HomeMy WebLinkAbout2021-07-01 ACHD Memo From: Becky McKay
To: Shari Stiles
Subject: FW:Centerville Subdivision TIS Review 2-Acceptance Email
Date: Thursday,July 1,2021 2:16:40 PM
ENGINEERING
SOLUTIONS
---------- Forwarded message ---------
From: Paige Bankhead <pbanl<headCcDachdidaho.org>
Date:Tue,Jan 12, 2021 at 3:03 PM
Subject: RE: Centerville Subdivision TIS Review 2
To: Chhang Ream <chh ream(@gmail.com>
Cc: Bill Parsons<bparsons(@meridiancity.org>
HI Chhang,
Thanks for the additional information that you provided. I just want to confirm, when you say 380 vph
during the PM peak hour in the below in reference to Cloverdale/Amity for the 2025 background
traffic analysis, you mean that the intersection will need to be improved when 380 trips are added in
the PM peak hour at the intersection, correct?
• The intersection is anticipated to exceed nummum operational thresholds and tnggem nutigation
umproxevoents by 2023 with an additional backgrround traffic increase of apprrkxiluately 380 vph
during the Phi peak hour beyond 2020 existing traffic volumes
o Traffic count&should be recollected in the future to verify traffic growth and tinprovement needs
If so, ACHD finds the TIS acceptable.
When you submit your application, can you submit an updated final TIS that includes the revisions you
submitted in the attached Executive Summary and the updated table in comment 1 attached? That
way it will be clear for us to follow when we write the staff report. Please also note if turn lanes are
warranted on Hillsdale Avenue at the site access (Hill Park Street) in the Executive Summary.
Thank you,
Paige Bankhead, E.I.
Planner III
Ada County Highway District
Development Services
1301 N. Orchard St. Ste. 200
Phone: (208) 387-6293
ACHD
ACHD Development Services is open for business at our new location at 1301 N.
Orchard Street, Suite 200 in the CSC building. Parking and building entrance are
located on west side of building.
From: Paige Bankhead
Sent: Friday,January 08, 2021 12:05 PM
To: Chhang Ream <chh ream(.__gmail.com>
Cc: Aimee Loudenslager<Aloudenslager(@achdidaho.org>
Subject: RE: Centerville Subdivision TIS Review 2
Hi Chhang,
We should have comments to you by the middle of next week.
Have a great weekend,
Paige Bankhead, E.I.
Planner III
Ada County Highway District
Development Services
1301 N. Orchard St. Ste. 200
Phone: (208) 387-6293
';W
ACHD Development Services is open for business at our new location at 1301 N.
Orchard Street, Suite 200 in the CSC building. Parking and building entrance are
located on west side of building.
From: Chhang Ream <chh ream(@Rmail.com>
Sent:Thursday,January 07, 2021 2:06 PM
To: Paige Bankhead <pbankhead(@achdidaho.org>
Cc: Aimee Loudenslager<Aloudenslager(@achdidaho.org>
Subject: Re: Centerville Subdivision TIS Review 2
[THIS EMAIL ORIGINATED EXTERNALLY. PLEASE USE CAUTION WHEN OPENING
ATTACHMENTS OR LINKS INSIDE THIS EMAIL.]
CAUTION: This email originated from outside your organization. Exercise caution when
opening attachments or clicking links, especially from unknown senders.
Hi Paige,
I'm checking to see if ACHD has any additional comments on the TIS.
Thank you.
Chhang
On Tue, Dec 8, 2020 at 9:40 AM Paige Bankhead <pbankhead(@achdidaho.org>wrote:
Thankyou!
From: Chhang Ream <chhream(@gmail.com>
Sent: Monday, December 07, 2020 5:26 PM
To: Paige Bankhead <pbankheadCcDachdidaho.org>
Cc:Aimee Loudenslager<AloudenslagerCcDachdidaho.org>
Subject: Re: Centerville Subdivision TIS Review 2
[THIS EMAIL ORIGINATED EXTERNALLY. PLEASE USE CAUTION WHEN
OPENING ATTACHMENTS OR LINKS INSIDE THIS EMAIL.]
CAUTION: This email originated from outside your organization. Exercise caution when
opening attachments or clicking links, especially from unknown senders.
Hi Paige,
Thank you for going over the review comments with us last week. We've revised the TIS
report addressing ACHD review comments and would like to make sure we addressed the major
items and provide staff the necessary information. Please find attached the Executive Summary for
your review and comment.
We would greatly appreciate it if you could share your comments and inputs. We're planning to use
this format for future TISs.
Thank you.
Chhang
On Fri, Dec 4, 2020 at 9:41 AM Paige Bankhead <pbankhead(@achdidaho.org>wrote:
Hi Chhang,
Our first review comments noted that the TIS should not assume that improvements necessary
for background conditions are feasible or will be constructed. We still need to see the results as if
the ACHD improvements were not constructed, as well as corresponding mitigation
recommendations.
We also need the number of trips allowed before improvements are warranted, even if the
intersection or roadway segment is listed in the CIP or IFYWP, or if the peak hour site traffic on
that roadway or intersection is less than 10%of the build out traffic. We need to have this
complete information per Policy 7106.7.3 for Alternative Mitigation measures.This information is
also useful for the lead agency processing the development application. It does not matter if only
the existing or background traffic trigger the improvements, we need to know the trip threshold
for improvements for the roadway segments and intersections that are shown to be failing.
Our comments still need to be addressed as issued. New review comments can come up as
information is updated and/or new information is provided in the TIS.
Let me know if you have any further questions or if you would like to set up a phone call.
Thanks!
Paige Bankhead, E.I.
Planner II
Ada County Highway District
Development Services
1301 N. Orchard St. Ste. 200
Phone: (208) 387-6293
to �r t,�r
��
ACHD Development Services is open for business at our new location at 1301 N.
Orchard Street, Suite 200 in the CSC building. Parking and building entrance are
located on west side of building.
From: Chhang Ream <chhreamPgmail.com>
Sent:Thursday, December 03, 2020 12:58 PM
To: Paige Bankhead <pbankhead(@achdidaho.org>
Subject: Re: Centerville Subdivision TIS Review 2
[THIS EMAIL ORIGINATED EXTERNALLY. PLEASE USE CAUTION WHEN
OPENING ATTACHMENTS OR LINKS INSIDE THIS EMAIL.]
CAUTION: This email originated from outside your organization. Exercise caution when
opening attachments or clicking links, especially from unknown senders.
Hi Paige,
We would like to coordinate our responses with ACHD hoping to avoid resubmitting the TIS. We
can also provide additional information if needed. Please find attached our draft responses to
ACHD 2nd review comments.
These comments are generally new to us and we would like to go over the comments and our
responses with you. Please let me know when is the best time we can call to discuss. We are
available anytime.
Thank you.
Chhang
On Wed, Dec 2, 2020 at 2:58 PM Paige Bankhead <pbankheadPachdidaho.org>wrote:
Hi Chhang,
Attached are the 2nd review comments for Centerville Subdivision. Please let me know if you
have any questions.
Thank you,
Paige Bankhead, E.I.
Planner II
Ada County Highway District
Development Services
1301 N. Orchard St. Ste. 200
Phone: (208) 387-6293
nn
{io r�sosr to cev�sco