HomeMy WebLinkAboutChange Order No 6 with Tuffy Excavation for WWTP Maintenance BuildingCITY OF MERIDIAN
33 EAST BROADWAY AVENUE
MERIDIAN, ID 83642
CONTRACT CHANGE ORDER
Change Order No.:
6
Project Number:
10163
Date:
4/10/2015
Effective Date:
4/10/2015
CONTRACTOR: BP #02 Tuffy Excavation
PROJECT: WWTP Maintenance Building
y�T
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description: $42,897.16
Additional site concrete, ADA ramp, paving and striping per City of Meridian direction. -
Attachment(s): Tuffy pricing dated 3/27/15
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price: $133,164.00
Original Contract Completion Date:
Original Contract Completion Days:
Net changes from previous C.O.'s.:
Net Days change form previous C.O.'s:
No. 0 to 0
No. 0 to 0
$52,172.60
Contract Price Prior to this C.O.:
Contract Completion Date before this C.O.:
$185,336.60
Net Increase (decrease) of this C.O.:
Net Days Increase (decrease) of this C.O.:
$42,897.16
Contract Price with all Approved C.O.'s:
Contract Completion Date with all Approved C.O.'s:
$228,233.76
RECOMMENDED: (CONSTRUCTION M6WAG&RL
REVIEWED: (PROJECT MANAGER)
J
By: Bryce Parker
By: David Allison
Date: /fes// S—
Date:
S S
AX T�IED:(CONTRACTOR)
APPROVED: (CITY PURCHA NGA NT)
BY��CCJJJJ /�`'�o'�A
By: Keith Watts
Date:
pTED qff
ate:
APPROV
o
ity of
By: Mayor T my a lJ eerd E IDI
it) Clerk, Jaycee L. o an
Date: 6—W Io
®et S
r JryH1 W
'`mf ,nom
R �r rOe iRF A5U55 y] n e
1Jbeniton
CON ST R U OT 1 O N
City of Meridian - Maintenance Building CM Project #21318
3401 N. Ten Mile Rd,
Meridian. ID 83642
Change Order Request
COR -027
Change Order Request: 027 for City Project #10163 Date:09/09/2015
To: From: Bryce Parker
CTA, Inc. Beniton Construction Company
800 West Main Street, Suite 800 P.O. Box 838
Boise, ID 83702 Meridian, ID 83680
Description
Category Status
,nal Sitework / Paving and Landscaping
-iir�r1l ,lUMM Y. "T -J"1.
Additional Sitework / Paving & Landscaping
4/15/2015
$44,532.16
Tully Excavation - Additional site concrete, ADA ramp, paving and striping per City of Meridian direction.
Lawn Co. - Additional landscape scope to coordinate patchback of maintenance and ops building utilities.
Approved By:
Construction Manager. Bryce Parker
Discipline Engineer #1:
Discipline Engineer #2:
Nle
Architect: Brock Martinson
Dated:
Dated:
Dated:
Dated:
$42,897.16
$ 1,635.00
$44,532.16
uffy Excavation, Inco
We'll Do Your DIRTy Work!
4028 Banner St. ■ Boise, Idaho 83709 ■ (208) 562-1720 ■ Fax: 562-1716
Public Works License # 13709-A-4(03300;02220;02310;02318;02740;02500;02855)
Contractor Registration # RCE-4530
Change Order # 9
VOIDS Out Change Orders 7 & 8
All Additional Sitework as of 3-27-15 Bryce, Cam, Ron M Site Walk
Demo North of New Maint Bldg & Controls Bldg. Repave & Concrete Work
City of Meridian Beniton
Meridian Idaho
Date: March 28, 2015
Project: WWTP Bid Package # 2 Owner/Contractor: City of Meridian Beniton
Location: 3401 N Ten Mile Rd Engineer: Keller Associates
Meridian ID Date of Plans: Per Beniton Direction
BID INCLUDES:
SCOPE OF WORK
ITEM
NO.
DESCRIPTION
QTY
UNIT
UNIT COST
TOTAL COST
Demo North of
(1)
Demo Asphalt 2.5
7192
SF
@
$
0.58
$ 4,171.36
Maint Bldg &
Thick & Existing
Controls Bldg -
Vertical Curbs &
Parking Asphalt &
Planters
Curbs & Islands &
Old ADA Ramp
New Asphalt Pave
(2)
Cut to Subgrades
7192
SF
@
$
1.07
$ 7,695.44
Areas
(3)
14" Structural Fill (In
1940
SF
@
$
0.93
$ 1,804.20
Planter Demo Areas
Only)
(4)
4" Aggregate Base
7192
SF
@
$
0.56
$ 4,027.52
(5)
3" Asphalt Paving
7192
SF
@
$
1.52
$ 10,931.84
Heavy Traffic Lanes
1 of 3
Project: WWTP Bid Package # 2 Owner/Contractor: City of Meridian Beniton
Location: 3401 N Ten Mile Rd Engineer: Keller Associates
Meridian ID Date of Plans: Per Beniton Direction
Prep for
Sidewalks North
Side of Controls
Bldg & East Side
of Operations
Bldg. ADA Ramp
(1) Each & Vertical
Curb Prep.
Concrete
Sidewalk Pours &
Thickend Edge
New Concrete
ADA Ramp
Stripping &
Signage
Mobilization
(6)
(7)
Cut to Subgrade & 1 LS @
Aggregate Base
Concrete 1428 SF @
Subcontractor Prices
$ 2,794.80 $
$ 6.00 $
2,794.80
8,568.00
(8)
Pour with New 1
EA @
$
572.00 $ 572.00
Truncated Dome
(9)
Restripe Parking Lot 1
LS @
$
550.00 $ .550.00
ADA Stalls & ADA
Signs
(10)
1
LS @
$
550.00 $ 550.00
Total
42,897.16
No Charge NOTICE
Includes Clearing & Grubbing Areas at Former Beniton Job Trailers Location
NOTICE:
Work Must be Done During Favorable Weather and While Mobilized.
All Asphalt Paving to be done during Final Paving for Maintenance Building
All work to be completed according to the project specifications and standard practices. Tuffy will be paid for
actual quantities installed. Progress payments are due upon each 30 day billing.
r ne amount aue snail bear interest at 1.5% from the date of the billing,
We assume that the project will be constructed during Favorable weather conditions. Should the on site soils
become frozen or saturated to the point that it becomes Not cost effective to continue Tuffy will cease operations
all operations until such time as the soils thaw and dry to the point that work can continue in a profitable
manner or until such time as an additional compensation agreement is reached and executed.
Any alterations to the project specifications, which involve an increase in cost, will only be performed with an
WAU�UL=u Uncnyo U1UU1 wniur win become an aaamon to the contract amount.
Tuffy reserves the right to withdraw this proposal if not accepted within 15 days.
We require a signed copy of this proposal be returned to Tuffy upon acceptance or award.
2of3
Project: WWTP Bid Package # 2 Owner/Contractor: City of Meridian Beniton
Location: 3401 N Ten Mile Rd Engineer: Keller Associates
Meridian ID Date of Plans: Per Beniton Direction
Upon acceptance this proposal shall become part of the contract documents!
Tuffy Excavation, Inc,
Authorized Signature: Date:
Acceptance of Proposal - The above prices are acceptable, and Tuffy Excavation, Inc. is authorized to perform the
work listed above.
Authorized Signature:
3of3
Date: