HomeMy WebLinkAboutCC - ACHD Staff Report 1 Little Creek Subdivision Development Services Department Project/File: Little Creek Subdivision / MPP16-0023/ H-2016-0076 This is an annexation, zoning, conditional use permit, and preliminary plat application to allow for the development of 51 four-plex lots consisting of 204 multi-family units and 3 common lots on 15.85 acres. The site is located at the southeast corner of Locust Grove Road and Wilson Lane in Meridian, Idaho. Lead Agency: City of Meridian Site address: 1470 N. Locust Grove Road Staff Approval: August 22, 2016 Applicant: David Alexander PO Box 7846 Boise, ID 83707 Representative: Scott Wonders JUB Engineers, Inc. 250 S. Beechwood Avenue, STE 201 Boise, ID 83709 Staff Contact: Mindy Wallace, AICP Phone: 387-6178 E-mail: mwallace@achdidaho.org A. Findings of Fact 1. Description of Application: The applicant is requesting approval of an annexation, zoning, conditional use permit, and preliminary plat application to allow for the development of 51 four-plex lots consisting of 204 multi-family units and 3 common lots on 15.85 acres. The site is located at the southeast corner of Locust Grove Road and Wilson Lane in Meridian, Idaho. The applicant’s proposal is consistent with the City of Meridian’s Future Land Use Map which called for High Density Residential. 2. Description of Adjacent Surrounding Area: Direction Land Use Zoning North General Commercial C-G South General Commercial C-G East High Density Residential R-40 West High Density Residential R-40 3. Site History: ACHD has not previously reviewed this site for a development application. 2 Little Creek Subdivision 4. Transit: Transit services are not available to serve this site. 5. New Center Lane Miles: The proposed development includes 0.0 centerline miles of new public road. 6. Impact Fees: There will be an impact fee that is assessed and due prior to issuance of any building permits. The assessed impact fee will be based on the impact fee ordinance that is in effect at that time. 7. Capital Improvements Plan (CIP)/ Integrated Five Year Work Plan (IFYWP): • The intersection of Locust Grove Road and Fairview Avenue is scheduled in the IFYWP to be widened to 7-lanes on the north leg, 7-lanes on the south, 9-lanes east, and 9-lanes on the west leg, and to be signalized. • Fairview Avenue is listed in the CIP for corridor preservation for future widening to 7-lanes from Meridian Road to Eagle Road between 2017 and 2021. • Locust Grove Road is listed in the CIP for to be widened to 5 lanes from Fairview Avenue to Ustick Road between 2017 and 2021. B. Traffic Findings for Consideration 1. Trip Generation: This development is estimated to generate 1,498 vehicle trips per day; 135 vehicle trips per hour in the PM peak hour, based on the traffic impact study. 2. Traffic Impact Study Thompson Engineers, Inc. prepared a traffic impact study for the proposed Little Creek Subdivision. Below is an executive summary of the findings as presented by Thompson Engineers, Inc. The following executive summary is not the opinion of ACHD staff. ACHD has reviewed the submitted traffic impact study for consistency with ACHD policies and practices, and may have additional requirements beyond what is noted in the summary. ACHD Staff comm ents on the submitted traffic impact study can be found below under staff comments. Executive Summary Introduction Thompson Engineers, Inc. has been retained to prepare a traffic impact study for the proposed Locust Grove Apartments in Meridian, Idaho. The project is located on Wilson Lane, east of Locust Grove Road. The purpose of this study is to evaluate the potential traffic impacts resulting from the project and make recommendations for mitigation of the impacts. The study is prepared in accordance with the requirements of the Ada County Highway District. Proposed Development The project is a residential development of approximately 120 apartments and 120 town home units. Study Area The area is anticipated to be Ada County, Idaho, including the City of Meridian. The primary impacts will be long Locust Grove Road. The study area will include the intersections of Locust Grove and Wilson Lane and Locust Grove Road and Fairview Avenue. Conclusions Below are the findings of this report: • Based on the trip generation methods recommended in the Trip Generation Manual, the site will generate 1,498 trips per day, of which 114 trips will occur during the AM peak hour and 135 trips during the PM peak hour. 3 Little Creek Subdivision • The site will access the transportation system via W ilson Lane. • The intersection of Locust Grove Road and Wilson Lane will operate at acceptable level of service under background and total traffic conditions in the build out year. The critical peak hour is in the PM. • The intersection of Fairview Avenue and Locust Grove Road is currently operating at poor level of service and will operate at unacceptable levels of service under background and total traffic conditions in the build out year. The critical peak hour is in the PM peak hour. A project for widening this intersection is included in the ACHD Five Year Capital Improvement Plan. Site traffic will compromise approximately 1% of the total traffic in the build out year. • Locust Grove Road is expected to operate at better than LOS D in the build out year based on ACHD policy for arterial roads. • The proposed site plan provides good circulation for vehicles on site. • The site approaches on Wilson Lane are in conformance with ACHD access standards. Turn lanes are not warranted. Staff Comments/Recommendations: ACHD’s Traffic Services and Planning Review staff has reviewed and generally agree with the findings and conclusions of the submitted traffic impact study. 3. Condition of Area Roadways Traffic Count is based on Vehicles per hour (VPH) * Acceptable level of service for a five-lane minor arterial is “D” (1,540 VPH). * Average Daily Traffic Count (VDT) Average daily traffic counts are based on ACHD’s most current traffic counts. • The average daily traffic count for Locust Grove Road south of Wilson Lane was 21,965 on 12/2/15. • The average daily traffic count for Wilson Lane east of Locust Grove Road was 625 on 12/2/15. C. Findings for Consideration 1. Site Access During ACHD’s review of the Little Creek Subdivision, the District’s Traffic Services staff noted on- going issues with the accessing Wilson Lane due to its proximity to the Locust Grove/Fairview intersection; approximately 400-feet south of the intersection. Locust Grove is marked for “Do not block intersection” at Wilson Lane, however, vehicles waiting at the Locust Grove/Fairview intersection stack south of Wilson Lane. This creates sight distance and stacking issues on Wilson Lane, as current residents have to wait to turn onto Locust Grove Road. This also creates issues for emergency services, who may be unable to access Wilson Lane in a timely manner due Roadway Frontage Functional Classification PM Peak Hour Traffic Count PM Peak Hour Level of Service Existing Plus Project Locust Grove Road 368-feet Minor Arterial 1,108 Better than “D” Better than “D” Wilson Lane 978-feet Local N/A N/A N/A 4 Little Creek Subdivision to the vehicle stacking on Locust Grove Road. With the addition of 204 multi-family units on one access point, Wilson Lane, these issues/concerns are exasperated. To provide easier access for the residents of the Little Creek Subdivision, additional access for emergency services, and to reduce stacking and delay at Wilson Lane, ACHD’s Traffic Services staff has recommended a modification of policy to allow a full access driveway on Locust Grove Road to serve the site. There is an existing driveway from the site onto Locust Grove Road located approximately 300-feet south of Wilson Lane and outside of the influence area of the Locust Grove/Fairview Avenue intersection. Staff recommends that this driveway be used to access the site, in addition to Wilson Lane. The driveway may be widened to a width of 36-feet. 2. Locust Grove Road a. Existing Conditions: Locust Grove Road is improved with 5-travel lanes, vertical curb, gutter, and 7-foot wide attached concrete sidewalks. There is 95-feet of right-of-way for Locust Grove Road (50-feet from centerline). b. Policy: Arterial Roadway Policy: District Policy 7205.2.1 states that the developer is responsible for improving all street frontages adjacent to the site regardless of whether or not access is taken to all of the adjacent streets. Master Street Map and Typology Policy: District Policy 7205.5 states that the design of improvements for arterials shall be in accordance with District standards, including the Master Street Map and Livable Streets Design Guide. The developer or engineer should contact the District before starting any design. Street Section and Right-of-Way Width Policy: District Policies 7205.2.1 & 7205.5.2 state that the standard 7-lane street section shall be 96-feet (back-of-curb to back-of-curb) within 120-feet of right-of-way. This width typically accommodates three travel lanes in each direction, a continuous raised or landscaped median with intermittent turn lanes, and safety shoulders. Street Section and Right-of-Way Width Policy: District Policies 7205.2.1 & 7205.5.2 state that the standard 5-lane street section shall be 72-feet (back-of-curb to back-of-curb) within 96-feet of right-of-way. This width typically accommodates two travel lanes in each direction, a continuous center left-turn lane, and bike lanes on a minor arterial and a safety shoulder on a principal arterial. Right-of-Way Dedication: District Policy 7205.2 states that The District will provide compensation for additional right-of-way dedicated beyond the existing right-of-way along arterials listed as impact fee eligible in the adopted Capital Improvements Plan using available impact fee revenue in the Impact Fee Service Area. No compensation will be provided for right-of-way on an arterial that is not listed as impact fee eligible in the Capital Improvements Plan. The District may acquire additional right-of-way beyond the site-related needs to preserve a corridor for future capacity improvements, as provided in Section 7300. Sidewalk Policy: District Policy 7205.5.7 requires a concrete sidewalk at least 5-feet wide to be constructed on both sides of all arterial streets. A parkway strip at least 6-feet wide between the back-of-curb and street edge of the sidewalk is required to provide increased safety and protection of pedestrians. Consult the District’s planter width policy if trees are to be placed within the parkway strip. Sidewalks constructed next to the back-of-curb shall be a minimum of 7-feet wide. Detached sidewalks are encouraged and should be parallel to the adjacent roadway. Meandering sidewalks are discouraged. 5 Little Creek Subdivision A permanent right-of-way easement shall be provided if public sidewalks are placed outside of the dedicated right-of-way. The easement shall encompass the entire area between the right- of-way line and 2-feet behind the back edge of the sidewalk. Sidewalks shall either be located wholly within the public right-of-way or wholly within an easement. Minor Improvements Policy: District Policy 7203.3 states that minor improvements to existing streets adjacent to a proposed development may be required. These improvements are to correct deficiencies or replace deteriorated facilities. Included are sidewalk construction or replacement; curb and gutter construction or replacement; replacement of unused driveways with curb, gutter and sidewalk; installation or reconstruction of pedestrian ramps; pavement repairs; signs; traffic control devices; and other similar items. ACHD Master Street Map: ACHD Policy Section 3111.1 requires the Master Street Map (MSM) guide the right-of-way acquisition, arterial street requirements, and specific roadway features required through development. This segment of Locust Grove Road is designated in the MSM as a Residential Arterial with 5-lanes and on-street bike lanes, a 72-foot street section within 98-feet of right-of-way. c. Applicant Proposal: The applicant hasn’t proposed any improvements to Locust Grove Road abutting the site. d. Staff Comments/Recommendations: Consistent with the Locust Grove/Fairview Avenue intersection project listed in ACHD’s IFYWP, the applicant should be required to dedicate additional right-of-way to total 59-feet from the centerline of Locust Grove Road abutting the site. The applicant should be required to replace and broken or deteriorated curb, gutter, or sidewalk on Locust Grove Road abutting the site. 3. Wilson Lane a. Existing Conditions: Wilson Lane is improved with 2-travel lanes and no curb, gutter or sidewalk abutting the site. Wilson Lane is improved with vertical curb, gutter, and a 5-foot wide attached concrete sidewalk across from the site and directly east of the site. There is 60-feet of right-of-way for Wilson Lane (30-feet from centerline). b. Policy: Commercial Roadway Policy: District Policy 7208.2.1 states that the developer is responsible for improving all commercial street frontages adjacent to the site regardless of whether or not access is taken to all of the adjacent streets. Street Section and Right-of-Way Policy: District Policy 7208.5 states that right-of-way widths for new commercial streets shall typically be 50 and 70-feet wide and that the standard street section will vary depending on the need for a center turn lane, bike lanes, volumes, percentage of truck traffic, and/or on-street parking. • A 36-foot street section (back-of-curb to back-of-curb) will typically accommodate two travel lanes and on-street parking. • A 40-foot street section (back-of-curb to back-of-curb) will typically accommodate two travel lanes and a center turn lane. • A 46-foot street section (back-of-curb to back-of-curb) will typically accommodate two travel lanes and a center turn lane and bike lanes. Sidewalk Policy: District Policy 7208.5.6 requires a concrete sidewalks at least 5-feet wide to be constructed on both sides of all commercial streets. If a separated sidewalk is proposed, a parkway strip at least 6-feet wide between the back-of-curb and street edge of the sidewalk is required to provide increased safety and protection of pedestrians. Consult the District’s planter width policy if trees are to be placed within the parkway strip. 6 Little Creek Subdivision A permanent right-of-way easement shall be provided if public sidewalks are placed outside of the dedicated right-of-way. The easement shall encompass the entire area between the right- of-way line and 2-feet behind the back edge of the sidewalk. Sidewalks shall either be located wholly within the public right-of-way or wholly within an easement.). c. Applicant’s Proposal: The applicant is proposing to complete Wilson Lane as a 40-foot street section with vertical curb, gutter, and a 5-foot wide attached concrete sidewalk abutting the site. d. Staff Comments/Recommendations: The applicant’s proposal meets District policy and should be approved, as proposed. 4. Driveways 4.1 Locust Grove Road a. Existing Conditions: There is one 30-foot wide driveway onto Locust Grove Road located approximately 300-feet south of Wilson Lane. b. Policy Access Points Policy: District Policy 7205.4.1 states that all access points associated with development applications shall be determined in accordance with the policies in this section and Section 7202. Access points shall be reviewed only for a development application that is being considered by the lead land use agency. Approved access points may be relocated and/or restricted in the future if the land use intensifies, changes, or the property redevelops. Access Policy: District policy 7205.4.6 states that direct access to minor arterials is typically prohibited. If a property has frontage on more than one street, access shall be taken from the street having the lesser functional classification. If it is necessary to take access to the higher classified street due to a lack of frontage, the minimum allowable spacing shall be based on Table 1a under District policy 7205.4.6, unless a waiver for the access point has been approved by the District Commission. Driveway Location Policy: District policy 7205.4.5 requires driveways located on minor arterial roadways from a signalized intersection with a single left turn lane shall be located a minimum of 330-feet from the nearest intersection for a right-in/right-out only driveway and a minimum of 660-feet from the intersection for a full-movement driveway. District policy 7205.4.5 requires driveways located on minor arterial roadways from a signalized intersection with a dual left turn lane shall be located a minimum of 330-feet from the nearest intersection for a right-in/right-out only driveway and a minimum of 710-feet from the intersection for a full-movement driveway. Successive Driveways: District policy 7205.4.6 Table 1a, requires driveways located on minor arterial roadways with a speed limit of 40 MPH to align or offset a minimum of 330-feet from any existing or proposed driveway. Driveway Width Policy: District policy 7205.4.8 restricts high-volume driveways (100 VTD or more) to a maximum width of 36-feet and low-volume driveways (less than 100 VTD) to a maximum width of 30-feet. Curb return type driveways with 30-foot radii will be required for high-volume driveways with 100 VTD or more. Curb return type driveways with 15-foot radii will be required for low-volume driveways with less than 100 VTD. Driveway Paving Policy: Graveled driveways abutting public streets create maintenance problems due to gravel being tracked onto the roadway. In accordance with District policy, 7205.4.8, the applicant should be required to pave the driveway its full width and at least 30- feet into the site beyond the edge of pavement of the roadway and install pavement tapers in accordance with Table 2 under District Policy 7205.4.8. 7 Little Creek Subdivision Cross Access Easements/Shared Access Policy: District Policy 7202.4.1 states that cross access utilizes a single vehicular connection that serves two or more adjoining lots or parcels so that the driver does not need to re-enter the public street system. c. Applicant’s Proposal: The applicant has proposed to close the existing driveway onto Locust Grove Road with vertical curb, gutter, and a 7-foot wide attached concrete sidewalk to match the improvements on either side. d. Staff Comments/Recommendations: As noted in Finding for Consideration 1 above the existing 30-foot wide driveway onto Locust Grove Road located approximately 300-feet south of Wilson Lane should remain as is. The driveway may be widened to a width of 36-feet. The driveway should be paved its full width beyond the edge of pavement of Locust Grove Road. 4.2 Wilson Lane a. Existing Conditions: There are no driveways onto from Wilson Lane from the site. b. Policy: Driveway Location Policy: District policy 7208.4.1 requires driveways located near intersections to be located a minimum of 75-feet (measured centerline-to-centerline) from the nearest street intersection. Successive Driveways: District Policy 7208.4.1 states that successive driveways away from an intersection shall have no minimum spacing requirements for access points along a local street, but the District does encourage shared access points where appropriate. Driveway Width Policy: District policy 7208.4.3 restricts commercial driveways to a maximum width of 40-feet. Most commercial driveways will be constructed as curb-cut type facilities. Driveway Paving Policy: Graveled driveways abutting public streets create maintenance problems due to gravel being tracked onto the roadway. In accordance with District policy, 7208.4.3, the applicant should be required to pave the driveway its full width and at least 30-feet into the site beyond the edge of pavement of the roadway. c. Applicant’s Proposal: The applicant is proposing to construct one 54-foot wide driveways onto Wilson Lane. The driveway proposed to have two 21-foot wide travel lanes and a 12-foot wide center landscape island. The driveway is proposed to be 840-feet east of Locust Grove Road (measured centerline to centerline). d. Staff Comments/Recommendations: The applicant’s proposal meets District policy, and should be approved, as proposed. To accommodate stacking at the Wilson Lane/Locust Grove intersection the applicant should be required to install “NO PARKING” signs on both sides of Wilson Lane from Locust Grove Road east 500-feet. The applicant should be required to pave the driveway it’s full width at least 30-feet into the site beyond the edge of pavement of Wilson Lane. 5. Tree Planters Tree Planter Policy: Tree Planter Policy: The District’s Tree Planter Policy prohibits all trees in planters less than 8-feet in width without the installation of root barriers. Class II trees may be allowed in planters with a minimum width of 8-feet, and Class I and Class III trees may be allowed in planters with a minimum width of 10-feet. 6. Landscaping Landscaping Policy: A license agreement is required for all landscaping proposed within ACHD right-of-way or easement areas. Trees shall be located no closer than 10-feet from all public storm drain facilities. Landscaping should be designed to eliminate site obstructions in the vision triangle at intersections. District Policy 5104.3.1 requires a 40-foot vision triangle and a 3-foot height restriction on all landscaping located at an uncontrolled intersection and a 50-foot offset 8 Little Creek Subdivision from stop signs. Landscape plans are required with the submittal of civil plans and must meet all District requirements prior to signature of the final plat and/or approval of the civil plans. 7. Other Access Locust Grove Road is classified as a minor arterial roadway. Direct lot access is prohibited to this roadway and should be noted on the final plat. D. Site Specific Conditions of Approval 1. Dedicate additional right-of-way to total 59-feet from the centerline of Locust Grove Road abutting the site. 2. Replace broken or deteriorated curb, gutter, or sidewalk on Locust Grove Road abutting the site. 3. Complete Wilson Lane as a 40-foot street section with vertical curb, gutter, and a 5-foot wide attached concrete sidewalk abutting the site, as proposed. 4. Maintain the existing 30-foot wide driveway onto Locust Grove Road located 300-feet south of Wilson Lane. Reconstruct the driveway as a curb return driveway with a 30-foot radii. Pave the driveway its full width at least 30-feet into the site beyond the edge of pavement of Locust Grove Road. This driveway may be widened to 36-feet in width. 5. Construct one 54-foot wide driveways onto Wilson Lane with two 21-foot wide travel lanes and a 12-foot wide center landscape island, located 840-feet east of Locust Grove Road, as proposed. Pave the driveway its full width at least 30-feet into the site beyond the edge of pavement of Wilson Lane. 6. Install “NO PARKING” signs on both sides of Wilson Lane from Locust Grove Road east 500- feet. 7. Payment of impacts fees are due prior to issuance of a building permit. 8. Comply with all Standard Conditions of Approval. E. Standard Conditions of Approval 1. All proposed irrigation facilities shall be located outside of the ACHD right-of -way (including all easements). Any existing irrigation facilities shall be relocated outside of the ACHD right- of-way (including all easements). 2. Private Utilities including sewer or water systems are prohibited from being located within the ACHD right-of-way. 3. In accordance with District policy, 7203.3, the applicant may be required to update any existing non-compliant pedestrian improvements abutting the site to meet current Americans with Disabilities Act (ADA) requirements. The applicant’s engineer should provide documentation of ADA compliance to District Development Review staff for review. 4. Replace any existing damaged curb, gutter and sidewalk and any that may be damaged during the construction of the proposed development. Contact Construction Services at 387-6280 (with file number) for details. 5. A license agreement and compliance with the District’s Tree Planter policy is required for all landscaping proposed within ACHD right-of-way or easement areas. 6. All utility relocation costs associated with improving street frontages abutting the site shall be borne by the developer. 7. It is the responsibility of the applicant to verify all existing utilities within the right-of-way. The applicant at no cost to ACHD shall repair existing utilities damaged by the applicant. 9 Little Creek Subdivision The applicant shall be required to call DIGLINE (1-811-342-1585) at least two full business days prior to breaking ground within ACHD right-of-way. The applicant shall contact ACHD Traffic Operations 387-6190 in the event any ACHD conduits (spare or filled) are compromised during any phase of construction. 8. Utility street cuts in pavement less than five years old are not allowed unless approved in writing by the District. Contact the District’s Utility Coordinator at 387-6258 (with file numbers) for details. 9. All design and construction shall be in accordance with the ACHD Policy Manual, ISPWC Standards and approved supplements, Construction Services procedures and all applicable ACHD Standards unless specifically waived herein. An engineer registered in the State of Idaho shall prepare and certify all improvement plans. 10. Construction, use and property development shall be in conformance with all applicable requirements of ACHD prior to District approval for occupancy. 11. No change in the terms and conditions of this approval shall be valid unless they are in writing and signed by the applicant or the applicant’s authorized representative and an authorized representative of ACHD. The burden shall be upon the applicant to obtain written confirmation of any change from ACHD. 12. If the site plan or use should change in the future, ACHD Planning Review will review the site plan and may require additional improvements to the transportation system at that time. Any change in the planned use of the property which is the subject of this application, shall require the applicant to comply with ACHD Policy and Standard Conditions of Approval in place at that time unless a waiver/variance of the requirements or other legal relief is granted by the ACHD Commission. F. Conclusions of Law 1. The proposed site plan is approved, if all of the Site Specific and Standard Conditions of Approval are satisfied. 2. ACHD requirements are intended to assure that the proposed use/development will not place an undue burden on the existing vehicular transportation system within the vicinity impacted by the proposed development. G. Attachments 1. Vicinity Map 2. Site Plan 3. Utility Coordinating Council 4. Development Process Checklist 5. Request for Reconsideration Guidelines 10 Little Creek Subdivision VICINITY MAP 11 Little Creek Subdivision SITE PLAN 12 Little Creek Subdivision Ada County Utility Coordinating Council Developer/Local Improvement District Right of Way Improvements Guideline Request Purpose: To develop the necessary avenue for proper notification to utilities of local highway and road improvements, to help the utilities in budgeting and to clarify the already existing process. 1) Notification: Within five (5) working days upon notification of required right of way improvements by Highway entities, developers shall provide written notification to the affected utility owners and the Ada County Utility Coordinating Council (UCC). Notification shall include but not be limited to, project limits, scope of roadway improvements/project, anticipated construction dates, and any portions critical to the right of way improvements and coordination of utilities. 2) Plan Review: The developer shall provide the highway entities and all utility owners with preliminary project plans and schedule a plan review conference. Depending on the scale of utility improvements, a plan review conference may not be necessary, as determined by the utility owners. Conference notification shall also be sent to the UCC. During the review meeting the developer shall notify utilities of the status of right of way/easement acquisition necessary for their project. At the plan review conference each company shall have the right to appeal, adjust and/or negotiate with the developer on its own behalf. Each utility shall provide the developer with a letter of review indicating the costs and time required for relocation of its facilities. Said letter of review is to be provided within thirty calendar days after the date of the plan review conference. 3) Revisions: The developer is responsible to provide utilities with any revisions to preliminary plans. Utilities may request an updated plan review meeting if revisions are made in the preliminary plans which affect the utility relocation requirements. Utilities shall have thirty days after receiving the revisions to review and comment thereon. 4) Final Notification: The developer will provide highway entities, utility owners and the UCC with final notification of its intent to proceed with right of way improvements and include the anticipated date work will commence. This notification shall indicate that the work to be performed shall be pursuant to final approved plans by the highway entity. The developer shall schedule a preconstruction meeting prior to right of way improvements. Utility relocation activity shall be completed within the times established during the preconstruction meeting, unless otherwise agreed upon. Notification to the Ada County UCC can be sent to: 50 S. Cole Rd. Boise 83707, or Visit iducc.com for e-mail notification information. 13 Little Creek Subdivision Development Process Checklist Items Completed to Date: Submit a development application to a City or to Ada County The City or the County will transmit the development application to ACHD The ACHD Planning Review Section will receive the development application to review The Planning Review Section will do one of the following: Send a “No Review” letter to the applicant stating that there are no site specific conditions of approval at this time. Write a Staff Level report analyzing the impacts of the development on the transportation system and evaluating the proposal for its conformance to District Policy. Write a Commission Level report analyzing the impacts of the development on the transportation system and evaluating the proposal for its conformance to District Policy. Items to be completed by Applicant: For ALL development applications, including those receiving a “No Review” letter: • The applicant should submit one set of engineered plans directly to ACHD for review by the Development Review Section for plan review and assessment of impact fees. (Note: if there are no site improvements required by ACHD, then architectural plans may be submitted for purposes of impact fee assessment.) • The applicant is required to get a permit from Construction Services (ACHD) for ANY work in the right-of- way, including, but not limited to, driveway approaches, street improvements and utility cuts. Pay Impact Fees prior to issuance of building permit. Impact fees cannot be paid prior to plan review approval. DID YOU REMEMBER: Construction (Non-Subdivisions) Driveway or Property Approach(s) • Submit a “Driveway Approach Request” form to ACHD Construction (for approval by Development Services & Traffic Services). There is a one week turnaround for this approval. Working in the ACHD Right-of-Way • Four business days prior to starting work have a bonded contractor submit a “Temporary Highway Use Permit Application” to ACHD Construction – Permits along with: a) Traffic Control Plan b) An Erosion & Sediment Control Narrative & Plat, done by a Certified Plan Designer, if trench is >50’ or you are placing >600 sf of concrete or asphalt. Construction (Subdivisions) Sediment & Erosion Submittal • At least one week prior to setting up a Pre-Construction Meeting an Erosion & Sediment Control Narrative & Plan, done by a Certified Plan Designer, must be turned into ACHD Construction to be reviewed and approved by the ACHD Stormwater Section. Idaho Power Company • Vic Steelman at Idaho Power must have his IPCO approved set of subdivision utility plans prior to Pre-Con being scheduled. Final Approval from Development Services is required prior to scheduling a Pre-Con. 14 Little Creek Subdivision Request for Appeal of Staff Decision 1. Appeal of Staff Decision: The Commission shall hear and decide appeals by an applicant of the final decision made by the Development Services Manager when it is alleged that the Development Services Manager did not properly apply this section 7101.6, did not consider all of the relevant facts presented, made an error of fact or law, abused discretion or acted arbitrarily and capriciously in the interpretation or enforcement of the ACHD Policy Manual. a. Filing Fee: The Commission may, from time to time, set reasonable fees to be charged the applicant for the processing of appeals, to cover administrative costs. b. Initiation: An appeal is initiated by the filing of a written notice of appeal with the Secretary of Highway Systems, which must be filed within ten (10) working days from the date of the decision that is the subject of the appeal. The notice of appeal shall refer to the decision being appealed, identify the appellant by name, address and telephone number and state the grounds for the appeal. The grounds shall include a written summary of the provisions of the policy relevant to the appeal and/or the facts and law relied upon and shall include a written argument in support of the appeal. The Commission shall not consider a notice of appeal that does not comply with the provisions of this subsection. c. Time to Reply: The Development Services Manager shall have ten (10) working days from the date of the filing of the notice of appeal to reply to the notice of the appeal, and may during such time meet with the appellant to discuss the matter, and may also consider and/or modify the decision that is being appealed. A copy of the reply and any modifications to the decision being appealed will be provided to the appellant prior to the Commission hearing on the appeal. d. Notice of Hearing: Unless otherwise agreed to by the appellant, the hearing of the appeal will be noticed and scheduled on the Commission agenda at a regular meeting to be held within thirty (30) days following the delivery to the appellant of the Development Services Manager’s reply to the notice of appeal. A copy of the decision being appealed, the notice of appeal and the reply shall be delivered to the Commission at least one (1) week prior to the hearing. e. Action by Commission: Following the hearing, the Commission shall either affirm or reverse, in whole or part, or otherwise modify, amend or supplement the decision being appealed, as such action is adequately supported by the law and evidence presented at the hearing. 15 Little Creek Subdivision Request for Reconsideration of Commission Action 1. Request for Reconsideration of Commission Action: A Commissioner, a member of ACHD staff or any other person objecting to any final action taken by the Commission may request reconsideration of that action, provided the request is not for a reconsideration of an action previously requested to be reconsidered, an action whose provisions have been partly and materially carried out, or an action that has created a contractual relationship with third parties. a. Only a Commission member who voted with the prevailing side can move for reconsideration, but the motion may be seconded by any Commissioner and is voted on by all Commissioners present. If a motion to reconsider is made and seconded it is subject to a motion to postpone to a certain time. b. The request must be in writing and delivered to the Secretary of the Highway District no later than 3:00 p.m. on the day prior to the Commission’s next scheduled regular meeting following the meeting at which the action to be reconsidered was taken. Upon receipt of the request, the Secretary shall cause the same to be placed on the agenda for that next scheduled regular Commission meeting. c. The request for reconsideration must be supported by written documentation setting forth new facts and information not presented at the earlier meeting, or a changed situation that has developed since the taking of the earlier vote, or information establishing an error of fact or law in the earlier action. The request may also be supported by oral testimony at the meeting. d. If a motion to reconsider passes, the effect is the original matter is in the exact position it occupied the moment before it was voted on originally. It will normally be returned to ACHD staff for further review. The Commission may set the date of the meeting at which the matter is to be returned. The Commission shall only take action on the original matter at a meeting where the agenda notice so provides. e. At the meeting where the original matter is again on the agenda for Commission action, interested persons and ACHD staff may present such written and oral testimony as the President of the Commission determines to be appropriate, and the Commission may take any action the majority of the Commission deems advisable. f. If a motion to reconsider passes, the applicant may be charged a reasonable fee, to cover administrative costs, as established by the Commission.