August 13, 2019
Honorable Mayor and City Council
City of Meridian
33 East Broadway Avenue
Meridian, ID 83642
Re: Burlingame Subdivision No. 1 — (H-2019-0080)
Dear Mayor and City Council:
1029 N. Rosario Street, Suite 100
Meridian, ID 83642
Phone: (208) 938-0980
Fax: (208) 938-0941
E-mail: beckym@engsol.org
We have reviewed staff comments for the City Council meeting of August 13, 2019, and have
the following responses:
VI. CITY/AGENCY COMMENTS & CONDITIONS
A. Planning Division - Site Specific Conditions:
1. The applicant will comply with conditions of approval associated with the development
agreement (H-2017-055) and the development agreement addendums under Instruments
Nos. 2018-014051 and 2018-119406.
2. The applicant will comply.
3. The applicant will comply.
4. The applicant's surveyor will modify the plat accordingly as requested under items a, b
and c.
5. The landscape architect will modify the landscape plan as requested under items a and b.
6. The landscape architect will provide a landscape plan for 5403 W. Cherry Lane and the
applicant shall install the landscape buffer as required under item a.
7. Understood.
8. The applicant will comply with the requirements for the multi -use path.
9. A letter will be provided from the U.S. Postal Service approving the location of
mailboxes.
C:\Documents\2019\190210 Burlingame subdivision No. 1-AMffiResponsesBurlingameNo1.doe
Meridian Mayor and City Council
August 13, 2019
Page 2
B. Public Works — Site Specific Conditions:
1. The applicant's surveyor will add a common lot to accommodate the sewer stub to the
property located south of the subject parcel.
2. The applicant has consulted with Meridian Public Works concerning the water
modeling of Phase 1. The water model indicated that the required fire flow cannot
be met for the buildable Lots 19 and 21, Block 3, until a second eight -inch water
main is extended south from Turnberry Subdivision. The applicant proposes to
remove Lots 19, 20 and 21, Block 3 from the final plat and construction plans. This
will allow the first phase to proceed into construction and completion of the
improvements. The applicant's engineer will begin design of Phase 2, which will
include the secondary water connection from Turnberry Subdivision. The water
line will have to be extended across the Nampa -Meridian Irrigation District's
Safford Lateral and Settlers Irrigation District's Settler Canal. The improvements
cannot be installed until after October 151h and prior to March 15th during the non -
irrigation season.
3. We respectfully request this condition be deleted, since it is not applicable. The
proposed sewer main line is not a dead-end line and will be extended in the future to
serve the Montessori School property.
General Conditions:
1. The applicant will comply.
2. Understood.
3. Understood.
4. The applicant will comply.
5. Understood.
6. Understood.
7. Understood.
8. Understood.
9. Understood.
10. Understood.
11. Understood.
CADocuments\2019\190210 Burlingame Subdivision No. 1-AMH\ResponsesBurlingameNol.doc
Meridian Mayor and City Council
August 13, 2019
Page 3
12. The applicant will comply.
13. Understood.
14. Understood.
15. Understood.
16. Understood.
17. Understood.
18. Understood.
19. The applicant will comply.
20. Understood.
21. Understood.
22. Understood.
23. Understood.
24. The applicant will comply.
We appreciate your review of this project. Please feel free to call me if you have additional
comments or questions.
Sincerely,
Eng7yMcKay