CONTRACT CHANGE ORDER
CHANGE ORDER NO. 1
PROJECT N0.
10507.B
DATE:
5/19/2016
EFFECTIVE DATE:
6/19/2015
CONTRACTOR: CASCADE ENTERPRISES, INC.
PROJECT: WWTP SAFETY UPGRADES
The Contractor Is horeby directed to make the following changes from the Contract Documents and Plans,
Doscription:
THE CONTRACTOR PRESENTED A BETTER SOLUTION FOR THE DIGESTER #3 STAIRS AND A
NEW LADDER TO ACCESS THE TOP OF THE DIGESTER.
Reason for Change Order:
THE CONTRACTOR PRESENTED A BETTER SOLUTION FOR THE DIGESTER #3 STAIRS TO
MODIFY THE ANGLE THE STAIRS WERE PLACED AND ADJUST THE WIDTH. ALSO THE
EXISTING LADDER TO THE ROOF OF THE DIGESTER WAS REPLACED WITH A NEW LADDER
THAT TIED INTO THE NEW STAIRS AND PLATFORM.
Attachments:
CONTRACTOR ESTIMATE
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price $ $ 48,928.00
Original Contract Times: 60
Net changes form previous Change Orders
Net changes form previous Change Orders
No.`to_,
No._lo_ (calendardays)
$
0
Contract Price Prior to this Change Order:
Contract Times prior to [his Change Order:
(calendardays)
$ 48,928.40
60
Net Increase (decrease) of this Change Order:
Net Increase (decrease) of this Change Order:
(calendardays)
$ 11,072.00
60
Contract Price with all Approved Change Orders:
Contract Times vdth all Approved Change Orders:
(calendardays)
$ 60,000.00
120
APPROVED: (CITY PURCHASING AGEN
ACCEP�gD. onlfactof)CAS EFJtTERPMSES
113y: Keith Walls /
Y
Date: G ! 5/
Dale: CSS�cr
RECOMMENDEEP: (Pro%ject,ivul ger) .,
Gprrick'tlelson '-''
nPrena
Dale: 18 May -15 p4°
0
co sr
IAI ItKI�
,y City of
jJaycee L. Holman
-?//s-
TRF Asea
03/03/15
Emily Skoro,
C/o City of Meridian
33 E. Broadway Ave.
Suite 200
Meridian, ID 83642
Project#10029A
Re: W WTP Safety Improvement Project Digester No.3 Alternate Pricing
Scope of Work: Access Stairs & Cantilevered Platform:
Cell: (208) 991.7146
Office: (208) 343.4009
Fax: (208)343.4838
7512 Lemhi St. Suite 3 — Boise, ID 83709
ryan@cascade-enterprises.com
PWC -C -003516 -AA -1-3-4
1) Galvanized Stairway w Aluminum Handrail & Cantilevered Landing (Straight) .................$ 18,860.00
a. Includes Saw -cutting Existing Asphalt
b. Includes 3ea 8" X 24" X 48" Slab Footings
C. Includes Mid -Landing at half -way point of stairs
d. Includes Ships Ladder Access to Digester Lid
e. Includes Shop Drawings
f. Does not Include Engineering
Original Scope @ Digester Access:
1) Platform & Access Modifications.................................................................................................$ 9,516.00
Total Change (Add) to Original Contract:
1) New Stair Proposed less Original Scope......................................................................................$ 9,344.00
a. Request additional 20 days for Change in Scope (pending approvals)
Final Design Additions:
1) Grating & Treads $ 698.00
2) Channel/HSS $ 473.67
3) Extra lbs to Galvanize $ 339.78
4) Detailing $ 500.00
5) Railing $ 992.00
6) Labor S 520.00
7) Subtotal $3,523.45
8) Subs OH& P @ 15% $ 528.52
9) Cascade OH& p @ 10% $ 405.20
10) Cost Impact $4,457.17
Total Change (Add) to Original Contract
1) Upon Approval of Additional Costs.............................................................................................$ 13,801.17
Sincerely,
Ryan Steinwand
Account/Project Manager