HomeMy WebLinkAboutChange Order No 1 for WRRF Headworks Capacity Expansion with CH2M HillCITY OF MERIDIAN CHANGE ORDER NO. 1
33 EAST BROADWAY PROJECT NO, 10044
MERIDIAN, ID 83642 DATE: 10/27/15
EFFECTIVE DATE: 11/4/15
TASK ORDER CHANGE ORDER
ENGINEER/CONSULTANT: CH2M Hill Engineering, Inc.
PROJECT: WRRF Headworks Capacity Expansion Phase 1 Design FY15
The Engineer/Consultant is hereby directed to make the following changes from the Task Order Documents.
Description: The Headworks Capacity Expansion Project design spans over FY15 and FY16. Phase 1 of the
design phase included all work performed in FY15. Phase 2 of the design phase will include all work performed
in FY16. CH2M HILL provided and completed engineering services for Phase 1 and will continue with Phase 2
of this project design. Phase 1 design included preliminary analysis and 30% design documents. Phase 2
design takes the 30% plans to bid ready design plans.
Reason for change order: Due to the design project spanning over two fiscal years, it was decided to break the
task order into the FY15 project phase and the FY16 project phase. Also by negotiating this change order after
30% drawings were complete, CH2M Hill would have a better understanding of the required costs to complete
the design plan set. This amendment to the task order represents the remainder of the design phase
requirements for the project that were budgeted for FY2016.
q
Attachments: Scope of Services (1b pages)
CHANGE IN TASK ORDER PRICE:
CHANGE IN TASK ORDER TIMES:
Original Task Order Price $231,285.00
Original Task Order Times: 90
Net changes form previous Change Orders
Net changes form previous Change Orders
No._0^ to 1_
No._ to _ (calendar days)
$0.00
0
Task Order Price Prior to this Change Order:
Task Order Times prior to this Change Order.
(calendar days)
$231,285.00
90
Net Increase (decrease) of this Change Order.
Net Increase (decrease) of this Change Order:
(calendar days)
$467,850.00
240
Task Order Price with all Approved Change Orders:
Task Order Times with all Approved Change Orders:
(calendar days)
$699,135.00
330
APPROVED: (CITY PURCHASI G R
INC.
ACCEPTED`:
�LENGINEERS,
By: Keith Watts
Date:
By.-
y:Date: Date:
%d Z
RECOMMENDED: (ASST CITY ENGINEER)
DAATE APP OVED EN COUNCIL
By:
NO SIGNATURE REQUIRED
Date: g
iTA
APP VED (CI - o��
ATTEST]
By: Mayor Tammy de eerd Crry
y: CItyZ , a e L. Holman
Date: — �'� ✓ E T49k
1 11T -y-j5
CHANGE ORDER NO. 1
TO
TASK ORDER NO. 10044
CITY OF MERIDIAN (OWNER) AND CH2M HILL ENGINEERS, INC. (ENGINEER)
WRRF - HEADWORKS CAPACITY EXPANSION
PHASE 2 DESIGN FY16
ENGINEER is currently engaged in the execution of Task Order 10044 in support of the
Wastewater Resource Recovery Facility Headworks Capacity Expansion project. ENGINEER
is following a traditional step -wise, phased approach to performing the work associated with
design of the UV system. The project design approach consists of:
• Project Chartering and Site Visit (Phase 1 Scope)
• Project Definition (Phase 1 Scope)
• Preliminary Engineering and Design (30 Percent Design — Phase 1 Scope)
• Design Development Documents (60 Percent Design)
• Final Design Documents (90 Percent Design)
• Bid -Ready Documents (100 Percent Design)
• Bid Period Services — assist City with bid process for selecting a general construction
contractor
The project is being delivered in two phases to align task order budget with City fiscal year
budgets. Per the list above, Phase 1 carries the project through the Preliminary Engineering
and Design task and Phase 2 will advance the project through Bid Period Services. The initial
Task Order 10044 is considered Phase 1 and this Change Order No. 1 constitutes Phase 2.
The tasks associated with this Change Order No. 1 are more fully described in the Scope of
Work section below:
SCOPE OF WORK
Task 1 — Project Management (Additional)
Additional project management will be provided by ENGINEER to manage, coordinate and
lead ENGINEER Team's activities and perform administration of the project design services
and project quality reviews. ENGINEER will provide the resources necessary for project
management throughout this phase of the project as described in the initial Task Order 10044.
Change Order No. 1 to Task Order 10044 Page 1 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH2MHILL Engineers, Inc.
Deliverables
• Periodic written project design schedule updates to keep the City's Project Manager
informed as to the changes to the initial schedule outlined in this Scope.
• Monthly project invoice statements with a brief description of the work performed.
Meetings (Unique to those identified below)
Bi -weekly telephone meeting conducted between City Project Manager and ENGINEER
Project Manager to discuss project status, review actions/issues pending, and other project
coordination.
Task 5 — Design Development Documents (60 Percent Design) — Phase 2 Task
The purpose of this task is to utilize the decisions of the project that were made in the
Preliminary Design Phase to complete and finalize the preliminary calculations of the previous
phase, and develop the project design to achieve a true "design freeze" at the conclusion of
this phase. Structures, equipment, major plant piping, process, and site plans will all be
finalized during this phase to allow final detailing of the same in the next phase of design.
Per City direction, ENGINEER will produce a check set of the drawings at this design stage for
submission to the City but will not halt the design efforts on the way to the Task 6 Final Design
(90 percent design) stage. The City will review the drawing check set and provide comments.
A check set of the specifications will not be produced nor will Basis of Design documentation
be submitted. Additionally, neither a construction cost estimate nor a construction schedule will
be submitted as part of this snapshot check-in.
Specific activities and work products from this phase are described in the following subtasks:
Subtask 5.1: Civil and Site Development
• Finalize horizontal locations of major site elements.
• Finalize floor, structure, and finish grade elevations.
• Define demolition requirements and limits.
• Define contractor staging, storage, and on -/off- site access corridors.
• Prepare preliminary site grading drawings.
• Identify limits and extents of site restoration.
• Develop preliminary yard piping and plant drain layouts.
• Coordinate with mechanical to develop odorous air duct layout.
• Show stormwater control design on the drawings.
• Finalize paving and site roadway concepts.
• Prepare first draft of technical specifications.
Change Order No. 1 to Task Order 10044 Page 2 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH21VIHILL Engineers, Inc.
Subtask 5.2: Architectural
• Develop building floor plans and elevations.
• Coordinate with I&C and electrical disciplines to finalize size and location of electrical and
control rooms.
• Coordinate with the mechanical discipline to establish the type of HVAC equipment, locate
HVAC equipment rooms, refine space requirements and routing for ductwork if required,
and finalize design R -values for all exterior walls.
• Coordinate with structural engineer to finalize the structural design concepts for the
facilities.
• Complete building and fire code analysis. Meet with local code official to review floor plans.
• Prepare first draft of technical specifications.
Subtask 5.3: Structural
• Review geotechnical design recommendations and coordinate with geotechnical engineer
to finalize foundation design criteria for proposed facilities.
• Document structural design for buildings and structures.
• Prepare preliminary foundation, floor, and roof framing plans.
• Coordinate with corrosion engineer to analyze materials and corrosion control
requirements, and to prepare a tech memo to document the corrosion control plan to be
implemented during design.
• Prepare first draft of technical specifications.
Subtask 5.4: Process
• Coordinate with equipment vendors.
• Final major equipment -sizing calculations.
• Finalize treatment plant gravity hydraulics and establish concepts for flow control and
hydraulic structures.
• Assemble catalog cuts for process equipment. Complete equipment data sheets or
equipment list on major equipment items.
• Coordinate with I&C on development of P&IDs.
• Coordinate with I&C on development of process control narratives.
• Continue developing mechanical layout plans and sections.
• Develop design drawings for modifications to existing facilities as required to tie-in the new
facilities.
• Final ancillary equipment sizing and line sizing calculations.
• Finalize ancillary equipment selection (type, size, weight, arrangement).
• Select piping materials.
Change Order No. 1 to Task Order 10044
WRRF — Headworks Capacity Expansion Design and Bid Services
CH2MHILL Engineers, Inc.
Page 3 of 9
• Prepare first draft of technical specifications.
Subtask 5.5: HVAC/Plumbing
• Prepare final sizing calculations for HVAC equipment based on energy code requirements
and selected building construction materials. Prepare HVAC equipment data sheets and
cut sheets.
• Locate major HVAC/Plumbing equipment on building plans.
• Prepare HVAC system block diagrams. Define HVAC system control philosophy.
• Coordinate with civil engineer for water supply and distribution, as well as plant drain
system.
• Locate major water/drain/sewer location on the building plans.
• Prepare first draft of technical specifications.
Subtask 5.6: Instrumentation and Control Systems (I&C)
• Add equipment/instrument tag numbering, naming, and abbreviation following existing
standard conventions used at the treatment plant.
• Design control system configuration to the existing standards at the treatment plant with
input from the City.
• Advance control philosophy including local control approach, control system, level of
automation, supervisory control based on the City's existing standards.
• Coordinate with the process engineer to prepare P&ID drawings including loop numbers
and instrumentation.
• Coordinate with City for communication and integration of new controls with existing plant
SCADA system.
• Summarize I&C system design philosophy in a process control narrative. Prepare
preliminary Instrument and 1/0 Lists, and SCADA interfaces. Develop preliminary control
system block diagram.
• Define control interfaces for package systems with local controls.
• Coordinate with HVAC engineer regarding control system requirements.
• Prepare first draft of technical specifications.
Subtask 5.7: Electrical
• Determine location of distribution apparatus and confirm necessary modifications to
existing equipment.
• Advance one -line diagrams for proposed facilities.
• Prepare detailed electrical load calculations for the facilities.
• Develop layout of the major electrical equipment including sizing of electrical room, if
needed. Determine equipment requiring uninterruptible power supplies (UPS). Coordinate
Change Order No. 1 to Task Order 10044 Page 4 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH2MHILL Engineers, Inc.
with I&C discipline to determine space requirements and locations for control equipment.
Locate major 1/0 termination panels, TJBs, and control panels.
• Define/document requirements and concepts for special systems such as: extensions of
existing telephone, data, and fire alarm system.
• Identify routing methods for electrical and communication conduit and tray. Lay out duct
bank system (major runs/manholes). Coordinate with I&C for conduit, conductor, and
raceway needs. Coordinate with civil yard piping. Locate manholes and hand holes.
• Develop preliminary lighting concepts and prepare preliminary lighting layout.
• Define hazardous locations (NFPA 820) and document.
• Prepare first draft of technical specifications including performance specifications for
interior lighting design by the contractor.
Deliverables
• 60% Design drawings (check set plot).
Assumptions
• The 60 percent design drawings will be provided to the City as an electronic deliverable
(PDF). City will review the deliverables and provide comments in written form within 5
working days. Comments received by the City will be addressed as part of the preparation
of the 90 percent design documents.
• The ENGINEER will not perform a QA/QC review of the 60 percent design drawings or
other design documents.
• The 60 percent drawings will not be stamped by a professional engineer.
Task 6 — Final Design Documents (90 Percent Design) — Phase 2 Task
The purpose of this task is to develop the design drawings, specifications, and schedules for a
final review.
Subtask 6.1: 90 Percent Design Document Completion
ENGINEER will progress the design and modify the contract documents to incorporate agreed
upon 60 percent review comments from the City and applicable regulatory agencies. The 90
percent documents will then be submitted to the City for their review. The following subtasks
are included:
• Incorporate responses to comments on the 60 percent Preliminary Design package.
• Prepare 90 percent design drawings.
• Prepare final technical specifications.
• Prepare final calculations.
• Complete checking and coordination review by design leads.
Change Order No. 1 to Task Order 10044 Page 5 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH2MHILL Engineers, Inc.
Subtask 6.2: 90 Percent Construction Cost Estimate and Schedule
• ENGINEER will update the construction cost estimate to provide the City with a Class 1
final construction cost estimate based on 90 percent Design Drawings and Technical
Specifications. A Class 1 estimate is typically considered to have an accuracy of +15 to —
10%.
ENGINEER will prepare an update to the estimated project design schedule. The general
construction milestone activities developed from the 30 percent design task will be adjusted
to reflect changes in the design schedule.
These cost and schedule estimates will be submitted to the City for review and discussion
following the 90 percent Design Workshop.
Deliverables
• 90% Design drawings
• Technical specifications.
• Updated Basis of Design Technical Memoranda by Discipline.
• ENGINEER's Class 1 construction cost estimate.
• ENGINEER's updated project schedule estimate.
Assumptions
• The Basis of Design TMs will be an update to the previously developed summaries by discipline to
document the changes from the 30 percent design task.
• The 90 percent drawings and specifications will be reviewed by the ENGINEER internal
QA/QC reviewers prior to submission to the City. The 90 percent drawings and
specifications will be reviewed by the City and comments adjudicated prior to preparation of
the Bid Ready (100 Percent) Documents.
The 90 percent drawings and specifications will not be stamped by a professional engineer
and are not to be distributed.
Task 7 — Bid Ready Documents (100 Percent Design) — Phase 2 Task
The purpose of this task is to develop the final contract drawings and specifications for
competitive bidding. ENGINEER will modify the contract documents to incorporate agreed
upon 90 percent review comments from the City, applicable regulatory agencies, and
ENGINEER's Quality Review Team. This task scope is based on all City review comments
being received prior to this phase of work and consists of the following subtasks:
• Incorporate responses to comments on the 90 percent Final Design Document.
• Prepare bid ready construction drawings.
• Prepare bid ready technical specifications, including front-end Division 01 documents.
Change Order No. 1 to Task Order 10044 Page 6 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH21vIHILL Engineers, Inc.
• Provide City with technical documents in support of the Meridian Building Permit application
and assist in the completion of the application.
Deliverables
• Bid Ready (100 Percent) Contract Documents in digital format (PDF) and 1 hard copy will
be delivered to the City.
• Bid Ready (100 Percent) Contract Documents will be delivered in digital format to DEQ for
review and approval.
• Digital (CD) and hardcopy technical documents as specified on the Meridian Building
Permit Application.
Assumptions
• DEQ review of the Bid Ready (100 Percent) Contract Documents will be concurrent with
the bid process and ENGINEER will incorporate DEQ comments into an addendum, if
necessary.
• No permitting tasks other than submittal of final documents to DEQ, Meridian Building
Permit, and Planning Department assistance are included in the final design scope of work.
• The bid -ready drawings and specifications will be stamped by a professional engineer.
Task 8 — Design Workshops — Phase 2 Task
ENGINEER will conduct a series of workshops with the City at critical periods during the
development of the project design as described below.
Final Design (90 Percent) Workshop
ENGINEER will assemble the work products from the Final Design task and submit the 90
percent Design Documents to the City for review and comment. A workshop will be held with
the City's personnel to receive and discuss comments and to reach closure on design issues.
Following the workshop, meeting minutes and responses to comments will be prepared and
submitted. The responses to comments will be incorporated into the 100 percent Construction
Documents. The workshop will be held at the CH2M HILL office. Discipline leads will
participate in person or via telephone when pertinent based on City review comments and
questions.
Deliverables
• Meeting minutes from each workshop.
Assumptions
• City will have reviewed the draft documents prior to the workshops and be prepared with
input and/or questions for discussion.
Change Order No. 1 to Task Order 10044 Page 7 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH2MHILL Engineers, Inc.
Task 9 — Bid Period Services for Construction Contract — Phase 2 Task
ENGINEER will respond to technical inquiries posed by prospective bidders throughout the bid
period concerning interpretation of the drawings and technical specifications. Bidders
questions sent to the City Purchasing Department will be routed to ENGINEER and responses
returned to Purchasing for inclusion in bid period addenda. The City will review responses by
the design team prior to issuance of addenda.
If requested by the City, ENGINEER will assist the City by participating in a pre-bid conference
for prospective bidders at the project site.
Deliverables
• Content for bid addenda.
Meetings
• Pre-bid meeting.
Assumptions
• The deliverables produced as part of this Task will be provided electronically (PDF) to the City PM
for distribution. ENGINEER will not provide printed sets.
• The City will be responsible for advertising and administering the bid as well as for awarding and
executing the contract.
• The general construction contract will only be bid once.
• Up to five ENGINEER staff will participate in the pre-bid meeting either in person or via conference
call. Four hours for each ENGINEER staff is assumed plus travel time.
• The budget for responding to bidders questions is based on an estimated 16 inquiries for a
total of 48 hours inclusive of processing time.
PROJECT ASSUMPTIONS
Assumptions listed in the initial Task Order 10044 remain applicable.
Change Order No. 1 to Task Order 10044 Page 8 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH21VIHILL Engineers, Inc.
TIME OF COMPLETION and COMPENSATION SCHEDULE
The following schedule is based on a Notice to Proceed (NTP) from the City in October 2015
and resulting in Task Order being completed by May 2016. An NTP issued on a different date
will change the schedule accordingly.
COMPENSATION AND COMPLETION SCHEDULE
Task
Description
Due Date
Compensation
1
Project Management
■ October 2015 through May
■ $ 48,000 (labor)
2016
■ $ 1,530 (expense) Subconsultant
5
Design Development Documents
■ November 2015 through
■ $ 115,315 (labor)
(60 Percent Design)
December 2015
■ $ 18,000 (expense) Subconsultant
6
Final Design Documents (90
■ December 2015 through
■ $ 168,800 (labor)
Percent Design)
February 2016
■ $ 19,350 (expense) Subconsultant
7
Bid Ready Documents (100
■ March 2016
■ $ 58,300 (labor)
Percent Design)
■ $ 13,600 (expense) Subconsultant
8 '
Design Workshops
■ February 2016
■ $ 4,350 (labor)
■ $ 1,975 (expense) Subconsultant
9 '
Bid Period Services for
■ April 2016 through May
■ $ 14,700 (labor)
Construction Contract
2016
■ $ 1,280 (expense) Travel
■ $ 2,650 (expense) Subconsultant
TASK ORDER TOTAL $467,850.00
DC Engineering is a sub -consultant to CH2M HILL on this project to provide electrical
engineering services. The associated sub -consultant cost is included as a project expense
and will appear on invoices submitted to the City as a separate line item cost.
The estimated travel expenses are based on the following:
o Task 9 Travel
o Airline: 2 people for 1 round-trip flight at $400 / flight
o Rental Car: 1 car for 2 days at $65 / day
o Lodging: 2 people for 1 night at per diem rate
o Meals: 2 people for 2 days at per diem rate
Task Order No. 10044 Value Summary:
Original Task Order -- $231,285
Amendment No. 1 -- $467,850
Change Order No. 1 to Task Order 10044 Page 9 of 9
WRRF — Headworks Capacity Expansion Design and Bid Services
CH21VIHILL Engineers, Inc.