HomeMy WebLinkAbout2014 SOUTHERN HIGHLANDS PHASE 1 & 2 OFFSITE UTILITIESlar T.O ENGINEEFI5 May 12,2014 City of Meridian Attn: Denny Cline 33 E. Broadway Ave, Ste 102 Meridian, lD 83642 RE: Southern Highlands Off-Site Utility Plan Review Dear Denny, This letter accompanies our resubmittal for Southem Highlands Off-Site Utility plans. Attached are the revised plans for your approval. We received your plan review comments dated May 9, 2014. Please find our responses to your comments below: Generel Plan Design 7. Water note #2 and sewer note #3 have been called out on the water plan/profile sheets at the locations noted. Sewer main crossings (future and current) are shown in the profile view. 8. The limits of the gravel drive have been shown in the plan view and a typical section is included on Sheet 4 (Grading and Drainage Plan). General Weter Design 14. Water main has been revised to show 5, minimum cover. 20. Valves have been added and called out as shown on the redlined plan set. General Sewer Design 30. Pipe lengths have been corrected. lnverts and alignment have been modified as necessary to r€flect the sewer changes through proposed Whitebark SuMivision. 36. Angle through manhole on Sheet 5 has been labeled. 48. Service line inverts have been added to the plans. Invert elevations were calculated to provide 5' depth at the back ofsidewalk. Grevity lrrigetion 63. Downstream users will not & affected by the removal/abandonment ofthe irrigation line in this project. Redlines (Not addressed ebove) I . Manholes installed as shown with the eccentric cone rotated towards the downstream invert will not have rims conflicting with future curb and gutter. 2. All manholes are less than l8' from rim to lowest invert, therefore 60" diameter manholes are not required. We rcspectively request that the City of Meridian approve the plans so we can commence construction. please contact us should you have any questions or comments. II U;,*-A+La^--^- n G. Carpenter, P.E. ect Manager 332 N. Broadmore wav Namp6, lD 83687 Phone 1208) 442'6300 Fax (208) 46m944 hfoolqengrnee.s.com to-engineers.corn Aviation I Transpodatiofl | Land D6v6lopmsnt I Municipat I W8to. Resolrcss I Surueying Corinne Haase, E.l.T. Staff Engineer MERIDIAN CITY DEVELOPMENT SERVICES SUBDIVISION REVIEW & INSPEGTION FEES Bill To: T and Nil Holdings Comments / Special lnstructions / Project Description: Phase- 1 oe+-sl,,<, DATE: 05/9/2014 RECORD # LD.RSU B.2O14.OO3O tNvotcE # 38771 REMIT TO: CITY OF MERIDIAN DEVELOPMENT SERVICES 33 E BROADWAY AVE, STE 2OO MERIDIAN ID 83642 tD**er I so.r.- PH 887 -221 1 I FX 887 -1297 REVIEWiINSPECT FEES QLPE FEES GENERAL FEES TOTAL DUE REVIEWED BY # OF REVIEWS TERMS D.CJi'"c., 2 Prior to QLPE plan submittal QUANTITY U NIT DESCRIPTION UNIT PRICE AMOUNT GENERAL FEES: EA Water / Sewer Modeling (First Phase Only) $328.00 $ EA PP W/S N/odel lnput (First Phase Only) $99.00 $ EA 2 lnch Landscape Water Meter $686.00 $ EA 4 lnch Turbo Landscape Water Meter $2,196.00 $ ERU Common Area Landscape Assessment $525.00 $ UTILITY PLAN REVIEW: 5,053.00 $0.40 $ 2,021.20 LF Additional Reviews (per linear foot) $0.20 $ LOT Subdivision Development (378.00 + 10-00 per Bldg lot) $10.00 $ EA Subdivision Development - Additional Reviews $'100.00 LF Privale Slreel (300.00 + 0.10 per linear foot) $0 10 $ LOT $5.00 $ AC Subdivision Grading / Drainage $ EA Sewer Lift Station (Flat Fee) $492.00 $ Floodplain Review (Flat Fee) $96.00 $ 4.00 EA QLPE Review (per Sheet) $250.00 $ 1,000.00 INSPECTION: 2,484.O0 LF Water System lnspection (per linear foot) $0.69 $ 1,713.96 2,569.00 LF Sewer System lnspeclion (per linear foot) $0.69 $ 1,772.61 EA Pl System lnspection (Number of Services) $ EA Sewage Lift Station lnspection (Flat Fee) $576.00 $ $ 5,507.77 $ 1,000.00 $ $ 6,507.77 LF Off Site Water/Sewer (per linear foot) $ $ LOT HOA Pl Plan and O&M (125.00 + 5.00 per Bldg lot) $5.00 Master Grading / Drainage (200.00 + 5.00 per Bldg lot) EA l\.4ake all checks payable to CITY OF MERIDIAN, referencing the invoice number. lf you have any questions concerning this invoice, please call Development Services at the number listed above. Bill To MERIDIAN CITY DEVELOPMENT SERVICES SUBDIVISION REVIEW & INSPECTION FEES Comments / Special lnstructions / Project Description Pl'r-t / ocr-strE ,u;.*e- Seurer Sr,o*1,.c-e'r tlr U. ) tu+lft+dEtrrDr B.is<. H-;1e.r lloflic.-S DArE:051912014 RECORD # LD-RSUB-20,14-0032 tNvotcE # 38775 REMIT TO: CITY OF MERIDIAN DEVELOPMENT SERVICES 33 E BROADWAY AVE, STE 2OO MERIDIAN ID 83642 PH 887-2211 I FX Aa7-1297 REVIEWINSPECT FEES QLPE FEES GENERAL FEES TOTAL DUE REVIEWED BY TERMS D.Cline- 2 Prior to QLPE plan submittal QUANTITY UNIT DESCRIPTION UNIT PRICE GENERAL FEES: EA Water / Sewer Modeling (First Phase Only) $328.00 $ PP W/S N,4odel lnput (First Phase Only) $99.00 s 2 lnch Landscape Water Meter $686.00 $ EA 4 lnch Turbo Landscape Water Nileler $2,196.00 $ ERU Common Area Landscape Assessment $s25 00 $ UTILITY PLAN REVIEW: 6,156.00 Off Site Water/Sewer (per linear foot) $0.40 $ 2,462.40 Additional Reviews (per linear foot) $0.20 LOT $ EA Subdivision Development - Additional Reviews $100.00 $ LF $0.10 $ LOT HOA Pl Plan and O&M (125.00 + 5.00 per Bldg lot) $5.00 $ LOT Master Grading / Drainage (200.00 + 5.00 per Blds lot) $5 oo $ AC Subdivision crading / Drainage $ EA $492.00 $ EA Floodplain Review (Flat Fee) $96.00 $ 7.00 EA QLPE Review (per Sheet) $250.00 1,750.00 $ INSPECTION: 3,364.00 LF Water System lnspection (per linear foot) $0.69 $to z,Jz t. 2,792.O0 LF Sewer System lnspection (per linear foot) $0.69 $ 1,926.48 Pl System lnspection (Number of Services) $ Sewage Lift Station lnspection (Flat Fee) $576.00 $ $ 6,710.04 $ 1,750.00 $ $ 8,460.04 # OF REVIEWS AMOUNT EA EA LF LF $ llr T.O ENGINEERS Ivf.ay 30,2014 To: George A. Murgel, P.E., Ph.D., CENTRA Consulting,Inc. Qualified Licensed Professional Engineer 413 W. Idaho St. Ste.302 Boise, lD 83702 RE: Phase #2 Southem Highlands Offsite Utilities Dear George: Thanks for taking the time to visit with me yesterday and review your comments over the phone. You and I worked through the majority of the comments together and I wanted to follow up with the below comments: Sheets5toll l. Added requested note. 2. After discussion you found this acceptable. 3. After discussion you found this acceptable. Sheet 5 l. Added Call out 2. Added Call out 3. After discussion you found this acceptable. 4. After discussion you found this acceptable. Sheet 6 l. After discussion you found this acceptable. 2. Added callout 3. This is found on sheet 5 4. Modified 5. Modified 6. Modified Sheet 7 l. After discussion you found this acceptable. 2. Modified 3. Modified 4. Modified 332 N Broadmore Way Nampa, lD 83687 Phone {208) 442-6300 Fax {208) 466-0944 rnfo@to-engrneers.com to-engineers,com Aviation I Transportation I Land Development I Municipal I Water Resources I Surveying llr T.O ENGINEEFIS Sheet 8 l. Added distances. 2. Sewer services are not known for future as lot locations may change. Per Denny's request I am sending plans directly to you and copying him with this letter. Please do not hesitate to call me if you have any questions. My office line is 442-6300 and my cell is 899-0688. Our goal is to have you signed off on these plans Monday. Thanks in advance for your prompt attention. 5. 6. 7. Modified Modified Modified ) G. Carpenter CC: Denny Cline - City of Meridian. cc:130134 332 N. Broadmore Way Nampa, lD 83687 Phone (208) 442-6300 Fax (208) 466-0944 rnfo@ro-engrneers.corn to-engineers com Aviation I Transportation I Land Development I Municipal I Water Resources I Surveying E DIA Land Development Services Meridian City Hall, Suite 102 33 E. Broadway Avenue Meridian, Idaho 83642 IDAHO Community Development Department TO: FROM: Denny Cline DATE: MEMORANDUM PW lnspectors: Joel Meusch WWTP: Tom Lee Water Department: Chip Hudson cc RE: File 6/to/L4 Phase 2 Offsite utilities Southern Highlands Enclosed are construction prints that have been stamped "Approved for Construction." A Pre-Con Meeting will be scheduled on Thursday the 12th . An invite will follow. Ph: 208.887.2271 a www. merid ia ncity.org Fax 208.887.t297 Rev:01/2013 E IDIAN Land Development Services Meridian City Hall, Suite 102 33 E, Broadway Avenue Meridian, Idaho 83642 I*AHO Community Development Department LETTER OF TRANSMITTAL Date 6/r0/1,4 To: John Carpenter P.E. T.O Engineers From Denny Cline Development Analyst ll Subject: Phase 2 Southern Highlands Subdivision Offsite Utilities Enclosed are the following coPrEs DATE DESCRIPTION 1, 6/1,0/1,4 Signed Approved for Construction Originals Remarks Please return four copies for staff distribution. Thank you Ph: 208.887.2271 www. merid ia ncity. oro Fax 208.887.7297 Rev:01/2013 t E IDIAN MayorTammy de Weerd City Council Members: Keith Bird Joe Borton Luke Cavener Genesis Milam IDAHO Charlie Rountree David Zaremba June 5. 2014 Mr. Pete Wagner, PE IDEQ Boise Regional Administrator 1445 N. Orchard Street Boise, Idaho 83706 Re: Project Approval - Phase 2 Southern Highland Subdivision Offsite Utilities Per the provisions in Idaho Code $ 39-1 18(2Xd), the City of Meridian has retained the services of CENTRA Consulting, Inc. as its Qualified Licensed Professional Engineer (QLPE), to veriflz that the plans and specifications proposed for the above-referenced project comply with the IDEQ Facility and Design Standards (IDAPA 58.01.16 and 58.01.08) and the applicable Meridian standards, and to approve the project for construction. By virtue of their attached letter, they have reviewed and approved the above referenced plans and specifications as complying with the Facility and Design Standards, and Engineering Standards of Care as it relates to the reviewed elements. The above referenced project complies with the City of Meridian's current Wastewater Facility Plan, and Sewer Master Plan, and our system has adequate capacity to accept sewage wastes for treatment. These determinations have been made by use of computer models developed for our Sewer Master Plan. This project is also within the City's urban service planning boundary. Our Domestic Water distribution system can provide water service and the minimum required fire flow ( 1000 GPM) and the minimum required residual pressure of 20 PSI. These determinations have been made by use of computer models developed for our Water Master Plan. The City of Meridian will own and operate the wastewater collection and domestic water distribution systems within this project upon final inspection and acknowledgement by formal acceptance letter. In essence, the City of Meridian "Will Serve" the project. Attached for your records is a complete and accurate copy of the plans and specifications reviewed in connection herewith, stamped "Approved for Construction." S ATTEN Stewart, P.E. Engineering Manager Tracy Crane, WWTP Plant Manager Chip Hudson, Water Department Mike Reno, Central District Health Dept. File Public Works Department . 33 E. Broadway Avenue, Suite 200 . Meridian, lD 83642 Phone 208-898-5500 , Fax 208-898-9551 . www.rTl€ridiancity.org CE\IIRA CONSULTING INC, MEMORANDUM J une 3.2014 To: Denny Cline, Development Analyst ll Development Services Division, City of Meridian From: George A. Murgel, P.E., Ph.D., Quallfied Licensed Professional Engineer (QLPE) Re: Phase 2 southern Highland Offsite Utilities Dear Denny: We have completed our review ofthe plans for the referenced prolect. The plans are approved for construction as allowed under ldaho Code 39-118(2)(d). The completed "Qualified Licensed Professional Engineer (QLPE) Review and Approval Checklist" (QLPE Checklist) is attached. The QLPE Checklist was prepared to meet the transmittal letter requirements specified in IDAPA 58.01 .08.504.03(b) and 58.01 .'16.400.03(b). The plans were marked as "Approved for Construction". Please note that the certifications required for Sections ll(B) and (C) of the QLPE Checklist must be satisfied with a will-serve letter and declining balance statement from the City. Electronic Files have been uploaded to the City of Meridian's FTP site in accordance with the terms of the Contract and we are returing one copy to the City for your records. Additionally we are returning one comlete set of the original redlines along with a second set of the reviewed pages with tifle sheet. Please contact me if you have any questions. George urgel, P.E., Ph CENTRA Consulting, lnc. Attachment: Qualified Licensed Professional Engineer (QLPE) Review and Approval checklist Cc: File Projectr City of Meridian QLPE Contracl: CENTRA Consulting, lnc .413West ldaho Street, Suite 302, Boise, ldaho. Tel: (208) 338-9400. Fax: (2OB) 338-3844 . www.centrainc.com State of ldaho Department of Environmental Quality 1410 North Hilton . Boise, ldaho 83706 . (208) 373-0502 QUALTFTED LTCENSED PROFESSIONAL ENGTNEER (OLPE) REVIEW AND APPROVAL CHECKLIST About this form o This checklist is optionalto use and is guidance from DEQ to qualified licensed professional engineers (QLPE). This checklist describes the required elements of a QLPE project transmittal letter and is intended to assist DEQ in the tracking of drinking water and wastewater projects, as well as assist the QLPE in reviewing and approving certain types of Plans and Specifications. o This checklist should be filled out by the qualified licensed professional engineer (QLPE) when the QLPE is reviewing and approving a project for construction under Idaho Code $ 39-l l8(2Xd). If the project requires DEQ approval prior to construction, the QLPE shall direct the Design Engineer to submit the plans and specifications through the normal DEQ review process. o This checklist may be used in place of a transmittal letter from the QLPE. r This and other design checklists are available at any DEQ regional office or online at htto ://www. deo. state. i d. us/water/assist business/en gineers/check lists.cfm. a The other checklists include additional information about submitting a package of plans and specifications for DEQ review. I. GENERAL PROJECT INFORMATION Project Name: Phase 2 Southern Highland Offsite Utilities Approving Authority*: CITY OF MERIDIAN Qualified Licensed Professional Engineer: Name: George A. Murgel, P.E., Ph.D. I 2 J Employer: CENTRA CONSULTING INC. 4 This approval is for: f, euUlic drinking water system simple water main extension I euUlic sewer system simple wastewater main extension 5 Design Engineer Name: John g. Carpenter Employer: T-O Engineers 6 Project Owner or Developer: (Please provide exact name of owner or authorized representative) Brad Pfannmuller Boise Hunter Homes Name: Firm: Address: City: 1025 s. Place, Suite 290 Eagle State: ID ZIP:83616 * Approving Authority refers to the City, County, Quasi-Municipal Corporation, is approving the plans and specifications per Idaho Code 39-l I QLPE Review and Approval Form Revised November 2008 Page 1 of 3 8(2Xd). or Regulated Public Utility that QLPE CHECKLIST II. REQUIRED CERTIFICATIONS Checklist ltem Yes A) I am the QLPE representing the Approving Authority x B) This project consists of simple wastewater main extension(s), simple water main extension(s), or both. It complies with the current facility plan or preliminary engineering report. The water or wastewater system has adequate capacity for the project. (lf required, please include declining balance spreadsheet to demonstrate capacity) x C) The Approving Authority has committed to serve this project and has reserved capacity for it. (Attach separate will serve letter or other documentation if needed.) x D) The Approving Authority will own and operate the project upon completion of construction. (Attach separate letter or other documentation if needed.) E) I have reviewed the plans and specifications and verified that they comply with the facility and design standards (IDAPA 58.01.08 and IDAPA 58.01.16) and engineering standards ofcare. III. PLAN & SPECIFICATION APPROVAL Ghecklist ltem Yes A) As the QLPE for the Approving Authority, I have approved the plans and specifications for construction. I am not the design engineer, nor was I otherwise involved in the design. x B) The plans and specifications have been marked as "Approved for Construction", and X a copy of the approved plans were transmitted to DEQ with this checklist. C) The plans are for simple wastewater main extension(s), simple water main extension(s), or both. No mechanical systems such as drinking water sources, treatment facilities, booster stations, storage facilities, or wastewater systems such as lift stations or treatment works are included with this project. ** D) This extension project will connect to: 1) Existing drinking water and/or wastewater mains owned by the Approving Authority. OR 2) A future main(s) not existing at the time of approval. The future main(s) will be owned by the Approving Authority. In such cases, sanitary restrictions will remain in force. ** Portions of a project that require DEQ approval must be approved by DEQ prior to the eLpE approval of the drinking water or wastewater extensions. Alternatively, the drinking water and/or wastewater extensions may be submitted to DEe for approval of the entire project. QLPE Review and Approval Form Revised November 2008 Page 2 of 3 x tr QLPE CHECKLIST IV, SAN'IARYRESTR'CT'OA'S If the project includes drinking water and wastewater main extensions that will be reviewed and approved separately, the two Approving Agencies must coordinate the review and approval as it pertains to the lifting of sanitary restrictions. Recommendation Yes I have reviewed and approved all drinking water and wastewater improvements included X in this project, and I recommend that the district health department release sanitary restrictions. OR I have reviewed and approved only the drinking waterf, wastewater f, (check one) improvements included in this project, and I recommend that the district health department release sanitary restrictions once they receive the approval from the other Approving Authority. I OR I recommend that the district health department leave sanitary restrictions in place. tr V. NOTE O'V RUTES AND STAA'DARDS This checklist addresses the majority of common items from the ldaho Rules for Public Drinking Water Systems (IDAPA 58.01.08), the Wastewater Rules (IDAPA 58.01.16, for QLPE approval of projects. However, this checklist is not all-inclusive, and users are expected to fully understand the rules and standards, apply them where necessary, and request interpretations from DEQ if there are any questions. DEQ regional offices may have additional written information that will assist in the design/approval process. VI. QLPE CERTIFICATION All responses indicated on the checklist above ore accurately re/lected in the attached Plans and Specifications. QLPE's, Signature, Date and Seal QLPE Review and Approval Form Revised November 2008 Page 3 of 3 Subdivision Development (378.00 + 10.00 per BIdg lot) $10.00 Private Street (300.00 + 0.10 per linear foot) Sewer Lift Station (Flat Fee) EA EA l\,4ake all checks payable to CITY OF MERIDIAN, referencing the invoice number. lf you have any questions concerning this invoice, please call Development Services at the number listed above.