HomeMy WebLinkAboutPSI Corporate Office - Stormwater Runoff Management and Treatment CalculationsPSI CORPORATE OFFICE STORMWATER RUNOFF MANAGEMENT AND TREATMENT CALCULATIONS Address: 2204 East Lanark Street Meridian, Idaho 83642 PREPARED BY: Breckon Land Design, Inc. P.O. Box 44465 Boise, Idaho 83711 ph: (208) 376-5153 fax: (208) 376-6528 OF C U 1 536 �Sl Project No. 13016.01 June 18, 2013 PURPOSE The purpose of this report is to confirm that the for the PSI Corporate Office is adequate for the of Environmental Quality standards. on-site storm water management system design 100 year design storm per the Idaho Department SITE DESCRIPTION The proposed site is located at 2204 East Lanark Street, Meridian, Idaho 83642. The limits of construction are approximately 2.00 acres as shown on the attached site plan. Currently the site is a relatively flat with existing improvements. Runoff water from the site is conveyed to valley gutters and curb gutters that flow water to an underground drainage system. The post development runoff will divide runoff between new grass infiltration swales and a new underground seepage bed. The site is bordered by commercial development on the north, south, west, and east. Dewatering is not expected. DESIGN CRITERIA The system is designed to accommodate the 100 year design storm using infiltration basin (swale) designs in accordance with recommendations given by the IDEQ Storm Water Best Management Practices Catalog. The storm water runoff flows were calculated using the Rational Method with a weighted post development runoff coefficient calculated for each drainage area. The rainfall intensity used was taken from the Intensity -Duration -Frequency Curve for Zone A in the IDEQ Storm Water Best Management Practices Catalog for the 100 year design storm. See Appendix B for a copy of this curve. PEAK FLOW ANALYSIS OUTLINE The proposed storm drainage piping system is sized to provide the necessary capacity to convey the 100 -year storm event and to provide for initial settlement of sediments in the runoff. The following steps were taken to design the storm drain lines. 1. Calculate the individual drainage basin areas (A) and estimate the Runoff Coefficient (C) and Time of Concentration (T) values for the developed basins. 2. Determine the maximum flow for each basin using the Rational Equation (Q=CIA), determining the Rainfall Intensity (1) from the Zone A Intensity -Duration -Frequency curves from the estimated T values. 3. Size the storm drain lines, sand and grease traps and inlets to accommodate the peak flows. PEAK FLOW ANALYSIS RESULTS The storm system has been sized to accommodate the 100 -year peak flow rates. Appropriately sized infiltration trenches have been located to provide initial settlement of sediments in the runoff and to accommodated storm water on site. DESIGN STORM DETENTION ANALYSIS OUTLINE The proposed storm drainage detention system is sized to provide the necessary capacity to store the 100 -year storm event and to provide for initial settlement of sediments in the runoff. The following steps were taken to design the storm drain retention. 1. Calculate the individual drainage basin areas (A) and estimate the Runoff Coefficient (C) and Time of Concentration (T) values for the developed basins. 2. Determine the maximum flow for each basin using the Rational Equation (Q=CIA), determining the Rainfall Intensity (1) from the Zone A Intensity -Duration -Frequency curves from the estimated T values. 3. Size the swale area and seepage bed size to accommodate the required volume. 100 YEAR DETENTION RESULTS The proposed detention basin system and underground seepage bed has been designed to adequately detain the 100 -year design storm event. 2 Appendix A Drainage Basin Map: N.T.S. 1233.19' DRAINAGE AREA #3 TOTAL SO: 41,014.26 sq.ft. TOTAL AC: 0.94 Impervious: 13,625.69 sq.ft. Ac: 0.31 Pervious: 27,388.57 sq.ft. Ac: 0.63 ■■■ DRAINAGE AREA #2 TOTAL SO: 7,846.88sg.ft. TOTAL AC: 0.18 6 Impervious: 3,627.13 sq.ft. Ac: 0.084 Pervious: 4,219.75 sq.ft. Ac: 0.096 DRAINAGE AREA #1 TOTAL SO: 28,895.25 sq.ft. TOTAL AC: 0.663 Impervious: 18,152.49 sq.ft. Ac: 0.42 Pervious: 10,742.76 sq.f� Ac: 0.24 PSI CORPORAT OFFICE FINISH FLOOR -------------------------------------- p5c�� IANARK S�RtET T DRAINAGE BASIN MAP N 5GALE: I"= 60'-0" Appendix B Intensity -Duration -Frequency Curve 20.0 = e.o m 6.0 W d 4.0 0) w = 2.0 L) z 1.0 z 0.e as 0.4 Lo z W }- 02 z J a .0e D6 z Q D4 f.- 0 10 15 20 30 40 5060 2 3 4 5 6 5 10 12 is z4 M I N U T E S H 0 U R S, 0 U R A T 1'0 N t �■■1■■�I�i•r ��■■■��■��ii■■mm���Mmmmmm�n �11II/IMMON No ®®o16 ,111 ���■IN TENS ITY-DURATION - • MOORE�11��1 'I 11111momms� NINE 111111111� oil wo ���■■llll���lle�l���:\. 11111mommilmoollmilill 10 15 20 30 40 5060 2 3 4 5 6 5 10 12 is z4 M I N U T E S H 0 U R S, 0 U R A T 1'0 N Appendix C Runoff Coefficients Table C-1. Typical "C" Values Description of Area Runoff Coefficients Business Downtown Areas 0,70-0.95 Neighborhood Areas 0.50- 0.70 Residential Single-family areas 0.30-0.50 Multi -units, detached 0.40-0.60 Multi units, attached 0.60-0.75 Residential (suburban) 0.25-0.40 Apartment dwelling areas 0,50 - 0.70 Industrial Light Areas 0.50-0.80 Heavy Areas 0.60-0.90 Parks, cemeteries 0.10-0.25 Playgrounds 0.20-0.35 Railroad yard areas 0.20-0.40 Unimproved areas 0.10-0.30 Streets Asphalt 0.70-0.95 Concrete 0.80-0.95 Brick 0.70-0,85 Drives and Walks 0.75-0.85 Roofs 0.75-0.95 Lawns - course textured soil (greater than 85% sand) Slope: Flat, 2% 0,05-0.10 Average, 2-7% 0.10-0.15 Steep, 7% 0.15-0.20 Lawns - tine textured soil (greater than 40% clay) Slope: Flat, 2% 0.13-0.17 Average, 2-7% 0.18-0.22 Steep, 7% 0.25-0.35 44 Developing Your Stormwater Pollution Prevention Plan A Guide for Construction Sites Appendix D Storm Water Calculations PSI Corporate Office, Meridian, Idaho DRAINAGE AREA #1 Area = 28,895 sf Area = 0.66 acres C = 0.67 Infiltration Characteristics (floor only): Infiltration Rate = 2 in per hr Width = 95 ft Length - 100 ft A perc. = 1500 sf Q perc. - 250.00 cf per hr Q perc. - 0.0694 cfs Infiltration Characteristics 1213 sidewalls only): Infiltration Rate = 2 in per hr Width (2x) 30 ft Length 2x - 200 ft A perc. = 468.07 sf Q perc. - 78.01 cf per hr Q perc. - 0.0217 cfs STORAGE VOLUME Time Time min. sec. REQUIRED (100 Year Storm): Intensity Q dev. inches/hr) (cfs) Vin (cf V out cf V storage 51 300 4.41 1.96 588 21 567 10 600 3.2 1.42 855 42 813 15 900 2.5 1.11 1,002 63 939 20 1200 2.2 0.98 1,175 83 1,092 30 1800 1.6 0.71 1,282 125 1,157 40 2400 1.4 0.62 1,496 167 1,329 50 3000 1.2 0.53 1,603 208 1,394 60 3600 1.1 0.49 1,763 250 1,513 120 7200 0.6 0.27 1,923 500 1,423 180 10800 0.45 0.20 2,164 750 1,414 240 14400 0.35 0.16 2,244 1,000 1,244 300 18000 0.3 0.13 2,404 1,250 1,154 360 21600 0.26 0.12 2,500 1,500 1,000 480 28800 0.22 0.10 2,821 2,000 821 600 36000 0.18 0.08 2,885 2,500 385 720 43200 0.14 0.06 2,693 3,000 -307 1080 64800 0.12 0.05 3,462 4,500 -1,038 1440 86400 0.085 0.04 3,270 6,000 -2,730 Vs Max= 1,513 of Maximum Storage Required Seepage Bed Volume (38% Voids) Seepage Bed Volume (x 15%) 1 hour 2 hours 3 hours 4 hours 5 hours 6 hours 8 hours 10 hours 12 hours 18 hours 24 hours Vs Max = 1,513 cf Maximum Storage Required 1000 al & 1 1500 al Sand and Grease Trapb Amcor Pre Cast A b = V sw = 3,026 sf of 6" deep Swale required 1,008.7 sf V sw = 2,017 sf of 9" deep swale required 756.5 sf V sw = 1,513 sf of 12" deep swale required 504.3 sf Depth = 1.0087 ft Swale Size= 15 ft wide x 100 ft long x 1.01 ft dee Velocity Through Baffle: T e:1 1000 al & 1 1500 al Sand and Grease Trapb Amcor Pre Cast A b = 4 sf See appendix D Q 10 min. I 1.42 cfs 1100 year Peak Q dev. At 10 min duration Velocity = 1 0.36 ft per sec. See a e Bed Recove Time (floor): Vs= 1,513cf er Q pc = 250.00 cf per hr Time Rec = 6.11 hours seeoacle Bed Recove Time 213 sidewalls : Vs= 1,513 of Qerc = 78.01 cf per hr Time Rec = 19.4 hours Time Rec = 1 0.81 Jdays Wei hted Runoff Coefficient "C" Runoff coefficients= 0.95 paved (impervious) 0.2 landscape (pervious) Impervious area = 18,152.49 sf 17244.866 sf Pervious area I 10,742.76 sf I 2148.552 sf Total Area = 128,895.25 1 sf I 0.67 "C' of 18" deep swale required. of 24" deep swale required of 36" deep swale required Psi corporate Office, Meridian, Idaho i DRAINAGE AREA #2 Area = 7,847 sf Area = 0.18 acres C = 0.55 Infiltration Characteristics (floor only): Infiltration Rate = 2 in per hr Width = 10 ft Length = 60 ft A perc. = 600 sf Q perc. = 100.00 cf per hr Q perc. - 0.0278 cfs Infiltration Characteristics ( 2/3 sidewalls only): Infiltration Rate - 2 in per hr Width (2x) - 20 ft Length 2x - 120 ft A perc. = 136.51 sf Q perc. = 22.75 cf per hr 1 0.0063 cfs STORAGE VOLUME Time Time (min.) sec. REQUIRED (100 Year Storm): Intensity Q dev. (inches/hr) (cfs Vin cf) V out (cf) V storage (c 5 300 4.41 0.43 130 8 122 10 600 3.2 0.32 189 17 172 15 900 2.5 0.25 222 25 197 20 1200 2.2 0.22 260 33 227 30 1800 1.6 0.16 284 50 234 40 2400 1.4 0.14 331 67 264 50 3000 1.2 0.12 355 83 271 60 3600 1.1 0.11 390 100 290 120 7200 0.6 0.06 425 200 225 180 10800 0.451 0.04 479 300 179 240 14400 0.351 0.03 496 400 96 300 18000 0.3 0.03 532 500 32 360 21600 0.26 0.03 553 600 -47 480 28800 0.22 0.02 624 800 -176 600 36000 0.18 0.02 638 1,000 -362 720 43200 0.14 0.01 596 1,200 -604 1080 64800 0.12 0.01 766 1,800 -1,034 1440 86400 0.085 0.01 723 2,400 -1,677 Vs Max - 290 cf Maximum Storage Required Seepage Bed Volume (38% Voids) Seepage Bed Volume (x 15%) 1 hour 2 hours 3 hours 4 hours 5 hours 6 hours 8 hours 10 hours 12 hours 18 hours 24 hours Vs Max = 290 cf Maximum Storage Required (1) 1000 al &1) 1500 al Sand and Grease Trap by Amcor Pre Cast A b = 4;T See appendix D V sw = 580 sf of 6" deep swells, required 193.3 sf of 18" deep swale required V sw = 387 sf of 9" deep swale required 145.0 sf of 24" deep swale required V sw = 290 sf of 12" deep swale required 96.7 sf of 36" deep Swale required Depth = 0.4833 ft Swale Size= 10 ft wide x 60 ft long x 0.48 ft deep Velocity Through Baffle: Type: (1) 1000 al &1) 1500 al Sand and Grease Trap by Amcor Pre Cast A b = 4;T See appendix D Q 10 min. 0.32 cfs 1100 year Peak Q dev. At 10 min duration Velocity = I 0.08 ft per sec. Seepage Bed Rec very Time Floor: V s = 290 cf Q perc = 100.00 cf er hr Time Rec = 2.9 hours Seepage Bed Recove Time 2/3 sidewalls : V s = 290 1cf Q perc = 22. 75 cf per hr Time Rec = 12.7hours Time Rec = 0.53 days 0.2 landscape (pervious) Impervious area = 3,627.13 sf 3445.7735 sf Pervious area I 4,219.75 sf 843.95 sf Total Area = I 7,846.88 sf 0.55 "C" PSI Corporate Office, Meridian, Idaho DRAINAGE AREA #3 Area= 41,014 sf Area = 0.94 acres �j C = 0.52 Infiltration Characteristics (floor only): Infiltration Rate = 2 in per hr Width = 15 ft Length = 55 ft A perc. = 825 sf Q perc. = 137.50 cf per hr Q perc. = 0.0382 cfs Infiltration Characteristics 1 213 sidewalls only): Infiltration Rate = 2 in per hr Width 2x = 30 ft Length (2x) = 110 ft A perc. = 677.20 sf Q perc. = 1 12.87cf per hr Q perc. = 0.0314 cfs STORAGE VOLUME REQUIRED (100 Year Storm): Time Time Intensity Q dev. min. (sec.) (inches/hr) (cls) Vin (cf) V out (CO(CO V storage 51 300 4.41 2.14 641 11 630 10 600 3.2 1.55 933 23 910 15 900 2.5 1.21 1,093 34 1,059 20 1200 2.2 1.07 1,282 46 1,237 30 1800 1.6 0.78 1,399 69 1,330 40 2400 1.4 0.68 1,632 92 1,541 50 3000 1.2 0.58 1,749 115 1,634 60 3600 1.1 0.53 1,924 138 1,786 120 7200 0.6 0.29 2,099 275 1,824 180 10800 0.451 0.22 2,361 413 1,948 240 14400 0.35 0.17 2,448 550 1,898 300 18000 0.3 0.15 2,623 688 1,936 360 21600 0.26 0.13 2,728 825 1,903 480 28800 0.22 0.11 3,078 1,100 1,978 600 36000 0.18 0.09 3,148 1,375 1,773 720 43200 0.14 0.07 2,938 1,650 1,288 1080 64800 0.12 0.06 3,777 2,475 1,302 1440 86400 0.085 0.04 3,568 3,300 268 Vs Max = 1,978 cf jMaximum Storage Required 1 hour 2 hours 3 hours 4 hours 5 hours 6 hours 8 hours 10 hours 12 hours 18 hours 24 hours V sb = 5,205 cf ISeepage Bed Volume (38% Voids) V sb 15%= 5985.932239 cf Seepage Bed Volume (x 15%) Depth = 7.3 ft See age Bed Depth Required Seepage Bed Size = 15 ft wide x 55 ft long x 7.3 ft deep Vs Max = 1,978 cf Maximum Storage Required (1) 1000gal Sand and Grease Trap 6 Amcor Pre Cast A b = V sw = 3,956 sf of 6" deep swale required 1,318.6 sf V sw= 2,637 sf of 9" deep swale required 989.0 sf V sw = 1,978 sf of 12" deep swale required 659.3 sf De th = 2.3975 ft Swale Size= 15 ft wide x 55 ft long x 2.40 ft deep Velocity Through Baffle: T e: (1) 1000gal Sand and Grease Trap 6 Amcor Pre Cast A b = 4 sf See appendix D Q 10 min. 1.55 cfs 100 year Peak Q dev. At 10 min duration Velocity = 0.39 ft per sec. See ace Bed Recove Time (floorl: V s = 1,978 cf Q pert = 137.50 cf per hr Time Rec= 1 14.41 hours See a e Bed Recove Time 213 sidewalls : Vs= 1,978 cf Qerc = 112.87 cfper hr Time Rec = 17.51 hours Time Rec = 0.73 days 0.2 landscape (pervious) Impervious area = 13,625.69 sf 12944.406 sf Pervious area 27,388.57 sf 8216.571 lisf Total Area = I 41,014.26 sf I 0.521"C" of 18" deep swale required of 24" deep swale required of 36" deep swale required MANHOLE FRAME AND COVER PER IDAHO PUBLIC WORK5 5TD5. (TYP) INLET PIPE (SEE PLAN FOR ORIENTATION) TOP VIEW 8'-6- ,2--0" '-6"11 ,2 -0" { 4'-6" , 2'-0" MANHOLE FRAME AND — COVER PER IDAHO PUBLIC TO SEEPAGE BED 1NORK5 5TANDARD5. (TYP) M GRADE ADJUSTING RINGS 8 -6 w w_ W r > INLET PIPE 24" . 3 OUTLET TO WEIR ELEVATION 3 5EEPAGE BED sll n f 3'-4 1/8" SIDE VIEW f 8'-0" --� NTC)T pr% I. 1000 GALLON PREGA5T CONCRETE BOX USE FABRIGATIOR5 STARDARD 51ZE A5 MANUFACTURED BY AMCOR PREGA5T, 2. INV. IN. > WEIR ELEV. BY I" MIN. UNLE55 OTHERWISE INDICATED ON PLAN5. 3. INV. OUT < WEIR ELEV. BY 3" MIN. UNLE55 OTHERWISE INDICATED ON PLAN5. 1000 GALLON SAND 1 AND GREASE TRAP ll,:,"�