HomeMy WebLinkAboutWalker Fox Brick and Block, Inc AIA Discovery ParkStandard Form of Agreement Between Owner and Contractor,Construction
Manager as Adviser Edition
Bid Package No.2 . Masonry
AGREEMENT made as of the Fourteenth day of December in the year Two Thousand
Eighteen
(In words, indicate day, monlh and year.)
BETWEEN the Owner:
(Name, legal status, address and other information)
City of Meridian
33 East Broadway Avenue
Meridian, Idaho 83642
and the Contractor:
(Name, legal status, address and other information)
Walker Fox Brick and Block, tnc.
2520 N. 32, Boise, Idaho 83703
Telephone Number: 208-949-5464
for the following Project:
(Name, location and detailed desciption)
City of Meridian - Discovery Park Shop Building
2l2l East Lake Hazel Road in Meridian, Idaho 83642
The work involves construction of a new 2,240 SF shop building
The Construction Manager:
(Name, legal status, address and other information)
Kreizenbeck, LLC DBA Kreizenbeck Constructors
I1724 West Executive Drive,
Boise, Idaho 83713
Telephone Number: (208) 336-9500
Fax Number: (208) 336-7 444
The Architect:
(Name, legal status, address and other information)
Insight Architects, P.A.
2238 S. Broadway Avenue, Boise, Idaho 83706
Telephone Number: 208-3 38-9080
The Owner and Confiactor agree as follows'
ADDITIONS AND DELETIONS:
The author of this document has
added information needed for its
completion. The author may also
have revised the text of the original
AIA standard lotm. An Additions and
Deletions Repolt that notes added
information as well as revisions to
the standard form text is available
from the author and should be
reviewed. A vertical line in the left
margin of this document indicates
where the author has added
necessary information and where
the author has added to or deleted
from the original AIA text.
This document has important legal
consequences. Consultation with an
attomey is encouraged with respect
to its completion or modification.
This document is intended to be
used in conjunction with AIA
Documents A232il -2009, General
Conditions of the Contract for
Construction, Constructjon Manager
as Adviser Edition; B132ru-2009,
Standard Form of Agreement
Between o(^rner and Architect,
Construction Manager as Adviser
Edition; and Cl 32ru-2009,
Strandard Form of Agreement
Between Oilner and Construction
Manager as Adviser.
AIA Document A232il-2009 is
adopted in this document by
reference. Do not use with other
general conditions unless this
document is modified.
AIA Docum.nt A132il - 2009 (formcrly A1OlilCta - 1992). Copyright O 1975, 1980' '1992 and 2009 by The American lnstitute of Architects. All rightr
rcrervcd. WARNING: This AlAi Document is pro(ected by'U.S. Copyrlght Lew and lnbmatlonal Unauthorlz.d ruproduction or dlstrlbutlon ofTrra0cc.
thi. AlAo Documcnt or anY Pordm ol lt may msult ln a.Y.ra civil and criminal penaltios, and wlll I
1 :07:46 MT on 12l1712018 under Oderunder the law. This docrrment was produed
not for resale.
Usor Notot:
be prosecuted to the maximum ertent possible
' No. 84496331 79 which expires on 1212812019, and is
lnit.
by AIA software at 1
(3B9ADA61 )
1
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 295 of 576
I raaLE oF ARTTcLES
I THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERM]NATION OR SUSPENSION
8 MISCELLANEOUSPROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
1O INSURANCEANDBONDS
I g*ogroph Deleted)
ARTICLE 1 THE CONTRACT DOCUTIENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other
Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed
in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and
are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract, together with
the performance bond and payment bond, if any, represent the entire and integrated agreement between the parties
hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of
the Contract Documents, other than Modifications, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specihcally indicated in
the Confiact Documents to be the responsibility of others.
Contrac-t Requirements: Provide all labor, material and equipment required to complete the masonry work as
noted in the construction documents and per the following:
I fnis contract specilically includes but is not limited to:
o Complete all masonry work as shown on the construction documents.
. Receive, install and grout hollow metal frames and miscellaneous embedded items located in masonry
walls.
r Provide and install all shoring and bracing, lintels and sills for your work, including block outs for all
masonry, as required for this scope of work.
o Include block out and lintel for mechanical louver Ll.
o Fumish and install all anchor bolts in masonry as per the construction documents.
o Provide insulated blankets and labor for weather protection of masonry work as requted.
o Fumish and install reinforcing steel for masonry.
r Grind split face materials smooth behind fixtures and equipment.
r Caulk all masonry-masonry, masonry-hollow metal and masonry-concrete joints.
. All masonry materials to have integral water repellent.
r Protection ofthe concrete slabs and adjacent surfaces from damage during the masonry work'
AIA Documcnt A132il - 2000 (lormcdy Al01ilCta - 1992). Copyright @ 1 975, 1 980, 1 992 and 2009 by The American lnstitute of Architects.
rrr.rv.d. WARNING: This ALA0 Documonl i3 protec'ted by U.S. Copyrlght Law and lnt mational T]!rtl.3. Unauthoriz.d rrproductlon or
All right3
dbtribution of
thl! AIA' Documcnt, or any porton ol i( may
under the law. This docurYtsnt was ptoduced by
not br r€sale.
U3Gr Notca:
civil and criminal p.naltiel, and will I
1 :07:46 MT on 12117 12018 unde? Ord,et
b. prosecutod to tho marimum oxtont possiblo
' No. M49633179 which expires on 12,2U2o19' and isrrgult ln ravcrr
lnit.
AIA software at 1
(3B9ADA61 )
2
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 296 of 576
lnit.
. Shrink wrap all block to prevent chips or damage, and dispose of all refuse off-site.
o All construction shall follow OSHA standards and requirements.
o Contractors Warranty (standard warranty) on the project is 2 years (minimum) from the date of final
acceptance in lieu of the I year as indicated in the project manual. Refer to the Supplementary General
Conditions included in the bid book. Extended warranties will be as noted in the contract documents.
This contract specifically excludes:
o Furnishing of the hollow metal frames.
o Sealing of masonry is by others.
ARTICLE 3 DATE OF CO}I]UENCEMENT AND SUBSTANTIAL COI{PLETION
$ 3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated
below or provision is made for the date to be fixed in a notice to proceed issued by the Owner.
(Insert the date of commencement, if it difers from the date of this Agreement or, if applicable, state that the date
will befixed in a notice to proceed.)
The commencement date will be hxed in a notice to proceed.
If, prior to the commencement of the Work, the Owner requires time to file mortgages, mechanics' liens and other
security interests, the Owner's time requirement shall be as follows:
$ 3.2 The Contract Time shall be measured from the date of commencement.
$ 3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than ( ) days from the date
of commencement, or as follows:
(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated wilh the date of
commencement. If appropriate, insert requiremenls for earlier Substantial Completion of certain portions of the
Work.)
The Contractor shall achieve Substantial Completion of the entire Work not later than June 14, 2019
(Table Deleted)
, subject to adjustments of this Contract Time as provided in the Contract Documents.
(Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time or for
bonus payments for early completion of the Work.)
In the event the Contractor, without excuse, fails to achieve Substantial Completion within the Contract Time, the
Conffactor shall pay to the Owner as liquidated damages, and not as a penalty, the sum of One Thousand Dollars
($1,000.00) or t/ro/o of the Contract Value (whichever is greater) for each and every calendar day following the end
of the Contract Time until Substantial Completion is achieved; provided that the Contractor shall not be liable for
liquidated damages for a day, or days ofthe excusable delay occurring during such period following the end ofthe
Contract Time.
ARTICLE4 CONTRACTSUM
$ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the
Contract. The Contract Sum shall be one of the following:
(Check the appropriate box.)
t X ] Stipulated Sum, in accordance with Section 4'2 below
not br resale.
Uscr Notes:
or3
IS
(3B9ADA61 )
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 297 of 576
t ] Cost of the Work plus the Contractor's Fee without a Guaranteed Maximum Price, in accordance
with Section 4.3 below
t ] Cost of the Work plus the Contractor's Fee with a Guaranteed Maximum Price, in accordance with
Section 4.4 below
@ased on the selection above, complete Section 4.2, 4.3 or 4.4 below. Based on the selection above, also complete
either Section 5. I .4, 5. I .5 or 5. I .6 below.)
$ 4.2 Stipulated Sum
$ 4.2.1 The Stipulated Sum shall be Sixty-Two Thousand Eight Hundred Fifty Dollars andZero Cents ($ 62,850.00
), subject to additions and deletions as provided in the Contract Documents.
$ t1.2.2 The Stipulated Sum is based on the following altemates, if any, which are described in the Contract
Documents and are hereby accepted by the Owner:
(State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the
Owner to accept other alternates subsequent to the execution of this Agreement, atlach a schedule of such other
alternates showing the amountfor each and the date when that amounl expires.)
$ 4.2.3 Unit prices, if any:
(Identify and state the unit pice, and state the quantity limitations, if any, to which the unit pice will be applicable.)
Item Units and Limitations Price per Unit ($0.00)
$ tl.2.tl Allowances included in the Stipulated Sum, if any:
(dentify allowance and state exclusions, if any, from the allowance pice)
Allowance
I e*ographs Deleted)
I paragraph Deleted)
I g*ogroph Deleted)
(Paragraphs DeleteQ
(Table Deleted)
not for resale.
Uler Not s:
or4
IS
lnit.
(3B9ADA61 )
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 298 of 576
I lfaragraphs Deleted)
I earagraph Deteted)
I earagraph Deleted)
(Paragraphs Deleted)
(Table Deleted)
I lParograph Deteted)
I garagraph Deleted)
(Paragraph Deleted)
(Paragraphs Deleted)
(Table Deleted)
I g*ograph Deleted)
ARTICLE 5 PAYMENTS
$ 5.1 Progress Payments
I S.t.t nasea upon Applications for Payment properly submitted to the Construction Manager by the Contractor, and
ipon certificati,on of ihe Project Application and Project Certificate forPayment or Application for Payment and
Cirtificate for Payment by tire Construction Manager and Architect and issuance by the Architect, the Owner shall
make progress payments Ln account of the Contract Sum to the Contractor as provided below and elsewhere in the
Confact Documents.
lnit.
not for resale.
Uscr Notec:
(3B9ADA61 )
of5
ts
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 299 of 576
$ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of
the month, or as follows:
$ 5.1.3 Provided that an Application for Payment is received by the Construction Manager not later than the Twenty-
fifth day of a month, the Owner shall make payment of the certified amount in the Application for Payment to the
Contractor not later than the Twenty-fifth day of the following month. If an Application for Payment is received by
the Construction Manager after the application date hxed above, payment shall be made by the Owner not later than
Thitty ( 30 ) days after the Construction Manager receives the Application for Payment.
(Federal, state or local laws may require payment within a certain peiod of time.)
$ 5.1.4 Progress Payments Where the Gontrac-t Sum is Based on a Stipulated Sum
S 5.1.4.1 Each Application for Payment shall be based on the most recent schedule of values submitted by the
Contractor and approved in writing by the Construction Manager and Architect in accordance with the Contract
Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work
and be prepared in such form and supported by such data to substantiate its accuracy as the Constnrction Manager
and Architect may require. This schedule, when, and only when, approved in writing by the Construction Manager
or Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment.
S 5.1.4.2 Applications for Payment shall show the percentage of completion of each portion of the Work as of the
end of the period covered by the Application for Payment.
$ 5.1.4.3 Subject to the provisions of the Contract Documents, the amount of each progress payment shall be
computed as follows:
.1 Take that portion of the Contract Sum properly allocable to completed Work as determined by
multiplying the percentage completion of each portion of the Work by the share of the total Confiact
Sum allocated to that portion of the Work in the approved schedule of values, less retainage of Five
percent ( 5.00 %). Pending final determination of cost to the Owner of changes in the Work, amounts
not in dispute may be included as provided in Section 7.3.9 of the General Conditions, as modified;
.2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and
suitably stored at the site for subsequent incorporation in the compteted construction (or, ifapproved
in writing in advance by the Owner, suitably stored offthe site at a location agreed upon in writing),
less retainage of Five percent ( 5.00 %);
.3 Subtract the aggregate of previous payments made by the Owner;
,4 Subtract amounts, if any, for which the Construction Manager or Architect has withheld or nullified a
Certificate for Payment as provided in Section 9.5 of the General Conditions, as modified; and
.5 Subtract amounts, if any, being withheld by the Owner or Construction Manager as provided in the
Contract Documents.
$ 5.1.4.4 The progress payment amount determined in accordance with Section 5.1.4.3 shall be further modified
under the following circumstances:
.1 Add, upon Substantial Completion of the Work, a sum sufftcient to increase the total payments to
Ninety-five percent ( 95.00 %) of the Contract Sum, less such amounts as the Construction Manager
recommends and the Architect determines for incomplete or defective Work, or both and unsettled
claims; and
.2 Add, if final completion of the Work is thereafter materially delayed through no fault of the Contractor,
any additional amounts payable in accordance with Section 9.10.3 of the General Conditions, as
modified.
S 5.1.1.5 Reduction or limitation of retainage, if any, shall be as follows:
(If it is intended, prior to Substantial Completion of the entire Work, to reduce or limit the retainage resultingfrom
the percentages inserted in Sections 5.1.4.3.1 and 5.1.4.3.2 above, and this is not explained elsewhere in the
Contract Documents, insert here provisions for such reduction or limitation.)
I No reduction in retainage will be allowed prior to final completion without written approval of the Owner
not for resale.
Usor Notos:
AIA Document Al32r - 2OOg (formedy AlOl ilCta - 1992). Copyright @ 1975, 1980, 1992 and 2009 by The American lnstilute of Architecls' All rightr
rcccilcd, WARNING: Thic AlAl Document is protected by'U.S. iopyright Law and lntomational Troatiec. Unauthorized reProduction or distribution of
this AlAo Documettt, or any portion of it, may resuh ln severe civil ind criminal penaltics, 8nd will ba prosecutcd to tha.meximum exbnt possible
undor tho taw. This document was produced by llA softrrare at 1 1 :07:46 MT on 12117 ti2}18 under Order No. 8449633179 which expires on 1?J2812019, and is
lnit.
(3B9ADA61 )
6
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 300 of 576
S 5.1.4.6 A condition will be included forbidding more retainage from a
contractor or supplier than retained from their portion of the Work.
(Paragraphs Deleted)
I e*agraphs Deleted)
I g*ogrophs Deleted)
$ 5.2 Final Payment
$ 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the
Contractor when
.1 the Contractor has fully performed the Contract except for the Contractor's responsibility to correct
Work as provided in Section 12.2 of AIA Document A232-2009 as modified, and to satis$ other
requirements, if any, which extend beyond final payment;
.2 the Contractor has submitted a final accounting for the Cost of the Work, pursuant to Exhibit A,
Determination of the Cost of the Work when payment is on the basis of the Cost of the Work, with or
without a Guaranteed Maximum payment; and
.3 a final Certificate for Payment or Project Certificate for Payment has been issued by the Architect; such
final payment shall be made by the Owner not more than 30 days after (l) the Contractor has fully
performed the Contract and (2) the issuance of the final Certificate for Payment or Project Certificate
for Payment, or as follows:
ARTICLE 6 DISPUTE RESOLUTION
$ 6.1 lnitial Decision ilaker
The Architect will serve as Initial Decision Maker pursuant to Section 15.2 of AIA Document 4232-2009 as
modified, unless the parties appoint below another individual, not a party to this Agreement, to serye as Initial
Decision Maker.
(If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker,
if other than the Architect.)
$ 6.2 Binding Dispute Resolution
For any Claim subject to, but not resolved by, mediation pursuant to Section 15.3 of AIA Document A232-2OO9 as
modihed, the method of binding dispute resolution shall be as follows:
(Check the appropiate box. If the Owner and Contractor do not select a method of binding dispute resolution
below, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims
will be resolved by liligation in a court of competentiurisdiction.)
I 1 Arbiration pursuant to Section 15.4 of AIA Document A232-2009
t X I Litigation in a court of competent jurisdiction.
t I Other: (Specify)
AIA Docum.nt 4132il -2009 (folmedy Al01
is AlA. Document is
ilCHa - 1902). Copyright O 1 975, I 980, 1 992 and 2009 by The American Institute of Architects. All right3
reserved. wARNING: Th prot c{od by U.S. Gopyrlght Law and lntcmallonal Tncatio!. Unauthorlz.d rcproduction or di3tribution of
thir AIA' Documcnt or rny pordon ot lt may nesuh ln scveru civll and cdmin.l pcnaltlct,and wlll bc prosacutcd to th. maximum.xtont po.slble
under the law. This document was produced by Oider No. 8449633179 shicfi expires on 12J2U2019' and is
not for resale.
U3cr Not s:
lnit.
AIA softrare at 11 :07:46 MT on 1217f2018 under
(3B9ADA61 )
7
Meridian City Council Meeting Agenda January 2, 2019 – Page 301 of 576
ARTICLE 7 TERMINATION OR SUSPENSION
$ 7.1 Where the Contrac{ Sum is a Stipulated Sum
$ 7.1.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document
4232-2009 as modified.
$ 7.1.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A232-2O09 as
modified.
I garagraphs Deleted)
ARTICLE 8 MISCELLANEOUS PROVISIONS
$ 8.'l Where reference is made in this Agreement to a provision of AIA Document A232-2009 as modified or
another Contract Document, the reference refers to that provision as amended or supplemented by other provisions
of the Contract Documents.
$ 8,2 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated
below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is
located.
(Insert rate ofinterest agreed upon, fany)
I sls of lolo per month
$ 8.3 The Owner's representative:
(Name, address and other information)
Mike Barton, Parks Superintendent
City of Meridian
Parks and Recreation Department
33 East Broadway Avenue, Suite 206
Meridian, Idaho 83642
$ 8.4 The Contractor's representative:
(Name, address and other informalion)
Brian Fox
2520 N. 32, Boise, Idaho 83703
Telephone Number: 208-345-8606
Fax Number: 208 -3 45 -21 42
Mobile Number: 208-949-5464
Email Address: walkerfox69@gmail.com
$ 8.5 Neither the Owner's nor the Contractor's representative shall be changed without ten days written notice to the
other party.
AIA Document A132il - 2009 (torm.rly Al01ilCta - 1902). copyright O 1975, 1980, 1992 and 2009 by The American lnstitute ofArchitects. All right!
rrrcryed, WARNING: Thi3 A[A' Oocument is protacted by U.S. Copyrlght Law lnd lnt mdlonal TBadcr. Unluthortzcd ruproduc'tlon or dl.tdhnlon of
thir AIA' Documcnt, or anY Portion or lt mly Eault ln rcvcrc clvll end crlmlnal pcnaltlco,and will bc procccift.d to thc marlmum crtcril poaslblc
under th6 law. This document was poduced Order No. 84496331 79 which expires on 1A2812019' and is
not for resale.
U3er Notos:
lnit.
by AIA software at 1 1:07:46 MT on 1211712018 under
(3B9ADA61 )
8
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 302 of 576
$ 8.6 Other provisions
ARTICLE 9 ENUMERATION OF CONTRAGT DOCUTUIENTS
$ 9.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated in
the sections below.
$ 9.1.1 The Agreement is this executed AIA Document A132-2009 as modified, Standard Form of Agreement
Between Owner and Contractor, Construction Manager as Adviser Edition.
$ 9.1.2 The General Conditions are, AIA Document A232-2009 as modified, General Conditions of the Contract for
Construction, Construction Manager as Adviser Edition.
$ 9.1.3 The Supplementary and other Conditions of the Contract:
Document Title
Exhibit A Conffact Document Schedule
One
Two
Date
December 13,2018
Pages
I
$ 9.,l.4 The Specifications:
(Either list the Specifications here or refer to an exhibit attached to this Agreement.)
Title of Specifications exhibit: Contract Document Schedule, Exhibit A, dated December 13, 2018
I frttle Deteted)
$ 9.1.5 The Drawings:
(Either list the Drawings here or refer to an exhibit attached to this Agreement.)
Title of Drawings exhibit: Contract Document Schedule, Exhibit A, dated December 13, 2018
I gotle Deleted)
$ 9.1.6 The Addenda, if any:
Number Date Pages
December 3,2018
December 7,2018
8
2
lnit.
Portions of Addenda relating to bidding requirements are not part of the Contract Documents unless the bidding
requirements are also enumerated in this Article 9.
$ 9.1.7 Additional documents, if any, forming part of the Contract Documents are:
.1 AIA Document A132rL2009, Exhibit A, Determination of the Cost of the Work, if applicable.
.2 AIA Document E201rL2007, Digital Data Protocol Exhibit, if completed, or the following:
.3 AIA DocumentE202rL2008, Building Information Modeling Protocol Exhibit, if completed, or the
following:
.4 Other documents, if any, listed below:
AIA Documcnt A132r - 2OOg (formcrly A10l ilClle - 1992). Copyright @ 1975, 1980, 1992 and 2009 by Th€ American Institute of Architects. All rlghts
rtsclod. tryARNlNG: This A[Ab Documo]rt is protec-ted by U.S. Copyright Law and lntomational Traatles. Unauthorizad rcproduction or distribution of
this AlAo Document, or any porlion of it, may resuh ln severe civil and criminal p6naltios, and will be prosocutod to the maximum crtent possible
underthelaw.Thisdod/mentwasprcducedOylAsonrrareat11:07:46MTo 12n7nO18underOrderNo.8449633179whidrexpireson12J28//2019'andis
not for resale.
Urer Noter:(3B9ADA61 )
9
I
Meridian City Council Meeting Agenda January 2, 2019 – Page 303 of 576
(List here any additional documents which are intended to form part of the Contract Documents. AIA
Document.4232-2009 provides that bidding requirements such as advertisement or invitation to bid,
Instructions to Bidders, sample forms and the Contractor's bid are not part of the Contract
Documents unless enumerated in this Agreement. They should be listed here only if intended to be
part of the Contract Documents)
All binding documents including the Invitation to Bid, Instructions to Bidders, Supplemental
Instructions to Bidders, Bid Proposal Forms, and the Project Schedule are intended to be part of the
Contract Documents.
AIA Document A232-2009 General Conditions
Exhibit A, Contract Document Schedule
dated December 13, 2018
ARTICLE 10 INSURANCE AND BONDS
The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 11 of AIA Document
A232-2009 as modified
Refer to Supplemental Conditions modifying AIA Document A232-2009 for changes and additions to Article 11
"Insurance and Bonds ".
Contractor is required to provide 100% Payment and Performance Bonds.
(Table Deleted)
This Agreement is entered into as of the day and year first written above.
OWNERS' atur
Tammy , Ma or
1 amrn e6w-rd Ka Inc
(Printed a and title) i Ili
1�� Y!�--
CONTRACTOR(Signature)
Brian Fux, President
(Printed name and title)
AIA Document A132nA —2009 (formerly A101 r"CMa —1992). Copyright ®1975, 1980, 1992 and 2009 by The American Institute of Architects. All rights
Inst. reserved. WARNING: This AIA® Document Is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of 10
this AIAe Document, or any portion of It, may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent possible
t under the law. This document was produced by AIA software at 11:07:46 MT on 12/17/2018 under Osier No. 8449833179 which expires on 12128/2019, and is
not for resale.
User Notes: (3B9ADA61)
EXHIBIT A
CONTRACT DOCUMENT SCHEDULE
CITY OF MERIDIAN
DISCOVERY PARK SHOP BUILDING
2121 E. LAKE HAZEL ROAD
MERIDIAN, IDAHO 83642
KC PROJECT NO. 16-080
December 13,2018
PROJECT DOCUMENTS as issued by lnsight Architects and prepared by the following project
team
Architect - lnsight Architects
MEP Engineer - Musgrove Engineering, P.A.
Structural Engineer - Structural Edge
Civil/Landscape Architect - The Land Group, lnc.
Construction Manager - Kreizenbeck, LLC dba Kreizenbeck Constructors
ADDENDUMS
Addendum No. One dated December 3, 2018
Addendum No. Two dated December7,2018
PROJECT MANUAL
lnstructions to Bidders, Volume 1 of 1 Complete - dated November 09, 2018
DRAWINGS - Dated 11/19/2018
ARCHITECTURAL
A0.1 CoverSheetA3.1 Roof & RCP Plans
A5.1 Sections & Details
51.1 Structural Details & Notes
MECHANICAL
M0.0 Mechanical Cover SheetM1.0 Mechanical Plan
ELECTRICAL
E0.0 Electrical Cover Sheet
E0.2 Electrical SpecsE1.0 Electrical Plans
CIVIL FOR REFERENCE ONLY
C2.10 MaterialArea J
C2.30 Layout Area J
C2.57 Site Section / Details
C4.17 Grading Area L
A.2.1
A.4.1
A6.1
M0.1
M2.0
E0.1
E0.3
E2.0
Floor & FND Plans
Exterior Elevations
Door & Finish Schedules
Mechanical Specs
Mechanical Schedules & Details
Lighting Compliance Forms
Electrical Specs
Electrical Schedules
Material Area L
Layout Area L
Grading Area J
c2.17
c2.33
c4.10
Discovery Park Shop Building
Page 1 of 1
December 13,2018