HomeMy WebLinkAboutExecuted Change Order No 2 with DC Engineering for SCADA System UpgradesCITY OF MERIDIAN V If"11. � t 114v.
33 EAST DROAAWAY PROJECT NO, 10417A
MERIDIA14, Ip 93U2 DATE : June 25, 2fi1&
CONTRACT CHANGE ORDER
ISG Engineering
Contractor 1s fieraby directed to make the follovrtng changes from tlio Contract Doeurnents and Plans.
I. Add into the system platform application additional walls 11, 17 and 26
2. Add into the aystern platform applimtlon additional wells 12, 16, 18, 23 and 26.
3. Specify new 8CADA hardware.
4. Setup temporary SCADA hardware_
5. Remove VVIN911 mobile.
6. Add coordination time for the condition based monitoring software installation project_
Remocn. for Chungo Order'_
Changes were not Included in the original scopo_ Additional time required.
Change order request from CC Engineering dates May 29, 201 S.
CHANGE IN CONTRACT" PRICE: CHANGE tN CONT€iACT TimEs..
Original Contract Prke
$47,600,00 Ortgfnat contract-5mes: 192 days
Not changes farm previous Change Orders
Net ehangaa farm previous Changs Orders
$23,600,00
7 clays
Cafftraet Price r'rklr10 this Change Ofdsr:
Contraot Times prior to this Change Order:
(ealeadardaysj
$71,1DD.t7tt
199 days
MA inoressa (dearaose) of Us Change carder
Net increase (der reasa) of Ehls Changs Order
(ra)endardays)
$20,900.00
go clays
Contract PrIcs with all Approved Change Wars:
Contra .Ct Timas With all Approved Change Orders:
(catandsrdays)
$92,t}0[I,t#p 289 .. days
APPROVED: (Oily i'urchastnp r4tan�gar} JAGCEPTED., (courracior)
IBy. Kollh Walls ��` gy: 1 ,
DJ
RECOMMENDED: (City Prajoalgonageo 0AT( APPROVED BY OOUNCI1_
By: :NO SIGNATURE Rt G_ 2ti1t2E
ra@te, r i O ThDAUII, r1;:
APPROVED: (orry) 2 p, �T;
' City of
t)y: P IDIA y Clark, ce . N I
kCiAfi
Date: --a Pi ` s � Vie;
$0f fi, 71E0S �a�y
440 E. Corporate Drive
Suite 103
Meridian, Idaho 83642
Phone: 208.288.2181
Fax: 208.288.2182
EN G IIV SERIN G
'�Y -
May 29, 2015
Mr, Clint Worthington
City of Meridian Public Works
33 East Broadway Ave
Meridian, ID 83642
Subject: SCADA Application Development - Programming Additional Services — Add Well 11, 17,
25, 12, 15, 18, 23, 26 and Condition based monitoring coordination.
Mr. Worthington,
The following additional services have been requested for the above referenced project. These changes
were not included in the original estimate and require additional time to complete. As a result we are
asking for an increase to our not to exceed amount of $20,900.00 (Twenty Thousand Nine Hundred
Dollars) to complete the programming and startup.
Project changes;
• Add into the system platform application additional wells 11, 17 and 25.
o Includes configure system platform objects for use in the application, populating
displays, configuring 1/0, and testing operation from remote site to Wonderware
application.
• Add into the system platform application additional wells 12, 15, 18, 23 and 26.
o Includes configure system platform objects for use in the application, populating
displays, and configuring UO. Testing froin the remote site to the Wonderware is not
included due to the fact that these sites have not been upgraded and connected to the
new corninunication network yet.
• Specify New SCADA hardware (monitors, PC's, cabling)
• Setup temporary SCADA hardware
• Remove WIN911 mobile (due to IT restricting web access this will not be feasible and it is not
currently supported on Win91 I Enterprise Edition)
• Add coordination time for the condition based monitoring software installation project. An
allowance of 40 hours to be billed T&M for support and coordination as needed.
DC Engineering
Fee breakout
Additional wells currently in-service:
$ 5,000.00
Additional future wells:
$ 6,000.00
Specify SCADA Hardware:
$ 2,500.00
Setup temporary SCADA Hardware:
$ 1,200.00
Deduct for WIN911 mobile
$ -1,000.00
Condition based monitoring coordination T&M
$ 4,200.00
Total:
$ 20,900.00
If you have any questions, or require additional information, please do not hesitate to ask.
Sincerely,
DC ENGINEERING, P.C.
C.,qpie Huddl estvpt
Lane Huddleston
2 CIC Engineering