HomeMy WebLinkAboutExecuted CO1 to Task Order 10454a.d1 SPF Storm Drainage ImprovementsCITY OF MERIDIAN
33 EAST BROADWAY AVENUE
MERIDIAN, ID 83642
CONTRACT CHANGE ORDER
Change Order No.: 1
Project Number.
10454
Date:
115/2015
Effective Date:
1/5/2015
CONTRACTOR: SPF Water Engineering
PROJECT: WWTP Stormwater and Asphalt Repairs
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description:
Design of additonal drainage area *6
Completion of As -Built Drawings
Reason for Change Order:
Change of work requested by the City. m
Attachments:
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price: $24,950.00
Original Contract Completion Date:
Original Contract Completion Days:
Net changes from previous C.O.'s.:
Net Days change form previous C.O.'s:
No. Q to Q
No. Q to Q
$0.00
Contract Price Prior to this C.O.:
Contract Completion Date before this C.O.:
$24,950.00
Net Increase (decrease) of this C.O.:
Net Days Increase (decrease) of this C.O.:
$5,000.00
Contract Price with all Approved C.O: s:
Contract Completion Date with all Approved C.O.'s:
$29,950.00
REVIEWED: (PRO NAG
4�_
ACCEPTED: (CONTRA TOR
By: David Aillso
By;
Date: 11511,5
Date: 1 � r, 2 p/5'
APPROVED: (CITY PURCHASING GENT)
By: Keith Watts
Date: