The Public Works Department respectfully requests the following items be placed on the
January 3 City Council agenda, under Consent Agenda, for Council's consideration:
South Area Lift Station and Pipeline Project. CH2M HILL has submitted a task order, scope
of work, and budget for the engineering services. They propose to complete the work for
$145,300. This is an extension of the miscellaneous wastewater services agreement
approved by City Council on the 18th of January, 2005 for the Engineering Services for
Miscellaneous Wastewater Projects.
This project provides engineering services for the preliminary design of a lift station in the
south area.
Recommended Council Action: The Public Works Department recommends
that City Council approves the contract for the South Area Lift Station and
Pipeline Project with CH2M HILL for $145,300 and authorize the Mayor to sign
it.
~ Landino Lift Station Upgrade. Two bids were received for this project as summarized below
and detailed in the attached spreadsheet:
.
Star Construction, LLC
Irminger Construction, Inc
$96,825.00
$109,000.00
.
This project consists of upgrading an existing lift station including removal and salvaging
existing pumps to the Owner, installation of two new submersible sewage pumps and related
mechanical and electrical work. The work also includes construction of a diversion structure,
piping, and related sitework.
8 Page 1
Recommended Council Action: The Public Works Department recommends
that City Council approves the contract for the Landing Lift Station Upgrade
with Star Construction, LLC for $96,825.00 and authorize the Mayor to sign it.
Bear Creek Chopper PumpNFD Pre-Purchase Project. One bid was received for this project
as summarized below and detailed in the attached spreadsheet:
.
Wm. H. Reilly & Co.
$27,448.00
This project consists of furnishing two Chopper Pumps and assocated Variable Frequency Drives for
installation by others.
Recommended Council Action: The Public Works Department recommends
that City Council approves the contract for the Bear Creek Chopper PumpNFD
Pre-Purchase Project with Wm. H Reilly & Co. for $27,448.00 and authorize the
Mayor to sign it.
Thank you for your consideration. Please contact me if you have any questions regarding
any of these items.
8 Page 2
PROJECT:
Landing Lift Station Upgrade
Bidder: Star Construction, LLC Irminger Construction, Inc.
Bid Submittal X X
Proposal Properly Completed X X
& Signed
BID AMOUNT: $96,825.00 $109,000.00