HomeMy WebLinkAboutTask Order 10022.C to Brown and Caldwell for WRRF Facility Plan Update FY2017TASK ORDER NO. 1OO22.C Pursuant to the MASTER AGREEMENT FOR PROFESSIONAL SERVICES BETWEEN crry oF MERtDtAN (OWNER) AND BROWN AND CALDWELL (ENGTNEER) This Task order is made this 22"d day of November, 2016 and entered into by and between the city of Meridian, a municipal corporation organized under the laws of the State of ldaho, hereinafter referred to as "City", and accepted by BROWN AND CALDWELL hereinafter referred to covenant and conditions contained in above mentioned parties dated Octob is as follows: as "Engineer'' pursuant to the mutual promises, the Master Agreement (Category 24) between the er 1,2014. The Project Name for this Task Order The City of Meridian (City) is upgrading the Meridian Wastewater Resource Recovery Facility (wRRF) to increase the level of treatment to meet expected lower National Pollutant Discharge Elimination system (NPDES) permit limits for total phosphorus (Tp) and ammonia. ln order to properly plan for both short- and long-term improvements necessary to meet these NPDES permit requirements, the City is completing a Facility Plan Update to supplement their previous facility plan completed in 2012. This Facility Plan Update will also serve to prepare the necessary planning and alternative evaluation documentation needed for regulatory approval and will incorporate all portions required by ldaho Department of Environmental Quality. The Facility Plan Update will include the following tasks: Task 1 - Project Management Task2-FacilityPlan SCOPE OF WORK Task 1 Project Management Objective. To manage, administer, and provide ongoing coordination for utilization of resources for the project. This task includes technical and financial management of the contract and acting as liaison with the City, operational staff, and project team. Task Order 10022.C WRRF Facility Plan Update FY 2017 Brown and Caldwell WRRF Facility Plan Update FY 2017 PROJECT UNDERSTANDING Page '1 of 10 Approach. lvlajor activities include the following: All communication from the consultant regarding the project will include the city project manager (PM) or designee. The city pM will be responsible for coordinaiing andproviding all review comments and the resolution of all issues to the Enginee; in a timely manner (typically 14 calendar days for design review); all other deiisions will be provided to the Engineer within 7 calendar days or less. ihe Engineer pM will be responsible for drafting meeting minules. The Engineer will document any and all requested changes to the scope of work using a Project change Request form. The Engineer pM wili collaborate with the city pN/L to develop an approach for addressing the change(s). The city pM will review all changes for approval and provide the Engineer with written approval prior to modifying the existing scope, schedule, or budget and prior to proceeding with any new or unscoped work activities. Attend project kickoff meeting with City staff via conference call. Attend up to four coordination meetings with City staff via conference call. City Responsibilities. Provide the following: 1. ldentif ication of a PM with final authority for City decisions. Timely review of products and decisions on issues critical to scheduled progress. ldentif ication and involvement of appropriate City staff . coordination of collected comments and resolution of any conflicting comments from all City reviewers prior to returning to the Engineer. Deliverables. Deliverables for the tasks listed above include the following items: 1. Monthly progress reports and invoices 2. Meeting minutes, as required Task 2 Subtask 2.1 Facility Plan Ci'tv Workshops obiective. Present the progress made on the Facility Plan and review key decisions and recommendations with City staff. Approach. Major activities include the following: 1. Conduct up to eight workshops with City staff through the life of the proiect to communicate progress made on the Facility Plan Update, review pertinent key topics, and plan next steps. Each workshop is assumed to be 3 hours in duration. lt is assumed that all workshops will require the attendance at least one out-of-town BC team member. All workshops will have three BC team members in attendance. Document the workshops and provide a summary of action items to team members at the conclusion of each workshop. Task Order 10022.C WRRF Facility Plan Updale FY 2017 Bro$m and Caldwell Page 2 of 10 Deliverables. Workshop agendas, materials, minutes, and summary of action items. Subtask 2.2 lnvestioate Existino Wastewater Svstem Conditions objective. To present the current and currently planned (in design or construction) syslems for the Meridian WRRF, including capacity of each major unit process. Approach. Major activities include the following: 1. ldentify the existing City planning area. 2. Conduct a survey with Meridian staff of the existing facilities. lnclude in this: a. lncorporale results of the 2015 Process lnvestigations report on unit process capacities. b. lncorporate results of the 20 16 DAFT Stress Testing lnvestigation report on DAFT capacities. c. lncorporate current upgrades for headworks and liquid stream that are in design or construction for updating existing system capacity. d. lncorporale existing water reuse praclices e. Discuss existing environmental conditions in the planning areaf. lncorporate a discussion on the limitations of the existing outfall system to the Boise River. g. Description of current NPDES permit Review the last 5 years of historical influent flows, loads, and population in the City Review any planned flow reduction measures for the City, including: h. l&l reductions in the collection system i. Water conservation around the Cityj. Water conservation requirements for new and existing housing developments, commercial developments, and induslries within the City Related waler quality planning documentation, including: k. State water quality requirements for receiving waters in the service area l. Designated uses for receiving waters m. Water quality and technology based effluent limitations n. Current TMDL issues for the receiving waters as they relate to future NPDES permit limitations Related City water resources planning (if different trom ZO12 facility plan) Related air quality permits Deliverables. Chapter in the Facility Plan summarizing findings of this subtask. Page 3 of 10Task Order 10022.C WRRF Facility Plan Update FY 2017 Brown and Caldwell ask 2.3 Pl,nnt Crit Objective. ldentify the planning criterla for use in allernatives evaluation and capital improvements planning for the Facility plan. Approach. Major activities include the following: 1. use the population and ind_rrstry growth flow and loading projeclions developed as part of the current General Sewer plan project. 2. Develop projections for primary and secondary solids production based on flow and load projections from the General Sewer plan. 3. Develop projections for biogas production based on digestion technology and solids production projections. 4. Establish future discharge location to set planning for options analysis (Five Mile Creek, Boise River, Water Reuse, or some combination). ' Establish discharge criteria for NPDES discharge or reclaimed water permits for anticipated flows and loads, depending on point of final discharge. This work will incorporate the findings of the city's Reclaimed water Evaluation, 5ut it is anticipated that some component of the effluent will be discharged to one of the wRRF's cunent outfalls at all times (i.e. reclaimed water use will not account for 100 percent of theplant f low). Establish luture temperature permit limits Discuss potential future discharge criteria. a. Microconstiutents/Compounds of Emerging Concern b. Temperature TMDL Deliverables. Chapter on f uture conditions tor the Facility Plan. Subtask 2.4 Liquid and olids Treatment Analvsis objective. Evaluate alternalives for upgrading the Meridian WBRF to meet planning criteria requirements for both liquids and solids streams. Approach. Major activities include the following: 1. lncorporale findings of the 20 15 Alternatives Analysis project evaluating expansion alternatives for the liquid stream processes to meet future growth -and permit conditions. update as needed based on permit changes that have been made since the project was completed. 2. lncorporate findings of the 2016 sidestream p Removal Evaluation analysis and the 2016 AirPrex Pilot Study. 3. lncorporate findings of the 2015 Sidestream Nitrogen Removal Evaluation. 4. Provide a discussion and cost analysis (AACE class 5) Ior a secondary road access to the trealment facility from the North or West side of the facility. Evaluate solids-stream discharge alternatives for the Meridian wRRF. Three potential discharge locations and material qualities will be evaluated as part of this work: landfill disposal, land application of Class B biosolids, and Class A biosolids. Task Order -1 0022 C WRRF Facilily Plan Updale FY 2017 page 4 of 10 Brown and Caldwell ldentify and evaluate required WRRF solids system improvements related to growth (i.e., capacity expansion) and repair and replacement projects. Evaluated options will relate to the final selected/recommended disposal option selected Do not provide an evaluation of standby power options for the facility, as this will be completed under a separate project. Provide planning level (AACE Class 5) cost estimate for alternatives idenlified for the solids system expansions. These costs will consider regulatory and growth related projects, which will have been identified lhrough the tasks noted above. Provide costs for liquid process expansion based on the cunent Headworks and Liquid Process Expansion design projects. Provide rough site plan showing plant layout for recommended alternatives. site plans will not be done in CAD. Recommend an alternative based on cost evaluation and input from the City. For the final selected expansion alternative for the facility (both solids and liquids): a. ldentify any site security limitations/requirements. b. ldentify f uture aesthetic needs for the facility (odor control, noise control, traffic control on and off site). c. Provide a staffing and organization evaluation, including future needs for staffing, organization of the utility, and projected costs of O&M for the expansion option- d. Provide an evalualion of non-treatment process needs, including administrative office space, lab space, maintenance space, and equipment storage space. e. lncorporating findings of other City studies inlo utility systems. These would include non-potable water, gas, communications and electrical systems within the site. Deliverables. Report chapters for discussion of alternatives and recommendation for expansion to be incorporated into the Facility Plan report. Subtask 2.5 Other Related Evaluations Objective. Provide an evaluation for resource recovery options and options for potential future permit limits not in the current permit. Approach. Major activities include the following: 1. Resource Recovery Study - this study will provide a discussion on various options for resource recovery, including phosphorus recovery, nitrogen recovery, reclaimed water uses, biosolids recovery for beneficial reuse and biogas recovery and reuse. These evaluations will not include any cost analysis and will be limited to potential options discussion and reservation of plant footprint for future implementation as desired by the City. The more detailed evaluations will include: a. Phosphorus recovery: a summary of the Sidestream P removal report and recommendations, as well as the findings of the AirPrex Pilot from 2016 and the previous Ostara pilot. Task Order 10022.C WRRF Facility Plan Updale FY 2017 Brown and Caldwell Page 5 of 10 b. Nitrogen recovery: a summary of recovery options for nitrogen/ammonia from sidestream treatment. c. Reclaimed water uses: a summary of the findings of the City's Future of Reclaimed Water study d. Biosoids Recovery for Beneficial Use: provide a discussion of options and rough sizing of established and innovative technologies that produce Class A solids or convert sludge to energy sources other than biogas. e. Biogas Beneficial Use: Provide discussion of options and rough sizing of established and innovative technologies for biogas use. i. Contact ldaho Power to discuss options for funding Provide a discussion of options and rough sizing of systems required to meet potential future microconstituenls limits, but no costing associated with this. Provide sutficient site space for future addition of these processes, as needed by the City. Provide a discussion of options and rough sizing of syslems required to meet potential fulure temperature TMDLs, but no costing associated with this. Provide sufficient site space for future addition of these processes, as needed by the City. Deliverables. Report section for discussion of alternatives to be incorporated into the Facility plan report. Subtask 2.6 CIP objective' Prepare a capital lmprovements plan (clp) for the Meridian WRRF thatprovides a clear outline of the regulatory-required projects between 201 9 and 2o3g (including estimated cost and approximate year for initiation of each project. lt is assumed the city will complete their own financial options evaluation for iunding of projects. Approach. Major activities include the following: r. Based on lhe recommendations from subtask 4, assess the delivery methods for project delivery for projects identified to support the selected alternatrve. The delivery analysis will consider project grouping and potential delivery methods to meet regulatory, financial, and organizational constraints. Using updated flow and loading estimates, NpDES permit renewal conditions, capacily assessment, and alternalives evaluation outcomes, prepare a clp for the Meridian wRRF. This clP will include planning-level (AACE class 5) cost estimates for projects and an estimated project initiation date. Deliverables. Report chapter lo be incorporated into the Facility plan Report. Task Order 10022.C WRRF Facitity ptan Update Fy 2Ot 7 Brown and Caldwell Page 6 ol 10 objective. Prepare a comprehensive facilities plan document that summarizes lhe findings from the above tasks and provides a clear framework for improvements to the Meridian WRRF. Approach. Major activities include the following: 1. summarize activities from subtask 2 through Subtask 6, including a comprehensive clP that will include costs and schedule lor improvements, in a draft Facility plan. lt is assumed that the draft Facility Plan will require the synthesis of information from the previous tasks for presentation to the lDEe. The Facility plan will be reviewed by a senior reviewer prior to being submitted to the City. Prepare a final Facility Plan that provides a clear action plan for WRRF Upgrades. Prepare lor and lead up to two meetings with the city and the lDEe to discuss the findings of the Facility Plan and the city's intended action plan for expansion. lt is assumed that two members of BC team will attend each of these two hour meetings. At least one person from BC will be from out of town. Deliverables. 1. Agenda and meeting materials for up to two meetings with the lDEe to discuss the findings of the Facility Plan. Draft Meridian Facilities Plan to be submitted electronically to the city for one round of review and comment. Final Draft Meridian Facilitles Plan to be submitted electronically to the lDEe for one round of review and comment. Final version of Meridian Facilities Plan to be submitted in electronic and hardcopy format to the City and the IDEQ. Subtask 2.7 Facilitv Plan Development KEY P RSONNEL David Bergdolt dberodolt@b rwncald.com (208) 389-7701 Rick Kelly rkellv@brwn cald.com (206) 749-2327 David Bergdolt will perform the administrative funclion including all program, policy, and contractual issues. Rick Kelly will be responsible for coordrnation during the study phaie and oversee all lechnical and project managemenl activities associated with the task order scope ol work. Task Order 10022.C WRRF Facility plan Update Fy 2017 Brown and Caldwell Page 7 of 10 MAJOR ASSUMPTI ONS Note that work scope is conceptual in nature, based on limited information, and should only be relied upon for general planning purposes. Consultant will rely upon, without independent information, information from third parties, including available information related to reports related to key plant processes. Recommendations and potential energy savings are based upon many data points and assumptions. Many of these variables are affected by the influent characteristics, costs of electricity and natural gas, planning level construction estimates, and O&lVl costs. Final results will depend on the variables which should be considered and reconfirmed as part of any preliminary design of potential improvements. The evaluation will rely on the accuracy of record drawings and historical records provided by the City. lf drawings, data, or historical records are deemed to inaccurate, additional field effort may be required. BC will alert the City if expanded field effort is required over what was anticipated al the time the scope was prepared. Estimates of digester gas production, variability, and quality design criteria will be based upon current digester gas production rates reported by the City relative to volatile solids reduction (VSR), variability in gas production reported by the City and any gas quality data provided by the City. Should information from the City be unavailable, typical design values will be used. Final results will depend on the quality and quantity of the data available from the City, and should be reconfirmed as part of any preliminary design of potential improvements. Any permits (including air) and associated support beyond those identified may be considered as additional services. The opinions of probable construction costs will be prepared to industry standards but will be subject to many influences including, but not limited to, price of labor and materials, schedule impacts, unknown or latent conditions of existing equipment or structures, and time or quality of performance by others. These types of issues are diflicult to forecast and are out of the control of BC and that actual costs may vary substantially from the estimates prepared by BC. BC is therefore unable to guarantee the accuracy of opinion of probable construclion costs beyond that of industry standards. The City will make available in a timely manner all drawings, records and site information obtained relative to the project, including topographical survey, and information related to any and all underground utilities, hazardous materials, easements, permits, geotechnical investigations, lab data, environmental surveys, etc. as necessary for completion of the work under the above detailed scope. The site does not have any environmental related concerns including contaminated soil, endangered species, etc. that would impact alternatives implementation or associated cost estimates. Environmental studies, including Phase 1 surveys or any other type of study/survey are not included as part of this 2 J b 7 4 5 8 I Page 8 ol 10 ASSUMPTIONS Task Order 10022.C WRRF Facility Plan Update FY 2017 Brown and Caldwell pro.ject scope. lf any regulatory agencies require additional studies be performed, they can be added as additional services, but may impact the overall project schedule. 'I 0. The initial effort is limited to the cost identif ied in the attached fee estimate. lf the effort to complete the identified tasks exceeds the estimate, the pM will coordinate with the City to identify areas we can limit our effort to the available budget. '1 1. Recommendations for future improvements that relate to specific nutrient reductions or other regulated requirements will be based upon our current understanding of requirements for future permits as provided by the City of Meridian. TIME OF COMPLETION ANd COMPENS ATION SCHEDULE The lollowing schedule is based on a Notice to Proceed (NTp) from the City by November 2016 and resulting in Final Design being completed by August 2017. A NTp issued on a different date will change the schedule accordingly. The Not-To-Exceed amount to complete all services listed above for this Task Order No. 10022.C is four hundred ninety seven thousand, seventy three dollars ($497,073.00). Any travel expense will be reimbursed, only if pre-approved by the Project Manager, and only per the City of Meridian Travel Policy. COMPENSATION AND COMPLETION SCHEDULE Task Descr!ption Compensation 1 Proiect Managemenl . 8t31t2017 $34,690.00 2 Facility Plan $462,383.00 2.1 Subtask 1 - Workshops (meeting minutes) .8131/2017 $41,449 Subtask 2 - Existing Conditions draft chapter . 3hO12017 $45,831 2.3 Subtask 3 - Planning Criteria draft chapter . 41712017 $58,018 2.4 Subtask 4 - Alternatives Analysis draft chapter . 6/30/2017 $209,354 2.5 Subtask 5 - Related Evaluations draft chapter . 712812017 45.934 Subtask 6 - CIP draft chapter .811'l/2017 $26,327 2.7 Subtask 7 - Facility Plan Development dratt report . A/1112017 $29,400 2.7.1 Subtask 7 - Facility Plan Development final report . 8/31/2017 $6,070 TASK ORDER TOTAL: $497,073.00 Task Order 10022.C WRRF Facilily Plan LJpdate FY 2017 Brown and Caldwell Page I of 10 Due Date . 8t31t2017 2.2 2.6 Reimbursable expenses will be paid at cost and only if pre -approved by the Project Manager. Any travel and/or reimbursables paid will be paid as part of the Not -To - Exceed Task Order Total per the Compensation and Completion Schedule above, CITY OF MERIDIAN _. OW AND CALDWELL BY: BY: TAMMY de W , MAYOR Dated: Approved by Council:— Attest: CJ C I s, Cl CLERK Purchasin Approv 1 BY:� KEIT A S, urchasing Manager City Project Manager Clint Dolsby Task Order 10022.0 WRRF Facility Plan Update FY 2017 Brown and Caldwell 7 DepartFiipfit App BY WAA�ENST�EAR�,Glty �Enginee�r� Dated:_ /I Page 10 of 10 CONTRACI CHECKTIST t.PROJECT INFORMATION Pu 5497,o79 Chan8e Order No tc Wo ctor/Consultant/DesiSn Engineer REQUESTING DEPARTMENT Brown & Caldwell Contract Amount: Project Name: Date Project Manager: Clint Dolsby .BUDGET INFORMATION (Proiect Manager to Completel t.Contract Type Fund: Depa.tment GLAccount Project Number: Wllthe project cross fiscalyears? 60 vesE ruo El Construction D Task Order El Professional Service E Equipment E Grant D tv.GRANT INFORMATION - to be completed only on Grant funded proiects waSe veriffcation 10 Days prior to bid due date N/A Grant fl Print, anach and amend bid by addendum (ifchanged)www.5arn.gov Print and attach oebarment Status (Federal Funded) N/A wage Determination Received N/A RFP / RFQ TASX ORDER Award based on Low Bid Hithest Ranked Vendor Selected (Bid Results Attached )ves E NoD (Ratings Atta€hed) Yes E No E Master Agreement Category Date MSA Roster Approved: 2a tol ll2ot4 TypicalAward Yes E No E lf no please state circumstances and conclusion: 7 day protest period ends: VI COI{TRACTOR / CONSULTANT REqUIRED INFORMATION Payment and Performance Bonds ReceilEd (Date) Builders Risk lns. Req'd: Yes E (onv .prlic.b.l. io. prcj.cte .bd. S10O),oO) lfyes, has policy been purchased? lnsurance Certificates Received (Date) Goodstanding Rating: N/A Corporalion Status sl3t/2ot7 v[.TASX ORDER SEIECTION (Project Manager to Complete] Reason consultant selected Check dll thot opply gr a2 E3 @4 Performaice on past projects E Quality of work E on time Qualified Pe6onnel Availability of personnel Localof personnel El on BudSet D Accuracy of Construction Ert Description of neSotiataon process and fee evaluation E.ter sup€ruiror .mc 10/1112016 v .AWARD INFORMATION Date Submitted to Clerk for ASenda November 17, 2016 ApprovalDate W85 subrnitted (ohry lor Pw co^stru.tion Poj.cte) NTP Date 10/6/2016 WRRF FACILITY PLAN UPDATE FY 2017 ls this a change order? ves E no E Budget Available (Pu rchasing attach report): ves El No ! FY Br-'dget: tY17 Enhancementr Yes E No E 3210 5s080 LOO22.C Print and anach the determrnation BASIS OF AWARD 8tD Expiration Date: NoE Rating: N/A &firatbn Date: slLll2016 8y: Oate lssued: t.PROJECT INFORMATION 5497,o7t ChanSe Ord€r No. c o Fa.ll Plan U nsultanVD€5i8n Englneer:Brown and caldwell Project Name Date:70l6/20L6 ls thls a chan8eorder? ves I ru E] REqUESTING DEPARTMENT Wastewater Resource ProJect Manager: Clint Dolsby BUDGET INFORMATION iI Man to Com t.Contract Type Fund: Department GLAccount Prorect Numben Eudget Avallable (Purchaslng attach report): v"' El No E FY Budget: 17 Enhancementr Y6 El no El 3270 LO022 Yet 60 Wllthe projed cross flscal yea rs? NoE Construction Task order Professlonal Servlce Equipment Grant tr E] tr trtr IV GRANT INFORMATION - to be completed only on Grant funded prolects Grant #WaEe oeteininatlon Recelved Wa& V€rlic.llon 10 Dayr prlor io bld due date oebarm.nt Statu3 (Fed.r.l runded) Prht 6nd Attach the determlnatlon Prin!, attach.nd am€nd bld by.dd.ndum {it.hrnscd)www.sam.gov Prlnt and attach BASIS OT AWARD BID RFP / RFq TASI( ORDER Award based on Low Bld Hlghert Ranked Vendor s.lected (8ld Results Attached)NoD!ENo I I(Ratln8s Atta ched) Y.t Master ASreement Category Date N4SA Ro,ter Approved: 2a TyplcalAwardY.'DoE If no plcase state clacumJtances and concluCon: 7 day protest perlod ends: VI CONINACTOR / CONSUI.TANT REQUIREO INFORMATION Paynent and Pertormanc€ Eondi Ra<llvad (Data)r Eullders Rhk lns. Req'd: Ycs D lott .DplL.b.h d pD,..i, .hd. S,"morOO) Explratlon Date:Corporatlon Status Explratlon Date Ratlng No!lf yes, has pollcy been purchated? lnsuranc€ ce.tlflcates Rec€lved (oate): CONTRACT CHECKLIST vlll.AWARD INFORMATION oate Submltted to Clerk for Agenda: Purchase Otder No.l Approvaloate 8yl Date lssued:WH5 subrnlfted {Oily tu. PW coinMtl@ tEj.dt) NTP Oate: Perform.nce on past projects E Quallty ofwork E on time Quallffed Personnel Avallablllty of personnel E1 tocalof rsonnel4 Reason Consultant Seleded Check o thdtopply El on Budget E Accuracy of Constructlon Est a2 trg O€rcdptlon of neSotlatlon process and fee €valuadoni Erown ard caldwell's scope of work for the faclllty plan update was reylewed lnt€rnally and compared to the lart fadllty plan comdeted for the Clty In 2012 by the team of CH2M HlLLand HgrR EnSl.eerln& lnc.5560,000. The current scope covered the elements r€qul.ed by the ldaho Department of Environmental Quallty tor a faclllty pla. and lncorporated requlrements from the recently adopted Publlc Works Tactlca I Plan. The fee of 5497,073 represents a savln recent work on the capaclty assessment (972,183), alternatlves evaluatlon (5236,234), and thelr famllla rlty from the lastfaclllty plan due to Erown and caldwell's th the p Contract Amount: 55080 RatlnSr _ IDSOS Viewing Business Entity Page I of3 IDAHO SECRETARY OF STATE Viewing Business Entity Lawerence Denney, Secretary of State I New Search ] [ Back to Summary ] I Get a certificate of existence for BROWN AND CALDWELL ] Monitor BROWN AND CALDWELL business filinost BROWN AND CALDWELL 201 NORTH CIVIC DRIVE SUITE 115 WALNUT CREEK, CA 94596 Type of Business: Status: State of Origin: Date of Origination/Authorization: Current Registered Agent: Organizational ID / Faling N umber: Number of Authorized Stock Shares: Date of Last Annual Report: Annual Report Due: Origina! Filing: Filed 30 Jul 1975 Amendments: Amendment Filed 30 Jul 1975 Amendment Filed 29 Oct 1975 Amendment Filed 23 Oct 1978 Amendment Filed 13 Nov L97A Amendment Filed 13 Nov L97A Amendment Filed 13 Nov 1978 Amendment Filed 13 Nov t97A Amendment Filed 13 Nov t978 CORPORATION, GENERAL BUSINESS GOODSTANDING 25 Oct 1988 CALIFORNIA 30 Jul 1975 C T CORPORATION SYSTEM 921 S ORCHARD ST STE G BOISE, ID 83705 c51813 16 Jun 2016 Jul 2077 I Helo lYe Print/View TIFF ] CERTIFICATE OF AUTHORITY I Help Me Print/View TIFF ] OTHER - RA OTHER - CHG RA MERGED WITH J. B. GILBERT AND ASSOCIATES NAME CHANGED TO BROWN AND CALDWELL STOCK CHANGE MERGED WITH CAMANCHE LAKE PARK MERGED WITH ].8. GILBERT AND ASSOCIATES STOCK CHANGE https://www.accessidaho.org/public/sos/corp/C5 I 8 I 3.html | 1t17 t2016