessary test instrumentation that has been calibrated within 1 year from
date of test to recognized test standards traceable to the NIST or approved source:
1. Properly calibrated field instrumentation permanently installed as a part of the
Work may be utilized for tests.
2. Prior to testing, provide signed and dated certificates of calibration for test
instrumentation and equipment.
F. Test measurement and result accuracy:
1. Use test instruments with accuracies as recommended in the appropriate
referenced standards. When no accuracy is recommended in the referenced
standard, use 1 percent or better accuracy test instruments:
a. Improved (lower error tolerance) accuracies specified elsewhere prevail
over this general requirement.
2. Do not adjust results of tests for instrumentation accuracy:
a. Measured values and values directly calculated from measured values
shall be the basis for comparing actual equipment performance to
specified requirements.
G. Report features:
1. Report results in a bound document in generally accepted engineering format
with title page, written summary of results compared to specified requirements,
and appropriate curves or plots of significant variables in English units.
2. Include appendix with a copy of raw, unmodified test data sheets indicating
test value, date and time of reading, and initials of person taking the data.
3. Include appendix with sample calculations for adjustments to raw test data and
for calculated results.
4. Include appendix with the make, model, and last calibration date of
instrumentation used for test measurements.
5. Include in body of report a drawing or sketch of the test system layout showing
location and orientation of the test instruments relative to the tested equipment
features.
March 2021 - DRAFT 46 05 94-2 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_94(IDS50) Page 902
Item#18.
H. Provide necessary fluids, utilities, temporary piping, temporary supports, temporary
access platforms or access means and other temporary facilities and labor
necessary to safely operate the equipment and accomplish the specified testing:
1. With Owner's permission, some utilities may be provided by fully tested
permanently installed utilities that are part of the Work.
I. Prepare and submit test reports as specified.
J. Testing levels:
1. Level 1 Tests:
a. Level 1 General Equipment Performance Test:
1) For equipment, operate, rotate, or otherwise functionally test for
15 minutes minimum after components reach normal operating
temperatures.
2) Operate at rated design load conditions.
3) Confirm that equipment is properly assembled, equipment moves or
rotates in the proper direction, shafting, drive elements, and bearings
are installed and lubricated in accordance with proper tolerances,
and that no unusual power consumption, lubrication temperatures,
bearing temperatures, or other conditions are observed.
b. Level 1 Pump Performance Test:
1) Measure flow and head while operating at or near the rated
condition; for factory testing, testing may be at reduced speeds with
flow and head corresponding to the rated condition when adjusted for
speed using the appropriate affinity laws.
2) Use of a test driver is permitted for factory tests when actual driver is
given a separate test at its point of manufacture as specified in
Section 26_05_09 or the applicable equipment section. Use actual
driver for field tests.
3) Record measured flow, suction pressure, discharge pressure, and
make observations on bearing temperatures and noise levels.
c. Level 1 Vibration Test:
1) Test requirement:
a) Measure filtered vibration spectra versus frequency in 3
perpendicular planes at each normally accessible bearing
housing on the driven equipment, any gears and on the driver;
1 plane of measurement to be parallel to the axis of rotation of
the component.
b) Vibration spectra versus frequency shall be in accordance with
Vibration Acceptance Criteria.
2) Equipment operating condition: Test at specified maximum speed.
d. Level 1 Noise Test:
1) Measure unfiltered overall A-weighted sound pressure level in dBA at
3 feet horizontally from the surface of the equipment and at a mid-
point of the equipment height.
2. Level 2 Tests:
a. Level 2 General Performance Test:
1) For equipment, operate, rotate, or otherwise functionally test for at
least 2 hours after components reach normal operating
temperatures.
2) Operate at rated design load conditions.
March 2021 - DRAFT 46 05 94-3 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_94(IDS50) Page�903
Item#18.
3) Confirm that equipment is properly assembled, equipment moves or
rotates in the proper direction, shafting, drive elements, and bearings
are installed and lubricated in accordance with proper tolerances,
and that no unusual power consumption, lubrication temperatures,
bearing temperatures, or other conditions are observed.
b. Level 2 Pump Performance Test:
1) Test 2 hours minimum for flow and head at the rated condition; for
factory testing, testing may be at reduced speeds with flow and head
corresponding to the rated condition when adjusted for speed using
the appropriate affinity laws.
2) Use of a test driver is permitted for factory tests when actual driver is
given a separate test at its point of manufacture as specified in
Section 26 05 09. Use actual driver for field tests.
3) Test for flow and head at 2 additional conditions; 1 at 25 percent
below the rated flow and 1 at 10 percent above the rated flow.
4) Record measured flow, suction pressure, discharge pressure, and
observations on bearing temperatures and noise levels at each
condition.
c. Level 2 Vibration Test:
1) Test requirement:
a) Measure filtered vibration spectra versus frequency and
measure vibration phase in 3 perpendicular planes at each
normally accessible bearing housing on the driven equipment,
any gears and on the driver; 1 plane of measurement to be
parallel to the axis of rotation of the component; measure actual
rotational speeds for each vibration spectra measured using
photometric or other tachometer input connected directly to the
vibration data collector.
b) Vibration spectra versus frequency shall be in accordance with
Vibration Acceptance Criteria.
2) Equipment operating condition: Repeat test requirements at design
specified maximum speed and at minimum speed for variable speed
equipment.
3) Natural frequency test of field installed equipment:
a) Excite the installed equipment and support system in
3 perpendicular planes, use same planes as operating vibration
measurement planes, and determine the as-installed natural
resonant frequency of the driven equipment, the driver, gears,
and supports.
b) Perform test at each bearing housing, at each support pedestal,
and for pumps on the suction and discharge piping.
c) Perform with equipment and attached piping full of intended
service or process fluid.
d. Level 2 Noise Test:
1) Measure filtered A-weighted overall sound pressure level in dBA for
each of 8 octave band mid-points beginning at 63 hertz measured at
3 feet horizontally from the surface of the equipment at mid-point
height of the noise source.
March 2021 - DRAFT 46 05 94-4 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_94(IDS50) Page 904
Item#18.
3. Level 3 Tests:
a. Level 3 General Equipment Performance Tests:
1) For equipment, operate, rotate, or otherwise functionally test for at
least 4 hours after components reach normal operating
temperatures.
2) Operate at rated design load conditions for 1/2 the specified time;
operate at each of any other specified conditions for a proportionate
share of the remaining test time.
3) Confirm that equipment is properly assembled, equipment rotates in
the proper direction, shafting and bearings are installed and
lubricated in accordance with proper tolerances, and that no unusual
noise, vibration, or temperatures are observed.
4) Take appropriate capacity, power or fuel consumption, torque,
revolutions per minute, pressure, and temperature readings using
appropriate test instrumentation to confirm equipment meets
specified performance requirements at the design rated condition.
5) Bearing temperatures: During maximum speed or capacity
performance testing, measure and record the exterior surface
temperature of each bearing versus time.
b. Level 3 Pump Performance Test:
1) Test 4 hours minimum for flow and head at or near the rated
condition; for factory testing, testing may be at reduced speeds with
flow and head corresponding to the rated condition when adjusted for
speed using the appropriate affinity laws.
2) Use of a test driver is permitted for factory tests when actual driver is
given a separate test at its point of manufacture as specified in
Section 26 05 09. Use actual driver for field tests.
3) Test each specified flow and head condition at the rated speed and
test at minimum as well as maximum specified speeds; operate at
each test condition for a minimum of 15 minutes; for factory testing,
test at other speeds may be omitted if test driver at reduced speeds
is used for rated condition testing.
4) Record measured shaft revolutions per minute, flow, suction
pressure, discharge pressure; record measured bearing
temperatures (bearing housing exterior surface temperatures may be
recorded when bearing temperature devices are not required by the
equipment section) and record observations on noise levels.
c. Level 3 Vibration Test:
1) Requirements: Same as Level 2 vibration test except data taken at
each operating condition tested and with additional requirements
below.
2) Perform High Frequency Enveloping Analysis for gears and bearings.
a) Measure bearing element vibration directly on each bearing cap
in a location close as possible to the bearing load zone that
provides a smooth surface and direct path to the bearing to
detect bearing defects.
b) Report results in units of acceleration versus frequency in cycles
per minute.
3) Perform Time Wave Form analysis for gears, low speed equipment
and reciprocating equipment; plot true peak amplitude velocity and
displacement versus time and label the period between peaks with
the likely cause of the periodic peaks (relate the period to a cause).
March 2021 - DRAFT 46 05 94-5 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_94(IDS50) Page�905
Item#18.
4) Plot vibration spectra on 3 different plots; peak displacement versus
frequency, peak acceleration versus frequency and peak velocity
versus frequency.
d. Level 3 Noise Test: Measure filtered, un-weighted overall sound pressure
level in dB at 3 feet horizontally from the surface of the equipment at mid-
point height and at 4 locations approximately 90 degrees apart in plan
view; report results for each of 8 octave band mid-points beginning at
63 hertz.
4. Level 4 Tests:
a. Level 4 General Equipment Performance Test:
1) For equipment, operate, rotate, or otherwise functionally test for at
least 8 hours after components reach normal operating
temperatures.
2) Operate at rated design load conditions for 1/2 the specified time;
operate at each of any other specified conditions for a proportionate
share of the remaining test time.
3) Confirm that equipment is properly assembled, equipment rotates in
the proper direction, shafting and bearings are installed and
lubricated in accordance with proper tolerances, and that no unusual
noise, vibration, or temperatures are observed.
4) Take appropriate capacity, power or fuel consumption, torque,
revolutions per minute, pressure, and temperature readings using
appropriate test instrumentation to confirm equipment meets
specified performance requirements at the design rated condition.
5) Bearing temperatures: During maximum speed or capacity testing,
measure and record the exterior surface temperature of each bearing
versus time.
b. Level 4 Pump Performance Test:
1) Test 8 hours minimum for flow and head; begin tests at or near the
rated condition; for factory and field-testing, test with furnished motor
at full speed.
2) Test each specified flow and head condition at the rated speed and
test at minimum as well as maximum specified speeds; operate at
each test condition for a minimum of 20 minutes or longer as
necessary to measure required performance, vibration, and noise
data at each test condition.
3) Record measured shaft revolutions per minute, flow, suction
pressure, discharge pressure; record measured bearing
temperatures (bearing housing exterior surface temperatures may be
recorded when bearing temperature devices not required by the
equipment section) and record observations on noise levels.
4) Bearing temperatures: During maximum speed or capacity testing,
measure and record the exterior surface temperature of each bearing
versus time.
5) Perform efficiency and/or Net Positive Suction Head Required
(NPSHr) and/or priming time tests when specified in the equipment
section in accordance with the appropriate HI standard and as
follows:
a) Perform NPSHr testing at maximum rated design speed, head
and flow with test fluids at ambient conditions; at maximum rated
speed, test at 15 percent above rated design flow, and
25 percent below rated design flow.
March 2021 - DRAFT 46 05 94-6 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_94(IDS50) Page 906
Item#18.
b) Perform efficiency testing with test fluids at maximum rated
speed.
c) Perform priming time testing with test fluids at maximum rated
speed.
c. Level 4 Vibration Test: Same as Level 3 vibration test.
d. Level 4 Noise Test: Same as Level 3 Noise Test except with data taken at
each operating condition tested.
K. Variable speed equipment tests:
1. Establish performance over the entire speed range and at the average
operating condition.
2. Establish performance curves for the following speeds:
a. The speed corresponding to the rated maximum capacity.
b. The speed corresponding to the minimum capacity.
c. The speed corresponding to the average operating conditions.
L. Pump tests, all levels of testing:
1. Test in accordance with the following:
a. Applicable HI Standards.
b. This Section.
c. Equipment sections.
2. Test tolerances: In accordance with appropriate HI Standards, except the
following modified tolerances apply:
a. From 0 to plus 5 percent of head at the specified flows.
b. From 0 to plus 5 percent of flow at the rated design point head.
c. No negative tolerance for the efficiency at the specified flows.
d. No positive tolerance for vibration limits. Vibration limits and test methods
in HI Standards do not apply, use limits and methods specified in this or
other Sections of the Specifications.
M. Drivers tests:
1. Test motors as specified in Section 26_05_09.
2. Test other drivers as specified in the equipment section.
N. Noise requirements and control:
1. Perform noise tests in conjunction with vibration test analysis.
2. Make measurements in relation to reference pressure of 0.0002 microbar.
3. Make measurements of emitted noise levels on sound level meter meeting or
exceeding ANSI S1.4, Type II.
4. Set sound level meter to slow response.
5. Unless otherwise specified, maximum free field noise level not to exceed
85 dBA measured as sound pressure level at 3 feet from the equipment.
O. Pressure testing:
1. Hydrostatically pressure test pressure containing parts at the appropriate
standard or code required level above the equipment component specified
design pressure or operating pressure, whichever is higher.
P. Inspection and balancing:
1. Statically and dynamically balance each of the individual rotating parts as
required to achieve the required field vibration limits.
March 2021 - DRAFT 46 05 94-7 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_94(IDS50) Page�907
Item#18.
2. Statically and dynamically balance the completed equipment rotating assembly
and drive shaft components.
3. Furnish copies of material and component inspection reports including
balancing reports for equipment system components and for the completed
rotating assembly.
Q. Critical speed of rotating equipment:
1. Satisfy the following:
a. The first lateral and torsional critical speed of all constant, variable, and
2-speed driven equipment that is considered rigid such as horizontal
pumps, all non-clog pumps, blowers, air compressors, and engines shall
be at least 25 percent above the equipment's maximum operating speed.
b. The first lateral and torsional critical speed of all constant, variable, and
2-speed driven equipment that is considered flexible or flexibly mounted
such as vertical pumps (vertical in-line and vertical non-clog pumps
excluded) and fans shall at least 25 percent below the equipment's lowest
operating speed.
c. The second lateral and torsional critical speed of all constant, variable,
and 2-speed equipment that is considered flexible or flexibly mounted
shall be at least 25 percent above the maximum operating speed.
R. Vibration tests:
1. Definitions:
a. Root mean square: for pumps operating at speeds greater than 600 rpm,
the vibration measurement shall be measured as the overall velocity in
inches per second root mean square (RMS).
b. Peak-to-peak displacement: The root mean squared average of the
peak-to-peak displacement multiplied by the square root of 2.
c. Peak velocity: The root mean squared average of the peak velocity
multiplied by the square root of 2.
d. Peak acceleration: The root mean squared average of the peak
acceleration multiplied by the square root of 2.
e. High frequency enveloping: A process to extract very low amplitude time
domain signals associated with impact or impulse events such as bearing
or gear tooth defects and display them in a frequency spectrum of
acceleration versus frequency.
1) Manufacturers: One of the following or equal:
a) Rockwell Automation, Entek Group, "Spike Energy" analysis.
b) CSI, "PeakVue."
f. Low speed equipment: Equipment or components of equipment rotating at
less than 600 revolutions per minute.
g. High speed equipment: Equipment and equipment components operating
at or above 600 revolutions per minute.
h. Preferred operating range: Manufacturer's defined preferred operating
range (POR) for the equipment.
i. Allowable operating range: Manufacturer's defined allowable operating
range (AOR) for the equipment.
2. Vibration instrumentation requirements:
a. Analyzers: Use digital type analyzers or data collectors with anti-aliasing
filter, 12 bit A/D converter, fast fourier transform circuitry, phase
measurement capability, time wave form data storage, high frequency
enveloping capabilities, 35 frequency ranges from 21 to 1,500,000 cycles
March 2021 - DRAFT 46 05 94-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_94(IDS50) Page 908
Item#18.
per minute, adjustable fast fourier transform resolution from 400 to
6,400 lines, storage for up to one hundred 3,200 line frequency spectra,
data output port, circuitry for integration of acceleration data to velocity or
double integration to displacement.
1) Manufacturers: One of the following or equal:
a) Computational Systems Inc., (CSI) Division of Emerson Process
Management, Model 2120A, Data Collector/analyzer with
applicable analysis software.
b) Pruftechnik, VIBXPERT II.
b. Analyzer settings:
1) Units: English, inches/second, mils, and gravitational forces.
2) Fast fourier transform lines: Most equipment 1,600 minimum; for
motors, enough lines as required to distinguish motor current
frequencies from rotational frequencies, use 3,200 lines for motors
with a nominal speed of 3,600 revolutions per minute; 3,200 lines
minimum for High Frequency Enveloping; 1,600 lines minimum for
low speed equipment.
3) Sample averages: 4 minimum.
4) Maximum frequency (Finax): 40 times rotational frequency for rolling
element bearings, 10 times rotational frequency for sleeve bearings.
5) Amplitude range: Auto select but full scale not more than twice the
acceptance criteria or the highest peak, whichever is lower.
6) Fast fourier transform windowing: Hanning Window.
7) High pass filter: Minus 3 dB at 120 cycles per minute for high speed
equipment. Minus 3 dB at 21 cycles per minute for low speed
equipment.
c. Accelerometers:
1) For low speed equipment: Low frequency, shear mode
accelerometer, 500 millivolts per gravitational force sensitivity,
10 gravitational force range, plus/minus 5 percent frequency
response from 0.5 hertz to 850 hertz, magnetic mount.
a) Manufacturers: One of the following or equal:
(1) Wilcoxon Research, Model 797L.
(2) PCB, Model 393C.
2) For high speed equipment: General purpose accelerometer,
100 millivolts per gravitational force sensitivity, 50 gravitational force
range, plus/minus 3dB frequency response range from 2 hertz to
12,000 hertz when stud mounted, with magnetic mount holder.
a) Manufacturers: One of the following or equal:
(1) Wilcoxon Research, Model 793.
(2) Entek-IRD Model 943.
3. Accelerometer mounting:
a. Use magnetic mounting or stud mounting.
b. Mount on bearing housing in location with best available direct path to
bearing and shaft vibration.
c. Remove paint and mount transducer on flat metal surface or epoxy mount
for High Frequency Enveloping measurements.
4. Vibration acceptance criteria:
a. Testing of rotating mechanical equipment: Tests are to be performed by
an experienced, factory trained, and independent authorized vibration
analysis expert.
March 2021 - DRAFT 46 05 94-9 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_94(IDS50) Page�909
Item#18.
b. Vibration displacement limits: Unless otherwise specified, equipment
operating at speeds 600 revolutions per minute or less is not to exhibit
unfiltered readings in excess of following:
Operating Conditions & Application Data Overall Peak-to-Peak Displacement
Field, mils Factory, mils
Operation within the POR 3.0 4.0
Operation within the AOR 4.0 5.0
Additive value when measurement location is
greater than 5 feet above foundation. 2.0 2.0
Additive value for solids-handling pumps 2.0 N/A
Additive value for slurry pumps 2.0 N/A
c. Vibration velocity limits: Unless otherwise specified, equipment operating
at speeds greater than 600 revolutions per minute is not to exceed the
following peak velocity limits:
Field Test Factory Test
HI Pump Type Horsepower Overall RMS Overall RMS
Horizontal Solids
Handling Centrifugal Below 33 hp 0.25 0.28
Pumps
Horizontal and Vertical Between 33 and 0.28 0.31
In-Line Centrifugal 100 hp
Pumps (other than Non- 100 hp and above 0.31 0.34
Clog type)
Vertical Solids Handling Below 33 hp 0.30 0.33
Centrifugal Pumps
Vertical Turbine, Mixed Between 33 and 0.32 0.35
Flow, and Propeller 100 hp
Pumps 100 hp and above 0.34 0.35
Non-Solids Handling Below 268 hp 0.15 0.19
Centrifugal Pumps
HI Types BB1, BB2, BB3,
BB4, BB5, OH1, OH2, 268 hp and above 0.19 0.22
OH3, OH4, OHS, and
OH7
Vertical Turbine, Mixed
Flow, and Propeller
Pumps HI Types VS1, Below 268 hp 0.13
VS2, VS3, VS4, VS5,
VS6, VS7, and VS8
Gear Reducers, Radial 268 hp and above 0.17
Slurry Pumps 0.25 0.30
March 2021 - DRAFT 46 05 94-10 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_94(IDS50) Page 910
Item#18.
Field Test Factory Test
HI Pump Type Horsepower Overall RMS Overall RMS
Motors See Applicable Motor See Applicable
Specification Motor
Specification
Gear Reducers, Radial Not to exceed AGMA Not to exceed
6000-1396 limits AGMA 6000-
B96 limits
Other Reducers, Axial 0.1 N/A
d. Equipment operation: Measurements are to be obtained with equipment
installed and operating within capacity ranges specified and without
duplicate equipment running.
e. Additional criteria:
1) No narrow band spectral vibration amplitude components, whether
sub-rotational, higher harmonic, or synchronous multiple of running
speed, are to exceed 40 percent of synchronous vibration amplitude
component without manufacturer's detailed verification of origin and
ultimate effect of such excitation.
2) The presence of discernable vibration amplitude peaks in Test Level
2 or 3 vibration spectra at bearing inner or outer race frequencies
shall be cause for rejection of the equipment.
3) For motors, the following shall be cause for rejection:
a) Stator eccentricity evidenced by a spectral peak at 2 times
electrical line frequency that are more than 40 percent of the
peak at rotational frequency.
b) Rotor eccentricity evidenced by a spectral peak at 2 times
electrical line frequency with spectra side bands at the pole pass
frequency around the 2 times line frequency peak.
c) Other rotor problems evidenced by pole pass frequency side
bands around operating speed harmonic peaks or 2 times line
frequency side bands around rotor bar pass frequency or around
2 times the rotor bar pass frequency.
d) Phasing problems evidenced by 1/3 line frequency side band
spectral peaks around the 2 times electrical line frequency peak.
4) The presence of peaks in a High Frequency Enveloping spectra plot
corresponding to bearing, gear or motor rotor bar frequencies or
harmonics of these frequencies shall be cause for rejection of the
equipment; since inadequate lubrication of some equipment may be
a cause of these peaks, lubrication shall be checked, corrected as
necessary and the high frequency envelope analysis repeated.
5. Vibration testing results presentation:
a. Provide equipment drawing with location and orientation of measurement
points indicated.
b. For each vibration measurement take and include appropriate data on
equipment operating conditions at the time vibration data is taken; for
pumps, compressors, and blowers record suction pressure, discharge
pressure, and flow.
c. When Vibration Spectra Data required:
1) Plot peak vibration velocity versus frequency in cycles per minute.
March 2021 - DRAFT 46 05 94-11 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_94(IDS50) Page�911
Item#18.
2) Label plots showing actual shaft or part rotation frequency, bearing
inner and outer race ball pass frequencies, gear mesh frequencies
and relevant equipment excitation frequencies on the plot; label
probable cause of vibration peaks whether in excess of specification
limits or not.
3) Label plots with equipment identification and operating conditions
such as tag number, capacity, pressure, driver horsepower, and point
of vibration measurement.
4) Plot motor spectra on a log amplitude scale versus frequency.
d. For low speed equipment, plot peak vibration displacement versus
frequency as well as velocity versus frequency.
e. Provide name of manufacturer and model number of the vibration
instrumentation used, including analyzer and accelerometer used together
with mounting type.
3.02 PLANNING PHASE
A. Submit test plans as specified in Section 017517 and this Section.
1. Indicate test start time and duration, equipment to be tested, other equipment
involved or required; temporary facilities required, number and skill or trade of
personnel involved; safety issues and planned safety contingencies;
anticipated effect on Owner's existing equipment and other information
relevant to the test.
2. Provide locations of all instruments to be used for testing. Provide calibration
records for all instrumentation.
3.03 COMMISSIONING PHASE
A. Source testing:
1. Witnessing not required unless specified otherwise in equipment section.
2. Witnessed tests: Schedule test date and notify Engineer at least 30 days prior
to start of test.
3. Test equipment as specified in Section 01_75_17 and equipment sections.
4. Test fluids as specified in Section 01_75_17.
5. Submit reports as specified in Section 01_75_17.
B. Installation testing:
1. Test equipment as specified in Section 01_75_17 and equipment sections.
C. Functional testing:
1. Witnessing required as specified in Section 01_75_17.
2. Schedule test date and notify Engineer at least 7 days prior to start of test.
3. Test equipment as specified in equipment sections. Test fluids as specified in
Section 01 75 17.
4. Submit reports as specified in Section 01_75_17.
D. Clean Water Facility Testing:
1. Test equipment as specified in Section 01_75_17 and equipment sections.
E. Closeout documentation:
1. Provide closeout documentation as specified in Section 01_75_17 and
equipment sections.
March 2021 - DRAFT 46 05 94-12 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_05_94(IDS50) Page 912
Item#18.
3.04 PROCESS START-UP PHASE
A. Process start-up:
1. Process start-up equipment as specified in Section 01_75_17 and equipment
sections.
B. Process Operational Period:
1. Operate equipment as specified in Section 01_75_17 and equipment sections.
2. Test fluids as specified in Section 01_75_17.
END OF SECTION
March 2021 - DRAFT 46 05 94-13 1170
pwalCarollolDocumentslClient/IDIMeridian/11700A101SpecificationslPre-Purchasel46_05_94(IDS50) Page�913
Item#18.
SECTION 46_63_83.01
PHOSPHORUS PRECIPITATION SYSTEM
PART1 GENERAL
1.01 SUMMARY
A. Scope of Work for Phosphorous Precipitation System Supplier (Supplier):
1. The Supplier shall furnish the process equipment for a Phosphorus
Precipitation System (System), as shown on the Drawings and specified
herein.
2. Process equipment to be furnished by Supplier under this Section includes,
but is not limited to, the following:
a. Phosphorus Precipitation Reactors (Reactors), complete with Reactor
support legs, access platforms, pipe connections, and removable Reactor
cover.
b. Phosphorus Precipitation Blowers.
c. Phosphorus Precipitation Aeration Diffusers and Appurtenances.
d. Phosphorus Precipitation Struvite Pumps.
e. Magnesium Chloride Bulk Storage Tank.
f. Magnesium Chloride Chemical Feed System.
g. Antifoam Chemical Feed System.
h. Instrumentation.
i. Process Control Panel and PLC Control System (including all
programming and integration).
B. Unless stated otherwise herein, process equipment to be furnished by the to-be-
determined contractor (Contractor) to complete System includes, but is not limited
to, the following:
1. Motor control center (MCC) including variable frequency drives (VFD)for
control of Phosphorus Precipitation Blowers.
2. Air, chemical and sludge/struvite piping and valves that interconnects the
System process equipment.
3. Power supply and communication connection including conduits and wiring to
System process equipment.
4. Concrete support pads and building to house System process equipment.
C. Supplier agrees that the System design, as specified in this Specification, the
related specification sections, and on the Drawings, will meet all performance
requirements. Any modifications to the specified equipment required to meet the
performance requirements that are attributed to the performance of the System
shall be the full responsibility of the Supplier.
D. Responsible Parties:
1. The following define the responsible parties associated with the Project:
a. Owner: City of Meridian, ID.
b. Contractor: To be determined by future bidding.
c. Engineer: Carollo Engineers.
d. Supplier: CNP Technology Water and Biosolids Corp.
March 2021 - DRAFT 46 63 83.01-1 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 915
Item#18.
E. Related sections:
1. Section 01 33 00 - Submittal Procedures.
2. Section 01_75_17 - Commissioning.
3. Section 01_78_23 - Operation and Maintenance Data.
4. Section 01 78 36 - Warranties and Bonds.
5. Section 01_81_01 - Project Design Criteria.
6. Section 43_11_33 - Rotary Lobe Blowers.
7. Section 43_23_57.10 - Progressing Cavity Pumps.
8. Section 43_33_20.01 - Liquid Chemical Diaphragm-Type Metering Pumps.
9. Section 43_41_43 - Polyethylene Tanks.
10. Section 46_05_94 - Mechanical Equipment Testing.
11. Section 46_63_83 - Phosphorus Recovery System.
12. Section 40 61 00 - Common Work Results for Process Control and
Instrumentation Systems.
13. Section 40_61_05- Packaged Control System Components.
14. Section 40_71_15 - Flow Measurement: Magnetic Flowmeters.
15. Section 40_72_24 - Level Measurement: Radar Pulse Time of Flight.
16. Section 40 72 36 - Level Measurement: Capacitance
17. Section 40 72 76 - Level Measurement: Switches.
18. Section 40 73 13 - Pressure/Vacuum Measurement: Gauges.
19. Section 40 73 23 - Pressure/Vacuum Measurement: Direct.
20. Section 40 73 64 - Pressure/Vacuum Instrument Valves.
21. Section 40 74 66 - Temperature Measurement: Temperature Switches.
22. Section 40_75_13 - Analyzers: pH.
23. Section 40_80_01 - Commissioning for Instrumentation and Controls.
1.02 SYSTEM DESCRIPTION
A. The System supplies magnesium chloride and low-pressure air to welded stainless
steel Reactors receiving anaerobically digested material. Positive displacement
blowers provide air for Reactor mixing and pH control. Magnesium chloride is dosed
based on a magnesium to soluble phosphorus ratio to the top of the Reactor for the
precipitation of struvite. Struvite crystals are removed periodically from the bottom of
the Reactor using an automated valve and progressive cavity pump. Struvite
crystals are either pumped to the top of the reactor (recycle mode) or to the Owner's
existing Digester No. 3 - Sludge Storage Tank (waste).
1.03 DESIGN CRITERIA
A. The System shall be designed based on the flow and load conditions listed below:
1. Design flow to the reactors (2020): 76 gpm.
2. Design flow to the reactors (2040): 145 gpm
3. Intermittent flushing flow to the reactors: up to 400 gpm:
a. Design intent is to provide flushing capabilities for several times per
day at up to 2 minutes per flush. Ultimate flushing schedule will be
dictated by the Owner's staff based on prevailing treatment conditions
at solids handling.
4. Minimum reactor detention time (all tanks) at 2040 design flow: 4.5 hours.
March 2021 - DRAFT 46 63 83.01-2 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 916
Item#18.
5. Digested solids feed properties:
a. TSS: 1.3 percent to 2.5 percent.
b. Dissolved ortho-phosphate: 310-340 mg/L.
c. Dissolved ammonia nitrogen: Greater than 900 mg/L.
B. The guaranteed system performance shall be:
1. The content of free (dissolved) ortho-phosphate between inlet and outlet of the
reactor is reduced by 90 percent.
2. The dose of magnesium required to achieve the above phosphorus removal
performance shall be no greater than 1.5 moles of magnesium added per
1.0 moles of free ortho-phosphate fed to the reactor.
3. Struvite particle size:
a. The minimum size of struvite particles produced in the system should
be sufficiently large and dense to achieve a minimum of 80 percent of
struvite mass removal during digested sludge dewatering.
C. The airflow to the Reactors will be supplied by rotary lobe blowers and the airflow
varied to maintain the desired flow rate to achieve sufficient mixing and sludge pH
to meet the performance requirements of the System. The rotary lobe blowers shall
be sized by the Supplier such that there is sufficient air volume and pressure to
operate the System as designed.
D. Comply with structural design requirements included in the contract documents.
E. Coordinate with mechanical equipment and instrumentation requirements specified
under each technical equipment specification.
1.04 QUALITY ASSURANCE
A. All equipment required for the System shall be furnished by a single entity (Supplier)
who, with the Contractor, shall be responsible for completeness of the system. The
Supplier shall be the sole source of information on all equipment furnished
regardless of the manufacturing source of the equipment.
B. Requirements of regulatory agencies and reference standards:
1. Comply with all local and federal regulations.
2. Comply with all necessary local and federal codes.
3. Also refer to Section 01 81 01.
1.05 SUBMITTALS
A. Submittals shall be submitted and approved by Owner, Contractor, and Engineer
prior to fabrication of equipment provided by Supplier. Submit all documentation in
electronic format (searchable PDF) to Engineer and Contractor. Except as may be
provided in technical specifications or under special circumstances, a submittal will
be returned to Supplier within 10 working days. If resubmittal required, Supplier
shall provide resubmittal within 15 calendar days.
B. Submit product data and shop drawings, operation and maintenance manuals, and
test reports to the Engineer for review as specified in Sections 01_33_00,
01_78_23, and as specified under each technical equipment specification.
March 2021 - DRAFT 46 63 83.01-3 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 917
Item#18.
C. Other:
1. Operation and maintenance manual in accordance with Owner requirements.
2. Unless noted otherwise, a list of spare parts and tools necessary to maintain
the equipment for a period of 5 years shall be provided.
a. Aeration diffusers:
1) 20 percent of the total diffuser membranes utilized on the project.
2) 10 percent of the perforated diffuser mounting hardware.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Delivery, storage, and handling of specified equipment and appurtenances will be in
accordance with Supplier recommendations.
B. Supplier's instructions shall be provided for unloading, examination, preparation,
and installing of the specified equipment and appurtenances.
1.07 GUARANTEE
A. The performance requirements of the system will be demonstrated by a
performance test during the first 6 months of operation, following stabilization of the
process. The performance test will demonstrate that the Supplier has complied with
the phosphorus removal criteria and chemical feed criteria specified herein.
1.08 PATENTS
A. The Supplier shall indicate if any patents or licenses are involved because of
equipment furnished, or process employed. The Supplier shall assume all costs of
patent fees or licenses for equipment or processes, and shall defend and save
harmless the Contractor, Owner and Engineer, and their agents from damages,
judgments, claims and expenses arising from license fees or claimed infringements
or any letters of patent or patent right, or because of royalty or fee for the use of any
equipment or process, structural feature or arrangement of any of the component
parts of the equipment supplied by Supplier when operated and maintained as
instructed by Owner; and the price stipulated for all such patent fees, licenses, or
other costs pertaining thereto.
B. License fees or royalties required in connection with use of the System shall be
included in the Contract Price.
PART PRODUCTS
2.01 SUPPLIER
A. Subject to compliance with the Contract Documents, the following Suppliers are
acceptable:
1. CNP Technology Water and Biosolids Corp, Kenosha, WI.
2. No equal.
2.02 GENERAL
A. All flanges shall be ANSI 125# standard sizes.
March 2021 - DRAFT 46 63 83.01-4 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 918
Item#18.
B. Allow for future struvite product recovery by accommodating the addition of reactor
tanks or extensions to the reactor tanks, plus the addition of pumps, blowers,
metering pumps, accessories, and a grit washer for separation of the product.
Submittals shall indicate the location and size of all connections to future equipment
and piping.
C. All metallic components in contact with process fluid shall be constructed of Type
316 stainless steel, unless specified otherwise under each technical equipment
specification.
2.03 COMPONENTS
A. Phosphorus precipitation reactors:
1. Provide reactors per Section 46_63_83.
2. Provide at least two reactor tanks, so that retention time at 2020 flow is within
the 4-5 hour HRT range and meeting the minimum HRT at 2040 flow provided
above.
B. Aeration equipment:
1. Provide rotary lobe blowers per Section 43_11_33.
2. Provide Abwasser Beluftungs Und Klartechnik (ABK) IFU Type VMS
perforated diffusers, or Supplier's recommended diffusers. Perforated diffuser
system furnished with the System shall be designed to meet the aeration
requirements as calculated by the Supplier.
C. Pumping equipment:
1. Provide progressing cavity pump per Section 43_23_57.10.
2. Pumps will be installed inside a building, underneath the Phosphorus
Precipitation Reactor.
D. Chemical storage and feed:
1. Provide magnesium chloride metering pump system and antifoam metering
pump system per Section 43_33_20.01.
2. Provide magnesium chloride storage tank and unloading station per
Section 43 41 43.
E. Instrumentation:
1. Magnetic flow meters in accordance with Section 40_71_15.
2. Thermal mass flow meters in accordance with Section 40 71 76.
3. Level transmitter in accordance with Section 40_72_24 and 40 72 36.
4. Level switches in accordance with Section 40 72 76
5. Pressure gauges in accordance with Section 40_73_13.
6. Pressure devices in accordance with Section 40 73 23.
7. Pressure instrument valves in accordance with Section 40 73 64.
8. Temperature switches in accordance with Section 40_74_66.
9. pH analyzer in accordance with Section 40_75_13.
F. Controls:
1. PLC Cabinet and control system programming provided in accordance with
Sections 40 61 05 and 40 64 01.
2. Programming and integration by Supplier.
March 2021 - DRAFT 46 63 83.01-5 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 919
Item#18.
G. Accessories:
1. Valves:
a. Provide 1 manual and 2 electrically actuated knife gate valves for each
reactor discharge in accordance with Section 40_05_65.01.
PART 3 EXECUTION
3.01 GENERAL
A. The Contractor shall inspect interior and exterior of the Reactors for defects upon
receipt at the job site and after installation. Any defects shall be repaired by
Supplier.
B. The Contractor shall provide the following for installation of system components:
Concrete slab and building for Phosphorus Precipitation Reactor and
appurtenances.
3.02 INSTALLATION
A. General
1. Supplier shall provide installation instructions. Contractor to install products in
accordance with manufacturer's and Supplier's instructions.
2. Contractor shall furnish all consumables prior to operation of the reactor.
3. Unless specified otherwise under each technical equipment specification,
Supplier shall furnish all anchoring hardware for the supplied equipment.
3.03 CLEANING
A. Supplier shall provide recommendations for cleaning all Reactor surfaces, inside
and out, and appurtenances after installation.
3.04 SOURCE TESTING:
A. Conduct Factory Acceptance Test (FAT) in accordance with Section 40_80_01.
3.05 FIELD QUALITY CONTROL
A. A Supplier's factory representative, who has complete knowledge of the proper
operation and maintenance of the specified equipment, shall be provided to instruct
representatives of the Contractor, Engineer, and Owner on the proper installation
and operation and maintenance.
B. Field testing, calibrating, and training of the control system and instrumentation in
accordance with Section 40 80 01.
C. Pre-demonstration Test:
1. The Supplier shall provide the services of a factory trained I&C engineer to
check and verify the PLC program functionality (Dry testing).
March 2021 - DRAFT 46 63 83.01-6 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 920
Item#18.
2. Instruments and other devices that require calibration and checkout will be
carried out after the Contractor has the equipment installed and verified
continuity. Instruments and devices shall be configured and demonstrated to
function prior to start-up. A document indicating the set points and calibration
shall be furnished for documentation records.
3. Complete pressure testing for all piping connected to or included in the
System. Include testing of feed, discharge, and overflow piping.
4. Fill the Phosphorus Precipitation Reactor with clean water and verify no
leakage from any component in the system:
a. Verify water tight seal on valves below the reactor using the flushing/drain
connections.
5. Demonstrate gravity flow from the system through the normal discharge piping
and emergency overflow piping.
6. Complete Pre-demonstration Testing for individual components of the system
specified in other specification sections.
7. Operate the complete System using water as the working fluid:
a. Fill the reactor with water and operate for a minimum of 24 hours without
providing continuous forward flow to the system.
1) Operate chemical metering pumps in manual mode.
2) Operate blowers in manual mode.
3) Operate the phosphorus precipitation pump in manual mode.
4) Verify operation of motorized valves.
5) Operate antifoam metering pumps in automatic mode. Demonstrate
operation of the pump based on high level signal from the reactor.
6) Demonstrate operation of the emergency overflow.
7) Add process water during the test as required to maintain the
necessary reactor volume.
b. Operate the system for a minimum of 8 hours while providing continuous
forward flow to the system using process water:
1) Provide process water to the system at a rate of approximately
60 gpm.
2) Demonstrate operation of the normal overflow from the reactor.
3) Operate chemical metering pumps in automatic mode. Demonstrate
control of the pump based on operator dosing setpoint and measured
flow to the reactor.
4) Operate blowers in automatic mode as recommended by the
Supplier.
5) Operate the struvite pump in automatic mode.
6) Operate antifoam metering pumps in automatic mode. Demonstrate
operation of the pump based on high level signal from the reactor.
7) Demonstrate operation of the emergency overflow.
3.06 DEMONSTRATION TEST
A. See Specification Section 01_75_17.
B. Performance testing:
1. The Owner shall be responsible for carrying out the performance testing, for
collecting all samples, for carrying out all laboratory tests and for keeping such
detailed records as may be necessary for determining whether the performance
guarantees have been met.
March 2021 - DRAFT 46 63 83.01-7 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 921
Item#18.
a. Copies of the laboratory results and records shall be submitted to the
Supplier and Engineer.
b. For the duration of the Performance Test, the Owner shall maintain daily
log sheets, operator notes, sample inspections, and instrument charts
produced in operation of the System.
c. Supplier shall review the records and laboratory results and provide
guidance to the Owner regarding the System operation.
2. The performance test shall be subject to the following general conditions:
a. All volumes specified shall be measured by tank gauges or calibrated
meters.
b. All laboratory analysis methods will be performed by the Owner or
Owner's representative laboratory. A list of methods will be provided to
the Supplier prior to the start of the Performance Test.
c. The Owner shall furnish all materials, utilities, services and personnel as
required to operate the plant during the performance tests.
d. The Contractor will notify the Supplier in writing thirty days in advance of
beginning the performance test.
C. The duration of the performance test shall be 30 days. The result of the
performance test shall be based on the average of the daily measurements.
D. The following recordings and samples shall be taken and analyzed by Owner to be
used for evaluation of the System during the Performance Test. All samples shall be
taken once daily for purposes of Performance Test:
1. System Flow: Influent (continuously measured - gallons per day).
2. TSS: Influent (mg/L).
3. Mg: Influent/Effluent (mg/L).
4. Alkalinity: Influent/Effluent (mg/L).
5. NH4-N: Influent/Effluent (mg/L).
6. Ortho-P: Influent/Effluent (mg/L).
7. Total-P: Effluent/Centrate (mg/L).
8. pH: Influent/Effluent (S.U.).
9. Temperature: Influent (degrees Celsius).
E. The Supplier and Owner will jointly review performance of the process system to
determine compliance with performance guarantees. Review will include, but not be
limited to, a comparison of influent and process design basis with the actual
performance results.
F. The Owner will promptly notify the Supplier of the failure to meet any process
guarantee and specify the respect in which such guarantee has not been met.
G. If the Supplier disputes any claimed failure, notice of such dispute shall be furnished
promptly to Owner.
B. Performance standards and exclusive remedy:
1. In the event that the system does not achieve the required level of
performance during the test period, the Supplier shall be permitted to conduct
two additional tests to meet the specified process guarantee criteria.
2. All additional testing must be concluded within three months upon completion
of the Pre-Demonstration Period.
March 2021 - DRAFT 46 63 83.01-8 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 922
Item#18.
3. If the system fails to achieve the required phosphorus removal and chemical
dose during the performance test period and fails any additional tests, the
Supplier shall pay for modifications to improve the performance.
END OF SECTION
March 2021 - DRAFT 46 63 83.01-9 1170OA10
pw:/ICarollo/DocumentslClient/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83.01(IDS50) Page 923
Item#18.
SECTION 46_63_83
PHOSPHORUS PRECIPITATION SYSTEM REACTOR
PART1 GENERAL
1.01 SUMMARY
A. Scope of Work for Phosphorous Precipitation System Reactor Supplier (Supplier):
1. The Supplier shall furnish the process equipment for a Phosphorus
Precipitation Reactor (Reactor), as shown on the Drawings and specified
herein. Other Phosphorous Precipitation System (System) components are
covered under separate specifications.
2. Process equipment to be furnished under this Section includes, but is not
limited to, the following:
a. Phosphorus precipitation Reactor, complete with Reactor support legs,
access platforms, pipe connections, and removable Reactor cover.
b. System accessories required for a complete and functional Reactor
system including, but not limited to, internal diffuser ring, diffuser supports,
baffles, manhole with access door, and pipe and electrical conduit
supports.
c. Design of anchor bolts for anchorage of Reactor to concrete pad. Supply
of anchor bolts by supplier, installation by Contractor.
B. Supplier agrees that the design, as specified in this Specification and on the
Drawings, will meet all performance requirements. Any modifications to the Reactor
required to meet the performance requirements that are attributed to the
performance of the System shall be the full responsibility of the Supplier.
C. Responsible Parties:
1. The following define the responsible parties associated with the Project:
a. Owner: City of Meridian.
b. Contractor: To be determined pending bidding by OWNER.
c. Engineer: Carollo Engineers.
d. Supplier: CNP Technology Water and Biosolids Corp.
D. Related sections:
1. Section 01_81_01 - Project Design Criteria.
1.02 REFERENCE STANDARDS
A. American Institute of Steel Construction (AISC) - 360 - Specification for Structural
Steel Buildings, 13th Edition or newer.
B. American Water Works Association (AWWA):
1. AWWA D100—Welded Steel Tanks, 2011 Edition or newer.
C. American Petroleum Institute (API):
1. 650 - Welded Steel Tanks for Oil Storage, 11 th Edition with addendum and
errata through 2011.
March 2021 - DRAFT 46 63 83-1 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 925
Item#18.
D. American Society of Mechanical Engineers (ASME):
1. Boiler and Pressure Vessel Code.
E. International Society for Testing and Materials (ASTM):
1. A276 - Standard Specification for Stainless Steel Bars and Shapes.
2. A304 - Standard Specification for Stainless Steel.
3. A325 - Standard Specification for High-Strength Bolts for Structural Steel
Joints.
4. A380 - Standard Practice for Cleaning, Descaling, and Passivation of Stainless
Steel Parts, Equipment, and Systems.
F. American Welding Society (AWS):
1. B2.1 - Standard for Welding Procedure and Performance Qualifications.
2. D1.6 - Structural Welding Code for Stainless Steel.
3. D10.4 - Recommended Practices for Welding Austentic Chromium-Nickel
Stainless Steel Piping and Tubing.
G. Occupational Safety and Health Act (OSHA).
H. 2015 International Building Code (IBC).
1.03 SYSTEM DESCRIPTION
A. The System supplies magnesium chloride and low-pressure air to a welded
stainless steel Reactor receiving anaerobically digested material. Positive
displacement blowers provide air for Reactor mixing and pH control. Magnesium
chloride is dosed based on a magnesium to soluble phosphorus ratio to the top of
the Reactor for the precipitation of struvite. Struvite crystals are removed
periodically from the bottom of the Reactor using an automated valve and
progressive cavity pump.
1.04 DESIGN CRITERIA
A. Phosphorus Precipitation Reactor:
1. Reactor tank dimensions and capacity (CNP Reactor):
a. Inside diameter: 13.78 feet.
b. Height: 34.00 feet.
c. Minimum volume: 20,000 gallons.
d. Number of tanks: 2.
2. Maximum instantaneous design Reactor inlet flow rate: 400 gallons per
minute.
3. The design of all items covered by this Section, including Reactor anchor
bolts, shall be designed and sealed, or reviewed and sealed by a registered
professional engineer in the State of Idaho.
4. The Reactor will be installed in accordance with the specified requirements of
this Section and the Supplier's instructions.
5. Pipe supports shall be the same material as the Reactor shell and shall be
provided and designed by the Supplier as indicated on the Drawings. Pipe
support systems shall be suitable for support of insulated and heat traced
piping.
6. Fittings: Pipe connections, nozzles, manholes, and accessories, as indicated
on the Drawings and in this Section, shall be by the Supplier.
March 2021 - DRAFT 46 63 83-2 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 926
Item#18.
7. Design Loads:
a. Pressure: Vent Reactor to prevent pressurization of the tank caused by air
flowing in and out of the Reactor with the cover installed. Design Reactor
vent for the airflow anticipated to enter the tank during normal operation
as well as under vacuum conditions if the tank was drained with the cover
installed.
b. Structural Design Requirements:
1) The structural design criteria to be used shall be as specified in
Section 018101. Where not explicitly stated in that section, the
Reactor Engineer of Record shall select design criteria based upon
reference documents such as ASCE7-10 or API Standard 650.
2) Structural design for concrete anchors (anchor bolts) shall conform to
the requirements of American Concrete Institute (ACI)
Standard 318 — Building Code Requirements for Structural Concrete
and Commentary, year 2011 edition. As a minimum, the provisions of
Appendix D —Anchoring to Concrete, shall be applied to the design
of the anchorage.
c. Reactor supports: Designed by Supplier in accordance with project
requirements and specification requirements herein.
d. Assembly bolts:
1) Bolted connection shall be avoided wherever suitable welded
connection can be provided.
2) In accordance with ASTM A193, Grade BBM.
3) Stainless steel.
e. Concrete anchors (anchor bolts) and chairs:
1) Anchor bolts, nuts and washers used for design of the Reactor
anchorage to concrete foundations shall conform to the following
material standards:
a) Type 316 stainless steel.
f. Openings in Reactor shell:
1) Locate openings in the tank shell where indicated on the Drawings.
2) Design and provide suitable reinforcement and welding around
opening in the Reactor shell:
a) Reinforcement and welding shall meet the minimum
requirements of reference document API 650, Section 5.
g. Pipe supports:
1) Provide process pipe, chemical pipe and electrical conduit supports
attached to the shell and framing that extend from the Reactor out to
the location of the items to be supported.
2) Pipe and conduit supports shall be spaced a maximum of 5 feet on
center.
3) Pipe supports shall be fabricated, including predrilled with holes, as
required for the attachment of the supported items. Pipe support
locations and other requirements shall be coordinated with the
Drawings.
h. Pipe and nozzle connections:
1) Locate pipe connections where indicated on the Drawings.
2) Provide suitable reinforcement and weld around pipe connections to
the Reactor shell.
3) Capable of resisting the following loads:
a) Dead loads.
b) Hydraulic thrust loads.
March 2021 - DRAFT 46 63 83-3 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 927
Item#18.
c) Wind loads.
d) Seismic loads.
e) Pipe Loads.
i. Shell plates:
1) Roll curved shell plates to the required radius regardless of
thickness.
j. Corrosion Allowance:
1) Shell plates and structural framing members used to fabricate the
Reactor tank, support legs and bracing shall include an additional
corrosion allowance thickness of 0.0625 inch.
k. Reactor overflow:
1) Design the Reactor overflow for 1.25 times the maximum flow rate.
2) Overflow type, locations, and details as indicated on the Drawings.
I. Flashing skirt:
1) The Reactor will be installed outside with a new treatment building
installed around the legs of the reactor, as indicated on the Drawings.
2) The Supplier shall provide a continuous and weather tight flashing
skirt around the full circumference of the Reactor. The skirt shall
extend horizontally off the shell of the Reactor.
1.05 QUALITY ASSURANCE
A. All equipment required for the System shall be furnished by a single entity (Supplier)
who, with the Contractor, shall be responsible for completeness of the system. The
Supplier shall be the sole source of information on all equipment furnished
regardless of the manufacturing source of the equipment.
B. Qualifications:
1. Fabricator qualifications:
a. Regularly engaged in the design, fabrication, and erection of welded steel
tanks of the type specified in this Section.
b. Provide a list of all steel tank projects completed in the last 5 years,
including names, addresses, and telephone numbers of the reference for
each project.
c. Reactor designer shall be a registered professional civil or structural
engineer in the State of Idaho, or a registered professional civil or
structural engineer in the State of Idaho shall review and stamp the
Reactor design.
d. Familiar with applicable regulations, codes, fire and safety orders.
e. Located within the United States.
C. Welder and Weld Inspector Qualifications:
1. Fabrication certification requirements:
a. Qualify personnel and procedures according to AWS B2.1 and D1.6
Structural Welding Code.
2. Weld inspection certification requirements:
a. Certified Welding Inspector (CWI): Certified by American Welding Society
to Standards AWS QC-1-88 and prior inspection experience using
governing welding codes.
March 2021 - DRAFT 46 63 83-4 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 928
Item#18.
b. Weld testing personnel: Personnel certified to perform non-destructive
testing (NDT) in accordance with current American Society of
Nondestructive Testing. Recommended practice No. SNT-TC-1A and all
supplements, NDT Level II.
D. Warranty:
1. Phosphorus Precipitation System Reactor:
a. Supplier shall guarantee the Reactor is suitable for intended service.
b. Supplier to warrant against defects in materials and workmanship of the
Reactor and that the Reactor will not fail or leak for a period of two (2)
years from the date of acceptance. Reactor Supplier shall provide the
warranty and repair any failures or leaks at no cost to the Owner.
1.06 SUBMITTALS
A. Submittals shall be submitted and approved by Owner, Contractor and Engineer
prior to fabrication of Reactor and any other equipment by Supplier. Submit all
documentation in electronic format (searchable .PDF) to Contractor. Except as may
be provided in technical specifications or under special circumstances, a submittal
will be returned to Supplier within 10 working days. If resubmittal required, Supplier
shall provide resubmittal within 15 calendar days.
B. Calculations and shop drawings:
1. Phosphorus Precipitation System Reactor:
a. Submit design calculations prior to or at same time that the detailed
Reactor drawings are submitted.
b. Design calculations shall be signed and sealed by a structural engineer
who is experienced in the design of steel tanks and registered in the State
of Idaho.
c. Submitted calculations shall include the following minimum data:
1) Printout or written hand calculations for each component of the
Reactor, its anchorage and appurtenances. These calculations shall
report as a minimum:
2) Actual design force or stress when subject to the specified design
criteria and calculated loads.
3) Available force or stress capacity.
4) Where applicable, deflection of individual members and the total
horizontal drift of the installed Reactor, when subject to controlling
loading combinations, assuming a fixed base support at the top of
the concrete foundation(s).
5) Reactor foundation loads (basic uncombined and combined)
including but not limited to dead, live, snow, ice, wind, and seismic.
d. Member sizes, dimensions, standard shape designations where
applicable and anchor bolt layouts.
e. Detail drawings with dimensions and callouts of all framing and bolted
connections, clips and lugs, hold down lugs, pipe brackets, and anchor
bolts.
f. Details of structural support members and lifting lugs.
g. Reactor and equipment weight when empty and when in service.
March 2021 - DRAFT 46 63 83-5 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 929
Item#18.
C. Certifications:
1. Phosphorus Precipitation System Reactor:
a. Documentation that demonstrates compliance with quality assurance
requirements.
b. Certified mill tests for stainless steel plate, structural members and each
component of bolted connections.
c. Fabricator's Certificate of Compliance with fabrication requirements.
d. Certify that the Reactors and accessories have been properly designed,
fabricated, erected, installed, inspected, and tested in accordance with,
and are ready for full-time service.
D. Shop Drawings:
1. Product technical data including:
a. Supplier's installation instructions for all equipment provided as part of the
System.
2. Complete fabrication and/or layout drawings including overall equipment layout
and piping interconnection drawings.
a. Show locations of all equipment, instrumentation, control panels, and
piping.
b. Show delineation of interfaces between Supplier and Contractor supplied
equipment, piping, and wiring for the complete System.
E. Welding:
1. Quality Assurance Inspection Reports.
F. Stainless Steel:
1. Product data.
2. Submit pickling and passivation procedures and material descriptions.
G. Other:
1. Operation and maintenance manual in accordance with Owner requirements.
2. A list of spare parts and tools necessary to maintain the equipment for a period
of 5 years.
1.07 DELIVERY, STORAGE, AND HANDLING
A. Delivery, storage, and handling of specified equipment and appurtenances will be in
accordance with Supplier recommendations.
B. Supplier's instructions shall be provided for unloading, examination, preparation,
and installing of the specified equipment and appurtenances.
C. Phosphorus Precipitation Reactor:
1. Prepare and protect Reactor for shipment in accordance with Supplier's
recommendations. In addition, prepare and protect the Reactor for shipment
as follows:
a. Mount Reactor on padded cradles supporting 120 degrees of the Reactor
circumference.
b. Reactor shall be mounted on protective framework so constructed as to
provide for easy handling with lifting lugs, cleats, to permit handling by
crane. Pipe connections, manways, or other fittings shall not be used for
lifting.
March 2021 - DRAFT 46 63 83-6 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 930
Item#18.
c. Protect all flanged pipe connections with wooden blinds bolted to the
flange and having a diameter of 2 inches greater than the outside
diameter of the flange. All openings are to be securely covered to prevent
entrance of dirt, water, and debris.
d. Do not ship components or other pieces loose inside the Reactor.
e. Load Reactor with at least 2 inches of clearance between the Reactor
(including fittings) and the bulkheads or bed of the vehicle.
f. Regardless of the mode of transportation, firmly fasten and pad all
components to prevent shifting of the load or flexing of components when
in transit.
1.08 EXTRA MATERIALS
A. Phosphorus Precipitation Reactor:
1. Provide the following spare parts: Two (2) sets of each size of gasket used for
the Reactor.
1.09 PATENTS
A. The Supplier shall indicate if any patents or licenses are involved because of
equipment furnished, or process employed. The Supplier shall assume all costs of
patent fees or licenses for equipment or processes, and shall defend and save
harmless the Contractor, Owner and Engineer, and their agents from damages,
judgments, claims and expenses arising from license fees or claimed infringements
or any letters of patent or patent right, or because of royalty or fee for the use of any
equipment or process, structural feature or arrangement of any of the component
parts of the equipment supplied by Supplier when operated and maintained as
instructed by Owner; and the price stipulated for all such patent fees, licenses, or
other costs pertaining thereto.
B. License fees or royalties required in connection with use of the System shall be
included in the Contract Price.
PART PRODUCTS
2.01 SUPPLIER
A. Subject to compliance with the Contract Documents, the following Suppliers are
acceptable:
1. CNP Technology Water and Biosolids Corp, Kenosha, WI.
2. Schwing Bioset, Inc., Somerset, WI.
2.02 GENERAL
A. All flanges shall be ANSI 125# standard sizes.
B. Phosphorus Precipitation Reactor:
1. Reactor shall be constructed of Type 316L stainless steel.
2. Reactor shall be free standing and installed outside of the equipment building.
3. The hopper bottom will be supported by a minimum of four columns.
4. Flow baffles and aeration diffusers will be provided as required to meet the
Supplier's design requirements.
March 2021 - DRAFT 46 63 83-7 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 931
Item#18.
5. The steel shell of the Reactor shall be of all welded construction utilizing rolled
flat plates that meet the material requirements of ASTM A240.
6. Nozzles shall have reinforcing pads where necessary for structural strength.
7. Reactors shall be completely shop welded. No field welding of Reactors is
permitted.
8. All welding shall be complete prior to installation.
9. Manholes in shell:
a. One 36-inch diameter manhole with bolted cover.
b. Provide suitable means to hold the manhole in an open position.
c. Use loose hinges to allow for easy bolting.
d. Provide gaskets for a watertight seal.
e. Provide suitable reinforcement and welding around openings in the
Reactor shell.
10. Pipe connections:
a. Provide flanged connections for all process piping including air, Reactor
feed, Reactor overflow, emergency overflow, and hopper discharge, as
indicated on the Drawings.
b. Locate pipe connections where indicated on the Drawings.
c. Provide suitable reinforcement and welding around pipe connections to
the Reactor shell.
11. Reactor cover:
a. Provide Reactor cover with construction and materials to match the
Reactor.
b. Provide lifting lugs and complete rigging plan for installation by Contractor.
c. Provide bolted connections with the Reactor shell with suitable
reinforcement and welding around the bolted connections between the
Reactor and Reactor cover.
d. Locate the following where indicated on the Drawings:
1) 24-inch access hatch.
2) Flanged connections for:
a) Reactor feed.
b) Reactor recycle.
c) Odorous air takeoff.
d) Process instrumentation.
e) Chemical conveyance.
f) Any other piping as indicated on the Drawings.
e. Provide suitable reinforcement and welding around pipe connections to
the Reactor cover.
12. Reactor Access:
a. Provide intermediate manway. Provide internal cross members suitable to
support scaffolding boards inserted through intermediate manway, to
support personnel access to diffusers for cleaning and replacement of
diffusers.
b. Provide platform at top of Reactor for access to all instrumentation,
manways, and access for cleaning.
c. Provide guardrail and handrail for platform.
d. All platform guardrail shall comply with OSHA 29 CFR 1910.24.
e. All grating and handrail shall be hot dipped galvanized. Structural support
members connected to the Reactor tank shall be stainless steel or hot dip
galvanized.
March 2021 - DRAFT 46 63 83-8 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 932
Item#18.
2.03 FABRICATION
A. Phosphorus Precipitation System Reactor:
1. In assembly and during welding, the component parts shall be adequately
clamped, supported and restrained to minimize distortion and for control of
dimensions. Weld reinforcement shall be as specified by the Reference
Standards, and excessive reinforcement shall be as ground down to within the
requirements. Upon completion of welding all weld splatter, flux, slag, and
burrs left by attachments shall be removed. Welds shall be repaired to produce
a workmanlike appearance, with uniform contours and dimensions. All external
corners and edges shall be ground to a 1/16-inch radius. All internal corners
and edges shall be ground to a 1/8-inch radius, or a greater radius if required
by the coating system.
2. All openings 4 inches and greater in nominal diameter shall be reinforced.
3. Reactor details shall use continuous seam welded joints and eliminate
unwelded joints that will promote corrosion or pockets that will accumulate
debris.
4. Stiffener and doubler plates shall be used where attachments to the shell will
result in excessive localized stresses due to welding supports or imposed
loads.
5. The entire Reactor interior shall present a smooth surface free of marked
depressions, offsets, abrupt edges, or other protrusions.
6. The Reactor and appurtenances shall be fabricated from a minimum number
of pieces, and longitudinal shell seams shall be staggered. Welding seams
shall be located to clear all nozzle openings. All flange faces shall be true to
the centerline of the nozzles, and bolt holes shall straddle center lines unless
noted elsewhere.
7. Manways shall be flanged, and, unless otherwise specified, have a nominal
diameter of at least 24 inches. The cover plate and flange shall each have a
net thickness, after machining, of at least 1/2 inch.
8. All fittings shall be flanged, unless specified otherwise.
9. Lifting lugs to be provided per the Supplier's recommendations to allow lifting
and placement of the Reactor. A safety factor of 2.0 applied to the maximum
permissible lifting load shall be used to design all lifting lugs. Lifting lug
material shall be the same as Reactor material.
10. Reactor Finish: Pickle and passivate after welding in accordance with ASTM
A380, prior to delivery on site. Do not deliver or install stainless steel
components that do not have an unblemished, uniform, even passivation layer
free of pitting, rust spots, heat tint, or discoloration of any kind.
PART 3 EXECUTION
3.01 GENERAL
A. The Contractor shall inspect interior and exterior of the Reactor for defects or
discoloration of stainless steel upon receipt at the job site and after installation. Any
defects upon delivery shall be repaired off-site by Supplier and re-delivered to job
site.
B. The Contractor shall provide the following for installation of system components:
Concrete slab, stairs, and building for Phosphorus Precipitation Reactor.
March 2021 - DRAFT 46 63 83-9 1170OA10
pw://Carollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 933
Item#18.
3.02 SHOP INSPECTION AND TESTING
A. After fabrication, but before any coating work, Reactor shall be subjected to a
hydrostatic pressure test in accordance with API 650.
B. Phosphorus Precipitation System Reactor
1. Reactor inspection includes, but is not limited to:
a. Visual inspection of all welds.
b. Spot radiography of the Reactor per API 650.
c. Dye pen test of the Reactor shell to the cone bottom joint.
d. Pneumatic test of all repads.
e. Hydrotesting.
C. All NDE including, but not limited to Magnetic Particle Testing (MT), Liquid Dye
Penetrant Testing (PT), Visual Examination (VT) will be performed to comply with
the requirements of API 650.
3.03 INSTALLATION
A. General
1. Supplier shall provide installation instructions.
B. Phosphorus Precipitation System Reactor:
1. The Reactor and components shall be adequately protected during
transportation. Damaged units will be rejected and shall be replaced with
undamaged units (or repaired in the field if acceptable by Owner).
2. Coating repairs, if required, shall be in accordance with Supplier
recommendations.
3.04 CLEANING
A. Supplier shall provide recommendations for cleaning all Reactor surfaces after
installation.
3.05 FIELD TESTING
A. Phosphorus Precipitation System Reactor
1. Hydrostatic leak test (24-hour duration) shall be conducted with the Reactor
full of clean water. If leakage occurs, the Reactor may be rejected and
replaced by Supplier with a new Reactor or repaired if repair approach is
acceptable to Owner.
B. A Supplier's factory representative, who has complete knowledge of the proper
operation and maintenance of the specified equipment, shall be provided to instruct
representatives of the Contractor on the proper installation and operation and
maintenance.
END OF SECTION
March 2021 - DRAFT 46 63 83-10 1170OA10
pw:/ICarollo/Documents/Client/ID/Meridian/11700A10/Specifications/Pre-Purchase/46_63_83(IDS50) Page 934
Item#18.
SYMBOL DRAWING VISIBLE FIELD - 1 FIELD-2 FIELD -3 FIELD-4 FIELD - 5 FIELD -6 SYMBOL DRAWING VISIBLE FIELD - 1 FIELD-2 FIELD -3 FIELD -4 FIELD - 5 FIELD -6
FIELDS FIELDS
M � m 1
Q HMI/SCADA SYSTEM 1 - TAG REFER REFER ACTION DESCRIPTION DESCRIPTION E - EXISTING INSTRUMENT 1 - TAG REFER REFER DESCRIPTION DESCRIPTION AREA NO. E - EXISTING
CN OPERATOR INTERFACE 2- LOOP NUMBER 1 2 O ALARM 2 5 F - FUTURE PRIMARY ELEMENT 1 2- LOOP NUMBER O O O O BUILDING NO. F - FUTURE
1p TERMINAL 3- FUNCTION NUM NUMERIC 6 a 3- FUNCTION 1 3 5 6 ROOM NO.
c� 6 3 4- DESCRIPTION SP - SET POINT 4- FURNISHED BY
1 a 5- DESCRIPTION STATUS 2 5- LOCATION
2 6- EXISTING/FUTURE TREND 5 6- EXISTING/FUTURE
0 5 INSTRUMENT/CONTROL ELEMENT 1 - TAG REFER REFER DESCRIPTION DESCRIPTION DESCRIPTION E - EXISTING
N PRIMARY FUNCTION 2- LOOP NUMBER O O O O F - FUTURE
Q OPERATOR ACCESSIBLE 3- FUNCTION
6 3 4- FURNISHED BY
N HARDWIRED 1/0 1 - TAG REFER REFER Al - ANALOG INPUT DESCRIPTION PAC - PROGRAMMABLE E - EXISTING 1 a 5- DESCRIPTION
m
� POINT 2- LOOP NUMBER �O O AO - ANALOG OUTPUT AUTOMATION F - FUTURE 2 5 6- EXISTING/FUTURE
3- FUNCTION 1 2 4 3 DI - DISCRETE INPUT CONTROLLER NO.
0 6 3 4- DESCRIPTION DO - DISCRETE OUTPUT PLC - PROGRAMMABLE Im
0 1 4 5- LOCATION HSC - HIGH SPEED COUNTER INPUT LOGIC INSTRUMENT/CONTROL ELEMENT 1 - TAG REFER REFER DESCRIPTION DESCRIPTION DESCRIPTION E - EXISTING
2 6- EXISTING/FUTURE RTD - RTD INPUT CONTROLLER NO. AUXILIARY FUNCTION 2- LOOP NUMBER O O O F - FUTURE
5 RIO - REMOTE I/O OPERATOR ACCESSIBLE 3- FUNCTION
VCP - VENDOR CONTROL 6 3 4- FURNISHED BY
PANEL NO. 1 a 5- DESCRIPTION
2 6- EXISTING/FUTURE
5
NETWORK/SOFTI/O 1 - TAG REFER REFER BUS ID DESCRIPTION PAC - PROGRAMMABLE E - EXISTING
mr-
2- LOOP NUMBER O CNET - CONTROLNET AUTOMATION F - FUTURE INSTRUMENT/CONTROL ELEMENT 1 - TAG REFER REFER DESCRIPTION DESCRIPTION LCP - LOCAL CONTROL E - EXISTING
7 3- FUNCTION 1 2 3 DNET - DEVICENET CONTROLLER NO. PRIMARY FUNCTION 2- LOOP NUMBER PANEL NO. F - FUTURE
6 3 4- DESCRIPTION ENET - ETHERNET/IP PLC - PROGRAMMABLE OPERATOR INACCESSIBLE 3- FUNCTION OO O O MCC - MOTOR CONTROL
1 a 5- LOCATION FF - FOUNDATION FIELDBUS LOGIC 4- FURNISHED BY XR - PROTECTION CENTER NO.
2 6- EXISTING/FUTURE MB - MODBUS RTU CONTROLLER NO. 6 3 5- LOCATION RELAY PCM - PROCESS CONTROL
5 7- DIGITAL NETWORK TABLE MB+ - MODBUS PLUS RIO - REMOTE I/O 1 a 6- EXISTING/FUTURE CR - CONTROL MODULE NO.
d MBTCP - MODBUS TCP VCP - VENDOR CONTROL 2 RELAY VCP - VENDOR CONTROL
DP - PROFIBUS DP PANEL NO. 5 IR - INTERPOSING PANEL NO.
PA - PROFIBUS PA RELAY
m PNET - PROFINET
INSTRUMENT/CONTROL ELEMENT 1 - TAG REFER REFER DESCRIPTION DESCRIPTION LCP - LOCAL CONTROL E - EXISTING
SERIAL - PROPRIETARY PROTOCOL AUXILIARY FUNCTION 2- LOOP NUMBER PANEL NO. F - FUTURE
OPERATOR INACCESSIBLE 3- FUNCTION OO O O MCC - MOTOR CONTROL
4- FURNISHED BY XR - PROTECTION CENTER NO.
6 3 5- LOCATION RELAY PCM - PROCESS CONTROL
1 a 6- EXISTING/FUTURE CR - CONTROL MODULE NO.
LOCAL OPERATOR 1 - TAG REFER REFER ACTION DESCRIPTION LOI - LOCAL OPERATOR E - EXISTING = RELAY VCP - VENDOR CONTROL
INTERFACE 2- LOOP NUMBER ALARM INTERFACE NO. F - FUTURE 2 IR - INTERPOSING PANEL NO.
3- FUNCTION OO O NUM - NUMERIC 2 5 LCP - LOCAL CONTROL 5 RELAY
6 3 4- DESCRIPTION SP - SET POINT PANEL NO.
1 a 5- LOCATION STATUS PCM - PROCESS CONTROL FIELD EQUIPMENT 1 - TAG REFER REFER DESCRIPTION DESCRIPTION AREA NO. E - EXISTING
2 6- EXISTING/FUTURE MODULE NO. NON-POWERED 2- LOOP NUMBER BUILDING NO. F - FUTURE
5 VCP - VENDOR CONTROL
PANEL NO. 6 3 3- FUNCTION/SIZE 3 3 6 ROOM NO.
a 4- FURNISHED BY
2 5- LOCATION
2
PILOT DEVICE 1 - TAG REFER REFER AM - AUTO/MANUAL DESCRIPTION LCP - LOCAL CONTROL E - EXISTING 5 6- EXISTING/FUTURE
OPERATOR INTERFACE 2- LOOP NUMBER BYPASS - BYPASS PANEL NO. F - FUTURE
3- FUNCTION 1 2 3 CL - CLOSE MCC - MOTOR CONTROL FIELD EQUIPMENT 1 - TAG REFER REFER DESCRIPTION DESCRIPTION AREA NO. E - EXISTING
s 3 4- DESCRIPTION E-STOP - EMERGENCY STOP CENTER NO. PRIMARY FUNCTION 2- LOOP NUMBER BUILDING NO. F - FUTURE
1 a 5- LOCATION FRLR - FIXED RATE/LEVEL RATE PCM - PROCESS CONTROL POWERED 6 3 3- FUNCTION 3 3 O ROOM NO.
2 6- EXISTING/FUTURE HOA - HAND/OFF/AUTO MODULE NO. a 4- FURNISHED BY
5 JOHC - JOG OPEN/HOLD/CLOSE RVSS- REDUCED VOLTAGE 5- LOCATION
JOJC - JOG OPEN/JOG CLOSE SOLID STARTER NO. 2 6- EXISTING/FUTURE
LH - LOW/HIGH VCP - VENDOR CONTROL 5
LOR - LOCAL/OFF/REMOTE PANEL N FIELD EQUIPMENT 1 - TAG MWH - MOTOR REFER DESCRIPTION DESCRIPTION DESCRIPTION E - EXISTING
LS - LEAD/STANDBY FREQUENCY
L - LOCK OUT STOP VFD - VARIABLEE AUXILIARY FUNCTION 2- LOOP NUMBER WINDING F - FUTURE
O O
LSR - LOCAL/STOP/REMOTE DRIVE NO. POWERED 3- FUNCTION HEATER
NOOT - NO OFFLINE/OFFLINE 6 3 4- FURNISHED BY TSH - TEMPERATURE
TRANSITION 14
5- DESCRIPTION SWITCH
OC - OPEN/CLOSE 2 6- EXISTING/FUTURE XSH - TORQUE
77 OLOL - ON LINE/OFF LINE 5 SWITCH
00 - OFF/ON
OP - OPEN
OSC - OPEN/STOP/CLOSE FIELD EQUIPMENT 1 - TAG MS - MOTOR REFER FVNR- FULL VOLTAGE 120VAC - 1P LCP - LOCAL CONTROL E - EXISTING
RST - RESET STARTER/DRIVE 2- LOOP NUMBER STARTER O NON-REVERSING STARTER 208VAC - 2P PANEL NO. F - FUTURE
a SAAM - SEMI AUTO/AUTO/MANUAL CUBICLE/CABINET 3- TYPE RVAT- REDUCED 3 FVR - FULL VOLTAGE REVERSING 208VAC - 3P MCC - MOTOR CONTROL
SEL - SELECT 6 4- VOLTAGE-POLE VOLTAGE AUTO STARTER 240VAC - 2P CENTER NO.
Q SP - STOP 1 - 2 5- POWER SOURCE TRANSFORMER PWS - PART-WINDING STARTER 240VAC - 3P PCM - PROCESS CONTROL
LO SPD - SPEED 6- EXISTING/FUTURE STARTER RVAT- REDUCED VOLTAGE AUTO 480VAC - 3P MODULE NO.
SS - START/STOP 3 RVSS- REDUCED TRANSFORMER STARTER 2400VAC - 3P VCP - VENDOR CONTROL
C) ST - START 4 VOLTAGE RVSS- REDUCED VOLTAGE SOLID 4160VAC - 3P PANEL NO.
5 SOLID STATE STATE STARTER
STARTER TS1W- TWO SPEED SINGLE
POWER DEVICE 1 - TAG CB - CIRCUIT REFER TM - THERMAL MAGNETIC 24VDC - 1 P DP - DISTRIBUTION E - EXISTING VFD - VARIABLE WINDING
U) PRIMARY FUNCTION 2- LOOP NUMBER BREAKER CIRCUIT BREAKER 120VAC - 1P PANEL NO. F - FUTURE FREQUENCY DRIVE VFD VFDTS2 TWO SPEED TWO WINDINGS
O - VARIABLE FREQUENCY
0�
OPERATOR ACCESSIBLE 3- FUNCTION DISC - DISCONNECT 208VAC - 2P LCP - LOCAL CONTROL DRIVE
0 6 3 4- VOLTAGE-POLE FU - FUSE 208VAC - 3P PANEL NO.
m 1 a 5- LOCATION 240VAC - 3P LP - LIGHTING PANEL NO.
2 6- EXISTING/FUTURE 240VAC - 2P MCC - MOTOR CONTROL
48
5 480VAC - 3P CENTER NO. INSTRUMENT BUBBLE LOCATIONS NOTES
Q-
u) 2400VAC - 3P PCM - PROCESS CONTROL
a, 4160VAC - 3P MODULE NO. O INSTRUMENT TAG IDENTIFICATION LETTERS TABLE
Q) PP - POWER PANEL NO. U
o VCP - VENDOR CONTROL w O2 OPERATOR PILOT DEVICE LEGEND
PANELNO. ._.—._._._._._._._._._._._._._._._._._._._.—._.—._.—._.—._.
ai POWER DEVICE 1 - TAG DISC - DISCONNECT REFER DESCRIPTION DESCRIPTION DESCRIPTION E - EXISTING I O EQUIPMENT TAGGING TABLE
m
AUXILIARY FUNCTION FOR 2- LOOP NUMBER O F - FUTURE z i 0
a, OPERATOR ACCESSIBLE 3- DESCRIPTION Q 4 1/0 TYPE DESIGNATIONS TABLE
DEVICES 6 3 4- DESCRIPTION w ._._._._._._._._._._._._._._._._._._._._._._._._._._._._.
1 a 5- DESCRIPTION 0 w SINGLE INSTRUMENT O5 INSTRUMENT TYPE DESIGNATIONS TABLE
2 6- EXISTING/FUTURE O 0 U
L z I_- a O U) WITH INTEGRAL
00 5 0 T � LU v _ TRANSMITTER O FURNISHED BY: FBO FURNISHED BY OWNER
v ILU LU
O w FBV FURNISHED BY VENDOR
POWER DEVICE 1 - TAG CB - CIRCUIT REFER MCP - MOTOR CIRCUIT 24VDC - 1 P DP - DISTRIBUTION E - EXISTING 0 z U
o PRIMARY FUNCTION 2- LOOP NUMBER BREAKER PROTECTOR 120VAC - 1 P PANEL NO. F - FUTURE '—I'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'—'
J SS - SOLID STATE CIRCUIT 208VAC - 2P LCP - LOCAL CONTROL OPERATOR 3- FUNCTION FU - FUSE O
INACCESSIBLE 6 3 4- VOLTAGE-POLE BREAKER 208VAC - 3P PANEL NO. w
a 1 a 5- LOCATION TM - THERMAL MAGNETIC 240VAC - 2P LP - LIGHTING PANEL NO. w _ (E)
0 2 6- EXISTING/FUTURE CIRCUIT BREAKER 240VAC - 3P MCC - MOTOR CONTROL 3:5 480VAC - 3P CENTER NO. 0- 0
2400VAC - 3P PCM - PROCESS CONTROL •—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•—•
4160VAC - 3P MODULE NO. o
PP - POWER PANEL NO. w_ SINGLE INSTRUMENT
VCP - VENDOR CONTROL w WITH REMOTE
PANEL NO. OEF] Oeeo TRANSMITTER
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENGINEERING RND ENV RONNIENTRL SOLUT ONS
GEBBAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
�O FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
o KMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
w CHECKED �� ��rollo 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�� �`� �� Mountain
DRAWING NO. SHEET NO.
I— WATERWORKS IDAHO OFFICES SYMBOLS AND ABBREVIATIONS -
J APPROVED O� BOISE - LEWISTON - MCCALL GN01
Page 935
PROJECT NO. 1170OA10 FILE NAME: 11700A1000GN001.dgn
Item#18.
INSTRUMENT TAG IDENTIFICATION LETTERS INSTRUMENT LINE SYMBOLS
INSTRUMENT OR CONNECTION
Q TO PROCESS
L
w w z PNEUMATIC SIGNAL
INSTRUMENT FUNCTION � � w � 0 J � �� -�/�����������T�
= O =
p_ z
~ w w U w J w w O O = z_ cz7 = o w ELECTRIC SIGNAL
o w w w O� O z0 O U p = _ CO O p _ o ~ > 0 = w
W C) Q U H J 2 z 2 J D cn
CD w co Of > U J U O w U U U = O = ~ J = cn Q Q p
J z z = g U z c� O _ = U O U Q12� W z > c� HYDRAULIC SIGNAL L L L L L
Q w Q z O W U z or_ p z z cn U = = Q J Q J Q w
7 w U Z w U � 0 CO U J Q Q Q Q w a
Q w Q W � L Q J � � CAPILLARY TUBE
N MEASURED VARIABLE U w U cn 3 Q O
ai z ELECTROMAGNETIC OR SONIC SIGNAL
p (GUIDED)
A ANALYSIS AE AT AIT AY Al AR AC AIC ARC AS ASLL ASL ASH ASHH ASHL AALL AAL AAH AAHH AL ELECTROMAGNETIC OR SONIC SIGNAL
(NOT GUIDED)
B BURNER FLAME BE BT BIT BY BI BR BC BIC BRC BS BSLL BSL BSH BSHH BALL BAL BAH BAHH BL INTERNAL SYSTEM LINK
C CONDUCTIVITY CE CT CIT CY CI CR CC CIC CRC CS CSLL CSL CSH CSHH CSHL CALL CAL CAH CAHH CL (SOFTWARE OR DATA LINK) o 0 0 0 0 0
D DENSITY DE DT DIT DY DI DR DC DIC DRC DS DSLL DSL DSH DSHH DSHL DALL DAL DAH DAHH DL
COPPER ETHERNET C C C C C
E
F FLOW FE FT FIT FY FI FIR FC FIC FRC FS FSLL FSL FSH FSHH FSHL FALL FAL FAH FAHH FQI FCV FG FL FIBER OPTIC ETHERNET F F F F F
FF FLOW RATIO FFY FFI FFC FFIC FFS FFL
G GAUGING (DIMENSION) WIRELESS ETHERNET W W W W W
H HAND (MANUAL)* HC HS* HA* HV HL HSS PROFIBUS DP PBD PBD PBD PBD PBD
d
> I CURRENT IT IIT IY II IR IC IIC IRC IS ISLL ISL ISH ISHH ALL IAL IAH IAHH IL
m J POWER PROFIBUS PA PBA PBA PBA PBA PBA
K TIME KY KI KR KC KIC KRC KS KSLL KSL KSH KSHH KALL KAL KAH KAHH KV KL
L LEVEL LE LT LIT LY LI LR LC LIC LRC LS LSLL LSL LSH LSHH LSHL LALL LAL LAH LAHH LCV LG LL DEVICENET DN DN DN DN DN
M MOISTURE OR HUMIDITY ME MT MIT MY MI MR MC MIC MRC MS MSLL MSL MSH MSHH MALL MAL MAH MAHH ML
FOUNDATION FIELDBUS FF FF FF FF FF
N EMERGENCY SHUTDOWN
0
P PRESSURE OR VACUUM PE PT PIT PY PI*** PR PC PIC PRC PS**** PSLL PSL PSH PSHH PSHL PALL PAL PAH PAHH PCV PL PROCESS LINE SYMBOLS
PD DIFFERENTIAL PRESSURE PDT PDIT PDY PDI PDR PDC PDIC PDRC PDS PDALL PDSL PDSH PDSHH PDALL PDAL PDAH PDAHH PDCV PDL
Q QUANTITY QE QT QIT QY QI QR QS QSLL QSL QSH QSHH QALL QAL QAH QAHH PRIMARY PROCESS FLOW
R RADIOACTIVITY IN PIPE
S SPEED SE ST SIT SY SI SR SC SIC SRC SS SSLL SSL SSH SSHH SALL SAL SAH SAHH SECONDARY PROCESS FLOW
T TEMPERATURE TE TT TIT TY TI TR TC TIC TRC TS TSLL TSL TSH TSHH TSHL TALL TAL TAH TAHH TCV TL IN PIPE
TD DIFFERENTIAL TEMPERATURE TDT TDIT TDY TDI TDR TDC TDIC TDRC TDS TDALL TDSL TDSH TDSHH TDALL TDAL TDAH TDAHH TDCV TDL PRIMARY PROCESS FLOW
U MULTIVARIABLE UI UR UC UIC URC US UL IN CHANNEL
V VISCOSITY VE VT VIT VY VI VR VC VIC VRC VS VSLL VSL VSH VSHH VALL VAL VAH VAHH VL SECONDARY PROCESS FLOW
IN CHANNEL
W WEIGHT WE WT WIT WY WI WR WS WSLL WSL WSH WSHH WALL WAL WAH WAHH
X UNCLASSIFIED XE XT XIT XY XI XR XC XIC XRC XS XSLL XSL XSH XSHH XALL XAL XAH XAHH XCV XG XL
XV VIBRATION XVE XVT XVY XVI XVR XVS XVSH XVSHH XVAH XVAHH XVL DESIGNATIONS
Y STATUS*** YI*** YL
Z POSITION ZE ZT ZIT ZY ZI ZS** ZV ZL**
EQUIPMENT ENCLOSURE - - - - - - - - - - - -
* REFER TO OPERATOR PILOT DEVICE LEGEND **** COULD ALSO BE PIS - FOR PRESSURE INDICATING SWITCH
** LETTER INDICATES POSITION (O=OPEN, C=CLOSED, R=RAISE, L=LOWER, ETC)
*** PI# # = 1,2,3 ETC. AND REPRESENTS A UNIQUE IDENTIFIER AND IS APPLICABLE TO ALL ITEMS IN THE TABLE ABOVE EXISTING
F— - - - - - - - �FUTURE
OPERATOR PILOT DEVICE LEGEND FUTURE
- - -
MISCELLANEOUS P&ID SYMBOLS
o PILOT DEVICE FUNCTION O w U O W 0 0 O
o � J Q co J O
�I O w O O W Q w J 5 LU �j ? _ _ w
_ O Q cn
m w p O O w cn O z m p W J W p J 0 cn cn O
a g a p U) p J Q o J Q w z — co m w CONTINUATION
w� Q z v o zQ U J z w oO U) 0 w0 w W z z DESC 2 FROM SHEET
a O U J O 0 w Q > J W z o H w � w O DESC 1
o� � � O� < W LL LU p O � U p 2 J LLJU O � W w O ~ A
o DEVICE TYPE � � p w z Q Q z w O w 0 w w v) CONTINUATION TAG # B
m O 6 W O J LU z Q � w J Q W m w
U QU = w O Q Q O z p O z U)
LL
0 Up O 0 LLJg O O X W UNIQUE CONTINUATION
) J w L O IDENTIFIER TO SHEET
a�
0
PILOT DEVICE TAG (HAND SWITCHES) HSA* HSB HSC HSD* HSE HSF HSG* HSH* HSI HSJ* HSK* HSL* HSM* HSN HSO* HSP HSQ* HSR HSS HST* HSU HSV HSW HSX HSY HSZ
PIPE CALLOUT PIPE SIZE
m
SCADA/HMI TAG (HAND ACTION) HAA HAB HAC HAD HAE HAF HAG HAH HAI HAJ HAK HAL HAM HAN HAO HAP HAQ HAR HAS HAT HAU HAV HAW HAX HAY HAZ
HSA* SELECTOR SWITCH POSITION EG: HSA(R) R = REMOTE, HSD(A)A = AUTO, ETC
1/0 TYPE DESIGNATIONS INSTRUMENT TYPE DESIGNATIONS SPECIFIC ABBREVIATIONS
L AUX1 RUNNING MSL MOTOR START LOW AM AMMONIA 03 OZONE SH SODIUM HYPOCHLORITE APH A PHASE MWH MOTOR WINDING HEATER SIGNAL CONTINUATION TO DRAWING FROM DRAWING J►
o AUX2 FAILED/FAULT MSM VALVE MODULATE CAP CAPACITANCE ORP OXIDATION REDUCTION POTENTIAL TDR TIME DOMAIN REFLECTOMETRY BPH B PHASE SSG SECONDARY SWITCHGEAR
U
AUXF1 RUNNING FORWARD MSP MOTOR STOP CGD COMBUSTIBLE GAS DETECTOR P PRESSURE TH THERMAL BRB BEARING BOTTOM SV* SOLENOID VALVE
o AUXH1 RUNNING HIGH MSR MOTOR START REVERSE CL CHLORINE P-SUB PRESSURE SUBMERSIBLE TSS TOTAL SUSPENDED SOLIDS BRT BEARING TOP SPD SURGE PROTECTIVE DEVICE
AUXL1 RUNNING LOW MST MOTOR START COND CONDUCTIVITY PC PARTICLE COUNTER TURB TURBIDITY BTFLY BUTTERFLY UPS UNINTERRUPTIBLE POWER SUPPLY
AUXR1 RUNNING REVERSE SS SPEED SIGNAL DO DISSOLVED OXYGEN PO PHOSPHOROUS US ULTRASONIC CPH C PHASE YA STATUS AUTO
SVC SOLENOID VALVE CLOSE ZC POSITION COMMAND FMCW FREQ. MODULATED CONT. WAVE PTOF PULSE TIME OF FLIGHT UVI UV INTENSITY CC* CALIBRATION COLUMN YR STATUS REMOTE
SVO SOLENOID VALVE OPEN ZCC POSITION COMMAND CLOSE HSF FLUORIDE R/I RESISTANCE TO CURRENT UVT UV TRANSMITTANCE HTR HEATER Y1 STATUS RUNNING
MS RUN ZCO POSITION COMMAND OPEN IS INTRINSIC SAFETY BARRIER ROT ROTAMETER VAC VACUUM HTU HEAT TRACE UNIT Y2 ALARM FAILED/FAULT
MSF MOTOR START FORWARD LEL LOWER EXPLOSIVE LIMIT RTD RESISTANCE TEMP DETECTOR
MSH MOTOR START HIGH II MAG MAGNETIC SC STREAMING CURRENT * CC#AND SV# #= 1, 2, 3 ETC. AND REPRESENTS A UNIQUE IDENTIFIER
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENGINEERING RND ENV RONNIENTRL SOLUT ONS
GEBBAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
oKMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
> CHECKED �� ���O 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
DRAWING NO. SHEET NO.
��' c,� WATERWORKS IDAHO OFFICES SYMBOLS AND ABBREVIATIONS - 11
J APPROVED O� BOISE - LEWISTON - MCCALL GN02
Page 936
PROJECT NO. 1170OA10 FILE NAME: 11700A1000GN002.dgn
Item#18.
ACTUATORS PIPING PUMPS BLOWERS/
COMPRESSORS
Q L
O
1p
L CENTRIFUGAL
�
DIAPHRAGM s r , l AIR GAP TEE AIR DRIVEN OR O SUBMERSIBLE SINGLE STAGE
BLOWER
N
O J L___J PNEUMATIC
O
N E ELECTRIC J HYDRAULIC _ DUAL SOLENOID
z D DISCRETE MODULATING ► ___ P OPEN/CLOSE BLIND FLANGE I UNION CENTRIFUGAL
Q r 1 X w/ SPEED CONTROL O CENTRIFUGAL BLOWER
STAGE
N L L PITA
E ELECTRIC C L———J - CAPPED OR ECCENTRIC
M MODULATING PLUGGED REDUCER
s CHEMICAL FEED VERTICAL RECIPROCATING
DIAPHRAGM TURBINE COMPRESSOR
E ELECTRIC CONCENTRIC EXPANSION
H HYDRAULIC INCREASER COUPLING
S I/P
SCREW
PNEUMATIC IY PNEUMATIC CONCENTRIC EXPANSION JOINT DIAPHRAGM �N COMPRESSOR
T HAND - P SINGLE SOLENOID P MODULATING � REDUCER VIBRATION
► X OPEN/CLOSE CENTER
s r---,
n HYDRAULIC _ DRAIN FLEXIBLE GEAR FAN
s r———, L———J y CONNECTION
� I -
d
——— _ PNEUMATIC ECCENTRIC QUICK
�', n PNEUMATIC PNEUMATIC - MODULATING INCREASER DISCONNECT PERISTALTIC VERTICAL LIQUID RING
'T' = P SINGLE SOLENOID P OPEN/CLOSE OR HOSE CHOPPER COMPRESSOR
r———, X w/SPEED CONTROL
w/ SPEED CONTROL INN
IJI SOLENOID J - J
PISTON ROTARY LOBE
.2 8 BLOWER
s
s
P PNEUMATIC
X DUAL SOLENOID PROGRESSIVE WATER CHAMP
OPEN/CLOSE CAVITY
s
Ix
P PNEUMATIC
DUAL SOLENOID
OPEN/HOLD/CLOSE
CHECK VALVES PRESSURE VALVES VALVES MISC
77 BACK FLOW BACKPIRESSURE
REGULATING
I O PREVENTER REGULATING � 3-WAY GATE PLUG CONCENTRIC AIR DAMPER FLOW CONDITIONER MOTOR '?,� SMOKE DETECTOR
m SELF CONTAINED
U
o BACKPRESSURE i i i i i STRAINER -
aO BALL REGULATING 3-WAY PLUG GATE-BURIED PLUG CONCENTRIC ;s; :s: :s: AIR/ CHEMICAL EYEWASH GAS CANNON � :- NOZZLE MECHANICALLY
c
EXTERNAL TAP VALVE BOX -BURIED VALVE BOX DIFFUSER CLEANED
LO
Q
cn �� DIAPHRAGM PRESSURE PLUG CONCENTRIC _1 L ORIFICE �� STRAINER
> CHECK SELF CONTAINED REDUCING 4-WAY GLOBE LUBRICATED BASKET STRAINER ® GRINDER I r RESTRICTION ' �,' WITH BLOW OFF
c
'P
m
a�
PRESSURE PLUG CONCENTRIC PERISTALTIC
STRAINER
DOUBLE FLAP REDUCING AIR-RELIEF HOSE LUBRICATED
u) BLOW-OFF SILENCER FILTER HEAT EXCHANGER COMPOSITE WYE TYPE
o� EXTERNAL BURIED VALVE � ® SAMPLER
o PRESSURE TAP Y BOX
—
�` FLAPPER REGULATING MUD PUMP DISCHARGE _ CALIBRATION FILTER SEPARATOR HOIST VAPOR HEATER
Q- ANGLE COLUMN v
U)
— u
.o'
SPRING LOADED F OR PULSATION
GENERAL PRESSURE RELIEF BALL NEEDLE TELESCOPING COALESCER HORIZONTAL MIXER DAMPENER VAPORIZER
U
0
N � n n m SPRING LOADED DESICCANT VENT
�I/I SWING VACUUM RELIEF — BALL V-NOTCH —��— PINCH DRYER FINE FILTER HOSE CONNECTION
a�
REFRIGERATED VENT TO
o � SWING BUTTERFLY PLUG ECCENTRIC EDUCTOR/EJECTOR INLET STRAINER DRYER ATMOSPHERE
0
U
BUTTERFLY- PLUG ECCENTRIC EQUIPMENT/INSTRUMENT ® FIRE ALARM/SENSOR INLINE STATIC MIXER RUPTURE DISK
BURIED VALVE BOX w-VALVE BOX LOCATOR
VALVE DESIGNATIONS
PLUG ECCENTRIC NO NORMALLY OPEN
CONE IWI LUBRICATED NC NORMALLY CLOSED EXHAUST FAN ® FLAME ARRESTER MATERIAL CHANGE SAMPLE PORT
FO FAIL OPEN
n PLUG ECCENTRIC FC FAIL CLOSE FLAME ARRESTER
—p� DIAPHRAGM LUBRICATED BURIED FLIP FAIL LAST POSITION w/THERMALLY MIXER SIGHT TUBE
VALVE BOX OPERATED
VALVE
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENGINEERING RND ENV RONNIENTRL SOLUT ONS
GEBBAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
Y ��� �O FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
oKMM �� �A ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
j CHECKED �� c.;p rolle% . 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
DRAWING NO. SHEET NO.
I— WATERWORKS IDAHO OFFICES SYMBOLS AND ABBREVIATIONS - Ill
J APPROVED O� BOISE - LEWISTON - MCCALL GN03
Page 937
PROJECT NO. 1170OA10 FILE NAME: 11700A1000GN003.dgn
Item#18.
FLOW FLUMES GATES LEVEL
Q SIDE VIEW PLAN VIEW
0
i� 0 SUSPENDED/
BATCH ^4� V-CONE LEOPOLD-LAGCO K FLAP 0 BUBBLER SUBMERSIBLE
0
Ne_ _N I TUBE
z O OR CORIOLIS PALMER-BOWLUS KNIFE I CAPACITANCE n TUNING FORK
R FLOW NOZZLE 1�11
Q
N 1�'1
nnM MAGNETIC D VORTEX —��— PARSHALL SLIDE III SLIDE ULTRASONIC
o � T
o A
FIDE LDIT
IREGULAR n K ORIFICE CUTTHROAT ® SLUICE II SLUICE I
�--/� U DIFFERENTIAL
PRESSURE
PADDLE WHEEL v TRAPEZOIDAL n
STOP STOP
U ELECTRODE
PISTON
WEIR
d
U
> ANNUBAR FLOAT
L <�j
n
o; BUTTERFLY
PITOT TUBE U INVERTED COLUMN
POSITIVE-
DISPLACEMENT
PROBE
PROPELLER-
TURBINE
RADAR PTOF
ROTAMETER
® THERMAL RADAR
(FREQUENCY
MODULATED
CONTINUOUS WAVE)
ULTRASONIC
ULTRASONIC
BIOGAS RADAR TDR
77
ai
PRESSURE/VACUUM TEMPERATURE WEIRS
0
PRESSURE DIFFERENTIAL PRESSURE PRESSURE SEALS SIDE VIEW PLAN VIEW
Q
ui
0
o TEMPERATURE
'I w/THERMOWELL
c
a PI PDI a RECTANGULAR RECTANGULAR
GAUGE w/o END CONTRACTIONS w/o END CONTRACTIONS
U) SEAL TEMPERATURE
0I GAUGE DIFFERENTIAL ANNULAR GAUGE
0 INDICATOR
U
a SEAL O THERMOMETER
.0 DIAPHRAGM
c
RECTANGULAR RECTANGULAR
w/ END CONTRACTIONS w/ END CONTRACTIONS
0 MANOMETER PDSL SEAL
DIFFERENTIAL SANITARY
PRESSURE
m
PDE SWITCH
EXAMPLE WEIGHT
PSH V-NOTCH V-NOTCH
(TRIANGULAR) (TRIANGULAR)
L
PRESSURE SWITCH
0
U PE PDIT PSH
DIFFERENTIAL HYDRAULIC
0 PRESSURE PRESSURE SWITCH
PDE TRANSMITTER PE
TRAPEZOIDAL TRAPEZOIDAL
STRAIN GAUGE (CIPOLLETTI) (CIPOLLETTI)
0
PIT
PRESSURE
TRANSMITTER
PE
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENGINEERING RND ENV RONNIENTRL SOLUT ONS
GEBBAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
oKMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
j CHECKED �� c.;p rolle% . 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
DRAWING NO. SHEET NO.
' c,� WATERWORKS IDAHO OFFICES SYMBOLS AND ABBREVIATIONS - IV
U) APPROVED O� BOISE - LEWISTON - MCCALL GN04
Page 938
PROJECT NO. 1170OA10 FILE NAME: 11700A1000GN004.dgn
Item#18.
MCC-1201 PCM-300
TERMINAL PANEL PLC
VFD-210
Q
SECTION - 3
o rJ-BOX
P-01-002 CUBICLE - 2
30HP, 480VAC, 42 AMPS
H MWH210-H/VFD210-33 <BLK-1> %AQ001
— — — — — — — — — - - - - - - - - - - - 33 MWH-210 11 - - - - - - - - - - - - - - 1 ::EOSLOT2
SS-210
C MOTOR VFD I AQ0001+ SPEED OUT
o MWH (MWH210_C/VFD210-X2) X2 WINDING SPEED 12 - — <WHT-1> RACK 1
N 210 — — - - - - - - - - - - - - - - HEATER OUT 1 - - - - - - - - - - - - 1 AQ0001-
LVFD210-11,12/PCM300-AQ001) — — —
PMP-210 SHLD
N UTILITY WATER PUMP T1 MOTOR: — — — — — — MP210-T1FD210-T1
— — - - - - ( - - - -/V- - -T ) - - - T1 13 (� - - - - - - - - - - - - -
25HP, 480VAC, 30 SB-210 1 1 1 1 FU1300-P1
0 INV. DUTY, TEFC PMP T2 PMP210-T2/VFD210-T2 MOTOR REMOTE � j _ _ _ _ _ _ _ _ _ _ _ _ _ <BLK-1> %A1001
o TOSHIBA MODEL: XYZ O — — - - - - - - - - - - - - - - - - - � - - - T2 SPEED 14 1
� 210 CONNECTION A1001+ Sg SPEED IN
T3 IN
PUMP _ _ _ _ _ _ — — — — — — (PMP210-T3FD210-T3) <WHT-1> 2 210/V — — — RACK 1
T3
200 GPM @ 20 FT TDH FU1300-M1 SLOT 3
900-1800 RPM
GOULD MODEL: XYZ j0X
LVFD210-13,14/PCM300-A1001) — — —
NC SHLD
(TSH210-NC/PCM300-CB1300Hl) �TSH210-NC/PCM300-FU1300H1)— — — - 1 %1001
FU1300-H1 TSH MTR TEMP
TSH C TSH210 C/PCM300 1001 TSH210-NC/PCM300 1001 <gLK> 210 RACK 1
210 1001 SLOT 4
MSP-210 15 (VFD210=15/PCM300-Q_001A) — — — — <BLK> %Q001
REMOTE Q001A 1 MSP STOP
a C-01-001 STOP 16 _VFD210=16/PCM300-Q001B) — — — — <RED> 2 210 RACK 1
( 1 Q001 B SLOT 5
�; _ — — — — (PSH210-1/PCM300-CB1300H2) PSI-210-1/PCM300-FU1300H2L — —
�, — — — — — — — — — — — — — — — — — — � — — — — — — — — — — —
FU1300-H2 PHOENIX
23 (VFD210=23/PCM300-00002) — — — — (C0002) MODEL: XYZ
E-STOP C0002 120 VAC
PE/PSH-210 24 �VFD210=24/PCM300-00003L — — — — (C0003) 3 4
UTILITY WATER HIGH PRESSURE 2 C0003
PE PS — — — (PSH210-2/PCM300-00001) — PSH210-1/PCM300-0001) — — — — _ (C0001) CR1 (CB1-300N1) %1005
MODEL: XYZ — - - - - - - — —
RANGE: 0-200 PSIG 210 210 C0001 1 210 2 9
PSH HI PRESS
SETPOINT: 50 PSIG (CB1300-H6) 5 6 (1005) 10 2 00 RACK 1
SLOT 4
MS-210
17 (VFD210=17/PCM300-Q002A) — — — — <gLU> 3 %Q002
REMOTE Q002A MS START
L-01-001 START 18 (VFD210=18/PCM300-Q002B) — — — — 4 210 RACK 1
L
Q002B SLOT 5
- - - - - - - - - - - - � �FIT210-L/PCM300-CB1210H) - - -
- — — — — — —
N CB1-210H 120VAC
- - - - - - - - - - - - - ,(FIT210-N/PCM300-CB1210N) - - -
G 1___gBl-21ON
— — — — — — — — — — — — — — — — — — — — — — � � — — — — — — — — — — — — — —
FE/FIT/FQT-210 GND
UTILITY WATER FLOW METER S-01-001 —
S-01-003
ENDRESS HAUSER 1 J-BOX
CAT NO.: XYZ FE FIT
FLOW RANGE: 200-2500 GPM — �1
FLOW TOTAL: 1 PULSE/500 GAL 210 210 2 I FU1300-P2
� <BLK-2> %A1002
r FLOW
<WHT-2> 210 RACK 1
A1002+ <
� � 4
FU1300-M2 SLOT 2
CD
o — — — — — I — — — — — — - - - - - - - - - - - --- �FIT210-1,2/PCM300-A1002)- - - - (FU1300-M3)
o=
4 SHLD
aFQT — - - - - - - - - - - - - - - - - - - - - - - � � - - - - - - - - - - - - - ->r� 3 4
210 5 I I FU1300-P3
rn L (C0004) CR2 %1002
0 4� — — — — — — — — — — — — — — — — — — — — — — — - - - - - - - - - - - - - C0004 1 210 2 3 FQ
FLOW TOT
r S-01-002 — — — — — — — — — — — — — — — — — — — — — — �FQT210-4,5/PCM300-FU1300P3; C0004) (CB1300-H7) 5 6 (1002) 4 210 RACK 1
�I _ _ _ _ _ _ _ _ _ _ _ _ _ _ _I SHLD SLOT4
— PHOENIX
of I LCP-210 P1 L — — — — — — (LCP210-P1/VFD210-1) — 1 — VFD210-19/PCM300-F_U13000H_3— — _ MODEL: XYZ %1003
o — — — — — — — — — — — — _ _ _ _ _ _
U I HSS P2 I 1 �� 1 AUX1-210 19 FFU1300-H4
H3 120 VAC 5 AUX1 RUNNING
L — — — — — — — — — — — — — — — — — — (LCP210-P2/VFD210-� — — LOCAL RUNNING VFD210-20/PCM300-1003 _ <BLU> 210 RACK 1
_ _ _ _ _ _ _
g i 210 P3 I I I 2 SPEED IN 20 6 SLOT 4
� � - - - - - - - - - - - - — — LCP210-P3/VFD2— �- — - - - - - - - - - - - - -
— — — — (L — — — — — ) — 3 21 VFD210-21/PCM300 FU1300H4 _ 7 %1004
I I AUX2-210 AUX2 FAIL
o I I - - - - - - - - - - - - - - - - - - - - - - - - - - - - 4 FAIL 22 (VFD210-22/PCM300-1004) - - - - — <ORG> 8 210 RACK
SLOT 4
C-01-002
U I -
1 — LCP210-1/VFD210-5
OFF - - - - - - - - - - - - - - - - (- - - - - - -)- - - - - 5
N — — — HSAL-210
0 I LOCAL REMOTE 2 I LOCAL
- - - - - - - - - - - - - - - - - - - - (LCP210-2/VFD210-666)- - - - - E
MODE
xoo 3
210 _ LC_P210-3/PCM300-FU1300H_5) — — _ %1006
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
0 I 4 i FU1300-H5 11 HSAR REMOTE
(LCP210-4/PCM300-1006) <YEL> 210 RACK 1
t - - - - - - - - - - - - - - - - - - - - — — — — — — — — — — — - - - - - - - - — — — — — — 12 SLOT
o
STOP oox I 1006
> 5
`6 LCP210-5/VFD210-7
J I I- - - - - - - - - - - - - — — — — — — — — (- - - - - - -)- - - - - 7 HSB-210
HSB -
�' I 6 I LOCAL FU1-300M 24 VDC
o (
I 210 LCP210-6/VFD210-8 — — — — —
g - - - - - - - - - - - - - - - - - - - - - - - - - -) 8 STOP +
START I (FU1300-P) FU1-300P
0 7 I _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - - - (LCP210-7/VFD210-999)- - - - - p 120 VAC
HSC 9 HSC-210 (CB1300-H) CB1-300H CB 1-300N (CB 1300-N)
I
210 8 — LOCAL
I — — — — (LCP210-8/VFD210_10) — — — — 10 START
_ _ _ _ _ _ _ _ _ _ THE ABOVE DRAWING IS INCLUDED AS AN EXAMPLE ONLY AND IS NOT PROJECT SPECIFIC. CONTRACTOR SHALL FURNISH LOOP
DIAGRAMS FOR THE ENTIRE FACILITY. PRELIMINARY DETAILED LOOP DIAGRAMS TO BE SUBMITTED FOR REVIEW PRIOR TO BEGINNING
CONSTRUCTION. THE LOOP DIAGRAM SHOWN ABOVE DISPLAYS THE LEVEL OF EXPECTED DETAIL.
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB
ENGINEERING AND ENVIRONMENTAL SOLUTIONS BAR IS ONE INCH ON
Y MERIDIAN WASTEWATER FACILITY FULL SIZE DRAWING
} DRAWN O� 1161 W. RIVER ST. SUITE 130 0 V
o KMM $�� Q � 110 ® BOISE, IDAHO 83702 E IDIAN�-- MERIDIAN, IDAHO PROJECT 11700A.10
j CHECKED CAM#wAm
. 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
DRAWING NO. SHEET NO.
�� c� WATERWORKS IDAHO OFFICES SAMPLE LOOP DRAWING
Q APPROVED O� BOISE - LEWISTON - MCCALL GN05
Page 939
PROJECT NO. 1170OAl0 FILE NAME: 11700A1000GN005.dgn
Item#18.
PROCESS SWITCHES HAND SWITCHES RELAYS TERMINAL BLOCKS 1/0 MISC
Q e
FLOAT SWITCH 00 NORMALLY OPEN d ■ TERMINAL < a > PLC DISCRETE 4 SOLENOID
CLOSE ON RISING LEVEL O O MOMENTARY PUSHBUTTON (Db RELAY COIL IN PLC/PCM PANEL a = INPUT OR OUTPUT AS INDICATED
o a TYPE
(0 c CR - CONTROL RELAY
- I _ NORMALLY CLOSED TD - TIME DELAY RELAY
FLOAT SWITCH c� � c� MOMENTARY PUSHBUTTON M - MOTOR STARTER COIL � TERMINAL < ANALOG > PLC ANALOG M METER UNIT
N OPEN ON RISING LEVEL L - MOTOR STARTER COIL- LOW SPEED IN MOTOR CONTROL CENTER a = INPUT OR OUTPUT AS INDICATED M = TYPE
cC).i H - MOTOR STARTER COIL- HIGH SPEED a
z F - MOTOR STARTER COIL- FORWARD
Q y THREE POSITION SELECTOR SWITCH
p PRESSURE SWITCH p p x- DENOTES POSITION CONTACTS R - MOTOR STARTER COIL- REVERSE TERMINAL HP MOTOR
N CLOSE ON RISING PRESSURE x00 CLOSED IN IN LOCAL STARTER CONTROL PANEL
b = TDON -TIME DELAY ON ENERGIZATION � DIGITAL > DIGITAL BUS
TDOFF - TIME DELAY ON DEENERGIZATION l
p y TWO POSITION SELECTOR SWITCH \ ��
o O-r6 PRESSURE SWITCH O O x- DENOTES POSITION CONTACTS c = TIMING RANGE/SETTING TERMINAL < BUS > O O CIRCUIT BREAKER
d OPEN ON RISING PRESSURE X0 CLOSED IN d = DESCRIPTION AT FIELD DEVICE
TEMPERATURE O CLOSE ON RISING TIEMPERATURE MUSHROOM HEAD PUSHBUTTON NORMALLY OPEN IN RRMUNAL p� DISCONNECT
CONTROL CONTACT
Z PUSH-PULL PUSHBUTTON
O TEMPERATURE SWITCH O O MAINTAINED CONTACT TERMINAL FUSE
OPEN ON RISING TEMPERATURE NORMALLY CLOSED IN FIELD PANEL
CONTROL CONTACT
PADLOCK SWITCH TRANSIENT SURGE
0- O FLOW SWITCH x- DENOTES POSITION CONTACTS O� TERMINAL
n CLOSE ON INCREASE IN FLOW x0x CLOSED IN I NOTC TIME DELAY CONTACT IN (USER CHOICE) PROTECTION
L J. NORMALLY OPEN
TIMED CLOSING
MWH-* MOTOR WINDING HEATER
FLOW SWITCH PULL CORD SWITCH Ely DIGITAL BUS CONNECTOR * - MOTOR TAG I.D.
OPEN ON INCREASE IN FLOW NCTO TIME DELAY CONTACT * - D - DEVICENET
017 NORMALLY CLOSED * = PA - PROFIBUS PA
Q TIMED OPENING * = DP - PROFIBUS DP
VIBRATION SWITCH U I U STOP-LOCKOUT PUSHBUTTON O * = H1 - FOUNDATION FIELDBUS H1
ICI OPEN ON RISING VIBRATION NOTO TIME DELAY CONTACT * - H2 - FOUNDATION FIELDBUS H2 SPACE HEATER
NORMALLY OPEN * _ E - ETHERNET
TIMED OPENING
SPRING-RETURN
Oho VIBRATION SWITCH 00 x- DENOTES POSITION CONTACTS NCTC TIME DELAY CONTACT
` CLOSE ON RISING VIBRATION x00 CLOSED IN NORMALLY CLOSED VARISTOR
TIMED CLOSING
�a TORQUE SWITCH
OPEN ON HIGH TORQUE INDICATORS CAPACITOR
TORQUE SWITCH
CLOSE ON HIGH TORQUE
O PILOT LIGHT RESISTOR
n
� � a = LENS COLOR
R = RED
0<16 NORMALLY CLOSED G = GREEN
LIMIT SWITCH
W = WHITE
a A=AMBER BATTERY
O B = BLUE
OzO NORMALLY CLOSED Y = YELLOW
HELD OPEN LIMIT SWITCH C = CLEAR
77
a
BEACON DIODE
a = LENS COLOR
O� NORMALLY OPEN R = RED
a LIMIT SWITCH G = GREEN
a WHITE � MOTOR OVERLOAD
W
A =AMBER HEATERS
Q NORMALLY OPEN B = BLUE
o HELD CLOSED LIMIT SWITCH M = MAGENTA
cn C = CLEAR
owl OVERLOAD CONTACT
m L' HORN
U)
0
<— DRAWOUT CONNECTION
0
m
U
0 GROUND
cn
c
2)
U)
a)
0
—0 a, LIGHTNING ARRESTOR
U
N
L
O
H1 H3 H2 H4
L
Q
O
U
CONTROL POWER
TRANSFORMER
0
X1 �X2
J
N
O
KI-*
ETM ELAPSED TIME METER
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENGINEERING RND ENV RONNIENTRL SOLUT ONS
GEBBAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
oKMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
j CHECKED �� ���O . 208.780.3990
Mountain INSTRUMENTATION DATE JANUARY 2021
DRAWING NO. SHEET NO.
I— WATERWORKS IDAHO OFFICES SCHEMATIC SYMBOLS
coAPPROVED O� BOISE - LEWISTON - MCCALL GN06
Page 940
PROJECT NO. 1170OA10 FILE NAME: 11700A1000GN006.dgn
Item#18.
EQUIPMENT TAGGING SYSTEM
EQUIPMENT
00 d EXAMPLE: SSPR1 FIT0010 REPRESENTS MAJOR PIECE OF EQUIPMENT
0
0
0
N
N EQUIPMENT TAGGING:
0
N
m AAAAXBBBYYYY
N
FACILITY IDENTIFICATION ASSET TYPE
0
o FACILITY CODE DESCRIPTION
Equipment Equipment
SDGC5 DIGESTER 4/5 CONTROL BUILDING Type Description Type Description
SDGC4 DIGESTER 4/5 ANNEX BUILDING ACN Air Condenser LCP Local Control Panel
FOUR DIGIT NUMERIC LOOP SDIGF DIGESTER GAS FLARE ACT Actuator Valve LIT Level Indicator
NUMBER SDIGF2 DIGESTER GAS FLARE 2
DIGESTER 6 ADL Auto Dialer LPR Life Preserver Ring
SDIG6 AED Automated External Defibrillator LVC Level Controller
ASSET TYPE FROM TABLE SDGC6 DIGESTER 6/7 ANNEX BUILDING
AHU Air Handler Unit LVR Louver
FACILITY INDENTIFICATION FROM ISSPRII SIDESTREAM BUILDING AIT Analyzer IndicatorTransmitter MCC Motor Control Center
TABLE ALC Active Line Conditioner MDM Modem SCADA
ARC Air Conditioner MDP Main Distribution Panel
ARU Air Unit MEC Mechanism
U
AUX Auxiliary Supporting Equip MIX Mixer
L: BFL Biofilter MKU Make-Up Unit
BKP Breaker Panel MPC Mini Power Center
BLW Blower MPS Module Power Supply UV
BOL Boiler MTR Motor
CDT Condensate Trap PDC Power Distribution Center UV
CFD Chemical Feeder PHC Phase Converter
CMP Compressor PIT Pressure Indicator
CRN Crane PLC Programming Logic Controller
CTF Centrifuge PMP Pump
DMP Dampener, Ventilation RCK Rack SCADA
DTC Detector RDC Reducer
ELE Elevator RTU Roof Top Return Unit
EWS Eye Wash Station SCB Scrubber
EXH Exhaust SCD SCADA System
FAK First Aid Kit SCG Security Gate
FAP Fire Alarm Panel SCN Screen
FAR Flame Arrestor SCV Screw Conveyor
FCV Flow Control Valve SIDS Service Disconnect
FIT Flow Indicator SGT Slide Gate
FLT Filter SMP Sampler (Composite)
GBX Gearbox SRV Server SCADA
GDT Gas Detector STN Strainer
GEN Generator SWC Screen Washer Compactor
GRID Grinder SWH Switch
77 GTC Grit Classifier SYS S stem
6 GTD Grit Dewaterer/Snail TDR Transducer
GTS Grit Settler TIT Temperature Indicator
a GTW Grit Washer/Slurry TNK Tank
HEX Heat Exchanger TRS Transformer
Q HFI Harmonic Filter UPS Uninterru tible Power Supply
o HMI Human-Machine Interface UVM UV Module
rn
o HSC H draulic S stems Center UVW UV System Bulb Washer
i
HST Hoist VAL Valve
�i HTR Heater VFD Variable Frequency Drive
u)i HUM Humidifier VNT Ventilator
o HVC HVAC WHT Water Heater
M IOJ 1/0 Junction Box WRT Wireless Router
Q ITC Intermediate/Timing Chamber WRW Weir Washer
0 LBC Load Bank Controller WST Work Station
U)
LBK Load Bank YLT Yard Lighting
a)
0
U
N
L
U
O7
O
L
O
O
U
0
cu
J
N
O
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB BAR IS ONE INCH ON
ENGINEERING AND ENV RONMENTRL SOLUT ONS MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
o KMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
w CHECKED �� ��r® o 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�� �`� �� Mountain
DRAWING NO. SHEET NO.
' c,� WATERWORKS IDAHOOFFICES EQUIPMENT TAGGING SYSTEM
J APPROVED O� BOISE - LEWISTON - MCCALL GN07
Page 941
PROJECT NO. 1170OA10 FILE NAME: 11700A1000GN007.dgn
Item#18.
GENERAL NOTES:
1. ALL ETHERNET CABLE TO BE CAT-6.
Q
LO
CD
O
0 # KEY NOTES:
1. PROVIDE NETWORK PANEL INCLUDING NEMA 12 WALL MOUNT
CN o ENCLOSURE, BACK PANEL, REDUNDANT 5-AMP 24 VDC POWER
N SUPPLIES, 8-PORT MANAGED 10/100/1000 Mbps ETHERNET SWITCH,
Q
AND ALL ANCILLARY COMPONENTS NECESSARY FOR A
75 FUNCTIONING NETWORK PANEL AS REQUIRED BY SPECIFICATION
o SECTION 40_67_01.
2. COORDINATE NETWORK TERMINATION PORT WITH OWNER.
0
0 3. VENDOR TO PROVIDE SEPARATE NETWORK CONNECTIONS FOR
a_ FACILITY SCADA AND INTERNAL VENDOR SYSTEMS.
RECOVERY REACTOR
CONTROL PANEL LEGEND:
SSPR1 LCP0100
I I �
FACILITY MANAGED ETHERNET SWITCH
c>n I -m• m•
C
NETWORK PANEL 1
SSPR1 LCP0001_ O I I e
r I I PLC RACK WITH POWER, CPU, COMMS,
1/0 MODULES, ETC.
O2CONNECTION TO EXISTING I ®P I I C
NETWORK SWITCH IN NORTH C C IC C C C
DIGESTER CONTROL BUILDING
Ll
I
I(VENDORPROVIDED) - - - - - - - - - - - - -I
I
J LOCAL OPERATOR INTERFACE (LOI)
U
U U
U
U U M. •m•
U ®' '®' VENDOR PROVIDED ETHERNET SWITCH
RECOVERY REACTOR 2
U U CONTROL PANEL
U SSPRl LCP0200
I- - - - - - - - - - - - - - - - - - - - I
I I
77
UU I
SSPR1 MCC0001 I m ® C
U — — — — — — — — — .®•
cn r U U—
Ll
DIFFUSER BLOWER 1 Loi
Q I SSPR1 VFD0300 I C C CLO
CD U U
cn
>� I I I O - - - - - - a - - - I
I I UU I 3
a� I DIFFUSER BLOWER 2 I C C C C C C C
u)� I SSPR1 VFD0400
I I I I
UP I — J I(VENDORPROVIDED) - - - - - - - - - - - - -I
— — — — — — — — — — — — — — — —
a
L
U
U)
C
O1
O
0
U
N
L
O7
O
L
O
O
U
0
J
N
O
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENGINEERING RND ENV RONNIENTRL SOLUT ONS
GEBBAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
oKMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
j CHECKED �� c.;vrolle% . 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
cf) DRAWING NO. SHEET NO.
' c,� WATERWORKS IDAHO OFFICES NETWORK BLOCK DIAGRAM
J APPROVED O� BOISE . LEWISTON - MCCALL N01
Page 942
PROJECT NO. 1170OA10 FILE NAME: 11700A1000N001.dgn
Item#18.
REMOTE DISCONNECT
#O KEY NOTES:
MCP WHERE INDICATED 1. SIZE CONTROL POWER TRANSFORMER IN ACCORDANCE WITH ALL
M O.L. ��� INDICATED LOADS.
AO
o «� ^
0 480V BO «� PMP-*
M
CN N 30 CO «____0 0-4111
Q
75
4 G N D
CONTROLTRANSFORMER L-- --�
PRIMARY FUSES
o H1 H3 H2 H410 CONTROL TRANSFORMER
480V PRI 1
120V SEC
120VAC
X1 X2
CONTROL GND
TRANSFORMER
SECONDARY FUSE HSD-*
OFF
HSD-*
HAND AUTO SV-*
OFF xoo
MS-* 3-O.L.S
CR1-* CR2-* CR3-* HAND- AUTO SVO-*
xoo M OPEN
OUTPUT
oox
L
H S DA-*
AUTO
I MS-*
RUN Ell! INPUT >
I OUTPUT oox
I oox
HSDR-*
AUTO SIGCOM >
INPUT >
oox
MS-* AUX1-*
AUX-* RUNNING
INPUT >
TSH-*
CR1-* HIGH TEMP
INPUT >
PSH-*
CR2-* HIGH PRESS
INPUT >
SIG COM >
CR1-*
77 TSH-*
CR
ai
U
a CR2-*
a PSH-*
� CR
m
Q
ui
0) MS-*
o AUX4-* MWH-*
c
m
a
C
CR1-* R3-*
° ly
CR
`°
U xoo
CR2-*
a
L
U
U)
T CR3-*
a�
0
U
N
L
O
L
Q
O
U
0
J
N
O
* = 0120 — — SSPR1 PMP0120 * = 0601 — — SSPRlVAL0601
1 STRUVITE PUMP * = 0220 - - SSPR1 PMP0220 2 SOLENOID VALVE * = 0602 - - SSPRlVAL0602
N07, N08 N14
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENG VEER NG AND ENV RONNIENTRL SOLUT ONS
GEB BAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
o KMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
LU CHECKED �� c�rO n . 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
DRAWING NO. SHEET NO.
I— WATERWORKS IDAHO OFFICES CONTROL SCHEMATICS -
J APPROVED O� BOISE - LEWISTON - MCCALL NO2
Page 943
PROJECT NO. 1170OA10 FILE NAME: 11700A1000N002.dgn
Item#18.
REMOTE DISCONNECT GENERAL NOTES:
WHERE INDICATED 1. SCHEMATIC WIRING IS BASED ON ONE OF THE NAMED
Q MCP LINE LOAD - MANUFACTURERS. REVISE SCHEMATIC AS REQUIRED TO PERFORM
LO REACTOR REACTOR
THE OPERATION SHOWN HERE AND DESCRIBED IN 17100 AND 17101
AO BASED ON THE SELECTED MANUFACTURER.
o
2. SIZE CONTROL POWER TRANSFORMER IN ACCORDANCE WITH ALL
N 480V BO M BLR-* INDICATED LOADS.
0 30
CO 1 1 3. REFER TO SPECIFICATION 17101 FOR CONTROL DESCRIPTIONS.
4 GND
CD
L-- -J
p MOV
O KEY NOTES:
0
p
VFD KEYPAD HMI 1. INCLUDE THE FOLLOWING MONITORING AND CONTROL SIGNALS
THROUGH THE ETHERNET CONNECTION.
H1 H3 H2 H410 CONTROL TRANSFORMER MONITORING SIGNALS
480V PRI
120V SEC CR2-* -RUN
-FAIL
X1 X2 -LOCAL CONTROL
120VAC VFD -REMOTE CONTROL
RUN -SPEED
-HIGH TEMPERATURE ALARM
-HIGH DISCHARGE TEMPERATURE ALARM
CONTROL SIGNALS
U
> VFD CR4-*
SET
FAILED CR -SPEED EREFERENCE
Af
VFD CR3-*
RUNNING
CR
HSA-*
OFF
LOCAL_ REMOTE
0 E: xoo LOCAL MODE REMOTE
SELECT SPEED
IN 1
ETHERNET/IP
xoo REMOTE * DIGITAL >
MODE
SELECT < BUS >
VFD-*
CR2-*
CR1-* CR6-*
CR
CR1-*
TSH-*
77
CR
ai
cn CR3-* RUNNING
a
R
Q � �
ui
cn Y2-*
o CR4-* FAULT
co
m
a A
°I
o CR6-*
U TSH2-*
CR Ua
L
U
U)
C
T
O
0
U
N
L
U
O7
O
L
O
O
U
0
J
N
O
3 DIFFUSER BLOWER * = 0300 — — SSPR1BLR0300
* = 0400 - - SSPR1 BLR0400
N09, N10
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENGINEERING RND ENV RONNIENTRL SOLUT ONS
GEBBAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
oKMM �� �� ��� BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
j CHECKED �� c.;p rolle% . 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
cf) DRAWING NO. SHEET NO.
I— WATERWORKS IDAHO OFFICES CONTROL SCHEMATICS - 11
J APPROVED O� BOISE - LEWISTON - MCCALL NO3
Page 944
PROJECT NO. 1170OA10 FILE NAME: 11700A1000N003.dgn
Item#18.
#O KEY NOTES:
g 1. NORTH DIGESTER CONTROL BUILDING (QTY OF 5).
Q
In 0 2. ANNEX BUILDING (QTY OF 2).
7t
0
r
r
N
O
N
Q
O
N
c0
DI
a SSPR1ZSO OPENED SSPR1ZSO OPENED
F- 000 F 000
SSPR1-PLC-0100 I l SSPR1 PLC 0200
DI I F-7-77 DI
SSPR1ZSC CLOSED SSPR1ZSC CLOSED
I 01 000 I
0 I 00 SSPR1-PLC-0100 I SSPR1-PLC-0200
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
E E I I
VFD 41.XX VFD OOOX
w
ry VFD VFD
cn 0 480VAC-3P 480VAC-3P
cn
MCC MCC
0
� I
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - rt - - - - - - - - - - -r - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
E V E Y
w PMP PIMP SSPR1ZSOC SSPR1ZSOC
u=
41.XX OOOX 0001 0002
S PR1FCV SSPR1FCV
0001 0002
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
REACTOR VESSEL EMERGENCY OVERFLOW
EMERGENCY OVERFLOW PLANT DRAIN BASIN
24 N04 6"OF m 8"OF
REACTOR VESSEL 2
a�
EMERGENCY OVERFLOW DIGESTER 3
25 cf) N04 6"OF 6"DS
a I I
I I
Q REACTOR VESSEL 1 &2 DIGESTER 3
17
0 26 N04 6'DS
>I I I
�I SIDESTREAM TREATMENT BUILDING
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --
6) DIGESTER 4&5
O
0
L
U
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
cn
.�- I I
U
REACTOR VESSEL 1
0 6"DS 6"DS 1 K14
DIGESTER 6
S PR1F V
U
N
:>
0001
co
I I I I
REACTOR VESSEL 2
co F
=>I
U 6"DS 6"DS 5 N06
S PR1FCV
SIDESTREAM TREATMENT BUILDING
°, L - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -0- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - J
ca
J
N
O
PMP41.XX O SSPRlFCV0001 SSPR1FCV0002
EXISTING DIGESTER 4&5 SLUDGE PUMPS REACTOR 1 SUPPLY VALVE REACTOR 2 SUPPLY VALVE
PMPOOOX =O
EXISTING DIGESTER 6 SLUDGE PUMPS
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 �"
m KMM Q`� ��� /� BOISE, IDAHO 83702 E IDIAN^-- MERIDIAN, IDAHO PROJECT 11700A.10
o CHECKED �� � -ca�� •� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�� �`� �� Mountain
W AT E R W O R K S IDAHO OFFICES SIDE STREAM FEED DRAWING NO. SHEET NO.
co
APPROVED
J Q BOISE - LEWISTON - MCCALL P&I D N04 107
Page 945
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N004.dwg
Item#18.
DO DO GENERAL NOTES:
SSPR1ZCO OPEN SSPR1ZCO OPEN
F 0107 1. REFER TO TANK MANUFACTURER DETAILS FOR
0106
Q I SSPR1-PLC-0100 I SSPR1-PLC-0100 MOUNTING INSTRUMENTS.
F-7� � DO I �� DO
SSPR1ZCC CLOSE SSPR1ZCC CLOSE 2. ALL VENDOR PROVIDED INSTRUMENTS ARE TO BE
0106 0107 INSTALLED BY THE CONTRACTOR.
SSPR1-PLC-0100 SSPR1 PLC 0100
N I F-77-7 DI I �� DI #O KEY NOTES:
N I SSPR1ZSO OPENED I SSPR1ZSO OPENED
F— 0107 0106 I 1. PRESSURE ELEMENT IS AT TANK. TRANSMITTER IS IN
SSPR1-PLC-0100 I I SSPR1-PLC-0100 PANEL AS SHOWN.
DI DI
CD I 1 SSPR1ZSC CLOSED I I SSPR1ZSC CLOSED 2. TOP OF TANK INCLUDES CLASS I, DIV 2 RATING. INSTALL
0106 I r 0107 TRANSMITTER OUTSIDE OF HAZARDOUS RATED AREA.
o SSPR1 PLC 0100
SSPR1 PLC 0100
Al Al Al AI Al Al DI I I �� DI I I �� DI
a SSPR1F SSPR1F SSPR1A PH SSPR1T SSPR1L SSPR11- SSPR1LSH I I SSPR1HSAR REMOTE I I SSPR1HSAR REMOTE
r 0003 r 0010 010 010 0103 0104 r 0105 I I 0106 I I [��\�01 /
p I SSPR1 PLC 0100 I SSPR1 PLC 0100 SSPR1-PLC-0100 SSPR1-PLC-0100 SSPR1-PLC-0100 SSPR1 PLC 01001 SSPR1-PLC-0100 I I SSPR1-PLC-0100 I I SSPR1-PLC-0100
— — — — — — — — — — — — — — — — — —I — — — — — — — — — — — — — — — — — — — — — — — - — — — — — — I— — — — — — - — — — — — — — — — — — — — — fi — — — — 1 — — — — — — — — I� — — - — — — — — — — — — — �I — — �- — — — — — — — — — — — — — — — — — — — — — — — — —
I I I I I I � II I II
LU
I I I I I I II I II
II I II
II I II I
O I TM I TM TM TM I I I I I TM I I I TM I I I TM
ry SSPR1CB 120VAC1P I SSPR1CB 120VAC1P SSPR1CB 120VAC1P SSPR1CB 24VDC I I I I SSPR1CB 24VDC I I I SSPR1CB 480VAC-3P I I I SSPR1CB 480VAC-3P
w I 0003 I 0010 0100 0102 I I I I I 0105 I I I 0106 I I I 0107
a O I PCM-0100 I PCM-0100 PCM-0100 PCM-0100 I I I I I PCM-0100 I I I SSPR1 BKP0001 I I I SSPR1 BKP0001
II I II
L J — � — — — — — — —I —I — — — — — — — r — — — — — —I — — — — — , — — — — — — I— — — — — — � — — — — — — — — — — — — — r — — — � — 1 — — — — — Irt — r LSR — — I — — — — — — - — t —LSR — - — — — — — — — — — — — — — — — — — — —
� � — — — — — — — I � FBV I I — — — — I I I I I I I I I s PS R1HSA I I I s PS R1HSA I
U- SSPR1FIT
L_ I FBV r � I I I I I I I I I I I I
SSPRTT
0003 L �� FBV I I I I I I 0106 I I I 0107 I
0010 I SSPR1 LCP I I I I I I I I I I OSC I I I OSC
S PR1 HSG i I I S PR1 HSG
MAGNETIC I 0100 I I I I I I I I I I I I
FBV THERMAL
SSPR1FE FBV L-I I I I I I I I I 0106 0107
SSPR1FE - - - - - - � I I I I I II I II
0003
0010 FBV � FBV � FBV � FBV I � \ FBV I L SSPR1ZSOC I I L SSPR1ZSOC I
L _ _ _ _ _ SSPR1AIT SSPR1TIT SSPR1LIT 1 SSPR1LIT L SSPR1LIT i 0106 I I 0107
0102 0102 0103 O 0104 0105 I I
FBV FBV
CAPACITANCE TUNING FORK L _ S PR1FCV S PR1FCV SSPR1SDC
FBV FBV �� FBV FBV 0106 0106 0107 FT1
07
SSPR1AE SSPR1LE SSPR1PE SSPR1LE
0102 0103 0104 0105
FUTURE ODOR
ANTI FOAM SUPPLY CONTROLS
—F =>
17 N05 112"AFM 6"VENT
SIDESTREAM FEED STRUVITE PUMP 1
1 N05 M M 0 6"DS T STRV NNNN05 4
MGCL2 SUPPLY ' ' STRUVITE PUMP 2
13 N05 112"MGCLEIIIIIIIIIIIIl—�3 STRV N05 7
r — — — — — — — — — — — — — — — — — — — — — — — — — —FFf
—
P
� I I
) I ——————
I
0
� I
Q 8"LPA i EMERGENCY OVERFLOW
LID o� I I 6"OF 24 N05
rn I I N04
>
c: I — I GRAVITY FEED
a)
1\4 oil TO DIGESTER 3
24 N05
fo I - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
I
C)
DIFFUSER BLOWERS
I
� 9 N10
N05
o LJ I I
I I
� I I
I I
I GRAVITY FEED E
D I TO DIGESTER 3
L
6"STRV 20 N05
o I I N07
U I E S PR1F V
I D 0107 I STRUVITE PUMP 1
o
EJ I I 6"STRV 2 N05
N07
:>
RECOVERY REACTOR
S PR1F V
o I (FURNISHED BY VENDOR) 0106
L — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — -
SSPR1 FIT0003 SSPR1 FIT0010 SSPRlAIT0102 F SSPR1 LIT0103 SSPR1 LIT0104 SSPR1 LIT0105 SSPR1 FCV0106 SSPR1 FCV0107
MAGNETIC FLOW METER * NF130 THERMAL FLOW METER * NF112 PH LEVEL TRANSMITTER * NL900 LEVEL TRANSMITTER * NL902 LEVEL SWITCH HIGH * NL901 FLOW CONTROL FLOW CONTROL
TYP NF135 TYP TYP TYP TYP 0.5HP 480VAC 3PH 0.5HP 480VAC 3PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWINGI
o KMM �� �i►/SAW/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
w CHECKED 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
Mountain
U) DRAWING NO. SHEET NO.
WATERWORKS IDAHO OFFICES RECOVERY REACTOR 1
J APPROVED 0 BOISE - LEWISTON - MCCALL P&I D N05
107
Page 946
PROJECT NO. 1170OA10 FILE NAME: 11700A1000NO05.dwg
Item#18.
DO DO GENERAL NOTES:
SSPR1ZCO OPEN SSPR1ZCO OPEN
0206 0207 1. REFER TO TANK MANUFACTURER DETAILS FOR
Q I SSPR1-PLC-0200 I SSPR1-PLC-0200 MOUNTING INSTRUMENTS.
DO I �� DO
SSPR1ZCC CLOSE SSPR1ZCC CLOSE 2. ALL VENDOR PROVIDED INSTRUMENTS ARE TO BE
o 0206 0207 INSTALLED BY THE CONTRACTOR,
SSPR1-PLC-0200 SSPR1-PLC-0200
`V I OPENED I DI OPENED O KEY NOTES:
CDSSPR1ZS0 SSPR1ZS0
r 0206 I � 0207 1. PRESSURE ELEMENT IS AT TANK. TRANSMITTER IS IN
SSPR1-PLC-0200 I I SSPR1-PLC-0200 PANEL AS SHOWN.
DI DI
SSPR1ZSC CLOSED SSPR1ZSC CLOSED 2. TOP OF TANK INCLUDES CLASS I, DIV 2 RATING. INSTALL
0206 I 0207 TRANSMITTER OUTSIDE OF HAZARDOUS RATED AREA.
o SSPR1-PLC-0200 SSPR1-PLC-0200
Al Al Al Al Al Al DI I I �� DI I I �� DI
a SSPR1F SSPR1F SSPR1A PH SSPR1T SSPR1L SSPR1L SSPR1LSH I I SSPR1HSAR REMOTE I I SSPR1HSAR REMOTE
r 0004 0020 020 020 0203 0204 r 0205 I I 0206 I I 0207
p I SSPR1 PLC 0200 I SSPR1 PLC 0200 SSPR1-PLC-0200 SSPR1-PLC-0200 SSPR1-PLC-0200 SSPR1-PLC-0200 I SSPR1-PLC-0200 I I SSPR1 PLC 0200 I I SSPR1 PLC 0200
— — — — — — — —I — — — — — — — — — — —I — — — — — — — — — — — — — — — — — — — — — — — - — — — — — — I— — — — — — —I — — — — — — — — — — — — — — t — — — — —I — — — — — — — —1 4- — — — — — — — — — — — — — — — — — — — — — —
LU
I
I I I I I I I I I I I
I
p I TM I TM TM TIM I I I I I TM I I I TM I I I TM
ry SSPR1CB 120VAC-1P I SSPR1 CB 120VAC-1P SSPR1 CB 120VAC-1P SSPR1CB 24VDC I I I I SSPR1 CB 24VDC I I I SSPR1CB 480VAC-3P I I I SSPR1 CB 480VAC-3P
w I 0004 I 0020 0200 0202 I I I I I 0205 I I I 0206 I I I 0207
a O I SSPR1-PCM-0200 I SSPR1-PCM-0200 SSPR1-PCM-0200 SSPR1-PCM-0200 I I I I I SSPR1-PCM-0200 I I I SSPRlBKP0001 I I I SSPR1BKP0001
L — — — — — — — — — — — — — — —I — —I - - - - - - - — — — — — — � - - - - - �I — — — — — II — — — — — II — — — — — — — — — — — — — — TI — — — — I — — — — — I I I — — — — — - rI II I - - — — — — — — — — — — — — — — — — —
LSR LSR
w I SS FBV I FBV r - - - - I I I I I I I I I S PS R1HSA I I I S PS R1HSA
L I SSPR1 FIT
0004 L ` � FBV I I I I I I 0206 I I I 0207 I
0020 I SSPR1 LCP I I I I I I I I I I OSC I I I OSC
S PR1 HSG i I I S PR1 HSG
MAGNETIC I 0200 I I I I I I I I I I I I
FBV THERMAL
SSPR1FE SSPR1FE FBV
I I II II II II II I YII
I I 0206 I I I
0207
L- - - - - - - -
0 000 I O/ FBV FBV FBV FBV I \ FBV I SSPR1ZSOC I i L SSPR1ZSOC
SSPR1AIT SSPR1TIT SSPR1 LIT O SSPRTT L SSPR1 LIT I 0206 I I 0207
0202 0202 0203 0204 0205
CAPACITANCE TUNING FORK L _ S PR1F V FBV SPR1SD L _ S PR1FCV FBV SPR1SD
FBV FBV �� FBV FBV 0206 E 0206 02077 0207
SSPR1AE SSPR1LE SSPR1PE SSPR1LE
0202 0203 0204 0205
FUTURE ODOR
ANTI FOAM SUPPLY CONTROLS
18 N06 112"AFM 6"VENT
SIDESTREAM FEED STRUVITE PUMP 1
5 N06 M M 0 6"DS :3"STRV
" N06 3
lo
MGCL2 SUPPLY ' ' STRUVITE PUMP 2
14 N06 112"MGCL N06 8
- - — — — — — — — — — — — — — — — — — — — — — — — — — - - - - �
P
� I I
)
I
� I I
Q 8"LPA i EMERGENCY OVERFLOW
CDI I 6"OF 25 N06
0') I I N04
o
GRAVITY FEED
TO DIGESTER a�
I I ♦li ♦li ♦Ii ♦li ♦li ♦li �I/ I 3
25 N06
of i ♦Ii ♦Ii ♦Ii ♦Ii ♦Ii ♦Ii �I� - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - � N07
. . . . . . . . . . . . . .
6..L
I
Q I
DIFFUSER BLOWERS
°' 10 N10
a N06
o LJ
I
U I
N
� I
N
I
I GRAVITY FEED E
D I TO DIGESTER 3
L I =16
0 6"STRV 21
o
U I 4SSPRlF
S PR1FCV 0207 I STRUVITE PUMP 2
0 6"ST6N06N08
RECOVERY REACTOR
(FURNISHED BY VENDOR) 0206
L — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
SSPR1 FIT0004 SSPR1 FIT0020 SSPRlAIT0202 SSPR1 LIT0203 SSPR1 LIT0204 SSPR1 LIT0205 I SSPR1 FCV0206 SSPR1 FCV0207
MAGNETIC FLOW METER * NF130 THERMAL FLOW METER * NF112 PH LEVEL TRANSMITTER * NL900 LEVEL TRANSMITTER * NL902 LEVEL SWITCH HIGH * NL901 FLOW CONTROL FLOW CONTROL
TYP NF135 TYP TYP TYP TYP 0.5HP 480VAC 3PH 0.5HP 480VAC 3PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM 0`� ��0 �i►/�A'I/' ® BOISE, IDAHO 83702 C '0m, 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
'-'-I CHECKED 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�� �`� �� Mountain
DRAWING NO. SHEET NO.
�� WATERWORKS IDAHO OFFICES RECOVERY REACTOR 2
J APPROVED 0 BOISE - LEWISTON - MCCALL P&I D N06
107
Page 947
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N006.dwg
Item#18.
Q
N
O
N
O
N
Q
o DI �7 DI
SSPR1HSDR AUTO SSPR1TSH TEMP
r 0120 0120
SSP�� DO R1-PLC-0100 � PR DI 1P
PR1-PLC-0100 DI
a SSPR1MS RUN i SSPRRlA X RUNNING SSPPR1PS
0120 0120 [�KQ12C
p SSPR1-PLC-0100 I SSPR1-PLC-0100 Z
SSPR1-PLC-0100
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — --4 — + — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
FVNR 0120
rFVNR
0 L — 480VAC-3P —_- - - - - - - - - - - �
w SSPR1 MCC0001
0
L - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - r - - - t - - - �- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
o _ _ _ _
r) I L HOA I S PR1 PMP FBV S PS R1 MWH FBV i SSPR1 PSH FBV
SSPR SA I 0120 0120 0120
�2O I PRESS SW
SSP T1R SH FBV FBV
SSPR CP SSPR1PE
I I 0120 0120
I 0120 I
J
J
J
J
J
J
J
J
RECOVERY REACTOR
r J �illillillillillillilliillillillillillillillillllllllll3 N07
6 RECOVERY REACTOR 1/1 N06::::>
1 2 N07 6"STRV
o L
c
m
Q
o RECOVERY REACTOR 1
—7
3"STRV 3"STRV 4
N07
c: N05
aD
RECOVERY REACTOR 1
of 24 N05
0 N07
ca
U
RECOVERY REACTOR RECOVERY REACTOR
Q- N06
c 22 N07 11111111 6"STRV 3"STRV 25 N07
c
P GRAVITY DISCHARGE
o RECOVERY REACTOR 1 DIGESTER 3
77
20 N07 6"ST RV 6"STRV 26 N0N074
ai
ca
m
c�
F-
L
_O
O
U
O
c�
J
N
O
SSPR1PMP0120 1 SSPRlPSH0120
STRUVITE PUMP 1 NO3 PRESSURE SWITCH HIGH * NP123
5HP 480VAC 3PH TYP
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWINGill
o KMM 0`� ��0 �i►/�A'I/' ® BOISE, IDAHO 83702 C '0m, 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
Ak�� - mgme
'-'-' CHECKED 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�� �`� �� Mountain
DRAWING NO. SHEET NO.
�� WATERWORKS IDAHO OFFICES RECOVERY REACTOR 1
< APPROVED
O BOISE - LEWISTON - MCCALL STRUVITE PUMP P&ID N07 107
C�
Page 948
PROJECT NO. 1170OA10 FILE NAME: 11700A1000N007.dwg
Item#18.
Q
N
N
O
N
O
N
Q
o �� DI �� DI
SSPR1HSDR AUTO SSPR1TSH TEMP
a? r 0220 F 0220
p I PLC-0200 I PLC 0200
F-77-7 DO I F-77-7 DI F-7-7--1 DI
a I SSPR1MS RUN I SSPR1AUX1 RUNNING SSPR1PSH
I 0220 I 0220 0220
0 I PLC-0200 I PLC-0200 PLC-0200
— — — — — — — — — — — — — — — — — — — — — — — — — — I— — I — — — — — — I— + — — — — — — — — — — - — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
I I
FVNR 0220
w I
U
FVNR
L _ 480VAC3P — — — — — — -
w SSPR1 MCC0001
a 0
U) Q — — — — — — — — — — — — — — — — — — — — — — — — — — — — I — — - — — + — — —� — — — — — — — —I — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
L
_ I FBV S R ,, FBVw i �
FBV
� r PM SSPR1PSH
HOA I 0220 0220
SSPR1HSA I 0220
I
0220 I FBV I PRESS SW
SSPR1TSH _ J SSPR1PE
0220
SSPR CP I 0220
I 0220 I
I J
J
J
J
J
J
J
J
J
RECOVERY REACTOR 1
J 7 N08
RECOVERY REACTOR I N05
in 6 N08 6"STRV J
L �
c
(D
q-
LO
o RECOVERY REACTOR 2
C) N08> Y STRV 3"STRV 8 N06
Cl
aD
I
of
0
c`a
U
2-
3"STRV
c
GRAVITY DISCHARGE
o RECOVERY REACTOR 2 DIGESTER 3
21 N�8 6"STRV 6"STRV 22 N0
U
N
(0
t
N
O)
N
(6
It
_O
O
U
0
c�
J
N
O
SSPR1PMP0220 1 SSPR1PSH0220
STRUVITE PUMP 2 NO3 PRESSURE SWITCH HIGH * NP123
5HP 480VAC 3PH TYP
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM 0`� ��0 �i►/�110% BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
Ak�� - mgme
I-'-I CHECKED 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�� �`� �� Mountain
DRAWING NO. SHEET NO.
�� WATERWORKS IDAHO OFFICES RECOVERY REACTOR 2
< APPROVED
O BOISE - LEWISTON - MCCALL STRUVITE PUMP P&ID N08 107
C�
Page 949
PROJECT NO. 1170OA10 FILE NAME: 11700A1000N008.dwg
Item#18.
#O KEY NOTES:
g 1. SEE CONTROL SCHEMATIC FOR LIST OF ETHERNET MONITORING
Q AND CONTROL POINTS.
0
N
O
N
O
N
Q
4
O
. O(0
ETHERNET F-77--1 DI F-7-77 DI
a SSPR1U SSPR1TSH HIGH TEMP SSPR1TSH HIGH TEMP
0300 0300 0304
p PLC-0100 SSPR1-PLC-0100 SSPR1-PLC-0100
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —o— — — — — — — — — I— — — — — — — — — {— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
I
VFD 0300
w I
ry VFD-6
O TM
ry SSPR1CB 120VAC-1P 480VAC 3P
w 0300 SSPRl MCC0001
a O SSPRBKP0002
_ _
L —I — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — I— — — — — — — — — �— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - �- - - - -Y - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
-I - - - - - - - - - - -Z - - - - , - - - - - - - - - - - -
I
_ I r —
LL I I I I
SSPR1 CP
0300 � I
I I
II- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 7 - - - - - - - - - - - -7�7 - - - - - - - - - - --- - - - - - I
I I I I I
I I I I I
I I
S PRS 1BLW FBV SSP T1R SH FBV — J
0300 0300
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
r I I
U)
0 I
SSPH FBV
LO
� I 0304 I
0
RTD
aril I SSPR1P1 FBV (SSPR1PI FBV SSPR1TI FBV SS R E FBV
0302 0303 0304
0301
ci
o I J/
U I
I I
2-
I
c AMBIENT AIR I DIFFUSER BLOWER 2
0
o I i 6"LPA 8"LPA 11 N100
I
DIFFUSER BLOWER PACKAGE
(FURNISHED BY VENDOR)
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
It
L
_O
O
U
O
c�
J
N
O
SSPR1 P10301 SSPR1 PI0302 SSPRlTSH0304
PRESSURE INDICATOR PRESSURE INDICATOR TEMPERATURE SWITCH
SSPR1BLW0300 3 SSPRlTI0303
AERATION BLOWER 1 NO3 TEMPERATURE INDICATOR
20HP 480VAC 3PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM �� �i►/�A'I/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
'0=090 w CHECKED A� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�`� Mountain
U) DRAWING NO. SHEET NO.
WATERWORKS IDAHO OFFICES DIFFUSER BLOWER 1
J APPROVED 0 BOISE - LEWISTON - MCCALL P&I D N09
107
Page 950
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N009.dwg
Item#18.
#O KEY NOTES:
1. SEE CONTROL SCHEMATIC FOR LIST OF ETHERNET MONITORING
AND CONTROL POINTS.
O
b ETHERNET DI DI
i SSPR1U SSPR1TSH HIGH TEMP SSPR1TSH HIGH TEMP
0400 0400 0404
O PLC-0200 PLC-0200 PLC-0200
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —o— — — — — — — — —I — — — — — — — — — —I — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
I
VFD 0400
w I I
ry VFD-6
o TM
ry SSPR1CB 120VAC-1P 480VAC 3P
�
-0400 SSPR1 MCC0001 I I
O SSPRBKP0002
� I
—I — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —I — — — — — — — — —I — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —o - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - �- - ---Y------------------------------ -----------L------------Z---, - - - - - - - - - - - -
I
_ I r -
LL I I I I
SSPR1 CP
0400 � I
I I
II- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 7 - - - - - - - - - - - --- - - - - - - - - - - - -A- - - - I
I I
I I I I
I I I j
� S PR1BL FBV SSP T1RSP SH FBV _ J
0400 0400
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
A
I I
I I
SSPH FBV
I
I 0404 I
I
I I RTD
I
SSPR1P1 FBV (SSPR1P1 FBV (SSPRlT)IFBV SSPR1TE FBV
-I IIIIII
a.-L
0�4,02 0 044
t AMBIENTAIR
IIIIIII
L RECOVERY REACT
OR 2
PA 10 N06N10
_::>
DIFFUSER BLOWER PACKAGE
(FURNISHED BY VENDOR)
L-
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - FUTURE BLOWER
DIFFUSER BLOWER 1 RECOVERY REACTOR 1
N09 N10
11 N10 9 N05 :>
SSPR1 P10401 SSPR1 PI0402 SSPR1TSH0404
PRESSURE INDICATOR PRESSURE INDICATOR TEMPERATURE SWITCH
SSPR1BLW0400 3 SSPRlTI0403
AERATION BLOWER 2 NO3 TEMPERATURE INDICATOR
20HP 480VAC 3PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWINGI
o KMM �� ��0 �i►/�A'I/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
'-'-' - 0090
CHECKED �� �� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�� �`� �� Mountain
DRAWING NO. SHEET NO.
� �� WATERWORKS IDAHO OFFICES
DIFFUSER BLOWER 2
J APPROVED O BOISE - LEWISTON - MCCALL P&I D N 10
107
Page 951
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N010.dwg
Item#18.
#O KEY NOTES:
Q 1. FLANGES WITH INDUSTRIAL GRADE WAX PAPER LOCATED NEAR
o OVERFLOW DISCHARGE.
N
2. PROVIDE MOORE INDUSTRIES ECT-DIN (OR EQUAL)SIGNAL
o ISOLATOR FOR 4-20 MA SIGNAL TO DISPLAYS.
No 3. VENDOR PROVIDED TANK INCLUDES CABLE STYLE LEVEL
N INDICATOR WITH FLOAT.
Q
4
0
a�
is
0 F-7-7--1 DI F-7-7--1 Al F-7-7-7 DI
a SSPR1LSH SSPR1L SSPR1LSH
r 0500 �10 050
0 PLC-0100 PLC-0100 PLC-0100
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — I— — — — — — — — — — — — —I — — — — — — - — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
� I I
� I
0
ry
0 TM I I
w SSPR1CB 120VAC-1P
w 0500
a 0 PCM-0100
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — �— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
m o
� .
-i (
w L SSPR1LSH FBV t. . . lLI 2 _ SS R1 FBV SSPR1LSH FBV
0500 0501 0502
RADAR
SSPR1LE FBV SSPR1LE FBV SSPR1LE FBV
0500 0501 0502
6"VENT
INSECT
SCREEN
77
ai
m 3"MGCL2 CONNECTION FOR BULK
MAGNESIUM CHLORIDE DELIVERY
0
c
m
Q
LO 3"OVRFLW
0
rn
0 3
'I
c
a�
ABOVE GROUND I BELOW GROUND
coS PR1T K MGCL2 PUMPS
o� O 0500
o 1-112"MGCL 12 N12
U INSECT
Q SCREEN
L
U
I
MGCL2 STORAGE TANK
o (FURNISHED BY VENDOR)
U
N
(0
t
N
O)
N
(6
F-
L
_O
O
0
0
O
c�
J
N
O
SSPR1LSH0500 SSPRITNK0500
LEVEL SWITCH HIGH MAGNESIUM CHLORIDE STORAGE TANK 1 HEAT TRACING
20AMP 120VAC 1PH
SSPR1 LIT0501 SSPR1 LSH0502
RADAR LEVEL LEVEL SWITCH HIGH
0-20 FT FT
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM �� �i►/�A'I/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
w CHECKED A� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�`� Mountain
U) DRAWING NO. SHEET NO.
WATERWORKS IDAHO OFFICES
MAGNESIUM CHLORIDE STORAGE TANK
J APPROVED 0 BOISE - LEWISTON - MCCALL P&I D N 11
107
Page 952
PROJECT NO. 1170OA10 FILENAME: 1170OA1000N011.dwg
Item#18.
GENERAL NOTES:
1. ADD CHEMICAL AIR RELEASE VALVE AT ALL HIGH POINTS.
DI
LO SSPRRl S R REMOTE #O KEY NOTES:
o r 0510
PLC-0100 1. EQUIPMENT FURNISHED BY VENDOR AND INSTALLED BY
DO CONTRACTOR.
o I SSPR1 MS RUN 2. COORDINATE 1/0 WITH SELECTED PUMP.
13� I F 0510
4 I I PLC 0100 o �� AlDI
3. MATCH FLOW METER PIPE SIZE AND PIPE CONNECTIONS IN
I I ��
SSPR1SB SPEED IN SSPR1AUX1 RUNNING ACCORDANCE WITH MANUFACTURER RECOMMENDATION.
y
o i i I 0510 PLC-0100 ILF51 PLC-0100 4. PROVIDE SANITARY SEAL.
o I I F--/,7-1 AO I F-7,7-1 DI Al Al
a I SSPR1 SS SPEED OUT SSPR1AUX2 FAILED SSPR1F SSPR1F
II —
0510 PLC 0100 I 0510 PLC 0100 i 0501 SSPR1 PLC 0100 I 050 PLC-0100
II
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —� tl — — — — — — — — — - — I— — — — — — — — — — — — — — — — — — — — — � — — — — — — — — — — — —I — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
111 I I I I
III I I I I
w III I I I I I
� III
o TM III I I I I TM I TM
U) SSPR1CB1 120VAC-1P
0510 I I I I I I SS 0501 B2 120VAC 1 P SSPRlC
0502 B2 120VAC 1 P
LU
a O SSPR1-EDP-0001 SSPR1 PCM 0100 I PCM-0100
III _ I _ I _ I_
or- — — — — — — — — — — — —I— — — — — — — — — — — — — I r1- - r — —I- - r — I — — — — — — — — — — — — — - -I- - - - - - - -
w
J- r — — — I— — — — — — — — — — — — — — - *- - - - - - - - - - - - — — — — — - 1 FBV I FBV
FBV FBV I L SSPR1 FIT L SSPR1 FIT
SSPR
1 S PR1PMP O I 0501 0502
I
0510 0510 I MAGNETIC MAGNETIC
SSPR1 FE FBV SSPR1FE FBV
I 0501 0502
I
I
I
I
I
I
I
I
I
I
I
OI
1 I z
o0
� z
O zo
I 3 z
O
U RECOVERY REACTOR
N0
77 I M M 1/2"MGCL 14 N06
=>
PLANT WATER
cn
o HOSE CONNECTION
� y I 4 � O
1 112"MGCLNINE illillill
Q IA RECOVERY REACTOR
CD o I L_J I M M 1/2"MGCL Fl 11 N05
:>
c PLANT WATER
ABOVE GROUND I HOSE CONNECTION MGCL2 PUMP 2 MGCL2 PUMP 2
N12 N13
of BELOW GROUND I 15 N13 16 N12
0
c`a I
U
Q MGCL2 STORAGE
c/) 12 N12 1 112"MGCL
PL- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
aa)i DRAIN
0
U
a)
(0
t
N
O)
N
(0
F-
L
_O
O
U
O
ns
J
m
O
SSPR1 PMP0510 SSPR1 FIT0501 SSPR1 FIT0502
MAGNESIUM CHLORIDE METERING PUMP NO.1 MAGNETIC FLOW METER MAGNETIC FLOW METER
0.25HP 120VAC 1 PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM ��0 �i►/�A'I/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
'-'-' CHECKED �� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�`� Mountain
U) DRAWING NO. SHEET NO.
WATERWORKS IDAHO OFFICES
MAGNESIUM CHLORIDE SYSTEM 1
J APPROVED O BOISE - LEWISTON - MCCALL P&ID N12 107
Page 953
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N012.dwg
Item#18.
GENERAL NOTES:
1. ADD CHEMICAL AIR RELEASE VALVE AT ALL HIGH POINTS.
Q
N F DI
SSPR1HSAR REMOTE #O KEY NOTES:
o r 0520
PLC-0100 1. EQUIPMENT FURNISHED BY VENDOR AND INSTALLED BY
N I F-77---1 DO CONTRACTOR.
N I SSPR1MS RUN
I F 0520
2. COORDINATE 1/0 WITH SELECTED PUMP.
PLC-0100
o I I � I Al �� DI 3. PROVIDE SANITARY SEAL.
SSPR1SB SPEED IN SSPR1AUX1 RUNNING
y
o i i l 0520 PLC-0100 I 0520 PLC-0100
AO a I i i SS�S SPEED OUT i SSPPRRlAAU 2 FAILED
0520 O PLC-0100 i 0520 PLC-0100
- {- - - - - - - - - +
III I I I
ry
w III
0 TMj11
SSPR1 CB1 1 0VAC-1 P
w 0520
a O SSPR1-EDP-0001
> w H
I
L — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — I — — — — — — — — — — — — _1 r — {— — — — — — — — - — T — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
? J - - - - - - - - - - - - - - - - - - —I— — — — — — — — — — - - - - - - Ir1- - 7 - - - - - - - - - - -1- - 7 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -I
- - - - - - - - - - - - - - - - - - - - �Y1 - -`v - - - - - - - - - - 1 - - - - - - - - - I
SSPR CP FBV S PS�PMP FBV 2
I 0520 0520 O I
L- — — — — — — — — — — — — — — — — — — — — — — - - - - - - - - - - - - - - - - - - - - - - - - - I
I
I
I
I
I
I
I
I
I
I
I
z
O
❑ m
� z
o
z
O
77
I
I
Y
U
-�° MGCL2 PUMP SUPPLY 3
N12 O I
Q 15 N13
MGCL2 DISTRIBUTION
LO N13
o LJ 1/2"MGCL 16 N12
>I
c: PLANT WATER
HOSE CONNECTION
U
o�
o - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
�a
U
.L
U
C
P
N
❑
U
N
(0
t
N
O)
N
(6
F-
L
_O
O
U
O
c�
J
N
O
SSPR1 PMP0520
MAGNESIUM CHLORIDE METERING PUMP NO.1
0.25HP 120VAC 1 PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM �� �i►/�A'I/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
'Omommme w CHECKED A� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�`� Mountain
U) DRAWING NO. SHEET NO.
WATERWORKS IDAHO OFFICES
MAGNESIUM CHLORIDE SYSTEM 2
J APPROVED 0 BOISE - LEWISTON - MCCALL P&I D N 13
107
Page 954
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N013.dwg
Item#18.
GENERAL NOTES:
1. ADD CHEMICAL AIR RELEASE VALVE AT ALL HIGH POINTS.
Q
DI
SSPR1HSAR REMOTE #O KEY NOTES:
F0610 PLC 0100 1. EQUIPMENT FURNISHED BY VENDOR AND INSTALLED BY
DO CONTRACTOR.
SSPR1MS RUN O 2. COORDINATE 1/0 WITH SELECTED PUMP.
I F =61
PLC-0100
o I I �� Al �� DI �� DI �� DI 3. PROVIDE SANITARY SEAL.
SSPR1SB SPEED IN SSPR1AUX1 RUNNING SSPR1HSDR REMOTE SSPR1HSDR REMOTE
0610 EF61 0601 060 4, DOUBLE CONTAINMENT PIPE.
p I I PLC-0100 I PLC-0100 I PLC-0100 I PLC-0100
a I I I SS�g SPEED OUT I SSP�R9�AU 2 AO DAILED I SSP�fR1�S 0 OPEN IDO
SSP�p OPEN
I I , 0610 , 0610 I I r
O I I I PLC-0100 I PLC-0100 , I rM6O M6OPLC-0100 , I PLC-0100
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —Ifil — — — — — — — — — - — I— — — — — — — — — — — — — — — 11 — — — — — — — — — —IL — — — — — — — — — — — — — — — — — — — — — — — — — —
, II I I I II II
ry
11 , I , I II II
o TM III I I I TM , TM
SSPRlC131 120VAC-1P 1 1 I I I I I SSPR1CB 120VAC-1P
� SS� 0610 � 1 1 I I I I 0601 I 601B 120VAC-1P
a O SSPR1-EDP-0001 I I I I I I i PCM-0100 i PCM-0100
> � II I , I
L
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —Lr, — — — — — — — — — fi — I — — — — — — — — — — — — — I� — - — — — — — — — —IJ- — - — — — — — — — — — — — — — — — — — — — — — — — —
Q I
w
- - - - - - - - - - - - -I- - - - - - - - - - -ItI- - - - - - - - - - - - - - + - - - - - - - � r - � HOA -1 r - � LOR -1
U I � - - - `'- - - - - - - - - - -06- _t - - - - - - - - - - -I- - L - - - - � i �� ��
I I SSPR1HSD ' ' SSPR1HSD '
� �' FBv FBV �
I SSPR1LCP S PR1PMP ' I I �01
I I �O2
I L - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - I I SSPR CP I I SSPR CP I
I I O I I I I
' '
SSPR AL SSPR1VAL
0601 T0602
I I
I I
I I
I I
I I
77
ANTI FOAM PUMP 2 I 3
_o N14
19 115 RECOVERY REACTOR 1
Q I I I 1/2"AFM 17 N05
LO
CD
' u ' 0
PLANT WATER HOSE '
�I L - - - - - - - - - - CONNECTION
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - — J �' LJ
SSPR1VAL PLANT WATER HOSE
f) VENT n r Fy 0601 CONNECTION S ANTIFOAM SYSTEM 2
o L
3/8 AFM 1/2"AFM N14 23
co
Q SSPR1V L
0602
u
0
TO FUTURE ANTI-FOAM
MIXING PUMP
U
N
co 112"AFM
m
c�
F-
L
_O
O
U
O
c�
J
N
O
SSPR1PMP0610 SSPRlVAL0601 2 SSPRlVAL0602 2
ANTI FOAM DOSING PUMP NO.1 SOLENOID VALVE NO2 SOLENOID VALVE NO2
0.25HP 120VAC 1 PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM �� �i►/�A'I/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
'Omommme CHECKED A� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�`� �� Mountain
U) DRAWING NO. SHEET NO.
W AT E R W O R K S IDAHO OFFICES ANTI FOAM SYSTEM 1
J APPROVED 0 BOISE - LEWISTON - MCCALL P&I D N 14
107
Page 955
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N014.dwg
Item#18.
GENERAL NOTES:
1. ADD CHEMICAL AIR RELEASE VALVE AT ALL HIGH POINTS.
DI
N SSPR�1 S R REMOTE #O KEY NOTES:
r �062AO
PLC-0200 1. EQUIPMENT FURNISHED BY VENDOR AND INSTALLED BY
N I F-7,;;�—I DO CONTRACTOR.
CD SSPR1MS RUN O 2. COORDINATE 1/0 WITH SELECTED PUMP.
I F =620
PLC-0200 3. PROVIDE SANITARY SEAL.
o I I �� Al �� DI
SSPR1SB SPEED IN SSPR1AUX1 RUNNING
1 — 4. DOUBLE CONTAINMENT PIPE.
0620 LF62
p I 1 PLC-0200 I PLC-0200
a III SS g SPEED OUT I SSPPRRlAAU 2 FAILED
—
1 , 0620 , 0620
O i 1 1 PLC-0200 I PLC-0200
— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —Ifil — — — — — — — — - — I— — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
, II I I
III I I I
w , 11
ry
O TM
Ijl
SSPRlC131 1 0VAC-1P
LU 0620 III I 1
a O SSPR1-EDP-0001 III I 1
w II
L — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —Ir, — — — — — — — — — fi — I — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — —
UI r - - - I- - - - - - - - - - -06- -`Y - - - - - - - - - - -L L - - - - � I
I
SSPR CP FBV S PR1PMP FBV
I I 0620 0620 I
IL - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - J I
I I
I I OI I
I I
I I
I — I
I 77
I = I
I — I
I = I
I =
I I
I I
I I
I I
I I
I I
I I
I I
U) I 3
o I
RECOVERY REACTOR
m I I 1/2"AFM 18 No0b6 N
C Oo I LJ I 4
�I I PLANT WATER HOSE
I
- - - - - - - - - CONNECTION
L - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - L_J
� — � PLANT WATER HOSE
cf)I ANTIFOAM STORAGE CONNECTION
_O
19 ANTIFOAM SYSTEM 1
N15 318"AFM
U 1/2"AFM 23 N14
2-
L
U
C
P
N
U
N
(0
t
N
O)
N
(6
It
_O
O
U
O
c�
J
N
O
SSPR1 PMP0620
ANTI FOAM DOSING PUMP 2
0.25HP 120VAC 1 PH
NO. REVISION BY DATE DESIGN VERIFY SCALE
GEB ENGINEERING AND ENVIRONMENTAL SOLUTIONS MERIDIAN WASTEWATER FACILITY BAR FULLS ONE IZEDRAH ON
NG
Y DRAWN �0 1161 W. RIVER ST. SUITE 130 OFULLSIZEDRAWING1
o KMM �� �i►/�A'I/' ® BOISE, IDAHO 83702 1 IAN�, MERIDIAN , IDAHO PROJECT 11700A.10
'Omommme w CHECKED A� 208.780.3990 INSTRUMENTATION DATE JANUARY 2021
�`� Mountain
U) DRAWING NO. SHEET NO.
W AT E R W O R K S IDAHO OFFICES ANTI FOAM SYSTEM 2
J APPROVED 0 BOISE - LEWISTON - MCCALL P&ID N15 107
Page 956
PROJECT NO. 1170OA10 FILE NAME: 1170OA1000N015.dwg
Item#18.
5
0����``
/' MAGNETIC FLOW
5 x D 3 x D ` TRANSMITTER ®W6V65�u9ER
LEVEL
Q THERMAL MASS w� w �®9 m TRANSMITTER
FLOW ELEMENT ; EM210
CONNECTING w TYP 0 0
STRAP _ � ® 0 ® FLEXIBLE CONDUIT
PACKING O o
1/4 FLOW o VENDOR POWER CABLE
TRANSMITTER
0 1 1/4" NIPPLE VENDOR SIGNAL CABLE
m
I FLEXIBLE
LU I
� CONDUIT
- - - I
o I 2 1 MAGNETIC
o -- FLOW TUBE
orri MAX. NOZZLE SPOOL PIECE W/2" Q1 MIN.
J HEIGHT 4 INCHES (AVAILABLE 0: 3", 4" AND 6")
THREADED O GROUND RINGS ` ( )
OUTLET PACKING NUT 1 z TANK FLANGE VERIFY W/MANUF.
' 1-#8 XHHW-2 w
PACKING SPLIT RING O �, �
O
COMPRESSION LOCKING COLLAR ' a
COLLAR
PROVIDE SUFFICIENT FLEXIBLE
CONDUIT TO ALLOW COMPLETE
REMOVAL OF FLOW ELEMENT
CAPACITANCE CABLE/ROD
d
NOTES: O 148 XHHW-2 CLEARANCE -
1. FOLLOW MANUFACTURER'S RECOMMENDED MAXIMUM TORQUE SETTINGS. DO 1.5 FEET
NOT OVER-TORQUE FLANGE BOLTS. OVERTIGHTENING THE FASTENERS WILL KEY NOTES: _
DEFORM SEALING FACES OR DAMAGE THE LINE.
2. ALWAYS TIGHTEN FLANGE BOLTS UNIFORMLY AND IN DIAGONALLY OPPOSITE 1O CONTRACTOR SHALL VERIFY ZERO POTENTIAL BETWEEN FLOW TUBE,
SEQUENCE. EARTH GROUND AND TRANSMITTER GROUND TERMINAL.
3. MOUNT METER SO THAT IT REMAINS FULLY FLOODED. 2 CONNECT TRANSMITTER GROUND TERMINAL TO GROUND RINGS.
4. INSTALL METER SUCH THAT THERE ARE NO PIPE BENDS FOR 5 PIPE DIAMETERS 3 CONNECT METER BODY TO EARTH GROUND POTENTIAL.
UPSTREAM AND 3 PIPE DIAMETERS DOWNSTREAM OF THE METER.
KEY NOTES: 4O EQUALIZE POTENTIAL VIA GROUND RINGS BETWEEN FLUID AND
NOTES: MAGMETER.
1. LENGTH OF PROBE TO BE DETERMINED BY MFG. 1O PIPE SUPPORTS BY MECHANICAL CONTRACTOR. NO SUPPORTS SHALL BE O PROVIDE BONDING JUMPER ON CONDUCTIVE PIPES.
INSTALLED AT THE METER HOUSING.
Nms
THERMAL MASS FLOWMETER INSTALLATION DETAIL NF130 MAGNETIC FLOW MOUNTING DETAIL NF135 REMOTE TRANSMITTER MAGNETIC FLOWMETER mi
TANK MOUNT CAPACITANCE TRANSMITTER
TYP TYP GROUNDING DETAIL MOUNTING DETAIL
S S 02/10/21
PRESSURE GAUGE (MIN. 3 2" DIA.
CALIBRATED IN APPLICABLE UNITS)
FOR PANEL MOUNTING WITH SNUBBER
1 PRESSURE SWITCH WITH
BUTTERFLY VALVE 16" THICK STEEL SNUBBER
BALL VALVE MOUNTING PLATE _
77 AS PER P&ID GALVANIZED
AFTER
(TYP 2) I BY TANK VENDORDUPLEX NPT
FABRICATION
a FLUSHING CONNECTOR /
a PROVIDED WITH LIT I a' FLEXIBLE
TUBING WITH
� TANK WALL COMPRESSION
Q LEVEL SWITCH i TYPE
LO FITTINGScn
FLANGED
C) FLEXIBLE CONNECTION
CONDUIT tlr'"M�4 w/RING
GASKET
�I ADJUST SPOOL LENGTH FLANGE & TRANSMITTER
of TO ALLOW FOR 1" SLEEVE SENSING
IMMERSION OF SENSOR O LIQUID O O
m TIP ❑ ❑ (FACTORY
U FILLED)
Q- TANK LOW REFERENCE I /
Un 2 WAFER-TYPE
PRESSURE
a SENSOR
0 1/2" FNPT CONNECTION
(TYP 2) 3" TANK FLANGE O O
Unn
HI-HI LEVEL
m
a�
KEY NOTES:
L
0 O PROVIDE GASKETS, GASKET MATERIAL TO MATCH
ASSOCIATED PIPING GASKET SPECIFICATION.
0 2O CONNECT TO TANK BLANKET IF REQUIRED.
J
N
O
ANNULAR SEAL WITH
NL901 TUNING FORK LEVEL SWITCH NL902 TANK LEVEL TRANSMITTER NP123 PRESSURE GAUGE AND PRESSURE
TYP MOUNTING DETAIL TYP TY� ps
SWITCH MOUNTING DETAIL
J 02/10/21 J 02/10/21
NO. REVISION BY DATE DESIGN VERIFY SCALE
ENG VEER NG AND ENV RONNIENTRL SOLUT ONS
GEB BAR IS ONE INCH ON
MERIDIAN WASTEWATER FACILITY
FULL SIZE DRAWING
DRAWN 1161 W. RIVER ST. SUITE 130 0 i"
oKMM �� �� ��� 04 BOISE, IDAHO 83702 E IDIAN MERIDIAN , IDAHO PROJECT 11700A.10
j CHECKED �� ��rO e . 208.780.3990
Q '�� �� '�� Mountain INSTRUMENTATION DATE JANUARY 2021
c��' `� WATERWORKS INSTRUMENTATION TYPICAL DETAILS DRAWING NO. SHEET NO.
APPROVED � �� IDAHO OFFICES
J �Q BOISE - LEWISTON - MCCALL TN01
Page 957
PROJECT NO. 1170OA10 FILE NAME: 11700A1000TN001.dgn
Item#18. ,c e n t msap.wcnp
NUMBER: 06638 DATE: 06/18/2021
TO: City of Meridian REF: CAROLLO PROJECT
33 E. Broadway Ave. NO. 1 1700A.10
Meridian, Idaho 83642
Proposal
Prepared For:
Meridian, ID
CNP MagPrexTM System
fj
E I.
zi®tX ------------
.i 1
- -
CNP Contact Local Representative
Jerod Swanson Chris McCalib
Regional Sales Manager Treatment Equipment Company
9586 58t" place 249 Main Ave S, Ste 107 #322
Kenosha, WI 53144 North Bend, WA 98045
Ph: (262) 654 6006
Direct: (612) 401 2006 Ph: (206) 909-1546
Email: Jerod.swanson@centrisys.us Email: chris@tec-nw.com
Page 1 1
Page 958
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
Item#18.
cnp
MAGPREXTM WITH SEQUESTRATION PROCESS (NO HARVESTING)
ITEM 1 DESIGN PARAMETERS
Our design calculations are based on the following parameters:
SEQUESTRATION PARAMETERS VALUE UNITS
Digested sludge flow rate to MagPrexTm
reactors 76 gpm
2020 - Design flow:
Digested sludge flow rate to MagPrexTM
reactors 145 gpm
2040 - Design flow:
Ortho-P in digested sludge, max 377 mg-P/L (as PO4-P)
ITEM 2 O&M REQUIREMENTS
ITEM VALUE UNITS
Estimated MgC12 Consumption at 30% 495 gallon/day
w/w solution - 2020 Design Flow, max
Estimated MgC12 Consumption at 30% 942 gallon/day
w/w solution - 2040 Design Flow, max
Total installed power 59 HP
O&M Labor requirements <1 hours/day
Page 12
Page 959
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
Item#18. entrisj ��j
cnp "
ITEM 3 SCOPE OF SUPPLY
QUANTITY
71 MagPrexTM MAP reactors
- 14 ft. diameter x 34 ft. high
1 2 - Minimum Volume: 20,000 gallons per reactor
- MOC: 316 SS
- Includes galvanized reactor platforms as per drawings
Blower and air distribution system
- VKM diffusers and air distribution for each reactor
2 2 - One (1) Aerzen Generation 5 Delta Blower Model GM 1 OS
per reactor
-Brake Horsepower (max) : 15 bHp
- Installed Power: 20 HP per blower
M902 storage tank (10,000 gallons)
Manufacturer: Snyder
3 1 - MOC: HDLPE (High Density Linear Polyethylene)
- Dimensions: 142" diameter x 226" overall height, flat-
bottom, domed-top
Prominent M902 dosing system (1 diaphragm pump per
reactor system, sigma controls and panel, no VFD)
- Includes two (2) dosing pumps per skid (one (1 )
4 1 pump per reactor system)
- Each pump rated up to 35.9 GPH
- Includes one (1 ) Dual Pump H/O/A Scada Interface
Panel 4X 316SS Enclosure per skid
Prominent Defoamer dosing system (1 diaphragm pump
per reactor system, sigma controls and panel, no VFD)
1 - Includes two (2) dosing pumps per skid (one (1 )
5 pump per reactor system)
- Each pump rated up to 35.9 GPH
- Includes one (1 ) Dual Pump H/O/A Scada Interface
Panel NEMA 4X FRP Enclosure per skid
Struvite discharge pumps (1 per each Reactor)
6 2 Flow Rate: 100 gpm
Pump Operating speed: 122 RPM
Page 3
Page 960
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
Item#18.
cn
Power requirement: 3ph, 60hz, 230/460V
Installed Power: 7.5 HP per pump
Manufacturer: Netzsch
7 2 Internal piping system for air distribution, chemical supply
and sludge handling
8 1 Valves provided per Appendix A attached
9 1 Set of Instrumentation provided per Appendix B attached
Control Panel for independent control of each system
10 2 (PanelView Plus 7 10" screen, NEMA 12, VFDs in MCC, no
panel cooling)
1 1 1 Anchor Bolt sizing
12 1 Start-up and commissioning services
13 1 Payment and Performance Bonds
*Note that there is a trade-off between polymer and cake solids improvement,
depending on the needs of the plant, one or the other can be maximized or
both can be improved simultaneously but to a lesser extent.
ITEM 4 SERVICES
CNP will furnish one factory representative for 20 days during 3 trips to assist in
installation inspection, start-up supervision, and operator training. Dates of
service to be scheduled upon Buyer's written request.
ITEM 5 PRICING
EQUIPMENT PRICE PER THE ABOVE SCOPE
MagPrexT`" Sequestration System Base Price $2,139,000.00
Reactor Material of Construction: 316SS
Deduct for using Painted Carbon Steel as
Reactors Material of Construction -$331,000.00
Note: Taxes are excluded (This is a tax-exempt project)
Due to the current fluctuating material prices -CNP reserves the right to
review quote with possible re-calculation of price at time of issuance of
Purchase Order. CNP reserves the right to adjust the tank pricing and
staircase pricing according to the steel index such as MEPS - NORTH
AMERICAN STAINLESS-STEEL PURCHASING PRICE INDEX (SPPI)
Page 14
Page 961
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
Item#18.
cnp
ITEM 6 LEADTIME
EQUIPMENT SUBMITTAL DELIVERY TIME AFTER
PREPARATION TIME APPROVED SUBMITTALS
MagPrex` Sequestration
10 weeks 40 weeks
System
ITEM 7 PAYMENT TERMS
Price Validity: 30 days from the quoted date.
Payment target: 30 days net
Delivery terms: FOB, Jobsite
Payment Item
1 .0 10% for Contract Approval & Signing
2.0 Receipt of Submittals - 70 days per proposal
2.0 10% for Approved Shop Drawing Submittals
2.0 10% for Approved Operation & Maintenance Manuals
3.0 60% for Delivery of Equipment
4.0 10% for Start Up & Commissioning (as broken down below)
4.1 Demonstration and Training (25% of 10%)
4.2 Functional Acceptance Testing (25% of 10%)
4.3 Operational Acceptance Testing (25% of 10%)
4.4 Performance Testing (25% of 10%)
ITEM 8 Liquidated Damages
Limited to $500/day starting 40 weeks after final submittal approval
ITEM 9 TERMS & CONDITIONS
All sales are subject to CNP and the Purchaser's mutually agreed upon Terms &
Conditions of sale. CNP's standard Terms & Conditions of sale are found at the
end of this document.
Page 15
Page 962
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
Item#18. ,centres- s
tcnp
ITEM 10 Performance Guarantee
Provided the design criteria is met as defined in specification 46_63_83.01-2
section 1 .03 A, the below performance guarantee from 46_63_83.01-2 section
1 .03 B shall be satisfied.
The guaranteed system performance shall be:
1 . The content of free (dissolved) ortho-phosphate
between inlet and outlet of the reactor is reduced by 90
percent.
2. The dose of magnesium required to achieve the above
phosphorus removal performance shall be no greater than
1 .5 moles of magnesium added per 1 .0 moles of free ortho-
phosphate fed to the reactor.
3. Struvite particle size:
a. The minimum size of struvite particles produced in the
system should be sufficiently large and dense to
achieve a minimum of 80 percent of struvite mass
removal during digested sludge dewatering.
ITEM 11 Warranty
Warranty: 24 months after date of startup or 30 months after delivery,
whichever comes first. Components that are subject to
usual wear, as well as damages caused by inadequate
attendance or faulty operation shall not be covered by
this warranty.
Five (5) year warranty from delivery on Magnesium
Chloride Storage tank as described.
Page 16
Page 963
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO9001:2015
Item#18.
C I'1
ITEM 12 CLARIFICATIONS AND EXCEPTI NS:
Spec 43_33_20.01-1 1 .04A MgC12 and Antifoam Dosing pump skids shall be
duplex (i.e. Two (2) dosing pumps per skid) with dual
discharges. Includes one (1) Dual Pump H/O/A Scada
Interface Local Control Panel per skid.
Spec 43_33_20.01-7 2.05E 3A Antifoam Dosing pumps local control panel shall be a
NEMA 4X FRP enclosure
Spec 46 63 83-9 Section 3.01 A Pre-inspection of the Reactors at the fabrication
facility for One (1) person over Two (2) days shall be
provided to the purchaser at their request at
additional cost. Reactor's must be signed off by the
purchaser as meeting specifications before Reactor's
can be shipped to site from the fabrication facility.
Tanks shall only be inspected at the fabrication
facility.
Spec 46 63 83-10 Sec 3.02A & 3.05B Hydrostatic Pressure testing shall be performed
at the job site. Hydrostatic Pressure testing is not able
to be performed at Fabrication site. Water for
Hydrostatic testing is supplied by others.
Spec 46 63 83-9 Section 3.05A Additional onsite time outside what is specified shall
be provided and billed at CNP's daily rate.
All Spec sections Instrumentation shall be provided as detailed in
Appendix B attached to this proposal.
Page 17
Page 964
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
Item#18. ftwcnp��
c e n tres- s
ITEM 13 SCOPE EXCLUSIONS
Stairwell & stairs
i Any site preparation work including surveying and soil sampling
■ Building and building plans; Civil works such as the foundation plate for
the system or the building
■ Structural and Civil engineering labor
— Pipes and piping (except from the outside flange of the reactor the
aeration ring inside the reactor)
Sludge holding or storage tanks for sludge equalization.
w Blowers do not include MCC Starter, VFD, External Controls, Isolation,
Valves, Anchor Bolts and Installation Hardware.
■ Anchor bolts
w Supply lines (water and electricity) as well as building services (lighting,
water supply / sink) in the office building
Concrete work and core drill holes
■ Permits
Readiness of the Equipment before requesting start-up service. Non-
readiness may incur additional charges.
Any other auxiliary equipment or service not detailed above.
Issued by
Josh Benoit
Applications Engineer
Date: 06/18/2021
Page 18
Page 965
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO9001:2015
Item#18. c e n tmsap.
ftwcnp��
Appendix A: Valves Supplied
Item Quantity I Description
1 2 6" DeZurik KGC Knife Gate Valve, 316SS body/gate, flanged
(one per ends, teflon packing, metal seat, handwheel actuator with
system) 304SS yoke. Model KGC, 6, ES, F1 , S2, SMP, S2-M*MN-HD12-
S1 .
2 4 6" DeZurik KGC Knife Gate Valve, 316SS body/gate, flanged
(two per ends, teflon packing, metal seat, electric actuator with
system) 304SS
yoke. Model KGC, 6, ES, F 1 , S2, SMP, S2-M*Rotork IQ 10.
3 1 Set of spare parts per spec section 40 05 57.23, 1 .06 including
stem nut, worm shaft subassembly, drive sleeve
subassembly, complete actuator seal kit, actuator gearbox
oil to fill 4 gearboxes, encoder, control module
4 1 1 Special warranty per spec section 01 78 36, 1 .06
Page 9
Page 966
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO9001:2015
Item#18.
cn p
Appendix B: Instrumentation Supplied
Instrument Service Description Instrument Type Manufacturer
Tag
SSPRI-FIT- Reactor 1 Sludge Magnetic Flow Meter Endress & Hauser
0003 Feed Flow Meter
SSPR 1-FIT- Reactor 1 Blower Thermal Mass Flow
0010 Thermal Mass Flow Meter
Meter Sierra Instruments
SSPR 1-AIT- Reactor 1 pH/Temp
0102 Transmitter pH Transmitter Hach
SSPR 1-AE- Reactor 1 pH/Temp pH Probe
0102 Probe Hach
SSPR 1-LE- Reactor 1 Foam
0103 Level Capacitive Rod Ma netrol
SSPR 1-LIT- Reactor 1 Level Pressure Transmitter
0104 Pressure Endress & Hauser
SSPR 1-LSH- Reactor 1 High Tuning Fork Switch
0105 Level Switch Endress & Hauser
SSPRI-FIT- Reactor 2 Sludge Magnetic Flow Meter Endress & Hauser
0004 Feed Flow Meter
SSPR 1-FIT- Reactor 2 Blower Thermal Mass Flow
0020 Thermal Mass Flow Meter
Meter Sierra Instruments
SSPR 1-AIT- Reactor 2 pH/Temp
0102 Transmitter pH Transmitter Hach
SSPR 1-AE- Reactor 2 pH/Temp pH Probe
0202 Probe Hach
SSPR 1-LIT- Reactor 2 Foam
0203 Level Capacitive Rod Ma netrol
SSPR 1-LIT- Reactor 2 Level Pressure Transmitter
0204 Pressure Endress & Hauser
SSPR 1-LSH- Reactor 2 High Tuning Fork Switch
0205 Level Switch Endress & Hauser
SSPR 1-TSH- Struvite Pump 1
0120 Stator Temperature Stator Temp Switch By Netzsch
Switch
SSPRI-PSH- Struvite Pump 1
0120 Discharge Pressure Pressure Switch
Switch Ashcroft
SSPRI-PI- Struvite Pump 1
0120 Discharge Pressure Pressure Gauge Ashcroft
Gauge
Pagel 10
Page 967
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
cn
SSPR 1-TSH- Struvite Pump 2
0220 Stator Temperature Stator Temp Switch By Netzsch
Switch
SSPRI-PSH- Struvite Pump 2
0220 Discharge Pressure Pressure Switch
Switch Ashcroft
SSPRI-P 1- Struvite Pump 2
0220 Discharge Pressure Pressure Gauge Ashcroft
Gauge
SSPR 1-TSH- Blower 1 Motor
0300 Temperature Switch By Aerzen
SSPRI-PI- Blower 1 Inlet Filter
0301 Pressure Gauge
By Aerzen
SSPRI-PI- Blower I Discharge
0302 Pressure Gauge
By Aerzen
SSPRI-TI- Blower 1 Discharge
0303 Temperature By Aerzen
Gauge
SSPR 1-TSH- Blower 1 Discharge
0304 Temperature Switch By Aerzen
SSPR 1-TSH- Blower 2 Motor
0400 Temperature Switch By Aerzen
SSPRI-PI- Blower 2Inlet Filter
0401 Pressure Indicator By Aerzen
SSPRI-PI- Blower 2 Discharge
0402 Pressure Indicator By Aerzen
SSPRI-TI- Blower 2 Discharge
0403 Temperature By Aerzen
Indicator
SSPR 1-TSH- Blower 2 Discharge
0404 Temperature Switch By Aerzen
SSPR 1-LSH- MgC12 Storage By Environmental
0500 Tank Leak Capacitive Switch Solutions
Detection Switch
SSPR 1-LIT- MgC12 Storage
0501 Tank Level Radar
Transmitter Endress & Hauser
SSPR 1-LSH- MgC12 Storage
0502 Tank High Level Float Switch
Switch
SSPR 1-FIT- Reactor 2 MgC12
0501 Dosing Pump Flow Magnetic Flow Meter By Skid Vendor
Meter
Page 1 11
Page 968
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
cn
SSPRI-FIT- Reactor 1 MgC12
0502 Dosing Pump Flow Magnetic Flow Meter By Skid Vendor
Meter
SSPRI-PI- MgCl2 Dosing
N/A Pump 1 Pressure By Skid Vendor
Indicator
SSPRI-PI- MgC12 Dosing
N/A Pump 1 Pulsation By Skid Vendor
Dampener
SSPRI-PI- MgCl2 Dosing
N/A Pump 2 Pressure By Skid Vendor
Indicator
SSPRI-PI- MgC12 Dosing
N/A Pump 2 Pulsation By Skid Vendor
Dampener
SSPRI-PI- Antifoam Dosing
N/A Pump 1 Pressure By Skid Vendor
Indicator
Antifoam Dosing
Pump 1 Pulsation By Skid Vendor
Dampener
SSPRI-PI- Antifoam Dosing
N/A Pump 2 Pressure By Skid Vendor
Indicator
Antifoam Dosing
Pump 2 Pulsation By Skid Vendor
Dampener
Page 1 12
Page 969
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO 9001:2015
Item#18. ftwcnp,
centr 'P4
TERMS AND CONDITIONS OF PURCHASE
These terms and conditions apply to all quotations,proposals,orders acknowledgements or confirmations and
contracts of CNP Corp. (hereinafter"Equipment"). As used in these terms and conditions of sale,the word
"Equipment"includes all hardware,parts,components,software and options.
1. ACCEPTANCE: Our sale to you is limited to and expressly made conditional on your assent to the terms and
conditions of sale herein and,if applicable,on the attendant quotation,both of which form a part of this order
and which supersede and reject all prior agreements, representations, discussions or negotiations, whether
written or oral, with respect hereto and any conflicting or additional terms and conditions of yours, or any
statement therein,whether or not signed by you. We will furnish only the quantities and Equipment specifically
listed on our quotations, proposals, or order acknowledgements or confirmations. We assume no responsibility
for the terms or conditions of, or for furnishing other equipment or material shown in, any plans and/or
specifications for a project to which the equipment quoted or ordered herein pertain or refer.
2. PRICES: Unless otherwise specified in writing,all quoted prices are firm for thirty (30) days from the date of offer.
Stenographic,clerical and mathematical errors are subject to correction.
3. DELIVERY: Dates for the furnishing of services and/or delivery or shipment of equipment are subject to change.
Quoted lead times are figured from the date of receipt of complete technical data and approved drawings as
such may be necessary. We shall not be liable,directly or indirectly,for any delay in or failure to deliver caused
by carriers or delays from labor difficulties,shortages,strikes or stoppages of any sort failure or delay in obtaining
materials from ordinary sources, fires, floods, storms, accidents, or other acts of God or force majeure, by any
statute,regulation,administrative order or decree or order orjudgment of a court of law or other causes beyond
our reasonable control. Unless otherwise agreed to in writing by us,in no event shall we be liable for any damages
or penalties whatsoever,or however designated,resulting from our failure to perform or delay in performing due
to any of the causes specified in this paragraph 3.
4. SHIPMENT,RISK OF LOSS,TAXES:Prices are in US Dollars, F.O.B.Jobsite,unless otherwise noted. Our prices do not
include federal,state,municipal or other government excise,sales,use,occupational,processing,transportation
or like taxes now in force or enacted in the future. You shall pay any taxes we may be required to collect or pay
now or at any time in the future(including interest and penalties imposed by any governmental authority),or any
taxes you may be required to pay,that are imposed on the sale,delivery or support of equipment purchased or
licensed as a part of this order, or you shall provide us with a tax exemption certificate acceptable to the
appropriate taxing authority.
5. CREDIT AND PAYMENT: Unless otherwise noted on our quotation, proposal, or order acknowledgement or
confirmation payment for equipment shall be thirty (30) days net. Any discount period which may be granted
by us begins on the invoice date and all payments are due thirty(30) days after the invoice date. All payments
should be made without deduction,deferment,set-off,lien,or counterclaim of any nature. All amounts due not
paid within the thirty(30) days after the date such amounts are due and payable shall bear interest at the lesser
of 1.5 percent per month or the maximum rate of interest allowed by law. We reserve the right at any time to
suspend credit or to change credit terms provided herein,when,in our sole opinion,your financial condition so
warrants. Failure to pay invoices when such invoices are due and payable, at our election, shall make all
subsequent invoices immediately due and payable irrespective of terms, and we may withhold all subsequent
deliveries until the full account is settled. We shall not,in such event, be liable for delay of the performance or
nonperformance of contract in whole or in part subsequent to such event.
6. CANCELLATIONS AND CHANGES: Orders which have been accepted by us are not subject to cancellation or
changes in specification except upon prior written agreement by us and upon terms that will indemnify us against
all losses resulting from or arising out of such cancellation or change in specifications. In the absence of such
indemnification, we shall be entitled to recover al damages and costs of whatever nature permitted by the
Uniform Commercial Code.
7. DEFFERED SHIPMENT: If shipment is deferred at your request, payment of the contract price shall become due
when you are notified that the equipment is ready for shipment. If you fail to make payment or furnish shipping
instructions we may either extend the time for doing so or cancel the contract. In case of deferred shipment at
your request,storage and other reasonable expenses attributable to such delay shall be payable by you.
8. EQUIPMENT WARRANTY AND REMEDY
a. For new equipment only,we warrant to you that the equipment that is the subject of this sale is free from
defects in design (provided that we have design responsibility),material and workmanship. The duration of
this warranty is twenty-four(24) months from startup or thirty (30) months from equipment delivery to Idaho
Page 13
Page 970
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO9001:2015
Item#18. ft
centres
wwcn p�("Warranty Period"). If you discoverwithin the War my Period a defect in design,material orworkmanship,
you must promptly notify us in writing,preserving the equipment for our inspection. Within a reasonable time
after such notification we will correct any such defect with either new or used replacement parts, at our
option. Such repair,including both parts and labor,is at our expense.
b. For repairs,parts and service provided by us,we warrant to you that the repairs,parts and service we provide
to you will be free from defects in material and workmanship. The duration of this warranty is ninety(90)days
from as applicable (i)the date which the machine required the repairs,parts or service is returned to you by
us, (ii) the date or your receipt of the part, (iii) the date of repair,if performed at your facility. If during this
ninety (90) day period you discover a defect in the repairs, parts or service you must promptly notify us in
writing.
c. All warranty service is subject to our prior examination and approval and will be performed by us at your
facility or at one of our service centers designated by us. All transportation to and from the designated
service center will be at our expense. If we are unable to repair the equipment to conform to the warranty
after a reasonable number of attempts,we will provide at our option,one of the following:(i)a replacement
for such equipment,or(ii) a full refund of the purchase price. These remedies are your exclusive remedies
for breach of warranty. Unless otherwise agreed in writing by us,our warranty extends only to you and is not
assignable to or assumable by any subsequent purchaser, in whole or in part, and any such attempted
transfer shall render all warranties provided hereunder null and void and of no other further force or effect.
d. We will use all reasonable efforts to obtain for you any manufacturer's guarantees or warranties for any sub-
assemblies included in the equipment. To the extent such warranties are assignable;we hereby assign to
you all warranties that are granted to us by our suppliers of any sub-assemblies contained in the equipment.
e. The warranties set forth above are inapplicable to and exclude (i) any product, components or parts not
manufactured by us or covered by the warranty of another manufacturer,(ii)damage caused by accident
or the negligence of you or any third party,normal wear and tear,erosion,corrosion or by disasters such as
fire, flood, wind and lightning, (iii) damage caused by your failure to follow all installation and operation
instructions or manuals or to provide normal maintenance,(iv)damage caused by unauthorized or improper
installation of attachments,repairs or modifications, (v) damages caused by a product or component part
which we did not design,manufacture,supply or repair,or(vi)any other abuse or misuse by you or any third
party.
f. EXCEPT AS SET FORTH IN SUBPARAGRAPHS (a)THROUGH (e)ABOVE,WE DISCLAIM ALL EXPRESS AND IMPLIED
WARRANTIES,INCLUDING BUT NOT LIMITED TO ANY IMPLLIED WARRANTY OF MERCHANTABILITY OR FITNESS FOR
A PARTICULAR PURPOSE.
9. OWNERSHIP: All drawings, designs, and specifications supplied by us have been prepared or assembled by us
and is solely our property. Such drawings,designs and specifications have been furnished in order to provide full
documentation and on the condition that they shall not be reproduced or copied in any manner whatsoever,
in whole Orin part,except for your internal use as necessary,and upon further condition that,as our sole property,
they shall not be used,in whole or in part,for furnishing information to others or for any purpose not specifically
authorized in writing signed by one of our corporate officers. These ownership provisions shall not be superseded
by any printed form used in connection with or arising out of a sale induced by a proposal or otherwise.
10. PATENT INFRINGEMENT:
(a) We warrant that the equipment in the condition sold to you is free of the rightful claim of infringement of any
apparatus claims of any third party U.S. patent issued as of the date of our acknowledgement and
acceptance of your order,and we will defend,indemnify and hold you harmless from such claims,provided,
however,we make no express or implied warranties of non-infringement and undertake no indemnification
in respect to third party rights where the alleged patent infringement is based upon or related to (i) any
method, process or product claims in third party U.S. patent, (ii) any combination of the equipment with
other equipment not supplied by us,(iii)any modifications of the equipment made by you and not approved
by us.
(b) You shall notify us within thirty (30) days of receipt of notice of an alleged third party patent infringement
claim that would entitle you to patent infringement indemnification pursuant to paragraph 1 1(a),and we
shall thereupon assume defense of the claim at our expense. We shall have the sole right to settle or
otherwise compromise a third party claim, including but not limited to the right to either (i) modify the
equipment to avoid infringement if you are agreeable to the modification, (ii) repurchase the equipment
from you at a price equal to the then current fair market value of the equipment, (iii) secure rights by the
assignment or license to permit continued use of the equipment.
(c) If a third party charges us with patent infringement relating to equipment sold by us to you,we shall have
the right to either(i) modify the equipment to avoid infringement if you are agreeable to the modification,
Page 14
Page 971
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO9001:2015
Item#18. in
centres
w c npe �
(ii) repurchase the equipment from you at a priequal to the then current fair market value of the
equipment, (iii) secure rights by the assignment or license to permit continued use of the equipment. If a
third party charges us with patent infringement on the basis set forth in paragraph 11 (a)(i), (ii) or(iii),you
shall hold us harmless for all expenses and awards of damage against us,and we shall also have the right to
modify or repurchase the equipment or to secure rights for continued use by way of assignment or license
set forth in this paragraph.
11. SAFETY AND HEALTH STANDARDS: The equipment described herein (or on specifications provided herewith)
complies with applicable safety and health standards issued pursuant to the Occupational Safety and Health
Act of 1970 (the Act) and in effect on this date as such standards are interpreted and understood by us.These
standards may be amended and/or their meaning may be clarified prior to shipment or performance, and if
such changes or clarification requires changes in the equipment described herein,we shall make the necessary
changes available to you. You shall pay for any and all changes at our prices therefore in effect at time of
shipment or performance,as the case may be. Because actual compliance by employers with the Act is beyond
our control,we cannot and do not represent that the use of the equipment described herein,nor the location,
installation or maintenance thereof,will comply with the Act or regulations and standards issued pursuant thereto.
We make no representation of compliance with safety and health standards contained in any statute,
regulations or ordinance of any state or political subdivision thereof applicable to the equipment described
herein unless you have notified us of the existence and contents of such standards and we have agreed in writing
to the incorporation of such standards in the specifications relating to such equipment. Nothing in this provision
shall operate to modify or affect in any manner whatsoever our disclaimer of any liability for consequential
damages contained elsewhere in these terms and conditions of sale.
12. INSPECTION: Upon prior written notice,you may make reasonable inspections of equipment at our facility. We
reserve the right to determine the reasonableness of the request and to select an appropriate time and location
for such inspection.You agree to execute appropriate confidentiality provisions upon our request prior to visiting
our facility. All costs of inspection shall be solely determined by us and shall be payable by you. No inspection
or expediting by you at the facilities of our suppliers is authorized.
13. SOFTWARE PROVISIONS: If software is provided hereunder,you are granted a nonexclusive, royalty free license
only for your use of the software provided with our equipment. Under this license you may: (i) use our software in
machine readable code only and only with the equipment provided, (ii) copy our software into any machine
readable object code form for backup purposes in support of your use of our software on the equipment
provided,and (iii) create one additional copy of the software for archival purposes only. This license may not be
assigned,sublicensed or otherwise transferred by you with our prior written consent. You hereby recognize and
acknowledge that the software provided to you hereunder comprises valuable trade secret and/or copyright
property of CNP (or its licensor) and you covenant that you will take adequate precautions against access to
the software by,or disclosure of the software to,anyone not authorized hereunder to use or have access to the
software.
14. TIME LIMIT FOR BRINGING SUIT:Any action you file against us,whether for breach of contract,including but not
limited to breach of warranty, or for negligence or strict tort, must be commenced within ninety (90) days
following the expiration of the Warranty Period.
15. MODIFICATION OF TERMS:The terms and conditions set forth herein are an integral part of our quotation,proposal
and/or order acknowledgement or confirmation. These terms shall not be deemed altered,modified or added
to by printed or other"standard"terms in the purchase order,acceptance or similar document. Our confirmation
or acknowledgement of any order is with the express understanding that all printed or other"standard"language
on any such documents submitted by you will be entirely disregarded to the extent that it varies from the terms
and conditions of this proposal/offer which may be modified only by typed or handwritten language in the body
of you order,acceptance or similar document,together with a written acknowledgement and acceptance of
such modification by us.
16. LIMITATION ON WARRANTIES:THE WARRANTIES SET FORTH HEREIN ARE IN LIEU OF ANY OTHER WARRANTIES,EXPRESS
OR IMPLIED, INCLUDING AN IMPLIED WARRANTY IF MERCHANTABILITY,AN IMPLIED WARRANTY OF FITNESS FOR A
PARTIC U LARPU R POSE,AND AN IMPLIED WARRANTYOF NONINFRINGEMENT. WE HERBY EXPRESSLY EXCLUDE FORM
THIS CONTRACT THE IMPLIED WARRANTY OF MERCHANTABILITY, THE IMPLIED WARRANTY OF FITNESS FOR A
PARTICULAR PURPOSE, AND THE IMPLIED WARRANTY OF NONINFRINGEMENT, OUR WARRANTIES AND LIABILITIES
HEREUNDER ARE LIMITED AS STATED HEREIN.
17. APPLICABLE LAW: Any controversy or claim arising out of the contract or the breach thereof shall be finally
decided with binding effect on both parties by the courts of Idaho and in accordance with the laws of the State
of Idaho,without giving effect to the provisions thereof relating to conflict of laws. THE EQUIPMENT AND PARTS
DESCRIBED IN THESE TERMS AND CONDITIOINS OF SALE MAY CAUSE INJURY IF NOT OPERATED PROPERLY AND FOR
Page 1 15
Page 972
Centrisys/CNP 9586 58th Place I Kenosha,WI 53144 USA P +1(262)654-6006 E info@centrisys.com I info@cnp-t
CNP-a division of Centrisys Corporation I ISO9001:2015
Item#18. in,centres we n �
THIS REASON ALL OPERATORS SHOULD BECOME THO UGHLY FAMILIAR WITH THE OPERATING INSTRUCTIONS
BEFORE OPERATING THE EQUIPMENT.
18. Indemnification and Insurance:
7.1 SUPPLIER shall indemnify and save and hold harmless CITY from and for any and all losses, claims, actions,
judgments for damages,or injury to persons or property and losses and expenses and other costs including
litigation costs and attorney's fees, arising out of, resulting from, or in connection with the performance of
this Agreement by the SUPPLIER,its servants,agents,officers,employees,guests,and business invitees,and
not caused by or arising out of the tortuous conduct of CITY or its employees.SUPPLIER shall maintain,and
specifically agrees that it will maintain,throughout the term of this Agreement, liability insurance,in which
the CITY shall be named an additional insured in the minimum amounts as follow:General Liability One Million
Dollars ($1,000,000) per incident or occurrence, Professional Liability One Million Dollars ($1,000,000) per
incident or occurrence, Automobile Liability Insurance One Million Dollars ($1,000,000) per incident or
occurrence and Workers' Compensation Insurance, in the statutory limits as required by law..The limits of
insurance shall not be deemed a limitation of the covenants to indemnify and save and hold harmless CITY;
and if CITY becomes liable for an amount in excess of the insurance limits, herein provided, SUPPLIER
covenants and agrees to indemnify and save and hold harmless CITY from and for all such losses, claims,
actions,orjudgments for damages or injury to persons or property and other costs,including litigation costs
and attorneys' fees,arising out of,resulting from,or in connection with the performance of this Agreement
by the SUPPLIER or SUPPLIER's officers,employs, agents,representatives or sub-SUPPLIERS and resulting in or
attributable to personal injury,death,or damage or destruction to tangible or intangible property,including
use of. SUPPLIER shall provide CITY with a Certificate of Insurance, or other proof of insurance evidencing
SUPPLIER'S compliance with the requirements of this paragraph and file such proof of insurance with the CITY
at least ten (10) days prior to the date SUPPLIER begins performance of its obligations under this Agreement.
In the event the insurance minimums are changed,SUPPLIER shall immediately submit proof of compliance
with the changed limits. Evidence of all insurance shall be submitted to the City Purchasing Agent with a
copy to Meridian City Accounting,33 East Broadway Avenue,Meridian,Idaho 83642
7.2 Any deductibles,self-insured retention,or named insureds must be declared in writing and approved by the
City. At the option of the City, either: the insurer shall reduce or eliminate such deductibles, self-insured
retentions or named insureds; or the SUPPLIER shall provide a bond, cash or letter of credit guaranteeing
payment of losses and related investigations,claim administration and defense expenses.
7.3 To the extent of the indemnity in this contract,SUPPLIER's Insurance coverage shall be primary insurance
regarding the City's elected officers, officials, employees and volunteers. Any insurance or self-insurance
maintained by the City or the City's elected officers,officials,employees and volunteers shall be excess of
the SUPPLIER's insurance and shall not contribute with SUPPLIER's insurance except as to the extent of City's
negligence.
7.4 The SUPPLIER's insurance shall apply separately to each insured against whom claim is made or suit is
brought,except with respect to the limits of the insurer's liability.
7.5 All insurance coverages for Suppliers subs shall be subject to all of the insurance and indemnity requirements
stated herein.
7.6 The limits of insurance described herein shall not limit the liability of the Supplier and Supplier's agents,
representatives,employees,or subcontractors.
7.7 The limits of insurance described herein shall not limit the liability of the Contractor and Contractor's agents,
representatives,employees,or subcontractors.
Page 16
Page 973