Loading...
HomeMy WebLinkAboutChange Order for Tully ParkMERIDIAN CITY COUNCIL MEETING: JULY 21, 1998 APPLICANT: GARY SMITH ITEM NUMBER: 19 REQUEST: DEPARTMENT REPORTS — CHANGE ORDER NO.5 — TULLY PARK AGENCY COMMENTS CITY CLERK: CITY ENGINEER: CITY PLANNING DIRECTOR: CITY ATTORNEY: CITY POLICE DEPT: CITY FIRE DEPT: CITY BUILDING DEPT: MERIDIAN SCHOOL DISTRICT: MERIDIAN POST OFFICE: ADA COUNTY HIGHWAY DISTRICT: ADA COUNTY STREET NAME COMMITTEE: CENTRAL DISTRICT HEALTH: NAMPA MERIDIAN IRRIGATION: SETTLERS IRRIGATION: IDAHO POWER: US WEST: INTERMOUNTAIN GAS: BUREAU OF RECLAMATION: OTHER; SEE ATTACHED CONTRACT All Materials presented at public meetings shall become property of the City of Meridian. CONTRACT CHANGE ORDER DATE: CONTRACT FOR: Tully Park Improvements ORDER NO. 5 OWNER: CITY OF MERIDIAN IDAHO TO: BOISE PAVING & ASPHALT COMPANY INC (Contractor) You are hereby requested to comply with the following changes from the contract Dlans and'sdecifications- Description of Changes In This Change Order list separately) INCREASE in Contract Price DECREASE in Contract Price 1. Bid Item SP -MC -1 Q; Dugouts Enlarged $1,760.00 $612,899.00 2. Add Sterilization to Parkin Lot $350.00 Contract Price with all approved Change Orders: 3. 4. Sum of Increase and Decrease: $2,110.00 Net Change in Contract Price: $2,110.00 JUSTIFICATION (attach supplemental documents): 1) Four dugout slabs enlarged per the direction of Parks Department, 2) Sterilize parking lot to reduce future maintenance requirements. See attached documents for additional information. CHANGE IN CONTRACT PRlr.F- Original Contract Price: $634,747.72 Previous Change Orders No. 1 to No. 4 ($21,848.72) Contract Price prior to this Change Order: $612,899.00 Net (Increase/Decrease) of this Change Order: $2,110.00 Contract Price with all approved Change Orders: $615,009.00 t CHANGE IN CONTRACT TIME: 11J uuuu,1 iC, 1L wm uecome a supplement to the Uontract and all provisions will apply hereto. ACKNOWLEDGEMENT OF CHANGE ORDER LIMITS BY CONTRACTOR The increase or decrease in Contract price and/or Contract time stated in each and every Change Order shall unequivocally comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes ordered by the Change Order. By executing the change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and/or time adjustments represent full compensation for all increases or decreases in cost or the time required to perform the Contract as whole arising directly or indirectly from the Change Order, including costs and delays associated with the interruption of schedules, extended overheads, delay, and cumulative impacts or ripple effect on all other non -affected work under Contract not changed by the Change Order. Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract price and/or time, subject to the current scope of the entire work as set forth in the Contract Documents. Acceptance of this Change order constitutes an agreement between Owner and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR will waive all rights to file a claim of the Change Order after it is properly executed. All Change Orders shall include a written record, submitted by the CONTRACTOR, that states the basis of cost amount, including time and materials data, that enables the Owner to determine the necessity and reasonableness of the Change Order. RECOMMENDED: APPROVED: APPROVED: ENGINEER OWNER CONTRACTOR DATE: DATE: DATE: I BOISE IPAVING & ASPHALT CO. P.O. BOX 5814 • BOISE, IpAHO 83705 • PHONE (208) 342-6787 • FAX (208) 385-9390 July 14, 1998 ! Brad Watson City of Meridian 200 E, Carlton, Suite 100 Meridian, ID 83642 i RE! Tully Park Improvements As per your request, enclosed is a copy of Record Steel's additional, costs for the change with the dugouts. The total cost for the dugouts is $ 1,760.00, Also, as per our agreement regarding the sterilization of the parking lot, the cost is $ 350.00. Should you have any questions feel free to call. sincerely, David Nielsen JUL 14 '98 14 18 208 385 9390 PAGE.,02 P r� F May 13 1998 RECORD >- 1854 E. Lanark Street, Meddlan ID .183642 Boise Paving and Asphalt Co, P.O. Box 5814 Boise Id. 83705 I Attn: Dave Nelson Re: Tully Park Improvements Change Order Request #6 & CONSTRUCTION, INC. (208)887-1401 . Fax: (208)888-9130 Dave: As per your request I have estimated the additional cost associated with the design change on the dug out pits. RSCI respectively requests an additional $400.00 per dugout pit to furnish and install the concrete pads per the i ew design. This tabulates to atotal change of S1,60.00. I ;I Please call if you have any questions or comments. I . I Thank you, Rich Cotner RSCI S:1DATANS WOPMUOBS\JOB2SOZPCOi6,Doc I i Certified WBE. MBE, 8(a) 9.0 1D 12164 -MA -1-3 W 0032585 OR 68403 WA SECORSCO33QK JUL 14 '98 14:18 208 385 9390 PAGE.03 " INVOICE '. LEE'S SPRAY SERVICE 2151 Lase Deer Flat Road 019242 S z 4 , Kuna, Idaho 83634 Phone (;08) 888-5500 rlease Pay Off Involca q'hah - ou JUL 14 '98 14:18 208 385 9390 PAGE.04 MERIDIAN CITY COUNCIL MEETING: MAY 19, 1998 APPLICANT: DEPARTMENT REPORTS— GARY SMITH ITEM NUMBER: 12 REQUEST: CHANGE ORDER TULLY PARK AGENCY COMMENTS CITY CLERK: CITY ENGINEER: CITY PLANNING DIRECTOR: CITY ATTORNEY: CITY POLICE DEPT: CITY FIRE DEPT: CITY BUILDING DEPT: MERIDIAN SCHOOL DISTRICT: MERIDIAN POST OFFICE: ADA COUNTY HIGHWAY DISTRICT: ADA COUNTY STREET NAME COMMITTEE: CENTRAL DISTRICT HEALTH: NAMPA MERIDIAN IRRIGATION: SETTLERS IRRIGATION: IDAHO POWER: US WEST: INTERMOUNTAIN GAS: BUREAU OF RECLAMATION: OTHER: SEE ATTACHED CONTRACT All Materials presented at public meetings shall become property of the City of Meridian. interoffice MEMORANDUM t0: Gary Smith, PE cc: Councilman Rountree, Tom Kuntz, File from: Brad R. Watson, PE �GI/ re: Tully Park Improvements date: May 15, 1998 Attached are proposed Change Orders Nos. 1 - 4 for approval at next Tuesday's Council meeting. Also included is an updated project budget. As we discussed this morning, there will be a Change Order No. 5 for installing the 15" pipeline from the existing irrigation box to Five Mile Creek. We should have a firm price early next week. from the desk of... Brad R. Watson, P.E. Asst. City Engineer City of Meridian 33 East Idaho Ave. Meridian, Idaho 83642 (208) 887-2211 c:\bw\m4\budget update.51598.mem.dot Fax: (208) 887-1297 CONTRACT CHANGE ORDER DATE: CONTRACT FOR: Tully Park Improvements ORDER NO.: 1 OWNER: CITY OF MERIDIAN, IDAHO TO: BOISE PAVING & ASPHALT COMPANY INC. (Contractor) You are hereby requested to comply with the following changes from the contract plans and specifications - Description of Changes In INCREASE DECREASE This Change Order in Contract in Contract list separately) Price Price 1. Delete Item SP -MC -7, Bike Rack; 3 Ea. $3,750.00 $1,250.00 2. Delete Item SP -MC -8, Trash Can w/ $7,200.00 Enclosure; 8 Ea. $900.00 3. Item 604.07.03,15" PVC; Add 60 If @ $1,092.00 $18.20/If 4. New Item, Add Irrigation Line w/ 3 - 4" $1,096.98 Orchard Valve 5. Item SP -GI -2, 3' Irrigation Ditch; Delete $150.00 60 If $2.50/If Sum of Increase and Decrease: 1 $2,188.981 $11,100.00 Net Change in Contract Price: 1 -$8,911.02 JUSTIFICATION (attach supplemental documents): 1 & 2) Provide funds for other unexpected, required improvements (pump station). 3, 4 & 5) Change irrigation in front of Courtney property from open ditch to piped w/ valves for irrigating lawn. CHANGE IN CONTRACT PRICF- Original Contract Price: $634,747.72 Previous Change Orders No, to No. none Contract Price prior to this Change Order: $634,747.72 Net (tnsFease/Decrease) of this Change Order: ($8,911.02) Contract Price with all approved Change Orders: $625,836.70 CHANGE IN CONTRACT TIME: Original Contract Time: 120 days (begin 10/22/97) Previous Change Orders No. to No. none Contract Time prior to this Change Order: 120 days Net (Increase/Decrease) of this Change Order: -0- Contract Time with all approved Change Orders: 120 days New Contract End Date: 6/1/98 (incl. Winter suspension) This document will become a supplement to the Contract and all provisions will apply hereto. ACKNOWLEDGEMENT OF CHANGE ORDER LIMITS BY CONTRACTOR The increase or decrease in Contract price and/or Contract time stated in each and every Change Order shall unequivocally comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes ordered by the Change Order. By executing the change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and/or time adjustments represent full compensation for all increases or decreases in cost or the time required to perform the Contract as whole arising directly or indirectly from the Change Order, including costs and delays associated with the interruption of schedules, extended overheads, delay, and cumulative impacts or ripple effect on all other non -affected work under Contract not changed by the Change Order. Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract price and/or time, subject to the current scope of the entire work as set forth in the Contract Documents. Acceptance of this Change order constitutes an agreement between Owner and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR will waive all rights to file a claim of the Change Order after it is properly executed. All Change Orders shall include a written record, submitted by the CONTRACTOR, that states the basis of cost amount, including time and materials data, that enables the Owner to determine the necessity and reasonableness of the Change Order. RECOMMENDED: DATE: ENGINEER APPROVED: DATE: OWNER APPROVED: DATE: CONTRACTOR CONTRACT CHANGE ORDER DATE: CONTRACT FOR: Tully Park Improvements ORDER NO.: 2 (Fence) OWNER: CITY OF MERIDIAN, IDAHO TO: BOISE PAVING & ASPHALT COMPANY, INC. (Contractor) You are hereby requested to comply with the following changes from the contract plans and specifications: Description of Changes In This Change Order list separately) INCREASE in Contract Price DECREASE in Contract Price 1. Bid Item SP -MC -10; Delete 533 If of 4' chain link fence @ $5.47/lf Contract Price prior to this Change Order: $2,913.90 2. Add 354 If of 8' chain link fence @ $13.13/lf $4,647.50 Contract Price with all approved Change Orders: 3. Bid Item SP -MC -3; Delete 146 If of 6' chain link fence @ $8.85/lf $1,292.10 4. 5. Sum of Increase and Decrease: $4,647.50 $4,206.00 Net Change in Contract Price: $441.50 JUSTIFICATION (attach supplemental documents): For pedestrian safety reasons, it was recommended portions of the sideline fences for the softball fields be increased in height from 4' to 8'. A total of 533 If of 4' fence and 146 If of 6' fence (total = 679 If) will not be used for the baseball fields. The 146 If of 6' fence originally planned for the baseball fields will be placed along the south park boundary which, as a result, removes the same quantity from Bid Item SP -MC -3, 6' Chain Link Fence (original bid: 1468 If @ $8.85/I0. Supporting documentation attached. CHANGE IN CONTRACT PRICE: Original Contract Price: $634,747.72 Previous Change Orders No. 1 to No. 1 ($8,911.02) Contract Price prior to this Change Order: $625,836.70 Net (Increase/Deerease) of this Change Order: $441.50 Contract Price with all approved Change Orders: $626,278.20 CHANGE IN CONTRACT TIMP Original Contract Time: 120 days (begin 10/22/97 - suspended 12/19/97) Previous Change Orders No. 1 to No. 1 None Contract Time prior to this Change Order: 120 days Net (Increase/Decrease) of this Change Order: -0- Contract Time with all approved Change Orders: 120 days New Contract End Date: 6/24/98 (Resume 4/22/98 after Winter sus ension i nis aocument will become a supplement to the Contract and all provisions will apply hereto. ACKNOWLEDGEMENT OF CHANGE ORDER LIMITS BY CONTRACTOR The increase or decrease in Contract price and/or Contract time stated in each and every Change Order shall unequivocally comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes ordered by the Change Order. By executing the change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and/or time adjustments represent full compensation for all increases or decreases in cost or the time required to perform the Contract as whole arising directly or indirectly from the Change Order, including costs and delays associated with the interruption of schedules, extended overheads, delay, and cumulative impacts or ripple effect on all other non -affected work under Contract not changed by the Change Order. Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract price and/or time, subject to the current scope of the entire work as set forth in the Contract Documents. Acceptance of this Change order constitutes an agreement between Owner and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR will waive all rights to file a claim of the Change Order after it is properly executed. All Change Orders shall include a written record, submitted by the CONTRACTOR, that states the basis of cost amount, including time and materials data, that enables the Owner to determine the necessity and reasonableness of the Change Order. RECOMMENDED: APPROVED: APPROVED: ENGINEER OWNER CONTRACTOR DATE: DATE: DATE: CONTRACT CHANGE ORDER DATE: CONTRACT FOR: Tully Park Improvements ORDER NO.: 3 (Misc,) OWNER: CITY OF MERIDIAN, IDAHO TO: BOISE PAVING & ASPHALT COMPANY INC. (Contractor) You are hereby requested to comply with the following changes from the contract plans and specifications: Description of Changes In INCREASE DECREASE This Change Order in Contract in Contract list se aratel Price Price 1. Bid Item SP -MC -11; Delete remainder $15,470.00 of Bball courts (85%); excavation already done (15%). 2. Bid Item 707.02.01; Change parking lot $1,176.00 valley utters from 4' to 3'. 3. Bid Item 706.03.02; Delete 654 If $5,886.00 parking lot vertical curbing $9.00/If 4. Linder Road detached sidewalk to $7,532.80 accommodate power pole alignment. Sum of Increase and Decrease: $7,532.80 $22,532.00 Net Change in Contract Price: $14,999.20 JUSTIFICATION (attach supplemental documents): 1) Provide funds for pump station. 2) 4' valley gutter not required in parking lot as originally designed; 3' valley gutter adequate per design engineer. 3) Deleted per Parks Dept. request. 4) Detached sidewalk to avoid costs of re -aligning power poles along Linder Road. See attached documents for additional information, CHANGE IN CONTRACT PRICF- Original Contract Price: $634,747.72 Previous Change Orders No. 1 to No. 2 ($8,469.52) Contract Price prior to this Change Order: $626,278.20 Net (Increase/Decrease) of this Change Order: ($14,999.20) Contract Price with all approved Change Orders: $611,279.00 CHANGE IN CONTRACT TIME: Original Contract Time: 120 days (begin 10/22/97 - suspended 12/19/97) Previous Change Orders No. 1 to No. 2 None Contract Time prior to this Change Order: 120 days Net (Increase/Decrease) of this Change Order: -0- Contract Time with all approved Change Orders: 120 days New Contract End Date: 6/24/98 (Resume 4/22/98 after Winter suspension) This document will become a supplement to the Contract and all provisions will apply hereto. ACKNOWLEDGEMENT OF CHANGE ORDER LIMITS BY CONTRACTOR The increase or decrease in Contract price and/or Contract time stated in each and every Change Order shall unequivocally comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes ordered by the Change Order. By executing the change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and/or time adjustments represent full compensation for all increases or decreases in cost or the time required to perform the Contract as whole arising directly or indirectly from the Change Order, including costs and delays associated with the interruption of schedules, extended overheads, delay, and cumulative impacts or ripple effect on all other non -affected work under Contract not changed by the Change Order. Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract price and/or time, subject to the current scope of the entire work as set forth in the Contract Documents. Acceptance of this Change order constitutes an agreement between Owner and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR will waive all rights to file a claim of the Change Order after it is properly executed. All Change Orders shall include a written record, submitted by the CONTRACTOR, that states the basis of cost amount, including time and materials data, that enables the Owner to determine the necessity and reasonableness of the Change Order. RECOMMENDED: APPROVED: APPROVED: ENGINEER OWNER CONTRACTOR DATE: DATE: DATE: CONTRACT CHANGE ORDER DATE: CONTRACT FOR: Tully Park Improvements ORDER NO.: 4 (Building) OWNER: CITY OF MERIDIAN IDAHO TO: BOISE PAVING & ASPHALT COMPANY INC. (Contractor) You are hereby requested to comply with the following changes from the contract plans and specifications: Description of Changes In INCREASE DECREASE This Change Order in Contract in Contract list separately) Price Price 1. Bid Item SP -MC -9; Maintenance $186.47 building ventilation exhaust moved 2. Bid Item SP -MC -9; Add headers for $753.25 jack trusses to exterior partition 3. Bid Item SP -MC -9; Restroom door $96.00 frames switched after panic hardware not installable 4. Bid Item SP -MC -9; Change exterior $480.70 coating from paint to sealer. Sum of Increase and Decrease: $1,516.42 Net Change in Contract Price: $1,516.42 JUSTIFICATION (attach supplemental documents): 1) Electrical panel installation did not allow placement of the vent exhaust as shown on the Plans. 2) Headers to exterior partition wall to support jack trusses not shown on Plans. 3) Plans showed doors opening inward; frames were installed for this but had to be switched to allow use of the specified panic hardware. 4) Changed for aesthetic purposes. See attached documents for additional information. CHANGE IN CONTRACT PRICE: Original Contract Price: $634,747.72 Previous Change Orders No. 1 to No. 3 ($23,468.72) Contract Price prior to this Change Order: $611,279.00 Net (Increase/Decrease) of this Change Order: $1,516.42 Contract Price with all approved Change Orders: $612,795.42 CHANGE IN CONTRACT TIME: Original Contract Time: 120 days (begin 10/22/97 - suspended 12/19/97) Previous Change Orders No. 1 to No. 3 None Contract Time prior to this Change Order: 120 days Net (Increase/Decrease) of this Change Order: -0_ Contract Time with all approved Change Orders: 120 days New Contract End Date: 6/24/98 (Resume 4/22/98 after Winter sus ension This document will become a supplement to the Contract and all provisions will apply hereto. ACKNOWLEDGEMENT OF CHANGE ORDER LIMITS BY CONTRACTOR The increase or decrease in Contract price and/or Contract time stated in each and every Change Order shall unequivocally comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes ordered by the Change Order. By executing the change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and/or time adjustments represent full compensation for all increases or decreases in cost or the time required to perform the Contract as whole arising directly or indirectly from the Change Order, including costs and delays associated with the interruption of schedules, extended overheads, delay, and cumulative impacts or ripple effect on all other non -affected work under Contract not changed by the Change Order. Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract price and/or time, subject to the current scope of the entire work as set forth in the Contract Documents. Acceptance of this Change order constitutes an agreement between Owner and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR will waive all rights to file a claim of the Change Order after it is properly executed. All Change Orders shall include a written record, submitted by the CONTRACTOR, that states the basis of cost amount, including time and materials data, that enables the Owner to determine the necessity and reasonableness of the Change Order. RECOMMENDED: ENGINEER APPROVED: OWNER APPROVED: DATE: DATE: DATE: