HomeMy WebLinkAboutPreviously Received ReportsACHD � cloolrll a t105lzl�cll July 7, 2017 Matt Derr, P.E. Breckon Landdesign RE: Avebury Subdivision / SUBP17-0042 PLAN REVIEW ACCEPTANCE Paul Woods, President Rebecca W. Arnold, Vice President Sara M. Baker, Commissioner Jim D. Hansen, Commissioner Kent Goldthorpe, Commissioner The District has reviewed the plans for the above referenced project, and they are accepted for public street construction once the following items are completed: 1. Sheet C9: you added keynote 21 to call out the inlet protection in the pond. Can you apply that to the inlet protection location 2. Please note: Effective December 7, 2016 the ACHD plat approval process has been changed and scheduling the plat on a Commission meeting agenda is no longer required. All standard requirements prior to plat approval are still required and ACHD staff kindly requests that you give us sufficient time to review and prepare the final plat for signature. 3. For plat signature; please reserve sufficient time in your schedule forACHD staff to review all the items associated with the plat, to include (but not limited to) agreements, easements and the final plat. All required items must be submitted and approved by ACHD prior to approval of the final plat. A minimum of one week must be allowed for ACHD to review and comment on some of the required items (i.e., but not limited to; Draft CC & R's and M & O Manuals). No assurances can be made for delayed submittals. 4. Comply with all Standard Requirements of approval. By stamping and signing the improvement plans, the Registered Engineer ensures the District that the plans conform to all District policies and standards. Variances or waivers must be specifically and previously approved by the District in writing. Acceptance of the improvement plans by the District does not relieve the Registered Engineer of these responsibilities. The fees and surety amount are shown on the attached checklist. Please provide original drawings to be stamped and signed. Required Pre -Construction Submittals: Provide one -original set of civil plans for ACHD stamp and approval. If construction does not commence and the project is delayed, the approval is subject to withdrawal under the following conditions. A new review will need to be conducted that will be subject to an additional plan review fee: • Changes in federal regulations that would result in necessary changes to the plan; i.e. ADA Requirements, water quality requirements, etc. • Expiration of the preliminary plat. Ada County Highway District • 3775 Adams Street • Garden City, ID • 83714 • PH 208 387-6100 • FX 345-7650 • www.achdidaho.org 2. Once approved by the District, provide two 11x17 scalable copies of the stamped plans w/plat to ACHD Development Review prior to scheduling a Pre -Construction Conference. The ACHD Inspection Division will not schedule a Pre -Construction Conference or issue a permit for work in the right-of-way until this is complete. 48 hours prior to requestinq the Pre -Construction Conference: • Pay Plan Review Fee. • Submit signed Inspection Agreement. • Pay Inspection Fee Deposit. Please note: The inspection deposit amount is an estimate for the inspection time for the project. Under the terms of the Inspection Agreement; the Developer will be responsible for any additional charges that may arise. • Provide approved copy of plans. • Provide the contractor and materials information on the attached form. • Notice: ACHD is now accepting SWPPP/ESC submittals on CD or thumb drive. The owner applicant must submit a Sediment and Erosion Control/Construction Site Discharge Control Narrative and Map prepared by a Certified Plan Designer to ACHD DevelopmentServices for approval prior to scheduling a Pre -Construction Conference. Note: ACHD will no longer accept SWPPP/ESC plans for review prior to ACHD acceptance of the civil plan. Please make sure the site plan submitted with the SWPPP/ESC Plans is an exact replication of the approved drainage plan and include any ACHD stamped sheets pertinent to the drainage design. Provide the ACHD Inspection Division one copy of the Erosion & Sediment Control Plan for offsite utility work i.e. the typewritten narrative & associated map for ACHD stamp and approval. Note: this must be separate from what has been submitted for the subdivision work. Please go to the link below for submittal requirements: http://achdweb achdidaho.orq/Departments/Enqineerinq/Stormwater/constErosionControl.aspx 4. Contact ACHD Development Services at 387-6284 to request the Pre -Construction Conference. The Pre -Construction Conference will not be scheduled until all the above conditions are met. 5. Provide additional sets of ACHD approved/signed construction plans for each contractor at time of Pre -Con. Prior to signature of the final plat the District will require the following items to be completed. 1. All fees paid (plat, surety). Developer must provide a financial surety for the amount shown on the attached surety calculation sheet. Acceptable forms of surety include cash, bank certificate of deposit in ACHD's name, or irrevocable letter of credit. Letters of credit must be issued by an FDIC insured financial institution with a local branch in Ada County. The letter of credit shall be for a term not less than six months and shall allow ACHD to present documents to draw on the letter of credit at the local branch. ACHD shall be the sole beneficiary of the financial surety (Attached is a description identifying surety requirements). Bonds shall meet the requirements as set forth in ACHD Policy Section 7103. If providing a letter of credit or bond, please email a draft of the LOC or bond to ACHD staff to review, prior to submitting the final document. 2. Provide signed Subdivision Improvement Agreement. 3. Provide an exact 8'/2" x 11" reduction of all sheets of the final plat mylar. Note, plat reduction must be signed and stamped by the PLS. 4. Provide 8'/2" x 11" vicinity map. 5. Provide final plat mylar signed by the owner and notarized 6. Provide original signed License Agreement for the storm drain easement areas. Allow 3 weeks for processing. 7. Provide original signed Master Storm Drain Confirmation Agreement 8. A copy of the amended CC & R's and the Maintenance and Operation Manual for any drainage facilities to be located in a common lot to be owned and maintained by the homeowners association. Allow 1 Week for review. Maintenance and Operation Manuals shall be bound and include the following: Note: Multi -phase developments under the same Homeowners Association must have one manual that includes all previous phases of the development. 1. An 11" x 17" reduction of the stamped approved construction plans of the subdivision showing the location of all storm drainage facilities. 2. An 8 1/2" x 11" copy of the final plat(s). 3. Engineering drawings of the facility. These drawings must show the details of each facility that accepts ACHD drainage that the homeowners are responsible for maintaining. The plan sheets must be folded and appended to the manual. 4. A written description of the maintenance required by the Homeowners Association. 5. An itemized list of the annual operating and maintenance tasks for the Homeowners Association. 6. A statement describing the primary purpose of the facility is for storm water. Any additions to the facility (such as park benches or additional landscaping) should be considered temporary and may be removed when heavy maintenance of the facility is needed. Replacement of these items will be the responsibility of the Homeowners Association. CC & R's Requirements 1. The recorded restrictive covenants shall include a section describing the maintenance responsibilities of the property owners within the development. The approved and recorded CC & R's must be submitted electronically to ACHD prior to the release of any monies and acceptance of the streets for maintenance. 2. The Maintenance and Operation Manual outlined above must be referenced. 3. The recorded restrictive covenants shall include wording that: a. Gives the District the right to inspect such facilities, and if necessary, promptly perform any required maintenance. b. Requires District concurrence with any proposed changes in the previously approved documents. C. Allows the District to assess the costs of any required maintenance to the property within the development, including the use of liens and/or assessment of maintenance costs against real property within the development. d. If there are roadside swales, CC&R's must describe the primary purpose of the swales adjacent to the lots is for storm water. Swales shall be maintained by the Home Owners Association and the individual homeowner. Swales are located within the District's Right - of -Way. • Include language to specify only one tree allowed per common lot line. Tree to be planted on the back side of swales. Required Post Construction Submittals: Record Drawings The following submittals are required after construction and prior to District acceptance of the public street improvements within the subdivision OR prior to plat approval if a surety has not been provided: 1. (1) 11 x17 reduced copy, a CD with pdf, and the CAD files of the As -Built Construction Drawings w/ plat. Please see the ACHD website for details regarding the requirements for the CAD files: http://achdweb.achdidaho.org/Documents/Forms/ZipFiles/CadToGIS.zip. Identify all changes and provide corresponding note describing the change. 2. Note: The As -Built Drawings will not be considered "accepted" by ACHD until construction of the subdivision is completed and approved. Required Prior to ACHD Acceptance of the Streets for Maintenance: Subdivision plat must be recorded; prior to ACHD accepting the streets for maintenance The District cannot accept the street and drainage improvements for public maintenance or release the developer's financial surety until these requirements have been met. If you have any questions please feel free to contact me at 387-6354 or malexander@achdidaho.org. Mike Alexander Engineering Tech I malexander(a)_achdidaho.org cc: Guy Hendrickson ACHD Surety Requirements Minimum Surety Amount • For plat signature, the minimum surety requirement is the amount calculated at plans acceptance or any subsequent increase in project scope. Developer may request an inspection for surety reduction if construction is partially complete meeting the following minimum: o All concrete work must be complete per plans and ACHD standards and signed off by Inspector by requesting a "Concrete Final" inspection. Once concrete is deemed complete, only the estimated value for the concrete will be reduced from the surety. o OR All storm drain and paving is complete per plans and ACHD standards and signed off by Inspector, storm drain is only included in the reduction if paving is complete. • To obtain plat signature with surety reduction punch list, Development Review may calculate a reduced surety amount upon request. • For plat signature with minimal punch list items (as determined by ACHD), the minimum surety is $10,000. • For plat signature with no punch list items (as determined by ACHD), but no record drawings have been submitted, the minimum is $5,000. • For subdivisions with roadside swales that are incomplete, the minimum will not be less than two times the swale deposit, plus any other punch list items. For subdivisions with required bridge work that is incomplete, the minimum will not be less than two times the cost estimate for the bridge work, plus any other punch list items. Surety Expiration • For Letters of Credit, ACHD will attempt to send a written notice of expiration within 45 -days of expiration. It is the developer and bank's responsibility to keep the surety current with ACRD. Letter of Credit extensions must be for minimum 90 -days. • Construction final inspections must be scheduled 10 -days or more prior to demand date of the Letter of Credit. If the work is not verified complete or final inspection scheduled before 10 -days of the demand date, the Letter of Credit must be extended a minimum of 90 - days or ACHD will file demand on the Letter of Credit. Web links to standard Development Services forms Bridge Design Checklist: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/BridgeReviewChecklist.pdf Confirmation Agreement for Master Perpetual Storm Water Drainage Easement: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/StormwaterDrainageConfirmationAgreeme nt2x Master Storm Drain Easement Plat Note: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/StormDrainageEasementPlatNote.pdf Current Fee Schedule: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/DevServicesFeeSched.pdf Driveway Approach Request: (Required for new connections to the public roadway) http://achdweb.achdidaho.orq/Documents/Forms/mostDocs/DrivewayApproachReguest.pdf Fire Dept Approval Form: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/FireDeptApproval.pdf License Agreement Application: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/LicenseAgreementGuidelines.pdf Plan Checklist: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/PlanChecklist.pdf Civil Plan Completeness Checklist: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/CivilPlanCompletenessChecklist.pdf Plat Checklist: http://achdweb.achdidaho.org/Documents/Forms/mostDocs/PlatSubmittal.pdf Impact Fee Schedule: http://achdweb.achdidaho.org/Documents/Engineering/ImpactFees/Ordinance231/ExhibitA FeeSchedu le.pdf Impact Fee Information: http://achdweb.achdidaho.org/Departments/En inq eering/DevelopmentServices/impactFees.aspx CENTRAL �• DISTRICT HEALTH DEPARTMENT MAIN OFFICE • 707 N. ARMSTRONG PL. • BOISE, ID 83704-0825 • (208) 375-5211 • FAX 327.8500 "To lutprove 1Ge itealf i of ourconanuailles by identiryittg sustainable solutions to cottantuttity health issues, developing partnerships for intpletnentalion ofstrategies, and deutonstralbtg our success iltrougli rtteusureatent of oulconres. " 18-0333 May 16, 2018 Christopher D. Rich Ada County Recorder 200 West Front Street Boise, ID 83702 RE: Avebury Subdivision Dear Mr. Rich:.... Central District Health Department has reviewed and does approve the final plat for this subdivision f6r central water and central sewer facilities. Final approval was given May 16, 2018. Sanitary restrictions as required by Idaho Code, Title 50, Chapter 13 have been satisfied based on a review by, a Qualified Licensed Professional Engineer (QLPE) representing the City of Meridian and the QLPE approval of the design plans and specifications and the conditions imposed on the developer for continued satisfaction of the sanitary restrictions. Buyer is cautioned that at the time of this approval, no drinking water extensions or sewer extensions were constructed. Building construction can be allowed with appropriate building permits if drinking water extensions or sewer extensions have since been constructed or if the developer is simultaneously constructing those facilities. If the developer fails to construct facilities then sanitary restrictions may be reimposed, it! accordance with Section 50-1326, Idaho Code, by the issuance of a certificate of disapproval, and no construction of any building or shelter requiring drinking water or sewer/septic facilities shall be allowed. Serving Valley, Eltttore, Boise, artd Ada Counties Ada / Boise Coltnty Office Elmore County Office Valley County Office 707 N. Armstrong Pi,. ' 520 E. 81h St. North 703 N. Ist St, Boise, ID 83704 Mountain Home, ID 83647 McCall, ID 83638 Enviro. Health: 327.7499 Enviro. Health: 587-9225 Ph. 634-7194 Reproductive Health: 327.7400 Family Health: 587-4407 FAX: 634-2174 Immunizations. 327-7450 WIC: 587-4409 Senior Nutrition: 327-7460 FAX: 5873521 WIC: 327.7488 FAX: 327.8500 Fire .Department .Approval City of: F1 Boise N Meridian ❑ Eagle ❑ Kuna ❑ Star ❑ N.W. Ada Subdivision: Avebury Subdivision Date: 6/8!17 Commercial Project: Engineer/Developer: Breckon Land Design Local Fire Department officials -please check appropriate items for your approval F16. I itials Check Approved Items ® Reduced Street Section (approved width 24' BTB ) (standard is 36' back of curb to back of curb) rolled curb ❑ Roundabout ❑ Permanent Turnaround ❑ Temporary Turnaround _.�. ❑ Emergency Turnaround ❑ Emergency Access Comments - Ada County Highway District • 3775 Adams Street • Garden qty, 10 • 83714 • PH 208 387 6170 • FX 387 6393 • www,achd.ada.ld.us Fire Department Approval City of: �] Boise N� Meridian [-] Eagle ❑ Kuna ❑ Star ❑ N.W. Ada Subdivision: Avebury Subdivision Date: 2/14/18 Commercial Project: N/A Engineer/Developer: Matthew Derr, P.E. Local Fire Department officiats - please check appropriate items for your approval Comments - Check Approved Items f J Reduced Street Section (approved widthdard is 36' back of curb to back of curb) ❑ Roundabout ❑ Permanent Turnaround ❑ Temporary Turnaround ❑ Emergency Turnaround ❑ Emergency Access Ada County Highway District • 3775 Adams Street • Garden City, ID • 83714 • PH 208 387 6170 • FX 387 6393 * www.achd.ada.id.us EIDIAN..-1-.--- IDAHv / May 08, 2017 Mr. Aaron Scheff IDEQ Boise Regional Administrator 1445 N. Orchard Street Boise, Idaho 83706 Re: Project Approval - Avebuiy Subdivision Mayor Tammy de Weerd City Council Members: Keith Bird Joe Borton Luke Cavener Genesis Milam Ty Palmer Anne Little Roberts Per the provisions in Idaho Code § 39-118(2)(d), the City of Meridian has retained the services of Keller associates .as its Qualified Licensed Professional Engineer (QLPE), to verify that the plans and specifications proposed for the above -referenced project comply with the IDEQ Facility and Design Standards (IDAPA 58.01.16 and 58.01.08) and the applicable Meridian standards, and to approve the project for construction. By virtue of their attached letter, they have reviewed and approved the above referenced plans and specifications as complying with the Facility and Design Standards, and Engineering Standards of Care as it relates to the reviewed elements. The above referenced project complies with the City of 's current Wastewater Facility Plan, and Sewer Master Plan, and our system has adequate capacity to accept sewage wastes for treatment. These determinations have been made by use of computer models developed for our Sewer Master Plan. This project is also within the City's urban service planning boundary. Our Domestic Water distribution system can provide water service and the minimum required fire flow (1000 GPM) and the minimum required residual pressure of 20 PSI. These determinations have been made by use of computer models developed for our Water Master Plan. The City of Meridian will own and operate the wastewater collection and domestic water distribution systems within this project upon final inspection and acknowledgement by formal acceptance letter.. In essence, the City of Meridian "Will Serve" the project. Attached for your records is a complete and accurate copy of the plans and specifications reviewed in connection herewith, stamped "Approved for Construction." Si cer y, Warren Stewart, P.E. Engineering Manager Public Works Department . 33 E. Broadway Avenue, Suite 200 . , ID 83642 Phone 208-898-5500. Fax 208-898-9551 . www.meridiancity.org KE L L E R 131 SW 511 Avenue, Suite A • Meridian, ID 83642 associate S 208.288.1992 phone • 208.288.1999 fax • www.kellerassociates.com May 5, 2017 Development Services Division City of Meridian Attn: Amanda McNutt 33 E. Broadway Ave. Meridian, ID 83642 Re: City of Meridian QLPE Review -Avebury Subdivision Keller Associates has reviewed the Avebury Subdivision construction plans dated May 3, 2017. The plans are approved for construction as allowed under Idaho Code 39-118(2)(d). The completed "Qualified Licensed Professional Engineer (QLPE) Review and Approval Checklist" (QLPE Checklist) is attached. The QLPE Checklist was prepared to meet the transmittal letter requirements specified in IDAPA 58.01.08.504.03(b) and 58.01.16.400.03(b). The plans were marked as "Approved for Construction". By stamping and signing the construction plans, the Registered Professional Engineer is responsible to ensure that said construction plans conform to all City standards, ordinances, and policies (arid State laws and statutes). Any variances or waivers to these standards, ordinances, or policies must be specifically and previously approved in writing by the City. Acceptance of the above referenced construction plans does not relieve the Registered Professional Engineer of those responsibilities. Please note that: the certifications required for Sections II(B) and (C) of the QLPE checklist must be satisfied with a will serve letter and declining balance statement from the City. Electronic files have been uploaded to the City of Meridian's FTP site in accordance with the terms of the contract and we are returning one copy to the City for your records. If you have any questions, please do not hesitate to call Keller Associates at (208) 288-1992. Sincerely, KELLER ASSOCIATES, INC. yan V. Morgan, P.E. QLPE Reviewer 214]11-172/17-174 Engineering Solutions, Satisfied Clients Clarkston a Idaho Falls • Meridian 9 Pocatello 9 Rocic Springs • Roseville . Salem State of Idaho Department of Environmental Quality 1410 North Milton • Boise, Idaho 83706 - (208) 373-0502 QUALIFIED LICENSED PROFESSIONAL ENGINEER (QLPE) REVIEW AND APPROVAL CHECKLIST About this form • This checklist is optional to use and is guidance from DEQ to qualified licensed professional engineers (QLPE). This checklist describes the required elements of a QLPE project transmittal letter and is intended to assist DEQ in the tracking of drinking water and wastewater projects, as well as assist the QLPE in reviewing and approving certain types of Plans and Specifications. • This checklist should be filled out by the qualified licensed professional engineer (QLPE) when the QLPE is reviewing and approving a project for construction under Idaho Code § 39-118(2)(d). If the project requires DEQ approval prior to construction, the QLPE shall direct the Design Engineer to submit the plans and specifications through the normal DEQ review process. • This checklist may be used in place of a transmittal letter from the QLPE. • This and other design checklists are available at any DEQ regional office or online at http:Hwww deq state id us/water/assist business/engineers/checklists.cfin. • The other checklists include additional information about submitting a package of plans and specifications for DEQ review. 1. GENERAL PROJECT INFORMATION Project Name: 2 Approving Authority* Avebury Subdivisioin CITY OF MERIDIAN 3 Qualified Licensed Professional Engineer: Name: Ryan V. Morgan; P.E., LEED AP Employer: Keller Associates 4 This approval is for: ® Public drinking water system simple water main extension ® Public sewer system simple wastewater main extension 5 Design Engineer Name: Matthew S. Derr Employer: Breckon Land Project Owner or Developer: (Please provide exact name of owner or authorized representative) Name: Guy Hendricksen Firm: Avebury Development, LLC Address: 408 S Eagle Road #103 City: Eagle State: ID ZIP: 83616 Approving Authority refers to the City, County, Quasi -Municipal Corporation, or Regulated Public Utility that is approving the plans and specifications per Idaho Code 39-118(2)(d). QLPE Review and Approval Form Page 1 of 3 Revised November 2008 QLPE CHECKLIST 11. REQUIRED CERTIFICATIONS Checklist Item Yes A) I am the QLPE representing the Approving Authority. B) This project consists of simple wastewater main extension(s), simple water main extension(s), or both. It complies with the current facility plan or preliminary engineering report. The water or wastewater system has adequate capacity for the project. (If required, please include declining balance spreadsheet to demonstrate capacity) C) The Approving Authority has committed to serve this project and has reserved capacity for it. (Attach separate will serve letter or other documentation if needed.) D) The Approving Authority will own and operate the project upon completion of construction. (Attach separate letter or other documentation if needed.) E) I have reviewed the plans and specifications and verified that they comply with the facility and design standards (IDAPA 58.01.08 and IDAPA 58.01.16) and engineering standards of care. W. PLAN & SPECIFICATION APPROVAL Checklist Item Yes A) As the QLPE for the Approving Authority, I have approved the plans and specifications for construction. I am not the design engineer, nor was I otherwise involved in the design. B) The plans and specifications have been marked as "Approved for Construction", and a copy of the approved plans were transmitted to DEQ with this checklist. C) The plans are for simple wastewater main extension(s), simple water main extension(s), or both. No mechanical systems such as drinking water sources, treatment facilities, booster stations, storage facilities, or wastewater systems such as lift stations or treatment works are included with this project. D) This extension project will connect to: 1) Existing drinking water and/or wastewater mains owned by the Approving Authority. OR 2) A future main(s) not existing at the time of approval. The future main(s) will be ❑ owned by the Approving Authority. In such cases, sanitary restrictions will remain in force. �* Portions of a project that require DEQ approval must be approved by DEQ prior to the QLPE approval of the drinking water or wastewater extensions. Alternatively, the drinking water and/or wastewater extensions may be submitted to DEQ for approval of the entire project. QLPE Review and Approval Form Page 2 of 3 Revised November 2008 QLPE CHECKLIST IV. SANITARY RESTRICTIONS If the project includes drinking water and wastewater main extensions that will be reviewed and approved separately, the two Approving Agencies must coordinate the review and approval as it pertains to the lifting of sanitary restrictions. Recommendation Yes I have reviewed and approved all drinking water and wastewater improvements included in this project, and I recommend that the district health department release sanitary restrictions. OR I have reviewed and approved only the drinking water[] wastewater ❑ (check one) ❑ improvements included in this project, and I recommend that the district health department release sanitary restrictions once they receive the approval from the other Approving Authority. OR I recommend that the district health department leave sanitary restrictions in place. ❑ V. NOTE ON RULES AND STANDARDS This checklist addresses the majority of common items from the Idaho Rules for Public Drinldng Water Systems (IDAPA 58.01.08), the Wastewater Rules (IDAPA 58.01.16, for QLPE approval of projects. However, this checklist is not all-inclusive, and users are expected to fully understand the rules and standards, apply them where necessary, and request interpretations from DEQ if there are any questions. DEQ regional offices may have additional written information that will assist in the design/approval process. Vl. QLPE CERTIFICATION All responses indicated on the checklist above are accurately reflected in the attached Plans and Specifications. QLPE's, Signature, Date and Seal QLPE Review and Approval Form Page 3 of 3 Revised November 2008 251 Seo CERTIFICATE OF ORGANIZATION y 0 LIMITED LIABILITY COMPANY FILED EFFECT'VL Title 30, Chapters 21 and 25, Idaho Code 2016 NOV 16 P,� rte* 04 Filing fee: $100 typed, $120 not typed 2• 4 1 Complete and submit the application in duplicate. SECR I s, R �, Or STATE 1. The name of the limited liability company is: STATE OF ioaHa AD800, LLC (Remember to include the words "Limited Liability Company," "Limited Company," or the abbreviations L.L.C„ LLC, or LC) 2. The complete street and mailing addresses of the principal office is: 408 S Eagle Road, Suite 103, Eagle ID 83616 Street Address (Mailing Address, if different) 3. The name of the registered agent and street address of the registered agent: Guy Hendricksen 408 S Eagle Road, Suite 103, Eagle ID 83616 (Name) (Address cannot be a post office box or postal mail box) 4. The name and address of at least one governor of the limited liability company: Guy Hendricksen 408 S Eagle Road, Suite 103, Eagle ID 83616 (Name) (Address) ame) (Address) (Name) (Address) me (Address) 5. Mailing address for future correspondence (annual report notices): 408 S Eagle Road, Suite 103, Eagle ID 83616 (Address) Signature of orgapjzer(s).. Signature: Printed Nam : y Hendricksen Signature: Printed Name: Rev 17!2015 Secretary of State use only IDAHO SECRETARY OF STATE 11/16/2016 05:00 CK -.3041 CT : 331277 BH : 1555G23 1G 100.00 = 100.00 ORG-W LLC 02 -V rlh>r14