Loading...
HomeMy WebLinkAbout JC Constructors, Inc WRRF Liquid Stream Capacity Change Order #8E ID Public IDAHO Works Department Moyor Tommy de Weerd Clty Ccrrndl llcrnbcrtr Keith Bird loe Borton Luhe Cquener Genesis Milom Anne Little Roberts Ty Folmer TO Keith Watts FROM:Dan Berthe, PE Staff Engineer II DATE:06n9n8 SUBJECT: WRRF LIQUID STREAM CAPACITY EXPANSION CHANGE ORDER #8 WITH JC CONSTRUCTORS INC. (JC) rOR A NOT TO EXCEED AMOUNT OF $105,572.33. I. DEPARTMENT CONTACT PERSONS Dan Berthe, Staff Engineer II Clint Dolsby, Assistant City Engineer Warren Stewart, City Engineer Dale Bolthouse, PW Director II. DESCRIPTION B. 489-0356 489-034t 489-0350 98s-1257 A.Background Council approved the construction phase of the Liquid Stream Capacity Expansion project in January of 2017. The project will allow the WRRF to meet future capacity demands as the City continues to grow, as well as complete part of the first phase of upgrades required to meet the new regulations set forth in our NPDES permit. Proposed Changes to Project Construction of the Liquid Stream Capacity Expansion project is currently underway. Additional funds are necessary to complete specified items. The additional work includes the coating of the fire sprinkler lines that will be located within the Chemical Building. Being that the fire sprinkler system is located within an area where they will be exposed to the acetic acid vapors, in order to help prolong the life of the material and reduce the maintenance costs in the future, JCC was asked for pricing to coat the sprinkler system lines. This cost is seen as an enhancement to the project. Page I of3 ( Meridian City Council Meeting Agenda November 7, 2018 – Page 271 of 520 The second component in the proposed change order is work associated with the layout, coordination and installation of seven variable frequency drives (VFDs) for the chemical feed pumps. The project design was based on the metering of pumps with integral speed controllers built into the pump units. The supplier submitted metering pumps with VFD speed control to the pump units in a separate, wall mounted panel enclosure. This separate panel was not rated for the space classification requirements of the chemical building pump room, so Watson-Marlow was required to resubmit with a pump that met the requirements. Their revised submittal, which met the classification requirements, included a $200,000 higher cost than the initial submittal. Numerous coordination efforts were conducted by all parties involved (COM, B&C, JCC, Challenger) to better identify an altemative that met design requirements, Operations requests/needs, and financial constraints of the project. Ultimately, JCC, Challenger, and WETCO (Challenger's panel builder/fabricator) arrived at a lower cost altemative which inlcluded mounting the VFDs in a modified PLC cabinet. The bulk of the CPR is for additional costs associated with the coordination and communication needed to resolve the issues regarding the VFD's, ultimately taking almost a year to complete. The third part of this proposed change is the installation of a coarse bubble diffuser within the secondary splitter box, as well as the installation of an additional eight diffusers on each drop leg within the mixed liquor channel. During the submittal process Sanitaire recommended eight additional diffusers per drop leg. This enhancement will allow Operations to reduce the amount of phosphorus, within the channel, via additional mixing. The fourth component of this change order work is for a change in material for the 20-inch internal mixed liquor return piping. The bid specifications allowed for numerous material options for this segment of work . JCC initially submitted shop drawings for the use of an epoxy lined and coated carbon steel pipe. City Operations staff had concerns over this due to the need for recoating every 7-10 years. Due to building constraints, the only viable options were to utilize the carbon steel or use a stainless steel material. After review of coating prices, it was estimated that the cost to recoat the carbon steel would end up higher than paying to change to the stainless steel pipe. The final component of the proposed change work includes the lowering of the overflow pipe within the stainless steel methanol tank. III. IMPACT A. Fiscal Impacts The project is under the WRRF Capacity Upgrades enhancement. The enhancement value is currently $44,479,699.00 for FY 15, 16, 17, 18, and 19. The enhancement value for FYl8 is $20,400,000. B. Project Costs: Fiscal Year 2017 Construction Contract Account Code / Codes 60-3590-961 s I Costs $10,750,000.00 Page 2 of 3Meridian City Council Meeting Agenda November 7, 2018 – Page 272 of 520 co #1 co #2 co #3 Fiscal Year 2018 Construction Contract co #4 co #5 co #6 co #7 co #8 Fiscal Year 20T9 Construction Contract C. Available Project Funding Fiscal Year FY]5 FY]6 FYI7 FYI8 FYI 9 60-3590-96151 60-3590-96151 60-3590-961 5 1 Total 60-3590-961 5 1 60-3590-961 s 1 60-3590-961 s I 60-3590-96 I 5 I 60-3s90-9615r 60-3590-961s1 Total 60-3s90-96 1 5 I $6,315,000.00 $6,315,000.00Total Total Construction Contract Cost $36,305,776.29 -$42,465.04 -$61,466.77 s94,514.57 $10,740,582.76 $18,500,000.00 $23,485.75 $57,707.03 $63,31 1.1 1 $500,117.31 $ 105,572.33 $19,250,193.53 Account Code / Codes 60-3590-96 I 5 1 60-3s90-96 I 5 1 60-3590-96 1 5 1 60-3590-96151 60-3s90-96 1 5 1 Total Funding $444,699.00 $2,900,000.00 $12,385,000.00 $20,400,000.00 $7,200,000.00 $43,329,699.00 D. Time Constraints In order to meet the requirements listed within the current NDPES permit, the Expansion Project must continue to move forward to meet the projected completion date. A delay in may alter that projected schedule. Departmental Approval Page 3 of 3 Meridian City Council Meeting Agenda November 7, 2018 – Page 273 of 520 ?){,,IAN CITY OF MERIDIAN Purchasing Department 33 E BROADWAY AVE, STE 106 MERIDIAN, ID 83642 TEL: (208) 489-0417 FAX: (208) 887-4813 @ CITY OF MERIDIAN Public Works Department \'UULiEt, rEU T--_- VENDOR JC Constructors 6t19t2018 IS BUDGET AMENDMENT REQUIRED? No CASE MANAGEMENT TICKET NO. DATE OF REQUEST AVAILABLE BUDGET AMOUNT $t .00 Purchase Requisition PURCHASE ORDER NUMBER MUST APPEAR ON ALL INVOICES. PACKING SLIPS CARTONS AND CORRESPONDENCE RELATED TO THIS ORDER PROJECT MANAGER Clint Dolsby/Dan Berthe TERMS NET FREIGHTTERMS PREPAID TIONDESTINA Dan Berthe PROJECT NAME: WRRF-Liquid Stream Capacitv Expansion-Construction P roiect CO #8 WRRF-Liquid Stream Capacity Expansion-Construction Proiect 1 $ 105,572.33 60 3590 96151 10601.D $ 105,572.33 $ $ $ $ $ $ $ $ $ AUTHORIZED COUNCIL SIcNATURE (if rcquired) NOTES: CouncilApprovalDate: $1 572.33 PART NUMBER / DESCRIPTION / COMMITMENT NAME / TASK ORDER / CONTRACT / PROJECT DESCR]PTION DEPT EXPENSE OR PRoJECT/ CODE GL ACCOUNT # COMMITMENT #FUND ACCOUNTING CODES QTY UNIT UNIT PRICE TOTAL AMOUNT Descri n of Purchase IDAHO ll Meridian City Council Meeting Agenda November 7, 2018 – Page 274 of 520 IAN CITY OF MERIDIAN 33 EAST BROADWAY IUERIDIAN, tD 83642 CHANGE ORDER CHANGE ORDER NO.8 PROJECT NO.10601.D CHANGE ORDER DATE:6t19t2018 EFFECTIVE DATE: CONTRACTOR JC Constructors lnc. PROJECT: WRRF Liquid Stream Capacity Expansion The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Description of additional work: (attach additional pages if needed) Please see attached sheet. WHO REQUESTED THE CHANGE City E Contractor WHY IS THE CHANGE NECESSARY Check all that apply tr Unforeseen / Hidden Conditions E Scope Change E Other - descibe belowf1 Error with the Plans and/or Specifications Explanation: This change order includes Change Proposal Requests (CPR) 48, 61 ,62,68, and 70. Please see attached sheet. REASON FOR CHANGE ORDER VS. BIDDING ADDITIONAL WORK Check all that apply E The work is in the area of the original contract and a conflict with the on-site contractor is probable and would make coordination of work difficult and bidding unreasonable. E time is of the essence and bidding would require the contractor to stop work and the City would face costly standby fees therefore making bidding disadvantageous D Emergency Work to correct unsafe conditions. tr Other - describe below ExplanatiOn: (attached additional pages if needed) Page 1 of 2 lllAkt) Meridian City Council Meeting Agenda November 7, 2018 – Page 275 of 520 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: $35,665,000.00 Original Contract Times: 896 days Net changes from previous Change Orders Net changes form previous Change Orders (calendar days) No. 1 to No. 7 No. 1 to No. 7 Nota charge «der rgmtam here $635,203.96 Nola change artier nueben hm 77 days Net Increase.(decrease} of this Change Owd'er:` . Net Increase (decrease) of this Change Order: .. �at.nara�) ,1;Q5572:33 .0. days . Total Change (Increase /decrease) to date: Total Days (Increase /decrease) to date: (calendardays) $740,776.29 77 days New Contract Price with all Approved Change Orders: New Contract Times with all Approved Change Orders: (calendar days) $36,305,776.29 973 days PROVED: (City Purchasing Manager) ACCEPTED: (Contractor) ?P-tM �[� y�J ----- By. Kelth Watts By. Date: Date: RECOMMENDED: (City Prole Manager) DATE APPROVED BY COUNCIL (If requked By: C)ry � ,J NO SIGNATURE REQUIRED Date: Y�`�tJ�llg DATE: METHOD OF COST DETERMINATION ! COST ANALYSIS OR VERIFICATION: Please see attached sheet Purchasing BudgetAvzd-W)le (Attach Report) Budget Information: Budget FY Ati�ettdment Date Submitted tD.Clerk for Agenda: Appmv4Date: Purchase Order No. Date Issued: Page 2 of 2 Change Proposal Requests (CPR) and Field Orderc CPR #48 Chemical Building - Fire Sprinkler Coating Description Summary: Work includes coating the fire sprinkler system pipe located within the Chemical Building. The coating will be Seaguard 6000. This coating is necessary to help prevent acetic acid vapors from oxidizing the pipe during tank filling. Reason for change: JCC raised a concern about coating the fire sprinkler lines in the Chemical Feed Building in RFI #202. Even though the acetic acid tank is fully vented to the atmosphere, external to the building, there is some potential over time that corrosion could occur on the fire sprinkler lines. This coating will help prevent against this. Cost Negotiation Process: JCC submitted CPR 48 to the City PM, City inspector, and B&C for their review and comment. Labor cost breakdowns and estimates on the coating provided to the reviewers. The proposed cost was found to be appropriate for the scope of work. The CPR was recommended by B&C and the costs were approved. Final Costs $5,493.79Days= 0 CPR #61 Chemical Metering Pumps VFD Panels Description Summary: Work includes the layout, coordination and installation of seven VFD panels for the chemical metering pumps. The VFD panel pricing was already included in the original project scope. This change covers the costs associated with labor spent by JCC and their subcontractor, Challenger, in coordinating the change in VFD classification and the assembly of the components in the field. Reason for change: The Watson-Marlow submittal for the chemical metering pumps differed from the design concept in that these pumps included separate VFD's for speed control instead of these being integral to the pump design. The VFD's are required to be located outside of the classified (Class I Div ll explosion proof requirements) space in the pump room or in an intrinsically safe enclosure. After the submittal came in, Brown & Caldwell researched other pump vendors, but were unable to find a style that met the flow demand requirements. BC also asked for a price from Watson Marlow to add an intrinsically safe enclosure to their scope and received a quote for more than $200,000 to include them. Following these initial inquiries, BC had several meetings with JCC and Operations to come up with other options including locating them on the building exterior and in the electrical room. Operations was not favorable to the building exterior option and there were space constraint challenges in the electrical room. Ultimately, Challenger and WETCO c€rme up with a solution to house the VFDs in their own panel, with the VFD HIM modules mounted on the PLC panel door. This was accepted by operations. Watson- Marlow is shipping this equipment loose and Challenger will assemble the components in the field per their plan with WETCO's supplied PLC. Cost Negotiation Process: JCC submitted CPR 61 to the City PM, City inspector, and B&C for their review and comment. Backup documentation was provided to the reviewers, that lays out the time and effort tied into coordinating the change in planned panel layouUdesign. The proposed cost was found to be appropriate for the scope of work and was recommened by BC. The CPR cost was approved. Final Cost= $27,433.36Days= 0 Meridian City Council Meeting Agenda November 7, 2018 – Page 277 of 520 CPR #62 - Secondary Splitter Box Coarse Bubble Diffuser Description Summary: lnstallation of a coarse bubble diffuser within the secondary splitter box immediately upstream of the baffle wall. Work also includes the installation of eight additional diffusers on each dropleg for a total of 24 additional diffusers. Reason for change: As part of the submittal, Sanitaire (diffuser and drop leg vendor) suggested adding an additional drop leg and more diffusers heads in the mixed liquor collection and secondary splitter box structures. Brown & Caldwell evaluated this from a process perspective and determined that it would be beneficial for channel mixing and preventing phosphorus release in the mixed liquor. Cost Negotiation Process: JCC submitted CPR 62 to the City PM, City inspector, and B&C for their review and comment. Breakdowns of labor costs, as well as material costs were provided. The proposed time and costs were reviewed and are considered to be in line with the standard for this type of work. The proposed cost was found to be appropriate and was recommended for approval by BC. The CPR costs was approved. Final Cost= $17,748.17 Days= 0 CPR #68 - 2O-inch ML Pipe Materials Description Summary: Work includes the construction of the 2O-inch Mixed liquor pipe, located within the Aeration Basins, in a 304L stainless steel schedule 55 pipe in lieu of the originally planned HDPE pipe. Reason for change: The original design included HPDE internal mixed liquor return piping in the aeration basins, however other pipe materials were listed as acceptable in the pipe specification. JCC bid an epoxy lined and coated carbon steel pipe material. There were concerns raised by operations and maintenance staff of having to re-coat this pipe (Brown & Caldwell estimated this would need to occur every 7-10 years). BC suggested going back to HDPE, however HDPE pipe prices have been a continuous problem on this project as they have increased dramatically since bid date and the pipe is difficult to get due to the Houston hurricane last summer impacting the resin production across the country. Also, the original design called for 20-inch DIPS HDPE (21.6-inch outer diameter), which would not fit in the 21-inch diameter holes JCC constructed in the basin baffle walls. BC agreed to entertain other pipe material options for these lines and looked at PVC (Cg0O/Schedule 4O/Schedule 80) and stainless steel. Unfortunately, the internal diameter of the PVC pipe options did not meet the flow hydraulics needed for these lines. Left with the coated carbon steel and stainless steel options, the preference was to go with stainless steel. The thought is that one re-coating of this pipe would likely be more than the incremental cost increase to change to stainless steel. JCC credited back the original bid price of the carbon steel pipe. Cost Negotiation Process: JCC submitted CPR 68 to the City PM, City inspector, and B&C for their review and comment. Breakdowns of labor costs, as well as material costs were provided. The proposed time and costs were reviewed and are considered to be in line with the standard for this type of work. The proposed cost was found to be appropriate and was recommended for approval by BC. The CPR costs was approved. Final Cost= $50,855.04 Davs=0 Meridian City Council Meeting Agenda November 7, 2018 – Page 278 of 520 CPR #70 - Stainless Stee! Methano! Tank Overflow Modifications Description Summary: Work includes lowering the overflow pipe within the Stainless Steel Methanol tank as the overflow pipe was in conflict with the floating roof. Reason for change: The methanol tank submittal had two original submittals - one for the tank and one for the internal floating cover (separate vendors). The initial internal floating cover submittal was rejected as it was not an acceptable material meeting the specification. The second submittal for the internal floating cover was approved, however at this point the tank had already been fabricated. When the floating cover arrived at the tank supplier for final fabrication, they realized the overflow pipe was in conflict with the floating cover. JCC was concerned about moving the overflow, as it reduced the volume of the tank. Brown & Caldwell evaluated the impact on tank filling requirements and determined the volume decrease was very minimal even at ultimate build-out conditions. Operations staff was acceptable to the change in volume as well. Cost Negotiation Process: JCC submitted CPR 70 to the City PM, City inspector, and B&C for their review and comment. Breakdowns of labor costs, as well as material costs were provided. The proposed time and material costs were reviewed and are considered to be appropriate for this type of work. The proposed cost was found to be appropriate and was recommended for approval by BC. The CPR costs was approved. Final Cost= $4,040.97Days= 0 Meridian City Council Meeting Agenda November 7, 2018 – Page 279 of 520 co #{ CPR #2 CPR #3 CPR #4 CPR #5 CPR #6 cPR #1 1 cPR #13 cPR #16 Dewatering Pipe Damage-Flood Chemical Building Roof Drain Lighting Change Vehicle Grounding 350 HP Aeration Blower Conduit 66" Dia. Pipe Material Credit AFFF Concentrate Line Material Screen to separate >3" cobble Eliminate Sub-Slab Waterproofing or Vapor Barrier / Dampproofing Water Bearing Tanks Discharge Elevation of Blower Building Drain Line Cap and Bulkhead for 66" SE Pipe for Future Tertiary Project Weather Delay $2,787.O1 $3,958.16 $0.00 $967.50 $3,1 02.90 -$58,290.00 -$750.00 $5,759.39 co#2 CPR #7 CPR #9 cPR#27 cPR #19 co #4 CPR #29A cPR #37 cPR #38 CPR #41C co #3 CPR #8 CPR #1OA CPR #124 cPR #24 cPR #28 Total= -$42,465.04 -$68,860.58 $0.00 $7,393.81 $0.00 Total= Total additional days= Total= CO Total Cost= Total= CO Total Cost= Total= CO Total Cost= Total= CO Total Cost= -$61,466.77 36 Cost $17,281 .30 $47,822.97 $9,706.79 $16,824.36 $2,879.1 5 Days AMS Fire Alarm Panel Gas Detector Galvanizing Screening Additional Week RASMAS Duct Bank Contaminated Soil Value Engineering Secondary Clarifier #7 Dewatering and SG Repair 7 10 3 $94,514.57 20 -$9,417.24 Cost $55,384.97 $22,923.13 -$83,600.00 $28,777.65 Days co #5 cPR #17 cPR #21 cPR#22 CPR#4.2 cPR #50 cPR #52 Primary Sludge Hatch Roof Curlcs Chemical Building Float Switches Blower VFDs RAS Transfer Subgrade Repair Drain Pump Guide Rail Assembly Rotameter Upgrade to Existing Non-Potable Water Lines SC7 Subgrade Delay Chemical Building Vapor Barrier Secondary Clarifier 6 Subgrade Repair RAS Transfer Station CMU Height $23,485.75 0 $14,068.51 Cost $3,578.46 $889.25 $27,107.94 $7,577.84 $1 I ,010.80 $7,542.74 Days $57,707.03 $71,77s.54 Cost $31,128.22 $12,726.31 $0.00 $13,446.38 $6,010.20 0 co #6 cPR #14 CPR #43E cPR #45 cPR #56 cPR #57 Days $63,311.1 1 $135,086.65 0 Meridian City Council Meeting Agenda November 7, 2018 – Page 280 of 520 co#7 cPR #30 cPR #46 cPR #58 co #8 cPR #48 cPR #61 cPR #62 cPR #68 cPR #70 Cost $57,432.3s $22,684.96 $420,000.00 Days 66-inch SE Modifications DO Probeffransmitter lnstalltion within Aeration Basins #6 and #8 Primary Power lmprovements Chemical Building - Fire Sprinkler Coating Chemical Metering Pumps VFD Panels Secondary Splitter Box Coarse Bubble Diffuser 20-inch ML Pipe Materials Stainless Steel Methanol Tank Overflow Modifications 21 Total CO Total Cost = Total CO Total Cost = $500,117.3'l 21 $635,203.96 Cost $5,493.79 $27,433.36 $17,748.17 $50,856.04 $4,040.97 Days $r05,572.33 $740,776.29 0 Meridian City Council Meeting Agenda November 7, 2018 – Page 281 of 520