HomeMy WebLinkAbout2020-04-30 Roadway Proportionate Share Study S:\projects\20-21 Tanner Creek Subdivision\doc\Tanner Creek Proportionate Share.docx Page 1 of 4 MEMORANDUM DATE: March 25, 2020 TO: Erika Bowen, P.E. Idaho Transportation Department CC: Mark Schultz Schultz Development FROM: Chhang Ream, P.E., PTOE CR Engineering, Inc. PROJECT: Tanner Creek Subdivision Meridian, Idaho SUBJECT: Proportionate Share Calculation – Meridian Road IC to Eagle Road IC Auxiliary Lanes This memorandum summarizes the proportionate share calculation for Tanner Creek Subdivision on the I-84 auxiliary lane improvements between Meridian Road interchange (IC) and Eagle Road IC. Table 1 summarizes the traffic data and proportionate share calculation. Based on the 2025 build-out year total traffic volumes, the proportionate share of Tanner Creek Subdivision is $144,901. Table 1 – Proportionate Share Calculation Summary Ramp 2018 Existing Traffic 2025 Background Traffic 2025 Site Traffic 2025 Total Traffic AM PM AM PM AM PM AM PM Meridian IC WB Off-Ramp 960 1,901 1,065 2,110 15 50 1,080 2,160 Meridian IC EB On-Ramp 965 580 1,071 644 46 32 1,117 676 Eagle IC WB On-Ramp 6,244 1,484 6,930 1,647 2 5 6,932 1,652 Eagle IC EB Off-Ramp 1,250 1,042 1,387 1,156 5 3 1,392 1,159 Total 14,426 16,011 158 16,169 Average % Site Traffic 0.98% ITD Improvement Costs Estimate $14,785,782 Tanner Creek Subdivision Proportionate Share $144,901 The following sections discuss the proposed development and traffic data. 181 East 50th Street Garden City, ID 83714 (208) 841-4996 3/25/20 S:\projects\20-21 Tanner Creek Subdivision\doc\Tanner Creek Proportionate Share.docx Page 2 of 4 Proposed Development & Site Traffic Tanner Creek Subdivision is an approved residential development located on Waltman Lane in the northwest corner of the Meridian Road interchange in Meridian, Idaho. A traffic impact study was completed for the project on November 8, 2017. Figure 1 shows the current development site plan. The current site plan contains 128 single- family units and 272 apartment units with an expected 2025 build-out year. The development will have access to the transportation system via a connection to Ruddy Drive at the western site boundary, a connection to Corporate Drive to the north, and via Waltman Lane to the east. Figure 1 – Site Plan I-84 EB Waltman Ln S:\projects\20-21 Tanner Creek Subdivision\doc\Tanner Creek Proportionate Share.docx Page 3 of 4 Table 2 summarizes the build-out site trip generation based on the 10th Edition of the ITE Trip Generation Manual and proposed land uses. Tanner Creek Subdivision is estimated to generate 2,786 trips per day, 187 AM peak hour trips, and 245 PM peak hour trips. Site traffic was distributed and assigned to the transportation system similar to the original study. The Linder Road overpass is not expected to be constructed by the build-out year of this development and was not considered in the site traffic distribution patterns. Approximately 10% of the site traffic expected to have origins/destinations west of the site and use the Ruddy Drive connection. Approximately 18% of the site traffic is expected to travel on the Corporate Drive connection to the north, and approximately 72% of the site traffic is expected to travel through the Waltman Lane and Meridian Road intersection. Approximately 53% of the site traffic is expected to travel through the Meridian Road interchange. Figure 2 summarizes the estimated site distribution patterns and peak hour volumes at the Waltman Lane and Meridian Road intersection and Meridian Road interchange. Table 2 – Build-Out Trip Generation Summary 2025 Build-Out Year Traffic & Improvements Costs No new traffic counts were collected for this analysis. 2018 existing counts at the Meridian Road and Eagle Road interchanges were provided by ITD. The cost estimate for the I-84 auxiliary lane improvements was also provided by ITD. To obtain 2025 background traffic, the existing counts were extrapolated with a 1.5% annual growth rate. This growth rate is consistent with the COMPASS forecasts. Single-Family Detached Housing 210 128 DU 1,305 50%652 50%653 Multifamily Housing (Mid-Rise)221 272 DU 1,481 50%741 50%740 2,786 1,393 1,393 Single-Family Detached Housing 210 128 DU 96 25%24 75%72 Multifamily Housing (Mid-Rise)221 272 DU 91 26%23 74%68 187 47 140 Single-Family Detached Housing 210 128 DU 129 63%81 37%48 Multifamily Housing (Mid-Rise)221 272 DU 116 61%71 39%45 245 152 93 Weekday Daily (vpd) Land Use ITE Code Size Unit Total Trips Primary Trips Entering Exiting Weekday Daily Total Trips Weekday AM Peak Hour (vph) Weekday AM Peak Hour Total Trips Weekday PM Peak Hour (vph) Weekday PM Peak Hour Total Trips S:\projects\20-21 Tanner Creek Subdivision\doc\Tanner Creek Proportionate Share.docx Page 4 of 4 Figure 1 – Estimated Site Traffic Distribution Patterns & Peak Hour Site Traffic 5 0 0 14 14 46 14 0 5 15 13 4 0 0 74 0 0 0 25 0 0 AM 0 5 0 AM 15 0 0 9 9 32 9 0 15 50 8 14 0 0 50 0 0 0 80 0 0 PM 0 15 0 PM Meridian Rd Interchange Waltman Lane & Meridian Road Waltman Lane & Meridian Road Meridian Rd Interchange1 1 2 2 1 2 33% 18 % 10 % 10 % 10% 9% 10% 72% 53 % I-84 EB Waltman Ln Corporate Dr Meridian Rd