HomeMy WebLinkAbout15448214_4_Bidding-Contract Documents - MTC Phase 3 (26-May-2021)_signed
OWNER
Meridian CenterCal, L.L.C.
13400 South Mountain View Corridor
Riverton, Utah 84065
Contact: Lance Blackwood, Project Manager
Office: 801.803.6480
Email: lblackwood@centercal.com
ENGINEER
NV5
690 S. Industry Way, Suite 10
Meridian, Idaho 83642
Contact: Robert Beckman, PE, PTOE
Direct: 208-275-8715
Mobile: 630-200-7782
Email: robert.beckman@NV5.com
Project Bid and Contract Documents Meridian Town Center
Page 3 of 114 Offsite Improvements - Phase 3
TABLE OF CONTENTS
TABLE OF CONTENTS ..................................................................................................................................................... 3
BIDDING INFORMATION ................................................................................................................................................ 5
INVITATION FOR BIDS ............................................................................................................................................... 7
INSTRUCTIONS TO BIDDERS ...................................................................................................................................... 9
Article 1. DEFINED TERMS ........................................................................................................................... 9
Article 2. COPIES OF BIDDING DOCUMENTS ............................................................................................... 9
Article 3. QUALIFICATIONS OF BIDDERS ...................................................................................................... 9
Article 4. EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE .......................... 10
Article 5. PRE-BID CONFERENCE ................................................................................................................ 12
Article 6. SITE AND OTHER AREAS ............................................................................................................. 12
Article 7. INTERPRETATIONS AND ADDENDA ............................................................................................ 12
Article 8. OMITTED .................................................................................................................................... 12
Article 9. CONTRACT Dates ........................................................................................................................ 12
Article 10. SUBSTITUTE AND “OR-EQUAL” ITEMS ....................................................................................... 12
Article 11. SUBCONTRACTORS, SUPPLIERS AND PROJECT TEAM ................................................................ 12
Article 12. PREPARATION OF BID ................................................................................................................. 13
Article 13. BID .............................................................................................................................................. 13
Article 14. SUBMITTAL OF BID ..................................................................................................................... 14
Article 15. MODIFICATION AND WITHDRAWAL OF BID ............................................................................... 14
Article 16. OMITTED .................................................................................................................................... 14
Article 17. BIDS TO REMAIN SUBJECT TO ACCEPTANCE .............................................................................. 14
Article 18. AWARD OF CONTRACT ............................................................................................................... 14
Article 19. CONTRACT SECURITY AND INSURANCE ..................................................................................... 15
Article 20. SIGNING OF AGREEMENT ........................................................................................................... 15
BID FORM ................................................................................................................................................................ 17
BID CERTIFICATE ..................................................................................................................................................... 23
CONSTRUCTION SCHEDULE .................................................................................................................................... 24
CASH FLOW SCHEDULE ........................................................................................................................................... 25
INFORMATION REQUIRED OF BIDDERS .................................................................................................................. 27
CONTRACT FORMS ...................................................................................................................................................... 30
CONSTRUCTION AGREEMENT ................................................................................................................................. 31
Article 1. WORK ......................................................................................................................................... 31
Article 2. THE PROJECT .............................................................................................................................. 31
Article 3. ENGINEER ................................................................................................................................... 31
Article 4. CONTRACT DATES ....................................................................................................................... 31
Article 5. CONTRACT PRICE ........................................................................................................................ 32
Article 6. PAYMENT PROCEDURES ............................................................................................................. 32
Article 7. INTEREST .................................................................................................................................... 32
Article 8. CONTRACTOR’S REPRESENTATIONS ........................................................................................... 32
Article 9. CONTRACT DOCUMENTS ............................................................................................................ 33
Article 10. MISCELLANEOUS ........................................................................................................................ 34
NOTICE TO PROCEED .............................................................................................................................................. 37
CHANGE ORDER ...................................................................................................................................................... 39
WORK CHANGE DIRECTIVE ..................................................................................................................................... 41
CERTIFICATE OF SUBSTANTIAL COMPLETION ......................................................................................................... 43
CERTIFICATE OF FINAL COMPLETION ...................................................................................................................... 45
CONTRACTOR’S PROJECT CERTIFICATION .............................................................................................................. 47
GENERAL CONDITIONS ................................................................................................................................................ 49
GENERAL CONDITIONS ............................................................................................................................................ 50
Project Bid and Contract Documents Meridian Town Center
Page 4 of 114 Offsite Improvements - Phase 3
Article 1. DEFINITIONS AND TERMINOLOGY ............................................................................................. 50
Article 2. PRELIMINARY MATTERS ............................................................................................................. 54
Article 3. CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE ............................................................. 55
Article 4. AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE POINTS ...... 56
Article 5. BONDS AND INSURANCE ............................................................................................................ 60
Article 6. CONTRACTOR’S RESPONSIBILITIES ............................................................................................. 64
Article 7. OTHER WORK ............................................................................................................................. 74
Article 8. OWNER’S RESPONSIBILITIES ....................................................................................................... 74
Article 9. STATUS OF OWNER’S REPRESENTATIVE AND ENGINEER DURING CONSTRUCTION .................. 75
Article 10. CHANGES IN THE WORK; CLAIMS ............................................................................................... 77
Article 11. COST OF WORK; CASH ALLOWANCES; UNIT PRICE WORK ......................................................... 79
Article 12. CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT DATES ................................................ 82
Article 13. TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK ... 84
Article 14. PAYMENTS TO Contractor AND COMPLETION ........................................................................... 87
Article 15. SUSPENSION OF WORK AND TERMINATION .............................................................................. 92
Article 16. DISPUTE RESOLUTION ................................................................................................................ 93
Article 17. MISCELLANEOUS ........................................................................................................................ 95
SUPPLEMENTARY CONDITIONS ................................................................................................................................... 97
SUPPLEMENTARY CONDITIONS .............................................................................................................................. 98
SPECIAL PROVISIONS ................................................................................................................................................. 113
SPECIAL PROVISIONS ............................................................................................................................................ 114
Bidding Information Meridian Town Center
Page 5 of 114 Offsite Improvements - Phase 3
BIDDING INFORMATION
Advertisement for Bids Meridian Town Center
Page 7 of 114 Offsite Improvements - Phase 3
INVITATION FOR BIDS
Separate sealed bids for the “Meridian Town Center – Offsite Improvements - Phase 3” project, which is comprised
of ITD Project A013(349); Key No. 13349 (the “Project”) must be received by Engineer at 690 S. Industry Way, Suite
10, Meridian, Idaho 83642 until 3:00 pm prevailing time on Monday, June 21, 2021.
General Project Description
The Project generally consists of the following “Work.” The descriptions below are general only. Please see the
Contract Documents for a complete description of the Work.
Southbound N Eagle Road widening from E River Valley Street to E Franklin Road inclusive of
pavement reconstruction, retaining walls, traffic signal modifications, and drainage facilities.
Contract Documents
The Contract Documents may be obtained from Engineer.
Contract Dates
Developer expects to issue a Notice to Proceed for the Project on or about July 14, 2021, provided that the Contract
has been approved by Idaho Transportation Department (“ITD”). The Substantial Completion deadline for the Work
will be February 17, 2022.
The above Substantial Completion deadlines are critical to Developer. Bids will be evaluated, in part, on Developer’s
evaluation of the bidder’s ability to achieve Substantial Completion of each portion of the Work on or before
Substantial Completion deadline for that portion of the Work.
All Work must be finally complete no later than thirty (30) days after Substantial Completion.
Pre-Bid Conference
A pre-bid conference will be held at via video conference call on Monday, June 7, 2021. . Meeting invite and web
link to be provided by Engineer. Bidder attendance at the pre-bid conference is encouraged but not required.
Licenses and Registrations
Each bidder must hold all licenses and registrations that may be required by applicable law for the bidder to fully
perform the Work, if the bidder is selected. Although the Project is not a public works project and not subject to the
licensing requirements for public work projects, each bidder and all of the bidder’s subcontractors must hold a valid
public works contractor’s license for the State of Idaho with all of the categories and bid limits to bid on the Project
as if it were a public works contract.
Additional Information
Questions or concerns regarding the Project should be directed in writing to:
Robert Beckman, PE, PTOE
NV5
690 S. Industry Way, Suite 10
Meridian, Idaho 83642
Direct: 208-275-8715
Email: robert.beckman@NV5.com
Instructions to Bidders Meridian Town Center
Page 9 of 114 Offsite Improvements - Phase 3
INSTRUCTIONS TO BIDDERS
ARTICLE 1. DEFINED TERMS
Terms used in these Instructions to Bidders will have the meanings indicated in the General Conditions,
Supplementary Conditions and Special Provisions. Additional terms used in these Instructions to Bidders have the
meanings indicated below which are applicable to both the singular and plural thereof:
(A) Bidder - The entity who submits a Bid pursuant to these Instructions to Bidders.
(B) Issuing Office - The office from which the Bidding Documents are to be issued and where the bidding
procedures are to be administered.
(C) Successful Bidder - The Bidder submitting a responsive Bid to whom Developer (on the basis of Developer’s
evaluations as hereinafter provided) elects to make an award.
ARTICLE 2. COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents may be examined or obtained as stated in the Invitation for Bids.
2.02 Complete sets of Bidding Documents must be used in preparing Bids; neither Developer nor Engineer nor
Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete
sets of Bidding Documents.
2.03 Developer, Engineer, in making copies of Bidding Documents available on the above terms, do so only for
the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3. QUALIFICATIONS OF BIDDERS
3.01 In order to bid on or perform public work, Bidder and its Subcontractors must hold a current Idaho public
works contractor’s license and any licenses as required by Laws and Regulations.
3.02 Bidder will submit with its bid written evidence of Bidder’s qualifications to perform the Work, including:
(A) A summary of Bidder’s performance on projects of similar or greater scope, complexity and schedule
constraints, including whether or not Bidder performed the project in accordance with Bidder’s
schedule obligations;
(B) Bidder’s present commitments on other project, including any future commitments that have the
potential to interfere with Bidder’s ability to perform the Work in accordance with schedule
commitments identified in the Bidding Documents;
(C) Bidders proposed team for the executive management of the Work, and for each member of the team,
the member’s experience and qualifications in performing projects of similar or greater scope,
complexity and schedule constraints;
(D) Bidders proposed team for the on-site supervision of the Work (e.g., project managers,
superintendents and any other valued members of the supervisory team), and for each member of the
team, the member’s experience and qualifications in performing projects of similar or greater scope,
complexity and schedule constraints;
(E) Bidder’s proposed construction schedule indicating how Bidder plans to complete the Work in
accordance with the applicable Contract Dates for the Work;
(F) Bidder’s current experience modification rate (EMR), as calculated by the National Council on
Compensation Insurance (NCCI), if available;
(G) Bidder’s proposed site safety plan for the Work; and
(H) Any other information that Bidder deems relevant for Developer’s consideration of Bidder’s
qualification to perform the Work in accordance with the terms of the Bidding Documents.
3.03 Bidder and its controlling equity holders and executive officers must not be persons or entities with whom
U.S. persons or entities are restricted from doing business under regulations of the Office of Foreign Asset
Instructions to Bidders Meridian Town Center
Page 10 of 114 Offsite Improvements - Phase 3
Control ("OFAC") of the Department of the Treasury (including those named on OFAC's Specially Designated
and Blocked Persons List) or under any statute, executive order (including the September 24, 2001,
Executive Order Blocking Real Property and Prohibiting Transactions with Persons Who Commit, Threaten
to Commit, or Support Terrorism), or other governmental action and to its knowledge there are no
investigations, claims or proceedings inconsistent with the foregoing.
ARTICLE 4. EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE
4.01 Subsurface and Physical Conditions
(A) The Supplementary Conditions identify:
(i) Those reports of explorations and tests of subsurface conditions at or contiguous to the Site
used in preparing the Bidding Documents.
(ii) Those drawings of physical conditions in or relating to existing surface and subsurface structures
at or contiguous to the Site (except Underground Facilities) used in preparing the Bidding
Documents.
(B) Copies of reports and drawings referenced in Section 4.01(A) will be made available by Engineer to any
Bidder on request. Those reports and drawings are not part of the Contract Documents, but the
“technical data” contained therein upon which Bidder is entitled to use as provided in Section 4.02 of
the General Conditions has been identified and established in Section 2 of the Supplementary
Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical
data” or any other data, interpretations, opinions, or information contained in the reports or shown or
indicated in the drawings.
4.02 Underground Facilities
Information and data shown or indicated in the Bidding Documents with respect to existing Underground
Facilities at or contiguous to the Site is based upon information and data furnished to Developer, Engineer
by owners of the Underground Facilities, or others.
4.03 Hazardous Environmental Condition
(A) The Supplementary Conditions identify those reports and drawings relating to a Hazardous
Environmental Condition identified at the Site, if any, used in preparing the Bidding Documents.
(B) Copies of reports and drawings referenced in Section 4.03(A) will be made available by Engineer to any
Bidder on request. Those reports and drawings are not part of the Contract Documents, but the
“technical data” contained therein upon which Bidder is entitled to use as provided in Section 4.06 of
the General Conditions has been identified and established in Section 2 of the Supplementary
Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical
data” or any other data, interpretations, opinions, or information contained in the reports or shown or
indicated in the drawings.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with
respect to subsurface conditions, other physical conditions and Underground Facilities, and possible
changes in the Bidding Documents due to differing or unanticipated conditions appear in Sections 4.02, 4.03
and 4.04 of the General Conditions. Provisions concerning responsibilities for the adequacy of data
furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any,
and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered
or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in
the Contract Documents to be within the scope of the Work appear in Section 4.06 of the General
Conditions.
4.05 On request, Developer will coordinate Bidder access to the Site to conduct any examinations, investigations,
explorations, tests, and studies as Bidder deems necessary for submission of a Bid. If Bidder desires to
perform exploratory work in the public right-of-way, Bidder must secure any necessary permits and licenses
for the exploratory work. Bidder must fill all holes and clean up and restore the Site to its former condition
upon completion of the explorations, investigations, tests, and studies.
Instructions to Bidders Meridian Town Center
Page 11 of 114 Offsite Improvements - Phase 3
4.06 Reference is made to Article 7 of the General Conditions for the identification of the general nature of other
work that is to be performed at the Site by others (such as utilities and other contractors) that relates to
the Work for which a Bid is to be submitted. On request, Developer will provide each Bidder with reasonable
access to (or copies of) the contract documents (other than portions thereof related to price) for the other
work.
4.07 It is responsibility of each Bidder before submitting a Bid to:
(A) Examine and carefully study the Bidding Documents, including any Addenda and the other related data
identified in the Bidding Documents;
(B) Visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions
that may affect cost, progress, and performance of the Work;
(C) Become familiar with and satisfy Bidder as to all Federal, State, and local Laws and Regulations that
may affect cost, progress, or performance of the Work;
(D) Carefully study all reports of explorations and tests of subsurface conditions at or contiguous to the
Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at
or contiguous to the Site (except Underground Facilities) which have been identified in the
Supplementary Conditions, and carefully study all reports and drawings of a Hazardous Environmental
Condition, if any, at the Site which have been identified in the Supplementary Conditions ;
(E) Obtain and carefully study (or assume responsibility for doing so) all additional or supplementary
examinations, investigations, explorations, tests, studies, and data concerning conditions (surface,
subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost, progress,
or performance of the Work or which relate to any aspect of the means, methods, techniques,
sequences, and procedures of construction to be employed by Bidder, including any specific means,
methods, techniques, sequences, and procedures of construction expressly required by the Bidding
Documents, and safety precautions and programs incident thereto;
(F) Agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests,
studies, or data are necessary for the determination of its Bid for performance of the Work at the price
bid and within the times and in accordance with the other terms and conditions of the Bidding
Documents;
(G) Become aware of the general nature of the work to be performed by Developer and others at the Site
that relates to the Work as indicated in the Bidding Documents;
(H) Correlate the information known to Bidder, information and observations obtained from visits to the
Site, reports and drawings identified in the Bidding Documents, and all additional examinations,
investigations, explorations, tests, studies, and data with the Bidding Documents;
(I) Promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder
discovers in the Bidding Documents and confirm that the written resolution thereof (issued by
Engineer) is acceptable to Bidder; and
(J) Determine that the Bidding Documents are generally sufficient to indicate and convey understanding
of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has
complied with every requirement of this Article 4, that without exception the Bid is premised upon
performing and furnishing the Work required by the Bidding Documents and applying any specific means,
methods, techniques, sequences, and procedures of construction that may be shown or indicated or
expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts,
errors, ambiguities, and discrepancies that Bidder has discovered in Bidding Documents and the written
resolutions thereof (issued by Engineer) are acceptable to Bidder, and that the Bidding Documents are
generally sufficient to indicate and convey understanding of all terms and conditions for performing and
furnishing the Work.
Instructions to Bidders Meridian Town Center
Page 12 of 114 Offsite Improvements - Phase 3
ARTICLE 5. PRE-BID CONFERENCE
A pre-bid conference will be held via video conference call as set forth in the Invitation for Bids. Engineer will be
present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Engineer will
transmit to all prospective Bidders of record any Addenda as Engineer considers necessary in response to
questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally
effective.
ARTICLE 6. SITE AND OTHER AREAS
The Site is identified in the Bidding Documents. All additional lands and access thereto required for temporary
construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the
Work are to be obtained and paid for by the Successful Bidder. Easement for permanent structures or permanent
changes in existing facilities are to be obtained and paid for by Developer unless otherwise provided in the Bidding
Documents.
ARTICLE 7. INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer in
writing. Interpretations or clarifications considered necessary by Engineer in response to any questions will
be issued by Addenda mailed or delivered to all parties recorded by Engineer as having received the Bidding
Documents. Questions received less than ten days prior to the date for opening of Bids may not be
answered. Only questions answered by Addenda will be binding. Oral and other interpretations or
clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by
Developer, Engineer.
ARTICLE 8. OMITTED
ARTICLE 9. CONTRACT DATES
The dates for the Work as set forth in Article 4 of the Construction Agreement.
ARTICLE 10. SUBSTITUTE AND “OR-EQUAL” ITEMS
The Contract, if awarded, will be on the basis of materials and equipment specified or described in the Bidding
Documents, or “or-equal” materials and equipment as defined in Section 6.05 of the General Conditions, or those
substitute materials and equipment approved by Engineer, and identified by Addendum. The materials and
equipment described in the Bidding Documents establish a standard of required type, function and quality to be
met by any proposed substitute or “or-equal” item. Request for clarification of materials and equipment
considered “or-equal” prior to the Effective Date of the Agreement must be received by the Engineer at least five
(5) days prior to the date for receipt of Bids. No item of material or equipment will be considered as a substitute
unless written request for approval has been submitted by Bidder and has been received by Engineer at least
fifteen (15) days prior to the date for receipt of Bids. Each request must conform to the requirements of
Section 6.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder.
Engineer’s or Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves
any proposed substitute item, the approval will be set forth in an Addendum issued to all prospective Bidders.
Bidders will not rely upon approvals made in any other manner.
ARTICLE 11. SUBCONTRACTORS, SUPPLIERS AND PROJECT TEAM
11.01 Bidder must submit to Developer a list of all Subcontractors and Suppliers proposed by Bidder for the Work.
Bidder will also submit to Developer a list of all members of Bidder’s proposed team for the Project. The list
must be accompanied by an experience statement with pertinent information regarding similar projects
and other evidence of qualification for each Subcontractor, Supplier or proposed member of Bidder’s team
Instructions to Bidders Meridian Town Center
Page 13 of 114 Offsite Improvements - Phase 3
for the Project. If Developer, Engineer, after due investigation, has reasonable objection to any proposed
Subcontractor, Supplier or Project team member, Developer may request apparent Successful Bidder to
submit a substitute, without an increase in the Bid.
11.02 If apparent Successful Bidder declines to make any substitution, Developer may determine the Bidder to be
non-responsive and reject the Bid. Any Subcontractor, Supplier or Project team member so listed and
against which Developer, Engineer makes no written objection prior to execution of the Contract will be
deemed acceptable to Developer, Engineer subject to revocation of the acceptance after the Effective Date
of the Agreement as provided in Section 6.06 of the General Conditions.
11.03 Bidder will not be required to employ any Subcontractor, Supplier or Project team member against whom
Bidder has reasonable objection.
ARTICLE 12. PREPARATION OF BID
12.01 The Bid form is included with the Bidding Documents, and can be found in the Project Plan Room.
12.02 All blanks on the Bid form must be completed by printing in ink or by typewriter and the Bid signed. A Bid
price must be indicated for each Bid item listed therein, or the words “No Bid,” “No Change,” or “Not
Applicable” entered.
12.03 A Bid by a legal entity must be executed in the entity’s name by a duly authorized representative of the
entity officer and accompanied by evidence of the representative’s authority to sign.
12.04 All names must be typed or printed in ink below the signatures.
12.05 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in
on the Bid form.
12.06 The Bid must have the name, title, address, telephone number and email address for the Bidder’s
representative for communication regarding the Bid.
12.07 The Bid must contain evidence of Bidder’s authority and qualification to do business in the State of Idaho.
Bidder’s Idaho public works contractor’s license number and Idaho contractor’s registration must also be
shown on the Bid form.
ARTICLE 13. BID
Bidders must submit the following documents in its Bid:
(A) A fully complete and signed Bid Form, which has a fixed, lump sum Contract Price for the performance
of the entire Work (and unit prices where requested on the Bid form);
(B) A fully complete and signed Bid Certificate in the form provided herein;
(C) All documents and information requested or required of Bidders, including the documents and
information requested in Section 3.02 and Section 11.01 of these Instructions;
(D) A construction schedule showing Bidder’s proposal for performance of the Work in accordance with
the Contract Dates identified in Article 4 of the Construction Agreement
(E) A cash flow projection analysis for Developer’s payments under the Contract that assumes the Work
progresses in accordance with the construction schedule proposed by the Bidder. The analysis will, for
each projected payment, illustrate the date of each scheduled application for payment, the date of
each scheduled payment, and the allocation of each projected application for payment into each of the
Work categories on the Bid Form;
(F) A fully complete Information Required of Bidders Form with all documents requested therein attached;
and
(G) A fully complete List of Subcontractors Form.
Instructions to Bidders Meridian Town Center
Page 14 of 114 Offsite Improvements - Phase 3
ARTICLE 14. SUBMITTAL OF BID
14.01 Each prospective Bidder will be furnished one copy of the Bidding Documents.
14.02 A Bid must be submitted no later than the date and time prescribed and at the place indicated in the
Invitation for Bids and must be enclosed in an opaque sealed envelope plainly marked with the Project title,
the name and address of Bidder, and must be accompanied by all other required documents. If a Bid is sent
by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate
envelope plainly marked on the outside with the notation “BID ENCLOSED.”
ARTICLE 15. MODIFICATION AND WITHDRAWAL OF BID
15.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the manner that a Bid
must be executed and delivered to the place where Bids are to be submitted prior to the date and time for
the opening of Bids.
15.02 If within twenty-four (24) hours after Bids are opened any Bidder files a duly signed written notice with
Developer and promptly thereafter demonstrates to the reasonable satisfaction of Developer that there
was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid.
ARTICLE 16. OMITTED
ARTICLE 17. BIDS TO REMAIN SUBJECT TO ACCEPTANCE
All Bids will remain subject to acceptance for the period of time stated in the Bid form, but Developer may, in its
sole discretion, release any Bid prior to the end of this period.
ARTICLE 18. AWARD OF CONTRACT
18.01 Developer reserves the right to reject any or all Bids, including without limitation, nonconforming,
nonresponsive, unbalanced, or conditional Bids. Developer further reserves the right to reject the Bid of
any Bidder whom it finds, after reasonable inquiry and evaluation, to be non-responsive. Developer also
reserves the right to waive all informalities and to negotiate contract terms with the Successful Bidder.
18.02 More than one Bid for the same Work from an individual or entity under the same or different names will
not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid
for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that
Bidder has an interest.
18.03 In evaluating Bids, Developer will consider whether or not the Bids comply with the prescribed
requirements, and any alternates, unit prices and other data.
18.04 In evaluating Bidders, Developer will consider the qualifications of Bidders and may consider the
qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for
the Work.
18.05 Developer may conduct any investigations as Developer deems necessary to establish the responsibility,
qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities
to perform the Work.
18.06 If the Contract is to be awarded, Developer will award the Contract to the responsible Bidder whose Bid is
deemed best by Developer with all things considered, including price, schedule, experience and other
factors.
18.07 For purposes of evaluating the Bids, Developer may elect to deem any Bids that are within Two Hundred
Thousand ($200,000) of each other to be “price equivalent” for purposes of evaluating the Bids. In such
event, Developer may rank each “price equivalent” Bid in accordance with Developer’s evaluation of (a) the
information provided by each Bidder pursuant to Section 3.02 and Section 11.01 of these Instructions, and
(b) if a post-Bid interview is requested by Developer, then the information and responses provided by
Bidder’s during the post-Bid interview. Bidder acknowledges and agrees that Developer’s ranking of “price
Instructions to Bidders Meridian Town Center
Page 15 of 114 Offsite Improvements - Phase 3
equivalent” Bids will naturally entail subjective consideration of the information provided, and that absent
clear and convincing evidence of bad faith, Developer’s ranking or selection of any “price equivalent” Bid
over any other “price equivalent” Bid will be final and binding on all Bidders.
ARTICLE 19. CONTRACT SECURITY AND INSURANCE
Article 5 of the General Conditions, as it may be modified by the Supplementary Conditions and Special Provisions,
sets forth Developer’s requirements as to the performance Bond, the payment Bond and insurance. When the
Successful Bidder delivers the executed Agreement to Developer, it must be accompanied by the Bonds and the
insurance documentation required therein.
ARTICLE 20. SIGNING OF AGREEMENT
When Developer notifies the Successful Bidder that it intends to award the Contract to the Successful Bidder, the
Successful Bidder will promptly cooperate with Developer to execute the Contract consistent with the award.
Bidder acknowledges that the Contract will be subject to adjustment prior to execution to make any corrections
desired by Developer and to reflect any changes or updates desired by Developer prior to execution.
Bid Form Meridian Town Center
Page 17 of 114 Offsite Improvements - Phase 3
BID FORM
MERIDIAN TOWN CENTER – OFFSITE IMPROVEMENTS - PHASE 3
Item No.Item Description Estimated
Quantity Unit Unit Price Bid Item Total
203-005A REM OF OBSTRUCTIONS 1 LS -$
203-025A REM OF CATCH BASIN 5 EACH -$
203-060A REM OF CONC SIDEWALK 390 SY -$
203-070A REM OF CURB & GUTTER 844 FT -$
203-075A REM OF FENCE 211 FT -$
203-105A REMOVAL OF MISC IRR STR 3 EACH -$
203-125C REM OF MISC ITEMS, PIPE 724 FT -$
203-130B OBLITERATION OF PVMT MARKINGS 6485 SF -$
203-135A REM OF SIGN 22 EACH -$
-$
205-005A EXCAVATION 12100 CY -$
205-040A GRANULAR BORROW 5900 CY -$
205-060A WATER FOR DUST ABATEMENT 400 MG -$
205-071A EXCAVATION AND REPAIR OF SOFT SPOTS 500 CY -$
-$
212-011A FIBER WATTLE 6824 FT -$
212-095A INLET PROTECTION 33 EACH -$
212-105A WATER POLLUTION & EROSION CTRL 10000 CA -$
-$
301-005A GRANULAR SUBBASE 18550 TON -$
303-022A 3/4" AGGREGATE TYPE B FOR BASE 5250 TON -$
401-020A CSS-1 DILUTED EMULSIFIED ASPHALT FOR TACK COAT 1800 GAL -$
405-245A APPROACH 10 EACH -$
405-435A SUPERPAVE HMA PAV INCL ASPH&ADD CL SP-3 5450 TON -$
-$
604-025A 12" IRR PIPE 59 FT -$
CenterCal Ph3, Eagle Rd Widening
MERIDIAN TOWN CENTER - OFFSITE IMPROVEMENTS PHASE 3
BID SCHEDULE - EAGLE ROAD WIDENING
Any reference in the Bid Schedule to an “estimated quantity” is Engineer’s estimate of the quantity of the “units” of the specified item in
the Work.Such quantity estimate is provided for convenience.Contract shall not base its bid on Engineer’s quantity estimate,but shall
instead independently calculate and verify the quantities of the units for each item required for the proper completion of the Work and
base its bid thereon.
Contractor’s Bid indicated on the Summary Page of the Bid Schedule.Such Bid, if accepted, will be the Contract Price in Article 5 of the
Construction Agreement.Such Total Bid is a lump sum and shall not be subject to adjustment for any variation between the estimated
quantities of each item in the Bid Schedule and the actual quantities of such item in the Work.
Any reference in the Bid Schedule to “unit price” shall be the price for each unit of the specified items, and shall be “unit prices” for the
purpose of Section 11.03 of the General Conditions.
The Work is defined in Section 1.01(A)(56) of the General Conditions.The division of the Work into line items on the Bid Schedule is solely
for Owner’s convenience.The omission from the Bid Schedule of any matter required by, or reasonably inferable from, the Contract
604-040A 21" IRR PIPE 6 FT -$
604-045A 24" IRR PIPE 123 FT -$
605-035A 18" STORM SEWER PIPE 734 FT -$
605-465A MANHOLE TY C 2 EACH -$
605-467A MANHOLE TY D 20 EACH -$
605-515A CATCH BASIN TY 2A 9 EACH -$
605-635A ADJUST MANHOLE COVERS 3 EACH -$
609-025A MINOR STR, IRR BOX 1 1 EACH -$
609-025B MINOR STR, IRR BOX 2 1 EACH -$
-$
610-015A FENCE TY 1B 211 FT -$
610-035A FENCE TY 4 275 FT -$
-$
612-005D W-BEAM GUARDRAIL 450 FT -$
612-115C GUARDRAIL TERMINAL, TANGENT 2 EACH -$
-$
614-015A SIDEWALK 1183 SY -$
614-025A CURB RAMP 191.5 SY -$
615-492A CURB & GUTTER TY. 2 2994 FT -$
-$
616-010A SIGNS TY B 53 SF -$
616-055A SIGN POST TY D 1 EACH -$
616-080A REMOVE AND REINSTALL SIGN (ON NEW POST)18 EACH -$
-$
618-025A STREET MONUMENT 3 EACH -$
-$
621-005A SEED BED PREPARATION 1.283 AC -$
621-010A SEEDING 1.283 AC -$
621-015A MULCHING 1.283 AC -$
621-035A FERTILIZING 1.283 AC -$
-$
626-010A TEMPORARY TRAFFIC CONTROL SIGNS 1239 SF -$
626-050A DRUMS 300 EACH -$
626-071A ARROW BOARD TY B 1000 HR -$
626-100A MISC TEMPORARY TRAF CONT ITEMS 1 LS -$
626-105A TRAF CONT MAINTENANCE 1500 MNHR -$
626-113A FLOOD LIGHTS 1 LS -$
626-114A PORTABLE CHANGEABLE MESSAGE SIGN (PCMS)1700 HR -$
626-135A WEIGHT BASED TUBULAR MARKERS 250 EACH -$
626-120A FLAGGER CONTROL 720 HR -$
-$
630-020B TRANS PAVEMENT MARKING THERMOPLASTIC 3122 SF -$
630-025A LONG PAVEMENT MARKING WATERBORNE 11160 FT -$
630-025B LONG PAVEMENT MARKING THERMOPLASTIC 12 FT -$
-$
640-015A SUBGRADE SEPARATION GEOTEXTILE TYPE III 15850 SY -$
645-010A CLASS III FIELD LABORATORY 1 LS -$
-$
656-005A EAGLE ROAD/FRANKLIN ROAD SIGNAL MODIFICATION 1 LS -$
656-005B EAGLE ROAD/PINE AVENUE SIGNAL MODIFICATION 1 LS -$
656-005C EAGLE ROAD/FAIRVEIW AVENUE SIGNAL MODIFICATION 1 LS -$
656-005D EAGLE ROAD/RIVER VALLEY STREET SIGNAL MODIFICATION 1 LS -$
-$
675-005A SURVEY 1 LS -$
675-010A DIRECTED SURVEYING OFFICE COMPUTATION 7000 CA -$
675-015A DIRECTED SURVEYING (CREW)18000 CA -$
-$
S501-15A MSE RETAINING WALL, SEGMENTAL BLOCK 2780 SF -$
S501-15B RETAINING WALL, GRAVITY CONCRETE BLOCK 140 SF -$
-$
S604-05A REM & RESET IRRIGATION (SPRINKLER SYSTEM)1 LS -$
-$
S901-05A SP OBSERVATION WELL 20 EACH -$
S901-05B SP OIL/WATER SKIMMER 20 EACH -$
S901-05C SP MODIFIED CATCH BASIN TY 3 13 EACH -$
-$
S904-05A EAGLE ROAD ATMS SYSTEM MODIFICATIONS 1 LS -$
-$
S911-05A SP INFILTRATION TRENCH 1447 FT -$
S912-05A SP LAWN REPAIR 6801 SY -$
S912-05B SP LANDSCAPE REPAIR 267 SY -$
-$
Z629-05A MOBILIZATION 1 LS -$ -$
Total Price:
Item No.Item Description Estimated
Quantity Unit Unit Price Bid Item Total
307.4.1.G.1.TYPE P SURFACE RESTORATION 221 SY
307.4.1.G.3.TYPE P SURFACE RESTORATION WITH PAVEMENT FABRIC 265 SY
308.4.1.A.1.PIPE BORING AND JACKING 20 LF
310.4.1.A.1.a.12" PVC, AWWA C900, DR18 WATER MAIN CASING 93 LF
310.4.1.A.1.b.16" PVC, AWWA C900, DR25 WATER MAIN CASING 119 LF
310.4.1.A.1.c.20" PVC, AWWA C900, DR25 WATER MAIN CASING 396 LF
310.4.1.A.1.d.20"Ø, 3/8" THICK STEEL WATER MAIN CASING 38 LF
310.4.1.A.1.e.24" Ø, 3/8" THICK STEEL WATER MAIN CASING 9 LF
310.4.1.A.1.f.INSTALL NEW WATER MAIN IN EXISTING WATER MAIN 520 LF
401.4.1.A.1.b.8" PVC, AWWA C900, DR18 WATER MAIN 154 LF
401.4.1.A.1.c.8" FUSIBLE PVC, AWWA C900, DR18 WATER MAIN 633 LF
401.4.1.A.1.d.12" PVC, AWWA C900, DR18 WATER MAIN 29 LF
401.4.1.A.1.e.12" (IPS) HDPE, AWWA C906, PE4710, DR9, WATER MAIN 277 LF
401.4.1.A.1.f.16" (IPS) HDPE, AWWA C906, PE4710, DR9, WATER MAIN 864 LF
402.4.1.A.1.a.6" GATE VALVE 1 EA
402.4.1.A.1.b.8" GATE VALVE 6 EA
402.4.1.A.1.c.12" GATE VALVE 8 EA
706.4.1.G.1CONCRETE REPAIR 16 SY
1001.4.1.A.1.SEDIMENT CONTROL 1 LS
1103.4.1.A.1.CONSTRUCTION TRAFFIC CONTROL 1 LS
2030.4.1.C.1.ADJUST EXISTING VALVE BOX TO GRADE 1 EA
2010.4.1.A.1.MOBILIZATION 1 LS
SP-1a
ABANDON EXISTING 6" WATER MAIN IN PLACE, FILL WITH
SAND OR LOW STRENGTH GROUT 142 LF
SP-1b
ABANDON EXISTING 12" WATER MAIN IN PLACE, FILL WITH
SAND OR LOW STRENGTH GROUT 993 LF
SP-1c ABANDON AND REMOVE EXISTING 6" WATER MAIN 44 LF
SP-1d ABANDON AND REMOVE EXISTING 12" WATER MAIN 7,146 LF
SP-1e ABANDON AND REMOVE EXISTING 2" WATER SERVICE LINE 10 LF
SP-1f ABANDON EXISTING 2" WATER SERVICE LINE IN PLACE 137 LF
SP-2 LAWN SOD RESTORATION 2,308 SF
SP-3 REMOVE EXISTING TREE 7 EA
SP-4 CCTV EXISTING 12" WATER MAIN TO CONFIRM SUITABILTY AS A CASING520 LF
SP-5 2" WATER SERVICE LINE (METER TO MAIN)122 LF
MERIDIAN TOWN CENTER - OFFSITE IMPROVEMENTS PHASE 3
BID SCHEDULE - WATER MAIN RELOCATION and ABANDONMENT
CenterCal Ph3, Water Main Relocation and Abandonment
Total Price:
Bid Form Meridian Town Center
Page 23 of 114 Offsite Improvements
BID CERTIFICATE
MERIDIAN TOWN CENTER – OFFSITE IMPROVEMENTS - PHASE 3
An executed copy of this Bid Certificate (this “Certificate”) must accompany the Bid.
Bidder represents, warrants and certifies to Developer as follows. Bidder acknowledges and agrees that Developer
will rely on the accuracy of Bidder’s representations, warranties and certifications herein for the consideration of
Bidder’s Bid, and if Bidder is the Successful Bidder, for entering into a Contract with Bidder.
1. Bidder has read and understands all Bidding Documents.
2. Bidder has fully performed all of its duties, obligations and responsibilities under the Bidding Documents,
including its responsibilities under Section 4.07 of the Bidding Instructions.
3. To the best of Bidder’s knowledge, information and belief after reasonable inquiry, the documents and
information provided by Bidder to Developer (a) are true and correct in all material respects; (b) do not
contain any untrue statement of material fact; and (c) do not omit a material fact required to be stated
therein or necessary to make the statements therein, in light of the circumstances under which they were
made, not misleading. If Contractor discovers that any document or information previously provided by
Contractor failed to comply with the foregoing sentence at the time it was provided, Contractor will
promptly (i) notify Developer of the specific document or information in question, (ii) the nature of the
failure to comply with the foregoing sentence and (iii) if known, the information that would have made the
prior document, report or information comply with the foregoing sentence.
4. Bidder acknowledges and agrees that the Project is not a public works project and Developer is not
obligated to award the Contract to the lowest responsive bidder, or otherwise in accordance with any of
the procedures or requirements for public works projects. Bidder specifically acknowledges and agrees that
the Bid Documents permit Developer to select the Bid that is deemed best by Developer with all things
considered, including price, schedule, experience and other factors.
5. Bidder is the party making Bidder’s Bid; and that the Bid is not made in the interest of, or on behalf of, any
other person or entity; that the Bid is genuine and not collusive or sham; that Bidder has not directly or
indirectly induced or solicited any other bidder to put in a false or sham bid, and has not directly or indirectly
colluded, conspired, connive or agreed with any bidder or anyone else to put in a sham bid, nor that anyone
will refrain from bidding; that Bidder has not in any manner, directly or indirectly, sought by agreement,
communication or conference with anyone to fix any price of Bidder or of any other bidder, nor to fix any
overhead, profit, or cost element of any price, nor of that of any other bidder, nor to secure any advantage
against Developer or any public body interested in the proposed contract; that all statements contained in
the Bid are true; and, further, that Bidder has not directly or indirectly submitted any price or any
breakdown thereof, nor the contents thereof, nor divulged information or data relative thereto, nor paid
and will not pay fee in connection therewith to any person or entity except to such person or entities with
a financial interest with Bidder or its business.
Signed on behalf of Bidder:
(Signature)
Name:
Name:
Date:
Bid Form Meridian Town Center
Page 24 of 114 Offsite Improvements
CONSTRUCTION SCHEDULE
MERIDIAN TOWN CENTER – OFFSITE IMPROVEMENTS - PHASE 3
[ To be provided by Bidder with Bid. ]
Bid Form Meridian Town Center
Page 25 of 114 Offsite Improvements
CASH FLOW SCHEDULE
MERIDIAN TOWN CENTER – OFFSITE IMPROVEMENTS - PHASE 3
[ To be provided by Bidder with Bid ]
Construction Agreement Meridian Town Center
Page 27 of 114 Offsite Improvements
INFORMATION REQUIRED OF BIDDERS
GENERAL INFORMATION
Bidder must furnish the following information. Failure to comply with this requirement will render the Bid
incomplete and may cause its rejection. Additional sheets may be attached as required.
(1) Bidder’s name and address (mail and business):
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
(2) Bidder’s telephone number:(___) ________________________________________
(3) Name and contact information for Bidder’s contact person for this bid:
Name: ________________________________________
Title: ________________________________________
Address: ________________________________________
Telephone: ________________________________________
Email: ________________________________________
(4) Bidder’s Idaho State Public Works Contractor License:
Primary Classification: ____________________________________________________
State License No.: _______________________________________________________
Supplemental Classification held, if any: _____________________________________
Bid Limit: ______________________________________________________________
(5) Number of years as a contractor in construction work of this type: _________________
(6) Names and titles of all officers of Bidder’s firm:
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
Construction Agreement Meridian Town Center
Page 28 of 114 Offsite Improvements
_______________________________________________________________________
(7) Name of person who inspected site of proposed work for your firm:
Name: __________________________ Date of Inspection: ___________________
Name: __________________________ Date of Inspection: ___________________
Name: __________________________ Date of Inspection: ___________________
(8) Name, address, and telephone number of Surety Company and agent who will provide the
required bonds on this contract:
Surety Company: __________________________________________________
Mailing Address: __________________________________________________
City, State, Zip: __________________________________________________
Contact: _____________________________________________________
Phone: _____________________________________________________
Attach to this Bid the proposed form of payment bond and performance bond.
(9) Attach to this Bid the experience résumés of the person who will be designated chief construction
superintendent and each person who will be assistant superintendents.
Construction Agreement Meridian Town Center
Page 29 of 114 Offsite Improvements
LIST OF SUBCONTRACTORS
Bidder must list below the name and address of each Subcontractor who will perform work under the
Contract in excess of one (1) percent of Bidder’s total bid price, and will also list the portion of the Work
which will be done by the Subcontractor. After the opening of Bids, no changes or substitutions will be
allowed except as identified in Section 6.06(B) of the General Conditions.
Work to be
Performed
Subcontractor’s
license number
Subcontractor’s
Name & Address
Percent of
total
contract
Note: Attach additional sheets, if required.
Construction Agreement Meridian Town Center
Page 30 of 114 Offsite Improvements
CONTRACT FORMS
Construction Agreement Meridian Town Center
Page 31 of 114 Offsite Improvements
CONSTRUCTION AGREEMENT
This Construction Agreement (this “Agreement”) is dated as of [December 31, 2020] (“Effective Date”) by and
between Meridian CenterCal, L.L.C., a Delaware limited liability company (“Developer”) and [Contractor], [Contractor
Entity Type] (“Contractor”).
Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as follows:
ARTICLE 1. WORK
Contractor will complete all Work as specified or indicated in the Contract Documents. The Work is defined in
Section 1.01(53) of the General Conditions.
ARTICLE 2. THE PROJECT
The Project for which the Work under the Contract Documents may be the whole or only a part is generally
described as “Meridian Town Center – Offsite Improvements - Phase 3”.
ARTICLE 3. ENGINEER
3.01 The Project has been designed and engineered by WHPacific, Inc., an Alaska corporation dba NV5
(“Engineer”).
3.02 Engineer’s authorized representative for the Project is:
Robert Beckman, PE, PTOE
NV5
690 S. Industry Way, Suite 10
Meridian, Idaho 83642
Office: 208-275-8715
Direct: 630-200-7782
Email: robert.beckman@NV5.com
ARTICLE 4. CONTRACT DATES
4.01 Time is of the Essence
All Contract Dates are of the essence under this Contract.
4.02 Contract Dates
(A) Notice to Proceed Not later than 30 days after Bid opening
(B) Substantial Completion of the entire Work February 17,, 2022
(C) Final Completion Within thirty (30) days after Substantial
Completion.
Contractor acknowledges that the Contract Dates are critical to Developer and Agency. Contractor
represents and warrants to Developer and Agency that the Contract Dates provide a reasonable time for
Contractor to timely complete all of the Work for the applicable Contract Dates, and include time for delays
by third parties, governmental agencies, unexpected events, winter weather and conditions, extreme
weather and all other matters that affect the ability of Contractor to timely perform the Work other than
Force Majeure (as defined in the General Conditions). Contractor is giving the foregoing representation and
warranty to Developer and Agency to induce Developer to enter into this Agreement with Contractor, and
Contractor agrees that Developer has relied on the foregoing representation and warranty and would not
have entered into this Agreement without it. Contractor agrees that the Contract Dates will not be subject
to any adjustment for any reason unless more than thirty (30) days of delay on the critical path are caused
Construction Agreement Meridian Town Center
Page 32 of 114 Offsite Improvements
by Force Majeure (as defined in the General Conditions). Further, Contractor agrees that if Contractor fails
to achieve Substantial Completion of the entire Work by the Contract Date specified, then Contractor will
pay Two Thousand Five Hundred Dollars ($2,500) per day to Agency as liquidated damages for each day
thereafter until Contractor achieves Substantial Completion of the entire Work. Contractor agrees that the
liquidated damages represent a reasonable estimate of the actual damages that would likely be incurred
by Agency due to Contractor’s failure to achieve Substantial Completion of the applicable Work by the
Substantial Completion Deadline.
ARTICLE 5. CONTRACT PRICE
As full compensation for Contractor’s performance of the Work in accordance with the Contract Documents,
Developer will pay Contractor, in the manner and at the times hereinafter provided, a fixed price of
__________________________________________ (____________________), subject to additions and deletions
(if any) as provided in the Contract Documents (the “Contract Price”).
ARTICLE 6. PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
Contractor will submit Applications for Payment in accordance with Article 14 of the General Conditions.
Engineer will process applications for Payment as set forth in the General Conditions.
6.02 Progress Payments; Retainage
(A) Developer will make progress payments on account of the Contract Price on the basis of
Contractor’s Applications for Payment as set forth in the Contract Documents. All progress
payments will be measured by the schedule of values established in Section 14.01 of the General
Conditions (and in that case of Unit Price Work based on the number of units completed) or, in the
event there is no schedule of values, as provided in the General Requirements.
(i) Prior to Substantial Completion, progress payments will be made in an amount equal to
ninety-five percent (95%) of Work completed (with the balance being retainage), but, in
each case, less the aggregate of payments previously made and less any amounts as
Engineer determines (or Developer may withhold), in accordance with Section 14.02 of
the General Conditions.
(ii) Upon Substantial Completion, Developer will pay an amount sufficient to increase total
payments to Contractor to an amount equal to ninety-five percent (95%) of the Work
completed, less any amounts as Engineer determines in accordance with Section 14.02 of
the General Conditions.
6.03 Final Payment
Upon final completion and acceptance of the Work in accordance with Section 14.07 of the General
Conditions, Developer will pay the remainder of the Contract Price as recommended by Engineer as
provided in Section 14.07 of the General Conditions.
ARTICLE 7. INTEREST
All moneys not paid when due as provided in Article 14 of the General Conditions will bear interest at the legal
rate set by Idaho Code § 28-22-104(2).
ARTICLE 8. CONTRACTOR’S REPRESENTATIONS
In order to induce Developer to enter into this Agreement Contractor makes the following representations:
(A) Contractor has examined and carefully studied the Contract Documents and the other related data
identified in the Bidding Documents.
Construction Agreement Meridian Town Center
Page 33 of 114 Offsite Improvements
(B) Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and site
conditions that may affect cost, progress, and performance of the Work.
(C) Contractor is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may
affect cost, progress, and performance of the Work.
(D) Contractor has carefully studied all: (1) reports of exploration and tests of subsurface conditions at or
contiguous to the Site and all drawings of physical conditions in or relating to existing surface or
subsurface structures at or contiguous to the Site, and (2) reports and drawings of Hazardous
Environmental Conditions, if any, at the Site.
(E) Contractor has obtained and carefully studied (or assumes responsibility for obtaining and carefully
studying) all additional or supplementary examinations, investigations, explorations, tests, studies and
data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site
or otherwise may affect the cost, progress, or performance of the Work or which relate to any aspect of
the means, methods, techniques, sequences, and procedures of construction to be employed by
Contractor, including applying the specific means, methods, techniques, sequences, and procedures of
construction, if any, expressly required by the Contract Documents to be employed by Contractor, and
safety precautions and programs incident thereto.
(F) Contractor does not consider that any further examinations, investigations, tests, studies, or data are
necessary for the performance of the Work at the Contract Price by the Contract Dates, and in accordance
with the other terms and conditions of the Contract Documents.
(G) Contractor is aware of the general nature of work to be performed by Developer and others at the Site
that relates to the Work as indicated in the Contract Documents.
(H) Contractor has correlated the information known to Contractor, information and observations obtained
from visits to the Site, reports and drawings identified in the Contract Documents, and all additional
examinations, investigations, explorations, tests, studies and data with the Contract Documents.
(I) Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that
Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is
acceptable to Contractor.
(J) The Contract Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for performance and furnishing of the Work.
ARTICLE 9. CONTRACT DOCUMENTS
9.01 Contents
(A) The Contract Documents consist of the following:
(i) This Agreement;
(ii) Performance Bond;
(iii) Payment Bond;
(iv) General Conditions;
(v) Supplementary Conditions;
(vi) All Special Provisions;
(vii) The Drawings identified by Engineer;
(viii) Addenda (if applicable);
1) Bid Addendum No. 1 dated [______________]; and
2) Bid Addendum No. 2 dated [______________].
(ix) The following which may be delivered or issued on or after the Effective Date of the
Agreement and are not attached hereto:
Construction Agreement Meridian Town Center
Page 34 of 114 Offsite Improvements
1) Written Amendments;
2) Work Change Directives; and
3) Change Order(s).
(B) There are no Contract Documents other than those listed above in this Article 9.
9.02 The Contract Documents may only be amended, modified, or supplemented as provided in Article 3 of the
General Conditions.
ARTICLE 10. MISCELLANEOUS
10.01 Terms
Terms used in this Agreement will have the meanings indicated in the General Conditions, Supplementary
Conditions and Special Provisions.
10.02 Entire Agreement
The Contract Documents set forth the full and complete understanding of Developer and Contractor
relating to the subject matter hereof as of the Effective Date and supersedes any and all negotiations,
agreements, understandings and representations made or dated prior thereto with respect to the subject
matter hereof.
10.03 Amendments
(A) The Contract may not be changed or amended orally. Any change or amendment of any term or
provision of the Contract will only be effective if completed pursuant to Section 3.04 of the General
Conditions . Any reference herein to “agreed by Developer”, “approved by Developer” or words of
similar import will mean Developer’s agreement in writing. Contractor will treat any verbal
authorization or direction for any change to be a directive to promptly prepare and deliver a proper
change document consistent with the verbal authorization or direction to Developer’s authorized
representative for review.
(B) To the extent that any terms, conditions, qualifications or other provisions appearing on, attached
to or related to any document provided to Developer by Contractor (including order
acknowledgments, delivery tickets, invoices, price lists, shop drawings, samples, warranties,
instructions or other documents) are inconsistent with the terms of this Agreement, whether or not
the document is accepted, approved or consented to by Developer, the terms, conditions,
qualifications or other provisions will not be binding on Developer unless the terms are expressly and
conspicuously agreed by Developer.
10.04 Assignment of Contract
(A) The Contract will inure to the benefit of and be binding upon the parties’ successors and permitted
assigns.
(B) In addition to the assignment rights set forth in the Supplementary Conditions, Developer may assign
the Contract in whole or in part, conditionally or otherwise, without Contractor’s approval provided
that the assignee is (a) an affiliate of Developer or the purchaser of the Project from Developer and
(b) the assignee agrees in writing to be bound by the Contract upon acceptance of the assignment.
Developer will immediately notify Contractor of any assignment. Any other assignment will require
Contractor’s prior written consent, which consent will not be unreasonably withheld; provided,
however, no assignment will relieve Developer of any duty or obligation under the Contract unless
otherwise agreed in Contractor’s approval of the assignment.
(C) Contractor may not assign this Agreement or any rights or obligations hereunder without
Developer’s approval. Any assignment without Developer’s approval will be void. No assignment will
relieve Contractor of any duty or obligation under this Agreement unless otherwise agreed in
Developer’s approval of the assignment.
Construction Agreement Meridian Town Center
Page 35 of 114 Offsite Improvements
(D) Contractor will not assign all or part of the monies due or to become due hereunder without
Developer’s consent. Any assignment must expressly subordinate the rights of the assignee to (i)
Developer’s rights under the Contract, (ii) payment of all Subcontractors, suppliers and laborers for
Work performed and all materials and equipment furnished, consumed, used or rented in
performance of the Work, (iii) payments of any amounts due to any jurisdiction over the Project or
Contractor for Work performed, including sales/use taxes, fees and employment taxes and (iv)
amounts payable to third parties for Work performance, including retirement contributions and
worker’s compensation insurance premiums.
[ end of text; signature page follows ]
Construction Agreement Meridian Town Center
Page 36 of 114 Offsite Improvements
IN WITNESS WHEREOF, Developer and Contractor have signed this Agreement in triplicate. One counterpart
each has been delivered to Developer and Contractor. All portions of the Contract Documents have been signed or
identified by Developer and Contractor, or by Engineer on their behalf.
This Agreement will be effective on _____________________, ______ (the “Effective Date”).
Developer MERIDIAN CENTERCAL, L.L.C., a Delaware limited liability
company
By: ___________________________
Name: ___________________________
Title: ___________________________
Contractor: [CONTRACTOR], [Contractor Entity Type]
By: ___________________________
Name: ___________________________
Title: ___________________________
Notice to Proceed Meridian Town Center
Page 37 of 114 Offsite Improvements
NOTICE TO PROCEED
Dated: [____________]
TO: [Contractor]
ADDRESS:
CONTRACT: Construction Agreement
Meridian Town Center – Offsite Improvements - Phase 3
Dated [____________]
You are notified that you may commence with the Work on [_________ ____, 2019]. By that date, you are to start
performing your obligations under the Contract Documents. The Contract Dates, including the dates of Substantial
Completion and the date for readiness for final payment are as set forth in Article 4 of the Agreement.
Before you may start any Work at the Site, you must comply with all requirements set forth in the Contract
Documents that apply prior to the commencement of Work at the Site, including, but not limited to, those
requirements set forth in Section 2.05 of the General Conditions.
[ Insert additional requirements, if any ]
MERIDIAN CENTERCAL, L.L.C., a Delaware limited liability company
By: ____________________________________
Name: ____________________________________
Title: ____________________________________
ACCEPTANCE OF NOTICE
Receipt of the foregoing Notice to Proceed is hereby acknowledged:
By: __________________________________ this _______ day of _______________, ______.
[CONTRACTOR], [Contractor Entity Type]
By: ____________________________________
Name: ____________________________________
Title: ____________________________________
Copy to Engineer
Change Order Meridian Town Center
Page 39 of 114 Offsite Improvements
CHANGE ORDER
No.
DATE OF ISSUANCE __________________ EFFECTIVE DATE
Developer: Meridian CenterCal, L.L.C.
Contractor:
Project: Meridian Town Center – Offsite Improvements - Phase 3
Developer’s Contract No. ________________________
Engineer: ________________________
Engineer’s Contract No. ________________________
Description:
Reason for Change Order:
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT DATES:
Original Contract Price
$______________________
Original Contract Dates:
Net Increase (Decrease) from previous Change Orders
No. _____ to _____:
$______________________
Net change from previous Change Orders No. _____
to _____:
Contract Price prior to this Change Order:
$______________________
Contract Dates prior to this Change Order:
Net Increase (Decrease) of this Change Order:
$______________________
Net Increase (Decrease) of this Change Order:
Contract Price with all approved Change Orders:
$______________________
Contract Dates with all approved Change Orders:
You are directed to make the above changes in the Contract Documents:
RECOMMENDED APPROVED BY OWNER ** ACCEPTED
By: By: By:
Engineer Developer Contractor
Date: Date: Date:
** Developer will not approve any Change Order without prior written approval of the Agency (STAR
Agreement; Section 4.3).
Work Change Directive Meridian Town Center
Page 41 of 114 Offsite Improvements
WORK CHANGE DIRECTIVE
No. _______________
DATE OF ISSUANCE: _______________________________ EFFECTIVE DATE: _________________________
Developer: (Name, Address)
_____________________________________________________________________________________________
Contractor: (Name, Address)
_____________________________________________________________________________________________
CONTRACT:
_____________________________________________________________________________________________
You are directed to proceed promptly with the following change(s):
Description:
Purpose of Work Directive Change:
Attachments: (list documents supporting change)
If Developer or Contractor believes that the above change has affected Contract Price, any claim for a Change
Order based thereon will involve one of the following methods as defined in the Contract Documents.
Method of determining change in Contract Price:
Unit Prices
Lump Sum
Cost of the Work ______________________________
Estimated increase (decrease) in Contract Price Estimated increase (decrease) in Contract Time:
$__________________________. Substantial Completion: ________ days
Ready for final payment: ________ days
If the change involves an increase, the estimated amount and the estimated time is not to be exceeded without further
authorization.
RECOMMENDED: AUTHORIZED:
_____________________________________ __________________________________________
Engineer Developer
By: __________________________________ By: _ ______________________________________
Application for Payment Meridian Town Center
Page 43 of 114 Offsite Improvements
CERTIFICATE OF SUBSTANTIAL COMPLETION
Developer: Meridian CenterCal, L.L.C.
Attn: Lance Blackwood, Project Manager
13400 South Mountain View Corridor
Riverton, Utah 84065
Contractor:
Project: Meridian Town Center – Offsite Improvements - Phase 3
Meridian, Idaho
Engineer’s Project No: _______
This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the following
specified parts thereof:
[Insert description of Work for Substantial Completion]
The Work to which this Certificate applies has been inspected by authorized representatives of Developer, Engineer,
Contractor, and Engineer, and that Work is hereby declared to be substantially complete in accordance with the
Contract Documents on
DATE OF SUBSTANTIAL COMPLETION
A tentative list of items to be completed or corrected is attached hereto. This list may not be all inclusive, and the
failure to include an item in it does not alter the responsibility of Contractor to complete all the Work in accordance
with the Contract Documents. The items in the tentative list must be completed or corrected by Contractor within
[twenty (20)] days of the above date of Substantial Completion.
From the date of Substantial Completion the responsibilities between Developer and Contractor for security,
operation, safety, maintenance, utilities, insurance, and warranties and guarantees will be as follows:
RESPONSIBILITIES
Developer:
Contractor:
The following documents are attached to and made a part of this Certificate:
Application for Payment Meridian Town Center
Page 44 of 114 Offsite Improvements
[For items to be attached, see definition of Substantial Completion as supplemented and other
specifically noted conditions precedent to achieving Substantial Completion as required by
Contract Documents.]
Executed by Engineer on ______________________, ________
NV5
By: ________________________________________
(Authorized Signature)
Contractor accepts this Certificate of Substantial Completion on _____________, _______
[Contractor], [Contractor Entity Type]
By: ________________________________________
(Authorized Signature)
Developer accepts this Certificate of Substantial Completion on _____________, _______
Meridian CenterCal, L.L.C., a Delaware limited liability company
By: __________________________________________
(Authorized Signature)
Certificate of Final Completion Meridian Town Center
Page 45 of 114 Offsite Improvements
CERTIFICATE OF FINAL COMPLETION
Developer: Meridian CenterCal, L.L.C.
Attn: Lance Blackwood, Project Manager
13400 South Mountain View Corridor
Riverton, Utah 84065
Project: Meridian Town Center – Offsite Improvements - Phase 3
Work : _______________________________
The above Work of the Project to which this Certificate applies has been inspected by authorized representatives of
Developer, Engineer, Contractor, Agencies and Engineer, and that Work of the Project is hereby declared to be final
and complete in accordance with the Contract Documents. The Contractor’s three (3) year Correction Period will
commence as of the date below.
DATE OF FINAL COMPLETION:
ACCEPTANCE BY:
Developer: MERIDIAN CENTERCAL, L.L.C., a Delaware limited liability company
By: Date:
Contractor: [Contractor], [Contractor Entity Type]
By: Date:
Engineer: NV5
By: Date:
Contractor’s Project Certification Meridian Town Center
Page 47 of 114 Offsite Improvements
CONTRACTOR’S PROJECT CERTIFICATION
STATE OF IDAHO )
) ss
COUNTY OF ADA )
_________________________________________________, being duly sworn according to law, deposes and says
that he is the
(Title or Office)
of (“Contractor”),
of that certain Construction Agreement dated [_________________] between Contractor and Meridian CenterCal,
L.L.C., a Delaware limited liability company (“Developer”) for construction of the Meridian Town Center – Offsite
Improvements - Phase 3 project (the “Project”), and that s/he is authorized to and does make this certificate on
behalf of Contractor.
Affiant further states that Contractor has paid in full for all labor, materials, equipment, services and other matters
provided or furnished on or for the Project.
Affiant further states that Contractor has paid in full for all subcontractors or suppliers who provided labor, materials,
equipment, services or other matters provided or furnished on or for the Project.
Contractor agrees to indemnify, defend and save Developer harmless -from all liabilities, claims or lawsuits arising
from or related to any labor, materials, equipment, services and other matters provided or furnished on or for the
Project.
DATED this __________________________ day of __________________, ______
_______________________________
Officer’s Signature
_______________________________
(Officer’s Name) (Title)
STATE OF IDAHO )
) ss
COUNTY OF _________ )
SUBSCRIBED AND SWORN to before me this _____ day of ____________, 20___.
Notary Public
My Commission expires
General Conditions Meridian Town Center
Page 49 of 114 Offsite Improvements
GENERAL CONDITIONS
General Conditions Meridian Town Center
Page 50 of 114 Offsite Improvements - Phase 3
GENERAL CONDITIONS
ARTICLE 1. DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
Wherever used in the Contract Documents and printed with initial capital letters or all capital letters, the
terms listed below will have the meanings indicated which are applicable to both the singular and plural
thereof.
(1) ACHD – Ada County Highway District, a body politic and corporate of the State of Idaho.
(2) Addenda – Written or graphic instruments issued prior to the opening of Bids which clarify, correct,
or change the Bidding Requirements or the Contract Documents.
(3) Agreement – The written Construction Agreement between Developer and Contractor for the Project.
(4) Agency – Idaho Transportation Department (ITD)
(5) Application for Payment – The form acceptable to Engineer which is to be used by Contractor during
the course of the Work in requesting progress or final payments and which is to be accompanied by
any supporting documentation as required by the Contract Documents.
(6) Asbestos – Any material that contains more than one percent asbestos and is friable or is releasing
asbestos fibers into the air above certain action levels established by the United States Occupational
Safety and Health Administration.
(7) Bid – The offer or proposal of a bidder submitted on the prescribed form setting forth the prices for
the Work to be performed.
(8) Bidding Documents – The Bidding Requirements and the proposed Contract Documents (including all
Addenda issued prior to receipt of Bids).
(9) Bidding Requirements – The requirements set forth in the Invitation for Bids, Instructions to Bidders
and Bid Form.
(10) Bonds – Performance and payment bonds and other instruments of security as may be required under
the Bidding Documents or Contract Documents.
(11) Change Order – A document recommended by Developer Representative and Engineer, which is
signed by Contractor and Developer, to authorize an addition, deletion, or revision in the Work or an
adjustment in the Contract Price or the Contract Dates, issued on or after the Effective Date of the
Agreement.
(12) Claim – A demand or assertion by Developer or Contractor seeking an adjustment of Contract Price or
Contract Dates, or both, or other relief with respect to the terms of the Contract. A demand for money
or services by a third party is not a Claim.
(13) Contract – The entire and integrated written agreement between Developer and Contractor
concerning the Work. The Contract supersedes prior negotiations, representations, or agreements,
whether written or oral.
(14) Contract Dates – As identified in Section 4.02 of the Agreement.
(15) Contract Documents – The Contract Documents establish the rights and obligations of the parties and
include the Agreement, Addenda that pertain to the Contract Documents, Contractor’s Bid (including
documentation accompanying the Bid and any post Bid documentation submitted prior to the Notice
of Award), the Notice to Proceed, the Bonds, these General Conditions, the Supplementary Conditions,
the Special Provisions, the Specifications and the Drawings as the same are more specifically identified
in the Agreement, together with all Written Amendments, Change Orders, and Engineer’s written
interpretations and clarifications issued on or after the Effective Date of the Agreement. Approved
Shop Drawings and the reports and drawings of subsurface and physical conditions are not Contract
Documents. Only printed or hard copies of the items listed in herein are Contract Documents. Files in
electronic media of text, data, graphics, and the like that may be furnished by Developer to Contractor
are not Contract Documents.
General Conditions Meridian Town Center
Page 51 of 114 Offsite Improvements - Phase 3
(16) Contract Price – The moneys payable by Developer to Contractor for completion of the Work in
accordance with the Contract Documents as stated in the Agreement (subject to the provisions of
Section 11.03 in the case of Unit Price Work).
(17) Contractor – The entity with whom Developer has entered into the Agreement.
(18) Correction Period - See Section 13.07 for definition.
(19) Cost of the Work – See Section 11.01 for definition.
(20) Drawings – That part of the Contract Documents prepared or approved by Engineer which graphically
shows the scope, extent, and character of the Work to be performed by Contractor. Shop Drawings
and other Contractor submittals are not Drawings as so defined.
(21) Effective Date of the Agreement – The date indicated in the Agreement on which it becomes effective,
but if no such date is indicated, it means the date on which the Agreement is signed and delivered by
the last of the two parties to sign and deliver.
(22) Engineer – The individual(s) or entity(ies) named as such in the Agreement.
(23) Engineer’s Consultant – An individual or entity having a contract with Engineer to furnish services as
Engineer’s independent professional associate or consultant with respect to the Project and who is
identified as such in the Special Provisions.
(24) Field Order – A written order issued by Engineer which requires minor changes in the Work but which
does not involve a change in the Contract Price or the Contract Dates.
(25) Force Majeure – See Section 12.03(B) for definition.
(26) General Conditions – These General Conditions, as the supplemented and amended by the
Supplementary Conditions and Special Provisions.
(27) General Requirements – Sections of Division 1 of the Specifications. The General Requirements pertain
to all sections of the Specifications.
(28) Hazardous Environmental Condition – The presence at the Site of Asbestos, PCBs, Petroleum,
Hazardous Waste, or Radioactive Material in such quantities or circumstances that may present a
substantial danger to persons or property exposed thereto in connection with the Work.
(29) Hazardous Waste – The term Hazardous Waste will have the meaning provided in Section 1004 of the
Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time.
(30) ITD – Idaho Transportation Department, an executive department of the State of Idaho.
(31) Laws and Regulations; Laws or Regulations – Any and all applicable laws, rules, regulations,
ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts
having jurisdiction.
(32) Liens – Charges, security interests, or encumbrances upon Project funds, real property, or personal
property.
(33) Notice of Award – The written notice by Developer to the apparent successful bidder stating that upon
timely compliance by the apparent successful bidder with the conditions precedent listed therein,
Developer will sign and deliver the Agreement.
(34) Notice to Proceed – A written notice given by Developer to Contractor fixing the date on which
Contractor will start to perform the Work under the Contract Documents.
(35) Developer – The individual, entity, public body, or authority with whom Contractor has entered into
the Agreement and for whom the Work is to be performed.
(36) Engineer – The individual(s) or entity(ies) named as such in the Agreement..
(37) Partial Utilization – Use by Developer of a substantially complete part of the Work for the purpose for
which it is intended (or a related purpose) prior to Substantial Completion of the Work.
(38) PCBs – Polychlorinated biphenyls.
(39) Petroleum – Petroleum, including crude oil or any fraction thereof which is liquid at standard
conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch
General Conditions Meridian Town Center
Page 52 of 114 Offsite Improvements - Phase 3
absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with
other non-Hazardous Waste and crude oils.
(40) Project – The total construction of which the Work to be performed under the Contract Documents
may be the whole, or a part as may be indicated elsewhere in the Contract Documents.
(41) Radioactive Material – Source, special nuclear, or byproduct materials as defined by the Atomic Energy
Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.
(42) Samples – Physical examples of materials, equipment, or workmanship that are representative of
some portion of the Work and which establish the standards by which such portions of the Work will
be judged.
(43) Shop Drawings – All drawings, diagrams, illustrations, schedules, and other data or information which
are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate
some portion of the Work.
(44) Site – Lands or areas indicated in the Contract Documents as being upon which the Work is to be
performed, including rights-of-way and easements for access thereto, and such other lands furnished
by Developer which are designed for the use of Contractor.
(45) Special Provisions – The Special Provisions that amends or supplements the other Contract
Documents.
(46) Specifications – That part of the Contract Documents consisting of written technical descriptions of
materials, equipment, systems, standards, and workmanship as applied to the Work and certain
administrative details applicable thereto.
(47) Subcontractor – An individual or entity having a direct contract with Contractor or with any other
Subcontractor for the performance of a part of the Work at the Site.
(48) Substantial Completion – The time at which the Work (or a specified part thereof) has progressed to
the point where, in the opinion of Engineer, the Work is sufficiently complete, in accordance with the
Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes
for which it is intended. The Work (or a specified portion thereof) will not be considered to be
substantially complete until construction traffic control has been removed and the Work (or the
specified portion thereof) can be safely used by the public for its intended purpose, despite the fact
that some item or items remain uncompleted. The terms “substantially complete” and “substantially
completed” as applied to all or part of the Work refer to Substantial Completion thereof.
(49) Supplementary Conditions – That part of the Contract Documents which amends and/or supplements
the other Contract Documents.
(50) Supplier – A manufacturer, fabricator, supplier, distributor, material man, or vendor having a direct
contract with Contractor or with a Subcontractor to furnish materials or equipment to be incorporated
in the Work by Contractor or any Subcontractor.
(51) Underground Facilities – All underground pipelines, conduits, ducts, cables, wires, manholes, vaults,
tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities,
including those that convey electricity, gases, steam, liquid petroleum products, telephone or other
communications, cable television, water, wastewater, storm water, other liquids or chemicals, or
traffic or other control systems.
(52) Unit Price Work – Work to be paid for on the basis of unit prices.
(53) Work – The entire construction or the various separately identifiable parts thereof required to be
provided under the Contract Documents. Work includes and is the result of performing or providing
all labor, services, and documentation necessary to produce such construction, and furnishing,
installing and incorporating all materials and equipment into such construction, all as required by, or
reasonably inferable from, the Contract Documents.
(54) Work Change Directive – A written statement to Contractor issued on or after the Effective Date of
the Agreement and signed by Developer upon recommendation of Engineer ordering an addition,
deletion, or revision in the Work, or responding to different or unforeseen subsurface or physical
General Conditions Meridian Town Center
Page 53 of 114 Offsite Improvements - Phase 3
conditions under which the Work is to be performed or to emergencies. A Work Change Directive will
not change the Contract Price or the Contract Dates but is evidence that the parties expect that the
change ordered or documented by a Work Change Directive will be incorporated in a subsequent ly
issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price
or Contract Dates.
(55) Written Amendment – A written statement modifying the Contract Documents, signed by Developer
and Contractor (upon recommendation of Engineer) on or after the Effective Date of the Agreement
and normally dealing with the non-engineering or non-technical rather than strictly construction-
related aspects of the Contract Documents.
1.02 Terminology
(A) Intent of Certain Terms or Adjectives
Whenever in the Contract Documents the terms “as allowed”, “as approved”, or terms of like effect
or import are used, or the adjectives “reasonable,” “suitable”, “acceptable”, “proper”, “satisfactory”,
or adjectives of like effect or import are used to describe an action or determination of Engineer as to
the Work, it is intended that such action or determination will be solely to evaluate, in general, the
completed Work for compliance with the requirements of and information in the Contract Documents
and conformance with the design concept of the completed Project as a functioning whole as shown
or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The
use of any such term or adjective will not be effective to assign to Engineer any duty or authority to
supervise or direct the performance of the Work or any duty or authority to undertake responsibility
contrary to the provisions of Section 9.10 or any other provision of the Contract Documents. The terms
“will”, “must” and “will” have the same meaning, which is that the matter is mandatory.
(B) Day.
The word “day” will constitute a calendar day of 24 hours measured from midnight to the next
midnight.
(C) Defective
The word “defective”, when modifying the word “Work” refers to Work that is unsatisfactory, faulty,
or deficient in that it does not conform to the Contract Documents or does not meet the requirements
of any inspection, reference standard, test or approval referred to in the Contract Documents, or has
been damaged prior to the recommendation for final payment by Engineer (unless responsibility for
the protection thereof has been assumed by Developer at Substantial Completion in accordance with
Section 14.04 and Section 14.05).
(D) Furnish, Install, Perform, Provide
(1) The word “furnish”, when used in connection with services, materials, or equipment, will mean to
supply and deliver said services, materials, or equipment to the Site (or some other specified location)
ready for use or installation and in usable or operable condition.
(2) The word “install”, when used in connection with services, materials, or equipment, will mean to put
into use or place in final position said services, materials, or equipment complete and ready for
intended use.
(3) The words “perform” or “provide”, when used in connection with services, materials, or equipment,
will mean to furnish and install said services, materials, or equipment complete and ready for intended
use.
(4) When “furnish”, “install”, “perform”, or “provide”, is not used in connection with services, materials,
or equipment in a context clearly requiring an obligation of Contractor, “provide” is implied.
(E) Unless stated otherwise in the Contract Documents, words or phrases which have a well-known technical
or construction industry or trade meaning are used in the Contract Documents in accordance with such
recognized meaning.
General Conditions Meridian Town Center
Page 54 of 114 Offsite Improvements - Phase 3
ARTICLE 2. PRELIMINARY MATTERS
2.01 Delivery of Bonds
When Contractor delivers the executed Agreements to Developer, Contractor will also deliver to
Developer such Bonds as Contractor may be required to furnish.
2.02 Copies of Documents
Developer will furnish to Contractor up to ten copies of the Contract Documents. Additional copies will
be furnished upon request at the cost of reproduction.
2.03 Commencement of Contract Dates; Notice to Proceed
A Notice to Proceed may be given at any time within 30 days after the Effective Date of the Agreement.
In no event will Notice to Proceed be given later than the thirtieth day after the Effective Date of the
Agreement, whichever is earlier, unless such Notice to Proceed is accepted by Contractor.
2.04 Starting the Work
Contractor will start to perform the Work on the date identified in the Notice to Proceed. No Work will
be done at the Site prior to the date identified in the Notice to Proceed.
2.05 Before Starting Construction
(A) Contractor’s Review of Contract Documents: Before undertaking each part of the Work, Contractor will
carefully study and compare the Contract Documents and check and verify pertinent figures therein and
all applicable field measurements. Contractor will promptly report in writing to Engineer any conflict,
error, ambiguity, or discrepancy which Contractor may discover and will obtain a written interpretation
or clarification (issued by Engineer) before proceeding with any Work affected thereby; however,
Contractor will not be liable to Developer, Engineer for failure to report any conflict, error, ambiguity, or
discrepancy in the Contract Documents unless Contractor knew or reasonably should have known thereof.
(B) Preliminary Schedules: Within ten days after the Effective Date of the Agreement (unless otherwise
specified in the General Requirements), Contractor will submit to Engineer for its timely review:
(1) a preliminary progress schedule indicating the times (number of days or dates) for starting and
completing the various stages of the Work, including any Contract Dates. The preliminary progress
schedule (and any updates thereto) must be consistent with the construction schedule that Contractor
provided to Developer in Contractor’s Bid;
(2) a preliminary schedule of Shop Drawing and Sample submittals which will list each required submittal
and the times for submitting, reviewing, and processing such submittal; and
(3) a preliminary schedule of values for all of the Work which includes quantities and prices of items which
when added together equal the Contract Price and subdivides the Work into component parts in
sufficient detail to serve as the basis for progress payments during performance of the Work. Such
prices will include an appropriate amount of overhead and profit applicable to each item of Work. The
preliminary schedule of values must be consistent with the bid schedule that Contractor provided to
Developer in Contractor’s Bid.
(C) Evidence of Insurance – Before any work at the Site is started, Contractor and Developer will each deliver
to the other, with copies to each additional insured identified in the Supplementary Conditions or Special
Provisions, certificates of insurance (and other evidence of insurance which either of them or any
additional insured may reasonably request) which Contractor and Developer respectively are required to
purchase and maintain in accordance with Article 5.
2.06 Preconstruction Conference
Before any Work at the Site is started, a conference attended by Contractor, Engineer, ITD and others as
appropriate will be held to establish a working understanding among the parties as to the Work and to
discuss the schedules referred to in Section 2.05(B), procedures for handling Shop Drawings and other
submittals, processing Applications for Payment, and maintaining required records.
2.07 Initial Acceptance of Schedules
General Conditions Meridian Town Center
Page 55 of 114 Offsite Improvements - Phase 3
Unless otherwise provided in the Contract Documents, at least ten days before submission of the first
Application for Payment a conference attended by Contractor, Engineer, and others as appropriate will
be held to review for acceptability to Engineer as provided below the schedules submitted in accordance
with Section 2.05.(B). Contractor will have an additional ten days to make corrections and resubmit the
schedules. No progress payment will be made to Contractor until acceptable schedules are submitted to
Engineer.
(1) The progress schedule will be acceptable to Engineer if it provides an orderly progression of the
Work to completion within the Contract Dates, and is consistent with the construction schedule
submitted by Contractor to Developer in Contractor’s Bid (unless otherwise approved by
Engineer). Such acceptance will not impose on Engineer responsibility for the progress schedule,
for sequencing, scheduling, or progress of the Work nor interfere with or relieve Contractor from
Contractor’s full responsibility therefore.
(2) Contractor’s schedule of Shop Drawing and Sample submittals will be acceptable to Engineer if it
provides a workable arrangement for reviewing and processing the required submittals.
(3) Contractor’s schedule of values will be acceptable to Engineer as to form and substance if it
provides a reasonable allocation of the Contract Price to component parts of the Work, and is
consistent with the bid schedule provided by Contractor to Developer in Contractor’s Bid.
ARTICLE 3. CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE
3.01 Intent
(A) The Contract Documents are complementary; what is called for by one is as binding as if called for by all.
(B) It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to
be constructed in accordance with the Contract Documents. Any labor, documentation, services,
materials, or equipment that may reasonably be inferred from the Contract Documents or from prevailing
custom or trade usage as being required to produce the intended result will be provided whether or not
specifically called for or show, at no additional cost to Developer.
(C) Clarifications and interpretations of the Contract Documents will be issued by Engineer (in coordination
with Engineer) as provided in Article 9.
3.02 Reference Standards
(A) Standards, Specifications, Codes, Laws, and Regulations
(1) Reference to standards, specifications, manuals, or codes of any technical society, organization, or
associates, or to Laws or Regulations, whether such reference be specific or by implication, will mean
the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of
Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise
specifically stated in the Contract Documents.
(2) No provision of any such standard, specification, manual or code, or any instruction of a Supplier will
be effective to change the duties or responsibilities of Developer, Engineer or Contractor, or any of
their subcontractors consultants, agents, or employees from those set forth in the Contract
Documents, nor will any such provision or instruction be effective to assign to Developer, Engineer, or
any of their’ s consultants, agents, or employees any duty or authority to supervise or direct the
performance of the Work or any duty or authority to undertake responsibility inconsistent with the
provisions of the Contract Documents.
3.03 Reporting and Resolving Discrepancies
(A) Reporting Discrepancies
If, during the performance of the Work, Contractor discovers any conflict, error, ambiguity, or
discrepancy within the Contract Documents or between the Contract Documents and any provision of
any Law or Regulation applicable to the performance of the Work or if any standard, specification,
manual or code, or of any instruction of any Supplier, Contractor will report it to Engineer in writing
General Conditions Meridian Town Center
Page 56 of 114 Offsite Improvements - Phase 3
at once. Contractor will not proceed with the Work affected thereby (except in an emergency as
required by Section 6.16(A)) until an amendment or supplement to the Contract Documents has been
issued by one of the methods indicated in Section 3.04; provided, however, that Contractor will not
be liable to Developer, Engineer for failure to report any such conflict, error, ambiguity, or discrepancy
unless Contractor knew or reasonably should have known thereof.
(B) Resolving Discrepancies
Except as may be otherwise specifically stated in the Contract Documents, the provisions of the
Contract Documents will take precedence in resolving any conflict, error, ambiguity, or discrepancy
between the provisions of the Contract Documents and:
a) the provisions of any standard, specification, manual, code, or instruction (whether or not
specifically incorporated by reference in the Contract Documents); or
b) the provisions of any Laws or Regulations applicable to the performance of the Work (unless such
an interpretation of the provisions of the Contract Documents would result in violation of such
Law or Regulation).
3.04 Amending and Supplementing Contract Documents
(A) The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work
or to modify the terms and conditions thereof in one or more of the following ways: (i) a Written
Amendment; (ii) a Change Order; or (iii) a Work Change Directive.
(B) The requirements of the Contract Documents may be supplemented, and minor variations and deviations
in the Work may be authorized, by one or more of the following ways: (i) a Field Order; (ii) Engineer’s
approval of a Shop Drawing or Sample; or (iii) Engineer’s written interpretation or clarification.
3.05 Reuse of Documents
Contractor and any Subcontractor or Supplier or other individual or entity performing or furnishing any
of the Work under direct or indirect contract with Developer: (i) will not have or acquire any title to or
ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof)
prepared by or bearing the seal of Engineer or Engineer’s Consultant, including electronic media editions;
and (ii) will not reuse any of such Drawings, Specifications, other documents, or copies on extensions of
the Project or any other project without written consent of Developer, Engineer and specific written
verification or adaptation by Engineer. This prohibition will survive final payment, completion, and
acceptance of the Work, or termination or completion of the Contract. Nothing herein will preclude
Contractor from retaining copies of the Contract Documents for record purposes.
ARTICLE 4. AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE POINTS
4.01 Availability of Lands
(A) Contractor acknowledges that the Site is the public right-of-way governed by ITD, and Contractor will
become aware of the general and special restrictions related thereto, including those set forth in the
Construction Documents. Contractor will be responsible for the location of Contractor’s staging and other
activities (including, construction parking, setup, layout, storage and preparation).
(B) Upon reasonable written request, Developer will furnish Contractor with a current statement of record
legal title and legal description of the lands upon which the Work is to be performed (other than any
public rights-of-way) and Developer’s interest therein (if any) as necessary for giving notice of or filing a
mechanic’s or construction lien against such lands in accordance with applicable Laws and Regulations.
(C) Contractor will provide for all additional lands and access thereto that may be required for temporary
construction facilities or storage of materials and equipment.
4.02 Subsurface and Physical Conditions
(A) Reports and Drawings: Section 2 of the Supplementary Conditions identify:
General Conditions Meridian Town Center
Page 57 of 114 Offsite Improvements - Phase 3
(1) those reports of explorations and tests of subsurface conditions at or contiguous to the Site that were
used in preparing the Contract Documents; and
(2) those drawings of physical conditions in or relating to existing surface or subsurface structures at or
contiguous to the Site (except Underground Facilities) that were used in preparing the Contract
Documents.
(B) Use by Contractor of Technical Data Authorized: Contractor may use the “technical data” contained in
such reports and drawings for general information about the Site, but such reports and drawings are not
Contract Documents. Contractor may not rely upon or make any Claim against Developer, Engineer, or
any of their Consultants with respect to:
(1) the completeness of such reports or drawings for Contractor’s purposes, including, but not limited to,
any aspects of the means, methods, techniques, sequences, and procedures of construction to be
employed by Contractor, and safety precautions and programs incident thereto; or
(2) other data, interpretations, opinions, and information contained in such reports or shown or indicated
in such drawings; or
(3) any Contractor interpretation of or conclusion drawn from any “technical data” or any such other
data, interpretations, opinions, or information.
4.03 Differing Subsurface or Physical Conditions
(A) Notice: If Contractor believes that any subsurface or physical condition at Site that is uncovered or
revealed:
(1) is of such a nature as to establish that any “technical data” identified in Section 4.02 is materially
inaccurate;
(2) is of such a nature as to require a change in the Contract Documents;
(3) differs materially from that shown or indicated in the Contract Documents; and
(4) is of an unusual nature, and differs materially from conditions ordinarily encountered and generally
recognized as inherent in work of the character provided for in the Contract Documents;
then Contractor will, promptly after becoming aware thereof and before further disturbing the
subsurface or physical conditions or performing any Work in connection therewith (except in an
emergency as required by Section 6.16(A)), notify Developer, Developer’ Representative and Engineer
in writing about such condition. Contractor will not further disturb such condition or perform any
Work in connection therewith (except as aforesaid) until receipt of written order to do so.
(B) Review: After receipt of written notice as required by Section 4.03(A), Engineer will promptly review the
pertinent condition, determine the necessity of Developer’s obtaining additional exploration or tests with
respect thereto, and advise Developer in writing (with a copy to Contractor) of their findings and
conclusions.
(C) Possible Price and Contract Dates Adjustments
(1) The Contract Price or the Contract Dates (subject to the terms and limitations of Section 12.03), or
both, will be equitably adjusted to the extent that the existence of such differing subsurface or physical
condition causes an increase or decrease in Contractor’s cost of, or time required for, performance of
the Work; subject, however, to the following:
a) Such condition must meet the categories described in Section 4.03(A); and
b) With respect to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be
subject to the provisions of Sections 9.08 and 11.03;
(2) Contractor will not be entitled to any adjustment in the Contract Price or Contract Dates if:
a) Contractor knew of the existence of such conditions at the time Contractor made a final
commitment to Developer in respect of Contract Price and Contract Dates by the submission of a
Bid or becoming bound under a negotiated contract; or
General Conditions Meridian Town Center
Page 58 of 114 Offsite Improvements - Phase 3
b) The existence of such condition could reasonably have been discovered or revealed as a result of
any examination, investigation, exploration, test, or study of the Site and contiguous areas
required by the Bidding Requirements or Contract Documents to be conducted by or for
Contractor prior to Contractor’s making such final commitment; or
c) Contractor failed to give the written notice within the time and as required by Section 4.03(A).
(3) If Developer and Contractor are unable to agree on entitlement to or on the amount or extent, if any,
of any adjustment in the Contract Price or Contract Dates, or both, a Claim may be made therefore as
provided in Section 10.05. However, Developer, Engineer, and their Consultants will not be liable to
Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges
of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute
resolution costs) sustained by Contractor on or in connection with any other project or anticipated
project.
4.04 Underground Facilities
(A) Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect
to existing Underground Facilities at or contiguous to the Site is based on information and data furnished
to Developer, Engineer by the owners of such Underground Facilities, or by others. Unless it is otherwise
expressly provided in the Special Provisions:
(1) Developer, Engineer will not be responsible for the accuracy or completeness of any such information
or data; and
(2) the cost of all of the following will be included in the Contract Price, and Contractor will have full
responsibility for:
a) reviewing and checking all such information and data,
b) locating all Underground Facilities shown or indicated in the Contract Documents,
c) coordination of the Work with the owners of such Underground Facilities, including Developer,
during construction, and
d) the safety and protection of all such Underground Facilities and repairing any damage thereto
resulting from the Work.
(B) Not Shown or Indicated:
(1) If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown
or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents,
Contractor will, promptly after becoming aware thereof and before further disturbing conditions
affected thereby or performing any Work in connection therewith (except in an emergency as required
by Section 6.16(A)), identify the owner of such Underground Facility and give written notice to that
owner and to Developer, Engineer. Construction Manager and Engineer will promptly review the
Underground Facility and determine the extent, if any, to which a change is required in the Contract
Documents to reflect and document the consequences of the existence or location of the
Underground Facility. During such time, Contractor will be responsible for the safety and protection
of such Underground Facility.
(2) If Construction Manager and Engineer conclude that a change in the Contract Documents is required,
a Work Change Directive or a Change Order will be issued to reflect and document such consequences.
An equitable adjustment will be made in the Contract Price or Contract Dates (subject to the terms
and limitations of Section 12.03), or both, to the extent that they are attributable to the existence or
location of any Underground Facility that was not shown or indicated or not shown or indicated with
reasonable accuracy in the Contract Documents and that Contractor did not know of and could not
reasonably have been expected to be aware of or to have anticipated. If Developer and Contractor are
unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment in
Contractor Price or Contract Dates, Developer or Contractor may make a Claim therefore as provided
in Section 10.05.
General Conditions Meridian Town Center
Page 59 of 114 Offsite Improvements - Phase 3
4.05 Reference Points
Developer will provide engineering surveys to establish reference points for construction which, in
Engineer’s judgment, are necessary to enable Contractor to proceed with the Work. Contractor will be
responsible for laying out the Work, will protect and preserve the established reference points and
property monuments, and will make no changes or relocations without the prior written approval of
Developer. Contractor will report to Engineer whenever any reference point or property monument is
lost or destroyed or requires relocation because of necessary changes in grades or locations, and will be
responsible for the accurate replacement or relocation of such reference points or property monuments
by professionally qualified personnel.
4.06 Hazardous Environmental Condition at Site
(A) Reports and Drawings: Reference is made to Section 2 of the Supplementary Conditions for the
identification of those reports and drawings relating to a Hazardous Environmental Condition identified
at the Site, if any, that have been used in the preparation of the Contract Documents.
(B) Use by Contractor of Technical Data Authorized: Contractor may use the “technical data” contained in
such reports and drawings, but such reports and drawings are not Contract Documents. Contractor may
not rely upon or make any Claim against Developer, Engineer or any of their Consultants with respect to:
(1) the completeness of such reports and drawings for Contractor’s purposes, including, but not limited
to, any aspects of the means, methods, techniques, sequences and procedures of construction to be
employed by Contractor and safety precautions and programs incident thereto; or
(2) other data, interpretations, opinions and information contained in such reports or shown or indicated
in such drawings; or
(3) any Contractor interpretation of or conclusions drawn from any “technical data” or any such other
data, interpretations, opinions or information.
(C) Contractor will not be responsible for any Hazardous Environmental Condition uncovered or revealed at
the Site which was not shown or indicated in Drawings or Specifications or identified in the Contract
Documents to be within the scope of the Work. Contractor will be responsible for a Hazardous
Environmental Condition created with any materials brought to the Site by Contractor, Subcontractors,
Suppliers, or anyone else for whom Contractor is responsible.
(D) If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for whom
Contractor is responsible creates a Hazardous Environmental Condition, Contractor will immediately: (i)
secure or otherwise isolate such condition; (ii) stop all Work in connection with such condition and in any
area affected thereby (except in an emergency as required by Section 6.16); and (iii) notify Developer,
Engineer (and promptly thereafter confirm such notice in writing). Developer will promptly consult with
Engineer concerning the necessity for Developer to retain a qualified expert to evaluate such condition or
take corrective action, if any.
(E) Contractor will not be required to resume Work in connection with such condition or in any affected area
until after Developer has obtained any required permits related thereto and delivered to Contractor
written notice: (i) specifying that such condition and any affected area is or has been rendered safe for
the resumption of Work; or (ii) specifying any special conditions under which such Work may be resumed
safely. If Developer and Contractor cannot agree as to entitlement to or on the amount or extent, if any,
of any adjustment in Contract Price or Contract Dates, or both, as a result of such Work stoppage or such
special conditions under which Work is agreed to be resumed by Contractor, either party may make a
Claim therefore as provided in Section 10.05.
(F) If after receipt of such written notice Contractor does not agree to resume such Work based on a
reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then
Developer may order the portion of the Work that is in the area affected by such condition to be deleted
from the Work. If Developer and Contractor cannot agree as to entitlement to or on the amount or extent,
if any, of an adjustment in Contract Price or Contract Dates (subject to the terms and limitations of Section
12.03) as a result of deleting such portion of the Work, then either party may make a Claim therefore as
General Conditions Meridian Town Center
Page 60 of 114 Offsite Improvements - Phase 3
provided in Section 10.05. Developer may have such deleted portion of the Work performed by
Developer’s own forces or others in accordance with Article 7.
(G) To the fullest extent permitted by Laws and Regulations, Developer will indemnify and hold harmless
Contractor, Subcontractors, Engineer, Engineer’s Consultants and the officers, directors, partners,
employees, agents, other consultants, and subcontractors of each and any of them from and against all
claims, costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs)
arising out of or relating to a Hazardous Environmental Condition provided that such Hazardous
Environmental Condition (i) was not shown or indicated in the Drawings or Specifications or identified in
the Contract Documents to be included within the scope of the Work; and (ii) was not created by
Contractor, Engineer, Engineer’s Consultants, or by anyone for whom any of the foregoing is responsible.
Nothing in this Section 4.06(E) will obligate Developer to indemnify any individual or entity from and
against the consequences of that individual’s or entity’s own negligence, and the negligence of any for
who they may be responsible.
(H) To the fullest extent permitted by Laws and Regulations, Contractor will indemnify and hold harmless
Developer, ITD, Engineer, Engineer’s Consultants, and the officers, directors, partners, employees, agents,
and other consultants, and subcontractors of each and any of them from and against all claims, costs,
losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys,
and other professionals and all court or arbitration or other dispute resolution costs) arising out of or
relating to a Hazardous Environmental Condition created by Contractor or by anyone for whom
Contractor is responsible. Nothing in this Section 4.06(F) will obligate Contractor to indemnify any
individual or entity from and against the consequences of that individual’s or entity’s own negligence, and
the negligence of any for who they may be responsible.
(I) The provisions of Sections 4.02, 4.03 and 4.04 are not intended to apply to a Hazardous Environmental
Condition uncovered or revealed at the site.
ARTICLE 5. BONDS AND INSURANCE
5.01 Performance, Payment, and Other Bonds
(A) Contractor will furnish performance and payment Bonds, each in an amount at least equal to the Contract
Price as security for the faithful performance and payment of all Contractor’s obligations under the
Contract Documents. These Bonds will remain in effect at least until one year after the date when final
payment becomes due, except as provided otherwise by Laws or Regulations or by the Contract
Documents. Contractor will also furnish such other Bonds as are required by the Contract Documents.
(B) All bonds will be in the form prescribed by the Contract Documents except as provided otherwise by Laws
or Regulations, and will be executed by such sureties as are named in the current list of “Companies
Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring
Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond
Branch, U.S. Department of the Treasury. All Bonds signed by an agent must be accompanied by a certified
copy of such agent’s authority to act.
(C) If the surety on any Bond furnished by Contractor is declared bankrupt or becomes insolvent or its right
to do business is terminated in any state where any part of the Project is located or it ceases to meet the
requirements of Section 5.01(B), Contractor will within 20 days thereafter substitute another Bond and
surety, both of which will comply with the requirements of Sections 5.01(B) and 5.02.
5.02 Licensed Sureties and Insurers
(A) All Bonds and insurance required by the Contract Documents to be purchased and maintained by
Developer or Contractor will be obtained from surety or insurance companies that are duly licensed or
authorized in the jurisdiction in which the Project is located to issue Bonds or insurance policies for the
limits and coverage’s so required. Such surety and insurance companies will also meet such additional
requirements and qualifications as may be provided in the Supplementary Conditions.
General Conditions Meridian Town Center
Page 61 of 114 Offsite Improvements - Phase 3
5.03 Certificates of Insurance
Contractor will deliver to Developer, with copies to each additional insured identified in the
Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by
Developer or any other additional insured) which Contractor is required to purchase and maintain.
Developer will deliver to Contractor, with copies to each additional insured identified in the
Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by
Contractor or any other additional insured) which Developer is required to purchase and maintain.
5.04 Contractor’s Liability Insurance
(A) Contractor will purchase and maintain such liability and other insurance as is required by Section 11 of
the Supplementary Conditions and as is otherwise appropriate for the Work being performed and as will
provide protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents, whether it
is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly
employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be
liable:
(1) claims under workers’ compensation, disability benefits, and other similar employee benefit acts;
(2) claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s
employees;
(3) claims for damages because of bodily injury, sickness or disease, or death of any person other than
Contractor’s employees;
(4) claims for damages insured by reasonably available personal injury liability coverage which are
sustained: (i) by any person as a result of an offense directly or indirectly related to the employment
of such person by Contractor, or (ii) by any other person for any other reason;
(5) claims for damages, other than to the Work itself, because of injury to or destruction of tangible
property wherever located, including loss of use resulting therefrom; and
(6) claims for damages because of bodily injury or death of any person or property damage arising out of
the ownership, maintenance or use of any motor vehicle.
(B) The policies of insurance so required by this Section 5.04 to be purchased and maintained will:
(1) with respect to insurance required by Sections 5.04(A)(3) through 5.04(A)(6) inclusive, include as
additional insureds (subject to any customary exclusion in respect of professional liability) Developer,
ITD, Engineer, Engineer’s Consultants, and any other individuals or entities identified in the
Supplementary Conditions, all of whom will be listed as additional insureds, and include coverage for
the respective officers, directors, partners, employees, agents, and other consultants and
subcontractors of each and any of all such additional insureds, and the insurance afforded to these
additional insureds will provide primary coverage for all claims covered thereby;
(2) include at least the specific coverages and be written for not less than the limits of liability provided
in the Supplementary Conditions or required by Laws or Regulations, whichever is greater;
(3) include completed operations insurance;
(4) include contractual liability insurance covering Contractor’s indemnity obligations under
Sections 6.07, 6.11 and 6.20;
(5) contain a provision or endorsement that the coverage afforded will not be canceled, materially
changed or renewal refused until at least 30 days prior written notice has been given to Developer,
ITD and Contractor and to each other additional insured identified in the Supplementary Conditions
to whom a certificate of insurance has been issued (and the certificates of insurance furnished by
Contractor pursuant to Section 5.03 will so provide);
(6) remain in effect at least until final payment and at all times thereafter when Contractor may be
correcting, removing, or replacing defective Work in accordance with Section 13.07; and
General Conditions Meridian Town Center
Page 62 of 114 Offsite Improvements - Phase 3
(7) with respect to completed operations insurance, and any insurance coverage written on a claims-
made basis, remain in effect for at least three (3) years after final payment (and Contractor will furnish
Developer and each other additional insured identified in the Supplementary Conditions, to whom a
certificate of insurance has been issued, evidence satisfactory to Developer and any such additional
insured of continuation of such insurance at final payment and one year thereafter).
5.05 Developer’s Liability Insurance
In addition to the insurance required to be provided by Contractor under Section 5.04, Developer, at
Developer’s option, may purchase and maintain at Developer’s expense Developer’s own liability
insurance as will protect Developer against claims which may arise from operations under the Contract
Documents.
5.06 Property Insurance
(A) Unless otherwise provided in the Supplementary Conditions, Contractor will purchase and maintain
property insurance upon the Work at the Site in the amount of the full replacement cost thereof (subject
to such deductible amounts as may be provided in the Supplementary Conditions or required by Laws and
Regulations). This insurance will:
(1) include the interests of Developer, ITD, Contractor, Subcontractors, Engineer, Engineer’s Consultants,
and any other individuals or entities identified in the Supplementary Conditions, and the officers,
directors, partners, employees, agents, and other consultants and subcontractors of each and any of
them, each of whom is deemed to have an insurable interest and will be listed as an additional insured;
(2) be written on a Builder’s Risk “all-risk” or open peril or special causes of loss policy form that will at
least include insurance for physical loss or damage to the Work, temporary buildings, false work, and
materials and equipment in transit, and will insure against at least the following perils or causes of
loss: fire, lightning, extended coverage, theft, vandalism and malicious mischief, earthquake, collapse,
debris removal, demolition occasioned by enforcement of Laws and Regulations, water damage, and
such other perils or causes of loss as may be specifically required by the Supplementary Conditions;
(3) include expenses incurred in the repair or replacement of any insured property (including but not
limited to fees and charges of engineers and architects);
(4) cover materials and equipment stored at the Site or at another location that was agreed to in writing
by Developer prior to being incorporated in the Work, provided that such materials and equipment
have been included in an Application for Payment recommended by Engineer;
(5) allow for partial utilization of the Work by Developer;
(6) include testing and startup;
(7) be maintained in effect until final payment is made, unless otherwise agreed to in writing by
Developer, Contractor; and
(8) contain a provision or endorsement that the coverage afforded will not be canceled or materially
changed or renewal refused until at least 30 days prior written notice has been given to Developer
and Contractor and to each other additional insured to whom a certificate of insurance has been
issued and will contain waiver provisions in accordance with Section 5.07.
(B) Contractor will purchase and maintain such boiler and machinery insurance or additional property
insurance as may be required by the Supplementary Conditions or Laws and Regulations which will include
the interest of Developer, Contractor, Subcontractors, Engineer, Engineer’s Consultants, and any other
individuals or entities identified in the Supplementary Conditions, each of whom is deemed to have an
insurable interest and will be listed as an insured or additional insured.
(C) Developer will not be responsible for purchasing and maintaining any property insurance specified in this
Section 5.06 to protect the interests of Contractor, Subcontractors, or others in the Work. The risk of loss
within such identified deductible amount will be borne by Contractor, Subcontractors, or others suffering
any such loss, and if any of them wishes property insurance coverage within the limits of such amounts,
each may purchase and maintain it at the purchaser’s own expense.
General Conditions Meridian Town Center
Page 63 of 114 Offsite Improvements - Phase 3
5.07 Waiver of Rights
Developer and Contractor intend that all policies purchased in accordance with Section 5.06 will protect
Developer, Contractor, Subcontractors, Engineer, Engineer’s Consultants, and all other individuals or
entities identified in the Supplementary Conditions to be listed as insureds or additional insureds (and the
officers, directors, partners, employees, agents, and other consultants and subcontractors of each and
any of them) in such policies and will provide primary coverage for all losses and damages caused by the
perils or causes of loss covered thereby. All such policies will contain provisions to the effect that in the
event of payment of any loss or damage the insurers will have no rights of recovery against any of the
insureds or additional insureds thereunder. Developer and Contractor waive all rights against each other
and their respective officers, directors, partners, employees, agents, and other consultants and
subcontractors of each and any of them for all losses and damages caused by, arising out of or resulting
from any of the perils or caused of loss covered by such policies and any other property insurance
applicable to the Work; and, in additional, waive all such rights against Subcontractors, Engineer,
Engineer’s Consultants, and all other individuals or entities identified in the Supplementary Conditions to
be listed as insureds or additional insureds (and the officers, directors, partners, employees, agents, and
other consultants and subcontractors of each and any of them) under such policies for losses and damages
so caused. None of the above waivers will extend to the rights that any party making such waiver may
have to the proceeds of insurance held by Developer as trustee or otherwise payable under any policy so
issued.
5.08 Receipt and Application of Insurance Proceeds
(A) Any insured loss under the policies of insurance required by Section 5.06 will be adjusted with Contractor
and made payable to Contractor as fiduciary for the insureds, as their interest may appear, subject to the
requirements of Section 5.08(B). Contractor will deposit in a separate account any money so received and
will distribute it in accordance with such agreement as the parties in interest may reach. If no other special
agreement is reached, the damaged Work will be repaired or replaced, the moneys so received applied
on account thereof, and the Work and the cost thereof covered by an appropriate Change Order or
Written Amendment.
(B) Contractor as fiduciary will have power to adjust and settle any loss with the insurers unless one of the
parties in interest will object in writing within fifteen (15) days after the occurrence of loss to Contractor’s
exercise of this power. If such objection be made, Contractor as fiduciary will make settlement with the
insurers in accordance with such agreement as the parties in interest may reach. If no such agreement
among the parties in interest is reached, Contractor as fiduciary will adjust and settle the loss with the
insurers and, if required in writing by any party in interest, Contractor as fiduciary will give bond for the
proper performance of such duties.
5.09 Acceptance of Bonds and Insurance; Option to Replace
(A) If either Developer or Contractor has any objection to the coverage afforded by or other provisions of the
Bonds or insurance required to be purchased and maintained by the other party in accordance with Article
5 on the basis of non-conformance with the Contract Documents, the objecting party will so notify the
other party in writing within 10 days after receipt of the certificates (or other evidence requested)
required by Section 2.05(C). Developer and Contractor will each provide to the other such additional
information in respect of insurance provided as the other may reasonably request. If either party does
not purchase or maintain all of the Bonds and insurance required of such party by the Contract
Documents, such party will notify the other party in writing of such failure to purchase prior to the start
of the Work, or of such failure to maintain prior to any change in the required coverage. Without prejudice
to any other right or remedy, the other party may elect to obtain equivalent Bonds or insurance to protect
such other party’s interests at the expense of the party who was required to provide such coverage, and
a Change Order will be issued to adjust the Contract Price accordingly.
5.10 Partial Utilization, Acknowledgement of Property Insurer
(A) Contractor will coordinate any partial occupy or use a portion or portions of the Work prior to Substantial
Completion of all the Work (as provided in Section 14.05) with Contractor’s property insurance providers
General Conditions Meridian Town Center
Page 64 of 114 Offsite Improvements - Phase 3
so such providers have notice thereof and effected any changes in coverage necessitated thereby. The
insurers providing the property insurance will consent by endorsement on the policy or policies, but the
property insurance will not be canceled or permitted to lapse on account of any such partial use or
occupancy.
ARTICLE 6. CONTRACTOR’S RESPONSIBILITIES
6.01 Supervision and Superintendence
(A) Contractor will supervise, inspect, and direct the Work competently and efficiently, devoting such
attention thereto and applying such skills and expertise as may be necessary to perform the Work in
accordance with the Contract Documents. Contractor will be solely responsible for the means, methods,
techniques, sequences, and procedures of construction, but Contractor will not be responsible for the
negligence of Developer, Engineer in the design or specification of a specific means, method, technique,
sequence, or procedure of construction which is shown or indicated in and expressly required by the
Contract Documents. Contractor will be responsible to see that the completed Work complies accurately
with the Contract Documents.
(B) At all times during the progress of the Work, Contractor will assign a project executive and competent
resident project managers, superintendents and assistants thereto who will not be replaced without the
approval of Engineer, except under extraordinary circumstances (such as any such person leaving the
employment of Contractor and any affiliated entities). Unless approved by Engineer, all project
executives, project managers, and superintendents must be same individuals identified in Contractor’s
Bid. The superintendent will be Contractor’s representative at the site and will have authority to act on
behalf of Contractor. All communications given to or received from the superintendent will be binding on
Contractor.
6.02 Labor; Working Hours
Contractor will provide competent, suitably qualified personnel to survey, lay out, and construct the Work
as required by the Contract Documents. Contractor will at all times maintain good discipline and order at
the Site.
6.03 Services, Materials, and Equipment
(A) Unless otherwise specified in the General Requirements, Contractor will provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction equipment and
machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary
facilities, and all other facilities and incidentals necessary for the performance, testing, start-up, and
completion of the Work.
(B) All materials and equipment incorporated into the Work will be as specified or, if not specified, will be of
good quality and new, except as otherwise provided in the Contract Documents. All warranties and
guarantees specifically called for by the Specifications will expressly run to the benefit of Developer. If
required by Engineer, Contractor will furnish satisfactory evidence (including reports of required tests) as
to the source, kind, and quality of materials and equipment. All materials and equipment will be stored,
applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with
instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents.
6.04 Progress Schedule
(A) Contractor will adhere to the progress schedule established in accordance with Section 2.07 as it may be
adjusted from time to time as provided below.
(1) Contractor will submit to Engineer for acceptance (to the extent indicated in Section 2.07) proposed
adjustments in the progress schedule that will not result in changing the Contract Dates. Such
adjustments will conform generally to the progress schedule then in effect and additionally will comply
with any provisions of the General Requirements applicable thereto.
General Conditions Meridian Town Center
Page 65 of 114 Offsite Improvements - Phase 3
(2) Proposed adjustments in the progress schedule that will change the Contract Dates will be submitted
in accordance with the requirements of Article 12. Such adjustments may only be made by a Change
Order or Written Amendment in accordance with Article 12.
6.05 Substitutes and “Or-Equals”
(A) Whenever an item of material or equipment is specified or described in the Contract Documents by using
the name of a proprietary item or the name of a particular Supplier, the specification or description is
intended to establish the type, function, appearance, and quality required. Unless the specification or
description contains or is followed by words reading that no like, equivalent, or “or-equal” item or no
substitution is permitted, other items of material or equipment or material or equipment of other
Suppliers may be submitted to Engineer for review under the circumstances described below.
(1) “Or-Equal” Items: If in Engineer’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in related
Work will be required, it may be considered as an “or-equal” item, in which case review and approval
of the proposed item may, in Engineer’s sole discretion, be accomplished without compliance with
some or all of the requirements for approval of proposed substitute items. For the purposes of this
Section 6.05(A)(1), a proposed item of material or equipment will be considered functionally equal to
an item so named if:
a) in the exercise of reasonable judgment Engineer determines that: (i) it is at least equal in quality,
durability, appearance, strength, and design characteristics; (ii) it will reliably perform at least
equally well the function imposed by the design concept of the completed Project as a functioning
whole, and;
b) Contractor certifies that: (i) there is no increase in cost to Developer; and (ii) it will conform
substantially, even with deviations to the detailed requirements of the item named in the Contract
Documents.
(2) Substitute Items
a) If in Engineer’s sole discretion an item of material or equipment proposed by Contractor does not
qualify as an “or-equal” item under Section 6.05(A)(1), it will be considered a proposed substitute
item.
b) Contractor will submit sufficient information to Engineer as provided below to allow Engineer to
determine that the item of material or equipment proposed is essentially equivalent to that named
and an acceptable substitute therefore. Requests for review of proposed substitute items of
material or equipment will not be accepted by Engineer from anyone other than Contractor.
c) The procedure for review of substitute items will be as set forth in Section 6.05(A)(2)d), as
supplemented in the General Requirements and as Engineer may decide is appropriate under the
circumstances.
d) Contractor will first make written application to Engineer for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application will certify that
the proposed substitute item will perform adequately the functions and achieve the results called
for by the general design, be similar in substance to that specified, and be suited to the same use
as that specified. The application will state the extent, if any, to which the use of the proposed
substitute item will prejudice Contractor’s achievement of Substantial Completion on time,
whether or not use of the proposed substitute item in the Work will require a change in any of the
Contract Documents (or in the provisions of any other direct contract with Developer for work on
the Project) to adapt the design to the proposed substitute item and whether or not incorporation
or use of the proposed substitute item in connection with the Work is subject to payment of any
license fee or royalty. All variations of the proposed substitute item from that specified will be
identified in the application, and available engineering, sales, maintenance, repair, and
replacement services will be indicated. The application will also contain an itemized estimate of all
costs of redesign and claims of other contractors affected by any resulting change, all of which will
General Conditions Meridian Town Center
Page 66 of 114 Offsite Improvements - Phase 3
be considered in evaluating the proposed substitute item. Engineer may require Contractor to
furnish additional data about the proposed substitute item.
(B) Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or
procedure of construction is shown or indicated in and expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method technique, sequence, or procedure of
construction approved by Engineer. Contractor will submit sufficient information to Engineer to allow
Engineer, in Engineer’s sole discretion, to determine that the substitute proposed is equivalent to that
expressly called for by the Contract Documents. The procedure for review by Engineer will be similar to
that provided in Subsection 6.05(A)(2).
(C) Evaluation: Engineer will be allowed a reasonable time within which to evaluate each proposal or
submittal made pursuant to Sections 6.05(A) and 6.05(B). Engineer will be the sole judge of acceptability.
No “or-equal” or substitute will be ordered, installed or utilized until Engineer’s review is complete, which
will be evidenced by either a Change Order for a substitute or an approved Shop Drawing for an “or equal.”
Engineer will advise Contractor in writing of any negative determination.
(D) Special Guarantee: Developer may require Contractor to furnish at Contractor’s expense a special
performance guarantee or other surety with respect to any substitute.
(E) Cost Reimbursement: Engineer will record time required by Engineer and Engineer’s Consultants in
evaluating substitute proposed or submitted by Contractor pursuant to Sections 6.05(A)(2) and 6.05(B)
and in making changes in the Contract Documents (or in the provisions of any other direct contract with
Developer for work on the Project) occasioned thereby. Whether or not Engineer approves a substitute
item so proposed or submitted by Contractor, Contractor will reimburse Developer for the charges of
Engineer and Engineer’s Consultants for evaluating each such proposed substitute.
(F) Contractor’s Expense: Contractor will provide all data in support of any proposed substitute or “or-equal”
at Contractor’s expense.
6.06 Concerning Subcontractors, Suppliers, and Others
(A) Contractor will not employ any Subcontractor, Supplier, or other individual or entity (including those
acceptable to Developer as indicated in Section 6.06(B)), whether initially or as a replacement, against
whom Developer may have reasonable objection. Contractor will not be required to employ any
Subcontractor, Supplier, or other individual or entity to furnish or perform any of the Work against whom
Contractor has reasonable objection.
(B) If the Contract Documents require the identity of certain Subcontractors, Suppliers, or other individuals
or entities to be submitted to Developer in advance for acceptance by Developer by a specified date prior
to the Effective Date of the Agreement, and if Contractor has submitted a list thereof, Developer’s
acceptance (either in writing or by failing to make written objection thereto by the date indicated for
acceptance or objection in the Bidding Documents or the Contract Documents) of any such Subcontractor,
Supplier, or other individual or entity so identified may be revoked on the basis of reasonable objection
after due investigation. Contractor will submit an acceptable replacement for the rejected Subcontractor,
Supplier, or other individual or entity, and the Contract Price will be adjusted by the difference in the cost
occasioned by such replacement, and an appropriate Change Order will be issued or Written Amendment
signed. No acceptance by Developer of any such Subcontractor, Supplier, or other individual or entity,
whether initially or as a replacement, will constitute a waiver of any right of Developer, Engineer to reject
defective Work.
(C) Contractor will be fully responsible to Developer, ITD, Engineer for all acts and omissions of the
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just
as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract Documents
will create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual
relationship between Developer, Engineer and any such Subcontractor, Supplier or other individual or
entity, nor will it create any obligation on the part of Developer, Engineer to pay or to see to the payment
General Conditions Meridian Town Center
Page 67 of 114 Offsite Improvements - Phase 3
of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
(D) Contractor will be solely responsible for scheduling and coordinating the Work of Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or
indirect contract with Contractor.
(E) Contractor will require all Subcontractors, Suppliers, or such other individuals or entities performing or
furnishing any of the Work to communicate with Engineer through Contractor.
(F) The divisions and sections of the Specifications and identifications of any Drawings will not control
Contractor in dividing the Work among Subcontractors or Suppliers or delineating the Work to be
performed by any specific trade.
(G) All work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate
agreement between Contractor and the Subcontractor or Supplier which specifically binds the
Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the
benefit of Developer, Engineer. Whenever any such agreement is with a Subcontractor or Supplier who is
listed as an additional insured on the property insurance provided in Section 5.06, the agreement
between Contractor and the Subcontractor or Supplier will contain provisions whereby the Subcontractor
or Supplier waives all rights against Developer, Engineer, Contractor, Engineer’s Consultants, and all other
individuals or entities identified in the Supplementary Conditions to be listed as insureds or additional
insureds (and the officers, directors, partners, employees, agents, and other consultants and
subcontractors of each and any of them) for all losses and damages caused by, arising out of, relating to,
or resulting from any of the perils or causes of loss covered by such policies and any other property
insurance applicable to the Work. If the insurers on any such policies require separate waiver forms to be
signed by any Subcontractor or Supplier, Contractor will obtain the same.
6.07 Patent Fees and Royalties
(A) Contractor will pay all license fees and royalties and assume all costs incident to the use in the
performance of the Work or the incorporation in the Work of any invention, design, process, product, or
device which is the subject of patent rights or copyrights held by others. If a particular invention, design,
process, product, or device is specified in the Contract Documents for use in the performance of the Work
and if to the actual knowledge of Developer, Engineer its use is subject to patent rights or copyrights
calling for the payment of any license fee or royalty to others, the existence of such rights will be disclosed
by Developer in the Contract Documents. To the fullest extent permitted by Laws and Regulations,
Contractor will indemnify and hold harmless Developer, Engineer, and Engineer’s Consultants, and the
officers, directors, partners, employees or agents, and other consultants of each and any of them from
and against all claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to
the use in the performance of the Work or resulting from the incorporation in the Work of any invention,
design, process, product, or device not specified in the Contract Documents.
6.08 Permits
(A) Unless otherwise provided in the Supplementary Conditions or Special Provisions, Contractor will obtain
and pay for all construction permits and licenses. Developer will assist Contractor, when necessary, in
obtaining such permits and licenses. Contractor will pay all governmental charges and inspection fees
necessary for the prosecution of the Work which are applicable at the time of opening of Bids, or, if there
are no Bids, on the Effective Date of the Agreement. Contractor will pay all charges of utility providers for
connections to the Work, and Developer will pay all charges of such utility owners for capital costs related
thereto, such as plant investment fees.
6.09 Laws and Regulations
(A) Contractor will give all notices and comply with all Laws and Regulations applicable to the performance
of the Work. Except where otherwise expressly required by the applicable Laws and Regulations, neither
General Conditions Meridian Town Center
Page 68 of 114 Offsite Improvements - Phase 3
Developer, Engineer nor Engineer will be responsible for monitoring Contractor’s compliance with any
Laws or Regulations.
(B) If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or
Regulations, Contractor will bear all claims, costs, losses, and damages (including but not limited to all
fees and charges of engineers, architects attorneys, and other professionals and all court or arbitration or
other dispute resolution costs) arising out of or relating to such Work; however, it will not be Contractor’s
primary responsibility to make certain that the Specifications and Drawings are in accordance with laws
and Regulations, but this will not relieve Contractor of Contractor’s obligations under Section 3.03
(C) Changes in Laws and Regulations not known at the time of opening of Bids (or, on the Effective Date of
the Agreement if there were no Bids) having an effect on the cost or time of performance of the Work
may be the subject of an adjustment in Contract Price or Contract Dates. If Developer and Contractor are
unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment, a Claim
may be made therefore as provided in Section 10.05.
6.10 Taxes
(A) Contractor will pay all sales, consumer, use, and other similar taxes required to be paid by Contractor in
accordance with the Laws and Regulations of the place of the Project which are applicable during the
performance of the Work.
6.11 Use of Site and Other Areas
(A) Limitation on Use of Site and Other Areas
(1) Contractor will confine construction equipment, the storage of materials and equipment, and the
operations of workers to the Site and other areas permitted by the Contract Documents and Laws and
Regulations (including, but not limited to, the areas for staging and other activities), and will not
unreasonably encumber the Site and other areas with construction equipment or other materials or
equipment. Contractor will assume full responsibility for any damage to any such land or area, or to
the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of
the Work.
(2) Should any claim be made by any such owner or occupant because of the performance of the Work,
Contractor will promptly settle with such other party by negotiation or otherwise resolve the claim by
arbitration or other dispute resolution proceeding or at law.
(3) To the fullest extent permitted by Laws and Regulations, Contractor will indemnify and hold harmless
Developer, ITD, Engineer, Engineer’s Consultant, and the officers, directors, partners, employees,
agents, and other consultants of each and any of them from and against all claims, costs, losses, and
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) arising out of or
relating to any claim or action, legal or equitable, brought by any such owner or occupant against
Developer, ITD, Engineer, or any other party indemnified hereunder to the extent caused by or based
upon Contractor’s performance of the Work.
(B) Removal of Debris During Performance of the Work: During the progress of the Work Contractor will keep
the site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal
and disposal of such waste materials, rubbish, and other debris will conform to applicable Laws and
Regulations.
(C) Cleaning: Prior to Substantial Completion of the Work Contractor will clean the Site and make it ready for
utilization by Developer. At the completion of the Work Contractor will remove from the Site all tools,
appliances, construction equipment and machinery, and surplus materials and will restore to the original
condition all property not designated or alteration by the Contract Documents.
(D) Loading Structures: Contractor will not load nor permit any part of any structure to be loaded in any
manner that will endanger the structure, nor will Contractor subject any part of the Work or adjacent
property to stresses or pressures that will endanger it.
6.12 Record Documents
General Conditions Meridian Town Center
Page 69 of 114 Offsite Improvements - Phase 3
(A) Contractor will maintain in a safe place at the Site one (1) record copy of all Drawings, Specifications,
Addenda, Written Amendments, Change Orders, Work Change Directives, Field Orders, and written
interpretations and clarifications in good order and annotated to show changes made during construction.
These record documents together with all approved Samples and a counterpart of all approved Shop
Drawings will be available to Engineer for reference. Upon completion of the Work, these record
documents, Samples, Shop Drawings and as-builts will be delivered to Engineer for Developer.
6.13 Safety and Protection
(A) Contractor will be solely responsible for initiating, maintaining and supervising all safety precautions and
programs in connection with the Work. Contractor will take all necessary precautions for the safety of,
and will provide the necessary protection to prevent damage, injury or loss to:
(1) all persons on the Site or who may be affected by the Work:
(2) all the Work and materials and equipment to be incorporated therein, whether in storage or of the
Site; and
(3) other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements,
roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or
replacement in the course of construction.
(B) Contractor will comply with all applicable Laws and Regulations relating to the safety of persons or
property, or to the protection of persons or property from damage, injury, or loss; and will erect and
maintain all necessary safeguards for such safety and protection. Contractor will notify owners of adjacent
property and of Underground Facilities and other utility owners when prosecution of the Work may affect
them, and will cooperate with them in the protection, removal, relocation, and replacement of their
property. All damage, injury, or loss to any property referred to in Section 6.13(A)(2) or 6.13(A)(3) caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other
individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone
for whose acts any of them may be liable, will be remedied by Contractor (except damage or loss
attributable to the fault of Drawings or Specifications or to the acts or omissions of Developer or Engineer
or Engineer’s Consultant, or anyone employed by any of them, or anyone for whose acts any of them may
be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of
Contractor or any Subcontractor, Supplier, or other individual or entity directly or indirectly employed by
any of them). Contractor’s duties and responsibilities for safety and for protection of the Work will
continue until such time as all the Work is completed and Engineer has issued a notice to Developer and
Contractor in accordance with Section 14.07(B) that the Work is acceptable (except as otherwise expressly
provided in connection with Substantial Completion).
6.14 Safety Representative
(A) Contractor will designate a qualified and experienced safety representative at the Site whose duties and
responsibilities will be the prevention of accidents and the maintaining and supervising of safety
precautions and programs.
6.15 Hazard Communications Programs
(A) Contractor will be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or among
employers at the Site in accordance with Laws and Regulations.
6.16 Emergencies
(A) In emergencies affecting the safety or protection of persons or the Work or property at the Site or
adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury, or loss. Contractor
will give Engineer prompt written notice if Contractor believes that any significant changes in the Work
or variations from the Contract Documents have been caused thereby or are required as a result thereof.
If Engineer determines that a change in the Contract Documents is required because of the action taken
by Contractor in response to such an emergency, a Work Change Directive or Change Order will be issued.
6.17 Shop Drawings and Samples
General Conditions Meridian Town Center
Page 70 of 114 Offsite Improvements - Phase 3
(A) Contractor will submit Shop Drawings to Engineer for review and approval by Engineer in accordance with
the acceptable schedule of Shop Drawings and Sample submittals. All submittals will be identified as
Engineer may require an in the number of copies specified in the General Requirements. The data shown
on the Shop Drawings will be complete with respect to quantities, dimensions, specified performance and
design criteria, materials, and similar data to show Engineer the services, materials, and equipment
Contractor proposes to provide and to enable Engineer to review the information for the limited purposes
required by Section 6.17(E).
(B) Contractor will also submit Samples to Engineer for review and approval by Engineer in accordance with
the acceptable schedule of Shop Drawings and Sample submittals. Each Sample will be identified clearly
as to material, Supplier, pertinent data such as catalog numbers, and the use for which intended and
otherwise as Engineer may require to enable Engineer to review the submittal for the limited purposes
required by Section 6.17(E). The numbers of each Sample to be submitted will be as specified in the
Specifications.
(C) Where a Shop Drawing or Sample is required by the Contract Documents or the schedule of Shop
Drawings and Sample submittals acceptable to Engineer as required by Section 2.07, any related Work
performed prior to Engineer’s review and approval of the pertinent submittal will be at the sole expense
and responsibility of Contractor.
(D) Submittal Procedures
(1) Before submitting each Shop Drawing or Sample, Contractor will have determined and verified:
a) All field measurements, quantities, dimensions, specified performance criteria, installation
requirements, materials, catalog numbers, and similar information with respect thereto;
b) All materials with respect to intended use, fabrication, shipping, handling, storage, assembly, and
installation pertaining to the performance of the Work;
c) All information relative to means, methods, techniques, sequences, and procedures of
construction and safety precautions and programs incident thereto; and
d) Contractor will also have reviewed and coordinated each Shop Drawing or Sample with other Shop
Drawings an Samples and with the requirements of the Work and the Contract Documents.
(2) Each submittal will bear a stamp or specific written indication that Contractor has satisfied
Contractor’s obligations under the Contract Documents with respect to Contractor’s review and
approval of that submittal.
(3) At the time of each submittal, Contractor will give Engineer specific written notice of such variations,
if any, that the Shop Drawing or Sample submitted may have from the requirements of the Contract
Documents, such notice to be in written communication separate from the submittal; and, in addition,
will cause a specific notation to be made on each Shop Drawing and Sample submitted to Engineer for
review and approval of each such variation.
(E) Review
(1) Engineer will timely review and approve Shop Drawings and Samples in accordance with the schedule
of Shop Drawings and Sample submittals acceptable to Engineer. Review and approval will be only to
determine if the items covered by the submittals will, after installation or incorporation in the Work,
conform to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract Documents.
(2) Review and approval will not extend to means, methods, techniques, sequences, or procedures of
construction (except where a particular means, method, technique, sequence, or procedure of
construction is specifically and expressly called for by the Contract Documents) or to safety
precautions or programs incident thereto. The review and approval of a separate item as such will not
indicate approval of the assembly in which the item functions.
(3) Review and approval of Shop Drawings or Samples will not relieve Contractor from responsibility for
any variation from the requirements of the Contract Documents unless Contractor has in writing called
General Conditions Meridian Town Center
Page 71 of 114 Offsite Improvements - Phase 3
to Engineer’s and Engineer’s attention to each such variation at the time of each submittal as required
by Section 6.17(D)(3) and Engineer has given written approval of each such variation by specific
written notation thereof incorporated in or accompanying the Shop Drawings or Sample approval; nor
will any approval by Engineer relieve Contractor from responsibility for complying with the
requirements of Section 6.17(D)(1).
(F) Resubmittal Procedures
Contractor will make corrections required by Engineer and will return the required number of
corrected copies of Shop Drawings and submit as required new Samples for review and approval.
Contractor will direct specific attention in writing to revisions other than the corrections called for by
Engineer on previous submittals.
6.18 Continuing the Work
Contractor will carry on the Work and adhere to the progress schedule during all disputes with Developer.
No Work will be delayed or postponed pending resolution of any disputes or disagreements, except as
permitted by Section 15.04 or as Developer and Contractor may otherwise agree in writing.
6.19 Contractor’s General Warranty and Guarantee
(A) Contractor warrants and guarantees to Developer, Engineer, and Engineer’s Consultants that all Work will
be in accordance with the Contract Documents and will not be defective. Contractor’s warranty and
guarantee hereunder excludes defects or damage caused by:
(1) abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or
(2) normal wear and tear under normal usage.
(B) Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents
will be absolute. None of the following will constitute an acceptance of Work that is not in accordance
with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance
with the Contract Documents:
(1) observations by Engineer;
(2) recommendation by Engineer or payment by Developer of any progress or final payment;
(3) the issuance of a certificate of Substantial Completion by Engineer or any payment related thereto by
Developer;
(4) use or occupancy of the Work or any part thereof by Developer;
(5) any acceptance by Developer or any failure to do so;
(6) any review and approval of a Shop Drawing or Sample submittal or the issuance of a notice of
acceptability by Engineer;
(7) any inspection, test, or approval by others; or
(8) any correction of defective Work by Developer.
6.20 Indemnification
To the fullest extent permitted by Laws and Regulations, Contractor will indemnify and hold harmless
Developer, ITD, Engineer, Engineer’s Consultants, and the officers, directors, partners, employees, agents,
and other consultants and subcontractors of each and any of them from and against all claims, costs,
losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys,
and other professionals and all court or arbitration or other dispute resolution costs) arising out of or
relating to the performance of the Work, provided that any such claim, cost, loss, or damage:
(1) attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible
property (other than the Work itself), including the loss of use resulting therefrom; and
(2) is caused in whole or in part by any negligent act or omission of Contractor, any Subcontractor,
any Supplier, or any individual or entity directly or indirectly employed by any of them to perform
any of the Work or anyone for whose acts any of them may be liable, regardless of whether or not
General Conditions Meridian Town Center
Page 72 of 114 Offsite Improvements - Phase 3
caused in part by any negligence or omission of an individual or entity indemnified hereunder or
whether liability is imposed upon such indemnified party by Laws and Regulations regardless of
the negligence of any such individual or entity.
(3) In any and all claims against Developer, ITD, Engineer or Engineer’s Consultants, or any of their
respective consultants, agents, officers, directors, partners, or employees by any employee (or the
survivor or personal representative of such employee) of Contractor, any Subcontractor, any
Supplier, or any individual or entity directly or indirectly employed by any of them to perform any
of the Work, or anyone for hose acts any of them may be liable, the indemnification obligation
under this Section 6.20 will not be limited in any way by any limitation on the amount or type of
damages, compensation, or benefits payable by or for Contractor or any such Subcontractor,
Supplier, or other individual or entity under workers’ compensation acts, disability benefit acts, or
other employee benefit acts.
(4) The indemnification obligations of Contractor under this Section 6.20 will not extend to the liability
of Engineer and Engineer’s Consultants or to the officers, directors, partners, employees, agents,
and other consultants and subcontractors of each and any of them arising out of:
a) the preparation or approval of, or the failure to prepare or approve, maps, Drawings, opinions,
reports, surveys, Change Orders, designs, or Specifications; or
b) giving directions or instructions, or failing to give them, if that is the primary cause of the injury
or damage.
6.21 Communications
(1) Contractor will keep Engineer fully informed of Contractor’s performance of the Work so Developer
Representative can have timely and meaningful opportunities to review and input. Without limiting
the generality of the foregoing sentence, Contractor will, as a matter of course, promptly provide
Developer Representative with copies of material documents and information relating to the
performance of the Work, including, meeting agendas, meeting minutes, material communications
with third parties, etc. Contractor will provide the documents and information to Developer
Representative in a manner that Developer Representative can readily identify and understand
matters for action or decision by Developer, Engineer. Contractor will be readily available to consult
with Developer, Developer Representative or Engineer (by telephone or in person), when reasonably
requested by Developer Representative, regarding the progress of the Work, Contractor’s
communications; pending matters for decision by Developer, Developer’ Representative or Engineer;
and other matters.
(2) Contractor will promptly notify Developer Representative of any actions or decisions required of
Developer, Engineer for Contractor to timely and properly perform the Work, and any deadlines
pertaining thereto to prevent delays in the Work. Whenever possible, the notice will be sufficiently in
advance of any applicable deadline to allow the deciding party a reasonable time to consult with
Contractor, consider alternatives and execute the action or decision. Contractor will consult with and
advise Developer, Engineer with respect to any decisions. Contractor will clearly and conspicuously
mark any urgent request for information or request for changes in the Work with the following phrase
in bold and highlighted text: "Urgent - Please Respond by [Insert Desired Response Date]" and
immediately bring the request to the personal attention of Engineer.
(3) Contractor covenants, represents and warrants to Developer, Engineer that any documents, reports
or information provided by Contractor (excluding third party reports) regarding this Agreement or
Contractor’s performance of the Work (including invoices, applications for payment, schedules,
completion reports, activity reports, Claims and other information) will, at the time provided, to be
best of Contractor’s knowledge, information and belief after reasonable inquiry, if any, based on
industry standards for contractors engaged in the construction of projects of similar scope and
complexity: (a) be true and correct in all material respects; (b) not contain any untrue statement of
material fact; and (c) not omit a material fact required to be stated therein or necessary to make the
statements therein, in light of the circumstances under which they were made, not misleading. If
Contractor discovers that any document, report or information previously provided by Contractor
General Conditions Meridian Town Center
Page 73 of 114 Offsite Improvements - Phase 3
failed to comply with the foregoing sentence at the time it was provided, Contractor will promptly (i)
notify Developer of the specific document, report or information in question, (ii) the nature of the
failure to comply with the foregoing sentence and (iii) if known, the information that would have made
the prior document, report or information comply with the foregoing sentence.
6.22 Contractor’s General Representations and Warranties
Contractor makes the following express representations and warranties to Developer, which are continuing
during the term of this Agreement and expressly made again at the execution of each Guaranteed Maximum
Price Amendment. Contractor will promptly notify Developer if Contractor discovers any of Contractor’s
representations or warranties are not true and correct in any material respect (either when initially made or
any time thereafter).
(1) (a) Contractor is a duly organized and validly entity existing under the laws of its state of origin and
has all requisite legal power and authority to execute, deliver and perform this Agreement; (b)
Contractor is properly licensed and registered by each Governmental Authority with jurisdiction over
Contractor or the Work; (c) the execution, delivery and performance of this Agreement have been
duly authorized by all requisite entity action of Contractor and there is no provision in its charter
documents or other documents requiring further consent by any other person or entity; (d) this
Agreement constitutes the legal, valid and binding obligation of Contractor, enforceable against
Contractor in accordance with its terms, except as enforceability may be limited by applicable
bankruptcy, reorganization, moratorium or similar laws affecting or limiting creditors’ rights generally
or by equitable principles relating to enforceability; and (e) Contractor is financially solvent, able to
pay its debts as they mature and has sufficient working capital to complete its obligations under this
Agreement.
(2) Contractor has thoroughly and carefully examined the Contract Documents (as a construction
contractor with expertise in examining and evaluating the suitability of documents for the
construction of projects of the scope and nature of the Project, but not as a licensed design
professional), and has found them to be complete, coordinated and suitable for construction of the
Work for the Contract Price and in accordance with the then current Project Schedule, and otherwise
for Contractor to timely and properly perform its obligations under this Agreement. Contractor agrees
that Developer is relying, in part, on Contractor’s advice and expertise in evaluating the suitability of
the Contract Documents for the construction of the Project. Contractor agrees that Contractor has not
received, nor has Contractor relied upon, any representation or warranty from Developer, Engineer
(express or implied), regarding the adequacy, fitness, suitability or constructability of the Contract
Documents, as Developer is relying on Contractor’s expertise for those determinations.
(3) Contractor has thoroughly and carefully examined the Contract Time and has found it to be complete
and to provide suitable time for Contractor’s performance of the Work in accordance with this
Agreement.
(4) Contractor has the knowledge, skills, experience, education and staffing to perform its duties and
obligations. The individual employees of Contractor who will perform services hereunder will be
knowledgeable and experienced in the technical disciplines and services to be performed.
(5) Contractor has (or will have as part of the Work) and will maintain all necessary licenses, permits, or
other authorizations necessary to perform its duties and obligations under the Contract Documents,
including, but not limited to, those necessary for the disposal of construction wastes, transportation
of materials and equipment and other services to be performed by Contractor, and business,
contractor and trade permits, registrations and licenses.
(6) Contractor is familiar with the local and other conditions which may be material to Contractor’s
performance of its obligations under the Contract Documents (including, but not limited to
transportation, seasons and climates, access, the handling and storage of materials and fuel and
availability and quality of labor and materials). Contractor has thoroughly and carefully examined the
market conditions related to the Work, including the availability and pricing of materials, labor,
supplies and all other things necessary for the performance of the Work and found them to be
General Conditions Meridian Town Center
Page 74 of 114 Offsite Improvements - Phase 3
adequate for Contractor to perform the Work as provided in the Contract Documents for no more
than the Guaranteed Maximum Price.
(7) Contractor represents, warrants and covenants that it is not and its controlling equity holders and
executive officers are not persons or entities with whom U.S. persons or entities are restricted from
doing business under regulations of the Office of Foreign Asset Control ("OFAC") of the Department
of the Treasury (including those named on OFAC's Specially Designated and Blocked Persons List) or
under any statute, executive order (including the September 24, 2001, Executive Order Blocking Real
Property and Prohibiting Transactions with Persons Who Commit, Threaten to Commit, or Support
Terrorism), or other governmental action and to its knowledge there are no investigations, claims or
proceedings inconsistent with the foregoing.
6.23 Waiver of Consequential Losses and Damages
Contractor waives and releases Developer, ITD, Engineer, Engineer’s Consultants, and the officers,
directors, partners, employees, agents, and other consultants and subcontractors of each and any of them
from and against all indirect or consequential claims, costs, losses, and damages arising out of or relating
to the performance of the Work, including, without limitation, losses or damages for income, profit,
financing, business and reputation, and for loss of management or employee productivity or of the
services of such persons.
ARTICLE 7. OTHER WORK
7.01 Related Work at Site
(A) Contractor acknowledges that Developer’s other contractors, utility owners, ITD, emergency service
providers and others will be performing other construction and other activities on or near the Site.
Contractor agrees that the Work includes the detailed and continuous coordination of the Work with the
activities of such other activities in a manner that allows such activities to be reasonably performed
concurrently with the Work. Such detailed and continuous coordination efforts will include, but not be
limited to, the meeting, scheduling, coordination and cooperation obligations set forth in the Contract
Documents.
(B) Contractor will afford each other contractor, ITD and each utility owner (and Developer, if Developer is
performing the other work with Developer’s employees) proper and safe access to the Site and a
reasonable opportunity for the introduction and storage of materials and equipment and the execution
of such other work and will properly coordinate the Work with theirs. Unless otherwise provided in the
Contract Documents, Contractor will do all cutting, fitting, and patching of the Work that may be required
to properly connect or otherwise make its several parts come together and properly integrate with such
other work. Contractor will not endanger any work of others by cutting, excavating, or otherwise altering
their work and will only cut or alter their work with the written consent of Engineer and the others whose
work will be affected. The duties and responsibilities of Contractor under this Section are for the benefit
of such utility owners and other contractors to the extent that there are comparable provisions for the
benefit of Contractor in said direct contracts between Developer and such utility owners and other
contractors.
(C) If the proper execution or results of any part of Contractor’s Work depends upon work performed by
others under this Article 7, Contractor will inspect such other work and promptly report to Engineer and
in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable
for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute
an acceptance of such other work as fit and proper for integration with Contractor’s Work except for
latent defects and deficiencies in such other work.
ARTICLE 8. OWNER’S RESPONSIBILITIES
8.01 Communications to Contractor
Except as otherwise provided in these General Conditions, Developer will issue all communications to
Contractor through Engineer.
General Conditions Meridian Town Center
Page 75 of 114 Offsite Improvements - Phase 3
8.02 Replacement of Engineer
In case of termination of the employment of Engineer or, Developer will appoint an owner’s
representative or engineer to whom Contractor makes no reasonable objection, whose status under the
Contract Documents will be that of the former Engineer or.
8.03 Furnish Data
Developer will promptly furnish the data required of Developer under the Contract Documents.
8.04 Pay Promptly When Due
Developer will make payments to Contractor promptly when they are due as provided in Sections 14.02(C)
and 14.07(C).
8.05 Lands and Easements; Reports and Tests
Developer’s duties in respect of providing lands and easements and providing engineering surveys to
establish reference points are set forth in Sections 14.01 and 14.05. Section 14.02 refers to Developer’s
identifying and making available to Contractor copies of reports and explorations and tests of subsurface
conditions and drawings of physical conditions in or relating to existing surface or subsurface structures
at or contiguous to the Site that have been used in preparing the Contract Documents.
8.06 Insurance
Developer’s responsibilities, if any, in respect to purchasing and maintaining liability insurance are set
forth in Article 5.
8.07 Change Orders
Developer is obligated to execute Change Orders as indicated in Section 10.03.
8.08 Inspections, Tests, and Approvals
Developer’s responsibility in respect to certain inspections, tests, and approvals is set forth in
Section 13.03(B).
8.09 Limitations on Developer’s Responsibilities
The Developer will not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and
Regulations applicable to the performance of the Work. Developer will not be responsible for Contractor’s
failure to perform the Work in accordance with the Contract Documents.
8.10 Undisclosed Hazardous Environmental Condition
Developer’s responsibility in respect to an undisclosed Hazardous Environmental Condition is set forth in
Section 4.06.
ARTICLE 9. STATUS OF OWNER’S REPRESENTATIVE AND ENGINEER DURING CONSTRUCTION
9.01 Engineer
Engineer will be Engineer during the construction period. The duties and responsibilities and the
limitations of authority of Engineer as Engineer during construction are set forth in the Contract
Documents and will not be changed without written consent of Developer, Engineer (which consent will
not be unreasonably withheld, conditioned or delayed).
9.02 Visits to Site
(A) Engineer and will make visits to the Site at intervals appropriate to the various stages of construction as
Engineer deem necessary in order to observe the progress that has been made and the quality of the
various aspects of Contractor’s executed Work. Based on information obtained during such visits and
observations, Engineer, for the benefit of Developer, will determine, in general, if the Work is proceeding
in accordance with the Contract Documents. Engineer will not be required to make exhaustive or
General Conditions Meridian Town Center
Page 76 of 114 Offsite Improvements - Phase 3
continuous inspections on the Site to check the quality or quantity of the Work. Engineer’s efforts will be
directed toward providing for Developer’s a greater degree of confidence that the completed Work will
conform generally to the Contract Documents. On the basis of such visits and observations, Engineer will
keep Developer informed of the progress of the Work and will endeavor to guard Developer against
defective Work.
(B) Engineer’s and Engineer’s visits and observations are subject to all the limitations on authority and
responsibility set forth in Section 9.10, and particularly, but without limitation, during or as a result of the
visits or observations of Contractor’s Work, Engineer will not supervise, direct, control, or have authority
over or be responsible for Contractor’s means, methods, techniques, sequences, or procedures of
construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to
comply with Laws and Regulations applicable to the performance of the Work.
9.03 Clarifications and Interpretations
(A) Engineer will issue with reasonable promptness such written clarifications or interpretations of the
requirements of the Contract Documents as Engineer may determine necessary, which will be consistent
with the intent of and reasonably inferable from the Contract Documents. Such written clarifications and
interpretations will be binding on Developer and Contractor. If Developer and Contractor are unable to
agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or
Contract Dates, or both, that should be allowed as a result of a written clarification or interpretation, a
Claim may be made therefore as provided in Section 10.05.
9.04 Authorized Variations in Work
(A) Engineer may authorize minor variations in the Work from the requirements of the Contract Documents
which do not involve an adjustment in the Contract Price or the Contract Dates and are compatible with
the design concept of the completed Project as a functioning whole as indicated by the Contract
Documents. These may be accomplished by a Field Order and will be binding on Developer and also on
Contractor, who will perform the Work involved promptly. If Developer and Contractor are unable to
agree on entitlement to or on the amount or extent, if any, of any adjustment in the Contract Price or
Contract Dates, or both, as a result of a Field Order, a Claim may be made therefore as provided in
Section 10.05.
9.05 Rejecting Defective Work
(A) Engineer will have authority to disapprove or reject Work which Engineer believes to be defective, or that
Engineer believes will not produce a completed Project that conforms to the Contract Documents or that
will prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. Engineer will also have authority to require special inspection or
testing of the Work as provided in Section 13.04, whether or not the Work is fabricated, installed, or
completed.
9.06 Shop Drawings, Change Orders and Payments
(A) In connection with Engineer’s and Engineer’s authority as to Shop Drawings and Samples, see
Section 6.17.
(B) In connection with Engineer’s and Engineer’s authority as to Change Orders, see Article 10, Article 11, and
Article 12.
(C) In connection with Engineer’s and Engineer’s authority as to Applications for Payment, see Article 14.
9.07 Determinations for Unit Price Work
(A) Engineer will determine the actual quantities and classifications of Unit Price Work (if any) performed by
Contractor. Engineer will review with Contractor Engineer’s preliminary determinations on such matters
before rendering a written decision thereon (by recommendations of an Application for Payment or
otherwise). Engineer’s written decision thereon will be final and binding (except as modified by Engineer
to reflect changed factual conditions or more accurate data) upon Developer and Contractor, subject
either party’s right to make a Claim pursuant to Section 10.05.
General Conditions Meridian Town Center
Page 77 of 114 Offsite Improvements - Phase 3
9.08 Decisions on Requirements of Contract Documents and Acceptability of Work
(A) Engineer will be the initial interpreter of the requirements of the Contract Documents and judge of the
acceptability of the Work thereunder. Claims, disputes and other matters relating to the acceptability of
the Work, the quantities and classifications of Unit Price Work, the interpretation of the requirements of
the Contract Documents pertaining to the performance of the Work, and Claims seeking changes in the
Contract Price or Contract Dates will be referred initially to Engineer in writing (though Engineer) in
accordance with the provisions of Section 10.05, with a request for a decision.
(B) When functioning as interpreter and judge under this Section 9.09, Engineer will not show partiality to
Developer or Contractor and will not be liable in connection with any interpretation or decision rendered
in good faith in such capacity. The rendering of a decision by Engineer (if authorized by Developer)
pursuant to this Section 9.09 with respect to any such Claim, dispute, or other matter (except any which
have been waived by the acceptance of final payment as provided in Section 14.07) will be a condition
precedent to any exercise by Developer or Contractor of such rights or remedies as either may otherwise
have under the Contract Documents or by Laws or Regulations in respect of any such Claim, dispute, or
other matter.
9.09 Limitations on Engineer’s Authority and Responsibilities
(A) Neither Engineer’s authority or responsibility under this Article 9 or under any other provision of the
Contract Documents nor any decision made by Engineer in good faith either to exercise or not exercise
such authority or responsibility or the undertaking, exercise, or performance of any authority or
responsibility by Engineer will create, impose, or give rise to any duty in contract, tort, or otherwise owed
by Engineer to Contractor, any Subcontractor, any Supplier, any other individual or entity, or to any surety
for or employee or agent of any of them.
(B) Neither Engineer nor Engineer will supervise, direct, control, or have authority over or be responsible for
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and
Regulations applicable to the performance of the Work. Engineer will not be responsible for Contractor’s
failure to perform the Work in accordance with the Contract Documents.
(C) Neither Engineer nor Engineer will be responsible for the acts or omissions of Contractor or of any
Subcontractor, any Supplier, or of any other individual or entity performing any of the Work.
(D) Engineer’s and Engineer’s review of the final Application for Payment and accompanying documentation
and all maintenance and operating instructions, schedules, guarantees, Bonds, certificates of inspection,
tests and approvals, and other documentation required to be delivered by Section 14.07(A) will only be
to determine generally that their content complies with the requirements of, and in the case of
certificates of inspections, tests, and approvals that the results certified indicate compliance with, the
Contract Documents.
(E) The limitations upon authority and responsibility set forth in this Section 9.09 will also apply to Engineer’s
Consultants and assistants.
ARTICLE 10. CHANGES IN THE WORK; CLAIMS
10.01 Authorized Changes in the Work
(A) Without invalidating the Agreement and without notice to any surety, Developer may, at any time or from
time to time, order additions, deletions, or revisions in the Work by a Written Amendment, a Change
Order, or a Work Change Directive. Upon receipt of any such document, Contractor will promptly proceed
with the Work involved which will be performed under the applicable conditions of the Contract
Documents (except as otherwise specifically provided).
(B) If Developer and Contractor are unable to agree on entitlement to, or on the amount or extent, if any, of
an adjustment in the Contract Price or Contract Dates, or both, that should be allowed as a result of a
Work Change Directive, a Claim may be made therefore as provided in Section 10.05.
General Conditions Meridian Town Center
Page 78 of 114 Offsite Improvements - Phase 3
10.02 Unauthorized Changes in the Work
(A) Contractor will not be entitled to an increase in the Contract Price or an extension of the Contract Dates
with respect to any Work performed that is not required by the Contract Documents as amended,
modified, or supplemented as provided in Section 3.04, except in the case of an emergency as provided
in Section 6.16 or in the case of uncovering Work as provided in Section 13.04(B).
(B) Contractor agrees to treat any verbal request, authorization or direction for a change in the Work (or any
communication of a similar import), and any written request, authorization or directive for a change in
the Work that is not a Change Order or Work Change Directive (regardless of form), to be a directive to
promptly prepare and deliver a Change Order or Work Change Directive proposal consistent with the
request, authorization or direction to Engineer for review. Contractor agrees that Developer will be under
no obligation to pay Contractor for any changes in the Work performed without a Change Order or Work
Change Directive, and Contractor will hold Developer harmless from any loss, damage, claim or expense
related to any changes in the Work performed without an executed Change Order or Work Change
Directive.
10.03 Execution of Change Orders
(A) When appropriate, Developer and Contractor will execute appropriate Change Orders (or Written
Amendments) covering:
(1) changes in the Work which are: (i) ordered by Developer pursuant to Section 10.01(A), (ii) required
because of acceptance of defective Work under Section 13.08(A) or Developer’s correction of
defective Work under Section 13.09, or (iii) agreed to by the parties;
(2) changes in the Contract Price or Contract Dates which are agreed to by the parties, including any
undisputed sum or amount of time for Work actually performed in accordance with a Work Change
Directive; and
(3) changes in the Contract Price or Contract Dates which embody the substance of any written
recommendation rendered by Engineer pursuant to Section 10.05; provided that, in lieu of executing
any such Change Order, an appeal may be taken from any such recommendation in accordance with
the provisions of the Contract Documents and applicable Laws and Regulations, but during any such
appeal, Contractor will carry on the Work and adhere to the progress schedule as provided in
Section 6.180.
10.04 Notification to Surety
If notice of any change affecting the general scope of the Work or the provisions of the Contract
Documents (including, but not limited to, Contract Price or Contract Dates) is required by the provisions
of any bond to be given to a surety, the giving of any such notice will be Contractor’s responsibility. The
amount of each applicable Bond will be adjusted to reflect the effect of any such change.
10.05 Claims and Disputes
(A) Notice: Claims must be initiated by notice to the other party and Engineer. Unless an earlier initiation is
required under the Contract, Claims must be initiated within a reasonable time after occurrence of the
event giving rise to such Claim or within a reasonable time after the claimant first recognizes the condition
giving rise to the Claim, whichever is later. Contractor acknowledges that Developer’s ability to
investigate, remedy or mitigate Claims will be substantially prejudiced if Contractor does not initiate a
Claim as soon as practical. Therefore, Contractor acknowledges that, as to claims by Contractor, “a
reasonable time” will mean as soon as practical but in any event (a) before Contractor does anything to
prejudice the of Developer, Engineer to investigate, remedy or mitigate such Claim, (b) no later than any
specific time period otherwise set forth herein, or (c) no more than fourteen (14) days after the Contactor
first recognizes or should have recognized the occurrence or condition giving rise to the Claim, whichever
is earlier.
(B) The responsibility to substantiate Claims will rest with the party making the Claim. All Claims by Contractor
will be supported by such documentation as is reasonably sufficient for Developer, Engineer to determine
the accuracy and appropriateness thereof. Such additional data will include, to the extent known or
General Conditions Meridian Town Center
Page 79 of 114 Offsite Improvements - Phase 3
through the exercise of reasonable diligence should be known at the time, at a minimum (a) a narrative
of the specific acts, events, facts and circumstances giving rise to the Claim, (b) an detailed accounting of
the amount of additional compensation, if any, requested by Contractor under the Claim; (c) an detailed
accounting of the amount of additional time, if any, requested by Contractor; (d) an analysis that confirms
not only that Contractor incurred the costs upon which the request for additional compensation is based
and the delays upon which request for the additional time is based, but that the costs or delay claimed
were actually a result of the act, event, circumstances or condition giving rise to the Claim, (e) an analysis
confirming that this Agreement entitles Contractor to the additional compensation or additional time
requested, (f) an analysis confirming that the Claim is not covered by insurance required of Contractor
under this Agreement (whether or not Contractor actually maintained such insurance), and (f) supporting
documentation sufficiently detailed to permit an informed analysis of the request by Developer, Engineer.
Failure to provide such additional information and documentation, to the extent such information and
documentation was reasonably available to Contractor, within the time allowed or within the format
required will, to the extent Developer’s interests are prejudiced, constitute a waiver of Contractor’s Claim.
(C) A Claim for an adjustment in Contract Price will be prepared in accordance with the provisions of
Section 12.01(B). A Claim for an adjustment in the Contract Time will be prepared in accordance with the
provisions of Section 12.02(B). Each Claim will be accompanied by claimant’s written statement that the
adjustment claimed is the entire adjustment to which the claimant believes it is entitled as a result of said
event. The opposing party will submit any response to Engineer and the claimant within fourteen (14)
days after receipt of the claimant’s last submittal (unless Engineer allows additional time).
(D) Engineer’s Decision: If authorized by Developer, Engineer will render a formal decision on a Claim in
writing within a reasonable time after receipt of the Claim and the response of the opposing party, if any.
Engineer’s written decision on such Claim, dispute, or other matter will be final and binding upon
Developer and Contractor unless a written notice of intention to appeal from Engineer’s written decision
is delivered by Developer or Contractor to the other and to Engineer within fourteen (14) days after the
date of such decision, and a formal proceeding is instituted by the appealing party in a forum of competent
jurisdiction, within fifty (50) days after Substantial Completion (unless otherwise agreed in writing by
Developer and Contractor), to exercise such rights or remedies as the appealing party may have with
respect to such Claim in accordance with applicable Laws and Regulations.
(E) If Engineer is authorized by Developer to render a formal decision and does not render a formal decision
in writing within thirty (30) days after receipt of the Claim and the response of the opposing party, if any,
a decision denying the Claim in its entirety will be deemed to have been issued 31 days after receipt of
the Claim and the response of the opposing party, if any.
(F) No Claim for an adjustment in Contract Price or Contract Dates will be valid if not submitted in accordance
with this Section 10.05.
ARTICLE 11. COST OF WORK; CASH ALLOWANCES; UNIT PRICE WORK
11.01 Cost of the Work
(A) Costs Included: The term “Cost of the Work” means the sum of the costs, except those excluded in
Section 11.01(B), that are necessarily incurred and paid by Contractor in the proper performance of the
specified Work to be performed on a Cost of the Work basis. When the value of any Work covered by a
Change Order or when a Claim for an adjustment in Contract Price is determined on the basis of Cost of
the Work, the costs to be reimbursed to Contractor will be only those additional (or saved) or incremental
costs required (or avoided) because of the change in the Work or because of the event giving rise to the
Claim. Except as otherwise may be agreed to in writing by Developer, such costs will be in amounts no
higher than those prevailing in the locality of the Project, will include only the following items, and will
not include any of the costs itemized in Section 11.01(B). For this Article 11, the phrase “the Work” means
the portion of the Work to be performed on a Cost of the Work basis.
(1) Payroll costs for employees in the direct employ of Contractor in the performance of the Work under
schedules of job classifications agreed upon by Developer and Contractor. Such employees will include
General Conditions Meridian Town Center
Page 80 of 114 Offsite Improvements - Phase 3
without limitation superintendents, forepersons, and other personnel employed full time at the Site.
Payroll costs for employees not employed full time on the Work will be apportioned on the basis of
their time spent on the Work. Payroll costs will include salaries and wages plus the cost of fringe
benefits, which will include social security contributions, unemployment, excise, and payroll taxes,
workers’ compensation, health and retirement benefits, bonuses, sick leave, vacation and holiday pay
applicable thereto. The expenses of performing Work outside of regular working hours, on Saturday,
Sunday, or legal holidays, will be included in the above to the extent authorized by Developer.
(2) Cost of all materials and equipment furnished and incorporated in the Work, including costs of
transportation and storage thereof, and Suppliers’ field services required in connection therewith. All
cash discounts will accrue to Contractor unless Developer deposits funds with Contractor with which
to make payments, in which case the cash discounts will accrue to Developer. All trade discounts,
rebates and refunds and returns from sale of surplus materials and equipment will accrue to
Developer, and Contractor will make provisions so that they may be obtained.
(3) Payments made by Contractor to Subcontractors for Work performed by Subcontractors. Contractor
will use its best efforts to secure Work to be performed by Subcontractors for a price and on terms
not greater than those prevailing at the Project. If requested by Developer, Contractor will obtain
competitive bids from subcontractors acceptable to Developer and Contractor and will deliver such
bids to Developer, who will then determine, with the advice of Engineer, which bids, if any, will be
acceptable. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the
Work plus a fee, the Subcontractor’s Cost of the Work and fee will be determined in the same manner
as Contractor’s Cost of the Work and fee as provided in this Section 11.01.
(4) Costs of special consultants (including but not limited to engineers, architects, testing laboratories,
surveyors) employed for services specifically related to the Work.
(5) Supplemental costs including the following:
a) The proportion of necessary transportation, travel, and subsistence expenses of Contractor’s
employees incurred in discharge of duties connected with the Work.
b) Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery,
appliances, office, and temporary facilities at the Site, and hand tools not owned by the workers,
which are consumed in the performance of the Work, and cost, less market value, of such items
used but not consumed which remain the property of Contractor.
c) Rentals of all construction equipment and machinery, and the parts thereof whether rented from
Contractor or others in accordance with rental agreements approved by Developer with the advice
of Engineer, and the costs of transportation, loading, unloading, assembly, dismantling, and
removal thereof. All such costs will be in accordance with the terms of said rental agreements. The
rental of any such equipment, machinery, or party will cease when the use thereof is no longer
necessary for the Work.
d) Sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is
liable, imposed by Laws and Regulations.
e) Deposits lost for causes other than negligence of Contractor, any Subcontractor, or anyone directly
or indirectly employed by any of them or for whose acts any of them may be liable, and royalty
payments and fees for permits and licenses.
f) Losses and damages (and related expenses) caused by damage to the Work, not compensated by
insurance or otherwise, sustained by Contractor in connection with the performance of the Work
(except losses and damages within the deductible amounts of property insurance established in
accordance with Section 5.06(C)) provided such losses and damages have resulted from causes
other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly
employed by any of them or for whose acts any of them may be liable. Such losses will include
settlements, made with the written consent and approval of Developer. No such, damages, and
expenses will be included in the Cost of the Work for the purpose of determining Contractor’s fee.
General Conditions Meridian Town Center
Page 81 of 114 Offsite Improvements - Phase 3
g) The cost of utilities, fuel, and sanitary facilities at the Site.
h) Minor expenses such as long distance telephone calls, telephone service at the Site, expressage,
and similar petty cash items in connection with the Work.
i) The cost of premiums for all Bonds and insurance Contractor is required by the Contract
Documents to purchase and maintain for the Work.
All Costs of the Work must be reasonable, customary and necessarily incurred by Contractor in the
proper performance of the covered Work. Contractor bears the burden of properly documenting and
establishing the reasonableness and appropriateness of any cost that Contractor claims to be part of
the Cost of the Work. Where any cost is subject to Developer’s approval, Contractor must obtain
Developer’s specific approval of the cost prior to incurring the cost. Costs of the Work must be
separately itemized and separately supported in Contractor’s invoices, and all Costs for any Change
Order, Work Change Directive or Claim must be separately itemized and supported. Contractor will
exercise controls as may be necessary for proper financial management of the Cost of the Work in
accordance with Contractor’s duties under the Agreement and best industry practices. Contractor will
contemporaneously maintain full, detailed and well-organized accounts (in accordance with generally
accepted accounting principles and best practices consistently applied) and records related to the Cost
of the Work such that Developer can easily identify each cost included in the Cost of the Work and the
documents and information in the records that substantiate the cost. Contractor will afford Developer
with full access to (during normal business hours), and will permit Developer to audit and copy,
Contractor's records and accounts relating to any Work performed on a Cost of the Work basis.
Contractor will preserve these records for a period of five (5) years after Final Payment or termination
of this Agreement or for any longer period as may be required by law. Contractor will not be entitled
to any reimbursement for expenses incurred by Contractor for access, audit and copying of
Contractor's records, as Contractor agrees as part of its duties and obligations under this Agreement
to keep its accounts and records in a format and condition that allows them to be easily and
conveniently inspected, audited and copied by Developer without delay and without causing
Contractor to incur material expense.
(B) Costs Excluded: The term Cost of the Work will not include any of the following items:
(6) Payroll costs and other compensation of Contractor’s officers, executives, principals (of partnerships
and sole proprietorships), general managers, engineers, architects, estimators, attorneys, auditors,
accountants, purchasing and contracting agents, expediters, timekeepers, clerks, and other personnel
employed by Contractor, whether at the Site or in Contractor’s principal or branch office for general
administration of the Work and not specifically included in the agreed upon schedule of job
classifications referred to in Section 11.01(A)(1) or specifically covered by Section 11.01(A)(4), all of
which are to be considered administrative costs covered by Contractor’s fee.
(7) Expenses of Contractor’s principal and branch offices other than Contractor’s office at the Site.
(8) Any part of Contractor’s capital expenses, including interest on Contractor’s capital employed for the
Work and charges against Contractor for delinquent payments.
(9) Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly
employed by any of them or for whose acts any of them may be liable, including but not limited to,
the correction of defective Work, disposal of materials or equipment wrongly supplied, and making
good any damage to property.
(10) Other overhead or general expense costs of any kind and the costs of any item not specifically and
expressly included in Sections 11.01(A) and 11.01(B).
(C) Contractor’s Fee: When the value of any Work covered by a Change Order or when a Claim for an
adjustment in Contract Price is determined on the basis of Cost of the Work, Contractor’s fee will be
determined as set forth in Section 12.01(C).
General Conditions Meridian Town Center
Page 82 of 114 Offsite Improvements - Phase 3
(D) Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to
Sections 11.01(A) and 11.01(B), Contractor will establish and maintain records thereof in accordance with
generally accepted accounting practices and submit in a form acceptable to Engineer an itemized cost
breakdown together with supporting data.
11.02 Cash Allowances
(A) It is understood that Contractor has included in the Contract Price all allowances so named in the Contract
Documents and will cause the Work so covered to be performed for such sums as may be acceptable to
Developer, Engineer. Contractor agrees that:
(1) the allowances include the costs to Contractor (less any applicable trade discounts) of materials and
equipment required by the allowances to be delivered at the Site, and all applicable taxes; and
(2) Contractor’s costs for unloading and handling on the Site, labor, installation costs, overhead, profit,
and other expenses contemplated for the allowances have been included in the Contract Price and
not in the allowances, and no demand for additional payment on account of any of the foregoing
will be valid.
(B) Prior to final payment, an appropriate Change Order will be issued as recommended by Engineer to reflect
actual amounts due Contractor on account of Work covered by allowances, and the Contract Price will be
correspondingly adjusted.
11.03 Unit Price Work
(A) When any Work in by a Change Order is covered by unit prices, or when a Claim for an adjustment in
Contract Price is determined on the basis of unit prices, the compensation to Contractor for such Work
will be only the applicable unit prices (unless Developer and Contractor agree otherwise). Determinations
of the actual quantities and classifications of such Unit Price Work performed by Contractor will be made
by Engineer subject to the provisions of Section 9.08.
(B) Each unit price will be deemed to include an amount considered by Contractor to be adequate to cover
Contractor’s overhead and profit for each separately identified item.
ARTICLE 12. CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT DATES
12.01 Change of Contract Price
(A) The Contract Price may only be changed by a Change Order or by a Written Amendment. Any Claim for
an adjustment in the Contract Price will be based on written notice submitted by the party making the
claim to the Engineer and the other party to the Contract in accordance with the provisions of
Section 10.05.
(B) The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price
will be determined as follows:
(1) where the Work involved is covered by unit prices contained in the Contract Documents, by
application of such unit prices to the quantities of the items involved (subject to the provisions of
Section 11.03). Unit prices breakdowns identified on the Bid are unit prices for purposes of the
Contract Documents; or
(2) where the Work involved is not covered by unit prices contained in the Contract Documents, by a
mutually agreed lump sum (which may include an allowance for overhead and profit not necessarily
in accordance with Section 12.01(C)(2)); or
(3) where the Work involved is not covered by unit prices contained in the Contract Documents and
agreement to a lump sum is not reached under Section 12.01(B)(2), on the basis of the Cost of the
Work (determined as provided in Section 11.01) plus a Contractor’s fee for overhead and profit
(determined as provided in Section 12.01(C)).
(C) Contractor’s Fee: The Contractor’s fee for overhead and profit will be determined as follows:
(1) a mutually acceptable fixed fee; or
General Conditions Meridian Town Center
Page 83 of 114 Offsite Improvements - Phase 3
(2) if a fixed fee is not agreed upon, then a fee based on the following percentages of the various portions
of the Cost of the Work;
a) for costs incurred under Sections 11.01(A)(1) and 11.01(A)(2), Contractor’s fee will be fifteen
percent (15%);
b) for costs incurred under Section 11.01(A)(3), Contractor’s fee will be five percent (5%);
c) where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no
fixed fee is agreed upon, the intent of Section 12.01(C)(2)a) is that the Subcontractor who actually
performs the Work, at whatever tier, will be paid a fee of fifteen percent (15%) of the costs
incurred by such Subcontractor under Sections 11.01(A)(1) and 11.01(A)(2) and that any higher tier
Subcontractor and Contractor will each be paid a fee of five percent (5%) of the amount paid to
the next lower tier Subcontractor;
d) no fee will be payable on the basis of costs itemized under Sections 11.01(A)(4), 11.01(A)(5) and
11.01(B);
e) the amount of credit to be allowed by Contractor to Developer for any change which results in a
net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in
Contractor’s fee by an amount equal to five percent of such net decrease; and
f) when both additions and credits are involved in any one change, the adjustment in Contractor’s
fee will be computed on the basis of the net change in accordance with Sections 12.01(C)(2)a)
through 12.01(C)(2)e), inclusive.
12.02 Change of Contract Dates
(A) The Contract Dates may only be changed by a Change Order or by a Written Amendment. Any Claim for
an adjustment in the Contract Dates will be based on written notice submitted by the party making the
claim to Engineer and the other party to the Contract in accordance with the provisions of Section 10.05.
(B) Any adjustment of the Contract Dates covered by a Change Order or of any Claim for an adjustment in
the Contract Dates will be determined in accordance with the provisions of this Article 12.
12.03 Delays Beyond Contractor’s Control
(A) Where Contractor is prevented from completing any part of the Work by the Contract Dates by Force
Majeure, the Contract Dates will be extended in an amount equal to the time lost due to such delay if a
Claim is made therefore as provided in Section 12.02(A). As a condition precedent to making any Claim
for delay, Contractor will specifically notify Developer of (a) the specific events or occurrences that
Contractor claims to be causing the prevention or delay of Contractor’s performance, (b) if known to
Contractor, the party or parties that Contractor believes to be responsible for such events or occurrences,
and (c) if known to Contractor, what actions Developer can take to avoid or overcome such events or
occurrences and mitigate the impacts therefrom. Contractor will not be entitled to make any Claim for
any impacts on Contractor’s performance occurring prior to the delivery of the foregoing notice to
Developer. Upon receipt of an impact notice hereunder from Contractor, Developer will promptly use
commercially reasonable efforts to cure impacts that are Developer’s responsibility, will keep Contractor
reasonably informed of such efforts and coordinate such efforts with Contractor.
(B) “Force Majeure” will mean acts, events or occurrences beyond the reasonable control of Contractor which
delay or otherwise prevent Contractor from timely performing its obligations under this Contract (other
than an obligation to pay money), including fires, floods, epidemics, earthquakes and other similar acts of
God; quarantine, blockade, war, insurrection or civil strife; strikes or labor disputes for a regional or
national level that does not involve labor employed by Contractor, any Subcontractor or any sub-
subcontractor; sabotage; refusal or failure of governmental authorities to grant necessary permits and
approvals for the Work through no fault of Contractor; unreasonably delays or interference caused by any
default of Developer’s obligations under the Contract Documents by Engineer (but first subject to notice
and cure periods identified in Section 12.06(B)); differing subsurface or physical conditions or
underground facilities (see Article 4); and other similar acts, events or occurrences, but only to the extent
such acts, events or occurrences are beyond the reasonable control of Contractor despite its prudent and
General Conditions Meridian Town Center
Page 84 of 114 Offsite Improvements - Phase 3
diligent efforts to prevent, avoid, delay or mitigate such acts, events or occurrences. Force Majeure does
not include acts, events or occurrences that (1) are the result of willful or negligent actions or inactions of
either Party; (2) do not have a real, quantifiable and adverse impact on the performance of Contractor;
or (3) would not ordinarily cause the same adverse impact on the performance of a diligent contractor
performing work of the same nature of the affected Work. Force Majeure does not include seasonal
adverse weather (e.g., extreme cold, snow, ice and other winter conditions), as the effects of seasonal
adverse weather have already be included in setting of the Contract Dates.
12.04 Delays Within Contractor’s Control
(A) The Contract Dates will not be extended due to delays within the control of Contractor or that are not
due to Force Majeure. Delays attributable to and within the control of a Subcontractor or Supplier will be
deemed to be delays within the control of Contractor.
12.05 Delays Beyond Developer’s and Contractor’s Control
(A) Where Contractor is prevented from completing any part of the Work within the Contract Dates due to
Force Majeure, an extension of the Contract Dates in an amount equal to the time lost due to such delay
will be Contractor’s sole and exclusive remedy for such delay; provided, however, the Contract Dates
include an allowance for thirty (30) days of delay on the critical path caused by Force Majeure, and
Contractor will not be entitled to any adjustment of the Contract Dates until the thirty (30) day allowance
has been exhausted by prior delays on the critical path.
12.06 Delay Damages
(A) In no event will Developer, Engineer be liable to Contractor, any Subcontractor, any Supplier, or any other
person or organization, or to any surety for or employee or agent of any of them, for damages arising out
of or resulting from:
(1) delays caused by or within the control of Contractor; or
(2) delays beyond the control of Developer, including but not limited to fires, floods, epidemics, extreme
weather conditions, acts of God, or acts or neglect by utility owners or other contractors performing
other work as contemplated by Article 7.
(B) Nothing in this Section 12.06 bars a change in Contract Price pursuant to this Article 12 to compensate
Contractor for Costs of the Work reasonably incurred due to unreasonable delay or unreasonable
interference directly attributable to actions or inactions of Developer, Engineer; provided, however,
Contractor may not make a Claim for any impacts on Contractor’s performance (1) that Contractor could
not reasonably have been expected to avoid, overcome or mitigate through the exercise of due foresight
and reasonable due diligence or (b) that occur prior to a five business day cure period after Developer’s
receipt of Contractor’s notice of the delay or interference (which notice must specify the cause, nature
and impact of the delay or interference).
ARTICLE 13. TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK
13.01 Notice of Defects
(A) Prompt notice of all defective Work of which Developer, Engineer has actual knowledge will be given to
Contractor. All defective Work may be rejected, corrected, or accepted as provided in this Article 13.
13.02 Access to Work
(A) Developer, Engineer, Engineer’s Consultants, Agency, Agency’s representatives, other representatives
and personnel of Developer, independent testing laboratories, and governmental agencies with
jurisdiction or interest will have access to the Site and the Work at reasonable times for their observation,
inspecting, and testing. Contractor will provide them proper and safe conditions for such access and
advise them of Contractor’s Site safety procedures and programs so that they may comply therewith as
applicable.
13.03 Tests and Inspections
General Conditions Meridian Town Center
Page 85 of 114 Offsite Improvements - Phase 3
(A) Contractor will give Engineer timely notice of readiness of the Work for all required inspections, tests, or
approvals and will cooperate with inspection and testing personnel to facilitate required inspections or
tests.
(B) Developer will employ and pay for the service of an independent testing laboratory to perform all
inspections, tests, or approvals required by the Contract Documents except:
(1) for inspections, tests, or approvals covered by Sections 13.03(C) and 13.03(D) below;
(2) that costs incurred in connection with tests or inspections conducted pursuant to Section 13.04(B) will
be paid as provided in said Section 13.04(B); and
(3) as otherwise specifically provided in the Contract Documents.
(C) If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) specifically
to be inspected, tested, or approved by an employee or other representative of such public body,
Contractor will assume full responsibility or arranging and obtaining such inspections, tests, or approvals,
pay all costs in connection therewith, and furnish Engineer the required certificates of inspection or
approval.
(D) Contractor will be responsible for arranging and obtaining and will pay all costs in connection with any
inspections, test, or approvals required for acceptance (by Developer, Engineer) of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such
inspections, tests, or approvals will be performed by organizations acceptable to Developer, Engineer.
(E) If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor
without written concurrence of Engineer, it must, if requested by Engineer, be uncovered for observation.
(F) Uncovering Work as provided in Section 13.03(E) will be at Contractor’s expense unless Contractor has
given Engineer timely notice of Contractor’s intention to cover the same and Engineer has not acted with
reasonable promptness in response to such notice.
13.04 Uncovering Work
(A) If any Work is covered contrary to the written request of Engineer, it must, if requested by Engineer, be
uncovered for Engineer’s and Engineer’s observation and replaced at Contractor’s expense.
(B) If Engineer considers it necessary or advisable that covered Work be observed by Engineer or inspected
or tested by others, Contractor, at the request of Engineer, will uncover, expose, or otherwise make
available for observation, inspection, or testing as Engineer may require, that portion of the Work in
question, furnishing all necessary labor, material, and equipment. If it is found that such Work is defective,
Contractor will pay all Claims, costs, losses, and damages (including but not limited to all fees and charges
of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to such uncovering, exposure, observation, inspection, and
testing, and of satisfactory replacement or reconstruction (including but not limited to all costs of repair
or replacement of work of others); and Developer will be entitled to an appropriate decrease in the
Contract Price. If the parties are unable to agree as to the amount thereof, Developer may make a Claim
therefore as provided in Section 10.05. If, however, such Work is not found to be defective, Contractor
will be allowed an increase in the Contract Price or an extension of the Contract Dates, or both, directly
attributable to such uncovering, exposure, observation, inspection, testing, replacement, and
reconstruction. If the parties are unable to agree as to the amount or extent thereof, Contractor may
make a Claim therefore as provided in Section 10.05.
13.05 Developer May Stop the Work
(A) If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or
equipment, or fails to perform the Work in such a way that the completed Work will conform to the
Contract Documents, Developer may order Contractor to stop the Work, or any portion thereof, until the
cause for such order has been eliminated; however, this right of Developer to stop the Work will not give
rise to any duty on the part of Developer to exercise this right for the benefit of Contractor, any
General Conditions Meridian Town Center
Page 86 of 114 Offsite Improvements - Phase 3
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any
of them.
13.06 Correction or Removal of Defective Work
(A) Contractor will correct all defective Work, whether or not fabricated, installed, or completed, or, if the
Work has been rejected by Engineer, remove it from the Project and replace it with Work that is not
defective. Contractor will pay all Claims, costs, losses, and damages (including but not limited to all fees
and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or
other dispute resolution costs) arising out of or relating to such correction or removal (including but not
limited to all costs of repair or replacement of work of others).
13.07 Correction Period
(A) If within three (3) years after the date of Substantial Completion or such longer period of time as may be
prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the
Contract Documents or by any specific provision of the Contract Documents, any Work is found to be
defective, or if the repair of any damages to the land or areas made available for Contractor’s use by
Developer or permitted by Laws and Regulations as contemplated in Section 6.11(A) is found to be
defective, Contractor will promptly, without cost to Developer and in accordance with Developer’s written
instructions: (i) repair such defective land or areas, or (ii) correct such defective Work or, if the defective
Work has been rejected by Developer, remove it from the Project and replace it with Work that is not
defective, and (iii) satisfactorily correct or repair or remove and replace any damage to other Work, to
the work of others or other land or areas resulting therefrom. If Contractor does not promptly comply
with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or
damage, Developer may have the defective Work corrected or repaired or may have the rejected Work
removed and replaced, and all Claims, costs, losses, and damages (including but not limited to all fees and
charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other
dispute resolution costs) arising out of or relating to such correction or repair or such removal and
replacement (including but not limited to all costs of repair or replacement of work of others) will be paid
by Contractor.
(B) In special circumstances where a particular item of equipment is placed in continuous service before
Substantial Completion of all the Work, the correction period for that item may start to run from an earlier
date if so provided in the Specifications or by Written Amendment.
(C) Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed
and replaced under this Section 13.07 within the Correction Period, the Correction Period with respect to
such Work will be extended for an additional period of one (1) year after such correction or removal and
replacement has been satisfactorily completed.
(D) Contractor’s obligations under this Section 13.07 are in addition to any other obligation or warranty. The
provisions of this Section 13.07 will not be constructed as a substitute for or a waiver of the provisions of
any applicable statute of limitation or repose.
13.08 Acceptance of Defective Work
(A) If, instead of requiring correction or removal and replacement of defective Work, Developer prefers to
accept it, Developer may do so. Contractor will pay all Claims, costs, losses, and damages (including but
not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) attributable to Developer’s evaluation of and
determination to accept such defective Work (such costs to be approved by Engineer as to
reasonableness) and the diminished value of the Work to the extent not otherwise paid by Contractor
pursuant to this sentence. If any such acceptance occurs prior to Engineer’s and Engineer’s
recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in
the Contract Documents with respect to the Work, and Developer will be entitled to an appropriate
decrease in the Contract Price, reflecting the diminished value of Work so accepted. If the parties are
unable to agree as to the amount thereof, Developer may make a Claim therefore as provided in
General Conditions Meridian Town Center
Page 87 of 114 Offsite Improvements - Phase 3
Section 10.05. If the acceptance occurs after such recommendation, an appropriate amount will be paid
by Contractor to Developer.
13.09 Developer May Correct Defective Work
(A) If Contractor fails within a reasonable time after written notice to correct defective Work or to remove
and replace rejected Work as required by Engineer in accordance with Section 13.06(A), or if Contractor
fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply
with any other provision of the Contract Documents, Developer may, after seven days written notice to
Contractor, correct and remedy any such deficiency.
(B) In exercising the rights and remedies under this Section, Developer will proceed expeditiously. In
connection with such corrective and remedial action, Developer may exclude Contractor from all or part
of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto,
take possession of Contractor’s tools, appliances, construction equipment and machinery at the Site, and
incorporate in the Work all materials and equipment stored at the Site or for which Developer has paid
Contractor but which are stored elsewhere. Contractor will allow Developer, Engineer, agents and
employees, Developer’s other contractors, and Engineer and Engineer’s Consultants access to the Site to
enable Developer to exercise the rights and remedies under this Section.
(C) All Claims, costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs)
incurred or sustained by Developer in exercising the rights and remedies under this Section 13.09 will be
charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in
the Contract Documents with respect to the Work; and Developer will be entitled to an appropriate
decrease in the Contract Price. If the parties are unable to agree as to the amount of the adjustment,
Developer may make a Claim therefore as provided in Section 10.05. Such claims, costs, losses and
damages will include but not be limited to all costs of repair, or replacement of work of others destroyed
or damaged by correction, removal, or replacement of Contractor’s defective Work.
(D) Contractor will not be allowed an extension of the Contract Dates because of any delay in the performance
of the Work attributable to the exercise by Developer of Developer’s rights and remedies under this
Section 13.09.
ARTICLE 14. PAYMENTS TO CONTRACTOR AND COMPLETION
14.01 Schedule of Values
The schedule of values established as provided in Section 2.070 will serve as the basis for progress
payments and will be incorporated into a form of Application for Payment acceptable to Engineer.
Progress payments on account of Unit Price Work will be based on the number of units completed.
14.02 Progress Payments
(A) Applications for Payments
(1) On or about the first business day of each month, Contractor will submit to Engineer for review an
Application for Payment filled out and signed by Contractor covering the Work completed as of the
date of the Application and accompanied by such supporting documentation as is required by the
Contract Documents, including conditional lien releases in the form approved by Developer for all
payments requested by Contractor, Subcontractor and any supplier of materials, equipment or
services. Unless otherwise approved by Developer, such lien releases will be in the form identified in
Section 40 of the Supplementary Conditions. If payment is requested on the basis of materials and
equipment not incorporated in the Work but delivered and suitably stored at the Site or at another
location agreed to in writing, the Application for Payment will also be accompanied by a bill of sale,
invoice, or other documentation warranting that Developer has received the materials and equipment
free and clear of all Liens and evidence that the materials and equipment are covered by appropriate
property insurance and other arrangements to protect Developer’s interest therein, all of which must
be satisfactory to Developer.
General Conditions Meridian Town Center
Page 88 of 114 Offsite Improvements - Phase 3
(2) Contractor’s submission of an Application for Payment will be Contractor’s express representation and
warranty to Developer, Engineer that, except as conspicuously stated in the application for payment
in sufficient detail to be a meaningful disclosure: (a) Contractor properly paid all Subcontractors and
anyone who provided labor, materials, equipment or services relating to all Work applicable to all
prior payments from Developer; (b) no later than payment of the application by Developer, all Work
covered by the application will be free and clear of liens, claims, security interests or encumbrances
in favor of Contractor, Subcontractors or other persons or entities making a claim by reason of having
provided labor, materials, equipment or services relating to the Work (except with respect to
retainage held by Developer); (c) there have been no changes to the Work except pursuant to
executed Change Orders and Change Directives; and (d) to the best of Contractor’s knowledge,
information and belief after reasonable inquiry, if any, based on industry standards for contractors
engaged in the construction of projects of similar scope and complexity: (i) the Work has progressed
in accordance with the Project Schedule; (ii) Contractor is not in default of its obligations under this
Agreement, and no event or circumstances has occurred that, but for a notice or the passage of time,
would be a Contractor default; (iii) neither Contractor nor any Subcontractor is in material default of
any Subcontract; and (iv) all of Contractor’s representations and warranties remain true and correct
in all material respects. Contractor agrees that Developer, Engineer will by relying on the true and
accuracy of Contractor’s representations and warranties herein in reviewing and paying Contractor’s
applications for payment. Contractor will promptly notify Developer if Contractor discovers that any
representation or warranty was not true and correct in all material respects at the time made.
(3) Beginning with the second Application for Payment, each Application will include (a) an affidavit of
Contractor stating that all previous progress payments received on account of the Work have been
applied on account to discharge Contractor’s legitimate obligations associated with prior Applications
for Payment, and (b) unconditional lien releases in the form approved by Developer for all previous
progress payments by Contractor, Subcontractors and any supplier of materials, equipment or
services.
(4) The amount of retainage with respect to progress payments will be as stipulated in the Agreement.
(B) Review of Applications
(1) Engineer will, within five (5) days after receipt of each Application for Payment, either indicate in
writing a recommendation of payment and present the Application to Developer or return the
Application to Contractor indicating in writing Engineer’s reasons for refusing to recommend payment.
In the latter case, Contractor will immediately make the necessary corrections and resubmit the
Application, it being understood that Developer must have an accurate, complete and approved
Application for Payment immediately thereafter in order to make payment on the date indicated in
Section 14.02(C). Contractor’s acknowledges and agrees that its failure to deliver an accurate and
complete Application for Payment to Engineer each month may result in the payment thereon being
delayed for one (1) month.
(2) Engineer’s and Engineer’s recommendation of any payment requested in an Application for Payment
will constitute a representation by Engineer to Developer, based on Engineer’s and Engineer’s
observations on the Site of the executed Work as an experienced and qualified design professional
and on Engineer’s and Engineer’s review of the Application for Payment and the accompanying data
and schedules, that to the best of their knowledge, information and belief:
a) The Work has progressed to the point indicated;
b) The quality of the Work is generally in accordance with the Contract Documents (subject to an
evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the
results of any subsequent tests called for in the Contract Documents, to a final determination of
quantities and classifications for Unit Price Work under Section 9.08, and to any other
qualifications stated in the recommendation); and
c) The conditions precedent to Contractor’s being entitled to such payment appear to have been
fulfilled in so far as it is Engineer’s and Engineer’s responsibility to observe the Work.
General Conditions Meridian Town Center
Page 89 of 114 Offsite Improvements - Phase 3
(3) By recommending any such payment, neither Engineer nor Engineer will thereby be deemed to have
represented that: (i) inspections made to check the quality or the quantity of the Work as it has been
performed have been exhaustive, extended to every aspect of the Work in progress, or involved
detailed inspections of the Work beyond the responsibilities specifically assigned to Engineer in the
Contract Documents; or (ii) that there may not be other matters or issues between the parties that
might entitle Contractor to be paid additionally by Developer or entitle Developer to withhold
payment to Contractor.
(4) Neither any review of Contractor’s Work for the purposes of recommending payments nor any
recommendation of any payment, including final payment, will impose responsibility on Engineer to
supervise, direct, or control the Work or for the means, methods, techniques, sequences, or
procedures of construction, or the safety precautions and programs incident thereto, or for
Contractor’s failure to comply with Laws and Regulations applicable to Contractor’s performance of
the Work. Additionally, any review or recommendation will not impose responsibility on Engineer to
make any examination to ascertain how or for what purposes Contractor has used the moneys paid
on account of the Contract Price, or to determine that title to any of the Work, materials, or equipment
has passed to Developer free and clear of any Liens.
(5) Engineer may refuse to recommend the whole or any part of any payment if, in their opinion, it would
be incorrect to make the representations to Developer referred to in Section 14.02(B)(2). Engineer
may also refuse to recommend any such payment or, because of subsequently discovered evidence
or the results of subsequent inspections or tests, revise or revoke any such payment recommendation
previously made, to such extent as may be necessary in their opinion to protect Developer from loss
because;
a) The Work is defective, or completed Work has been damaged, requiring correction or
replacement;
b) The Contract Price has been reduced by Written Amendment or Change Orders;
c) Developer has been required to correct defective Work or complete Work in accordance with
Section 13.09; or
d) Engineer has actual knowledge of the occurrence of any of the events enumerated in
Section 15.02(A).
(C) Payment Becomes Due
(1) Provided that Contractor submits an accurate and complete Application for Payment as required by
this Article 14, the amount recommended by Engineer will (subject to the provisions of
Section 14.02(D)) become due, and when due will be paid by Developer to Contractor, thirty (30) days
following the receipt of the Application for Payment.
(D) Reduction in Payment
(1) Developer may refuse to make payment of the full amount recommended by Engineer because;
a) Claims have been threatened or made against Developer on account of Contractor’s performance
or furnishing of the Work;
b) Liens have been threatened or filed in connection with the Work, except where Contractor has
delivered a specific Bond satisfactory to Developer to secure the satisfaction and discharge of such
Liens;
c) There are other items entitling Developer to a set-off against the amount recommended; or
d) Developer has actual knowledge of the occurrence of any of the events enumerated in
Sections 14.02(B)(5)a) through 14.02(B)(5)c) or Section 15.02(A).
(2) If Developer refuses to make payment of the full amount recommended by Engineer, Developer must
give Contractor prompt written notice (with a copy to Engineer) stating the reasons for such action
and promptly pay Contractor any amount remaining after deduction of the amount so withheld.
General Conditions Meridian Town Center
Page 90 of 114 Offsite Improvements - Phase 3
Developer will promptly pay Contractor the amount so withheld, or any adjustment thereto agreed to
by Developer and Contractor, when Contractor corrects to Developer’s satisfaction the reasons for
such action.
(3) If it is subsequently determined that Developer’s refusal of payment was not justified, the amount
wrongfully withheld will be treated as an amount due as determined by Section 14.02(C)(1).
14.03 Contractor’s Warranty of Title
(A) Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the Project or not, will pass to Developer not later than
the time of payment free and clear of all Liens.
14.04 Substantial Completion
(A) When Contractor considers the entire Work ready for its intended use Contractor will notify Developer,
Engineer in writing that the entire Work is substantially complete (except for items specifically listed by
Contractor as incomplete) and request that Engineer issue a certificate of Substantial Completion.
Promptly thereafter, Developer, ITD, Contractor, Engineer will make a pre-final inspection of the Work to
determine the status of completion. If Engineer do not consider the Work substantially complete,
Engineer will so notify Contractor in writing giving the reasons therefore. If Engineer considers the Work
substantially complete, Engineer will prepare and deliver to Developer a tentative certificate of
Substantial Completion which will fix the date of Substantial Completion. There will be attached to the
certificate a tentative list of items to be completed or corrected before final payment. Developer will have
seven (7) days after receipt of the tentative certificate during which to make written objection to Engineer
as to any provisions of the certificate or attached list. If, after considering such objections, Engineer
concludes that the Work is not substantially complete, then Engineer will within 14 days after submission
of tentative certificate to Developer notify Contractor in writing, stating the reasons therefore. If, after
consideration of Developer’s objections, Engineer considers the Work substantially complete, the
Engineer will within said 14 days execute and deliver to Developer and Contractor a definitive certificate
of Substantial Completion (with a revised tentative list of items to be completed or corrected) reflecting
such changes from the tentative certificate as Engineer believe justified after consideration of any
objections from Developer. At the time of delivery of the tentative certificate of Substantial Completion,
Engineer will deliver to Developer and Contractor a written recommendation as to division of
responsibilities pending final payment between Developer and Contractor with respect to security,
operations, safety, and protection of the Work, maintenance, heat, utilities, insurance, and warranties
and guarantees. Unless Developer and Contractor agree otherwise in writing and so inform Engineer in
writing prior to the issuing of the definitive certificate of Substantial Completion, Engineer’s and
Engineer’s aforesaid recommendation will be binding on Developer and Contractor until final payment.
(B) Developer will have the right to exclude Contractor from the Site after the date of Substantial Completion,
but Developer will allow Contractor reasonable access to complete or correct items on the tentative list.
14.05 Partial Utilization
(A) Contractor acknowledges that certain portions of the Work will be subject partial use prior to Substantial
Completion as set forth in the Contract Documents. Contractor agrees that the Work includes the
coordination of such partial use with the Work in a manner that allows such partial use to be reasonably
performed concurrently with the Work. Such coordination efforts will include, but not be limited to, the
meeting, scheduling, coordination and cooperation obligations set forth in the Contract Documents.
(B) Except for partial use identified in Section 14.05(A), use by Developer at Developer’s option of any
substantially completed part of the Work that can be used by Developer for its intended purpose without
significant interference with Contractor’s performance of the remainder of the Work, may be
accomplished subject to the following conditions:
(1) Developer at any time may request Contractor in writing to permit Developer to use any such part of
the Work which Developer believes to be ready for its intended use and substantially complete. If
Contractor agrees that such part of the Work is substantially complete, Contractor will certify to
General Conditions Meridian Town Center
Page 91 of 114 Offsite Improvements - Phase 3
Developer, Engineer that such part of the Work is substantially complete and request Engineer to issue
a certificate of Substantial Completion for the part of the Work. Contractor at any time may notify
Developer, Engineer in writing that Contractor considers any such part of the Work ready for its
intended use and substantially complete and request Engineer to issue a certificate of substantial
Completion for that part of the Work. Within a reasonable time after either such request, Developer,
Contractor, Engineer will make an inspection of that part of the Work to be substantially complete,
Engineer will make an inspection of that part of the Work to determine its status of completion. If
Engineer do not consider that part of the Work to be substantially complete, then Engineer will notify
Developer and Contractor in writing giving the reasons therefore. If Engineer considers that part of
the Work to be substantially complete, the provisions of Section 14.04 will apply with respect to
certification of Substantial Completion of that part of the Work and the division of responsibility in
respect thereof and access thereto.
14.06 Final Inspection
Upon written notice from Contractor that the entire Work or an agreed portion thereof is complete,
Engineer will promptly make a final inspection with Developer, ITD and Contractor and will notify
Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or
defective. Contractor will immediately take such measures as are necessary to complete such Work or
remedy such deficiencies.
14.07 Final Payment
(A) Application for Payment
(1) After Contractor has, in the opinion of Engineer, satisfactorily completed all corrections identified
during the final inspection and has delivered, in accordance with the Contract Documents, all
maintenance and operating instructions, schedules, guarantees, Bonds, certificates or other evidence
of insurance certificates of inspection, marked-up record documents, Contractor may make
application for final payment following the procedure for progress payments.
(2) The final Application for Payment will be accompanied (except as previously delivered) by: (i) all
documentation called for in the Contract Documents, including but not limited to the evidence of
insurance required by Subsection 5.04(B)(7); (ii) consent of the surety, if any, to final payment; and
(iii) complete and legally effective releases or waivers (which will be in the final forms identified in
“Lien Release Forms” section of the Supplementary Conditions or other form satisfactory to
Developer) of all Lien rights arising out of or Liens filed in connection with the Work.
(3) In lieu of the releases or waivers of Liens specified in Section 14.07(A)(2) and as approved by
Developer, Contractor may furnish receipts or releases in full and an affidavit of Contractor that: (i)
the conditional releases and receipts include all labor, services, material, and equipment for which a
Lien could be filed; and (ii) all payrolls, material and equipment bills, and other indebtedness
connected with the Work for which Developer or Developer’s property might in any way be
responsible have been paid or otherwise satisfied. If any Subcontractor or Supplier fails to furnish such
a release or receipt in full, Contractor may furnish a Bond or other collateral satisfactory to Developer
to indemnify Developer against any Lien.
(B) Review of Application and Acceptance
(1) If, on the basis of Engineer’s and Engineer’s observation of the Work during construction and final
inspection, and Engineer’s and Engineer’s review of the final Application for Payment and
accompanying documentation as required by the Contract Documents, Engineer is satisfied that the
Work has been completed and Contractor’s other obligations under the Contract Documents have
been fulfilled, the Engineer will, within ten days after receipt of the final Application for Payment,
indicate in writing Engineer’s recommendation of payment and present the Application for Payment
to Developer for payment. At the same time Engineer will also give written notice to Developer and
Contractor that the Work is acceptable subject to the provisions of Section 14.09. Otherwise, Engineer
will return the Application for Payment to Contractor, indicating in writing the reasons for refusing to
General Conditions Meridian Town Center
Page 92 of 114 Offsite Improvements - Phase 3
recommend final payment, in which case Contractor will make the necessary corrections and resubmit
the Application for Payment.
(C) Payment Becomes Due
(D) Thirty days after the presentation to Developer of the Application for Payment and accompanying
documentation, the amount recommended by Engineer will become due and, when due, will be paid by
Developer to Contractor.
14.08 Final Completion Delayed
If, through no fault of Contractor, final completion of the Work is significantly delayed, and if Engineer so
confirms, Developer will, upon receipt of Contractor’s final Application for Payment and recommendation
of Engineer, and without terminating the Agreement, make payment of the balance due for that portion
of the Work fully completed and accepted. If the remaining balance to be held by Developer for Work not
fully completed or corrected is less than the retainage stipulated in the Agreement, and if Bonds have
been furnished as required in Section 5.01, the written consent of the surety to the payment of the
balance due for that portion of the Work fully completed and accepted will be submitted by Contractor
to Engineer with the Application for such payment. Such payment will be made under the terms and
conditions governing final payment, except that it will not constitute a waiver of Claims. The remaining
balance of any sum included in the final Application for payment but held by Developer for Work not fully
completed and accepted will become due when the Work is fully completed and accepted.
14.09 Waiver of Claims
Contractor’s acceptance of final payment will constitute a waiver of all Claims by Contractor against
Developer other than those previously made in writing which are still unsettled.
ARTICLE 15. SUSPENSION OF WORK AND TERMINATION
15.01 Developer May Suspend Work
At any time and without cause, Developer may suspend the Work or any portion thereof for a period of
not more than ninety (90) consecutive days by notice in writing to Contractor, Engineer which will fix the
date on which Work will be resumed. Contractor will resume the Work on the date so fixed. Contractor
will be allowed an adjustment in the Contract Price or an extension of the Contract Dates, or both, directly
attributable to any such suspension if Contractor makes a Claim therefore as provided in Section 10.05.
15.02 Developer May Terminate for Cause
(A) The occurrence of any one or more of the following events will justify termination for cause:
(1) Contractor’s failure to perform the Work in accordance with the Contract Documents, including, but
not limited to, (A) failure to supply sufficient skilled workers or suitable materials or equipment or (B)
failure to adhere to the progress schedule established under Section 2.07 as adjusted from time to
time pursuant to Section 6.04;
(2) Contractor’s disregard of Laws or Regulations of any public body having jurisdiction;
(3) Contractor’s disregard of the authority of Engineer; or
(4) Contractor’s violation in any substantial way of any provision of the Contract Documents.
(B) If one or more of the events identified in Section 15.02(A) occur, Developer may, after giving Contractor
(and the surety, if any) seven (7) days written notice, terminate the services of Contractor, exclude
Contractor from the Site, and take possession of the Work and of all Contractor’s tools, appliances,
construction equipment, and machinery at the Site, and use the same to the full extent they could be
used by Contractor (without liability to Contractor for trespass or conversion), incorporate in the Work all
materials and equipment stored at the Site or for which Developer has paid Contractor but which are
stored elsewhere, and finish the Work as Developer may deem expedient. In such case, Contractor will
not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the
Contract Price exceeds all claims, costs, losses, and damages (including but not limited to all fees and
charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other
General Conditions Meridian Town Center
Page 93 of 114 Offsite Improvements - Phase 3
dispute resolution costs) sustained by Developer arising out of or relating to completing the Work, such
excess will be paid to Contractor. If such claims, costs, losses, and damages exceed such unpaid balance,
Contractor will pay the difference to Developer. Such claims, costs, losses, and damages incurred by
Developer will be reviewed by Engineer as to their reasonableness and, when so approved by Engineer,
incorporated in a Change Order. When exercising any rights or remedies under this Section, Developer
will not be required to obtain the lowest price for the Work performed.
(C) Where Contractor’s services have been so terminated by Developer, the termination will not affect any
rights or remedies of Developer against Contractor then existing or which may thereafter accrue. Any
retention or payment of moneys due Contractor by Developer will not release Contractor from liability.
15.03 Developer May Terminate For Convenience
(A) Upon notice to Contractor, Engineer, Developer may, without cause and without prejudice to any other
right or remedy of Developer, elect to terminate the Contract. In such case, Contractor will be paid
(without duplication of any items):
(1) for completed and acceptable Work executed in accordance with the Contract Documents prior to the
effective date of termination;
(2) for expenses sustained prior to the effective date of termination in performing services and furnishing
labor, materials, or equipment as required by the Contract Documents in connection with
uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses
(determined as provided in Section 12.01(C));
(3) for all claims, costs, losses and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or arbitration or other dispute resolution
costs) incurred in settlement of termination contracts with Subcontractors, Suppliers, and others; and
(4) for reasonable expenses directly attributable to termination.
(B) Contractor will not be paid on account of loss of anticipated profits, loss of anticipated revenue, lost
opportunity, overhead or other economic loss or damages arising out of or resulting from such
termination.
15.04 Contractor May Stop Work or Terminate
If, through no act or fault of Contractor, the Work is suspended for more than ninety (90) consecutive
days by Developer or under an order of court or other public authority, or Engineer fails to act on any
Application for Payment within thirty (30) days after it is submitted, or Developer fails for thirty (30) days
to pay Contractor any sum finally determined to be due, then Contractor may, upon seven days written
notice to Developer, Engineer, and provided Developer, Engineer do not remedy such suspension or
failure within that time, terminate the Contract and recover from Developer payment on the same terms
as provided in Section 15.03. In lieu of terminating the Contract and without prejudice to any other right
or remedy, if Engineer has failed to act on an Application for Payment within thirty (30) days after it is
submitted, or Developer has failed for thirty (30) days to pay Contractor any sum finally determined to be
due, Contractor may, seven (7) days after written notice to Developer, Engineer, stop the Work until
payment is made of all such amounts due Contractor, including interest thereon. The provisions of this
Section 15.04 are not intended to preclude Contractor from making a Claim under Section 10.05 for an
adjustment in Contract Price or Contract Dates or otherwise for expenses or damage directly attributable
to Contractor’s stopping the Work as permitted by this Section.
ARTICLE 16. DISPUTE RESOLUTION
16.01 Direct Discussions
In the event of a Claim, Developer and Contractor will promptly cause their respective representatives to
confer and exert their good faith efforts to reach a reasonable and equitable resolution as soon as
practical. If such representatives are unable to resolve the issue within a reasonable time (as determined
by either representative), either representative may refer the matter to the parties’ responsible officers
for resolution. Following such referral, the parties’ responsible officers will have at least fourteen (14)
General Conditions Meridian Town Center
Page 94 of 114 Offsite Improvements - Phase 3
days (seven (7) days if a payment dispute) to resolve the Claim. If the parties fail to settle such dispute
within such period (including any failure of responsible officers to confer in such period), the provisions
of Section 16.02 will apply unless the parties agree otherwise.
16.02 Mediation
Any Claim not resolved pursuant to Section 16.01 will be subject to mediation upon demand of either
party. The parties will endeavor to select the mediator by mutual agreement. In absence of mutual
agreement within ten (10) days, Developer will notify Contractor of not less than three candidates, and
Contractor will chose the mediator from the list of candidates within five (5) days thereafter by notice to
Developer. All candidates will be independent construction professionals, attorneys or judges. The
mediator will set the rules of the mediation. Any party to the mediation can invite additional parties to
the mediation if the presence of such additional party is required for a complete resolution of any Claim.
The parties will share the mediator’s fee and any filing fees equally. Unless otherwise agreed, the
mediation will be held within sixty (60) days of the demand for mediation and will be held in a mutually
acceptable location in Boise, Idaho. Agreements reached in mediation will be enforceable as settlement
agreements in any court having jurisdiction thereof. Developer will have the right, but not the obligation,
to waive the requirements of this Section 16.02 for any Claim if Developer believes mediation of such
claim would be futile or contrary to the efficient resolution of the Claim.
16.03 Optional Arbitration
If the parties do not resolve a Claim through mediation pursuant to Section 16.02, Developer has the right,
but not the obligation, to elect to resolve the dispute through arbitration pursuant conducted in
accordance with the Idaho’s Uniform Arbitration Act (Title 7, Chapter 9, Idaho Code). Contractor
acknowledges and agrees that it is critical to Developer to have the option to direct Claim to a binding
dispute resolution proceeding that Developer deems appropriate to further the efficient resolution of the
Claim. Contractor further acknowledges that (i) Developer will be involved in more relationships with
other parties than Contractor, (ii) Developer has greater exposure to liability than Contractor, and (iii)
disputes may vary from simple claims by users to complicated contractual disputes. Accordingly,
Contractor agrees that it is fair, reasonable and appropriate for Developer to have the option to select
arbitration for any particular Claim. Developer’s election for arbitration will be made in writing and
delivered to Contractor. The arbitrator may be any construction professional, construction attorney or
retired judge selected by mutual agreement, or in absence of such agreement, as appointed pursuant to
applicable law. The arbitrator will set the rules, procedures and schedule for the arbitration, it being the
intent of the parties that the arbitration be as expeditions and informal as the nature of the dispute
permits. The arbitrator may order the exchange of documents as the arbitrator deems appropriate;
provided, however, Developer may elect to have discovery in the arbitration be in accordance with the
Idaho Rules of Civil Procedure. In such event, any party participating in the arbitration will have the right
to conduct discovery in the same manner as parties in a legal or equitable proceeding under the Idaho
Rules of Civil Procedure then in effect. All discovery matters, including time limits, scheduling orders and
discovery disputes will be decided by the arbitrator in the same manner as a judge under the Idaho Rules
of Civil Procedure. If the arbitrator is not able to fully enforce any party’ discovery rights under this
Section, the affected party may institute or continue a legal or equitable proceeding in any court of
competent jurisdiction and venue for the purpose of enforcing its discovery rights.
16.04 Litigation
Any Claim not otherwise resolved through this Article 16 will be resolved by a court of competent
jurisdiction in Idaho and each party hereby irrevocably and unconditionally submits to such exclusive
jurisdiction and venue.
16.05 Attorneys’ Fees
In the event of any litigation or arbitration between the parties arising from or related to this Agreement
(whether sounding in tort, contract or otherwise), the prevailing party will be entitled to receive from the
other party reasonable attorneys’ fees, including court costs, expert witness fees and related costs, of
such action and any appeal therefrom. To promote fairness and prevent the excessive awards, the
General Conditions Meridian Town Center
Page 95 of 114 Offsite Improvements - Phase 3
prevailing party in any monetary damages Claim will not be awarded attorneys’ fees in an amount greater
than the ratio that the final monetary award for such Claim bears to the highest monetary amount
demanded by the prevailing party for that Claim. By way of example, if one party sues the other party
demanding $100,000, but recovers $10,000, such party may not be awarded more than 10% of its
reasonable attorneys’ fees.
16.06 Continuing Performance
Unless otherwise agreed, Contractor will continue diligently with performance of the Work pending final
resolution of a Claim and Developer will continue to make payments to Contractor in accordance with
this Contract Documents.
16.07 Subcontracts
Unless otherwise agreed, Contractor must incorporate this Article 16 into all Subcontracts so that all
involved Subcontractors are bound to the dispute resolution terms to the extent that Contractor is bound
to Developer.
ARTICLE 17. MISCELLANEOUS
17.01 Giving Notice
Whenever any provision of the Contract Documents requires the giving of written notice, it will be
deemed to have been validly given if delivered in accordance with Section 3 of the Supplementary
Conditions.
17.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to exclude
the first and include the last day of such period. If the last day of any such period falls on a Saturday or
Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted
from the computation.
17.03 Cumulative Remedies
The duties and obligations imposed by the Contract Documents and the rights and remedies available
thereunder to the parties hereto are in addition to, and are not to be constructed in any way as a limitation
of, any rights and remedies available to any or all of them which are otherwise imposed or available by
Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents,
and the provisions of this Section will be as effective as if repeated specifically in the Contract Documents
in connection with each particular duty, obligation, right, and remedy to which they apply.
17.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract
Documents, will survive final payment, completion, and acceptance of the Work or termination or
completion of the Agreement.
17.05 Controlling Law
This Contract is to be governed by the law of the state in which the Project is located.
17.06 Waivers, Consents and Approvals
No waiver, consent or approval hereunder may be oral. Any waiver of any term or provision of this
Contract, and any consent or approval hereunder, will only be effective if given in writing and signed by
the waiving, consenting or approving party. No waiver, relaxation, forbearance, delay, indulgence or
failure by either party to enforce any of the terms, covenants, conditions or other provisions of the
Contract at any time will in any way prejudice, affect, limit, modify or waive that party’s right thereafter
to enforce or compel strict compliance with every term, covenant, condition or other provision hereof,
any course of dealing or custom of the trade notwithstanding. No delay or omission on the part of a party
General Conditions Meridian Town Center
Page 96 of 114 Offsite Improvements - Phase 3
will operate as a waiver thereof, nor will any waiver by either party of any breach of the Contract operate
as a waiver of any subsequent or continuing breach of the Contract.
17.07 Interpretation
(A) In the event that any provision or portion of the Contract Documents, or the application thereof, become
invalid, illegal or unenforceable in any respect under the Law of any jurisdiction, the validity and
enforceability of the remaining provisions or portions, or applications thereof, will not be affected
thereby.
(B) Were the context requires, words importing the singular will include the plural and vice versa, and words
importing persons will include entities. A reference in this Contract to any article, section, exhibit, clause
or Section is, except where it is expressly stated to the contrary, a reference to such article, section,
exhibit, clause or Section in the Contract. Headings are for convenience of reference only. Each reference
to the Contract will include a reference to each agreed variation of or supplement to the Contract as may
be amended, varied or supplemented from time-to-time. Where the context requires, any reference to a
person, entity or party will include such person’s, entity’s or party’s successors and permitted assigns.
References to the word “include” or “including” are to be construed without limitation.
(C) The Contract Documents will be construed without regard to the identity of the person who drafted the
various provisions of the same. Each and every provision of this Agreement and such other documents
and instruments will be construed as though the parties participated equally in the drafting of the same.
Consequently, the parties acknowledge and agree that any rule of construction that a document is to be
construed against the drafting party will not be applicable to the Contract Documents.
Supplementary Conditions Meridian Town Center
Page 97 of 114 Offsite Improvements
SUPPLEMENTARY CONDITIONS
Supplementary Conditions Meridian Town Center
Page 98 of 114 Offsite Improvements - Phase 3
SUPPLEMENTARY CONDITIONS
These Supplementary Conditions supplement and amend the General Conditions. In the event of any conflict
between these Supplementary and the General Conditions, the requirement that places the greater or more
stringent obligation on Contractor will govern. All conditions, requirements, services and other matters set forth in
these Supplementary Conditions are included in the Work and the Contract Price, and are to be provided by
Contractor without additional payment or consideration. Capitalized terms not otherwise defined herein will have
the meaning set forth in the General Conditions.
1. GOVERNING AGREEMENTS
Contractor must examine and be familiar with all terms, conditions and requirements set forth in each of the
documents identified as a “Governing Agreements and Permits” section of the FTP Site managed by Engineer.
All conditions, requirements, services and other matters set forth in the Governing Agreements are included in
the Work and Contractor will perform the Work in strict compliance therewith. In the event of any conflict
between or among the any of the above mentioned documents and the Contract Documents, the more stringent
requirement on Contractor will govern. Contractor will promptly report any actual or potential conflicts
discovered between or among the above mentioned documents and the Contract Documents to Engineer for
resolution.
2. REFERENCE DOCUMENTS
The reports and drawings relating to conditions at the Site (or related to the Site) that have been utilized by the
Engineer in the preparation of the Contract Documents are available from Engineer and can be found in the
“Reference Documents” section of the FTP Site managed by Engineer. The foregoing documents are not
complete depictions of the existing conditions at the Site. The existing conditions at the Site may vary in some
areas from that indicated on the foregoing documents.
3. NOTICES
All notices, consents, approvals, orders, acceptances, confirmations and other communications required or
permitted by the Contract must be in writing and delivered by hand (including by messenger or courier), by
reputable overnight courier (e.g., FedEx, Airborne) or by certified or registered US Mail (postage prepaid) or by
facsimile at the addresses or numbers set forth below or at such other addresses or numbers as the party
receiving notice may subsequently designate by way of replacement by notice to the other parties pursuant to
this Section:
If to Developer: Meridian CenterCal, L.L.C.
Attn: Lance Blackwood, Project Manager
13400 South Mountain View Corridor
Riverton, Utah 84065
Telephone: (801) 793-0195
Email: lblackwood@centercal.com
Supplementary Conditions Meridian Town Center
Page 99 of 114 Offsite Improvements - Phase 3
with a copy of any Claim or notice of suspension or termination to:
Meridian CenterCal LLC
c/o CenterCal Properties LLC
Attn: Craig Trottier, President, Intermountain
140 North Union Avenue, Suite 225
Farmington, Utah 84025
Email: ctrottier@centercal.com
Meridian CenterCal LLC
c/o CenterCal Properties LLC
Attn: Sean Dennison, General Counsel
1960 E. Franklin Avenue
El Segunda, California 90245
Email: sdennison@centercal.com
Givens Pursley LLP
Attn: Franklin G. Lee
601 W. Bannock Street
Boise, Idaho 83702
Email: franklee@givenspursley.com
If to Contractor:
Attn:
Telephone:
Email:
If to Engineer: NV5
Attn: Robert Beckman, PE, PTOE
690 S. Industry Way, Suite 10
Meridian, Idaho 83642
Direct: 630-200-7782
Email: robert.beckman@NV5.com
If to ITD: Idaho Transportation Department
Attn: Daris Bruce, District 3 Resident Engineer
PO Box 8028
Boise, Idaho 83707-1129
Office: 208-334-8331
Email: daris.bruce@itd.idaho.gov
with a copy of any Claim or notice of suspension or termination to:
Gary D. Luke
Deputy Attorney General
Civil Litigation Division
Idaho Transportation Department
311 W. State Street
PO Box 7129
Boise, Idaho 83707-1129
Office: 208-334-8812
Supplementary Conditions Meridian Town Center
Page 100 of 114 Offsite Improvements - Phase 3
Email: gary.luke@itd.idaho.gov
Idaho Transportation Department
Attn: Caleb Lakey, District 3 Engineer
8150 Chinden Blvd.
Boise, Idaho 83714-1367
Office: 208-334-8300
Email: caleb.lakey@itd.idaho.gov
Any communication will be deemed received upon actual receipt (or attempted delivery if delivery is
refused) at the addresses set forth above.
4. CONSTRUCTION STANDARDS
Except as modified herein, the Work must be performed in strict compliance with the current edition of the
Idaho Standards for Public Works Construction (the “ISPWC”), and all supplements and amendments thereto
adopted by the City of Meridian (the “Meridian Supplements”) . Contractor is required to be a holder of the
ISPWC, and the Meridian Supplements. In addition, Contractor is required to comply with the current Idaho
Transportation Department Standard Specifications for Highway Construction, Supplemental Specifications for
current Idaho Standard Specifications and Idaho Transportation Department Quality Assurance Manual for
Construction (the “ITD Standard”) for certain Work on S. Eagle Road.
Contractor is required to obtain the current versions and supplements of ISPWC, ITD and City of Meridian
standard drawings in order to complete the Work.
In the event of any conflict between or among the standard and requirements set forth herein, the more
stringent requirement on Contractor will govern.
5. WEEKLY COORDINATION MEETINGS
Contractor will organize and hold weekly coordination meetings with Developer, Developer’s other contractors,
Engineer, ITD and its other contractors, ACHD and its other contractors (if appliable), utility companies,
emergency services and any other interest agencies and contractors. Contractor will provide a suitable location
and facility for such meetings.
6. CONSTRUCTION SCHEDULE REQUIREMENTS
Contractor will prepare, furnish and update, all as set forth herein, a ‘Gantt Chart’ based critical path method
(CPM) schedule for all activities of Contractor, Developer, ITD and others for the Project as set forth herein (the
“Construction Activity Schedule”). The Construction Activity Schedule must be consistent with the Contract
Dates and other time obligations set forth in, or adopted pursuant to, the Contract Documents.
Contractor will submit the initial schedule and each update to Developer, Engineer, and ITD. The initial schedule
must be submitted before the preconstruction conference. Updates must be submitted prior to each weekly
coordination meeting.
Developer’s acceptance of any schedule will not relieve Contractor of its responsibilities under the Contract
Documents for timely performance of the Work.
Contractor will not stop the Work for any length of time without Developer’s written consent. Should the
prosecution of the Work be discontinued or changed for any reason, Contractor will notify Developer at least
two (2) working days in advance of changing or resuming operations.
Developer may withhold progress payments if Contractor fails to provide the schedule and updates as required.
Supplementary Conditions Meridian Town Center
Page 101 of 114 Offsite Improvements - Phase 3
Developer and Contractor will meet for joint review, correction and adjustment of the initial schedule at the
preconstruction meeting and at each weekly coordination meeting.
Contractor will update the Construction Activity Schedule weekly. Each weekly update must be accompanied
by a written narrative describing the status of the critical path and any revisions to the schedule will be included
with the update. The updated schedule must be resubmitted if it does not contain the required upon
information.
At the written request of Developer, and within three (3) calendar days, Contractor will submit a supplemental
schedule if the actual progression of the Work is, as determined by Developer, significantly different than that
represented on the schedule. No extra payment will be made for a supplemental schedule should it be required.
Each Construction Activity Schedule submittal to Developer and ITD must include one electronic copy
compatible with Microsoft Project and Adobe PDF.
The Construction Activity Schedule must conform to the following specifications:
A. Schedule Report sorted by Activity or Noted Number:
• Activity information must include activity numbers, activity descriptions, durations, float, percent
complete, scheduled start and finish dates, and actual start and finish dates.
• The activity descriptions and durations will be such that the applicable Work is readily identifiable
and the progress on each activity can be readily measured.
• Activities will include, but are not limited to, engineering, surveying, permitting, submittals,
approvals, procurement, fabrication, utility accommodations, and construction. All schedule
constraints and Contract Dates, when applicable, must be shown. All dummies, leads and lags must
be identified.
B. Estimated Man-Hours per Day and Working Days per Week:
The chart must indicate the number of workdays per week, shifts per day, hours per shift, holidays and
a general description of the major equipment to be used.
C. Critical Path must be clearly defined:
• The schedule must clearly show the sequence and interdependence of all activities required for
complete performance of all items of work under the contract and must indicate the critical path.
• Contractor’s submittal to Developer for change order work and claims must include an analysis of
the schedule showing any schedule change, disruption, and any disruptions of contract time.
• Updated charts must show the progress of each activity, the percent complete, remaining duration
and all schedule revisions, and clearly define impact to Critical Path, if applicable. Anticipated cash
flow, due to the duration of the project, will be required quarterly.
D. A schedule of when each individual road segment will be milled and paved. No milling is to occur on
any roadway segment without Agency’s prior approval. The schedule for one or more segments may
need to be shifted in order to minimize impacts to traveling public from other construction impacts
that may be in the roadway segment area.
E. The Construction Activity Schedule must be flexible and allow for potential for schedule adjustments
by Developer or ITD. The adjustments, if any, will be included in the Contract Price.
7. DOCUMENT CONTROL SYSTEM
Contractor must use the then current version of Oracle® Primavera Submittal Exchange for Contractor’s
document control system, unless other system that is approved by Engineer (the “Submittal System”).
Supplementary Conditions Meridian Town Center
Page 102 of 114 Offsite Improvements - Phase 3
Unless otherwise approved by Engineer, all submittals must be transferred to Engineer in electronic (PDF)
format using the Submittal System. The intent of the Submittal System is to expedite the construction process
by reducing paperwork, improving information flow, and decreasing turnaround time. The Submittal System is
not intended for color samples, color charts, or physical material samples, all of which may be delivered to
Engineer through any reasonable means.
Contractor is responsible for reviewing and approving each submittal in accordance with the Contract
Documents prior to submission thereof to Engineer. The review comments of Developer, Engineer and/or others
Architect / Engineer will be made available on the Submittal System. Contractor will receive notice of completed
review through the Submittal System. Contractor is responsible for distribution of reviewed submittals to
Contractor’s subcontractors and suppliers. Contractor is responsible for any post-review matters required by
the review comments, including corrections, changes, resubmittals and other tasks.
Contractor will bear all expenses related to Contractor’s use of the Submittal System, including the full cost of
any subscription in their proposal.
8. PUBLIC ENGAGEMENT MEETINGS
Developer and ITD believe that it is important that members of the public to have the opportunity to attend
public engagement meetings to learn about the Project and be informed about the progress of the Project.
Accordingly, Contractor agrees to work with Developer, Engineer, ITD and the City of Meridian to provide
information about the Project and to participate in a forum that allows the public to express their concerns
about the Project. Meeting management, logistics, organization, facilitation and communication will be
managed by Engineer, who will serve as the lead agency for Public Involvement. At a minimum, the public
meetings will:
A. Be held at least monthly;
B. Be located at a suitable facility near the Project for the expected attendance at the meeting;
C. Be held no earlier than 6:00 pm and no later than 9:00 pm, Monday through Friday;
D. Be advertised at least one week in advance on signs on the Project site as may be approved by Engineer;
E. Have Contractor’s key project managers and superintendents in attendance;
F. Provide update on the status and schedule of the Work, which update will not exceed 30 minutes;
G. Have schedule information available in a “take home” format identifying the key elements of the Work
(from the perspective of a member of the public) to be performed during the next calendar month;
H. Reserve at least one hour for members of the public to ask questions and express concerns;
I. Contractor will endeavor to answer each question and address each concern verbally during the meeting,
and will follow up in writing as to any question not answered or concern not addressed in the meeting
(unless excused by Engineer, which is intended for any questions or concerns that are irrelevant,
inappropriate or duplicative of previous responses).
Engineer will have a meeting notice sign-up sheet, and provide notices of future meetings to each person that
request notice (by mail or email, as selected by the member of the public requesting notice).
Contractor will take notes reflecting all questions or concerns by members of the public, and provide the same
to Engineer and ITD.
9. PAYMENT AND PERFORMANCE BONDS
The payment and performance bonds to be provided pursuant to Section 5.01 of the General Conditions must
be a in form and content acceptable to Developer and ITD, and must comply with all requirements set forth in
the Public Contracts Bond Act (i.e., Idaho Code § 54-1925 et. seq.). Developer and ITD must be named as
beneficiaries and obligees of the bonds.
Supplementary Conditions Meridian Town Center
Page 103 of 114 Offsite Improvements - Phase 3
10. PUBLIC WORKS LICENSES
Contractor and all Subcontractors must be licensed as a public works contractor in the State of Idaho (see
Chapter 19, Title 54, Idaho Code) at all times during the bidding and performance of the Contract.
11. REQUIRED INSURANCE
(A) Coverages Required. In addition to Contractor’s obligations under Section 5.04 of the General Conditions,
Contractor must purchase and maintain the insurance as set forth below for matters that may arise out of
or result from Contractor’s operations and completed operations under this Contract or for which
Contractor may be legally liable, whether the operations be by Contractor or by a Subcontractor or by
anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be
liable.
(1) Commercial General Liability coverage with the following per project annual aggregate limits, using
ISO Form CG 25030397 (or a substitute form providing equivalent coverage):
General Aggregate Limit Not less than $10,000,000;
(other than Product-Completed Operations)
Product-Completed Operations Agg. Limit Not less than $10,000,000;
Personal and Advertising Injury Limit Not less than $10,000,000;
Each Occurrence Limit Not less than $10,000,000;
The policy or policies must include (i) broad form property damage coverage including, but not limited to,
damage arising from blasting, explosion, collapse of structures or other property or damage to underground
utilities and property with any X.C.U. exclusion removed, (ii) protective liability coverage (iii) product and
completed operations coverage (iv) contractual liability coverage, and (v) personal injury coverage,
including libel, slander, wrongful eviction and false arrest. All policies must be written on an occurrence
basis rather than claims made. The policy must name Developer and ITD as additional insured by
endorsement, and the policy must contain a separation of insureds (cross liability) clause and a breach of
warranty clause as approved by Developer, and the certificate must so indicate. The above limits may be
provided by any combination of primary and excess policies. The liability insurance must be primary and
not contributing to any insurance available to Developer, and Developer’s insurance will be in excess
thereof. The limits of any insurance will not limit the liability of Contractor under the Contract or otherwise.
The indicated coverage limits may achieved by a combination of primary and excess liability coverages.
(2) Workers Compensation insurance providing statutory limits of liability, and Employers Liability limits
of One Million Dollars ($1,000,000) per disease/accident/ employee, which policy must contain a
waiver of subrogation in favor of Developer and ITD.
(3) Comprehensive Automobile Liability Insurance for all owned, non-owned and hired vehicles with
single combined limit of not less than Two Million Dollars ($2,000,000) per occurrence;
(4) Contractor’s Pollution Liability Insurance, applicable to all premises and operations including clean-up
costs resulting from pollution caused or aggravated by Contractor, bodily injury and property damage
resulting from pollution conditions, bodily injury property damage and clean-up costs from
transported cargo, and business interruption caused by pollution conditions. The insurance must have
a combined single limit of not less than Five Million Dollars ($5,000,000) per incident with a Five Million
Dollar ($5,000,000) aggregate limit.
(5) Any further coverage required of Contractor by applicable Laws and Regulations.
Supplementary Conditions Meridian Town Center
Page 104 of 114 Offsite Improvements - Phase 3
(B) Period of Coverages. All policies must be in effect prior to the commencement of performance of Work. All
policies must remain in effect until one (1) years after final payment to Contractor or termination of the
Contract, and thereafter when the insured is correcting defective or nonconforming deliverables or Services
or otherwise performing Services related to defective or nonconforming work by others. The Products and
Completed Operations coverage and the Professional Liability coverage must remain in effect for five (5)
years after final payment to Contractor or termination of the Contract, provided that the coverage remains
available to Contractor on a commercially reasonable basis during that period. Contractor’s Pollution
Liability Insurance coverage must remain in effect for five (5) years after final payment to Contractor or
termination of the Contract, provided that the coverage remains available to Contractor on a commercially
reasonable basis during that period.
(C) Additional Insureds. The policies required by Subsections (1), (3) and (4) of this Section 11 must name
Developer and ITD their respective members, partners, officers, directors, employees and agents, and the
successors and assigns of the foregoing, as additional insureds, using ISO additional insureds endorsement
CG 2010-1185, CG 2010-0704, or CG 2037-0704 or a substitute providing equivalent coverages. All coverage
afforded to the additional insureds must (1) be primary and noncontributory as to any insurance or self-
insurance retention of the additional insureds, (2) provide the same types and extents of coverages afforded
to the primary insureds, and must not be limited to the “vicarious liability” of the additional insureds,
provided that this subpart (C) hereof will not be interpreted or applied to require coverage of liability of the
additional insureds in violation of applicable law, (3) waive all rights of subrogation against the additional
insureds, (4) include ongoing and completed operations and (5) be maintained for the same durations as
set forth in subpart (B) above.
(D) Proof and Maintenance of Coverage. One or more certificates of insurance in forms acceptable to
Developer, as well as copies of all additional insured endorsements required by this Section 11, must be
furnished to Developer prior to commencement of the Services and thereafter as the coverages are
renewed during the period during which the coverages are required to be maintained and thereafter prior
to Contractor’s performance of any correction or curative Services or Services relating to any corrective or
curative work or services by others. Complete copies of insurance policies must be provided to Developer
upon written request. The certificates of insurance and all policies required by this Section 11 must include
provisions requiring that coverage will not be cancelled, terminated, modified to reduce coverage or
allowed to expire without thirty (30) days prior written notice to Developer. Contractor will provide no less
than thirty (30) days’ prior written notice to Developer.
(E) Effect of Noncompliance. Failure of Contractor or its Subcontractors to comply with the requirements of
this Section 11 will constitute a material breach of the Contract entitling Developer, without waiving other
rights or remedies, to terminate the Contract for cause or to purchase the required insurance and charge
the cost to Contractor. Nothing herein negates or reduces Contractor’s responsibilities or liabilities under
the Contract or under applicable law; this Section 11 rather sets out Contractor’s obligations only with
respect to insurance. Performance of the Work will constitute a continuing warranty that Contractor,
Consultants and Subcontractors are in compliance with the requirements set out in this Section 11.
Contractor agrees that Developer’s failure to ascertain that Contractor, Consultants or Subcontractors have
not strictly complied with the requirements set out in these Supplementary Conditions will not constitute
a waiver of Contractor’s, Consultants, or Subcontractors’ obligations set out herein.
(F) Insurance will Not Limit Liability. The minimum limits of any insurance coverage required to be carried by
Contractor will not limit Contractor’s liability under any indemnity provision of under the Contract
Documents.
12. CONTRACTOR’S INDEMNITY
To the fullest extent permitted by applicable law, Contractor will indemnify, defend and hold Developer and ITD
(and the officers, directors, commissioners, managers, members, employees and agents of any of them) (each
Supplementary Conditions Meridian Town Center
Page 105 of 114 Offsite Improvements - Phase 3
an “Indemnitee”) from and against any and all claims by third persons arising out of the performance of the
Work or the Contract; provided, however, Contractor will not be obligated to indemnify an Indemnitee for
damages arising out of bodily injury to persons or damage to property caused by or resulting from the sole
negligence of the Indemnitees or their agents, employees or contractors.
13. CORRECTION PERIOD, WARRANTIES, GUARANTEES
Developer may at any time assign Contractor’s obligations under Section 13.07 of the General Conditions
(Correction Period) to ITD. Further, Developer may at any time assign any warranties or guarantees required
under the Contract Documents to ITD. Upon receipt of notice of any assignment(s), Contractor will fully and
faithfully perform the obligations for the benefit of ITD.
14. SWPPP
Contractor must obtain the Environmental Protection Agency (EPA) Construction General Permit (CGP) and
Contractor must file a Notice of Intent (NOI) and develop and implement an approved Storm Water Pollution
Prevention Plan (SWPPP) prior to commencement of any construction activities hereunder. Contractor must not
file a Notice of Termination (NOT) with the EPA until authorized in writing by Developer and ITD. Authorization
for Contractor to file the NOT will be granted by Developer and ITD when the area subject to the CGP has
achieved final stabilization as defined in the CGP. ITD will provide applicable assistance as necessary with the
CGP application; however, ITD does not assume any additional liability for storm water violations on property
outside of their respective jurisdictions.
15. AGENCY APPROVAL OF MATERIALS CERTIFICATIONS
Contractor must promptly provide all material certifications to Engineer. Engineer will provide the material
certifications to ITD for review and approval (with a reasonable period to provide an opportunity for review)
prior to Developer’s acceptance and payment for any incorporated materials. Contractor acknowledges that any
failure or delay in providing material certifications to Engineer may delay Developer’s acceptance of, and
payment for, incorporated materials.
16. BASIS OF UNIT PRICE QUANTITIES
Unless otherwise specified herein, all payments made on unit prices will be based on in-place, completed and
accepted unit quantities. Determinations of the actual quantities and classifications of the Unit Price Work
performed by Contractor will be made by Engineer subject to the provisions of Section 9.08 of the General
Conditions.
17. CONTRACT DATES FOR SUBSTANTIAL COMPLETION AND FINAL COMPLETION
Time is of the essence with respect to all of Contractor’s obligations. Contractor must perform all Work in
accordance with Contractor’s schedule obligations under the Contract Documents, including Article 4 of the
Agreement. The Contract Dates for Substantial Completion and Final Completion will only be extended by a
Change Order in accordance with the Contract Documents (including Article 12 of the General Conditions)
18. ASSIGNMENT OF CONTRACT
Contractor hereby consents to the assignment of some or all of the Contract to ITD or any designee of ITD. The
assignment may occur at any time and may be conditional or otherwise. Upon receive of notice of the
assignment, Contractor will promptly execute any confirmation of the consent reasonably requested by ITD.
19. NIGHT WORK
Supplementary Conditions Meridian Town Center
Page 106 of 114 Offsite Improvements - Phase 3
Contractor may perform Night Work as allowed by the Agency. “Night Work” is Work performed during the
hours of 10 pm to 5 am. Contractor will submit a traffic control plan for Night Work to Developer and the Agency
for approval not less than fourteen (14) days prior to Contractor’s desired start date for Night Work.
20. CONSTRUCTION PHASING AND TRAFFIC CONTROL
(A) As soon as practical after execution of this Contract, Contractor provide Developer and ITD with a detailed
construction phasing and traffic control plans to Developer and ITD for review and approval prior to
construction. The traffic control plans must address advanced construction signing and detailed traffic
control for each phase of work and must address pedestrian detours whenever construction activities
necessitate closure of any existing pedestrian facilities.
(B) A traffic control plan is provided in the Contract Documents. If Contractor chooses to change the traffic
control plan, Contractor must submit detailed traffic control plans to Agency for review and approval prior
to construction.
21. ADA DURING CONSTRUCTION
As used herein, any reference to the “ADA” means the then current Americans with Disabilities Act of 1990, as
amended, and any regulations promulgated thereunder.
The needs and control of all road users (motorists, bicyclists, and pedestrians within the highway and/or public
right‐of‐way, including persons with disabilities in accordance with the ADA through a temporary traffic control
“TTC” zone will be an essential part of highway construction, utility work, maintenance operations, and the
management of traffic incidents. The primary function of TTC is to provide for the reasonably safe and efficient
movement of road users through or around TTC zones while reasonably protecting workers, responders to
traffic incidents, and equipment. Temporary facilities, including reasonably safe pedestrian routes around work
sites, are also covered by the accessibility requirements of the ADA.
Implementation of TTC plans and installation and maintenance of devices will be the responsibility of Contractor
performing the construction, alteration and/or maintenance of the highway or public right‐of‐way. When an
existing continuous sidewalk or street crossing route cannot be maintained for pedestrians because of
construction, either temporary walkways with curb ramps are to be provided, or the construction will be phased
to maintain access to the affected addresses. Contractors will have flexibility as long as the requirements are
met.
The location of the construction project and whether or not accessible facilities are present will also determine
the extent of the needed temporary facilities. Contractor is only required to maintain practical continuity
where accessible facilities already exist. On low speed rural roads that do not have sidewalks and are used by
bicyclists, no additional measures are needed as the bicycles can share the available travel lanes with other
traffic. On moderate to higher speed rural roads, if a bike lane exists then it should be properly detoured,
complete with signage, to provide a safe route through or around the Work area. If a work zone affects vehicular
traffic to a business, residence, school or any other type of pedestrian generating location with existing
accessible facilities, then pedestrian and handicapped access must be maintained. A continuous route for all
pedestrians, including the disabled and bicyclists, will be maintained at all times. When existing pedestrian
facilities are disrupted, closed, or relocated in a TTC zone, the temporary facilities will be detectable and include
accessibility features consistent with the features present in the existing pedestrian facility. The temporary
route should enable pedestrians to bypass the construction site while minimizing the retracing of their steps or
going significantly out of their way. Additional consideration must be given to the disabled since they may not
have the physical or cognitive ability to improvise (e.g. balancing along the curb or a very narrow path) or use
unofficial alternatives (e.g. using an adjacent grass surface). Temporary routes must meet the accessibility
guidelines of the ADA for permanent facilities and must be marked with the proper signage. Should existing
Supplementary Conditions Meridian Town Center
Page 107 of 114 Offsite Improvements - Phase 3
crosswalks at signalized intersections be closed or made inaccessible, temporary crosswalks should be painted
in an accessible location. Temporary signals should include pedestrian phases.
Contractors must not block temporary walkways with Contractor parking, materials piles, signs, rubble or
rubbish. Construction equipment and equipment operation must be separated from the temporary walkways.
At work zones where higher volumes of pedestrian traffic or school children exist, pedestrian fences or other
protective barriers may be needed to prevent access into the construction area.
22. CONSTRUCTION OF ADA FACILITIES
Contractor is responsible for determining the required construction surveying and grades to meet ADA
requirements for all pedestrian curb ramps listed in the plans. Station/Offset information provided in the plans
for ramp geometry are for general location reference only. Contractor will determine the specific length/slope
of all ramp features to meet ADA requirements that will include, but not be limited to:
a. Landing width, depth, and slope
b. Ramp width, cross slope, and running slope
c. Flare slopes
d. Truncated dome panel depth, distance from leading edge of curb line, depth, width, color and dome
dimensions.
ADA requirements for dimensions and slopes provided on ISPWC or ITD standard drawings and the plans are
generally absolute maximum and minimum values and no tolerances are allowable unless otherwise noted on
the plans.
23. WET WEATHER PAVEMENT CONSTRUCTION
Contractor is advised of possible wet weather construction. The pavement sections shown on Project plans
assume construction will occur during a dry period.
24. FAILED QUALITY ASSURANCE TESTS
Re-testing necessitated by the failure of quality assurance testing of materials placed by Contractor will be at
Contractor’s expense. These costs will be deducted from progress payments.
25. PROJECT MAINTENANCE DURING CONSTRUCTION
Contractor will be responsible for Project maintenance throughout the life of the contract. This responsibility
includes, but is not limited to, grading, proper and adequate drainage, access for emergency equipment, and
appropriate access for property owners and dust control.
Contractor will be responsible for maintaining both on-site and off-site roadway facilities that are adversely
affected by construction activities, including hauling. This maintenance may include, but is not limited to, street
sweeping to eliminate tracking (within the Project limits, adjacent streets, private driveways, and parking lots),
and roadway repairs due to truck and equipment traffic. Required roadway facility maintenance will be at the
discretion of the Agency’s Engineer.
The cost of all maintenance of the Work will be included in the Contract Price
Contractor will provide a water truck and driver at the disposal of Agency’s Engineer for dust abatement for use
at Agency’s Engineer discretion. Failure to adequately provide dust control will be grounds for stopping work
until the condition is corrected. If Contractor fails to provide adequate dust control, the Agency’s Engineer may
Supplementary Conditions Meridian Town Center
Page 108 of 114 Offsite Improvements - Phase 3
arrange for dust control by third parties. The costs to provide dust control by those other than Contractor if
required will be deducted from the progress estimates.
26. ACCESS DURING CONSTRUCTION
Access to adjacent properties must be maintained at all times. Access includes providing an adequate surface
(free of protruding rocks, holes and mud) for all emergency vehicles and pedestrians. Contractor must
coordinate with the on-duty captain for any traffic control changes in front of the fire station or work on their
approach.
27. COORDINATION WITH UTILITIES
Contractor is responsible for contacting and coordination with any utility providers as necessary for the
successful completion of the Project. The coordination will include, but not be limited to, working other than
normal operation hours to permit the relocation of utilities and construction of the roadway within the time
frame of this contract.
Utility coordination was requested through identified utility companies during the design of the Project. Utility
information is shown only for surface features, and if provided by the owner of the utility for non‐surface
features. The information shown is for reference purposes only and does not necessarily represent actual field
conditions. Engineer assumes no liability for the accuracy of the information shown, or conflicts due to
inaccurate or incomplete utility information. Contractor must call Dig Line a minimum of forty-eight (48) hours
prior to any excavation to request utility locations at 1‐800‐342‐1585. Dig Line does not cover ITD owned utilities
and Contractor will be responsible for contacting ITD to identify the location of their owned utilities.
Contractor must expose all existing utility crossings to verify locations and elevations prior to any other
construction that may affect those utilities. Contractor will coordinate and accommodate work with utility
companies. The utility company contacts are provided elsewhere in the Contract Documents, and/or are
available in the public records.
28. DAMAGE BEYOND CONSTRUCTION LIMITS
Contractor must promptly repair damage to any property outside the construction limits of the Work.
Contractor will obtain a release from the property owner specifying that they are satisfied with the repair work.
A copy of the letter will be submitted to Agency and Developer. Final release of contract retainage will not be
authorized until this provision has been met.
29. RETAIN & PROTECT EXISTING ITEMS
All items outside of the right‐of‐way and temporary construction easements must be protected unless
specifically noted otherwise on the plans.
30. PROPERTY CORNERS & SURVEY MONUMENTS
Reference all public and private land survey monuments that will be disturbed by construction activities prior
to disturbing. Reestablish the monuments at no additional cost to the Agency’s and Developer before Final
Completion of the Project. Section corner and Quarter corner monuments reset after construction must include
corner perpetuations and filing with the appropriate county. Perform all monument work in accordance with
Title 55, Chapter 16, Idaho State. If a monument is found during construction but is not shown on the Contract
Documents and must be reset, Contractor will notify Developer prior to reestablishing at Developer’s expense.
31. STORM DRAIN & IRRIGATION FLOWS
Supplementary Conditions Meridian Town Center
Page 109 of 114 Offsite Improvements - Phase 3
Contractor is responsible for transmitting existing storm drain and irrigation flows during construction. The
existing roadside ditches carry both storm drain and irrigation flows. Maintaining these flows may require
Contractor to install temporary collection, pumping and bypass systems.
32. ASPHALT CUTTING
All cutting of existing asphalt pavement must be by saw cut.
33. TRENCHES
Unless otherwise indicated in the Drawings or Special Provisions, trench excavation and bedding requirements
will be in accordance with Division 300 "Trenching" of the ISPWC Specifications except as noted herein. All costs
associated with pipe backfill (which must be lean concrete or similar) will be included in the Contract
Price.
34. SOURCES
Contractor must use approved commercial source(s) for all materials to be embanked or processed for
placement. Sources that are owned or controlled by any state or county owned or controlled sources will not
be allowed for this Contract. Contractor to assume all costs incurred for obtaining approvals for use of source(s).
35. EXCESS MATERIAL SITE
Excess or unsuitable material removed from the Project will become property of Contractor. Contractor will be
responsible for providing a site for the disposal of excess or unsuitable materials. If bituminous material is to be
disposed of, it is the responsibility of Contractor that the site will meet the requirements of the Idaho
Department of Environmental Quality, EPA and have all applicable permits and environmental clearances. All
excess material sites must be approved by Agency and Developer. No separate payment will be made for the
acquisition or operation of the sites, or for loading, hauling or unloading the materials at the site.
36. PROPERTY OWNER COORDINATION
Contractor will coordinate items of Work affecting adjacent property with the property owner(s) or their agents.
37. WARNING & REGULATORY SIGNS
Existing warning and regulatory signing must be retained and protected throughout the Project limits unless
otherwise noted. This may require multiple relocations. Existing warning and regulatory signs that are
designated for removal and replacement and do not conflict with construction traffic control signs will be
maintained during construction and, if necessary, relocated to locations where the signs are visible to traffic and
serve their original purpose.
38. ON SITE SUPERVISION
Contractor will provide competent on‐site supervision during all construction activities, including all
Subcontractor activities. The superintendent must be identified at the preconstruction conference, and will at
a minimum be on‐site from the notice to proceed date to the completion date. If Contractor must replace any
superintended (which will be governed by the General Conditions), Contractor must notify Agency and
Developer within five (5) working days before the event occurs.
39. COORDINATION FOR IRRIGATION CONSTRUCTION
Supplementary Conditions Meridian Town Center
Page 110 of 114 Offsite Improvements - Phase 3
Contractor will be responsible for contacting and working with the irrigation district, ditch riders, property
owners, and any other parties as reasonably necessary to coordinate and install irrigation facilities required
under this Contract.
Contractor will not cause the interruption of irrigation water flows. Contractor will take whatever measures are
necessary to conduct their work, including installing irrigation facilities, in a manner that will not interrupt the
delivery of irrigation water or otherwise cause adverse effects to the irrigation water delivery system or to
irrigation water users. The measures may include conducting work outside of normal hours.
Contractor will be solely liable for any damage claims due to its failure to comply with this section.
40. HIGH WATER TABLE AND DEWATERING
Contractor is advised that a high water table may exist in the Project area.
Construction activities that require excavation may also require dewatering. If dewatering is required, the water
surface will be maintained at least 1-foot below the bottom of the excavation. Contractor will coordinate all
dewatering activities with Agency and Developer prior to construction and obtain a short term Activity
Exemption from Idaho Department of Environmental Quality by contacting Craig Shepard at 373-0550.
Water levels will be maintained below the trench bottom during all types of pipe laying and joining operations.
The dewatering method must be discussed with Engineer and approved prior to construction. Dewatering
methods will comply with the construction General Permit (NPDES Permit) filed by Contractor and ITD approved
SWPPP plan. Contractor will provide a written dewatering plan to be included in the SWPPP. Non-compliance
must be noted in the inspection report and included in the SWPPP. SWPPP must be modified to correct non-
compliance within 7 calendar days. Ditches or other facilities that are silted in due to Contractor's dewatering
activities will be cleaned and restored to their original state. All dewatering on the Project is part of the Work.
Contractor will be required to modify Contractor’s equipment or operations to prevent damage to the exposed
subgrade because of high ground water.
Contractor is responsible for maintaining the integrity of the exposed subgrade. Degradation due to Contractor’s
operations will be remedied under guidance of a geotechnical engineer at Contractor’s expense.
41. LIEN RELEASE FORMS
The conditional and unconditional lien releases referenced in Section 14.02(A) of the General Conditions must
be in the following form unless otherwise approved by Developer:
WAIVER AND RELEASE FORMS
CONDITIONAL WAIVER AND RELEASE UNCONDITIONAL WAIVER AND RELEASE
The undersigned Contractor hereby waives and
releases all mechanics’ lien rights, claims of lien,
equitable liens and bond rights on or against
Developer or Project for all labor, services,
subcontract work, equipment and material
furnished up to and including ___________ (the
“Release Date”) excepting only (i) amounts retained
The undersigned Contractor has been PAID IN FULL
and hereby waives and releases all mechanics’ lien
rights, claims of lien, equitable liens and material
bond rights on or against Developer or Project for all
labor, services, subcontract work, equipment and
material furnished up to and including __________
(the “Release Date”) excepting only (i) amounts
Supplementary Conditions Meridian Town Center
Page 111 of 114 Offsite Improvements - Phase 3
by Developer, (ii) items furnished after the Release
Date and (iii) if checked here □, the attached list of
outstanding items. This release does not cover any
retention or items furnished after the Release Date.
Contractor will hold Developer harmless from and
against any and all claims on account of work
performed and materials furnished on the project
up to and including the date set forth below by any
third parties on behalf of Contractor.
This release is CONDITIONAL, and will be effective
only upon payment to Contractor in the sum of
$______________________. If payment is by check,
this waiver is effective only when check is paid by
the bank upon which it is drawn. Before any person
relies on this release, such person should verify
payment to Contractor.
This release is for the benefit of, and may be relied
upon by Developer, its lenders and the guarantor of
any loan made by its lenders and the principal and
surety on any labor and material bond posed for the
Project.
I CERTIFY UNDER PENALTY OF PERJURY UNDER
LAWS OF THE STATE OF IDAHO THAT THE ABOVE IS
A TRUE AND CORRECT STATEMENT.
SIGNATURE:
____________________________________
(Authorized Corporate Officer/Partner/Developer)
(Title) _________________________________
Company Name: ________________________
Dated this ___ day of ______________, 201__
Project Name: __________________________
Project Address: ________________________
______________________________________
retained by Developer, (ii) items furnished after the
Release Date and (iii) if checked here □, the attached
list of outstanding items. This release does not cover
any amounts retained by Developer or items
furnished after the Release Date. Contractor will
indemnify, defend and hold Developer harmless from
and against any and all claims for payment on account
of work performed and materials furnished on the
Project up to and including the date set forth above
by any third parties through or on behalf of
Contractor.
This release is UNCONDITIONAL and will be effective
immediately. This release is for the benefit of, and
may be relied upon by Developer, its lenders and the
guarantor of any loan made by its lender and the
principal and surety on any labor and material bond
posed for the Project.
NOTICE: THIS DOCUMENT IS ENFORCEABLE
AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE
NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE
A CONDITIONAL WAIVER AND RELEASE FORM.
I CERTIFY UNDER PENALTY OF PERJURY UNDER
LAWS OF THE STATE OF IDAHO THAT THE ABOVE IS
A TRUE AND CORRECT STATEMENT.
SIGNATURE:
____________________________________
(Authorized Corporate Officer/Partner/Developer)
(Title) _________________________________
Company Name: ________________________
Dated this ___ day of ______________, 201__
Project Name: __________________________
Project Address: ________________________
______________________________________
A. The conditional lien releases referenced in Section 14.07(A)(3) of the General Conditions must be in the
following form unless otherwise approved by Developer:
CONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT
Upon receipt by the undersigned of a check from ___________________________ in the sum of
(Maker of Check)
$__________________ payable to _________________________________________________
Supplementary Conditions Meridian Town Center
Page 112 of 114 Offsite Improvements - Phase 3
(Amount of Check) (Payee or Payees of Check)
and when the check has been properly endorsed and has been paid by the bank upon which it is drawn, this
document will become effective to release any mechanic’s lien, materialman’s lien, construction lien, design
professional’s lien, or similar lien, any stop notice or bonded stop notice, or any bond right or claim the undersigned
has on the job of _______________________ located at
(Developer)
_______________________________________.
(Job Description)
This release covers the final payment to the undersigned for all labor, services, equipment, or material furnished on
the job, except for disputed claims for additional work in the amount of $________________. Before any recipient
of this document relies on it, the party should verify evidence of payment to the undersigned.
Dated: ____________________________ ________________________________
(Company Name)
By _____________________________
(Title)
B. The unconditional lien releases referenced in Section 14.07(A)(2) of the General Conditions must be in the
following form unless otherwise approved by Developer:
UNCONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT
The undersigned has been paid in full for all labor, services, equipment or material furnished, to
__________________ on the job of __________________ located at ______________________
(Your Customer) (Developer)
__________________________________________ and does hereby waive and release any
(Job Description)
right to a mechanic’s lien, materialman’s lien, construction lien, design professional’s lien, or similar lien, any stop
notice or bonded stop notice, or any right or claim against a labor and material bond on the job, except for disputed
claims for extra work in the amount of $______________.
Dated: ____________________________ ________________________________
(Company Name)
By _____________________________
(Title)
NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING
UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN
PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM.
Special Provisions Meridian Town Center
Page 113 of 114 Offsite Improvements - Phase 3
SPECIAL PROVISIONS
Special Provisions Meridian Town Center
Page 114 of 114 Offsite Improvements - Phase 3
SPECIAL PROVISIONS
These Special Provisions supplement the General Conditions and the Supplementary Conditions. In the event of any
conflict between these Special Provisions and the General Conditions or Supplementary Conditions, the requirement
that places the greater or more stringent obligation on Contractor will govern. All conditions, requirements, services
and other matters set forth in these Special Provisions are included in the Work and the Contract Price, and are to
be provided by Contractor without additional payment or consideration. Any provision of these Special Provisions
stating or implying that payments will be made for identified items or requirements under any basis or category will
be interpreted to mean that the item or requirement is included in the Contract Price and will be provided by
Contractor without any additional payment or compensation.
Capitalized terms not otherwise defined herein will have the meaning set forth in the General Conditions.
See the “Special Provisions” document provided by Engineer.
Provided, however, delete the Section entitled “Completion Time and Liquidated Damages”, as such matters are
addressed elsewhere in the Contract Documents.
The terms “site” and “project” and “contract” and similar words have the same meaning as “Site” and “Project” and
“Contract” and similar words as defined in the General Conditions.
PROJECT NO. A013(349); KEY NO. 13349 Page 1 of 35
SPECIAL PROVISIONS
IDAHO PROJECT NO. A013(349)
MERIDIAN TOWN CENTER – OFFSITE IMPROVEMENTS PHASE 3 Ada County
The following special provisions and all addenda issued supplement or modify the 2018 Idaho
Transportation Department Standard Specifications for Highway Construction:
2019 Supplementals for the Idaho Transportation Department 2018 Standard Specifications for
Highway Construction, 2020 Quality Assurance Manual, 2020 Quality Assurance Special Provision
for State Acceptance (10/19/2019), 2020 Special Provision for 405 Superpave Hot Mix Asphalt
(07/21/2020), 2020 Standard Drawings, and Title VI Special Provisions.
SOURCE IDENTIFICATION
Designated source(s): Designated source(s) are not identified for this contract/project.
Contractor provided sources. Provide an approved source(s) for all materials to be embanked or
processed for placement. Department owned or controlled sources will not be allowed for this contract.
Cost. Assume all costs incurred in obtaining approvals for use of source(s).
CONTRACT TIME AND LIQUIDATED DAMAGES
Work will not start earlier than July 14, 2021 or later than July 30, 2021 and must be completed within
120 working days.
Once started, work must continuously progress until completion.
The amount of liquidated damages for failure to complete the work on time will be $2,500 per day.
CONTRACTOR NOTES
CITY OF MERIDIAN UTILITY WORK
This contract contains work for the City of Meridian water main relocation and abandonment which will
be accomplished by Contractor forces under this construction project. All documents pertaining to this
work are included herein. Payment for completed in-place work for these utility improvements is subject
to approval by the City of Meridian. Coordinate material submittals, installation, field reviews, changes in
conditions and approvals with Jared Hale, City of Meridian Public Works Department, (208) 898-5500.
COMPACTION
All compaction to be Class “A” for this project, unless otherwise specified.
DAMAGE BEYOND CONSTRUCTION LIMITS
Damage to any area or items outside the construction limits of this project including, but not limited to
existing landscape, irrigation and storm drain facilities, utilities and pavement must be promptly restored
to original condition, or better. The cost to complete such repairs is considered the Contractor’s
responsibility, with no additional cost to the Owner. All items within the temporary construction
easements including, but not limited to, trees, bushes, utilities, pipes, driveways, planters, signs,
sprinklers, lawns, etc. must be retained and protected unless specifically noted otherwise on the plans or
approved.
PROJECT NO. A013(349); KEY NO. 13349 Page 2 of 35
DEWATERING
Groundwater levels vary throughout the year. Dewatering may be required for various construction
activities. Determine appropriate dewatering techniques and perform all dewatering measures, including
water-quality measures required to complete the project. Dewatering will be considered incidental to the
work item requiring dewatering and no separate payment will be made.
DIVERSITY MANAGEMENT SYSTEM 01/18
Vendor Account
All contractors, consultants, suppliers, and service providers bidding and performing the Department’s
federal-aid funded projects are required to register as vendors at https://itd.dbesystem.com. Vendors
register online once, with annual reminders to check and update their company information as needed.
The information vendors provide in the registration process is federally required. Also, vendors must
have system accounts in order to participate in the Department’s online contract payment reporting
program. This system is used by many neighboring states, so conduct a search for your business before
creating new account. If you have questions, the Department’s diversity management system includes a
“Help/First Time Visitors” section and training tutorials.
Bidder Registration
A bidders registration questionnaire is required after a vendor account has been created. If you have
questions, the Department’s diversity management system includes a “Help/First Time Visitors” section
and training tutorials.
ELECTRICAL WORK 01/18
This contract contains work for which a licensed electrical firm will be required. Complete the sheet
provided for compliance with IC 67-2310, or provide an explanation as to why an electrical license is not
required.
EMBANKMENT MATERIALS
Use granular subbase meeting the requirements of 703.11 for all project embankments.
EMPLOYMENT AGENCY 01/18
The designated employment agency is as follows:
Idaho Department of Labor Office
219 W. Main St.
Boise, ID 83735-0030
EQUIPMENT AND PETROLEUM STAGING AREAS
All staging and storage areas for equipment and materials (including fuel) must be approved prior to use.
Obtain all necessary environmental clearances prior to use. All costs associated with environmental
clearances will be considered incidental to other items of work and no separate payment will be made.
Locate all staging and storage areas, including fuel, a minimum of 150 feet away from wetlands,
irrigation ditches, and any other water features.
PROJECT NO. A013(349); KEY NO. 13349 Page 3 of 35
IDAHO IMPLEMENTATION OF AASHTO MANUAL FOR ASSESSING SAFETY
HARDWARE, 2ND EDITION (2016)
The following safety hardware must meet AASHTO 2016 MASH criteria, ITD’s Standard Drawings, and
if the hardware is a proprietary product it must be approved on ITD’s Qualified Product List (QPL) for
new permanent installations and full replacements:
· W-beam
· Cast-in-place concrete barriers
· W-beam tangent terminals and buried-in-backslope terminals
· W-beam flared terminals and terminals installed on a flare
· Crash cushions
· Transitions
· Permanently installed portable barriers
· Bridge rails
For contracts with a letting date/bid opening date after December 31, 2019, the following safety hardware
may be MASH 2009/2016 or NCHRP 350 complaint for new permanent installations and full
replacements:
· Cable barriers
· Double-sided or median terminals
· Cable barrier terminals
· Sign supports
· All other breakaway hardware
For projects utilizing December 2018 Standard Drawings release or earlier, replace the 612 series sheets
with the 612 series from the latest Standard Drawings release.
Temporary work zone devices (including portable barriers, truck- and trailer-mounted attenuators,
portable changeable message signs (PCMS), temporary traffic signals, and camera trailers) manufactured
after December 31, 2019, must have been successfully tested to the 2016 edition of MASH. Such devices
manufactured on or before this date, and successfully tested to NCHRP Report 350 or the 2009 edition of
MASH, may continue to be used throughout their normal service lives.
PAVEMENT SURFACE SMOOTHNESS 01/18
Meet (Straight Edge) pavement smoothness.
REQUIREMENTS OF THE CONTRACTOR WHEN ON RAILROAD PROPERTY 06/19
Union Pacific Railroad (Railroad Company), at its determination, may provide inspection, security,
flagging, or other protective services as necessary for the protection of the Railroad Company property or
operations whenever there are Contractor operations on Railroad Company property. Costs charged to
the Contractor for services provided by the Railroad Company will be reimbursed by the Department at
invoice cost.
Consider recommendations made by the Railroad Company regarding activities or operations on Railroad
Company property. The Department will not relieve the Contractor of liability by accepting
recommendations made by the Railroad Company.
All employees needing access to Railroad Company property must hold a current certification of safety
training as required by the Railroad Company. Visit https://contractororientation.com to access training
courses. Training fees are incidental to mobilization.
PROJECT NO. A013(349); KEY NO. 13349 Page 4 of 35
The Railroad Company reserves the right to stop and/or require modifications to any Contractor
operations on Railroad Company property that, at the Railroad Company determination, could create or is
creating an eminent hazard to Railroad Company property or operations.
Perform work on Railroad Company property in a manner satisfactory to the Railroad Company. Perform
work at a time and in a manner that will not damage the track or interfere unnecessarily with the
movement of trains or other authorized users of the track(s) of the Railroad Company.
Notify the Railroad Company at least 30 business days before the start of work on Railroad Company
property to enable the Railroad Company to furnish railroad flagging or other protective services as might
be necessary to ensure the safety of Railroad Company operations.
Dress suitably to perform work safely and in a manner that will not interfere with vision, hearing, or free
use of hands or feet when on Railroad Company property. Wear the following clothing and personal
protective equipment:
a) Waist length shirts with sleeves.
b) Trousers covering the entire leg, with any flare-legged style tied to prevent catching.
c) Sturdy footwear such as work boots. No open-toed (e.g., sandals), thin soled (e.g., tennis or
walking shoes), or high-heeled shoes are allowed.
d) ANSI Class II or III highly visible outer wear.
e) Protective headgear per ANSI/ISEA Z89.1, latest revision. The Department recommends that all
hard-hats be affixed with the entity’s name or logo.
f) Eye protection per ANSI/ISEA Z87.1, latest revision. Provide additional eye protection to meet
specific job situations (e.g., welding, grinding).
g) Hearing protection per 29 CFR 1910.95.
Contact the Railroad Company at 1-888-877-7267 before commencing work on Railroad Company
property to determine if any telecommunication or other facilities are located within the area. Locate and
protect any known telecommunication facilities at no expense to the Railroad Company.
Do not discharge explosives on Railroad Company property without the prior consent of the Railroad
Company. The Railroad Company reserves the right to impose additional conditions and restrictions on
the Contractor when explosives are used, stored, or transported on Railroad Company property in addition
to the following:
a) Provide a minimum of 48 hours’ notice to the Department and the Railroad Company, excluding
weekends and holidays, before discharging any explosives unless the Railroad Company has
agreed otherwise.
b) Discharge explosives loaded in holes or otherwise readied for discharge that same day during
daylight hours at a time acceptable to the Railroad Company.
c) Take precautionary measures and construct temporary shelters necessary to guard against danger
of damage, destruction, or interference arising out of or connected with any blasting,
transportation, handling, storage, security, or use of explosives, at no expense to the Railroad
Company.
d) Use, store, and transport explosives in a manner acceptable to the Railroad Company and in
accordance with local, state, and federal laws and regulations, including, without limitation,
United States Department of Labor, Bureau of Labor Standards, Safety and Health Regulations
for Construction, 29 CFR Part 1518, Subpart U--"Blasting and the Use of Explosives;" and
Occupational Safety and Health Administration Occupational Safety and Health Standards, 29
CFR Part 1910, Subpart H--"Hazardous Materials".
Do not foul the drainage ditches or railroad ballast with debris. Remove all debris at the completion of
the work at no expense to the Railroad Company.
PROJECT NO. A013(349); KEY NO. 13349 Page 5 of 35
Do not place combustible material, erect any structure, or obstruct the view along the tracks on Railroad
Company property without prior approval from the Railroad Company.
TRAFFIC SIGNAL EQUPMENT REMOVAL AND SALVAGE
The existing traffic signal equipment specified for removal and salvage to ACHD in the plans for the
Eagle Road signals shall remain the property of the Ada County Highway District and shall be delivered
to the ACHD Signal Shop at 3775 N Adams St, Garden City, ID. Please contact Brian Crespin (208)
387-6190 or the designated ACHD Signal Inspector for arrangements. Other existing signal equipment
specified for removal and disposal shall become the property of the Contractor and shall be disposed of in
accordance with procedures documented in the 2018 ITD Standard Specifications for Highway
Construction or as directed by the ITD or ACHD Representative. Removal of the existing signal
equipment shall be incidental to the associated signal pay item for each specific signal.
USE TAX 3/13
The exercise of control over State-owned material (or ACHD owned material) by a Contractor who is
improving real property (roadways, etc.) will incur the imposition of a use tax by the State.
Contact the Idaho State Tax Commission (Telephone No. (208) 334-7618) concerning Section 63-3609,
Idaho Code, and IDAPA 35, Title 01, Chapter 02, Sales Tax Administrative Rule 012, "Contractors
Improving Real Property", and Rule 013, "Road and Paving Contractors".
In the case of aggregates the amount of this tax will differ depending on whether the material is obtained
from a State-owned material source or whether it is obtained from a State-owned stockpile. Use tax is
due on the fair market value of the material, and the crushed value is higher than for unprocessed
material.
The tax will also differ depending on whether a Contractor both crushed the material and placed it on the
roadway, or the Contractor performs only one of these operations and hires a subcontractor to perform the
other. If the contractor hires a subcontractor to crush the material, he must pay a sales tax to the crusher
for this fabrication labor. If the Contractor crushes and applies the material, or gives material he crushes
to a subcontractor for application, the Contractor owes use tax on the royalty value.
Tables for ACHD and City of Meridian supplied equipment are shown under the specific pay items.
The cost of State supplied materials is:
Signal Equipment (656-005A): $23,198.35
Signal Equipment (656-005B): $41,739.35
Signal Equipment (656-005C): $0.00
Signal Equipment (656-005D): $0.00
ATMS Equipment (S904-05A): $0.00
TOTAL: $64,937.70
ON PAGE 26, SUBSECTION 102.03 – EXAMINATION OF PLANS, SPECIFICATIONS, AND
PROJECT SITE 05/19
Replace the first sentence of the 3rd paragraph with the following:
Immediately notify the Owner in writing of any errors or omissions on the plans and proposal
forms or inconsistencies between these documents and the project site. Do not take advantage of
errors or omissions in the contract documents.
PROJECT NO. A013(349); KEY NO. 13349 Page 6 of 35
ON PAGE 30, SUBSECTION 103.02 - AWARD OF CONTRACT 1/18
Add the following after the second paragraph.
The Owner may delay the award to obtain approvals from ITD. The Owner will not consider
increases in costs because of this delay in award.
ON PAGE 32, SUBSECTION 104.01 - INTENT OF CONTRACT 01/18
Add the following:
Voluntary Partnering:
The Department encourages the foundation of a cohesive partnership between the Department
and the Contractor with its subcontractors. Structure the partnership to draw on the strengths of
each organization to identify and achieve reciprocal goals. Ensure objectives are effective and
efficient with contract performance and completion within budget, on schedule, and in
accordance with the contract.
Ensure partnership is bilateral in makeup, and participation is voluntary. Any cost associated
with effectuating this partnering will be agreed to by both parties and shared equally.
The Contractor's on-site project manager and the Engineer will meet to implement this partner
initiative within 30 calendar days of notice to proceed and before the preconstruction conference,
to plan a partnering development seminar/team building workshop. This planning session should
determine attendees, agenda, duration, and location. Suggested attendees include the Department
representatives (the Engineer and key project personnel) and the Contractor's project management
(e.g., on-site project manager and key supervision personnel and subcontractors). The project
design engineers and key local government personnel should be invited to attend as necessary.
Hold periodic follow-up workshops throughout the duration of the contract as agreed by the team
members.
A partnership charter does not change the legal relationship between the parties to the contract
nor relieve either party from the terms of the contract.
ON PAGE 39, SUBSECTION 105.07 – UTILITY FACILITIES 01/18
Add the following:
Request locates of buried utilities by contacting the Utility One-Call Center by calling 1-800-342-1585, e-
mailing digline@digline.com or faxing 1-800-342-1586.
The following utility companies have facilities located with the project limits. Coordinate with the
following utility companies.
AT&T
JT Andrews – (208) 841-5093
jt@cwc64.com
AT&T has existing facilities in CenturyLink conduit along Eagle Rd between Pine and Fairview
that will be impacted by proposed improvements. CenturyLink responsible for relocation.
Coordinate timing for CenturyLink to perform relocation and/or adjustments.
PROJECT NO. A013(349); KEY NO. 13349 Page 7 of 35
City of Meridian
Jared Hale – (208) 898-5500
jhale@meridiancity.org
Engineering Project Manager – Public Works Department
Relocation work to be performed by Contractor under this contract. Coordinate all work with City
of Meridian.
CenturyLink (Includes Level 3 Communications facilities on Plans)
Brandy Walker – (208) 454-4059
brandy.walker@centurylink.com
Local Network Engineer
CenturyLink has existing facilities along Eagle Rd impacted by proposed improvements.
Coordinate timing for CenturyLink to perform relocation and/or adjustments.
Idaho Power
Ethan Morgan – (208) 388-6510
emorgan@idahopower.com
Project Manager
Idaho Power has existing facilities along Eagle Rd impacted by proposed improvements.
Coordinate timing for Idaho Power to perform relocation and/or adjustments.
Intermountain Gas Company
Will Lindsey – (208) 484-8278
Will.lindsey@intgas.com
Intermountain Gas has existing facilities along Eagle Rd impacted by proposed improvements.
Coordinate timing for Intermountain Gas to perform relocation and/or adjustments.
Nampa & Meridian Irrigation District (NMID)
David Duvall – (208) 466-0663
dduvall@nmid.org
Assistant Water Superintendent
NMID has existing facilities along Eagle Rd impacted by proposed improvements. Coordinate
timing for NMID to perform relocation and/or adjustments.
Settlers Irrigation District (SID)
Mack Myers – (208) 343-5271
mack@settlersirrigation.org
SID has existing facilities along Eagle Rd impacted by proposed improvements. Coordinate
timing for SID to perform relocation and/or adjustments.
Sparklight (Cable One on Plans)
Matthew Gibbs – (208) 455-5562
Matthew.Gibbs@Sparklight.biz
Construction Coordinator
Sparklight has existing facilities along Eagle Rd impacted by proposed improvements. Coordinate
timing for Sparklight to perform relocation and/or adjustments.
PROJECT NO. A013(349); KEY NO. 13349 Page 8 of 35
Syringa Networks
Chase McCoy – (208) 866-3716
cmccoy@syringanetworks.net
Outside Plant Technician
Syringa has existing facilities along Eagle Rd impacted by proposed improvements. Coordinate
timing for Syringa to perform relocation and/or adjustments.
Zayo Fiber Group (Includes Integra Telecom facilities on Plans)
Gary Foster – (817) 665-4685
Gary.foster@zayo.com
Zayo has existing facilities along Eagle Rd impacted by proposed improvements. Coordinate
timing for Zayo to perform relocation and/or adjustments.
ON PAGE 61, SECTION 106.09 – MATERIAL SOURCES
Add the following:
Provide weed control as specified in 107.20 in all sources to prevent transfer of noxious weeds to
the project.
ON PAGE 74, SUBSECTION 107.10 RESPONSIBILITY FOR INJURY DAMAGE 06/19
Add the following:
D. Insurance for Railroad
Protect and hold harmless Union Pacific Railroad and any authorized user (any entity that has
rights by permit, agreement, or contract to use Railroad Company property including its tracks)
against all loss, liability, and damage arising from the Contractor activities on Railroad Company
property.
Before commencing work on Railroad Company property and without expense to the Railroad
Company, furnish the following insurance to the Railroad Company and include coverage for
Authorized Users:
Railroad Protective Liability Insurance naming the Railroad Company as insured with a
combined single limit of $2,000,000 per occurrence with a $6,000,000 aggregate for bodily injury
and property damage. The policy form will be AAR-AASHTO with broad form coverage for
"Physical Damage to Property" (ISO Form GL 00 30) or as revised ISO-RIMA (Form CG 00 35)
and include pollution arising out of fuels and lubricants brought to the project site (ISO Form CG
31 or equivalent). This insurance might be available for purchase through the Railroad Company.
Union Pacific Railroad Company requires a company issued “folder number” that can be
obtained from the company’s Real Estate Office through Casey Moore at (402) 544-8549.
Provide certificates of insurance to the Railroad Company and the Department. Maintain this
insurance in full force when working on Railroad Company property. Insurance must be
acceptable to the Railroad Company, written by an insurance company authorized to transact
business in Idaho with a current Best’s Insurance Guide Rating of B and Class VII or better.
Include the cost of providing railroad protective liability insurance in the cost of mobilization.
PROJECT NO. A013(349); KEY NO. 13349 Page 9 of 35
ON PAGE 82, SUBSECTION 108.01 - SUBLETTING OF CONTRACT 01/18
Delete the second sentence and substitute the following:
If the Engineer consents to subletting a portion of the work, the Contractor will use its own
organization to perform work amounting to at least 30 percent of the original contract amount.
ON PAGE 84 of 548, SECTION 107.20 – WEED CONTROL
Add the following:
Inspect fill material and locations before transporting and using on the project. The origin of the
material and surrounding soils of the source shall be included in the inspection documentation.
The State of Idaho Department of Agriculture Seed Laboratory, Boise, Idaho (208) 332-8630,
may test source locations at the request of the Engineer.
ON PAGES 104 AND 105, SUBSECTION 109.04 – INCREASES OR DECREASES DUE TO
TAXES 10/19
Delete subsection 109.04, in its entirety, and replace with the following:
109.04 Increases or Decreases Due to Taxes.
The total contract amount includes applicable federal, state, and local taxes and duties. The
Owner will not adjust the contract amount for increases or decreases due to taxes, unless the
amount of an increase or decrease is greater than $100.00 from the contract amount. Notify the
Engineer promptly of a statute, court decision, written ruling, or regulation that will result in an
increase or decrease in the contract amount. Price escalation will be calculated in accordance with
109.02.B using ITD’s form (e.g., ITD-2624, ITD-2625).
A. Increases Due to Taxes.
The Owner will increase the contract amount if the following conditions exist:
1. A statute, court decision, written ruling, regulation, or price escalation on materials (e.g.,
asphalt) based on nationally published cost indexes increases federal, state, or local
excise tax or duty on the transactions or property covered by the contract and takes effect
after the contract date or causes an increase in sales tax burden through price escalation.
2. The statute, court decision, written ruling, or regulation was unanticipated by the Owner
and the Contractor before the contract date.
3. The Contractor pays or bears the burden of the federal, state, local excise tax or duty, or
rate increase. The Owner will increase the contract amount by the amount of the tax,
duty, or rate increase paid by the Contractor. If requested by the Engineer, verify in
writing the new federal, state, local excise tax or duty, or rate increase was not included
in the contract amount.
B. Decreases Due to Taxes.
The Owner will decrease the contract amount if the following conditions exist:
1. A statute, court decision, written ruling, regulation decreases federal, state, or local excise
tax or duty on the transactions or property covered by the contract and takes effect after
PROJECT NO. A013(349); KEY NO. 13349 Page 10 of 35
the contract date.
2. The statute, court decision, written ruling, regulation, or price de-escalation on materials
(e.g., asphalt) based on nationally published cost indexes was unanticipated by the Owner
and the Contractor before the contract date or causes a decrease in sales tax burden
through price de-escalation.
3. The Contractor pays or bears a lesser burden for federal, state, local excise tax or duty, or
rate decrease. The Owner will decrease the contract amount by the amount of the relief,
refund, or drawback. Pay this amount to the Owner as directed. The Owner will also
decrease the contract amount if the Contractor, through fault or negligence or failure to
follow the Engineer’s instructions, is required to pay or bear the burden of a federal, state,
or local excise tax or duty, or does not obtain a refund or drawback.
203-130A & 203-130B REMOVAL (OBLITERATION) OF PAVEMENT MARKINGS
ON PAGE 123, SUBSECTIONS 203.01 - DESCRIPTION
Add the following:
Description. Removal (or obliteration) of pavement markings shall include removing designated painted
pavement markings and/or plastic pavement marking tape, in accordance with these specifications, as
shown on the plans, or as directed. Areas to be removed include pavement markings that will conflict
with construction traffic control (including detour) and construction traffic control markings that will
conflict with the final permanent pavement markings shall be promptly obliterated.
ON PAGE 123, SUBSECTIONS 203.02 - MATERIALS
Add the following:
Materials. The asphalt used for the fog coat shall conform to Section 702.
ON PAGE 123, SUBSECTIONS 203.03 - CONSTRUCTION REQUIREMENTS
Add the following
Construction Requirements. Removal shall be accomplished before any change is made in the traffic
pattern. The method of obliteration shall be one that which leaves minimal pavement scars, visible paint
or surface texture differences that could be confused with pavement markings. Painting over existing
stripes with black out paint, asphaltic products, etc. is not considered to meet the requirements for
obliteration.
Blasting using a hard and angular abrasive is the preferred method of removing painted pavement
markings and grinding is the preferred method of removing thermoplastic type pavement markings. Both
methods of removal shall require a fog coat of asphalt to be placed over all areas that have had pavement
markings obliterated to relieve ghosting of the obliterated lines. The fog coat shall be applied as specified
in Section 408. All equipment used for removal or applying the fog coating shall be capable of meeting
the time constraints as noted in the plans. Fog coats shall not be used on concrete surfaces.
The grinding equipment shall have a self-contained dust collection system capable of containing the waste
debris and dust that will be produced. Waste debris shall be disposed of in an approved upland solid
waste site. The grinder unit shall be able to control the maximum depth of the grooves to 1/8 inch below
the average pavement surface profile. The average pavement surface profile shall be determined using a
Tire Tread Depth Gage. The Tire Tread Depth Gage shall be placed on the pavement surface and the
plunger depressed until contact is made with the bottom of the pavement. The gage is then removed
without disturbing the plunger. The surface profile is read to the nearest 1/32 inch on the calibrated
plunger. The plunger is then zeroed and the procedure is repeated until three readings are taken in four
PROJECT NO. A013(349); KEY NO. 13349 Page 11 of 35
different locations of the work. The readings are then averaged to calculate the average pavement surface
profile. The grinding shall not be more than 1/8 inch below the average of these readings. The grinder
head shall be capable of rotating to meet the slope of the roadway so that one edge will not grind deeper
that the other edge. The grooved area shall be uniform in depth and width. If grooved depth exceeds 1/8
inch below the average pavement surface profile, work shall be suspended until corrective measures are
identified by the Contractor and approved. Any pavement marking remaining after grinding shall be
removed by blasting.
ON PAGE 125, SUBSECTIONS 203.04 - METHOD OF MEASUREMENT
Add the following
Method of Measurement. Obliteration of Pavement Markings (lane lines) will be measured by the
square foot pavement marking. Obliteration of Special Pavement Markings (stop bars, cross walks, turn
arrows, or turn lane text) as well as longitudinal markings and will be measured by the square foot of
pavement marking removed.
ON PAGE 125, SUBSECTIONS 203.05 - BASIS OF PAYMENT
Add the following
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
203-130B Removal (Obliteration) of Pavement Markings SF
No payment will be made for areas where grooving exceeds 1/8 inch. No separate payment will be made
for removal of traffic buttons. Asphalt for fog coat shall be considered incidental to this item and no
additional payment will be made.
ON PAGE 151, SUBSECTION 213.02 – MATERIALS
Add the following:
Do not place fine grained subsurface soils from unsuitable excavation in infiltration basins,
retention/detention basins, or within roadside ditches.
ON PAGE 416, SUBSECTION 621.05 – BASIS OF PAYMENT
Add the following after the last paragraph:
If seeding is performed between May 1st and October 14th, watering shall be considered as
incidental to seeding and the cost thereof included in the contract unit price for seeding.
ON PAGE 418, SUBSECTIONS 616.04 – DESCRIPTION, METHOD OF MEASUREMENT
Replace with the following
The engineer will measure acceptably complete work by the following:
Signs: Sign will be measured to the nearest 0.1 square foot. All brackets, brace angles and other
aspects of the installation shall be incidental and included in the measured square footage.
Installation of signs shall include all signs, brackets, and braces as well as installation
PROJECT NO. A013(349); KEY NO. 13349 Page 12 of 35
Posts: Breakaway wood and steel sign posts shall be measured per each including the foundations
and shall include installation and any repairs to existing landscaping elements impacted by the
installation.
Reinstall Signs: Existing signs to be relocated and installed on new posts with new brackets shall
include the costs of new brackets and braces as well as installation. Measured by total sign and post
assembly. Multiple sign panels on a single post shall be counted as a single reinstallation.
SECTION 616-SIGNS AND SIGN SUPPORTS
ON PAGE 418, SUBSECTIONS 616.04 – DESCRIPTION METHOD OF MEASUREMENT
Replace with the following
The engineer will measure acceptably complete work by the following:
Signs: Sign will be measured to the nearest 0.1 square foot. All brackets, brace angles and other
aspects of the installation shall be incidental and included in the measured square footage.
Installation of signs shall include all signs, brackets, and braces as well as installation
Posts: Breakaway wood and steel sign posts shall be measured per each including the foundations
and shall include installation and any repairs to existing landscaping elements impacted by the
installation.
Reinstall Signs: Existing signs to be relocated and installed on new posts with new brackets shall
include the costs of new brackets and braces as well as installation. Measured by total sign and post
assembly. Multiple sign panels on a single post shall be counted as a single reinstallation.
ON PAGE 418, SUBSECTIONS 616.05 – BASIS OF PAYMENT
Replace with the following.
Payment for accepted work will be made as follows:
Pay Item Pay Unit
616-010A New Sign Type B (complete) SF
616-050A Breakaway Steel Sign Post, Type E EA
616-055A Breakaway Wood Sign Post (Type D) EA
616-080A Reinstall Signs (complete) EA
ON PAGE 429, SUBSECTION 621.01 – DESCRIPTION
Add the following:
Apply seed, including seed bed preparation, fertilizing, seeding, mulch mixtures, mulching,
mulch anchoring (mechanical or tackifiers), HECPs, erosion blankets, and watering in the areas
as shown in the plans.
The Owner may require seeding operations in conjunction with Subsection 212.
621-005A Seed Bed Preparation – 1.283 Acres
621-010A Seeding – 1.283 Acres
621-015A Mulching – 1.283 Acres
621-035A Fertilizing – 1.283 Acres
PROJECT NO. A013(349); KEY NO. 13349 Page 13 of 35
Seed all disturbed areas on the project site, including foreslope, backslope, embankment areas or
as directed. Complete seeding operations by hydroseeding methods.
ON PAGE 429, SUBSECTION 621.03.A – GENERAL
Replace the first sentence of the fifth paragraph with the following:
Use broadcast seeding or hydroseeding applications on all slopes as indicated on the plans.
ON PAGE 430, SUBSECTION 621.03 – CONSTRUCTION REQUIREMENTS
Add the following to Part B. Seedbed Preparation:
Have Engineer preapprove all topsoil material within the project area before moving and placing
the topsoil in areas to be seeded.
Topsoil material must conform to section 107.20 and section 213 prior to placement.
ON PAGE 431, SUBSECTION 621.03 – CONSTRUCTION REQUIREMENTS
Part D - SEEDING
Delete the first sentence and replace with the following:
Furnish seed in accordance with 711.05 Seed. Use the mix and rate of seeding specified.
Delete first sentence of paragraph 3.
Add the following to the third paragraph:
Agitation of seed in hydro-seeder shall not exceed 30 minutes. Do not allow trucks or equipment
on the area after seed is in place.
Apply seed directly to the soil surface after seedbed preparation. Seed disturbed areas as stated
above with the following the seed mix and rates.
Seed mix for disturbed ground in the right-of-way, mechanical seeding 3:1 or flatter slopes:
Grass Species Mix
· Ephraim Crested Wheatgrass (AGCR) – 2 lbs/ac
· Sheep Fescue (FEOVO) – 4 lbs/ac
· Mountain Home Sandberg Bluegrass (POSE) – 4 lbs/ac
· Indian Ricegrass (ORHY) – 6 lbs/ac
· Thickspike Wheatgrass – 10 lbs/ac
Seed Mix for areas beyond 20 feet of end of pavement and slopes steeper than 3:1:
Grass & Native Species Mix
· Ephraim Crested Wheatgrass (AGCR) – 2 lbs/ac
· Mountain Home Sandberg Bluegrass (POSE) – 4 lbs/ac
· Sheep fescue (FEOVO) – 4 lbs/ac
· Indian Ricegrass (ORHY) – 6 lbs/ac
· Thickspike Wheatgrass – 10 lbs/ac
PROJECT NO. A013(349); KEY NO. 13349 Page 14 of 35
· Western Yarrow (ACMIL) – 2 lbs/ac
· Lewis Blue Flax (LILE) – 5 lbs/ac
ON PAGE 432, SUBSECTION 621.03 – CONSTRUCTION REQUIREMENTS
Add the following to 621.03.E.1:
Apply soil amendments (compost, or manufactured organic soil amendments) at manufacturer’s
recommended rate according to the slope gradient and soil conditions. Submit manufacture’s
recommended rates for each product to be used prior to application and a copy of the purchase
invoices after approval.
ON PAGE 432, SUBSECTION 621.03 – CONSTRUCTION REQUIREMENTS
Add the following to 621.03.E.3.
Provide a qualified hydraulic mixture with longevity of 6-12 month period. Mulch shall have a
Cover Factor meeting Large Scale Testing of < 0.01 coverage (or not to exceed 0.05% coverage);
must meet ASTM D7322¹ – 600% minimum (or 600%-800%). If using a wood fiber product,
80% of the wood fiber will be thermally processed (within a pressurized vessel) with ±3%.
ON PAGE 416, SUBSECTION 621.05 – BASIS OF PAYMENT
Add the following after the last paragraph:
If seeding is performed between May 1st and October 14th, watering shall be considered as
incidental to seeding and the cost thereof included in the contract unit price for seeding.
ON PAGE 438, SUBSECTION 624.03 – CONSTRUCTION REQUIREMENTS
Add the following to 624.03:
Place materials at locations shown on the plans or as directed.
SECTION 656-TRAFFIC SIGNAL INSTALLATION
ON PAGE 482, SUBSECTION 656.01 – DESCRIPTION
Add the following:
Description. The work for the above listed items includes the installation and/or modification of
permanent traffic signal and illumination systems as shown on the plans. This includes, but is not limited
to poles, mast arms, foundations, pole and mast arm equipment, light fixtures, pole and mast arm signs,
cabinets, junction boxes, conduit and wiring. This item also includes the removal and disposal or salvage
to ACHD (as specified in the plans) of existing traffic signal equipment when it is no longer needed.
ON PAGE 482, SUBSECTION 656.02 & 03 – MATERIALS & CONSTRUCTION
REQUIREMENTS
Add the following:
Materials & Construction Requirements. All work shall follow the most current ACHD Section 1130
(General Conditions), ACHD Section 1131 (Illumination, Traffic Signal Systems, and Electrical), and
ACHD Section 1150 (Intelligent Transportation Systems) supplements to the current edition of the Idaho
PROJECT NO. A013(349); KEY NO. 13349 Page 15 of 35
Standards for Public Works Construction (ISPWC), the ACHD Traffic Standard (TS) Drawings and these
Special Provisions. All of the above referenced ACHD documents can be found at:
https://www.achdidaho.org/Departments/Engineering/Traffic/trafficStandards.aspx
No exceptions to ACHD and ITD Policy, Standards and the ISPWC will be allowed unless specifically
approved in writing by ACHD and/or ITD. The Contractor is required to have on hand to perform this
work the current edition of the ISPWC standards, the current edition of the ITD SSHC, and the current
edition of the ACHD Supplemental Specifications, including ACHD’s Traffic Specifications and
Standard Drawings, and these Special Provisions.
ON PAGE 8 OF THE ACHD SECTION 1130 GENERAL CONDITIONS, change the title of Subsection
1130.03.D to ACHD & City Furnished Materials, and add the following:
The Contractor will be required to purchase and obtain, at the Contractor’s expense, all ACHD and City
supplied equipment listed in the tables below from ACHD and the City of Meridian Fire Department. The
Contractor shall contact the ACHD Traffic Operations Department and the City of Meridian Fire
Department a minimum of 30 calendar days in advance of anticipated installation to coordinate purchase
of the equipment and schedule pick up of items supplied by ACHD and the City. The Contractor shall
verify pick up time, date and location a minimum of two business days in advance of pick up.
All other equipment required for construction of the complete Traffic Signal and Illumination Systems as
shown in the plans shall meet the requirements of the ACHD Section 1131 Supplemental Provisions and
Traffic Standard Drawings and shall be purchased and obtained by the Contractor at the Contractor’s
expense.
ON PAGE 8 OF THE ACHD SECTION 1130 GENERAL CONDITIONS, Subsection 1130.03.E – Use
Tax, add the following:
PROJECT NO. A013(349); KEY NO. 13349 Page 16 of 35
ACHD Supplied Equipment for EAGLE ROAD & FRANKLIN ROAD (656-005A)
Signal Poles
Type X Up to 55' mast arm (see specs for dual arms)22150 5,515.00$ -$
Type XI Up to 65' mast arm (see specs for dual arms)22155 6,730.00$ 1 6,730.00$
12' Pedestrian mounting Pole 23701 1,230.00$ 2 2,460.00$
4'10" Pedestrian Push Button Pole 23702 370.00$ -$
30' Luminaire Pole 22995 1,555.00$ -$
40' Luminare pole 23000 1,590.00$ -$
30' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23015 1,820.00$ -$
40' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23010 2,185.00$ -$
Total 9,190.00$
Signal Pole Extensions For Luminaires
"A" Pole Extension 17'22160 1,380.00$ -$
"B" Pole Extension 5' add to "A" only 22165 900.00$ -$
"C" Pole Extension 7'22166 1,130.00$ 1 1,130.00$
Total 1,130.00$
Signal Mast Arms
20'23100 960.00$ -$
25'23200 1,085.00$ -$
30'23300 1,300.00$ -$
35'23400 1,445.00$ -$
40'23500 1,575.00$ -$
45'23600 1,765.00$ -$
50'23700 2,265.00$ -$
55'23800 2,790.00$ -$
60'23900 4,205.00$ 1 4,205.00$
65'24000 5,190.00$ -$
Total 4,205.00$
Luminaire Mast Arms
4'23098 146.00$ -$
6'23099 160.00$ -$
12'23050 254.00$ -$
15'23075 370.00$ -$
20'23020 505.00$ 1 505.00$
Total 505.00$
Electrical Services and Luminaires
200 Amp entrance 100 AMP (dual meter) pedestal 27548 2,498.00$ -$
LED Luminaire Fixture 21337 188.35$ 1 188.35$
250/400 Watt Luminaires (including bulb and shorting cap)21330 374.00$ -$
Signal cabinet side mount UPS 27540 4,749.44$ -$
Total 188.35$
Vehicle Signal Heads and Mounts
12" 3 Section R/A/G Ball LED 21120 408.00$ 4 1,632.00$
12" 3 Section R/A/G Arrow LED 21121 419.00$ 3 1,257.00$
12" 3 Section R/R/Y Ball LED HAWK Style 21119 472.00$ -$
12" 4 Section R/A/A/G Arrow LED 21118 527.00$ -$
12" 5 Section Protected/ Permissive LED 21117 925.00$ -$
Signal Head Pole Mounting Bracket 21122 177.00$ 3 531.00$
Total 3,420.00$
Pedestrian Signal Heads Buttons And Mounts
16" Hand / Man LED Ped Head 21215 178.00$ -$
Pedestrian Push button assemblies 21401 164.00$ -$
Accessible Pedestrian Push Button Assemblies 21402 530.00$ 8 4,240.00$
Pedestrian Head Mounting Brackets (mounts 1 head)21124 160.00$ 2 320.00$
Total 4,560.00$
Control Equipment and Cabinets
Trafficware Commander TS2-1 Controller 21520 4,150.00$ -$
Malfunction Management Unit (MMU)21519 1,329.00$ -$
Size 6 TS2-1 Control Cabinet 21522 11,670.00$ -$
Size 5 TS2-1 Control Cabinet 21521 11,360.00$ -$
Naztec Cromax Time Switch (school flashers)21516 620.00$ -$
Rectangular Rapid Flashing Beacon Controller 21325 1,515.00$ -$
Rectangular Rapid Flashing Beacon Head 21326 363.00$ -$
Solar RRFB Controller 21325 1,772.00$ -$
Solar RRFB Head 21327 363.00$ -$
Video Detection Camera, Mount, Vip Cards, & Wire 21532 2,221.50$ -$
Video Detection VU-COM Card 21534 1,680.00$ -$
Single Point Video Detection Camera 21536 3,240.00$ -$
Single Point Video Detection Processor 21539 9,946.00$ -$
Total -$
SHEET TOTAL 23,198.35$
All Items On This Page Will Be Acquired From ACHD Traffic Operations
Price list Updated 5/20/2020 All pricing is current for 2020
Signal Materials & Poles/Mast Arms Signal Location =Eagle Rd/Franklin Rd
ITEM Inv # Cost Quantity Total
PROJECT NO. A013(349); KEY NO. 13349 Page 17 of 35
\
ACHD Supplied Equipment for EAGLE ROAD & PINE AVENUE (656-005B)
Signal Poles
Type X Up to 55' mast arm (see specs for dual arms)22150 5,515.00$ -$
Type XI Up to 65' mast arm (see specs for dual arms)22155 6,730.00$ 2 13,460.00$
12' Pedestrian mounting Pole 23701 1,230.00$ 3 3,690.00$
4'10" Pedestrian Push Button Pole 23702 370.00$ 2 740.00$
30' Luminaire Pole 22995 1,555.00$ -$
40' Luminare pole 23000 1,590.00$ -$
30' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23015 1,820.00$ -$
40' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23010 2,185.00$ -$
Total 17,890.00$
Signal Pole Extensions For Luminaires
"A" Pole Extension 17'22160 1,380.00$ 2 2,760.00$
"B" Pole Extension 5' add to "A" only 22165 900.00$ -$
"C" Pole Extension 7'22166 1,130.00$ -$
Total 2,760.00$
Signal Mast Arms
20'23100 960.00$ -$
25'23200 1,085.00$ -$
30'23300 1,300.00$ -$
35'23400 1,445.00$ -$
40'23500 1,575.00$ -$
45'23600 1,765.00$ -$
50'23700 2,265.00$ -$
55'23800 2,790.00$ -$
60'23900 4,205.00$ 1 4,205.00$
65'24000 5,190.00$ 1 5,190.00$
Total 9,395.00$
Luminaire Mast Arms
4'23098 146.00$ -$
6'23099 160.00$ -$
12'23050 254.00$ -$
15'23075 370.00$ -$
20'23020 505.00$ 2 1,010.00$
Total 1,010.00$
Electrical Services and Luminaires
200 Amp entrance 100 AMP (dual meter) pedestal 27548 2,498.00$ -$
LED Luminaire Fixture 21337 188.35$ 1 188.35$
250/400 Watt Luminaires (including bulb and shorting cap)21330 374.00$ -$
Signal cabinet side mount UPS 27540 4,749.44$ -$
Total 188.35$
Vehicle Signal Heads and Mounts
12" 3 Section R/A/G Ball LED 21120 408.00$ 5 2,040.00$
12" 3 Section R/A/G Arrow LED 21121 419.00$ 6 2,514.00$
12" 3 Section R/R/Y Ball LED HAWK Style 21119 472.00$ -$
12" 4 Section R/A/A/G Arrow LED 21118 527.00$ -$
12" 5 Section Protected/ Permissive LED 21117 925.00$ -$
Signal Head Pole Mounting Bracket 21122 177.00$ 6 1,062.00$
Total 5,616.00$
Pedestrian Signal Heads Buttons And Mounts
16" Hand / Man LED Ped Head 21215 178.00$ -$
Pedestrian Push button assemblies 21401 164.00$ -$
Accessible Pedestrian Push Button Assemblies 21402 530.00$ 8 4,240.00$
Pedestrian Head Mounting Brackets (mounts 1 head)21124 160.00$ 4 640.00$
Total 4,880.00$
Control Equipment and Cabinets
Trafficware Commander TS2-1 Controller 21520 4,150.00$ -$
Malfunction Management Unit (MMU)21519 1,329.00$ -$
Size 6 TS2-1 Control Cabinet 21522 11,670.00$ -$
Size 5 TS2-1 Control Cabinet 21521 11,360.00$ -$
Naztec Cromax Time Switch (school flashers)21516 620.00$ -$
Rectangular Rapid Flashing Beacon Controller 21325 1,515.00$ -$
Rectangular Rapid Flashing Beacon Head 21326 363.00$ -$
Solar RRFB Controller 21325 1,772.00$ -$
Solar RRFB Head 21327 363.00$ -$
Video Detection Camera, Mount, Vip Cards, & Wire 21532 2,221.50$ -$
Video Detection VU-COM Card 21534 1,680.00$ -$
Single Point Video Detection Camera 21536 3,240.00$ -$
Single Point Video Detection Processor 21539 9,946.00$ -$
Total -$
SHEET TOTAL 41,739.35$
All Items On This Page Will Be Acquired From ACHD Traffic Operations
Price list Updated 5/20/2020 All pricing is current for 2020
Signal Materials & Poles/Mast Arms Signal Location =Eagle Rd/Pine St
ITEM Inv # Cost Quantity Total
PROJECT NO. A013(349); KEY NO. 13349 Page 18 of 35
ACHD Supplied Equipment for EAGLE ROAD & FAIRVIEW AVENUE (656-005C)
Signal Poles
Type X Up to 55' mast arm (see specs for dual arms)22150 5,515.00$ -$
Type XI Up to 65' mast arm (see specs for dual arms)22155 6,730.00$ -$
12' Pedestrian mounting Pole 23701 1,230.00$ -$
4'10" Pedestrian Push Button Pole 23702 370.00$ -$
30' Luminaire Pole 22995 1,555.00$ -$
40' Luminare pole 23000 1,590.00$ -$
30' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23015 1,820.00$ -$
40' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23010 2,185.00$ -$
Total -$
Signal Pole Extensions For Luminaires
"A" Pole Extension 17'22160 1,380.00$ -$
"B" Pole Extension 5' add to "A" only 22165 900.00$ -$
"C" Pole Extension 7'22166 1,130.00$ -$
Total -$
Signal Mast Arms
20'23100 960.00$ -$
25'23200 1,085.00$ -$
30'23300 1,300.00$ -$
35'23400 1,445.00$ -$
40'23500 1,575.00$ -$
45'23600 1,765.00$ -$
50'23700 2,265.00$ -$
55'23800 2,790.00$ -$
60'23900 4,205.00$ -$
65'24000 5,190.00$ -$
Total -$
Luminaire Mast Arms
4'23098 146.00$ -$
6'23099 160.00$ -$
12'23050 254.00$ -$
15'23075 370.00$ -$
20'23020 505.00$ -$
Total -$
Electrical Services and Luminaires
200 Amp entrance 100 AMP (dual meter) pedestal 27548 2,498.00$ -$
LED Luminaire Fixture 21337 188.35$ -$
250/400 Watt Luminaires (including bulb and shorting cap)21330 374.00$ -$
Signal cabinet side mount UPS 27540 4,749.44$ -$
Total -$
Vehicle Signal Heads and Mounts
12" 3 Section R/A/G Ball LED 21120 408.00$ -$
12" 3 Section R/A/G Arrow LED 21121 419.00$ -$
12" 3 Section R/R/Y Ball LED HAWK Style 21119 472.00$ -$
12" 4 Section R/A/A/G Arrow LED 21118 527.00$ -$
12" 5 Section Protected/ Permissive LED 21117 925.00$ -$
Signal Head Pole Mounting Bracket 21122 177.00$ -$
Total -$
Pedestrian Signal Heads Buttons And Mounts
16" Hand / Man LED Ped Head 21215 178.00$ -$
Pedestrian Push button assemblies 21401 164.00$ -$
Accessible Pedestrian Push Button Assemblies 21402 530.00$ -$
Pedestrian Head Mounting Brackets (mounts 1 head)21124 160.00$ -$
Total -$
Control Equipment and Cabinets
Trafficware Commander TS2-1 Controller 21520 4,150.00$ -$
Malfunction Management Unit (MMU)21519 1,329.00$ -$
Size 6 TS2-1 Control Cabinet 21522 11,670.00$ -$
Size 5 TS2-1 Control Cabinet 21521 11,360.00$ -$
Naztec Cromax Time Switch (school flashers)21516 620.00$ -$
Rectangular Rapid Flashing Beacon Controller 21325 1,515.00$ -$
Rectangular Rapid Flashing Beacon Head 21326 363.00$ -$
Solar RRFB Controller 21325 1,772.00$ -$
Solar RRFB Head 21327 363.00$ -$
Video Detection Camera, Mount, Vip Cards, & Wire 21532 2,221.50$ -$
Video Detection VU-COM Card 21534 1,680.00$ -$
Single Point Video Detection Camera 21536 3,240.00$ -$
Single Point Video Detection Processor 21539 9,946.00$ -$
Total -$
SHEET TOTAL -$
All Items On This Page Will Be Acquired From ACHD Traffic Operations
Price list Updated 5/20/2020 All pricing is current for 2020
Signal Materials & Poles/Mast Arms Signal Location =Eagle Rd/Fairview Ave
ITEM Inv # Cost Quantity Total
PROJECT NO. A013(349); KEY NO. 13349 Page 19 of 35
ACHD Supplied Equipment for EAGLE ROAD & RIVER VALLEY STREET (656-005D)
Signal Poles
Type X Up to 55' mast arm (see specs for dual arms)22150 5,515.00$ -$
Type XI Up to 65' mast arm (see specs for dual arms)22155 6,730.00$ -$
12' Pedestrian mounting Pole 23701 1,230.00$ -$
4'10" Pedestrian Push Button Pole 23702 370.00$ -$
30' Luminaire Pole 22995 1,555.00$ -$
40' Luminare pole 23000 1,590.00$ -$
30' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23015 1,820.00$ -$
40' Angle Lighting Structures (Ada/Mesa Style Luminaire Poles)23010 2,185.00$ -$
Total -$
Signal Pole Extensions For Luminaires
"A" Pole Extension 17'22160 1,380.00$ -$
"B" Pole Extension 5' add to "A" only 22165 900.00$ -$
"C" Pole Extension 7'22166 1,130.00$ -$
Total -$
Signal Mast Arms
20'23100 960.00$ -$
25'23200 1,085.00$ -$
30'23300 1,300.00$ -$
35'23400 1,445.00$ -$
40'23500 1,575.00$ -$
45'23600 1,765.00$ -$
50'23700 2,265.00$ -$
55'23800 2,790.00$ -$
60'23900 4,205.00$ -$
65'24000 5,190.00$ -$
Total -$
Luminaire Mast Arms
4'23098 146.00$ -$
6'23099 160.00$ -$
12'23050 254.00$ -$
15'23075 370.00$ -$
20'23020 505.00$ -$
Total -$
Electrical Services and Luminaires
200 Amp entrance 100 AMP (dual meter) pedestal 27548 2,498.00$ -$
LED Luminaire Fixture 21337 188.35$ -$
250/400 Watt Luminaires (including bulb and shorting cap)21330 374.00$ -$
Signal cabinet side mount UPS 27540 4,749.44$ -$
Total -$
Vehicle Signal Heads and Mounts
12" 3 Section R/A/G Ball LED 21120 408.00$ -$
12" 3 Section R/A/G Arrow LED 21121 419.00$ -$
12" 3 Section R/R/Y Ball LED HAWK Style 21119 472.00$ -$
12" 4 Section R/A/A/G Arrow LED 21118 527.00$ -$
12" 5 Section Protected/ Permissive LED 21117 925.00$ -$
Signal Head Pole Mounting Bracket 21122 177.00$ -$
Total -$
Pedestrian Signal Heads Buttons And Mounts
16" Hand / Man LED Ped Head 21215 178.00$ -$
Pedestrian Push button assemblies 21401 164.00$ -$
Accessible Pedestrian Push Button Assemblies 21402 530.00$ -$
Pedestrian Head Mounting Brackets (mounts 1 head)21124 160.00$ -$
Total -$
Control Equipment and Cabinets
Trafficware Commander TS2-1 Controller 21520 4,150.00$ -$
Malfunction Management Unit (MMU)21519 1,329.00$ -$
Size 6 TS2-1 Control Cabinet 21522 11,670.00$ -$
Size 5 TS2-1 Control Cabinet 21521 11,360.00$ -$
Naztec Cromax Time Switch (school flashers)21516 620.00$ -$
Rectangular Rapid Flashing Beacon Controller 21325 1,515.00$ -$
Rectangular Rapid Flashing Beacon Head 21326 363.00$ -$
Solar RRFB Controller 21325 1,772.00$ -$
Solar RRFB Head 21327 363.00$ -$
Video Detection Camera, Mount, Vip Cards, & Wire 21532 2,221.50$ -$
Video Detection VU-COM Card 21534 1,680.00$ -$
Single Point Video Detection Camera 21536 3,240.00$ -$
Single Point Video Detection Processor 21539 9,946.00$ -$
Total -$
SHEET TOTAL -$
All Items On This Page Will Be Acquired From ACHD Traffic Operations
Price list Updated 5/20/2020 All pricing is current for 2020
Signal Materials & Poles/Mast Arms Signal Location =Eagle Rd/River Valley St
ITEM Inv # Cost Quantity Total
PROJECT NO. A013(349); KEY NO. 13349 Page 20 of 35
ON PAGE 485, SUBSECTION 656.04 – METHOD OF MEASUREMENT
Replace with the following:
Method of Measurement Traffic signal and illumination system installation and modifications will be
measured by lump sum for each signal modification. The ACHD Signal Inspector shall supervise the
installation the Traffic Signal and Illumination Systems Complete. An ACHD Signal Technician will
make fully operational and test the systems and equipment as indicated on the plans and this specification.
All work included in the plans or specified herein pertaining to installation of the items on the plans shall
be considered as part of the work. No specific unit measurement will apply, but measurement will be for
the sum of all items for complete systems to be furnished and installed. This includes, but is not limited
to:
· Purchase, acquisition, and installation of all required ACHD supplied and City supplied
equipment and payment of the use tax on said equipment.
· Purchase, acquisition, and installation of all Contractor supplied equipment.
· Payment to Idaho Power to connect new power services and reconnect existing power services as
specified in the plans.
ON PAGE 454, SUBSECTION 656.05 – BASIS OF PAYMENT
Replace with the following:
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
656-005A Traffic Signal Modification – Eagle Road/Franklin Road Lump sum (LS)
656-005B Traffic Signal Modification – Eagle Road/Pine Avenue Lump sum (LS)
656-005C Traffic Signal Modification – Eagle Road/Fairview Avenue Lump sum (LS)
656-005D Traffic Signal Modification – Eagle Road/River Valley Street Lump sum (LS)
S501-15A MSE RETAINING WALL, SEGMENTAL BLOCK
S501-15B RETAINING WALL (GRAVITY CONCRETE BLOCK)
I. Description. Design, provide, fabricate and install all materials for the retaining walls. Construct
retaining walls in accordance with the plans, design drawings and these specifications.
Related work may include temporary shoring to construct the walls, scour countermeasures placement
and finish grading at the wall toes, and erosion countermeasures construction at the wall ends.
Do not allow any extra surcharge on the constructed retaining walls, such as an accumulation of
blasted rock and soil during rock blasting. Repair any damage to walls at no cost to the Department.
II. Design Requirements.
A. General: Design the retaining walls as shown on the plans. The Department has provided
preliminary dimensions for estimating purposes only. Perform a design for a chosen proprietary
system that will establish the following criteria, as a minimum:
1. Concrete unit dimensions for each layer.
2. Size of concrete leveling pad (if required by proprietary system or as shown in the plans).
3. Quality and quantity of backfill.
PROJECT NO. A013(349); KEY NO. 13349 Page 21 of 35
Design the wall in accordance with the AASHTO LRFD Bridge Design Specifications, 9th
Edition and with latest revisions. Design the walls for a design life of 75 years for permanent
structures, 100 years for walls around bridge abutments (that are supported by spread footings
placed on wall backfill), building, critical utilities, and 3 years for temporary structures.
Unless founded on bedrock, embed the wall at least 1 foot at the wall front face (for walls
constructed along rivers or streams, this embedment is measured from the bottom of the potential
scour depth) or as shown on the plans, whichever is greater.
B. Detailed Design Drawings
Submit five sets of design drawings with computations to the Engineer. Include details,
dimensions, quantities, and cross sections necessary to construct the wall. Prepare plans to ITD
standards and include elevation view, plan view, and section view sheets for each wall,
containing the following:
1. Elevation view. Show the elevations at break points at the top of each wall face and at the top
of each leveling pad (or bottom of each wall). Show concrete unit component details in the
design drawings.
2. Plan view. Show dimensions tying break points at the top of each wall face and top of each
leveling pad (or bottom of each wall) to the roadway centerline.
3. Section (side) views. Show dimensions tying break points at the top of each wall face and at
the top of each leveling pad (or bottom of each wall) to the roadway centerline. Show
excavation limits for wall construction.
4. Material takeoff for each wall, listing quantities for each main wall components, and
incidental items required for construction.
5. Details for concrete units, leveling pads, coping if required. Design for wall end treatment,
such as burying the wall ends, turning the wall ends into the slope and show them in the
design drawings.
6. Design for drainage system as shown on the plans or this specification. As a minimum,
design and provide an underdrain system for draining water away from the backfill and the
wall.
7. Concrete coping details (cast in place or precast, if required).
Stamp and sign calculations and design drawings by a Professional Engineer licensed in the State
of Idaho.
Provide design calculations and design drawings to the Engineers for review and approval before
fabrication of wall elements. Allow at least 15 working days for the Engineer to review and
approve the design calculations and design drawings.
Before project completion, provide the Engineer with as-built drawings in PDF format.
III. Materials.
A. General.
Arrange to purchase or manufacture the necessary components for the selected pre-approved wall
system from the following supplier list or approved equals. Use only one type of wall in the
project unless indicated otherwise in the plans.
Wall System Manufacturer or
Supplier
Facing Type Limitations
PROJECT NO. A013(349); KEY NO. 13349 Page 22 of 35
PYRAMID
MODULAR
BLOCK
Reinforced Earth Co.
9025 East Kenyon Ave.,
Suite 200
Denver CO, 80237
(303) 790 1481
Small Concrete Block
-Not approved for use
within 20 feet of bridge
abutments.
-Maximum height is 15
feet.
GENESIS WALL
SYSTEM
Contech Engineered
Solutions
2550 E. Mariposa
Eagle, ID 83616
(208) 220-8684
Small Concrete Block
-Not approved for use
within 20 feet of bridge
abutments.
-Maximum height is 15
feet.
Tensar geogrid
reinforcement only.
GEOWALL PRO
GEOWALL MAX
Basalite Concrete
Products
1300 E. Franklin
Meridian, ID 83642
(208) 888-4050
Small Concrete Block
-Not approved for use
within 20 feet of bridge
abutments.
-Maximum height is 15
feet.
Tensar geogrid
reinforcement only.
ANCHOR
DIAMOND,
VERTICA,
VERTICA
PRO
Central Pre-Mix Concrete
Products Co.
16310 East Marietta Ave.
Spokane, Washington
99216
(509) 926-8235
Small Concrete Block
-Not approved for use
within 20 feet of bridge
abutments.
-Maximum height is 15
ft. in ITD Dist. 1 and 2
and 10 ft. in ITD
District 3, 4, 5 and 6.
KEYSYSTEM 1 Contech Engineered
Solutions
2550 E. Mariposa
Eagle, ID 83616
(208) 220-8684
Small Concrete Block
-Not approved for use
within 20 feet of bridge
abutments.
-Maximum height is 40
feet.
MESA Tensar International
Corp.
19883 12th Ave. NE
Poulsbo, WA 98370
(360) 981 0222
Small Concrete Block
-Approved for use
within 20 feet of bridge
abutments to a
maximum height of 30
feet.
-Maximum height is 50
feet when greater than
20 feet from bridge
abutments.
REDI-ROCK Cougar Mountain Precast
PO Box 1836
Eagle, ID 83616
(208) 891 8800
Large Concrete Block -Not approved for use
within 20 feet of bridge
abutments.
-Maximum height is 40
ft.
-TenCate Miragrid XT
as backfill
reinforcements only
LOCK-BLOCK Ultrablock, Inc
815 NE 172nd Ave.
Vancouver, WA 98684
(800) 377 3877
Large Concrete Block -Not approved for use
within 20 feet of bridge
abutments.
PROJECT NO. A013(349); KEY NO. 13349 Page 23 of 35
-Maximum height is 15
ft.
RECON ReCon Retaining Wall
System, Inc.
7600 W 27th Street, #
229
St. Louis Park, MN
55426
(952) 922 0027
Large Concrete Block -Not approved for use
within 20 feet of bridge
abutments.
-Maximum height is 20
ft.
-Only Strata Grids SG
350 & 550 can be used
as backfill
reinforcements.
GRAVIX Earth Wall Products
1427 Walcutt's Way
Marietta, GA 30064
(678) 594-3451
Semi-Gravity Wall
System
-Not approved for use
within 20 feet of bridge
abutments. Maximum
height is 25 feet.
Verti-Block-
Gravity
Verti-Block
PO Box 2347
Sandy, UT 84091
Coeur d’Alene Paving,
Inc.
120 E. Anton Avenue
Coeur d’Alene, ID 83815
Block/Gravity -Maximum height is 12
feet high for walls with
level backfill and no
traffic loads within 6.0
feet of the back of the
top wall block, 10 feet
for walls with level
backfill and traffic
loads adjacent to the
wall, and 9 feet for
walls with sloping
backfill up to as steep
as 3:1 (H:V).
-Not approved for use
within 20 feet of a
bridge abutment.
Elevate Utility Concrete Products,
LLC
2495 W. Bungalow Road
Morris, IL 60450
Precast Concrete
Counterfort Retaining
Semi-Gravity Wall
System
1. Only retaining
wall backfill
meeting ITD
Special
Provisions
requirements
will be
allowed.
Retaining wall
bearing
capacity,
sliding and
passive (if
used) resistance
must be based
on the actual
soil type(s)
beneath and in
front of the
wall(s).
PROJECT NO. A013(349); KEY NO. 13349 Page 24 of 35
2. The retaining
wall drainage
system must be
defined via the
use of an
approved drain
system. All
wall designs
must account
for
groundwater
accumulation
behind the wall
below the drain
system
elevation.
Drainage socks
around drain
pipes will not
be allowed.
3. All retaining
wall subgrade,
support fill and
backfill
compaction
shall meet ITD
Class A
compaction
requirements.
Provide a Certificate of Compliance (along with backup test reports) in accordance with 106.04 of
the Standard Specifications certifying that all materials provided by the Contractor or a
manufacturer under Section III of these special provisions comply with the specifications for the
wall system. Provide certifications before starting wall construction. Obtain written approval from
the Engineer for non-specified materials or material from sources not listed in the contract
documents.
B. Concrete Block Requirements.
Provide Class 40A Concrete that complies with 502 of the Standard Specifications, except
as modified in these Special Provisions. Obtain Engineer approval before using retarding
or accelerating agents, or additive containing chloride.
1. Large Concrete Blocks and GRAVIX Wall System Units.
a. Testing and Inspection. The Engineer will determine precast unit acceptability on the
basis of compressive strength tests and visual inspection. The Engineer will consider
precast units acceptable before 28 days if strength has reached the 28-day specified value.
The Contractor or supplier shall furnish facilities and perform necessary sampling and
testing in an expeditious and satisfactory manner. The Department will consider panels
utilizing Type I or II cement acceptable for placement in the wall when initial
compressive strengths (as defined in these Special Provisions) exceed 85 percent of 28-
day strength requirements. The Department will consider panels utilizing Type III
PROJECT NO. A013(349); KEY NO. 13349 Page 25 of 35
cement acceptable for placement in the wall before 28 days only when compressive
strength exceeds the 28-day strength requirement.
b. Casting. Place the concrete in each unit without interruption and consolidate by the use
of an approved vibrator, supplemented by hand tamping as necessary to force the
concrete into the forms corners and prevent formation of stone pockets or cleavage
planes. Use clear form oil from the same manufacture throughout the casting operation.
c. Curing. Fully support units in their forms until the concrete reaches a minimum
compressive strength of 1,000 psi.
d. Concrete Finish and Color. Unless indicated otherwise, provide units with concrete
facing texture and color as provided by the wall manufacturer. Submit the proposed
concrete facing texture and color to the Engineer for approval before casting.
e. Tolerances. Manufacture concrete blocks within the following tolerances:
· Dimension within ³/16 inch for block height.
· Dimension within ½ inch for block width, unless field cut for fitting purposed.
· The block depths shall be at least equal to the design depths shown in the shop
drawings.
f. Compressive Strength. The Engineer will determine concrete wall unit acceptance with
respect to compressive strength based on production lots. The Department defines a
production lot as a group of units represented by a single compressive strength sample
that consists of 40 blocks or a single day's production, whichever is less. During the
concrete unit production, the manufacturer will randomly sample the concrete in
accordance with 502.02 of the Standard Specifications. The Engineer may randomly
select a single compressive strength sample, consisting of a minimum of five cylinders or
coupons, for every production lot.
Prepare cylinders for compressive strength tests on 6 in by 12 in specimens in accordance
with ASTM C31. For every compressive strength sample, cure at least two cylinders in
the same manner as the panels and tested at approximately 7 days. The average cylinder
compressive strength will determine the initial concrete strength. In addition, cure three
cylinders or coupons in accordance with 502.02 and tested at 28 days.
The average 28-day cylinder or coupon compressive strength be the production lot
compressive strength.
If the initial strength test results indicate a compressive strength in excess of 4,000 psi,
then the Engineer will use these test results for that production lot and may waive the
requirement for testing at 28 days for that particular production lot.
The Engineer will accept a production lot if the compressive strength test result is greater
than or equal to 4,000 psi.
If the compressive strength test result is less than 4,000 psi, the Engineer will
base production lot acceptance on meeting all the following criteria:
· Ninety percent of the compressive strength test results exceed 4,150 psi for the
overall production.
· The average compressive strength test results exceed 4,250 psi for six consecutive
lots.
· No individual compressive strength test results shall fall below 3,600 psi.
In the event that a production lot fails to meet the specified compressive strength
requirements, the Engineer will reject that production lot.
g. Rejection. In addition to the preceding paragraphs, the engineer may reject a panel or lot
with any of the following defects:
· Defects that indicate imperfect molding.
· Defects that indicate honeycombed or open texture concrete.
· Cracked or chipped panels.
· Front-panel color variation due to excess form oil or other reasons.
PROJECT NO. A013(349); KEY NO. 13349 Page 26 of 35
h. Handling, Storage and Shipping. Handle units with care to eliminate chipping and
fractures.
2. Modular (Segmental) Block Wall and Cap Units. Meet the following referenced documents:
ASTM C90 Specifications for Load Bearing Masonry Units
ASTM C140 Methods of Sampling and Testing Concrete Masonry Units
ASTM C331 Specifications for Lightweight Aggregates for Concrete Masonry Units
ASTM C595 Specifications for Blended Hydraulic Cements
AASHTO M295 Specifications for Coal Fly Ash and Raw or Calcined Natural Pozzolan
for Use in Concrete
AASHTO M302 Specification for Ground Granulated Blast Furnace Slag Cement
i. Cementitious Materials. Provide materials that comply with the following
specifications:
· Portland Cement, Modified Portland Cement, Blended Cements - 701 of the
Standard Specifications.
· Secondary Cementitious Materials - 714 of the Standard Specifications.
ii. Aggregates - Provide aggregates that comply with 703 of the Standard
Specifications.
a. Testing and Inspection. The Engineer will determine modular concrete wall and cap unit
acceptability on the basis of installation, compressive strength tests, and visual inspection
in accordance with ASTM C140 Annex A3. The Contractor or his supplier shall furnish
facilities and perform necessary sampling and testing in an expeditious and satisfactory
manner.
b. Concrete Finish and Color. Provide a concrete surface for the straight front face with the
manufacturer’s ordinary "brokenface" surface finish unless otherwise shown on the plans.
Add unit color(s), when required, by the addition of pigment to the concrete. Before
manufacturing, provide the actual finish and color during the submittal process.
c. Tolerances. Manufacture modular concrete units within the following tolerances:
· Dimension within ⅛ inch except for pin and kidney receiving hole or keyways
require 1/16 inch tolerance.
· Ensure the individual block height is ±1/16 inch of the specified dimension.
· Provide hollow units with a wall thickness of at least 1.25 inch.
· Texture front face with "brokenface" pattern, which will vary due to random nature
of splitting process. Ensure the front face is ± 1 inch of the theoretical unit
dimension.
d. Compressive Strength. The Engineer will determine modular concrete unit acceptance
with respect to compressive strength basis on the production lots. Maximum number of
blocks per lot is 2000 or one day production, whichever is less. The Engineer may
randomly sample a production lot in accordance with ASTM C140 Annex A3. Perform
compressive strength test and submit results to the Engineer
Provide wall and cap block units that comply with the following strength requirements:
· Minimum required compressive strength, average of 3 coupons: 4000 psi
· Minimum required compressive strength, individual coupons: 3550 psi
In the event that a production lot fails to meet the specified compressive strength
requirements, the Engineer will reject that production lot.
Ensure the modular concrete wall and cap units also meet the following requirement:
Test Method Value
Maximum Water Absorption ASTM C 140 5% maximum
If water absorption of modular block units determined by ASTM C140 is not available,
then ensure the modular concrete wall and cap units comply with the following freeze-
PROJECT NO. A013(349); KEY NO. 13349 Page 27 of 35
thaw test requirements when tested in accordance with ASTM C 1262. Provide modular
block units which have weight loss for four out of five specimens tested not exceeding
1 percent initial weight at the conclusion of 150 freeze-thaw cycles when tested in water;
or not exceeding 1.5 percent initial weight at the conclusion of 50 cycles when tested in a
saline (3 percent sodium chloride by weight solution). Submit to the Engineer for review
and approval test reports and certifications for units cast with the same material, concrete
mix design, manufacturing process, and curing method conducted not more than
24 months before delivery to the project
e. Rejection. In addition to the preceding paragraphs, the Engineer may reject a block or lot
with any of the following defects:
· Defects that indicate imperfect molding.
· Defects that indicate honeycombed or open texture concrete.
· Cracked or chipped blocks.
· Front-block color variation due to excess form oil or other reasons.
f. Handling, Storage and Shipping. Handle units with care to eliminate chipping and
fractures.
C. Coping For Walls: Provide Class 40A concrete for coping in accordance with 502 of the
Standard Specifications if coping is required. Provide metal reinforcement for coping in
accordance with 503 of the Standard Specification.
D. Leveling Pad: Provide a gravel or non-reinforced concrete leveling pad consisting of Class 22
concrete as shown on the plans.
E. Backfill Material.
Provide the material that is free of shale, organic matter, mica, gypsum, clay, or soft, poor
durability particles and meets the following property requirements:
1. The material shall have a minimum internal friction angle of 34º, determined in accordance to
test method AASHTO T-236. Perform this test on material finer than No. 10 sieve
compacted to 95% of the maximum dry density as determined by AASHTO T-99. The
Engineer may waive the requirement for AASHTO T-236 test if the material has 80% or
more material that is larger than ¾ inch and in this case an internal friction angle of 34º can
be used in the design.
2. The reinforced backfill material shall also meet the following property requirements:
Property Test
Method Sieve Size Percent Passing Remarks
Gradation AASHTO
T-27&11
4 in. 100
No. 40 0-60
No. 200 0-15
F. Core Fill and Drainage Aggregate Material for Segmental Block Wall Units.
Provide core fill and drainage aggregate material for block wall units that is well-graded crushed
stone or granular material meeting the following requirements:
Sieve Size Percent Passing
1 in 100
¾ in 50 - 75
No. 4 0 - 60
No. 40 0 - 50
PROJECT NO. A013(349); KEY NO. 13349 Page 28 of 35
No. 200 0 – 5
IV. Construction Requirements.
A. General. Ensure a field technical representative from the proprietary wall system to be on site
for at least 2 days at the beginning of initial wall erection and available during the remaining wall
erection to assist the Contractor and Engineer. The field representative shall have been involved
in successfully construction of at least three walls with sizes and complexity similar to the walls
of this project in the last five years.
B. Wall Excavation. Excavate the wall in accordance with 210 of the Standard Specifications and
as shown on the plans.
C. Foundation Preparation. Grade the structure foundation level for a width equal to or exceeding
the bottom units or as shown on the plans. Before wall construction, compact the foundation, if
not in rock, as directed by the Engineer. Remove and replace foundation soils found to be
unsuitable as directed by the Engineer.
Cure the concrete leveling pad at least 12 hours before placement of wall units or segmental
concrete units.
D. Wall Erection. Place concrete units in their final position as shown on the design drawings.
Handle and place concrete units by work force or lifting devices. Place concrete units in
successive horizontal lifts in the sequence shown on the design drawings as backfill placement
and compaction proceeds. Place backfill material behind the concrete units while maintaining the
facing in the desired position with temporary wedges or bracing in accordance with the wall
supplier's recommendations. Ensure vertical tolerances and horizontal alignment tolerances along
the wall line for concrete units are within ¾ inch when measured with a 10 foot straight edge.
Ensure the maximum offset in any unit joint is ¾ inch. Check the position and tolerances of each
concrete unit row before erecting the next row. Should any units be out of tolerance, remove the
fill, and reset units to their proper position. Install GRAVIX wall elements following the
manufacturer’s recommended procedure.
Remove and reconstruct walls or wall portions constructed outside the tolerances in these Special
Provisions, walls with negative batter (batter in excess of vertical away from the wall), or if the
batter becomes negative during construction. The Department will not make additional payment
for this work.
F. Backfill Placement. Closely follow each erection course of concrete units with backfill
placement. Place backfill in 12 inch loose lifts or less. Place backfill so as to avoid facing
element damage or misalignment. Remove and replace wall materials that become damaged or
disturbed during backfill placement, or correct as directed by the Engineer at no additional cost to
the Department. Correct wall facing element misalignment or distortion due to work not
associated with these Special Provisions as directed by the Engineer at no additional cost to the
Department.
Ensure lift thickness after compaction is 12 inches or less. Decrease this lift thickness, if
necessary, to obtain the specified density. Compact backfill by running the compactor in
direction parallel to the wall face.
Achieve compaction within 3 ft. behind the wall by at least five passes, or as directed, of a
lightweight mechanical tamper, roller, or a vibratory system.
PROJECT NO. A013(349); KEY NO. 13349 Page 29 of 35
Compact backfill to 95 percent of the maximum density as determined by AASHTO T-99,
Method C or D (with oversize correction as outlined in this test). Uniformly distribute the
backfill material moisture content before and during compaction throughout each layer, unless
otherwise directed by the Engineer. Place backfill material with a moisture content range
between optimum moisture and optimum moisture minus 4 percentage points, as determined by
AASHTO T-99. Remove and rework backfill material which has moisture content in excess of
the upper moisture limit until the moisture content is uniformly acceptable throughout the entire
lift.
Backfill field density testing will be performed at the same frequency as for bridge abutments and
approach slabs per the “Structure Backfill” construction type under Item 210- Compacting
Backfill in the ITD Quality Assurance Manual.
Do not place backfill materials when they are frozen. Do not place backfill materials on snow
cover or frozen materials.
At the end of each day's operation, slope the backfill away from the wall face to direct surface
runoff away from the wall. In addition, do not allow surface runoff from adjacent areas to enter
the wall construction site.
V. Method of Measurement.
The Engineer will measure acceptably completed work by the square foot of wall surface area from the
leveling pad top to the top concrete unit or coping tops (if coping is used).
VI. Basis of Payment
The Department will pay for accepted quantities at the contract unit price as follows:
Pay Item Pay Unit
S501-15A MSE Retaining Wall, Segmental Block SF
S501-15B Retaining Wall (Gravity Concrete Block) SF
Coping, leveling pad, structural excavation, compacting backfill, and wall drainage system are all
incidental. Field representative services costs are incidental. Temporary shoring to construct the walls,
scour countermeasures placement and finish grading at the wall toes, and erosion countermeasures
construction at the wall ends are either incidental or paid for under other items.
S604-05A REMOVE AND RESET IRRIGATION (SPRINKLER SYSTEM)
Description. This work shall consist of removing and replacing the existing sprinkler irrigation system to
the finished grade within the construction area as shown on the plans, or as directed.
Construction Requirements. The Contractor shall record the locations of the existing sprinkler
irrigation system and sprinkler heads in the area of construction impacts. The Contractor shall remove and
reset the existing system, to the locations recorded or as directed. Any damage to the existing sprinkler
heads from the contractors operation will be replaced by the Contractor at Contractor’s expense. Upon
completion of the roadway and curb sections, the contractor shall replace the existing sprinkler irrigation
conduits with the same size of conduit that was removed. Where possible all sprinkler heads will be
retained and placed at the approximate locations from which they were removed. Any sprinkler heads
which require movement in the widened areas shall be relocated perpendicular to the original location or
as directed.
PROJECT NO. A013(349); KEY NO. 13349 Page 30 of 35
Any extra conduit, sprinkler heads, elbows or other miscellaneous hardware required to restore a
functioning sprinkler irrigation system shall be considered incidental to this item.
The existing sprinkler heads shall be adjusted flush with the finished surface.
If any construction occurs during the irrigation season, it shall be the Contractor’s responsibility to
maintain irrigation to any adjacent areas which may be connected to the irrigation system being
reconstructed.
Method of Measurement. Remove and Reset Irrigation, will be measured by the Lump Sum.
Basis of Payment- Payment for accepted work will be made as follows.
Pay Item Pay Unit
S604-05A Remove and Reset Irrigation (Sprinkler System) LS
S901-05A SP OBSERVATION WELL
Description. This work shall consist of furnishing and installing the observation wells as shown on the
plans and in accordance with these special provisions.
Materials. Non-perforated Pipe shall meet the requirements of Subsection 706.14, ASTM D-3034 SDR
35 for drilled wells Polyvinyl Chloride (PVC) Pipe.
Perforated Pipe shall meet the requirements of Subsection 706.14, ASTM D-3035 SDR 35 Polyvinyl
Chloride (PVC) Pipe and shall have 15 rows of 6 3/8” diameter holes spaced at 3” O.C. vertically.
Drainage Geotextile Type I conforming to Section 718 – Geotextiles
Concrete conforming to Section 509.
Metal Reinforcement conforming to Section 503.
For 2” washed drain rock and filter sand specifications see Item S911-05A.
Construction. The observation well shall be installed at the locations and as detailed on the plans. Two
observation wells are required per infiltration trench system to monitor the system and check
functionality.
The concrete collar shall be constructed in accordance with the applicable portions of Sections 509-
Concrete, and 503-Metal Reinforcement.
PVC pipe shall be installed to meet the requirements of Subsection 602.03.
The PVC shall be wrapped in drainage geotextile Type 1
Method of Measurement. Observation Well will be measured per each installation including all labor
and materials.
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
PROJECT NO. A013(349); KEY NO. 13349 Page 31 of 35
S901-05A SP Observation Well Each
This item shall include installation, drainage geotextile, PVC pipe, drain rock, filter sand, finder wire,
concrete collar and reinforcement, PVC Cap, Well Cover and all other miscellaneous items and labor
necessary to construct the Observation Well.
S901-05B OIL/WATER SKIMMER
Description. This work shall consist of furnishing and installing the Oil/Water Skimmer as shown on the
plans and in accordance with these special provisions.
Materials. The Oil/Water Skimmer shall be as detailed in the plans and have a minimum 10” cleanout
and shall be a Nyloplast 30R Snout, Envirohood, Ravenshood or approved equal...
Construction. The Oil/Water Skimmer shall be installed at the locations and as detailed on the plans.
Method of Measurement. Oil/Water Skimmer will be measured per each installation including all labor
and materials.
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
S901-05B SP Oil/Water Skimmer Each
S901-05C SP MODIFIED CATCH BASIN TYPE 3
Description. This work consists of constructing a Modified Catch Basin Type 3 in conformity with the
lines as shown in plans or as directed. This item shall also include, but not be limited to, the form work,
placement of concrete and reinforcing steel, grate as detailed in the plans, and connection to the storm
sewer pipe.
Materials. Materials shall be in accordance with the requirements for a standard Type 3 Catch Basin and
Subsection 605.02.
Concrete conforming to Section 509.
Metal Reinforcement conforming to Section 503.
Construction Requirements. Modified Catch Basin Type 3 shall be installed in accordance with ITD
Standard Drawing 605-20 and Subsection 605.03, or as directed.
In addition the Modified Catch Basin Type 3 shall include a 24” wide x 6” thick concrete apron around all
four sides of the catch basin or to match the edge of existing concrete sidewalk. The concrete apron shall
angled as necessary to match the slopes at the location of the catch basin.
Method of Measurement. Modified Catch Basin Type 3 will be measured per each, complete in place.
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
S901-05C Modified Catch Basin Type 3 Each
PROJECT NO. A013(349); KEY NO. 13349 Page 32 of 35
S904-05A ATMS INSTALLATION
Description. This work shall consist of removal, replacement, and/or installation of Advanced Traffic
Management System (ATMS) equipment as shown on the plans. All materials necessary for the complete
installation shall be furnished by the Contractor with the exception of materials specifically noted to be
furnished by Ada County Highway District (ACHD) or other agencies. Contractor shall contact the
ACHD Congestion Management Supervisor a minimum of 30 calendar days in advance to coordinate
delivery of items supplied by ACHD. Contractor shall verify delivery time, date and location a minimum
of three business days in advance of delivery.
Materials & Construction Requirements. All work shall follow the most current ACHD Section 1130
(General Conditions), ACHD Section 1131 (Illumination, Traffic Signal Systems, and Electrical), and
ACHD Section 1150 (Intelligent Transportation Systems) supplements to the current edition of the Idaho
Standards for Public Works Construction (ISPWC), the ACHD Traffic Standard (TS) Drawings and these
Special Provisions. All of the above referenced ACHD documents can be found at:
https://www.achdidaho.org/Departments/Engineering/Traffic/trafficStandards.aspx
The materials to be incorporated in the installation of ATMS equipment shall be listed in the bid package.
All materials and methods required under this section, unless otherwise superseded herein, shall conform
to the current Manual on Uniform Traffic Control Devices (MUTCD) and to the ATSSA Quality
Standards for Work Zone Traffic Control Devices.
No exceptions to ACHD and ITD Policy, Standards and the ISPWC will be allowed unless specifically
approved in writing by ACHD and/or ITD. The Contractor is required to have on hand to perform this
work the current edition of the ISPWC standards, the current edition of the ITD SSHC, and the current
edition of the ACHD Supplemental Specifications, including ACHD’s Traffic Specifications and
Standard Drawings, and these Special Provisions.
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
S904-05A Eagle Road ATMS System Modifications Lump sum (LS)
S911-05A SP INFILTRATION TRENCH
Description. This item shall include all costs associated with the construction of the infiltration trenches
at the locations, grades, dimensions and details shown in the plans and detail sheets.
Materials. Materials shall meet the following requirements:
Filter sand shall consist of uncrushed aggregate meeting the following gradation requirements:
SIEVE SIZE PERCENT PASSING
3/8 in. 100
No. 4 95-100
No. 16 45-80
No. 50 10-30
No. 100 3-10
No. 200 0-4
2” washed drain rock material shall consist of uncrushed aggregate meeting the following gradation
requirements:
PROJECT NO. A013(349); KEY NO. 13349 Page 33 of 35
SIEVE SIZE PERCENT PASSING
2 in 100
1 in. 25-60
3/8 in. 0-4
No. 200 0-2
Gradations shall be determined by AASHTO T27 and T11.
Filter Sand gradation testing every 500 C.Y. or accepted by certification with suppliers QC gradations.
2” Drain Rock gradation testing every 1000 C.Y. or accepted by certification with suppliers QC
gradations.
Filter Sand conforming to 703.02.
Materials shall meet 703.01 General Requirements.
Drainage Geotextile Type I conforming to Section 718 – Geotextiles
Perforated Corrugated High Density Polyethylene HDPE conforming to 706.16 with perforations as
detailed on the plans. Solid Corrugated High Density Polyethylene HDPE conforming to 706.16 as
detailed on the plans.
Construction Requirements. Infiltration facilities shall be constructed per the construction plans and per
the Manufacturer’s recommendations.
Filter Sand and 2” drain rock shall be from an ITD approved source and shall be placed according to the
details shown in the plans.
2” drain rock should be aesthetically acceptable to the Owner.
Care shall be taken during excavation and placement of filter sand to avoid compaction of the underlying
soils. Filter sand shall extend into free-draining material. When placing drain rock, care should be taken
to avoid damage to drainage geotextile and perforated drain pipe.
Structure excavation shall meet the requirements of Section 210 – Structure Excavation and Compacting
Backfill. Subgrade shall not be compacted.
The bottom of the filter sand shall extend a minimum of 2 feet into free draining soil and the bottom of
the 2” drain rock shall be at least 3 feet from any ground water encountered. Contractor shall have a
percolation test performed by soils engineer after infiltration facility is fully excavated to ensure design
infiltration rate (8 in/hr) is met. Notify the engineer immediately if these conditions are not met.
Method of Measurement. The quantity of Infiltration Trench will be measured by the linear foot of the
constructed length, from beginning of drainage rock to end of drainage rock.
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
S911-05A SP Infiltration Trench FT
This item shall include excavation and backfill, 2” drain rock, drainage geotextile, 18” perforated drain
pipe (where applicable), ¾” minus aggregate, filter sand, and all other miscellaneous items and labor
necessary to construct the Infiltration Trench.
PROJECT NO. A013(349); KEY NO. 13349 Page 34 of 35
S912-05A SP LAWN REPAIR
Description. This work shall consist of preparing, grading, sodding, and fertilizing the lawn areas which
have been disturbed as a result of construction activities.
Materials. Grass sod shall consist of Merion, Park, Delta or Windsor Kentucky Bluegrass, or
combinations of approved fine textured grasses suitable for the area designated for sodding. Grasses shall
be true to type and name in accordance with the Standard Plant Names current edition by the editorial
Committee of the American Joint Committee on Horticultural Nomenclature. Grass sod to be furnished
shall not be less than 10 months old and shall have prior approval at the supply source before cutting for
delivery to the planting site. Delivered sod shall show evidence of having been properly handled and
cared for. Sod showing evidence of improper handling or discoloration due to prolonged storage prior to
delivery and placement will be rejected.
Individual sod pieces shall be cut to a uniform size with square corners at a uniform depth of 1 to 1 1/4
inches.
Fertilizer shall have a chemical analysis of 12-6-6, or an approved equal.
Soil Amendment for sodding shall consist of sand in which particle sizes range from coarse to very coarse
(0.02 to 0.08 inch diameter) and Cascade Soil Aid, decomposed sawdust, peat moss, or equivalent.
Construction Requirements. All old damaged turf shall be removed to a uniform depth.
The lawn area shall be tilled to remove vegetative growth. All stones, hard clods, roots, sticks, debris and
other matter encountered during tilling which is detrimental to the preparation of a good seedbed, or
which is toxic to the growth of grass, shall be removed from the area and disposed of as directed.
Soil amendment shall be spread uniformly to a depth of 2" over the area and thoroughly rototilled to a
depth of four inches.
After cultivation, the area shall be carefully fine graded and rolled to provide a fine textured, smooth and
firm surface, free of any foot prints, undulations or irregularities. All irregularities in the surface that form
pockets where water will stand or accumulate shall be smoothed out to provide good drainage. The
finished grade of the sod bed shall be 1 1/4 to 1 1/2 inches below the finished grade of the walks to permit
the placing of sod to final grade 1/4 inch below the finished grade of the walks.
The first row of sod shall be laid in a straight line and subsequent rows placed parallel to and tightly
against each other. The joints between strips shall be butted together, tightly and shall not have any gaps.
Lateral joints shall be staggered. Care shall be exercised to insure that the sod is not stretched or
overlapped, and that all joints are butted tight.
After placing sod, the lawn shall be adequately rolled diagonally with a 100 pound sod roller and watered
heavily. The surface of the finished sod shall be smooth and uniform.
Fertilizer shall be applied at the manufacturer's recommended rate one month after sodding is complete.
The establishment period for the sod lawn shall end two weeks after completion and acceptance of the
lawn. Fertilizer shall not be used within 50-ft of a waterway or wetland.
Method of Measurement. The quantity of Lawn Repair to be measured will be measured by the number
of square yards of sod laid according to specifications, complete in place.
Basis of Payment. Payment for accepted work will be made as follows:
PROJECT NO. A013(349); KEY NO. 13349 Page 35 of 35
Pay Item Pay Unit
S912-05A SP Lawn Repair SY
S912-05B SP LANDSCAPE REPAIR
Description. This work shall consist of replacing impacted landscaping with similar plants and features.
Materials. Match existing landscaping in adjacent areas or as directed by the Engineer.
Construction Requirements. Replace plantings and other landscaping features with similar type using
locally accepted practices.
Method of Measurement. The quantity of Landscape Repair to be measured will be measured by the
number of square yards of repaired area according to specifications, complete in place.
Basis of Payment. Payment for accepted work will be made as follows:
Pay Item Pay Unit
S912-05B SP Landscape Repair SY
Eagle Road Water Main Relocation and Abandonment
City Project #11079
CITY OF MERIDIAN
EAGLE ROAD
WATER MAIN RELOCATION AND ABANDONMENT
GENERAL PROVISIONS
1. BASIS OF PAYMENT
Except as modified herein, the various work items called for on the "Bid Schedule" will be
performed, measured and paid for as indicated on said Bid Schedule and as provided in the
Current Edition of the Idaho Standards For Public Works Construction (ISPWC); the City of
Meridian Supplemental Specifications and Drawings to the ISPWC (and any addendums);
adopted ACHD Supplements and Idaho Department of Transportation (ITD) Standard
Specifications. The Contractor is required to be a current holder of the Idaho Standards For
Public Works Construction, Meridian Supplemental Specifications and Drawings, all ACHD
supplements and ITD Standard Specifications. Any work required to complete the project but not
specifically included in a bid item shall be considered incidental to the project and no separate
payment shall be made.
2. DAMAGE
The Contractor will be responsible for retaining and protecting all fire hydrants, mail boxes,
sprinkler systems, shrubs, sod, landscaping, trees, fences, etc., within the construction limits,
unless otherwise shown on the plans. The Contractor will also be responsible for retaining and
protecting all improvements outside the construction limits. Any items damaged shall be
promptly repaired or replaced to a condition “equal to or better” than existed prior to
construction by the Contractor. The cost to complete such repairs shall be considered as
incidental to the cost of the project and no separate payment will be made.
3. PROJECT MAINTENANCE
The Contractor will be responsible for project maintenance throughout the life of the contract.
This responsibility includes, but is not limited to, dust control, maintenance of irrigation
facilities, blading, maintenance of detours, maintenance of all intersecting street approaches,
proper and adequate drainage, access for emergency equipment and appropriate access for
property owners.
The cost of all maintenance work shall be considered incidental to other project work and no
separate payment will be made.
4. COORDINATION
It shall be the Contractor's responsibility to contact and work with the property owners, irrigation
districts, ditch riders, utility companies, and any other parties as necessary to coordinate and
install improvements required by this project. This coordination effort shall include, but not be
limited to, coordination with utility companies in their efforts to relocate their facilities as a
Eagle Road Water Main Relocation and Abandonment
City Project #11079
result of this project, and working other than normal working hours to permit the relocation of
the utilities and construction of the required improvements within the time frame of this contract.
Utility information is shown only for surface features. The information shown is for reference
purposes only and does not necessarily represent actual field conditions. The Engineer assumes
no liability for the accuracy of the information shown, or conflicts due to inaccurate or
incomplete utility information. The Contractor shall call Dig Line a minimum of 48 hours prior
to any excavation to request utility locations at 1-800-342-1585.
The Contractor shall expose all existing utility crossings to verify locations and elevations prior
to any other construction that may affect those utilities. The cost associated with exposing the
existing utilities is considered incidental to the project and no separate payment will be made
unless otherwise specified on plans.
Contractor shall coordinate all work with property owners and complete all work within existing
public utilities or irrigation easements. All disturbed surfaces shall be restored to a condition
equal to or better than existed prior to construction. All surface restoration shall be considered
incidental to the project and no separate payment will be made.
5. ACCESS TO PROJECT
Local access, business, and emergency vehicle access shall be maintained at all times.
6. QUANTITY PAYMENT
Payment will be made for the actual quantity of each bid item completely installed and accepted
by the Owner. Payment will be based upon the units specified for each item at the unit prices
shown in the bid schedule or approved change order.
7. COMPACTION
Compaction requirements shall be in accordance with Section 204 – Structural Excavation and
Compacting Backfill, Section 306 - Trench Backfill, and applicable sections of Division 800 –
Aggregates & Asphalts, of the ISPWC Specifications; Subsection 205.03(F) of the ITD
Standard Specifications for Highway Construction. The cost to complete this work including
watering and drying shall be considered incidental to the cost of the project and no additional
payment shall be made. Contractor shall provide compaction testing of all materials by an
independent thirty party testing firm. A copy of testing results shall be provided to the City
Public Works Inspector.
All excavation and trenching shall meet OSHA requirements and the applicable portions of the
ISPWC and the ITD Standard Specifications. All cost to complete trench excavation and
backfill is considered incidental to the pipe installation bid item and no separate payment will be
made.
Eagle Road Water Main Relocation and Abandonment
City Project #11079
8. LANDSCAPING
The Contractor shall maintain the existing landscaping in the same condition as found. If the
contractor is unable to work around the landscaping then the work shall be completed and the
contractor shall repair or replace the landscaping to an "as good or better condition" than existed
before work started. The Contractor shall retain and protect any sprinkler systems encountered,
unless specifically designated otherwise. The cost of this work shall be considered incidental to
the project. All work to remove and reinstall existing trees or bushes shall be completed by a
licensed landscape contractor. Removed trees or bushes that Contractor plans to reinstall shall
be properly bedded and irrigated during construction activities. If existing trees and bushes are
replaced with a new tree or bush, they shall be of same type and property owner shall approve
items prior to Contractor planting items. Each new tree shall have a minimum caliper of
2-inches.
9. MISCELLANEOUS
The Contractor shall repair or pay the owner to repair, any utility damaged during construction.
The Contractor shall repair any sprinkler systems damaged during construction. The cost of
these repairs, unless specifically identified as a bid item, shall be considered as incidental to the
cost of the project, and no separate payment will be made.
Removing and resetting of any existing street signs, fences, mailboxes, or miscellaneous items as
required shall be incidental to the project and no separate payment shall be made.
The Contractor shall perform, coordinate and schedule various construction tasks such that
adequate protection is provided to all existing and new underground utilities.
10. HIGH VOLTAGE, OVERHEAD, POWER LINES
The Contractor's attention is directed to, and compliance is required with, the requirements of
Title 55, chapter 24, Idaho Code, which regulates certain work by contractors near high voltage,
overhead, power lines.
11. SURVEYING
The Owner will provide one set of horizontal control construction stakes for each new fire
hydrant, new water main casing, new water main bend and at 100’ intervals along new water
main. Vertical control shall be based off roadway improvement plans and roadway staking
provided by others.
It shall be the Contractor’s responsibility to protect construction stakes once requested by the
Contractor. Construction stakes destroyed after being requested by the Contractor shall be
restored at Contractor’s expense. These costs shall be deducted from progress payments. The
Contractor shall remove all construction stakes remaining at project completion. The cost to
remove stakes shall be considered incidental to the project.
Contractor shall preserve all survey land monuments. If monuments are disturbed, Contractor
shall be responsible for having a licensed professional surveyor reestablish monuments. Cost
Eagle Road Water Main Relocation and Abandonment
City Project #11079
shall be considered incidental to project. If Contractor fails to have monuments reestablished,
the Owner shall contract with a licensed surveyor to reestablish disturbed monuments and the
cost shall be deducted from the final payment.
12. TESTING
Contractor shall provide compaction testing of all materials by an independent third-party testing
firm. A copy of testing results shall be provided to the City Public Works Inspector. The
Contractor shall provide all testing required to meet ACHD and ITD permit requirements.
Contractor shall complete all ITD required forms for inspection, material testing and material
certification.
Trenches and asphalt shall be tested per the appropriate section of the ISPWC, ACHD and ITD
permit requirements.
Re-testing necessitated by the failure of quality assurance testing of materials placed by the
Contractor shall be at the Contractor’s expense. These costs shall be deducted from progress
payments.
13. ON-SITE SUPERVISION
The General Contractor shall provide competent on-site supervision during any and all
construction activities by his forces or subcontractors. The superintendent shall be identified at
the preconstruction conference, and at a minimum be on-site from notice to proceed date to the
substantial completion date. If for any reason the superintendent needs to be replaced by the
General Contractor, a written notice must be submitted to the Owner within (5) five working
days before the event occurs.
14. PERMITS
The Contractor, at his own expense, shall procure all permits, certificates and licenses required
of him by law for execution of the work. He shall comply with all federal, state, or local laws,
ordinances or rules and regulations relating to the performance of the work. He shall file such
reports of construction as required by law. The cost for this work is considered incidental to the
project and no separate payment will be made.
Contractor shall be responsible for obtaining an ACHD right-of-way permit (which is a no cost
permit) for water line work on public roadways adjacent to Eagle Road (SH-55). A copy of the
permit shall be provided to the City of Meridian Project Manager prior to starting work.
This work is subject to the requirements of any permits obtained from the Idaho Department of
Transportation (ITD) to complete the roadway and utility improvements. The Contractor shall
comply with the requirements of all permits. The Contractor shall be responsible for contacting
ITD and providing all notifications and forms as required by the permit. The cost of compliance
is considered incidental to the project and no separate payment will be made.
Eagle Road Water Main Relocation and Abandonment
City Project #11079
15. SERVICE INTERUPTIONS
Contractor shall provide continuous sewer and water service to all affected properties. Service
disruptions of less than 4 hours may be acceptable with prior approval from the city. Property
owners shall be notified of any service disruptions a minimum of 48 hours in advance.
Contractor shall prepare a shutdown plan and submit the plan to the City at the pre-construction
conference for review and approval. No work shall begin until the plan is approved by the City.
The plan shall include the number of shutdowns, limits of each shutdown, time frame of each
shutdown and properties to be impacted by each shutdown. The plan shall also include
information about how the Contractor plans to notify impacted properties prior to each shutdown
and which properties will be notified with each shutdown. If during construction the contractor
wishes to make changes to the plan then the Contractor shall revise the plan and resubmit it to
the City for approval.
15. PRIVATE PROPERTY ACCESS
Prior to starting work on private property, the Contractor shall obtain written permission from
the property owner to access each property to do the work. The Contractor shall take pictures of
each property prior to starting the work. After all work is completed, the Contractor shall take
pictures of each property and have each property owner provide written documentation that their
property has been restored to an acceptable level. A copy of the pictures and written
documentation shall be provided to the City. Contractor shall notify each property owner a
minimum of 48 hours in advance of starting work on their property and/or any service
interruptions.
Contractor shall be responsible for contacting property owners and business owners to develop a
work activity plan and a work schedule that is acceptable to the property owner, business owners
and the City. Contractor shall be expected to develop a work activity plan and a work schedule
that will limit the impact to businesses and associated parking lots.
The Contractor shall be responsible for having each property owner sign the release form
provided in Appendix B of these documents. The form shall be signed once all work has been
completed. Final payment shall not be made by the City of Meridian until a copy of each form
has been provided to the City.
Eagle Road Water Main Relocation and Abandonment
City Project #11079
SPECIAL PROVISIONS
1. 307.4.1.G.1 – TYPE P SURFACE RESTORATION
ON PAGE 1 OF SECTION 307 OF THE ISPWC, PART 1, add the following:
All work shall be in accordance with the Contractor’s Ada County Highway District right-of-
way permit for water line work on public roadways adjacent to Eagle Road (SH-55).
All work is subject to the requirements of any permits obtained from the Idaho Department of
Transportation (ITD) to complete the roadway and utility improvements. The Contractor shall
comply with the requirements of all permits. The Contractor shall be responsible for contacting
ITD and providing all notifications and forms as required by the permit.
ON PAGE 2 OF SECTION 307 OF THE ISPWC, PART 2, add the following:
All materials within public roadways shall be in accordance with the requirements of the Ada
County Highway District or the Idaho Transportation Department, whichever is the roadway
governing agency.
ON PAGE 5 OF SECTION 307 OF THE ISPWC, PART 3.8.B, add the following:
All construction within public roadways shall be in accordance with the requirements of the Ada
County Highway District or the Idaho Transportation Department, whichever is the roadway
governing agency.
ON PAGE 5 OF SECTION 307 OF THE ISPWC, PART 3.8.C, add the following:
Base and subbase section shall match existing section unless otherwise required or approved by
the Ada County Highway District or the Idaho Transportation Department, whichever is the
roadway governing agency.
ON PAGE 5 OF SECTION 307 OF THE ISPWC, PART 3.8.E, add the following:
Pavement section shall match existing section unless otherwise required or approved by the Ada
County Highway District or the Idaho Transportation Department, whichever is the roadway
governing agency.
ON PAGE 9 OF SECTION 307 OF THE ISPWC, PART 4.1, add the following:
Construction limits for this item shall be as shown on the plans. Any surface restoration required
beyond the specified construction limits shall be made by the Contractor at his expense and no
separate payment will be made unless pre-approved by the City of Meridian.
2. 307.4.1.G.3.1 – TYPE P SURFACE RESTORATION WITH PAVEMENT FABRIC
ON PAGE 1 OF SECTION 307 OF THE ISPWC, PART 1, add the following:
Eagle Road Water Main Relocation and Abandonment
City Project #11079
All work shall be in accordance with the Contractor’s Ada County Highway District right-of-
way permit for water line work on public roadways adjacent to Eagle Road (SH-55).
All work is subject to the requirements of any permits obtained from the Idaho Department of
Transportation (ITD) to complete the roadway and utility improvements. The Contractor shall
comply with the requirements of all permits. The Contractor shall be responsible for contacting
ITD and providing all notifications and forms as required by the permit.
ON PAGE 2 OF SECTION 307 OF THE ISPWC, PART 2, add the following:
All materials within public roadways shall be in accordance with the requirements of the Ada
County Highway District or the Idaho Transportation Department, whichever is the roadway
governing agency.
ON PAGE 3 OF SECTION 307 OF THE ISPWC, PART 2.4.A, replace the section with the
following:
Type III geotextile (filter fabric) shall be placed between the subgrade and the subbase in
accordance with section 718.07 of ITD Standard Specifications for Highway Construction.
ON PAGE 6 OF SECTION 307 OF THE ISPWC, PART 3.9.B, add the following:
All construction within public roadways shall be in accordance with the requirements of the Ada
County Highway District or the Idaho Transportation Department, whichever is the roadway
governing agency.
ON PAGE 6 OF SECTION 307 OF THE ISPWC, PART 3.9.C, add the following:
Base and subbase section shall match existing section unless otherwise required or approved by
the Ada County Highway District or the Idaho Transportation Department, whichever is the
roadway governing agency.
ON PAGE 6 OF SECTION 307 OF THE ISPWC, PART 3.9.E, add the following:
Pavement section shall match existing section unless otherwise required or approved by the Ada
County Highway District or the Idaho Transportation Department, whichever is the roadway
governing agency.
ON PAGE 9 OF SECTION 307 OF THE ISPWC, PART 4.1, add the following:
Construction limits for this item shall be as shown on the plans. Any surface restoration required
beyond the specified construction limits shall be made by the Contractor at his expense and no
separate payment will be made unless pre-approved by the City of Meridian.
3. 308.4.1.A.1. – PIPE BORING AND JACKING
ON PAGE 1 OF SECTION 308 OF THE ISPWC, PART 1.1.A, add the following;
Eagle Road Water Main Relocation and Abandonment
City Project #11079
This item includes furnishing all materials, equipment, and labor necessary to bore pipe
crossings at the locations shown on the plans. Includes bore pit excavation and backfill, and all
other miscellaneous work and materials required for a complete and workable installation. The
steel casing pipe, pipe skids and end seals shall be furnished under the casing pipe bid item.
Contractor shall contact governing irrigation district at least five days prior to starting work near
irrigation facilities.
4. 310.4.1.A.1. – PIPE CASING AND SLEEVING
See Section 310 of the City of Meridian Supplemental Specifications to the ISPWC.
ON PAGE 5 OF SECTION 310 OF THE SUPPLEMENTAL SPECIFICATIONS, PART 2, add
the following:
Carrier pipe skids shall be a polyethylene casing spacer/insulator suitable for use with the type of
carrier pipe material. They shall be a Calpico Model PX casing insulator, a CCI Piping Systems
Model CSP casing spacer or an approved equal. The Contractor shall confirm that the casing
spacer/insulator is suitable for use with the type of carrier pipe and the size of casing prior to
ordering the casing spacer/insulator. It is expected that the Calpico Model PX casing insulator
will not be suitable for use with all of the carrier pipes types and casing sizes included in this
project.
Water tight end seals shall be 1/8” thick neoprene seal boots attached to the pipe with stainless
steel worm gear bands.
Joint Restraints on PVC bell and spigot pipe shall be Uni-Flange Series 1350 or approved equal.
Contractor shall verify joint restraints fit inside casing and adjust casing size as necessary prior
to ordering casing.
ON PAGE 5 OF SECTION 310 OF THE ISPWC, PART 3, add the following:
Carrier pipe skids shall be installed in water main casings. Skids are not required on water
service lines of 2” Ø or less.
The ends of the annular space on all sleeves and casings shall be sealed with water tight seal
boots.
The casing pipe shall be installed at the same slope as the carrier pipe and the carrier pipe shall
be centered inside the sleeve or casing pipe.
Joint restraints shall be installed on PVC bell and spigot pipe water main at each joint inside
casing.
The annular space between the casing and carrier pipes SHALL be filled when the carrier pipe is
HDPE pipe. The annular space between the casing and carrier pipe SHALL NOT be filled
when the carrier pipe is fusible PVC pipe.
Eagle Road Water Main Relocation and Abandonment
City Project #11079
When extending an existing steel casing the new steel casing shall be welded to the existing steel
casing to seal off the joint. Joints shall be butt welded or butt welded using butt straps if
necessary to protect existing pipe.
When using an existing water main as a casing pipe for a new water main, the existing water
main shall be completely drained and or pumped out to remove all water prior to installing the
new water main.
ON PAGE 6 OF SECTION 310 OF THE SUPPLEMENTAL SPECIFICATIONS TO THE
ISPWC, PART 4.1.A., replace with the following:
Pipe Casing and Sleeving: By the linear foot measured on a horizontal basis through the
centerline of the casing or sleeve pipe for the size of pipe indicated. Includes casing or sleeve
pipe, pipe skids, carrier pipe joint restraints, annular space filling, end seals, and all
appurtenances necessary for the completion of the bid item.
5. 401.4.1.A.1. – WATER MAIN
ON PAGE 4 OF SECTION 401 OF THE ISPWC, PART 2.2., add the following:
Water main shall be bell and spigot PVC pipe, fusible end PVC pipe, or HDPE pipe as indicated
on the plans. HDPE flange adapters and HDPE bend fittings shall match the HDPE pipe
pressure class.
ON PAGE 7 OF SECTION 401 OF THE ISPWC, PART 2.8.C., add the following:
A HDPE pipe concrete anchor shall be installed at the locations shown on the plans. The
concrete shall be per ISPWC Section 703 – Cast-in-Place Concrete. The minimum compressive
strength of the concrete shall be 2,500 psi. Multiple electrofusion flex restraints shall be attached
to the outside of the pipe and centered in the concrete anchor. The number of flex restraints used
shall be per manufactures recommendations. The electrofusion flex restraint shall be by GF
Piping Systems, Integrity Fusion Products or approved equal.
ON PAGE 9 OF SECTION 401 OF THE ISPWC, PART 3.2.R., add the following:
HDPE pipe shall be joined together by heat fusion (butt welds) and the HDPE pipe shall be
allowed to acclimate to new temperature for a time period recommended by pipe manufacturer
prior to connecting any fittings or valves.
Fusible PVC pipe and HDPE pipe fusion process shall be performed by a technician and/or
contractor licensed and trained by pipe manufacturer. Only appropriately sized and outfitted
fusion machines that have been approved by the pipe supplier shall be used for the fusion
process. Each fusion joint shall be recorded and logged by an approved electronic monitoring
device (data logger) connected to the fusion machine, which utilizes a current version of the pipe
supplier’s recommended and compatible software.
ON PAGE 9 OF SECTION 401 OF THE ISPWC, PART 3.2.S., add the following:
Eagle Road Water Main Relocation and Abandonment
City Project #11079
Contractor shall provide all temporary piping, valves, blow-offs, and other items required to
install the new water pipe and to maintain service to existing users.
ON PAGE 11 OF SECTION 401 OF THE ISPWC, PART 3.9, add the following:
Flushing and disinfection shall be in accordance with section 401.3.9 of the City of Meridian
Supplemental Specification and Drawings to the ISPWC. Heavily chlorinated water (above
normal system residuals) shall be flushed through a dechlorinator such as a Romac Dechlorinator
(378-0320) or other commercial device capable of dechlorinating the disinfection water
concentration and flow encountered. Contractor shall receive permission in writing from land
owner, irrigation district or storm drain system owner prior to discharging to land, irrigation
facility or storm drain system.
Flushing shall also be in accordance with the Idaho Department of Environmental Quality
(IDEQ) Guidance for Public Water System Disposal of Water from Construction, Maintenance,
and Operations. This document can be found at:
http://www.deq.idaho.gov/media/1117311/pws-disposal-guidance-0414.pdf
ON PAGE 17 OF SECTION 401 OF THE ISPWC, PART 4.1.A., add the following:
Fittings are called out on the plans in order to aid the Contractor in understanding the intent of
the planned construction. All required fittings are considered incidental to the pipe bid item and
no separate payment will be made. Any additional fittings required to complete the work which
are not shown on the plans shall be furnished and installed by the Contractor under the pipe bid
item and no separate payment will be made. The Contractor may provide fittings differing from
those called for on the plans with the approval of the Meridian Public Works Department.
The Contractor shall provide all materials, equipment, and labor necessary to make adjustments
at non-potable pipe crossings to install water main in accordance with the Idaho Rules for Public
Drinking Water Systems (IDAPA 58.01.08).
6. 402.4.1.A.1. – GATE VALVE
ON PAGE 4 OF SECTION 402 OF THE ISPWC, PART 2.7, add the following:
Valve box lids shall be a non-pop lid as manufactured by SW Services. Lid shall be blue in color
and stamped “WATER”.
ON PAGE 4 OF SECTION 402 OF THE ISPWC, PART 3.2, add the following:
Contractor shall protect and retain valve covers through all phases of construction. Preliminary
adjustments may be required to allow placing of base courses and paving over the valve boxes.
Valve boxes shall be adjusted to final grade and the concrete collar constructed after paving is
completed.
7. 706.4.1.G.1. – CONCRETE REPAIR
ON PAGE 3 OF SECTION 706 OF THE ISPWC, PART 3, add the following:
Eagle Road Water Main Relocation and Abandonment
City Project #11079
All pedestrian ramps damaged during construction shall be reconstructed with ADA detectable
warning domes in accordance with the ISPWC, ITD requirements, ACHD requirements, and
ADA requirements.
All concrete repair shall occur from existing joint to existing joint.
ON PAGE 7 OF SECTION 706 OF THE ISPWC, PART 4.1.G., add the following:
Construction limits for this item shall be as shown on the plans. Any concrete repair required
beyond the specified construction limits shall be made by the Contractor at his expense and no
separate payment will be made unless pre-approved by the City of Meridian.
8. 1001.4.1.A.1. – SEDIMENT CONTROL
ON PAGE 1 OF SECTION 1001 OF THE ISPWC, PART 1.1, add the following:
This item shall also include furnishing all materials, equipment and labor required to provide
storm water management during construction in accordance with the City of Meridian’s
Construction Storm Water Management Program. See Appendix A.
ON PAGE 1 OF SECTION 1001 OF THE ISPWC, PART 1.1, add the following:
The Contractor shall prepare and submit an Erosion and Sediment Control Plan (ESCP) to the
City, ITD and ACHD for approval. The Contractor shall make any required changes to the
ESCP and resubmit for final approval. A copy of the final approved ESCP shall be provided to
the City of Meridian prior to starting work. Coordinate erosion and sediment control activities
with the City Project Manager, City Inspector and or Environmental Programs Coordinator.
Contractor shall be responsible for providing all storm water management in accordance with all
local, state, and federal laws. Contractor shall determine expected area of disturbance and apply
for applicable permits. Contractor shall prepare and submit a Storm Water Pollution Prevention
Plan (SWPPP), Notice of Intent, Notice of Termination, and any other required forms to the
EPA.
Contractor is responsible for installing, maintaining, removing and disposing of all Best
Management Practices (BMPs) and for all documentation required to keep the ESCP current.
All items that are not specifically itemized on the bid schedule shall be considered incidental to
the project.
9. 1103.4.1.A.1. – CONSTRUCTION TRAFFIC CONTROL
ON PAGE 1 OF SECTION 1103 OF THE ISPWC, PART 1.1, add the following:
This item includes providing all necessary traffic control to complete the City of Meridian utility
work that is not provided as part of the roadway improvement project traffic control bid item.
ON PAGE 7 OF SECTION 1103 OF THE ISPWC, PART 4.1.A., replace the entire section with:
Eagle Road Water Main Relocation and Abandonment
City Project #11079
Payment for Traffic Control shall be on a lump sum basis. Partial payment shall be made as
follows: 1) 50% of the contract unit price will be made on the first progress payment. 2)
Remaining 50% of contract unit price will be made on the second progress payment.
10. 2030.4.1.C.1. – ADJUST EXISTING VALVE BOX TO GRADE
ON PAGE 1 OF SECTION 2030 OF THE ISPWC, PART 1.1.A, add the following:
All adjustments required on new water valve boxes installed as part of this project shall be
considered incidental to the gate valve bid item.
Existing valve box lids shall be replaced with an ABS/Polycarbonate non-pop lid as
manufactured by SW Services. Lid shall be blue in color and stamped “WATER”.
A concrete collar shall be constructed at each valve box.
ON PAGE 3 OF SECTION 2030 OF THE ISPWC, PART 3.1.F., replace the entire section with
the following:
Contractor shall protect and retain all existing valve covers through all phases of construction.
Preliminary adjustments may be required to allow placing of base courses and paving over the
valve boxes. Valve boxes shall be adjusted to final grade and the concrete collar constructed
after paving is completed.
11. 2010.4.1.A.1. – MOBILIZATION
ON PAGE 1 OF SECTION 2010 OF THE ISPWC, PART 2.1.A., replace the entire section with:
Project information signs shall be furnished, installed and subsequently removed at each end of
the project. Signs shall be prepared in accordance with ITD permit, ACHD permit and City of
Meridian Standard Drawing G4.
ON PAGE 2 OF SECTION 2010 OF THE ISPWC, PART 4.1.A., replace the entire section with:
Payment for Mobilization shall be on a lump sum basis. Partial payment for Mobilization
shall be made as follows: 1) 50% of the contract unit price will be made on the first progress
payment. 2) Remaining 50% of contract unit price will be made on second progress payment.
12. SP-1 – ABANDON EXISTING WATER LINE
Description: This section of the specifications includes furnishing all materials, equipment and
labor necessary to abandon existing water lines at the locations shown on the plans.
Workmanship: All existing water lines to be abandoned shall be excavated and removed from
the project unless otherwise noted on the plans to be abandoned in place and filled with sand or
low strength grout. Existing water lines shall be abandoned in place and filled when the line to
be abandoned falls within the existing Eagle Road pavement and the pavement is not being cut as
part of the roadway improvement project.
Eagle Road Water Main Relocation and Abandonment
City Project #11079
Abandonment and removal of existing water lines shall consist of excavating and removing all
pipe, fittings, valves, thrust blocks, concrete collars and other appurtenances from the project
site.
Abandonment in place and filled with sand or low strength grout, shall consist of excavating and
removing all fittings, valves, thrust blocks and concrete collars from the project site. The
existing pipe shall be filled with sand or low strength grout and each end of the existing pipe
shall be capped or plugged with 24” of concrete.
When an existing water service line to be abandoned is connected to an existing water main that
is to be kept in service, then a red brass plug shall be installed in the service saddle at the existing
water main and a minimum of 5’ of the service line shall be removed. Abandoned service pipe
shall be removed to the extent possible, without performing significant amounts of additional
unnecessary excavation.
Contractor shall allow the City to inspect all removed materials and the City shall determine
which materials they wish to retain. Contractor shall deliver all materials the City wishes to
retain to the City Water Department storage yard. Contractor shall remove all other materials
from the job site and dispose of them at an appropriate site.
Measurement and Payment: Abandon Existing Water Main shall be on a per each basis and
shall include all labor, equipment, and materials necessary for the completion of the bid item.
Payment for this item shall be made under:
SP-1 Abandon Existing Water Line…………………………..…………...…..Per Linear Foot
13. SP-2 – LAWN SOD RESTORATION
Description: This item includes furnishing all materials, equipment, and labor necessary to
restore existing sod surfaces or establish new sod surfaces at the locations specifically shown on
the plans. All other existing sod areas damaged during construction shall be restored and
considered incidental to the project.
Materials: Fertilizers shall comply with the following chemical analysis:
15% to 20% Nitrogen (N)
20% to 25% Phosphorous (P2O5)
2% to 10% Potassium (K2O)
Sod shall consist of Merrion, Parks, Delta or Windsor Kentucky Bluegrass or combinations of
approved fine textured grasses suitable for the area to be sodded and closely matching adjacent
grass.
Workmanship: The lawn areas shall be tilled to a minimum depth of 6 inches by such means as
will loosen the soil and bring it to condition suitable for fine grading. Prior to and during the
operation, the surface shall be made free of vegetative growth. All stones, hard clods, roots,
sticks, debris and other matter encountered during tilling which are detrimental to the
Eagle Road Water Main Relocation and Abandonment
City Project #11079
preparation of a good seed bed, or which are toxic to the growth of grass, shall be removed.
Four inches of topsoil shall then be placed under the areas to receive sod.
The area shall be floated and rolled to bring it to the finished grade. All irregularities in the
surface that form pockets where water will stand shall be smoothed out to provide good
drainage. The finished grade of lawn area adjacent to walks, curbs, driveways and pavements
shall be approximately 1 inch below adjacent grades.
Fertilizers shall be spread evenly over the cultivated areas at a rate of 4 pounds per 1,000 square
feet and shall be uniformly incorporated into the upper 3 inches of the soil, after which the areas
shall be worked as necessary to provide a smooth, firm but friable lawn bed at the established
grades.
Sod shall be placed in straight strips. The joints between strips shall be butted together, tight and
without gaps. Sod shall be placed in a manner to stagger the end joints of the rolls. The sod shall
be rolled with a 100-pound roller after placement. The surface of the finished sod shall be
smooth, uniform and mowable.
Contractor shall repair any damaged sprinkler systems and adjust all disturbed sprinkler heads.
Measurement and Payment: Lawn Sod Restoration shall be on a square foot basis and shall
include all labor, equipment, and materials necessary for the completion of the bid item.
Construction limits for this item shall be as shown on the plans. Any sod restoration required
beyond the specified construction limits shall be made by the Contractor at his expense and no
separate payment will be made unless preapproved by the City.
Payment for this item shall be made under:
SP-2 Lawn Sod Restoration…………........……………………………...…..Per Square Foot
14. SP-3 – REMOVE EXISTING TREE
Description: This item includes furnishing all materials, equipment, and labor necessary to
remove existing trees at the locations shown on the plans.
Workmanship: The entire tree shall be removed, including the stump and roots, or if the removal
of the roots could damage nearby structures or utilities, the Contractor shall grind up the stump
and shallow roots.
The Contractor shall be responsible for protecting existing trees not called out for removal with
the water line improvement project area and must use practible care in the protection of trees,
tree branches and tree roots within the construction limits. Excavation for the water line
improvements shall be carried out in a way that avoids root damage as much as practicable.
Existing trees overhanging the project area may be impacted by the Contractor’s construction
activities. If necessary, the Contractor shall trim existing tree limbs and roots that can’t be
avoided. All trimming shall be performed by a tree service company under the supervision and
direction of a certified arborist.
Eagle Road Water Main Relocation and Abandonment
City Project #11079
Measurement and Payment: Remove Existing Tree shall be on a per each basis and shall include
all labor, equipment, and materials necessary for the completion of the bid item.
Payment for this item shall be made under:
SP-3 Remove Existing Tree...…………………………………......………...……..…Per Each
15. SP-4 – CCTV EXISTING WATER MAIN TO CONFIRM SUITABILITY AS A CASING
Description: This item includes furnishing all materials, equipment and labor necessary to
complete a CCTV inspection on the existing water main to confirm its suitability for using as a
casing pipe at the locations shown on the plans.
Workmanship: Contractor shall confirm that the existing pipe is in good condition and that there
are no fittings on the water main or other issues that would prevent the installation of a new
water main within the existing water main.
Measurement and Payment: CCTV Existing Water Main to Confirm Suitability as a Casing
shall be on a per linear foot basis and shall include all labor, equipment, and materials necessary
for the completion of the bid item.
SP-4 CCTV Existing Water Main to Confirm Suitability as a Casing…..…..Per Linear Foot
16. SP-5 – WATER SERVICE LINE (METER TO MAIN)
Description: This item includes furnishing all materials, equipment and labor necessary to
install a new water service line from the new mater main to an existing or relocated water meter
setter at the locations shown on the plans.
Workmanship: City of Meridian Specifications prohibit the splicing of water service lines
therefore, a new line shall be installed continuous from the new water main to the existing meter
setter unless identified on the plans and approved by the City of Meridian.
Transferring the connection of a service from an existing main to a new main shall only occur
after the new main is completed, pressure tested, disinfected and approved for service.
Transferring the service shall consist of excavating the service at the water meter, excavation of a
trench from the existing meter to the new water main, furnishing and installing a tapping saddle
and corporation stop, furnishing and installing a new service line from the new main to the
existing meter setter, making all connections, backfilling the trench and other work required to
complete the transfer. The existing service pipe shall be removed to the extent possible, without
performing significant amounts of additional unnecessary excavation.
Measurement and Payment: Water Service Line (Meter to Main) shall be on a per linear foot
basis and shall include all labor, equipment, and materials necessary for the completion of the
bid item.
Eagle Road Water Main Relocation and Abandonment
City Project #11079
Payment for this item shall be made under:
SP-5 Water Service Line (Meter to Main). ……...……………………………Per Linear Foot
Eagle Road Water Main Relocation and Abandonment
City Project #11079
A P PENDIX A
CONSTRUCTION STORM WATER
MANAGEMENT PROGRAM (CSWMP)
FOR CITY OF MERIDIAN
CONTRUCTION PROJECTS
Revised July 2, 2013
CITY CAPITAL IMPROVEMENT PROJECTS
WATER POLLUTION CONTROL
GENERAL
Water pollution control work shall conform to the provisions in the latest edition of the
Construction Stormwater Management Program (CSWMP) For City of Meridian Construction
Projects and all other local , State and Federal requirements for prevention of stormwater
pollution from construction activity including, but not limited to , the U.S. Environmental
Protection Agency (EPA) Construction General Permit (CGP).
The Contractor shall obtain other National Pollutant Discharge Elimination System (NPDES)
permits that apply to activities and mobile operations within or outside of the project limits
including asphalt batch plants , material borrow areas , concrete plants, staging areas, storage
yards , or access roads. Copies of additional required coverage permits shall be maintained with
the stormwater management plan.
The Contractor shall perform water pollution control work in conformance with the requirements
of the CSWMP; any Stormwater Pollution Prevention Plan (SWPPP) or Erosion Sediment
Control Plan (ESCP) as well as the Construction General Permit (CGP) and its addenda in effect
on the day Notice of Award is dated, or which became effective during the life of the
construction project as directed by the EPA.
The CGP and other references to Federal documents related to performing water pollution
control work are available from the Environmental Protection Agency 's (EPA) web site at:
http://cfpub.epa.gov/npdes/stormwater/cgp.cfm
EROSION AND SEDIMENT CONTROL PLANS
For City construction projects that do not require coverage under the CGP, the Design
Consultant shall prepare an Erosion and Sediment Control Plan (ESCP). The ESCP will be a
simplified version of the SWPPP associated with larger projects and include the following
components:
• Project name, location map, and responsible Contractor;
• Project description;
• Identification of potential pollutants and potential impacts on water quality; and ,
• Plan drawings depicting storm water management strategy, including the management of
wastes and non-storm water discharges.
For City construction projects that do not require coverage under the CGP, and are constructed
entirely within the Ada County Highway District (ACHD) right of way , the Design Consultant
shall prepare the Erosion and Sediment Control Plan (ESCP) to meet ACHD 's storm water
management requirements identified in the District's Municipal Separate Storm Sewer System
(MS4) permit.
A-1
CS WMP -Appendix A_Rev ise d Ju ly 2, 201 3.doc
A substantially complete ESCP will be submitted by the Design Engineer to the City Project
Manager prior to the beginning of bidding process for City approval. The Public Works
Environmental staff will review and approve the ESCP prior to the start of bid process. Upon
bid award and prior to implementation on site, the Contractor shall review and amend the
substantially complete ESCP for site specific conditions and/or changes in BMP's as necessary,
submit a Final ESCP to the City for review and approval, and implement the Final ESCP on site.
The Final ESCP shall be updated as required throughout construction phase using a modification
process similar to that for SWPPPs. The ESCP will be active on each City Project until the City
accepts the work. All ESCP inspections and end of project processes shall follow the SWPPP
process noted below.
STORM WATER POLLUTION PREVENTION PLAN (SWPPP)
For projects requiring coverage under the CGP, the Design Consultant shall develop and provide
to the City Project Manager for bid documents, a substantially complete SWPPP document. The
Public Works Environmental staff will review and approve all substantially complete SWPPP's
prior to inclusion into the bid documents. Upon bid award, the Contractor shall review and
amend the bid SWPPP to include contractor specific information such as duly authorized forms
and for site specific conditions and/or changes in BMP's as necessary, submit a Final SWPPP to
the City for review/approval and implement the SWPPP on site. The Public Works
Environmental staff will review and approve all Final SWPPP's prior to either operator filing an
NOI and implementation on site. The substantially complete SWPPP and Final SWPPP must
be in color, hole punched and inserted into a hard cover three ring binder, must follow the
formatting of the latest EPA SWPPP template, must be site specific, shall conform to the
requirements in the current CGP and shall include water pollution control practices for storm
water and non-storm water from areas within and outside of the job site related to construction
activities for this contract such as:
1. Staging areas.
2. Storage yards.
3. Access roads.
4. Disturbed areas.
The SWPPP shall include a schedule that:
A. Describes when work activities that could cause water pollution will be
performed.
B. Identifies soil stabilization and sediment control practices for disturbed soil area.
C. Includes dates when these practices will be complete.
The SWPPP shall include temporary water pollution control practices and their associated
contract items of work as shown on the plans or specified in these special provisions.
A-2
CSWMP -Appendix A_Revised July 2, 2013.doc
A substantially complete SWPPP will be submitted to the City Project Manager by the Design
Consultant prior to the beginning of bidding process for City approval. The Public Works
Environmental staff will review, request any necessary changes to, and approve the substantially
complete SWPPP prior to the start of bids. Upon Notice to Proceed, Contractor shall have 10
days to provide the necessary Contractor related information to be included in the substantially
complete SWPPP. Contractor related information will include, but may not be limited to;
Operator information, responsible person information and training, amended substantially
complete SWPPP for site specific conditions and/or changes in BMP's as necessary. Once the
Contractor completes review of the substantially complete SWPPP and provides the necessary
Contractor related information and makes proposed changes, the Contractor shall submit the
updated substantially complete SWPPP for approval to the City Project Manager. The
Contractor shall allow 10 days for the City's Public Works Environmental staff review. If
revisions are required, the City will provide comments and specify the date that the review
stopped. The Contractor shall revise and resubmit the Final SWPPP within 10 days of receipt of
the City's comments. The City's review will resume when the updated substantially complete
SWPPP, with changes, is resubmitted. When the City approves the Final SWPPP, the Contractor
shall submit two copies of the approved Final SWPPP to the City. Upon completion of a Final
SWPPP, the City and the Contractor shall coordinate together to submit separate Notices of
Intent (NOI) to EPA Region 10. The SWPPP shall be updated as required throughout
construction phase using a similar amendment process as stated in the EPA CGP. The SWPPP
will be active on each City Project until the City accepts the work or until the City releases the
contractor from responsibility as an operator as defined in the EPA CGP.
The Contractor shall not perform earth disturbing activities, as defined in the current version of
the EPA CGP, that may cause water pollution until the Final SWPPP has been approved by the
City, both the Contractor and the City meet the required waiting period as defined by the current
EPA CGP after filing separate NOis, and a preconstruction SWPPP inspection with the
Contractor and City has been conducted and meets the approval of the City Inspector. The City's
review and approval shall not waive any contract requirements and shall not relieve the
Contractor from complying with Federal, State and local laws, regulations, and requirements.
The Contractor shall modify the Final SWPPP, as required by current versions of the City
CSWMP and the EPA CGP throughout the life of the project to meet site requirements.
If there is a change in construction schedule or activities, the Contractor shall prepare a
modification to the Final SWPPP to identify additional or revised water pollution control
practices. The Contractor shall submit the modification to the City Project Manager who will
forward to the Public Works Environmental staff for review within a time agreed to by the City
not to exceed the number of days specified for the preparation of the Final SWPPP. The City
will review the modification within the same time allotted for the review of the Final SWPPP.
If directed by the City or requested in writing by the Contractor and approved by the City,
changes to the water pollution control work specified in these special provisions will be allowed.
Changes may include addition of new water pollution control practices. The Contractor shall
incorporate these changes in the Final SWPPP.
A-3
CSWMP -Appendix A_Revised July 2, 2013.doc
The Contractor shall keep a copy of the approved Final SWPPP and all modifications at the job
site. The Final SWPPP and all modifications shall be made available when requested by a
representative of the EPA; a state, tribal or local agency approving sediment and erosion plans,
grading plans, or storm water management plans; local government officials; the operator of a
municipal separate storm sewer receiving discharges from the site; and representatives of the
U.S. Fish and Wildlife Service or the National Marine Fisheries Service to the requestor.
Requests from the public shall be directed to the City.
IMPLEMENTATION REQUIREMENTS
The Contractor's responsibility for SWPPP implementation shall continue throughout any
temporary suspension of work ordered by the City.
The Contractor shall provide a qualified responsible person with applicable qualifications to
update SWPPPs, conduct and record inspections, and to meet other CGP requirements. A
qualified responsible person shall, at minimum, possess a City of Boise Responsible Person
certification and either be certified through the International Erosion Control Association as a
Certified Professional in Erosion and Sediment Control or Certified Professional in Stormwater
Quality; have completed a 4-hour stormwater erosion & sediment control training such as the
Idaho Transportation Department's Resident Engineer Stormwater training, or other similar
government agency training; or have similar comparable experience and certification through
another recognized agency. A copy of the certification shall be provided in the SWPPP.
At a minimum, the Owner and the Contractor shall sign and certify the SWPPP and all
associated stormwater management documentation in accordance with the CGP. If the ranking
corporate officer does not sign the SWPPP and all associated stormwater management
documentation, then they must be signed by a duly authorized person so designated by the
Contractor in a formal letter on corporate letterhead.
If the Contractor or the City identifies a deficiency in the implementation of the approved Final
SWPPP, the deficiency shall be corrected in accordance with the current EPA CGP,. The
deficiency shall be corrected before the onset of precipitation. If the Contractor fails to correct
the deficiency by the agreed date or before the onset of precipitation, the City may correct the
deficiency and deduct the cost of correcting deficiencies from payments.
If the Contractor fails to conform to the provisions of this section, "Water Pollution Control," the
City Inspector, Project Manager or Surface Water Program Administrator may order the
suspension of work (at Contractor's expense) until the project complies with the requirements of
this section.
The Contractor shall construct water pollution control items identified in the SWPPP. The
Contractor shall maintain the water pollution control items until the City has accepted the project
and the Contractor has filed an NOT with the EPA. The Contractor can only file an NOT after
receiving authorization to do so by the City.
A-4
CSWMP -Appendix A_Revised July 2, 2013.doc
INSPECTION AND MAINTENANCE
Weekly storm water management inspections will be conducted on City construction sites. The
Contractor and the City will perform weekly storm water management inspections together. One
copy of the City's Inspection Form or the current version of the EPA's Stormwater Construction
Site Inspection Report will be completed by both the City and the Contractor, including
signatures, during the weekly storm water management inspection. Alternate inspection forms
may be utilized, provided they have been previously reviewed and approved for use by the City
at the time of finalizing the SWPPP. The Contractor shall inspect the water pollution control
practices identified in the SWPPP as follows:
A. Before a forecasted storm,
B. After precipitation that causes site runoff,
C. At 24-hour intervals during extended precipitation,
D. On a predetermined schedule, a minimum of once every 7 days.
The Contractor shall oversee the maintenance of the water pollution control practices.
REPORTING REQUIREMENTS
If the Contractor identifies discharges into surface waters or drainage systems causing or
potentially causing pollution, or if the project receives a written notice or order from a regulatory
agency, the Contractor shall immediately inform the City Inspector and Project Manager. The
Contractor shall submit a written report to the Project Manager within 7 days of the discharge,
notice or order. The report shall include the following information:
A. The date, time, location, and nature of the operation, type of discharge and
quantity, and the cause of the notice or order.
B. The water pollution control practices used before the discharge, or before
receiving the notice or order.
C. The date of placement and type of additional or altered water pollution control
practices placed after the discharge, or after receiving the notice or order.
D. A maintenance schedule for affected water pollution control practices.
PROJECT COMPLETION
The City may authorize removal of the Contractor from further storm water management
obligations once the construction is completed. Contractor must submit a completed "Contractor
Request to File Project Notice of Termination" for City review to the Project Manager. The
Contractor Request to File Project Notice of Termination is included in Appendix D of the City's
CSWMP. Upon completion of construction and City approval of the "Contractor Request to File
Project Notice of Termination", the Contractor may submit their NOT thereby shifting
responsibility for final stabilization to the City. The NOT serves as notification that construction
activities with a potential to release pollutants are complete and that the construction site is
A-5
CSWMP -Appendix A_Revised July 2, 2013.doc
stabilized, and that stormwater inspections and documents are complete and accurate in
accordance with the provisions of the CGP.
END OF PROJECT DOCUMENTATION
Before the City accepts the project and before final payment, contractor must supply the City
with a copy of all storm water management documentation associated with the project including
the field copy of the SWPPP, completed inspection forms and any other documentation to meet
the requirements of the CGP. The copies must be in color, 3 ring hole punched and inserted into
a hard cover three ring binder, and must follow the formatting of the EPA SWPPP template.
PAYMENT
During each estimate period the Contractor fails to conform to the provisions in this section,
"Water Pollution Control," or fails to implement water pollution control practices the City may
withhold payment.
The contract price presented in the schedule of values for preparing and implementing the storm
water pollution prevention plan shall include full compensation for furnishing all labor,
materials, tools, equipment, and incidentals and for doing all the work involved in preparing,
obtaining approval of, and amending the SWPPP, as specified in the Standard Specifications and
these special provisions, and as directed by the City or City's Duly Authorized Representative.
The contract price is a fixed price and any changes to the project for additional storm water
pollution prevention to comply with the CGP after the start of construction will be at the
Contractor's expense. The contract price shall be itemized and stated as in "Measurement and
Payment" parts of Division 1000 of the ISPWC.
Payments for storm water pollution prevention will be made as follows:
A. Upon City approval of the SWPPP and a preconstruction SWPPP Inspection with a
Project Compliance rating of 1, 50 percent of the contract item price for storm water
pollution prevention may be included in Contractors progress payment request.
B. Upon City acceptance of the project, the remaining 50 percent of the contract item
price for storm water pollution prevention may be included in Contractor's progress
payment request.
Implementation of water pollution control practices in areas outside the project limits not
specifically provided for in the SWPPP or in these special provisions will not be paid for.
A-6
CSWMP -Appendix A_Revised July 2, 2013.doc
Eagle Road Water Main Relocation and Abandonment
City Project #11079
APPENDIX B
PROPERTY OWNER RELEASE FORM
Eagle Road Water Main Relocation and Abandonment
City Project #11079
CITY OF MERIDIAN
PROPERTY OWNER RELEASE FORM
Property Owner Name: ______________________________________________________
Property Address: ______________________________________________________
______________________________________________________
CONTRACTOR CERTIFICATION
_______________________________, hereinafter referred to as “CONTRACTOR”, entered into an
Agreement with the City of Meridian, hereafter referred to as “CITY”, to perform and furnish all
services and work in association with the City of Meridian project
___________________________________________________________________________.
CONTRACTOR review of the completed restoration work effort was performed on __________ Day of
_________________________________, 2021 at _________ (P.M.) (A.M.).
It is my opinion the area has been satisfactorily restored to a condition equal to or better than condition
prior to construction.
________________________
Authorized Contractor Signature Date
PROPERTY OWNER RELEASE
I, ________________________________________ (property owner’s name), have reviewed the
CONTRACTOR’S restoration work operation on the subject property and it has been performed to a
satisfactory condition, including, but not limited to:
• Backfill and compaction
• Repair/replacement of items damaged by CONTRACTOR
• Removal of construction debris including rocks and stones
• Utility repair
• Surface restoration completed
• Irrigation/drainage conveyance systems functional
Property Owner Name (Printed)
________________________
Property Owner Name (Signature) Date