HomeMy WebLinkAboutCC - ITD Plat Letter Comment
May 2, 2013
Michael Wardle
Director of Planning
Brighton Corporation
12601 W. Explorer, Suite 200
Boise, Idaho 83713 VIA EMAIL
Re: Bainbridge Subdivision – US 20-26 West of Meridian Road
The Idaho Transportation Department (ITD) has been asked to determine the needed right-of-
way for the Bainbridge Subdivision on US 20-26 (Chinden Boulevard) west of Meridian Road.
ITD has the following response.
ITD has a draft corridor plan for US 20-26. There are two different cross sections for the areas
east and west of Meridian Road. Your project is west of Meridian Road. The current thinking
identifies two alternatives:
A minimum of 70-ft half-width if the sidewalk, landscaping and lighting are outside the
ITD ROW.
A minimum of 100-ft half-width if any of the sidewalk, landscaping and lighting is
inside the ITD ROW.
ITD has a draft corridor plan for US 20-26. This is the planned cross-section for US 20-26
west of Meridian Road.
This is the planned cross-section for US 20-26 east of Meridian Road. This cross section (from
the corridor plan) shows the sidewalk within the right-of-way, but ITD practice has been
revised since the corridor plan was developed. Current practice is that the 70-ft half-width
only works if the sidewalk, landscaping and lighting are outside the ITD ROW.
Please note that this letter identifies only the current planning practice. The final design will be
based upon discussions with the City of Eagle and other issues.
We can also do a license agreement for landscaping in the right-of-way if that makes your site
look better.
If you have any questions, you may contact me at 334-8377.
Sincerely,
Dave Szplett
Development Services Manager
dave.szplett@itd.idaho.gov