HomeMy WebLinkAboutChange Order No 2 with Brown and Caldwell for WRRF Capacity ExpansionE 1DrA�
BbAlt6
CITY OF MERIDIAN
TASK ORDER AMENDMENT No 2
BROWN AND CALDWELL
For
WRRF CAPACITY EXPANSION DESIGN FY16 - PROJECT NO. 10601.A
CONTRACTOR NAME:
DEPARTMENT NAME:
Brown and Caldwell
Public Works:
ADDRESS:
ADDRESS:
950 West Bannock Street, Suite 350
Boise, ID 63702
33 E. Broadway
Meridian, ID 83642
CURRENT CONTRACT INFORMATION:
Contract Name: WRRF CAPACITY EXPANSION p9,910N FY19 Prolect No. 10801.A
Previous Amendment Date: 90ober 7, 2019 Previous Amendments: 1
Current Contract Dates: START: October 7. 2016 COMPLETION: November 30.2015
Current Contract Amount (Inclusive of Previous Amendments to Date): $573.806.00
AMENDMENT TO EXERCISE OPTION TO RENEW
(Check at/ that Apply)
T Amendment to Contract Performance
X Amendment to Contract Dates
X Amendment to Contract Amount
_ Other. (Explain)
DESCRIPTION OF REASON FOR AMENDMENT: (Attach all relevant documentation detailing amendment):'
Continuation of existing task order services and addition of final design tusks for FY16.
NEW CONTRACT INFORMATION:
Amendment Date: January 12. 2016
New Contract Dates: START: January 7.2018 COMPLE ION: September 30.2018
Amount of Amendment Change $2.813.918.00
New Contract Amount (Inclusive of Previous Amendments to Date): $3.187.824.04
ALL OTHER TERMS AND CONDITIONS OF THE ORIGINAL CONTRACT AND PREVIOUS
AMENDMENTS REMAIN UNCHANGED AND IN FULL FORCE AND EFFECT.
CITY OF RiLI
F
sy
TAMMY de ERD, MAYOR
Dated: /jZ-jKP Uc cs
Attes : , City of
,1D,
a.. IGAll 0
JAYCEE ROLMAN, CLERK ISE-AL�
BROWN D LDWELL
BY: '_
MAOTHA S. KNOWLTON, VICE-PRESIDENT
Dated:Lq} R d1 L
--
Approved by City istontent
BY:
KEITKWATTS, PURCHASIN_117--
PW Department Authorization }� `t^,_
AMENDMENT NO. 2
to
TASK ORDER NO. 10601.A
WRRF CAPACITY EXPANSION
DESIGN FY15
This amendment continues the Scope of Work from the original Task Order. Tasks 300,
310, 330 and 340 continue and Tasks 203, 204, 205, 206, 207, 208, 209, 210, 220 and
320 are commenced.
The following table summarizes key assumptions for the major design disciplines:
Civil/Geotechnical
• Topographical survey information and base mapping will be obtained for the
design of new facilities in the "greenfield" area north and west of the existing
WRRF processing facilities.
• Existing topographical survey information and base mapping will be utilized for
the design modifications of existing facilities.
• Legal, easement, and plat surveys for the WRRF site will not be required.
• Civil site work plans will only be provided for areas of the site that involve
significant disturbance to existing grading.
• Site drawings will only be prepared for sectors in the plant where new facilities
are to be constructed.
• Landscaping plans will not be prepared.
• New access roadway work will be limited to the "greenfield" portion of the site. No
traffic analysis or traffic control design is required.
• The capacity of the existing stormwater collection and control facilities is
adequate to handle the new construction.
• The capacity of the existing fire protection system is adequate to handle the new
construction.
• The foundation design of new or modified facilities will be based on geotechnical
information obtained for this Project.
• In soils, foundation, groundwater, and other subsurface investigations, the actual
characteristics may vary significantly between successive test points and sample
intervals and at locations other than where observations, exploration, and
investigations have been made. Because of the inherent uncertainties in
subsurface evaluations, changed or unanticipated underground conditions may
occur that could affect the Project cost and/or execution. The conditions and
cost/execution effects are not the responsibility of Consultant.
• New groundwater pumping facilities are not required.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 1 of 13
Brown and Caldwell
Stru ctura I/Arch itectu r
al/Geotechnical
• Conventional spread foundations will be required for all new facilities. Over
excavation, preload, or piles will not be required.
• Underdrain systems and groundwater relief valves are limited to process tanks
that will be emptied for maintenance purposes. The underdrain systems will not
be operated when a process tank is in service..
• Building architecture (materials, construction) will be similar to existing structures.
• No landscape architect services will be required for this Project.
• No permanent cranes will be required.
• No retaining walls will be required.
Process/Mechanical Hydraulic profile for new liquid stream processes (from the headworks discharge
to tertiary treatment inlet) with hydraulic existing grade line values to be provided
by City.
• Design concerning "plant -wide" utility systems such as basin drainage, water and
in -plant waste collection/disposal will be limited to extension of and/or changes to
existing piping. No new structures or equipment will be needed.
• Corrosion control provisions not required for buried piping.
• Active cathodic protection not required for buried piping.
• Piping 3 inches in diameter and smaller will be field -routed.
• Contractor -designed pipe supports based upon a performance specification
• A building sprinkler system and hazardous condition monitoring are required for
only for Chemical Feed Building 2.
• No odor control.
Electrical An evaluation of the existing primary feed and standby power generation systems
will be provided during the PER/30 Percent Design phase, with a
recommendation of whether modification will be required during the Final Design
phase to incorporate the additional loads identified during the PER/30 Percent
Design phase.
• Utility coordination will be provided during the Final Design phase for any
modifications required to accommodate new loads.
• Fire detection/alarm design will be by the Contractor based on a performance
specification.
• PER/30 Percent Design phase documents will be limited to a basis of design TM,
discipline general drawings, site drawings identifying major electrical system tie-
ins/sources, and electrical load distribution.
• Discipline specifications will be provided during the Final Design phase only.
• A comprehensive power system study will be provided during the Final Design
phase. A report will be provided to the City documenting the fault analysis,
protective device study, arc flash evaluation, and a sample of recommended
signage.
• Code review will be limited to the City -adopted version of NFPA Sections 820
and 497.
• Public address system design or modification will not be included.
• Electrical document review will be provided by Consultant, prior to submittal to
the City.
• Contractor -designed conduit and cable tray supports will be based upon a
performance specification.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 2 of 13
Brown and Caldwell
Instrumentation &
Controls (I&C)
• I&C will match the existing system and components available during the Project.
• I&C will be similar in type and sophistication to what currently exists. Analog
elements and components will be used, and no significant modifications to
existing I&C equipment or systems will be needed. No significant modifications to
existing valve or gate operators and mechanical equipment or systems will be
needed.
• A design for modifying the existing programmable logic controller (PLC) -based
supervisory control and data acquisition system will be provided for the process
areas being modified. Significant modifications to existing I&C equipment or
systems will not be required.
• The City will provide "as -built" documentation of the existing process
instrumentation and control system. City -provided information will include, but not
be limited to, existing motor and control circuit diagrams, panel shop drawings,
process instrument information, and process control system software
documentation.
• The new instrumentation and control system will be based on the use of PLCs.
Plant status monitoring will be by the existing commercially available PC-based
software package: Wonderware, by Schneider Electric Software. Remote access
to plant components will not be provided.
• PERM Percent Design will include process & instrumentation diagrams (P&IDs),
completed to a level sufficient to identify the primary processes and process
equipment and extent of major modification of treatment process. P&IDs will be
completed during the Final Design phase.
• PERM Percent Design will include a Control System Block Diagram drawing
depicting the site's major network modifications. Final Design will update the
drawing to include all network modifications, in the Project -modified process
areas only.
• Discipline specifications will be provided during the Final Design phase only.
• The Basis of Design TM will be provided during the PERM Percent Design
phase, without modification during Final Design.
• Programming is excluded from this scope of work. This effort will be deferred to
the construction phase of this Project and will be based on the assumption that a
subcontractor will be hired by the City to perform this work during the
construction Project.
• Security system and video system design are excluded as part of this scope of
work.
• Vendor -supplied control system packages will be interfaced through hardwired
signals or networked signals, when available.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 3 of 13
Brown and Caldwell
Task Descriptions
Specific tasks to be performed by Consultant and City to implement the Phase A scope
of work are summarized in the work breakdown below and described in further detail on
the following pages.
Su
rt
200 Series Tasks: Final Design
The 200 Series tasks are for effort required to advance the design from the PER/30
Percent Design level to public bidding. This will be accomplished with two major
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 4 of 13
Brown and Caldwell
101 To o raphic Survey and Base Mapp
102 Geotechnical Investi ation and Repc
103 Architectural Prelimina Design
W104
Civil PreliminaryDesign
105 Structural Preliminary Design
M
106 Process -Mechanical Preliminary DeE
*
cl U
107 Building -Mechanical Preliminary Dei
108 Electrical Preliminary Design
uj
109 Instrumentation Prelimina Design
110 Document Pre aration
Q
203 Architectural Design
204 Civil Desi n
a)
U)
205 Structural Design
�C
206 Process -Mechanical Design
207 Building Mechanical Design
'
c
208 Electrical Design
LL
209 Instrumentation Desi n
210 Document Preparation
220 Bid Period Services
C:
300 Project Management
5 E .F o aa)
310 Coordination Meetin s
a) a) a> Q
o 0 0 C. i>
320 Permigin Assistance
a�
�- U)
330 Cost Estimatin and Schedulin
340 Quality Assurance/Quality Control Q
400 Series Submittals
Changes/RFIs
c
op
Q .°
Site Coordination/Progress Meetings
L
Field Inspections
CL
o c
Record Drawings
aa) U
O&M Manual Update
Start -Up Support Services
Proiect MananPmPnt
Su
rt
200 Series Tasks: Final Design
The 200 Series tasks are for effort required to advance the design from the PER/30
Percent Design level to public bidding. This will be accomplished with two major
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 4 of 13
Brown and Caldwell
milestone deliverables: Permit Set and Bid Set. After addressing comments from the
Permit Set submittal, a Bid Set will be developed and submitted to the City for public
bidding of the Project.
Specific assumptions that apply to all detailed design phases include the following:
• Decisions logged in the PERM Percent Design phase will be followed in the detailed final
design tasks. Decisions that are changed or altered drastically will be addressed by
amendment if necessary.
Task 203 — Architectural Design
Objective: To perform architectural design for the permit and bid set documents.
Activities/Approach: An architectural plan will be completed by using the services of an
architectural subconsultant. The architectural design will be based on the architectural
nature of the existing structures at the site. The Architectural subconsultant will directly
prepare all architectural drawings and specifications required to construct the
architectural treatment for the new Chemical Addition Facilities included in the Project.
City's Responsibilities: Review Permit Set.
Work Products: Architectural (A) drawings and specifications will be included with the
permit and bid set document submittals.
Task 204 — Civil Design
Objective: To design general and civil site design work for the permit and bid set
documents.
Activities/Approach: This task consists of all work necessary for completion of the
general, civil, and site design included in this Project. Civil drawings and specifications
will be based on "greenfield" topographic base mapping and as -built drawings of the
existing facilities and buried utilities, engineering calculations, and new/existing
background geotechnical information. This task also includes design of roads, site
excavation and grading, yard piping and utilities, drainage conveyance, and erosion
control.
City's Responsibilities:
Review Permit Set.
• Confirm site utility features through field locates or other methods where there is reasonable
expectation the base map drawings may require additional information or verification.
Work Products: General (G) and civil (C) drawings and specifications will be submitted
with the permit and bid set document submittals.
• General drawings will include title sheet and vicinity maps, drawing index, general symbols,
legends, and abbreviations, hydraulic profile, process flow diagram, and mass balance.
• Civil drawings will include site plan, site demolition plans, paving and grading plans, yard
piping plans, miscellaneous details, temporary erosion/sedimentation control details, and
various site plans and sections.
Task 205 — Structural Design
Objective: To provide structural design for the permit and bid set documents.
Activities/Approach: Structural drawings will be based on as -built drawings of the existing
facilities, structural calculations, and new/existing background geotechnical information
updated as part of the geotechnical investigations during preliminary design. The
controlling code will be the 2012 International Building Code with local amendments.
Structural drawings and specifications will be prepared for walls, footings, beams slabs,
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 5 of 13
Brown and Caldwell
structural steel, concrete reinforcement, anchor bolts, bracing, miscellaneous metals,
and other structural aspects of any new/existing facilities associated with the Project.
City's Responsibilities: Review Permit Set.
Work Products: This task includes structural analysis and calculations associated with
design of structures. Structural (S) drawings and specifications will be submitted with
the permit and bid set documents.
Task 206 — Process Mechanical Design
Objective: To provide process mechanical design for the permit and bid set documents.
Activities/Approach: This task consists of all work necessary for completion of the P&IDs
included in this Project. P&ID drawings will be based on as -built drawings of the existing
facilities, engineering calculations, and the characteristics of new process equipment
needed for this Project. This task also includes detailed process design, equipment
sizing and selection for each process area, process piping layout, and the preparation of
mechanical plan view, mechanical sections, and specifications.
City's Responsibilities:
Review Permit Set
• Provide all necessary shop drawings, submittals, records, sole source agreements, and
operation and maintenance information necessary to establish the facilities conditions that
the mechanical design is based on.
Work Products: P&ID (1) drawings and mechanical (M) drawings and specifications will be
submitted with the final and bid document submittals.
Task 207 — Building -Mechanical Design
Objective: To prepare building mechanical design for the permit and bid set documents.
Activities/Approach: This task includes the following:
• Finalizing the building mechanical design and equipment sizing/selection.
• Finalizing the building mechanical plans and sections.
• Incorporating all the necessary details into the contract drawings.
• Drafting and finalizing all necessary building mechanical specifications.
City's Responsibilities:
• Review Permit Set.
• Provide all necessary shop drawings, submittals, records, and operation and maintenance
information necessary to establish the facilities conditions that the building mechanical
design is based on.
Work Products:
• HVAC (H) drawings and plumbing/utility (U) drawings
• Assistance and contribution to process mechanical for the P&ID and mechanical drawings
• Permit and bid set document specifications
Task 208 — Electrical Design
Objective: Perform electrical design drawings for the permit and bid set documents.
Activities/Approach: The scope of this task consists of all work necessary to prepare all
electrical power improvements for the Project, including all raceway and cable
schedules, and control schematics with reference to I&C-specified process
instrumentation and control devices. Electrical design drawings will include plans, one -
line diagrams, lighting and receptacles plans, electrical conduit and conductor
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 6 of 13
Brown and Caldwell
schedules, and electrical construction details. Electrical plan drawings will show
equipment locations and associated cable or raceways and indicate equipment
connections as home -run type symbols with reference to which motor control center or
electrical panel that a cable is to be connected. Specific activities are as follows:
• Review the general and mechanical design requirements.
• Define hazardous areas in the Project buildings and sites.
• Determine primary power and standby power generation requirements, as needed.
• Prepare one -line diagrams for the plant distribution systems.
• Complete motor and control schematics for all electrical devices external to vendor -supplied
equipment.
• Complete a comprehensive power system study and develop a final report.
• Develop electrical specifications.
• Develop electrical drawings, including site plans, lighting protection plans, and building
plans.
• Develop raceway and cable and panel schedules.
City's Responsibilities:
• Review Permit Set.
• Supply current as -built drawings for all buried and exposed power supply cables, duct
banks, raceways, instrument cables, communication cabling, yard piping, process piping,
and structures at the plant.
Work Products:
• Analysis, studies, and calculations associated with design of electrical systems
• Electrical (E) drawings, specifications, and final reports will be submitted with the permit and
bid set document submittals
Task 209 — Instrumentation Design
Objective: To develop instrumentation and controls drawings and specifications for the
permit and bid set documents.
Activities/Approach: The scope of this task consists of all work necessary to develop the
instrumentation and controls construction documents for this Project. Design drawings
will include instrumentation system diagrams, control diagrams, loop diagrams, gas
monitoring systems, and 1/0 cabinets. Specific activities are as follows:
• Finalize P&IDs with process mechanical.
• Write narrative descriptions of control strategies and sequences.
• Specify sensors and instruments to be used and coordinate with electrical for hazardous
environments requirements.
• Complete drafting of instrumentation and control system drawings, including symbol and
detail sheets.
• Provide control system network diagrams.
• Develop specifications for control system hardware and software requirements.
• Provide specification coordination within electrical and mechanical equipment sections.
City's Responsibilities: Review Permit Set
Work Products
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 7 of 13
Brown and Caldwell
• Design drawings and specifications for providing instrumentation equipment and control
system modifications, as described above.
• Instrumentation (1) drawings and specifications will be submitted with the permit and bid set
document submittals.
Task 210 — Document Preparation
Objective: Prepare the Permit Set and the Bid Set.
Activities/Approach: Draft version of the drawings and specifications will be prepared and
submitted for the permit and bid set document submittals. All specifications will be
prepared in Microsoft Word. Consultant will prepare electronic copies (pdf half -sized
composite drawings) and one bound paper, camera-ready full-sized original of the
Project manual for internal distribution to the City and for public bidding. The City will be
responsible for advertising and bidding the Project manual.
City's Responsibilities:
Review permit and bid set document submittals.
• Coordinate interaction with IDEA for review of Permit Set.
Work Products:
• Drawings and specifications will be submitted with the permit and bid set document
submittals and will be included in the Project manual.
• Submit the Permit Set to IDEA for review. Address comments as part of preparation of the
bid set documents.
• Integrate City -supplied front-end documents into the manual. Prepare technical
specifications of the Project manual (Part B).
• Coordinate technical specifications with other parts of the Project manual, including the
general terms and conditions and the drawings.
• Assemble drawings and specifications for the bid set version of the Project manual for this
Project (one paper full-sized original plus a pdf file of the documents).
• Stamp, sign, and seal the bid set version of the Project manual.
Task 220 — Bid Period Services
Objective: To assist the City with bidding the Project.
Activities/Approach: The City will be responsible for advertising and bidding the Project
manual. Consultant will assist the City as requested during the bid period. This budget
includes a labor allowance of 240 hours for assisting the City with the Project bidding.
Detailed activities include:
Prepare addenda for City distribution as required prior to bid closing.
Attend and participate in the City -led pre-bid conference.
Respond to bidder questions during the bid period. This task is based on a 4 -week bidding
process.
Assist with bid evaluations.
City's Responsibilities:
Lead efforts to electronically distribute plans and specifications and addenda to prospective
bidders and maintain the plan holder's list.
Lead the pre-bid conference.
Perform bid evaluations.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 8 of 13
Brown and Caldwell
Work Products: Addenda documents
300 Series Tasks: Project Management and Design Support Services
The 300 Series tasks involve activities required for managing the Project and those
activities that are common throughout the Project duration.
Task 300 — Project Management
Objective: To provide management, direction, coordination, and control of all work
associated with Project schedule, budget, subconsultants, technical quality, and
monthly progress reports and invoices for the Project.
Activities/Approach: This task includes the following activities:
• Develop a Project Management Plan for internal use.
• Develop a Health and Safety plan for internal use.
• Maintain critical -path schedules.
• Prepare monthly project status reports. Progress reports will identify budget status, progress
status, activities of the previous month, and up -coming activities.
• Supervise project staff.
• Manage in-house budget and schedule.
• Procure, supervise, and coordinate the activities of subconsultants providing specialized or
supplemental engineering services.
City Responsibilities: None.
Work Products:
Monthly progress reports and invoices
Subconsultant contracts
Task 310 — Coordination Meetings
Objective. To provide a regular forum for receipt, exchange, response, and
documentation of Project planning, design, and management related issues and
decisions during the Project.
Activities/Approach. This task includes the following coordination meetings:
• Weekly conference calls (one hour duration) between Consultant's project manager (PM)
and the City's PM to review Project status, schedule, contract issues, and other Project
management related issues. The Project duration for Phase A is estimated to be 17 months.
Consultant will combine these meetings as much as possible with other on-site visits.
• Kick-off meeting between City staff, PM, and design manager (DM) to review major planning
and design elements, schedule, and development/tracking of issues/decision log.
• Ten workshops on-site at the City's WRRF with PM, DM, and up to two additional design
engineers (discipline leads) to present and review findings, discuss design issues/decision
log progress, and obtain site access for information gathering.
• Two 8 -hour workshops on-site at the City's WRRF to discuss the PER/30 Percent and
Permit Set submittals. Consultant attendance will include PM, DM, and up to four additional
design engineers (discipline leads).
• Weekly internal Project team meetings during the PER/30 Percent Design phase and bi-
weekly internal Project team meetings during the Final Design phase (1 -hour duration
teleconference between Consultant disciplines) for a duration of up to 17 months to discuss
design issues, review schedule, and coordinate amongst discipline team members.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 9 of 13
Brown and Caldwell
City Responsibilities:
• Attend all Project coordination meetings to provide timely input on issues/decision log
progress.
• Review and provide comments on meeting notes.
Work Products:
• Agenda to be distributed prior to all coordination meetings
• Issues/decision log
• Meeting notes for all Project coordination meetings
Task 320 — Permitting Assistance
Objective: To assist the City in preparing and submitting permits and other regulatory
documents required for the Permit Set documents and associated with new facility
construction.
Activities/Approach: This task involves assisting the City with permit and regulatory
document development that will be required as part of the Project. At this time, it is not
certain which permits will be required. For budgeting purposes, the following permits
and/or approvals have been tentatively identified and included in this scope of work:
IDEQ
— The PER/30 Percent Design submittal will be transmitted to IDEQ upon approval of the
City.
— PER/30 Percent Design IDEQ comments will be resolved by Consultant to the
satisfaction of the IDEQ for transition to the Final Design phase.
— The Permit Set will be transmitted to IDEQ upon approval by the City.
— Permit Design comments will be resolved by Consultant to the satisfaction of IDEQ prior
to issuance of Bidding Documents.
• City Building Services Permit
— The Permit Set will be transmitted to the City Building Services Department upon
approval by the City.
— Permit Set comments will be resolved by Consultant to the satisfaction of the City
Building Services Department prior to issuance of Bidding Documents.
• Stormwater Pollution Prevention Permit (SWPPP)
— Consultant will include drawings for installation of best management practices (BMPs)
facilities in the Bidding Documents.
— Consultant will include a specification in the Bidding Documents outlining the
construction contractor's responsibilities for using the drawings in support of developing
the SWPPP and submitting a Notice of Intent (NOI) to the Environmental Protection
Agency (EPA) for coverage under the construction general permit as site operator.
Other permits and regulatory documents may be identified during the Project and will be
added to this scope and budget upon written authorization by the City. It is assumed
that wetlands, biological assessments, or archaeological investigations and surveys will
not be necessary. It is also assumed that the construction contractor will secure other
Project -related permits such as the grading, building, electrical, and plumbing permits.
No effort associated with right-of-way permits is included as all construction activities
will occur within the site boundaries of the existing WRRF.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 10 of 13
Brown and Caldwell
City Responsibilities:
• Review Consultant response packages to IDEQ and City Building Services prior to
submission.
• Provide review comments to the general contractor in the development of the SWPPP.
• Upon approval of the general contractor's SWPPP and permit application, submit a NOI to
the EPA as the site owner.
• Conduct inspections as required by the SWPPP throughout the duration of the construction
activities.
Work Products:
• Permit Set package to IDEQ
• IDEQ response comment documentation package for Permit Set
• Permit Set package to City Building Services
• City Building Services response comment documentation package for Permit Set
• SWPPP BMPs specification and drawings
Task 330 — Construction Cost Estimate and Construction Schedule
Objective: To provide construction cost estimate and construction schedule at each
design phase milestone.
Activities/Approach: Consultant will estimate the probable construction cost and schedule
based on the PER/30 Percent Design and Permit Set submittals. Class 3 and Class 1
estimates will be submitted respectively in accordance with the Association for the
Advancement of Cost Engineering Estimate Classification System.
City's Responsibilities:
• Review cost estimates and construction schedule.
Work Products:
• Cost Estimates. Consultant will prepare construction cost estimates for the PERM Percent
design and Permit Set completion levels. Consultant will subdivide the cost estimate by
process area and engineering disciplines.
• Construction Schedule. Consultant will prepare a basic work breakdown structure schedule
estimate at the PER/30 Percent Design submittal. A detailed critical path construction
schedule will be submitted with the Permit Set which will also identify necessary flow by-
passing and sequencing during construction.
Task 340 — QA/QC
Objective: To implement a QA/QC program to review products from this scope. City and
regulatory agency review comments will also be incorporated to prepare and complete
the permit and bid set documents. Additionally, the City is assumed to participate in this
process and provide independent review of products.
Activities/Approach: Consultant will provide appropriate calculation and deliverable QA
reviews by in-house, senior staff members. No external value engineering reviews are
included in this scope.
City Responsibilities:
• Review and provide comments to design decision/issues log
• Participate in QA/QC reviews and provide written comments and feedback regarding review
documents
Work Products:
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 11 of 13
Brown and Caldwell
Design decision/issues log
TIME OF COMPLETION and COMPENSATION SCHEDULE
The following schedule is based on a Notice to Proceed (NTP) for Amendment No. 1
from the City by December 2015 and resulting in completion of the tasks by September
2016. An NTP issued on a different date will change the schedule accordingly.
The estimated expenses are included in the amounts below and are based on the
following:
• Task 203 Architectural Preliminary Design - Subconsultant: CTA Group — $54,914
• Task 207 Building -Mechanical Preliminary Design - Subconsultant: CTA Group — $32,102
• Task 208 Electrical Preliminary Design - Subconsultant: DC Engineering — $340,000
• Task 310 Coordination Meetings (6 trips) - Airfare: one person @ $421 per round trip ticket
Meals and incidentals: one person at per diem rate ($46/day) - Lodging: one person for one night
at per diem rate ($83/night)
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 12 of 13
Brown and Caldwell
COMPENSATION AND COMPLETION SCHEDULE
Task
I Description
Due Date
Compensation
100
PER/30 PERCENT DESIGN
■
101
Topographic Survey and Base Mapping Support
N/A
102
Geotechnical Investigation and Report Support
N/A
103
Architectural Preliminary Design
N/A
104
Civil Preliminary Design
NIA
105
Structural Preliminary Design
N/A
106
Process — Mechanical Preliminary Design
N/A
107
Building — Mechanical Preliminary Design
N/A
108
Electrical Preliminary Design
N/A
109
Instrumentation Preliminary Design
N/A
110
Document Preparation
N/A
200
FINAL DESIGN
■
203
Architectural Design
September 2016
$54,914
204
Civil Design
September 2016
$186,310
205
Structural Design
September 2016
$499,815
206
Process — Mechanical Design
September 2016
$694,844
207
Building — Mechanical Design
September 2016
$36,201
208
Electrical Design
September 2016
$358,102
209
Instrumentation Design
September 2016
$85,388
210
Document Preparation
September 2016
$58,322
220
Bid Period Services
September 2016
$42,125
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 12 of 13
Brown and Caldwell
The Not -To -Exceed amount to complete all services listed above for this Amendment
No. 2 to Task Order No. 10601.A is two million, five hundred -thirteen thousand nine
hundred eighteen dollars ($2,513,918.00). No compensation will be paid over the Not -
to -Exceed amount without prior written approval by the City in the form of a Change
Order. Monthly invoices shall be billed as a percentage of work completed. Any and all
travel will only be reimbursed if pre -approved by the Project Manager, and only per the
City of Meridian Travel Policy. Reimbursable expenses will be paid at cost and only if
pre -approved by the Project Manager, and accompanied by an itemized receipt. Any
travel and/or reimbursables paid will be paid as part of the Not -To -Exceed Task Order
Total per the Compensation and Completion Schedule above.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 13 of 13
Brown and Caldwell
300
PROJECT MANAGEMENT AND DESIGN
SUPPORT SERVICES
■
300
Project Management
September 2016
$79,799
310
Coordination Meetings
September 2016
$137,276
320
Permitting Assistance
September 2016
$29,746
330
Construction Cost Estimate and Construction
Schedule
September 2016
$92,864
340
QA/QC
September 2016
$158,212
TASK ORDER AMENDMENT
NO.2 TOTAL:
$2,513,918.00
The Not -To -Exceed amount to complete all services listed above for this Amendment
No. 2 to Task Order No. 10601.A is two million, five hundred -thirteen thousand nine
hundred eighteen dollars ($2,513,918.00). No compensation will be paid over the Not -
to -Exceed amount without prior written approval by the City in the form of a Change
Order. Monthly invoices shall be billed as a percentage of work completed. Any and all
travel will only be reimbursed if pre -approved by the Project Manager, and only per the
City of Meridian Travel Policy. Reimbursable expenses will be paid at cost and only if
pre -approved by the Project Manager, and accompanied by an itemized receipt. Any
travel and/or reimbursables paid will be paid as part of the Not -To -Exceed Task Order
Total per the Compensation and Completion Schedule above.
Amendment No. 2 to Task Order 10601.A WRRF Capacity Expansion FY2015 Page 13 of 13
Brown and Caldwell
IDSOS Viewing Business Entity
110-7 01 mvl�
_.
VA rOUT TA I f
Page I of 3
Lawerence Denney, Secretary of State
Search Back to Summary ]
Get a certificate of s BROWN t CALDWELL
[ Monitor BROWN AND CALDWELL business filings ]
201 NORTH CIVIC DRIVE
SUITE 115
WALNUT CREEK, CA 94596
Type of Business: CORPORATION, GENERAL BUSINESS
Status: GOODSTANDING 26 Oct 1988
State of Origin: CALIFORNIA
Date of 30 Jul 1975
Origination/Authorization:
Current Registered Agent: C T CORPORATION SYSTEM
921 S ORCHARD ST STE G
BOISE, ID 83705
Organizational ID / Filing C51813
Number:
Number of Authorized Stock
Shares:
Date of Last Annual Report: 19 Jun 2015
Annual Report Due: Jul 2016
[ Help Me PrintJView TIFF ]
Filed 30 Jul 1975 CERTIFICATE OF AUTHORITY
[ Help Me Print/View TIFF ]
Amendment Filed 30 Jul 1975 OTHER - RA
Amendment Filed 29 Oct OTHER - CHG RA
1975
Amendment Filed 23 Oct MERGED WITH J. B. GILBERT AND
1978 ASSOCIATES
Amendment Filed 13 Nov NAME CHANGED TO BROWN AND CALDWELL
1978
Amendment Filed 13 Nov STOCK CHANGE
1978
Amendment Filed 13 Nov MERGED WITH CAMANCHE LAKE PARK
1978
Amendment Filed 13 Nov MERGED WITH J.B. GILBERT AND
1978 ASSOCIATES
Amendment Filed 13 Nov STOCK CHANGE
1978
http://www.accessidaho.org/public/sos/corp/C51813.html 1/7/2016