HomeMy WebLinkAboutChange Order with Wright Brother's Construction for Generations Plaza 2CONTRACT CHANGE ORDER
DATE: October 18, 2000 ORDER NO.:
CONTRACT FOR: GENERATIONS PLAZA PHASE 2
OWNER: CITY OF MERIDIAN, IDAHO
01
TO:
Wright Brothers Construction
(Contractor)
You are hereby requested to comply with the following changes from the contract
plans and specifications:
Description of Changes In INCREASE DECREASE
This Change Order in Contract Price in Contract Price
(list separately)
Excavate Contaminated Soil $630.00
Additional General Requirements
for Contaminated Soil Delay $485.06
Electrical Lighting Change $0.00
Change of Drinking Fountain -$465.00
Deduct for Donated Concrete -$175.00
Costs
Sum of Increase and Decrease: $475.06
Net Change in Contract Price: $475.06
JUSTIFICATION (attach supPlemental documents):
CHANGE IN CONTRACT PRICE:
Original Contract Price:
Previous Change Orders No. 0 to No. 0
Contract Price prior to this Change Order:
Net (Increase/Decrease of this Change Order:
29
$88,780.00
0
$88,780.00
$475.06
Contract Price with all approved Change Orders: $89,255.06
CHANGE IN CONTRACT TIME:
Original Contract Time:
Nov. 17, 2000
0
Nov. 17, 2000
Previous Change Orders No. 0 to No. 0
Contract Time prior to this Change Order:
Net (Increase/Decrease) of this Change Order:
3 days
Contract Time with all approved Change Orders:
Nov. 22,2000
This document will become a supplement to the Contract and all provisions
will apply hereto.
ACKNOWLEDGEMENT OF CHANGE ORDER LIMITS
BY CONTRACTOR
The increase or decrease in Contract price and/or Contract time stated in each and
every Change Order shall unequivocally comprise the total price and/or time
adjustment due or owed the CONTRACTOR for the work or changes ordered by the
Change Order. By executing the change Order, the CONTRACTOR acknowledges
and agrees that the stipulated price and/or time adjustments represent full
compensation for all increases or decreases in cost or the time required to perform
the Contract as whole arising directly or indirectly from the Change Order, including
costs and delays associated with the interruption of schedules, extended overheads,
delay, and cumulative impacts or ripple effect on all other non-affected work under
Contract not changed by the Change Order. Signing of the Change Order
constitutes full and mutual accord and satisfaction for the adjustment in Contract
price and/or time, subject to the current scope of the entire work as set forth in the
Contract Documents. Acceptance of this Change order constitutes an agreement
between Owner and CONTRACTOR that the Change Order represents an equitable
adjustment to the Contract, and that CONTRACTOR will waive all rights to file a
claim of the Change Order after it is properly executed.
All Change Orders shall include a written record, submitted by the CONTRACTOR,
that states the basis of cost amount, including time and materials data, that enables
the Owner to determine the necessity ar~ re~s( ~ableness of the Change Order.
~~uMMENDED~ David Koga ~ ~ I DATE: 10/18/00
'~ ~'~,~ / / LA~SCAP~R~H ~
~~PPI ~0~ D :~~~~_~~ DATE:
...... ~ z~. m~~/~ON~CTOR