HomeMy WebLinkAboutPrimary Health Meridian - Hydrological Assessment Report (2)Primary Health Meridian City of Meridian, Ada County, Idaho HYDROLOGICAL ASSESSMENT REPORT 9-12-2013 Prepared For: Rocky Mountain Development Boise, ID Prepared By: FNGINtERS SURVEYORS PLANNERS 3023 Copper Point Dr. #201 Meridian, ID 83642 Scott Sherrow, PE Date: September 10, 2013 Primary Health Meridian Hydrological Assessment Report Primary Health Meridian INTRODUCTION...................................................................................................................................1 GENERAL PROJECT DESCRIPTION...............................................................................................1 PROJECT DESIGN CONCEPTS........................................................................................................1 HYDRAULIC ASSUMPTIONS: .................... ___ .... __ ................... ..................................................... I Table 1 — Basin Characteristics Summary .........................................................................2 Table 2 — Stormwater Summary ............................................................................................2 STORMWATERFACILITIES.............................................................................................................3 SEEPAGEBED..........................................................................................................................3 Table 3 — Seepage Bed Summary.........................................................................................3 II. Tab 1: Drawing Documents Post Development Drainage Maps Grading & Drainage Plan III. Tab 2: Calculations, Spreadsheets and Computer Model Output DB1- Seepage Bed — Volume and Flow Sand/Grease Trap Calculations IV. Tab 3: Engineering Support Documentation Strata's Geotechnical Report—August 21, 2006 Project No. 13-3023—Primary Health—Meridian- Hydrological Assessment Report LEI • 3023 Copper Point Dr. • Meridian, ID 83642 • P: 208.846.9600 ENGINEERS SURVEYORS Pt AN N E RS I. Primary Health Meridian INTRODUCTION The Primary Health Meridian project is situated within the City of Meridian, Ada County, being located in the northeast corner of the intersection of E. Overland Road and S. Wells Avenue. The Rockery Mountain Development is proposing to develop a +-5,600 sf building on approximately 0.73 acres. The purpose of this report is to determine the hydrologic impacts that the proposed development may have on the existing runoff patterns and flow characteristic from the site. This hydrological assessment was completed after review of the following information: The past development plans, topographic and boundary map information; historical storm data (Ada County); available SCS soil maps; and the Geotechnical Engineering Report prepared by Strata, Inc. This data was then analyzed with the Rational Method utilizing a computer modeling spreadsheet for the drainage basins. This program provides information on storm runoff volumes, peak rate of discharge, and storage design storage volume requirements. Design recommendations are based on the results of the analysis. GENERAL PROJECT DESCRIPTION The site is bounded on the north by E. Overland Road, to the south and west by undeveloped plated lots and to the east by S. Wells Avenue. Ground cover consists of bare dirt to light field grasses. PROJECT DESIGN CONCEPTS Storm water runoff from the portions of the building roof surface and hard scape areas will be conveyed to an oil & sand separator and to the proposed infiltration facilities. Portion of the roof system and landscape areas not subject to vehicular traffic will be conveyed to depressed areas within the landscaped areas. For additional information on the drainage basin locations and limits, refer to the drainage basin maps located in Tab 1 of this report. On-site storm water improvements for the project will consist of curb and gutters, catch basins, manholes, stormwater conveyance pipelines, sand/grease traps (pretreatment water quality structure) and the infiltration facilities. Stormwater utility improvements provided for the project will be in accordance with ACHD's Storm Water Management Manual, and per ACHD's storm water management policies as amended by the City of Meridian. The infiltration facilities will consist of underground seepage beds. For the purpose of hydrological analysis and for computer modeling of Primary Health Meridian project, the following basin conditions were modeled utilizing the Excel Spreadsheet published by ACHD Dated April 14, 2013, Seepage Beds4 Post -Development runoff Volume (100 yr storm event), to determine storage and infiltration requirements and to determine conveyance system sizing requirements, Rational Method Runoff. HYDRAULIC ASSUMPTIONS: Project No. 13-3023—Primary Health—Meridian- Hydrological Assessment Report LEI • 3023 Copper Point Dr. • Meridian, ID 83642 • P: 208.846.9600 ENGINEERS SURVEYORS PLANNERS LEI utilized the following assumptions in establishing the post -development stormwater runoff conditions for the proposed Primary Health Meridian project hydrological assessment/report: Runoff Evaluation Method: A spreadsheet program based on the Rational Method was utilized. The following Items were reviewed: • Established values from the Intensity -Duration -Frequency Curve Chart for "Zone A" from the ACHD's Storm Water Management Manual • The 100 -yr storm event with 60 minute duration was evaluated to determine the developed runoff volume. • Existing site conditions • Drainage patterns Runoff Coefficient "C": Per Section 8130.2 ACHD's Storm Water Management Manual, C values were chosen. C = 0.95, which represents the asphalt paving was used and a value of C = 0.2, which represents landscape areas. Rainfall Intensity "I": I values, are determined from the Intensity -Duration -Frequency's listed in Section 8130.2 ACHD's Storm Water Management Manual. Time to Concentration "Tc": Tc values are calculated for each basin using the FAA Method (Used by City of Boise). This method analyzes the combination of sheet flow, shallow concentrated flow, and channel flow characteristics associated for each drainage basin to arrive at an overall time which represents the length of time required for a particle of water to flow hydraulically from the most distant point in the watershed to the outlet or design point. The minimum value of 10 minutes was used in the analysis. POST DEVELOPMENT CONDITIONS Computer modeling of the design storm for the post -development condition of the Primary Health Meridian project utilizing the Rational Method produced the following results, see Table 1&2: I axle I — oasm L naractensTlcs aummar Basin Area Acres Impervious Acres Pervious Acres Avg. Runoff Coeff. D131 0.43 0.353 0.077 0.82 DB2 0.19 0.064 0.13 0.45 See computer spreadsheets Tab 2 for details. rauroa—vwnnvraacl vuuuuary Basin Storm Event Flow Rate Storage Time of (Q100) Volume req.* Conc. DB1 100 yr 1.10 1,461 10.00 DB2 100 yr 0.28 401 10.00 `See computer spreadsheets Tab 2 for details. Page 2 Project No. 13-3023 — Primary Health — Meridian - Hydrological Assessment Report LEI: •3023 Copper Point Dr. - Meridian, ID 83642 • P: 208.846.9600 [NGI4Et RS SURVEYeRS PLANNERS STORMWATER FACILITIES The stormwater disposal systems are designed to contain the 100 -year storm event. The location and parameters of the seepage bed facilities have been detailed in the construction plans for which all sheets relating to the storm water seepage beds have been included in the Tab 1 of this report. Storm water from surface runoff and the building will ultimately be conveyed either to the infiltration facilities or retained on site within the landscape areas. The storm water infiltration facilities will be configured in accordance with the general guidelines published by ACHD associated with storm water treatment/retention/infiltration and in accordance with ACHD's storm water management policies as amended by the City of Meridian. A typical sand/oil trap has been designed into the stormwater system to provide water quality treatment of the flowrate of run-off associated with the 100 yr storm event before discharging into infiltration basins. Secondary water quality treatment is provided by maintaining a three foot separation between the bottom of pond and the seasonal high ground water elevation. SEEPAGE BED The seepage beds for the Primary Health Meridian project have been designed to fully contain the 100 - year storm event. For the design of seepage beds, Strata's Geotechnical Report dated August 21, 2006 was referenced to determine soil characteristics & infiltration rates to size the seepage beds and to determine depth to bedrock. Using the data from the computer modeling spreadsheet and geotechinicl reports recommended infiltration rates; the required storage volume for the seepage bed was determined. A void space (e) of 40% was assumed and used to size the seepage beds. The Table 3 summarizes seepage beds sizing results. Table 3 — Seepage Bed Summary Seepage Width Length Depth Infiltration Actual Bed Rate Storage' ft. ft: ft. in/hr) (cu.f DB1 15 40 6 8 1,448 Length x Width x Depth x e Page 3 Project No. 13-3023 — Primary Health — Meridian - Hydrological Assessment Report LEI: •3023 Copper Point Dr. • Meridian, ID 83642 • P: 208.846.9600 TAB 1 DRAWING DOCUMENTS NVId 39VNIVMG (INV 9NIUtlH9 OHtl01'Nvlalwaw 9Niuim 3NV9 H1lV3H AHVWIHd im i3 � k 5 tl EB NVId 39VNIVMG (INV 9NIUtlH9 OHtl01'Nvlalwaw 9Niuim 3NV9 H1lV3H AHVWIHd i3 � k 5 tl EB }} CALCULATIONS SPREADSHEETS COMPUTER MODEL OUTPUT 9/4/2013 Project Primary Health Basin Data Basin ID Area Pervious Impervious CN Ave Tc Min 125yr Q25 CFS 1 100 yr in/hr Q700 CFS Acres CN=0.20 CN=0.95 I in/hr DB1 0.43 0.077 0.353 0.82 10 2.37 0.83 3.11 1.09 DB2 0.194 0.13 0.064 0.45 10 2.37 0.21 3.11 0.27 Rational Method Q = C*I*A C = 0.9 (Runoff Coefficient forthe Rational Method) A = 0.86 acres (contributing area) I = #N/A in/hr(Rainfall Intensityforthe Design Storm Duration; Design Storm Tc ___________________________________------------- 2 5 Boise Area Intensity -Duration -Frequency Intensity (inches per hour) 10 25 30 50 ________________ 100 0.17 10 min 1.21 1.67 1.96 2.37 2.44 2.73 3.11 0.25 15 min 1.02 1.41 1.66 2.00 2.06 2.30 2.62 0.33 20 min 0.85 1.17 1.37 1.67 1.72 1.91 2.28 0.42 25 min 0.74 1.01 1.19 1.44 1.48 1.65 2.02 0.50 30 min 0.71 0.98 1.15 1.39 1.43 1.59 1.82 0.58 35 min 0.59 0.81 0.95 1.14 1.18 1.31 1.50 0.67 40 min 0.54 0,74 0.87 1.05 1.08 1.20 1.37 0.75 45 min 0.50 0.68 0.81 0.97 1.00 1.11 1.26 0.83 50 min 0.47 0.64 0.75 0.90 0.93 1.04 1.17 0.92 55 min 0.45 0.62 0.73 0.88 0.90 1.01 1.15 1.00 1 hour 0.45 0.62 0.73 0.88 0.90 1.01 1.15 2.00 2 hours 0.27 0.36 0.42 0.50 0.52 0.58 0.66 3.00 3 hours 0.20 0.27 0.32 0.37 0.38 0.43 0.48 6.00 6 hours 0.13 0,17 0.20 0.23 0.24 0.27 0.30 12.00 12 hours 0.08 0.11 0.13 0.15 0.16 0.18 0.19 24.00 24 hours 0.05 0.07 0.08 0.09 0.10 0.11 0.12 ACHD Calculation Sheet for Finding Peak Discharge/Volume - Rational Method NOTE: This worksheet is intended to be a guideline to standardize ACHD checking of drainage calculations and shall not replace the Engineer's calculation methodology. These calculations shall establish a minimum requirement. The Engineer's methodology must result in facilities that meet or exceed these calculations in order to be accepted. User input in yellow cells. To accept default value type- in yellow cell and point to 1 Project Name Primary Health -Meridian Parking & Building 2 Is area drainage basin map provided? yes (map must be included with stormwater calculations) 3 Enter Design Storm For Volume (100 -year per ACHD policy) I00 4 Enter number of storage facilities (25 max) 5 Area of Drainage Sublesin (SF or Acres) Acres Acre 6 Determine the Weighted Runoff Coefficient (C) C=((CIKA1)+(C2xp2)+(CnxAn)]/A. Weighted Avl Clickto Show Moie Subuiaas 11 Subbasin 1.10 5ubbasin Subbasln Subbasin Subbasin Subbasin Subbasin Subbasin Subbasin 1 Subbasin 2 3 4 5 6 ] 8 9 10 0.43 Enter W0 Volume (Vvru= Cyr Ili am lm a above) xAx1600) Vin, 432 ft' 13 D111chon Approvei Dtsvha pe Pate to Sunoco Waters (If applicable) oafs 0.43 0.82 0.82 Calculate Overland Flow Tme of Concentration in Minutes (Tc) or use default user cawlate A 10 min [lh "1, I V ^ Calculate me Port-Proletl peak discharge (QPevi u.,• 1.10 Rs m Calculate Peak Civv9 (uses 2" storm) Com�0 i� d eUd SieXlc(am{x ra,unf.r.ax (used for S/G Tap threat valued , WQstmn conveyance rystem Bain, j Resdemam rrw>!k 05-0.44) II Csl,u late Iota l runoff v.I(V)(far sizing pitman, storages V 1,461 f[ V = C, (Trz61 parks-cewraoaln aS0-025 12 Calculate Vwq (for s Ing WO facilal es) 6121-035 nxllryyd sand. Enter Fell 'I ti I e Storm I(80th pe rc,,i=034 in) 80th 0.34 In Enter W0 Volume (Vvru= Cyr Ili am lm a above) xAx1600) Vin, 432 ft' 13 D111chon Approvei Dtsvha pe Pate to Sunoco Waters (If applicable) oafs ev0 Plnnd corehaq _ 1117111,1: 496 it, 1,029 - _ c. 1.461 tl Wimaeed Kpaxil cref kia.ts for %ar:mr, Surfzrs rsyr ofwOxi, rmnon caertai`c' Scs-re Drna.—ares,a.]a-3%w wzm.=rWmf.»eda.eu asa-a.� d eUd SieXlc(am{x ra,unf.r.ax 6.35-USa aw-o,rs Resdemam rrw>!k 05-0.44) lwMnert daalMeq re¢ a.ia Ie��rtri� and Caxemerfal t'shearcas Nrar arm 111110 I aao parks-cewraoaln aS0-025 Wahgrrusfe 6121-035 nxllryyd sand. 621-0-40 vn,,ao,ed. oto -ono soarers 9/11/2013, 11:42 AM \\Leistomge\common\Projects\Rocky Mountain Development\Primary Health McGdiam Ui ;APFYid@APnmary Health- Parking & Building ACHD Method SD Cals 2013-9.5 SAS ACHD Calculation Sheet for Sizing Seepage Bed With Optional Chambers NOTE: This worksheet is Intended to be a guideline to standardize ACHD checking of drainage calculations and shall not replace the Engineer's calculation methodology. these calculations shall establish a minimum requirement. The Engineer's methadmlogy most result in Facilities that meet or exceed these calculations in order to be accepted. Note this spreadsheet pulls information from the "Peak Cbv" tab Calculate Post -Project Flows (for pre -project flows, increase number of storage facilities to create new tab) User input in yellow cells. To accept default value type= in yellow all and point to computed cell 1 Project Name Primary Health- Meridian Parking & Building 2 Enter number of 5eepage Beds (25 max) B Design Stolrn V ,fay,:.. C Welgbted BunoH C.01cAnl c u B F' 5 Area A IA6res) Gx LSb If 6Approved drsaharge rare for tl¢ gl,cu storm if nuCalle) O.BO r1� 2 Design VPI W/B5%Sal in, Per, , B In/hf V 4VEI 0%Sxdiment for Per, W Ii 8$a t T' or l Occm Wldlh of All Drain Rock W 15.01, 9 Ser Total Design Depth of All Drain Rad D 60 ft Rock only. Dm Nol Include Pllte Sand Depth m' fi'mel 10 Void Ratio of Dra1n Rork VouB CA UA for 1.5"-1" drain rock and 3(4"Chlps star, I l Design Infiltration Rate IS III/hr mah) peo, B In/hr 12 Area lnfiltratlon Apert CBS It 13 Volmne lonidaflon Vpem 404 ft'/h, 14 Stu of or( Dr. ➢la Pipv IS In 15 CSNnIata Total Storage Pal Foal 5Pf=Apf"WAD A,., ,,xVo1d511/2Peitglen I _-.. �.-.Ili, Period tinN ro: �pvl� rt55�^ I 40 ft IE fn, 90% h, 1 i,.,.,.. n..-1 1111 1nnVnum 19 Total Length W Iwd Pipa PREF1 1 40 nREf' s�nutis„hamhe:.; ipe ml Cf»rM1bF:: V ,fay,:.. 2 YDlulce ro Soore. u P 11 3 YestiNed Chambre Width Gx LSb If anneaced Clvrnber actrch Cd ➢ 56 H ®®mss®®®® CW 3.06 h Vast Lacca IkntaBaf Cb-ambea stonage Vm ume &;ss ",tH local M. or ell Un&a Beourked 0 an 4Are.-r of k4dersa. dads. 4 voMrse hifilmown vwx sf.[ 6To— lm Bar. star, 9cP6.. wlMme In 24 sodtWmwm IE fn, 90% h, 1 i,.,.,.. n..-1 1111 1nnVnum 19 Total Length W Iwd Pipa PREF1 1 40 nREf' s�nutis„hamhe:.; ipe ml Cf»rM1bF:: V ,fay,:.. 2 YDlulce ro Soore. u P 11 3 YestiNed Chambre Width Gx LSb If anneaced Clvrnber actrch Cd ➢ 56 H inszal'kd Chamber tm®h CW 3.06 h Vast Lacca IkntaBaf Cb-ambea stonage Vm ume &;ss ",tH local M. or ell Un&a Beourked 0 an 4Are.-r of k4dersa. dads. 4 voMrse hifilmown vwx sf.[ 6To— lm Bar. star, 9cP6.. wlMme In 24 sodtWmwm 9/11/2013,11:44 AM \\Leisiorage\common\PraJeRs\Pocky Mountain DevelopmentrPdm3ry Health Meridian\Sto,t,Or fnnw,WAm rpQ0 kR1th - Parking & Building ACHD Method SD Cals 2013-9-S 3A5 ACHD Calculation Sheet for Sand/Grease Traps NOTE: This worksheet is intended to be a guideline to standardize ACHD checking of drainage calculations and shall not replace the Engineer's calculation methodology. These calculations shall establish a minimum requirement. The Engineer's methodology must result in facilities that meet or exceed these calculations in order to be accepted. Steps for Sand/Grease Trap Velocity Calculation User input in yellow cells. To accept default value type = in yellow cell and point to computed cel 1 Project Name Primary Health - Meridian Parking & Building [Hier npmper UT>ana/urease (raps 10 maxi 1 reference for Throat widths (inch) Baffle Throat Boise VeIn ty the Vault Size Number of Peak Flow Spacing width Area (ftz) 0.5 fps el Vel 1000 G S/G Traps Q -ds inch inch 60.0 max. ok? 1000 G I 1 1.1 19 48 6.33 0.17 60 reference for Throat widths (inch) \\Leistorage\common\Projects\Rocky Mountain Development\Primary Health Meridian\Storm Drainage\Primary HEWn/-2Rir%idA&4 AM Building ACHD Method SD Cals 2013-9-5 SAS Version 5.5, April 2013 ADS Boise Vault Lar -ken WQU, BMP 16 1000 G 48.0 50.5 n/a 1500 G 60.0 61.5 n/a NQU1000 n/a n/a 60 NQU1500 n/a n/a 60 \\Leistorage\common\Projects\Rocky Mountain Development\Primary Health Meridian\Storm Drainage\Primary HEWn/-2Rir%idA&4 AM Building ACHD Method SD Cals 2013-9-5 SAS Version 5.5, April 2013 ACHD Calculation Sheet for Finding Peak Discharge/Volume - Rational Method NOTE: This worksheet is intended to be a guideline to standardize ACHD checking of drainage calculations and shall not replace the Engineer's calculation methodology. These calculations shall establish a minimum requirement. The Engineer's methodology must result in facilities that meet or exceed these calculations in order t0 be accepted. Steps for Peak Discharge Rate wring the Rational Method caieulated for post bojau Calculate Post -Project Flows (far pre -project flows, increase number of storage facilities to create new tab) User input in yellow cells. To accept default value type = in yellow cell and point to computed cell 1 Project Name Primary Health - Meridian - Building&Landscape 2 is area drainage basin map provided? Yes (mop must be included with stormwater calculations) 3 Enter Design Storm For Volume (100 -year per ACHD policy) 100 4 Enter number ofstorage facilities (25 max) 5 Area of Drainage Subbasin (SF or Acres) Acres Acre 6 Determine the Weighted Runoff Coefficient (C) C=((C1xA1)+(C2xA )+(CnxArd]/A Weighted Asti F1 Subbasin a.0 nvn Subbasin Subbasin Subbasin Subbasin Subbasin Subbasin Subbasin Subbasin 1 Subbasin2 3 4 5 6 ] 8 9 10 0.19 VJFT c 8'1' saee4 0.19 0.45 0.45 ]Calculate Overland Flow Time of Concentration in Minutes(Tc) or use default !k_ cxsxaie A 10 min mAitr.—� V nage Sanwa nmeou, r9., nm 'm an a.0 nvn 9 Calculate the Post-Pfo]ect peak bsclerge(OPeakl 0,111 024 cfs to Cakuiate Peak Caul fuses 2y strai 4.. 0.10 Os (used for SAG Tay tivoat aloofly. WOsterm conveyance system sizing ] 4s5-aS2 461.Ti 11 Calculate total runoff.. V)Ifor Shing primary swrage) V 354 IL' V = Ci (rc=60)Ax36(10 a]ff I 2 Calculate Vwq (for suing WO f idi tles) 295 Enter Pereenttle Storm I (BOB, percentile=0.34 m) 00th 0.34 m Fater WO Velum, V,L"- Cxi(from bne above)xA.3600) V111 105 ft .� Detention: Approved Discharge Pate to SUHace Waters (if applicable) cis -; volt:,, Sn,m,aoy -,L, J 1'VUP b..v ;-i r +'nen: 129 ftC - 3S4 Il 9/11/2013,12:29 PM \\Leist... ge\common\Pmjects\Rocky Mountain Development\Primary Health MCMdie atS 5abiri "arfigorPrimary Health - Landscape & Building ACHD Method SD Cals 2013-9-5 SAS Mill ivWl cowil e+as fore 5®b¢s ryPcofsaf. all Cawfil 'C- 5".,. cv. racoon Wean am -2,95 41541 -am S:oi:e.hreilr htul�eY.mitT 4s5-aS2 461.Ti Resdenai. Vr xxf ass -ate r'.Oab,Ix tdwel&Le beffi a]ff loaun i aev Ca+vanmF we., u. 295 Parris- vemeeemn aaa-ass im,.dc. mm_* 5 .^ailraad lxrd xea an 0441 dr,ern, a ,rem VJFT c 8'1' saee4 9/11/2013,12:29 PM \\Leist... ge\common\Pmjects\Rocky Mountain Development\Primary Health MCMdie atS 5abiri "arfigorPrimary Health - Landscape & Building ACHD Method SD Cals 2013-9-5 SAS ACHD Calculation Sheet for Sizing Ponds NOTE: This worksheet is intended to be a guideline to standardize ACHD checking of drainage calculations and shall not replace the Engineer's calculation methodology, These calculations shall establish a minimum requirement The Engineer's methodology must result in faciligeethat meet or exceed these rahulatmm In order to be accepted. User Input M yellow cells. To accept defauh value type= in yellow cell and point to computed sell I Pralect Name Primary Heahh-Meridian- Building& Wndempe um. re nrlV=S.I t ]00 link,,: Le,. r i.... ... OOO ria i V 407 fly .n -.r_. 1 nv ✓ omdHm'f .eh serge, m,ye vNv. Storm rotation I Ito 1.1 I Q RumfVoll Perc Vol I preI I Tnml Msa Vol risrbarge Discharge I Reed sA Stage Ohl New Rags (k( good! PUM surface, oAc 5F45bpe WMhat lxngtbai sur (kyl 5(4.11 5[age(F[f Stage (h"( ,.,Lou, 0 Felc t I vahmn Seage lh'( verm"gle lig WldHl It 11-l" InI W AO IS Lngtl i o l Eui Ol lita m I.. 150.0 u side a.m. DUvy Hn' 3.W f3 Enmr Bnunm rc—tru, Iski Ie Encu. cup Banc 6"51,on lmsa lF Ema, VVII III aze 11—IGn fwSEl IDSSB ,gi 111 mz Berwuen,,relay and 1, alv Ea.n. d,n I i n 0.00 [S Enz-r E4valinn II 303.50 IH Liles , ligh 5rqundWatm Elwr�tlr,,n O.oO11 I _ Mm l , c,hnn,d B.m di, rFIr ..50 5 In/hr III c rIA IIIvl, icnnI, ISI LI I Ii m,riil. E 01hlmmul,"I I k_., 21 Sind window At,e I.I IIehaV A.1 l0 ft Enle, owIn,Inlil,lo, Storm rotation I Ito 1.1 I Q RumfVoll Perc Vol I preI I Tnml Msa Vol risrbarge Discharge I Reed sA Stage Ohl New Rags (k( good! PUM surface, oAc 5F45bpe WMhat lxngtbai sur (kyl 5(4.11 5[age(F[f Stage (h"( SarM E. 0— AreaAw Stege (hs( n'i. ArnaAnl OVERIDE OVERIOE vahmn Seage lh'( 1111Jli, 103Lo i W[I J.P LRo g(fl ty [Mil 1141511 100 is lR4_M 'I VII, ?.rev, 15111 ;5N9 s5 e— I. "I It ISt_5 33., 15f.b 13.3 Ifl%t 1, l3 I,S;n — rr.,in tnrnor,. ", to 5n,.i adrahl. ,rebay Siu r, sPk-lnnic In tMltai,. 1 neunl 9/1112013; 1230 PM \\Leirtaage\rnmmon\prolcGs\Rocky Mountain Development\Pnmary Health Meridian\Storm Draln'yscredistOigni &pelt g nrdscape & Building ACHD Method SD Cal, 2o13-95 SAS TAB 3 GEOTECHNICAL REPORT STRe3Ta <fOFEC,••cG,q. lNPREEl+�hG d MP1fNtM5 IFSi WG -rna`�' Frov iH¢Ejr o..r�p Vr Mr. Taylor Merrill The West Park Company, Inc. P.O. Box 344 Meridian, ID 83642 Dear Mr. Merrill: August 21, 2006 File: WESTCO B06186A RE LETTER REPORT Preliminary Geotechnical Evaluation Proposed Commercial Development Overland Road and Eagle Road Meridian, Idaho STRATA, Inc. is pleased to present our authorized preliminary geotechnical evaluation for the proposed commercial development on an approximate 80 -acre property located south and west of the intersection of Overland Road and Eagle Road in Meridian, Idaho. The purpose of our services was to provide you with the preliminary information that may assist your planning and conceptual design efforts for the overall development. Additionally, STRATA has performed an evaluation of near -surface soils in the northern portion of the site with respect to placement of structural fill, and support of lightly loaded commercial structures in this area. Our services were performed referencing our confirming proposal dated August 7, 2006. PROJECT UNDERSTANDING We understand you plan to develop an approximate 80 -acre parcel for future retail and commercial development, as well as residential development. Commercial and retail development is anticipated to be located in the northern and central portions of the site, with residential development proposed in the southern portion. The site will be accessed from Overland Road to the north and by local streets to the east and west. FIELD EXPLORATION AND LABORATORY TESTING On August 9, 2006, STRATA observed the excavation of 11 test pits across the subject property. Test pit locations are presented on Plate 1, Site Plan and were approximately located in the field relative to existing site features. Test pit locations were not surveyed, but were labeled and staked in the field, so the locations may be documented at a later time period. Test pits were loosely backfilled roughly level with the ground surface at the completion of our field investigation. We recommend all test pit backfill be re - excavated to sufficient depth to expose native soil, and replaced with structural fill. This will heap to reduce the potential for localized test pit backfill settlement. The soils encountered within the test pits were described and classified referencing ASTM D 2487 and ASTM D 2488, Unified Soil Classificat€on System (USCS). The test pit logs and a brief explanation of the USCS are presented in the Appendix Select soil wwwstratageote<h.cn m Proposed Commercial Developmern Overland Road and Eagle Road File: WESTCO B06186A Paget samples were obtained for index laboratory testing. Index laboratory test results are presented on individual test pit logs. Subsurface Conditions Soils encountered within the test pits generally consist of lean clay at or near ground surface, overlying variably cemented clayey sand, silty sand, and silt grading to poorly - graded gravel or silty gravel with depth- Lean clay was typically observed at ground surface in all test pits, and was generally described as brown to dark brown. very stiff to hard and slightly moist to moist. Clay soils were observed to extend to depths of approximately 0.5 to as deep as 4 feet below ground surface with the depth of clay typically increasing from north to south. Underlying near -surface clay, light brown to reddish -brown, very stiff to hard, sandy silt, dense to very dense silty and clayey sand was observed. Calcium -carbonate cementation was observed throughout these soils to varying degrees, with these soils extending to depths of 2 to 4 feet in the northern portion of the site and to depths of 4.5 to in excess of 10 feet for the remainder of the site. Poorly -graded gravel and/or silty gravel with sand was typically encountered in test pits underlying cemented soils. The depth to silty gravel and poorly -graded gravel was observed to vary significantly with gravel typically present at depths of 2 to 6 feet in the northern portion of the site, becoming deeper in the southern portion of the site with gravel not encountered within the exploration depths in some locations. Groundwater was not encountered within the depths explored during this investigation. Groundwater levels in the site vicinity are related to agricultural and commercial irrigation as well as canal leakage in the general area. Based on our knowledge of the site, observed subsurface conditions, and review of topographic information, we anticipate that groundwater will remain at depths of greater than approximately 15 to 20 feet below ground surface throughout the year. However, note that groundwater levels may vary with seasonal changes in irrigation, precipitation, infiltration, and development to the project site. These groundwater depths are only an estimate and some seasonal and yearly fluctuation may be observed. PRELIMINARY GEOTECHNICAL OPINIONS AND RECOMMENDATIONS It is our preliminary opinion the site is suitable, from a geotechnical standpoint, for future commercial development and associated infrastructure provided the recommendations outlined in this letter and future evaluation for the site development plan are accomplished. The findings contained herein reflect our understanding of the project concepts and subsurface conditions encountered during exploration- The opinions provided herein should be used only for planning and not final design STRATA can provide final geotechnical recommendations relative to foundation and slab pavement design, site grading and drainage, and subsurface stormwater disposal as the design of the project develops. www.stratageatech.com -