HomeMy WebLinkAbout2014 SOUTHERN HIGHLANDS PHASE 1 OFFSITE UTILITIESE IDIAN Land Development Services Meridian City Hall, Suite 102 33 E, Broadway Avenue Meridian, Idaho 83642 :DAr-*O Community Development Department DATE: 6t12t14 PRE-CONSTRUCTION MEETING FOR: Phase f & 2 Southern H hlands Offsite Utilities CONTRACTOR: GRAVEL. <*zi - MERIDIAN PUBLIC WORKS INSPECTORS ARMY CORPS OF ENGINEERS _ SECTION 404 PERMITTING The applicant shall be responsible for application and compliance with any Section 404 Permifting that may be required by the Army Corps of Engineers. DRAWINGS OF RECORD AND CONSTRUCTION COSTS: The Engineeris responsible to keep a record of changes to the approved construction drawings. These changes shall be noted on the plans and labeled, "Record Drawings", by the Project Design Engineer. These "RECORD DRAWINGS" should be delivered to the Public Works Department within 30 days after construction is completed and pior to Certificates of Occupancy being issued. A PROPOSED set of RECORD DRAWINGS shou/d be submifted to the Engineeing Depaftment pior to running all required documents. The possibility exists that changes may be needed for them to be accepted. Projects will not be accepted as final until Record Drawings and Construction Cosfs are submitted. CITY OF MERIDIAN APPROVED PLANS: 1. All plans being used on the job must have the City of Meridian "Approved for Construction" 2. Any changes fo fhese plans need to have prior City approval. Check with your lnspector. stamp. STAN DARD D RAWI NG S & S PECI FICA7"/ONS; Current edition must be on site rn possessio n of the contractor. MEETING ATTENDANCE: See Attached List COMMENTS: PUBLIC WORKS: ACHD: JOINT TRENCH: lnspector Office Phone Cellular Phone EmailAddress Joel Meusch 898-5500 409-9913 imeusch@meridiancitv.orq [/]urray Jones 898-s500 830-7701 ionesm @merid iancity. orq Patrick Cotten 898-5500 830-7885 pcotten @merid iancitv. orq Darrell Gogert 898-5500 401-4743 dqoqert@meridiacity. org Brad Standley 898-5500 484-2326 bstand lev@ merid iancitv. orq IRRIGATION DISTRICT Rev.2l21l14 a MATERIAL SUPPLIERS: PIPING - <-at f.-Zzr+fEZ MH'S - /Za 4rZ:€ 1 1 GENERAL CONSTRUCTION COMMENTS Contractor shall notify the Meridian Public Works Dept. (898-5500) when materials are on site. Call must be made a minimum of 24 hours prior to construction. 4. The Contractor pouring sidewalks shall stamp the water and sewer service locations 5. The Contractor installing sewer or water pipe shall repair any damages incurred during the installation of Joint Trench utilities. 6. The Contractor installing sanitary sewer and water shall install sleeves across the roadways to carry pressurized irrigation piping. The Meridian Public Works Department and the Ada County Highway District shall inspect the sleeve installation. 7. Waterand Sewer Service lineending locations shall be marked with finder wire and a 2" x 4" or 3" wooden post. The locater post shall be set a minimum of4 ft. above ground and painted green for sewer and blue for water. 8. Potable . and Eighteen Non-Potable (18) inches service of vertical lines are separation now subject must to be all maintained DEQ crossing/between separation all main issues. and service lines. SEWER CONSTRUCTION 1. A minimum of 12" of clean chips required over pipe, 4" under pipe. 2. Maximum number of grade rings allowed on sewer manholes is 12 inches. 3. Maximum depth of sewer service at property line is 5 feet. Service lines shall be extended a minimum of 10 feet past the property line or back of sidewalk. 4. An air pressure test and TV inspection is required after all underground utilities have been installed. Please schedule testing a minimum of 24 hours in advance. A visual inspection of the sewer manholes and lines will be made after final paving is completed to confirm alldebris has been removed. The Contractor is requested to do a walk through (after paving) before calling for an inspection. WATER CONSTRUCTION 'l . A minimum of 12" of clean sand required over pipe, 6" under pipe. 2. No one is to operate any water valves except the l\4eridian Public Works Depa(ment. Notify your assigned lnspector when the operation of any water valve is required. 3. Continuity testing on the locating wire is now required by the Contractor. lt must be done in the presence of the Public Works lnspector. 4. The City of l\4eridian now requires a minimum 2 hour pressure test on the water system. Please schedule testing a minimum ofz{ 'qt hours in advance. 5. The Contractor shall disinfect, flush and obtain an appropriate number of water samples from the system for bacteriological testing. Disinfection is limited to 5 days maximum. Sampling and testing shall follow immediately. Samples must be taken in the presence of the Public Works lnspector, who willthen take possession of the samples and let you know what the results are. 6. ln paved areas, blow offs shall have a maximum of (1) 4" and ('1) 2" grade ring and shall have a concrete collar installed. 7. Contractor will obtain permission from or notify appropriate entities (such as irrigation district and ACHD) prior to any flushing. Contractor must make a reasonable effort to prevent damage to other projects by their flushing and to be aware of the potential for flushing by others that will affect their project and plan for such an event. 2. Weekend and/or hohday work and inspection must have prior approval (See your ASSIGNED PW lnspector) ?Z l/rA4/ 4?.//C.'l1Z ^/ '/'.6. arrarlll flr'.lz.r ^yr u6';rQ)",r'.{ dr 3. Trench wZter cannot be ailowed into existing City sewer OR water mains during constructio n. l*Zz?ay',r 2 Rev.2l28h4 MISCELLANEOUS COMMENTS . PRECONSTRUCTION MEETING For '.** No building permits will be issued for this project until the following items have been completed: 1. Final Plat has been recorded into Ada County Records 2. 314" minus road base is installed and approved bythe 3. Street Name Signs are instalted. f/A 4. Municipal water system has passed pressure, bacteriological and continuity testing and has been activated by the Meridian Public Works Department. 5. Municipal sewer system has been TV'ed (and approved) and passed the pressure testing. *"** No Certificates of Occupancy will be issued in this project until the following items have been completed: Public Works Department has finaled the municipal water and sewer systems. "Record Drawings" have been accepted by the Public Works Department. Final construction costs have been submitted to the Public Works Department. Pressurized lrrigation System has been accepted by the entity having jurisdiction over said system and the Design Engineer has submitted a Letter of Cgmpliance that states the system has been built, and functions according to the approved plans. tt/f ln addition to the above items are any items specifically noted in the Development Agreement for this subdivision/project which must be satisfied. The Pressurized irrigation system in this project is to be owned and maintained by il/* l, the undersigned, indicate by my signature that I understand and will abide by the aforementioned discussion topics. I understand that failure to comply or abide by this document or any of the approved plan requirements is a violation and may subject myself and/or the project to a Stop Work Order, Notice of Violation, Civil Penalties or any combination thereof 8"."a ?€o,, e^ /l' 6- ^.-l A.."ss a--Ji 1 3 4 f RESPONSIBLE PARTY ,./1* COMPANY: B^'. € llu-+.n l. ADDRESS: lO75 CONTACT NUMBER 9'loLt a 1^:le 2to 4 SIGNATURE: Rev.2l28l14 7. Contractor will obtain permission from or notify appropriate entities (such as irrigation district and ACHD) prior to any flushing. Contractor must make a reasonable effort to prevent damage to other projects by their flushing and to be aware of the potential for flushing by others that will affect their project and plan for such an event. 3 DATE: 6t12t14 PRE-CONSTRUCTION MEETING FOR: Phase 1 & 2 Southern Highlands Offsite Utilities NAMEADDRESS COMPANY CELL # EMAIL Dennyorg ClinelTfrfw- ,City of Meridian - CD 887 -2211(Office) d cl i ne@ me rid ia n city. ! Meridian lnspector See Front Page See Front Page Gz .r*tfuiz// ,1 -r;-ra- .r'fi-fr/t /nD'7- l41t tL.Lvtrtt?i 5Tlzarr+ {tot-o-?+rt.t Ctyttrev,+d@ SWg-'-, S6n q1a1t82 -N;cla 'VArnt; Aztt- c)QZ\ 6-r<*frruASe-, O :r{*la xo^ Q\t..S Fc[- DA\\lz-L.:nS+. Ya\- n3b q-_\ixbrr€r$e.(;:t b;r,*,, he"r C.o. m to?- sruI bll *n E /tLn'r/,;rnu h . o.o, l1Il.a O*r*tnfuz- 'TrO fu,eric<c< 64e-aA?4 J&*t*ntz tl-Q-i+s Alar, no B,;ae l/.:t-, //ome) et"?- /o4/ F,n^.\'o a L; o" h**{ * hio * tseO i,uzecA CK E^/btu@aa &r-os9o Coa C 4'&/kaazaattt/: ,1ot tlAuntto Aarcro (orh <32 -770 / E,z,rb g(-*rrilu, Cnm 1q4- ?Zza 4 Rev.2l21l14 CITY OF MERIDIAN ACCEPTANCE OF RECORD / ELECTRONIC DRAWNGS Within thirty (30) days of completion of constructlon, before Building Occupancy Permits are issued, or prior to finat payment for Capital Proiects, the Design Engineer shall submit a complete, updated set of Record / Electronic Drawings of the project to the Public Works Deparlment / Engineering Division. The Community Development and Public Works Depaftments encourage Consultants to submit a sel of proposed Record Drawings to ensure accurate compliance prior to generating copies. The Record Drawings shall be reviewed for accuracy and may be rejected if changes to the original construction plans have not been addressed. MINIMUM Following are the City of Meridian's minimum requirements for approval of Record / Electronic Drawings. A,, sheels ln the original drawing sef shal/ be modlfied as noted below and marked in the lower right hand corner as RECORD DRAI//,ING. They ryg! be stamped, signed and dated by a Stafe of ldaho Registered Professional Engi neer: Record Drawing submiftals shall show the following surveyed and adiusted data: 1. Sewer manhole rims and t-type cleanout rims and inverts are to be located horizontally and vertically. Design elevations (rims and inverts) in the profile shall be crossed through and the revised (invert and rim) elevations added. Design grades shall be recalculated to show installed grade. These revised grades shall be shown with revision clouds. Changes in types and lengths of pipe must also be shown. 2. Domestic water fire hydrants, water valves, air vac stations, prv stations and blowoff locations are to be located horizontally and vertically. Known changes in types and lengths of pipe or any other changes to the domestic water system must also be shown. 3. Recycled water fire hydrants, water valves, air vac stations and blowoff locations are to be located horizontally and vertically. Known changes in types and lengths of pipe or any other changes to the recycled water system must also be shown. 4. Any other changes to the construction drawings should be noted and shown with a revision cloud. 5. All surveyed points (as noted above) are to be shown on a separate layer in the electronic AutoCAD file. Record Drawing submittals shall be as follows: (See specifics on back of page) 1 . Three (3) complete copies (Zerox or Blueline). 2. Two (2) electronic copies on CD of the above plans in the following formats. a. City of Meridian - Record Drawing Submiftal: One (1) AutoCAD drawing format. Coordinate the formatting with Public Works. One (1) complete set of drawings in PDF format. b. DEQ - Record Drawing Submittal: One 1) complete Thi D will be of drawings in PDF format. rded to DEQ along with the City Certification letter. E., Engineerlng Manager Devel op m ent Serui ces M a n ager -tz/7 zz /t- Date l?-21-?D(z- Date ngineer Signature Date Date: October 25, 2012 d- -tztr'--------.------ Requirements on Record Drawings 1.. Sewer Mains - called out in profile or on plan a. Size of Pipe b. Pipe Length between Manholes, Cleanouts, or other fittings c. Material d. Slope 2. Water Mains - called out on drawings a. Line lengths - fitting to fitting b. Material c. Pipe Size Ada County Projection - can be attained through the Ada County Surveyor's page orthrough City of Meridian Public Works GIS department. Contact Matt Hoffman at mhoffman@meridiancitv.ors if you have any questions or need a copy. Date: October 25, 2012 CITY OF MERIDIAN ACCEPTANCE OF RECORD / ELECTRONIC DRAWNGS Within thirty G0) days of completion of construction, before Building Occupancy Permits are issued, or prior to final payment for Capital Projects, the Deslgn Engineer shall submit a complete, updated set of Record / Electronic Drawings of the proiect to the Public Works Department / Engineering Division. The Community Development and Public Works Depaftments encourage Consu/tants to submit a set of proposed Record Drawings to ensure accurate compliance prior to generating copies. The Reard Drawings shall be reviewed for accuracy and may be rejected ff changes to the original construction plans have not been addressed MINIMUM REOUIREMENTS Following are the City of Meridian's minimum requirements for approval of Record / Electronlc Drawings. A/ slreets in the ofiginal drawing sel shafl be modlfied as noted below and marked in the lower right hand corner as RECORD DRAI///.NG. They must be stamped, signed and dated by a State of ldaho Registered Professional Engineer: Record Drawing submlttals shall show the following surveyed and adjusted data: 1. Sewer manhole rims and t-type cleanout rims and inverts are to be located horizontally and vertically. Design elevations (rims and inverts) in the profile shall be crossed through and the revised (invert and rim) elevations added. Design grades shall be recalculated to show installed grade. These revised grades shall be shown with revision clouds. Changes in types and lengths of pipe must also be shown. 2. Domestic water fire hydrants, water valves, air vac stations, prv stations and blowoff locations are to be located horizontally and vertically. Known changes in types and lengths of pipe or any other changes to the domestic water system must also be shown. 3. Recycled water fire hydrants, water valves, air vac stations and blowoff locations are to be located horizontally and vertically. Known changes in types and lengths of pipe or any other changes to the recycled water system must also be shown. 4. Any other changes to the construction drawings should be noted and shown with a revision cloud. 5. All surveyed points (as noted above) are to be shown on a separate layer in the electronic AutoCAD file. Record Drawing submitlals shall be as follows: (See specifics on back ofpage) 1. Three (3) complete copies (Zerox or Blueline). 2. lwo (2) electronic copies on CD of the above plans in the following formats. a. City of Meidian - Record Drawing Submittal: One (1) AutoCAD drawing format. Coordinate the formatting with Public Works. One (1) complete set of drawings in PDF format. b. DEQ - Record Drawing Submittal: One 1) complete Th D will be of drawings in PDF format. rded to DEQ along with the City Certification letter. E., Engineering Manager ent Services Manager Z )2- l?-z-?-?brz- zZzlE Eng, er of rd Signature ou/r" / Date Date Requirements on Record Drawings L. Sewer Mains - called out in profile or on plan a. Size of Pipe b. Pipe Length between Manholes, Cleanouts, or other fittings c. Material d. Slope 2. Water Mains - called out on drawings a. Line lengths - fitting to fitting b. Material c. Pipe Size Ada County Projection - can be attained through the Ada County Surveyo/s page or through City of Meridian Public Works GIS department. Contact Matt Hoffman at mhoffman@meridiancitv.org if you have any questions or need a copy. E IDIAN MayorTammy de Weerd City Council Members: Keith Bird Joe Borton Luke Cavener Genesis Milam IDAHO Charlie Rountree David Zaremba 615114 Mr. Pete Wagner, PE IDEQ Boise Regional Administrator 1445 N. Orchard Street Boise, Idaho 83706 Re: Project Approval -Phase I Southern Highland Subdivision Offsite Utilities Per the provisions in Idaho Code $ 39-118(2Xd), the City of Meridian has retained the services of CENTRA Consulting, Inc. as its Qualified Licensed Professional Engineer (QLPE), to verifo that the plans and specifications proposed for the above-referenced project comply with the IDEQ Facility and Design Standards (IDAPA 58.01.16 and 58.01.08) and the applicable Meridian standards, and to approve the project for construction. By virtue of their attached letter, they have reviewed and approved the above referenced plans and specifications as complying with the Facility and Design Standards, and Engineering Standards of Care as it relates to the reviewed elements. The above referenced project complies with the City of Meridian's current Wastewater Facility Plan, and Sewer Master Plan, and our system has adequate capacity to accept sewage wastes for treatment. These determinations have been made by use of computer models developed for our Sewer Master Plan. This project is also within the City's urban service planning boundary. Our Domestic Water distribution system can provide water service and the minimum required fire flow (1000 GPM) and the minimum required residual pressure of 20 PSI. These determinations have been made by use of computer models developed for our Water Master Plan. The City of Meridian will own and operate the wastewater collection and domestic water distribution systems within this project upon final inspection and acknowledgement by formal acceptance letter. In essence, the City of Meridian "Will Serve" the project. Attached for your records is a complete and accurate copy of the plans and specifications reviewed in connection herewith, stamped "Approved for Construction." Warren Stewart, P.E. Engineering Manager Tracy Crane, WWTP Plant Manager Chip Hudson, Water Department Mike Reno, Central District Health Dept. File Public Works Department . 33 E. Broadway Avenue, Suite 200 . Meridian, lD 83642 Phone 208-898-5500 . Fax 208-898-9551 r www.rTteridiancity.org %8e,. CE\IIRA CONSULTING INC MEMORANDUM J une 3. 2014 To: Denny Cline, Development Analyst ll Development Services Division, City of Meridian From: George A. Murgel, P.E., Ph.D., Qualified Licensed Professional Engineer (QLPE) Re: Phase #1 Southern Highland Offsite Utilities Dear Denny: We have completed our review of the plans for the referenced project. The plans are approved for construction as allowed under ldaho Code 39-1'18(2Xd). The completed "Qualified Licensed Professional Enganeer (QLPE) Review and Approval Checklist" (QLPE Checklist) is attached. The QLPE Checklist was prepared to meet the transmittal letter requirements specified in IDAPA 58.01.08.504.03(b) and 58.01 .16.400.03(b). The planswere marked as "Approved for Construction". Please note that the certifications required for Sections ll(B) and (C) of the QLPE Checklist must be satisfled with a will-serve letter and declining balance statement from the City. Electronic Files have been uploaded to the City of Meridian's FTP site in accordance with the terms of the Contract and we are returing one copy to the City for your records. Additionally we are returning two sets of the original redlines. Please contact me if you have any questions George Murgel, P.E., CENTRA Consulting, lnc. Attachment: Qualified Licensed Professional Engineer (QLPE) Review and Approval Checklist Cc: File Project: City of Meridian QLPE Contrad: CENTRA Consulting, lnc. . 413 West ldaho Street, Suite 302, Boise, ldaho . Tel: (208) 338-9400 . Fax: (208) 338-3844 . www.centrainc.com D, State of ldaho Department of Environmental Quality 1410 North Hilton . Boise, ldaho 83706 . (208) 373-0502 QUALTFTED LTCENSED pROFESSTONAL ENGTNEER (ALPE) REVIEW AND APPROVAL CHECKLIST About this form o This checklist is optional to use and is guidance from DEQ to qualified licensed professional engineers (QLPE). This checklist describes the required elements of a QLPE project transmittal letter and is intended to assist DEQ in the tracking of drinking water and wastewater projects, as well as assist the QLPE in reviewing and approving certain types of Plans and Specifications. . This checklist should be filled out by the qualified licensed professional engineer (QLPE) when the QLPE is reviewing and approving a project for construction under Idaho Code $ 39-l l8(2)(d). If the project requires DEQ approval prior to construction, the QLPE shall direct the Design Engineer to submit the plans and specifications through the normal DEQ review process. o This checklist may be used in place of a transmittal letter from the QLPE. o This and other design checklists are available at any DEQ regional office or online at htto://www.deo.state. id.us/water/r business/enqineers/checkl ists.cfm a The other checklists include additional information about submitting a package of plans and specifications for DEQ review. I. GENERAL PROJECT INFORMATION Project Name: Phase #l Southern Highlands Offsite Utilties Approving Authority X: CITY OF MERIDIAN Qualified Licensed Professional Engineer: Name: George A. P.E., Ph.D. I 2 J Employer: CENTRA CONSULTING INC 4 This approval is for: f RuUIic drinking water system simple water main extension [l euUtic sewer system simple wastewater main extension Design Engineer Name: Chad S. Kinkela 5 Employer: CK P.C 6 Project Owner or Developer: (Please provide exact name of owner or authorized representative) T&M Holdings, LLC Name: Firm: Address: City: 16166 N 20'h Street Nampa State: Idaho ZIP 83 687 Approving Authority refers to the City, County, Quasi-Municipal Corporation, or is approving the plans and specifications per Idaho Code 39- I l8(2Xd). QLPE Review and Approval Form Revised November 2008 Page 1 of 3 Regulated Public Utility that QLPE CHECKLIST il, Checklist ltem Yes A) I am the QLPE representing the Approving Authority B) This project consists of simple wastewater main extension(s), simple water main extension(s), or both. It complies with the current facility plan or preliminary engineering report. The water or wastewater system has adequate capacity for the project. (lf required, please include declining balance spreadsheet to demonstrate capacity) C) The Approving Authority has committed to serve this project and has reserved capacity for it. (Attach separate will serve letter or other documentation if needed.) X D) The Approving Authority will own and operate the project upon completion of construction. (Attach separate letter or other documentation if needed.) E) I have reviewed the plans and specifications and verified that they comply with the facility and design standards (IDAPA 58.01.08 and IDAPA 58.01.16) and engineering standards ofcare. III. PLAN & SPECIFICATION APPROVAL Checklist ltem Yes A) As the QLPE for the Approving Authority, I have approved the plans and specifications for construction. I am not the design engineer, nor was I otherwise involved in the design. B) The plans and specifications have been marked as "Approved for Construction", and a copy of the approved plans were transmitted to DEQ with this checklist. C) The plans are for simple wastewater main extension(s), simple water main extension(s), or both. No mechanical systems such as drinking water sources, treatment facilities, booster stations, storage facilities, or wastewater systems such as lift stations or treatment works are included with this project. ** x x D) This extension project will connect to: l) Existing drinking water andlor wastewater mains owned by the Approving Authority x OR 2) A future main(s) not existing at the time of approval. The future main(s) will be owned by the Approving Authority. In such cases, sanitary restrictions will remain in force. ** Portions of a project that require DEQ approval must be approved by DEQ prior to the eLpE approval of the drinking water or wastewater extensions. Alternatively, the drinking water and/or wastewater extensions may be submitted to DEe for approval of the entire project. QLPE Review and Approval Form Revised November 2008 Page 2 of 3 x x tr QLPE CHECKLIST IV. SAru'TARYRESTR'CT'OruS If the project includes drinking water and wastewater main extensions that will be reviewed and approved separately, the two Approving Agencies must coordinate the review and approval as it pertains to the lifting of sanitary restrictions. Recommendation Yes I have reviewed and approved all drinking water and wastewater improvements included X in this project, and I recommend that the district health department release sanitary restrictions. OR I have reviewed and approved only the drinking water! wastewater f] (check one) improvements included in this project, and I recommend that the district health department release sanitary restrictions once they receive the approval from the other Approving Authority. OR I recommend that the district health department leave sanitary restrictions in place. V. NOTE ON RULES AND STANDARDS This checklist addresses the majority of common items from the Idaho Rules for Public Drinking Water Systems (IDAPA 58.01.08), the Wastewater Rules (IDAPA 58.01.16, for QLPE approval of projects. However, this checklist is not all-inclusive, and users are expected to fully understand the rules and standards, apply them where necessary, and request interpretations from DEQ if there are any questions. DEQ regional offices may have additional written information that will assist in the design/approval process. VI. QLPE CERTIFICATION All responses indicated on the checklist above are accurately reJlected in the attached Plans and Specifications. QLPE's, Signature, Date and Seal QLPE Review and Approval Form Revised November 2008 Page 3 of 3 tr