Change Order No 1 with Sletten Construction for Well 21 Iron and Manganese Removal
CITY OF MERIDIAN CHANGE ORDER NO. 1 33 EAST BROADWAY PROJECT NO. 10340.F MERIDIAN, ID 83642 DATE: 4/21/2015 EFFECTIVE DATE: 2/27/2015 CONTRACT CHANGE ORDER CONTRACTOR: Sletten Construtlon Company PROJECT: WELL 21 IRON AND MANGANESE REMOVAL / TREATMENT FACILITY The Contractor Is hereby directed to make the following changes from the Contract Documents and Plans. Description: 1. Revise pipe route for the gravity sanitary sewer lateral. (See WCD 001) 2. Change the horizontal metal siding, fascia and soffit panels to Cement Fiber Board. (See WCD 002) 3. Add Arc Flash Hazard analysis and installation of labels to all panels and service equipment. (See WCD 003) 4. Increase fence height from 6 feet to 8 feet. (See attached Quote) 5. Provide an exterior hose bib within the bulk storage tank enclosure. (See WCD 005) 6. Change Sodium Hypochlorite Transfer Pump suction piping and vent line between bulk storage tank and transfer pump to 2" diameter instead of 1"diameter. (See WCD 006) 7. Add a 20"x24" access panel in ceiling of existing building to allow access to the attic fan. (See attached Quote) Reason for Change Order: Design Changes Attachments: WCD's 001— 003 & WCD's 005-006 & Cost Proposals 134250-02 and 134250-07 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $ 5117,100.00 Original Contract Times: October 1, 2014 to April 10, 2015 Net changes form previous Change Orders Net changes form previous Change Orders No.— to No._to_ (calendardays) $0.00 None Contract Price Prior to this Change Order: Contract Times poor to this Change Order: (calendardays) $587,100.00 192 days Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order: (calendardays) $32,836.13 Mays Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders: (calendardays) $619,936.13,Ks - October 1, 2014 to April 17, 2015 APPROVED: (CITY PURCHA ING NAGER 2` ACCEPT f): SI on Ian o any) o By: Keith Watts I �I AE ►'d ?f90 Ha en 1 Date: 4 Z / �,J y IS m 4 RECOMMENDED: (Project Manager) ^ S WE APP ED BY COUNCIL '� b By: Cllnl Worthington. / ' T o ATURE REQUIRED Date: z2 DATE: 1'-1 APPR CI --- ATTEBT: j-m® By: Mayor Tjrfimyy�/e Weed! By: City Cler , Ja ee L. Holman M CONSTRUCTION • DESIGN BUILD y COMPANiSS LAS VEGAS • PHOENIX • GREAT FALLS • BOISE • CODY City of Meridian 33 East Broadway Avenue Meridian, Idaho 83642 Aft: Clint Worthington Project: Well 21 Iron and Manganese Removal Facility SCC Project No. 134250 COST PROPOSAL NO: 134250-01 Date: 02-Oct-14 DOCUMENT REFERENCE: WCD 001 Date: 20-Sep-14 cc: Field / File DESCRIPTION: Please find below and attached the costs associated with the sanitary sewer revisions requested by CH2M Hill in Work Change Directive (WCD) No. 001. Labor MatUExpense/Rental Subcontracti Description Qty Unit MH Type Rate Cost Unit Rate Cost Costs T.A. Dibble Excavation Added Manhole & 8" Sewer 1 LS $10,061.00 SUBTOTALS Labor,Mat°I,Sub) 1 $0.001 0.001 $10,061.00 Subtotal $10,061.00 *Due to this Change The Contract Time will be increased OH @ 10 % $1,006.10 decreased Profit @ 5% $553.36 _X_ unchanged Bonds & Insurance @ 2% $232.41 to be determined by( ) days COST PROPOSAL TOTAL $11,852.86 * PLEASE REVIEW AND SIGN BELOW FOR INCLUSION INTO THE NEXT OWNER CHANGE ORDER. Sletten Companies X Dated: 6202 W. Gowen Road Ron Hagen - Project Manager Boise, ID 83709 X Dated: Phone: 208-658-9888 Fax: 208-658-8626 X Dated: 7 T. A. Dibble Excavation, Inc. !f _ 1 Commercial and Industrial {I Public Works # 11117-A-4 Idaho Contractors License RCE-5255 Sletten Construction Boise, ID Attn: Jerry Hine 1200 W. Lake Hazel Lane Boise, Idaho 83705 (208) 866-0405 Ceti FAX (208) 344-3004 September 29, 2014 Re: TA Job #0-020 Well 21— Meridian Change Order Request Add 8" Sewer & Manhole This is our Change Order Request for the additional work to add 49 ft. of 8" sewer line and add 1 ea. Manhole, including excavation, materials, labor and equipment as follows: 1 ea. 48" Manhole @ $5,945/ea. 49 ft. 8" Sewer Pipe @ $84/ft. Total Change Order Request If you have any questions, call my cell at 869-2345 Thanks Tyler Dibble tdibble@tadibble.com 208-869-2345 Equal Opportunity Employer Certified WBE Contractor $ 5,945.00 4,116.0 $1 .00 WORK CHANGE DIRECTIVE No. 001 PROJECT: WELL 21 IRON AND MANGANESE REMOVAL PROJECT DATE OF ISSUANCE: September 18, 2014 EFFECTIVE DATE: date of Authorization by Owner OWNER: City of Meridian Project No. CONTRACTOR: Sletten Construction ENGINEER: CH2M HILL You are directed to provide a price quotation for the following change(s): Revised pipe route for the gravity sanity sewer lateral from the new Well 21 Treatment Room to the tie-in location with the existing sanitary sewer located to the east of the Well 21 site. Purpose of Work Change Directive: Sanitary sewer pipe re-routed to keep the pipe on City property. If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change order based thereon will involve one or more of the following methods of determining the effect of the change(s). Method of determining change in Contract Price: Method of determining change in Contract Times: ❑ Unit Prices ❑ Contractor's records ❑ Lump Sum ❑ Engineer's records ❑ Other ❑ Other Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times: $ Substantial Completion: 0 days; Ready If the change involves an increase, the estimated amount for final payment: 0 days. If the change is not to be exceeded without further authorization. involves an increase, the estimated times are not to be exceeded without further authorization. RECOMMEND by ENGINEER: AUTHORIZED by OWNER: I2 (Authorized Signature) (Authorized Signature) S1NWmoo0 019 „° v�rlarv�i usiu oum��n°m-u.a Qo 1i1° vonar�i'.w..w.m'.�"'a. � S � � xnw •°mww R � S%i wn ae Nasln3e ova N•aN �°e,�n..ua.o�we...ueeu.rvw°wn � s R 80 YiaiS SWLIM•It Ohm SIOLEO Y YI > •e° l=�°�+ NVId 1f10Abl 3115 F ��'���` °111HWZH� � �9• a g � � � ibyy5b@@((^ 1V Y a SW£ Enw u a °m I'M IN p z - Y W 5 ¢qeq s RR m w G c H 3 i�2ga 3��' 'ufm �. S ii 0 itz E;@ 115 ES Y o m oa5s ' x 5 0g off= a o a wg a _ w �'? k 3 e ; w t; 8< m 8W7 m $ �3U€ s sg €ALL m�s s z� s<oo I I I 1 ol I � I j p I AS a NIW m'1 NNI.I• 6 I I i I I 55 I \ ° oar uj uj W U fn a 5° r lx Qm ° ° 14 ! Z- 3 s �w CL 4 � b`� �uwiffi a � 4- P-s rXXn0 QQ w W S W U u W K z ir 7N O*l�. o�'m I tFF3— le -- _ _ I ° �as >C u3m oval ss��r .Pme S1N3wn000 018 san.P o�. a;uau r�vgrrvo� usla ou e��m maunalu,ae �W wgarzr�ll ����N� }q g a POWPP TN.na ,i x0 WIN uw6KC PNwuM'IJND A V WI "�'p y'PVWI � � i $ j MdV AB NdS1A3tl 31V0 'ON Npatj WUA�a,l PnmP�tl �uu�Gwry Numl 2 • '' "'""'"""'""""i0'"" "0L°0 Us NVld 3JVNIV210 ONV JNIdVUE) a d ugGVNYp W] VN] Y �I L40EL !� '�,s� ° rY W s a s � 81g" F— a LL� _ m�8� �1 Z o i a a m o EPA €Wo s O J 8 to m=8 h° l Z H Eq n rr� 2 W gf m 3 HI, Hod E 92 dg m 4 W ass tl I I I I I I I so I I I � I I a 1s,e� os uez I I I I • M, 1619 � I I � I I�s 1P SS / OU�;§ m �CS0-g WUv)�' 3 F— _ 3 �Q� C LLI 7 4 a mom m 3 0 � 0 . zm ig m..m.eunr,w ,�e.,..woe .Puriaw 3u`uu"�iuiiv..,.wieiu::w_,.�:�::ww ri'isb :diiwo:vd.wMiiau�:::viu'o�:' moauu :u,m.�mMauw b1Ny W11JUU Uld awn.P:-0n». n whaa�i sivasoue W 01�1a 111 ronartr•� P 0'..M wrfll>'rY. x0 1gg 0lN eP GrCe e4Mr.l lAtPtW ondv xe r+aslnau azva or+ uw•it»Pn»,in•P»e..».ewrvw.»n 3lldOMd ONV NVId ua n masawuers-t.avn �pi T a3M3S A2lVlINVS � d L40£L .�rvrpwn 'Wo � �� '�•;';���' '711HWZHJ � ��. � a MAN * � i5l3AlAi NI /QNS 1' rli soli. En � �- ���.��� ������� � stFli}II nNI Mui Mltl ' 8 w F- E li sNDO �NraW Zy ss r r� Wi 11 W 1 s ry g _ g y; I a ogo En ESE RE o 04 !yFxfig zt{o{L.tao g ag¢� € Z66AAL•NI ANI $ it 7 b t3 MWE-NEI a 3 3 u 3gKi ` a < g9, Z �a � RM g H of lima 1 /�. 0. U a� �r �1 2 q 9 B v g R n t n ry 2AR 8 R o CONSTRUCTION • DESIGN BUILD � � � COMi�AMiSS LAS VEGAS • PHOENIX • GREAT FALLS • BOISE • CODY City of Meridian 33 East Broadway Avenue Meridian, Idaho 83642 Aft: Clint Worthington Project: Well 21 Iron and Manganese Removal Facility SCC Project No. 134250 COST PROPOSAL NO: 134250-06 Date: 17-Mar-15 DOCUMENT REFERENCE: WCD 002 Date: 18-Nov-14 cc: Field / File DESCRIPTION: Please find below and attached the costs associated with the siding & fascia revisions associated with WCD 002. Theese costs are essentially only for the sheathing underlayment and the painting costs as the actual siding, soffit, and fascia costs are offset with the credits for the prefinished metal originally shown. Added exterior sheathing under siding Paint allowance for siding, soffits, fascia, & trim that were otherwise unfinished cement siding, soffit, and fascia costs material and instal costs are offset with credit from original prefinished metal mtrls ISUBTOTALS (Labor Qty Unit MH 224 SF 8 843 SF *Due to this Change The Contract Time will be Rate Cost Unit Rate Cost 32.50 $260.00 SF $0.93 $ 208.32 $ 260.001 $ 208.32 J $ Subtotal increased OH @ 10 % decreased Profit @ 5% _X_ unchanged Bonds & Insurance @ 2% to be determined by( ) days COST PROPOSAL TOTAL * PLEASE REVIEW AND SIGN BELOW FOR INCLUSION INTO THE NEXT OWNER CHANGE ORDER. Sletten Companies X Dated: 6202 W. Gowen Road Ron Hagen - Project Manager Boise, ID 83709 X Dated: Phone: 208-658-9888 Fax: 208-658-8626 X Dated: Costs $674.40 674.40 1,142.72 $114.27 $62.85 $26.40 $1,346.24 1 WORK CHANGE DIRECTIVE No. 002 PROJECT: WELL 21 IRON AND MANGANESE REMOVAL PROJECT DATE OF ISSUANCE: November 18, 2014 EFFECTIVE DATE: November 18, 2014 OWNER: City of Meridian Project No. CONTRACTOR: Sletten Construction ENGINEER: CH2M HILL You are directed to provide a price quotation for the following change(s): Change the shown horizontal metal siding, fascia, and soffit panels to Cement Fiber Board (e.g. James Hardie) products. Siding to be 8-1/4" horizontal siding. Siding to be installed over 5/8" min. exterior grade sheathing with water/vapor barrier as required by manufacturer. All butt joints to have additional flashing at all joints per manufacturer's standard installation details. Trim to be 4/4. Soffit material to be continuous vented Hardie panels. See attached: - Revised drawing sheets 0704-FIL-AR-201, 0704-FIL-AR-302, 0704-FIL-AR-301, and 0704-FIL-AR-402 - Hardie Siding Material List as provided by Contractor supplier Final paint colors for siding and trim to be chosen from manufactures full range of colors. Purpose of Work Change Directive: If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change order based thereon will involve one or more of the following methods of determining the effect of the change(s). Method of determining change in Contract Price: Unit Prices Lump Sum Other Estimated increase (decrease) in Contract Price: If the change involves an increase, the estimated amount is not to be exceeded without further authorization. RECOMMEND by ENGINEER: un (Authorized Signature) Method of determining change in Contract Times: ❑ Contractor's records ❑ Engineer's records ❑ Other Estimated increase (decrease) in Contract Times: Substantial Completion: 0 days; Ready for final payment: 0 days. If the change involves an increase, the estimated times are not to be exceeded without further authorization. AUTHORIZED by OWNER: (Authorized Signature) o� m� SNOIIVA313 HOIN3.LX3 mm mm Y _ 11 OO 0 1'1'1.1.1'1 I �AFi ;1;1;1�1�1�1�11 Ihh444l.�11 I 1.1-►-1.1.1•LI _ 0 Iil®o.1.�.1.1.1,1. 1 1 1 1 1 I�I�I�I�I�I�IW i�i�1�1�1�1� I�'- •-1 1 1 1 IIIIIIM 1111 1111111111111° _ �''t'''t' 1111111 1111 IIIIIIY 1111 °1°1°1°1°1°1°'i •1.1°1°1°1°1 1�1�1�1�1�1�11 ! II1�1�1�1�111• 1 1 ::: 11111'll 1111111 rr _®_ oe1e1e1�1e1e. � I 0 1_ i 1■1■1.�■1■1■ O Ali � � 0 '''',',''','® I© rrrrrl 44444h a till !1!1!1!1!1!1 ;1;1;1;1;1;1 61.I.L... . 11111- - Q ■III ® . ��.1.1.1.1.1.1' O 9.L�i.1.1.1.1.1� ,.�De . p��,.•�� �„ ,,o�.., ,• . a.,....�,a • • •.aw � �M N wn a I � � �,'� I w•q yw•w WP•l,wwn,l nnau•tl •.•ueM,.IlWuoil _ SNO11OBS ONI011n9 � -�: � � = s g L - Fl MdV A6 NWSIA3tl 31vo 'ON ..Iw.wwNn �wruaauNaw ��� 9 � _ ..,,., . '111 H WZHO Mal W 8 a R 1 g �g Y III of Il.l W u D 6$~ iZz} lo gg 4 m ID2 F D Z ffi WU' DidDE e Q Y1Y a O Qg j� d W � ;�$ Ra 9�3 j62�� 3 O �J ,ice - I I s I I I!7 ________ I Y O U - i e o 1 a I L---- I _________ I - n V I c I O _ -- - w i L_-; O W -L o ��` , e - z o - -- --------------------- --- o _ - m I d g < U D nwnc�+su.:wm ,iw.w awe '-'-^w,ovw.x: oe o:.',o W�:,.'i:.:,:f:,:e au,we:�.:. n"•,•'.,•wi'wv"i.:�o'oe:w S,.N3W(1o0 w9 353tl f tl cuw..n,00 @ NO W.M'..i1+W � Ttli MdV AB NOISN3tl 31W ON Ne�.l....+u.+l l...tl.mm.amry Muoq $ a � «�^ SNOU33S IIVM I - ..rowwn� 10 lA w Z y$g� pF kO O � o } uj LLI W oa in��3t7°FiFw 3AN 1 O um a owri ..r+wkeo S1NBiNnoOO 018 HV353tl! u11�1353tl!M DOOM tiq ti � cpi�{wivoi.tx laaw �u swa cvarnva :! I i g »n w ..n w.n •.mww g $ m 0— As ..sI w MA 'ON all 3 —_ tZ MM 1VtllIL]3LH:M' SIIVi34 Y " �.IiWw MA4� � e� • R 3 9 R ok, k W o lip o ,�. WIZ N R s LU U NIw.B Y w Z y Y a CO --- C9 U Q LL g " > a " q�i €?o� Z 8�p z CL .19 w r a 2g 8W Who GC �3; 4 SHELL ON 0 ca ; o H �u j I R J" R w0 a 3 §2 Z w 3 p W1 U U �g Q 19 .0 >000000JUIL2 3= I * * * 300 E WATERTOWER. * * * Section: 1 HARDIE SIDING AND TRIM BIG STRETCH WHITE CAULK 1211 TEXTURED SIDING CORNERS 4/4 X 5.5 RUSTIC HARDIE TRIM 24 "X8' HARDIE CDRMIL, VENT SOFFIT 1 / 4 " 4 X8 HARDIE CEDARMI LL SOFFIT de LF 9/32XI-3/8 HEM LATTICE ##267 50/1 8 -1 / 4 " HARD I E SEL, -- CDR. PR.MD SDG 1 4/ 4 X 3.5 RUSTIC HARDIE TR I M BIG STRETCH WHITE CAULK 1/2 "X10' Z-METAL Section: 1 Sub -Total Section: 2 1211 TRIM OPTION OPTION FOR 1211 TRIM PIECE AR TOP PLA` E BASER ON ELEVATION RENDERING FROM PAGE AR201. REPLACE THIS LIME WITH 12 PIECES OF 1X4 HARDIE TRIM 4 /4 X 11.25 RUSTIC HARDIE TRIM CONSTRUCTION • DESIGN BUILD OMPANIES LAS VEGAS • PHOENIX • GREAT FALLS • BOISE • CODY City of Meridian 33 East Broadway Avenue Meridian, Idaho 83642 Aft: Clint Worthington Project: Well 21 Iron and Manganese Removal Facility SCC Project No. 134250 COST PROPOSAL NO: 134250-03 Date: 06-Jan-15 DOCUMENT REFERENCE: WCD 003 Date: 25-Nov-14 cc: Field / File DESCRIPTION: Please find below and attached the costs associated with the Arc Flash Hazard analysis requested by CH2M Hill in Work Change Directive (WCD) No. 003. Labor MatUExpense/Rental Subcontractor Description Qty Unit MH Type Rate Cost Unit Rate Cost Costs Challenger Companies Provide Arc Flash Study 1 LS $5,290.00 SUBTOTALS Labor,Mat'I,Sub) 1 $0.001 0.001 $5,290.00 Subtotal $5,290.00 *Due to this Change The Contract Time will be increased OH @ 10 % $529.00 decreased Profit @ 5% $290.95 _X_ unchanged Bonds & Insurance @ 2% $122.20 to be determined by( ) days COST PROPOSAL TOTAL $6,232.15 * PLEASE REVIEW AND SIGN BELOW FOR INCLUSION INTO THE NEXT OWNER CHANGE ORDER. Sleften Companies X Dated: 6202 W. Gowen Road Ron Hagen - Project Manager Boise, ID 83709 X Dated: Phone: 208-658-9888 Fax 208-658-8626 X Dated: Challenger Companies Change Order cost estimate Project: Well # 21, Meridian 1 /5/2015 CO # 1 Material costs total RVAUV Ia:a_V■ neers 11 IBased on the one -line drawino for this oroiect. I hours total 0.00 cost per hr 62.00 total labor 0.00 Total Material Costs 4600.00 Total Labor Costs 0.00 Taxes 0.00 Permit Costs Overhead & Profit 690.00 TOTAL JOB COST 5290.00 Owners signature Date Contractors signature Date Sub Contractors Signature This Change Order becomes part of and in conformance with existing contract Date WORK CHANGE DIRECTIVE No. 003 PROJECT: WELL 21 IRON AND MANGANESE REMOVAL PROJECT DATE OF ISSUANCE: November 25, 2014 EFFECTIVE DATE: November 25, 2014 OWNER: City of Meridian Project No. CONTRACTOR: Sletten Construction ENGINEER: CH2M HILL You are directed to provide a price quotation for the following change(s): Perform Arc Flash Hazard analysis per the calculation method outlined in NFPA 70E, Annex D. Provide and install Arc Flash Hazard labels to all panels and service equipment on the premises. Purpose of Work Change Directive: Per City of Meridian direction. If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change order based thereon will involve one or more of the following methods of determining the effect of the change(s). Method of determining change in Contract Price: ■ Unit Prices Lump Sum Other Estimated increase (decrease) in Contract Price: If the change involves an increase, the estimated amount is not to be exceeded without further authorization. RECOMMEND by ENGINEER: (Authorized Signature) Method of determining change in Contract Times: Contractor's records Engineer's records Other Estimated increase (decrease) in Contract Times: Substantial Completion: 0 days; Ready for final payment: 0 days. If the change involves an increase, the estimated times are not to be exceeded without further authorization. L-02 AUTHORIZED by OWNER: (Authorized Signature) CONSTRUCTION • OESIGN BUILD st COMPANIES_ LAs VEGAS •PHOENIX •GREAT FALLS • BOISE • COOY COST PROPOSAL NO: 134250-02 City of Meridian 33 East Broadway Avenue Meridian. Idaho 83642 Att: Clint Worthington Project: Well 21 Iron and Manganese Removal Facility SCC Project No. 134250 Date: 20-Jan-15 DOCUMENT REFERENCE: N/A cc: Field / File Date: N/A DESCRIPTION: Please find below and attached the costs associated with providingg n�ew 8' chain ink fence and gates at the N. E. and W sides of the project per the attached sketch. Materials to be black f'1/Gcoated. Description Oty Unit Labor MH Type Rate Cost MWV/Expense/Rentai Unit Rate Cost Subcontractor Costs i Butte Fence I Revised quote for 420' f 8' 1 1 1 LS i 1 I I ! I I I i I I $18.074.00 fence, gates, and PVC coated I I I I I Butte Fence Oti anal quote for base bid 1 -1 1 LS I I I I I {$8,525.00j contract work I I ! r ! I I I I I i i I I I I I I ! I I I I I I I I I I I I SUBTOTALS Labor.Mat'I.Sub $9.549.00 _ I 0.00 S0.00 'Due to this Change The Contract Time wN be increased _ decreased X. unchanged to be determined by { ) days Subtotal OH ® 10 % Profit ® 5% Bonds & Insurance ® 2% COST PROPOSAL TOTAL 9.549.00 $954.90 $525.20 $220.58 S11,249.68 ricNac nc vrc rY Hryu %'PILXiv OCLVW rVIT tUWN&H UHANUE URDER. Slerien Compan as __ Dated; lack- 7:%:76202 W Gowen Road Ron Hagen- Project Manager Bohm ID 83709 Phone 208-658-98M X Dated: Fax 208&658.8626 X Dated. 10. C •t4M r��nits,n. Butte Fence, Inc. 2049 E. Wilson Lane Meridian. ID 83642 Phone(208) 884-0203 Fax (208) 884-8929 ID Cont. # RCE•2292 Nev. Lisc. #0075048 Ore List. #158340 ID Public Works # PWC.C-15911.8.4 Quote Ta City of Meridian Phone Fax Quote Bait Right, Bait to Last Customer No.; MERIDIANWATE Quote No.. 44731 Ship To: Well 21 Treatment Facility Date Ship Via F.O.B. Terms 08114/14 1 Payable Upon Receipt umber Purchase Order Number-7— Sates Person Required Tom Tom Billingsley 08/14/14 Quantity Number _ Description Unit Price Amount [Required I Shipped I B.O. 1 Chain Link Material & 6850.00 6850.00 Installation, 1 6' Tall X 20' Long Swing 975.00 975.00 Gate & 6' Tall X 4' Wide Walk Gate. 1 Demo. Of Existing Fence 700.00 700.00 And 15' Gate 8525.00 8525.00 This bid is based upon approximate footage. The final cost may vary according to the actual product used and labor required to complete the Job. Pennits. sprinkler Ones and other unmarked lines are the customers responsibility. Hard soli and digging condidons may increase the price of labor. Any changes on the project must be approved and signed by the customer. This bid is valid for 30 days from date given. Customer Signature Date FINANCING AVAILABLE OAC FOR UP TO 12 MONTHS, SAME AS C45H TALK TO YOUR SALES REPRESENTATIVE ���°tW��l�m1R.• BUTTE FENCE, INC. Quote 2049 E. Wilson Lane Built Right, Built to Last $,T INC Meridian, ID 83642 �4 Phone (208) 884-0203 Customer No.: MERIDIANWATE Fax (208) 884-8929 Quote No. 46691 ID Cont # RCE-2292 Nov. Lisc #0075048 Ore. Lisc, #158340 ID Public Works # PWC-C-15911-84 Quote To: Sletten Companies Ship To. Well 21-Treatment Facility 6202 West Gowen Rd. 300 East Watertower Boise, ID 83709 Black Vinyl Fence Meridian. Id Phone (208) 658-9888 Fax (208) 658-8626 Date Ship Via F.O.B. f Terms _ 01/13/15 Payable Upon Receipt Purchase Order Number Sales Person Required Tom Billingsley 01113115 Quantity_ Required I Shipped Item Number Description Unit Price Amount 1 420' Of 2" X 9 Gauge X 9910.00 9910.00 8' Tall Black Vinyl Fence, 1 4'WX87 Chain Link Man Gate 3768.00 3768.00 20'WX8'T Dbl. Drive Gate 2 Each 1 Demo Of Existing Gate 700.00 700.00 And Fence. 420.000 Professional installation 8.80 3696.00 Includes Concrete REVISED 1/19/2015 1807400 1807400 This bid Is based upon approximate footage. The final cost may vary according to the actual product used and tabor required to complete the job. Permits, sprinkler lines and other unmarked Ones are the customers responsibility. Hard soil and digging conditions may increase the price of labor. Any changes on the project must be approved and signed by the customer. This bid Is valid for 30 days from date given. Customer Signature Date FINANCING AVAILABLE OAC FOR UP TO 12 MONTHS, SAME AS CASH TALK TO YOUR SALES REPRElSENTATWE o1- 1 ctsqc( CONSTRUCTION • DESIGN BUILD • • COMPANIES LASVEGAS • PHOENIX • GREAT FALLS • BOISE • CODY COST PROPOSAL NO: 134250-04 City of Meridian Date: 05-Mar•15 33 East Broadway Avenue Meridian, Idaho 83642 DOCUMENT REFERENCE: WCD o05 Aft: Clint Worthington Date: 20•Feb•15 Project: Well21 Iron and Manganese Removal Facility SCC Project No.134250 cc: Field / File DESCRIPTION: Please find below and attached the costs associated with addition of the new hose bibb in the bulk tank storage area per WCD 005 Description My Unit Labor MH Type Rate Cost Ma(V&pense/Aentai Unit Rate Cost Subcontractor Costs Buss Mechanical New Hose Bibb on Exterior I 1 1 LS ! ( $1,024.00 I 1 I - _ I I ! ! I I I I I I I I I I I I I I l I I I i I I I I I I } I I I I I ! I I SUBTOTALS Labor,Mat'I,Sub W $1,024.00 I I S0.0o L.00 •Due to this Change The Contract Time will be _ increased decreased ,)_ unchanged to be determined by ( ) days Subtotal OH ® 10 % Profit ® 5% Bonds & Insurance ® 2% COST PROPOSAL TOTAL $1,024. 00 $102.40 $56.32 $23.65 $1,206.37 MCA= PFCVICVV AMM SIL*IV 0CLUYY I-UH I USIA I E NEXT OWNEH CHANGE UR/DER. Slenen Companies X Dated: 8202 W Gowen Road Ron Hagen - Project Manager Boise. 1083709 X Dated: Phone 208.658.9888 Fax, 20"5&8626 X Dated: NQ Proposal Request Ldaj BUSS Mechanical Services Inc. P.O. Box 190476 Boise, Idaho 83719-0476 DATE: 2-23-2016 Sletten Construction Att: Roll Re: CHANGE PROPOSAL REQUEST JOB: Well 21 JOB # 14131 Buss # 5.1 GC/ARCH. CP# WCD•005 DESCRIPTION: Cost to core drill and add HB•2 Material pipe valve& fittings $ 418.68 Equipment $ Expendables 2%of labor $ 7.00 Tools Tax $ 25.12 Installation 7.5 hrs $ 349.95 Material management $ Supervision 0 hrs $ Project Management 0.5 hrs \ $ 27.50 Subsistence $ Cleanup $ Warran /Asbuiits $ 25.00 Safety total $ 853.25 PERMIT TOTAL $ 29.86 $ 883.11 SUBCONTRACTORS Other Temp.cont. Sheetmetal Insulation $48.00 TOTAL $ 48.00 $ 931.11 BOND OVERHEAD & PROFIT TOTAL REQUEST TOTAL PRICE 10% $ $ 93.11 1,024.22 $ 1,024 EXCLUSIONS: Per Bid Proposal PROPOSAL BY, Chris Buss j TIME EXTENSION REQUESTED PROPOSAL GOOD FOR 30 DAYS 14131-5.1-WCD-005 I Category Size (Item Desc (Qty (Mat Ext FId Ext FIXTURES ( (HB-2 ( 11 222.741 2 FIXTURES (CORE DRILL ( 11 1001 1 COPPER KLM-LEAD FREE 13/4" IL -HARD TUBE ( 81 34.3281 0.272 COPPER KLM-LEAD FREE 13/4" 190 ELBOW CxC ( 41 6.8321 1.428 COPPER KLM-LEAD FREE 13/4" ( BALL/VLV SWT 150 2PC ( 11 19.111 0.357 COPPER KLM-LEAD FREE 11-1/2" (COUPLING ( 11 5.712 0.51 COPPER KLM-LEAD FREE 03/4" (HANGERS ( 21 8.541 0.85 COPPER KLM-LEAD FREE 13/4" JJOINTS--SOLDER ( 131 0l 0 COPPER KLM-LEAD FREE 11-1/2" )JOINTS --SOLDER ( 41 0l 0 COPPER KLM-LEAD FREE (Unsized (SOLDER LBS-LEAD FREE ( 0,151 1.261 0 COPPER KLM-LEAD FREE (Unsized IPRESTO UTE B tank ( 0.031 0.5671 0 COPPER KLM-LEAD FREE 13/4" (ADAPTERCxM 11 2.6741 0.4165 COPPER KLM-LEAD FREE 1-1/2" x3/4" IREDUCED TEE - BRANCH ( 11 16.009 I 0.6885 COPPER KLM-LEAD FREE (Unsized (FLUX--2 OZ. CAN 1 0.151 0,841 0 COPPER KLM-LEAD FREE lUnsized (ABRASIVE CLOTH-25YD ( 0.011 0.071 0 1 (GRAND TOTAL 1 1 418.6821 7.522 WORK CHANGE DIRECTIVE No. 005 PROJECT: WELL 21 IRON AND MANGANESE REMOVAL PROJECT DATE OF ISSUANCE: February 20, 2015 EFFECTIVE DATE: February 20, 2015 OWNER: City of Meridian Project No. CONTRACTOR: Sletten Construction ENGINEER: CH2M HILL You are directed to provide a price quotation for the following change(s): Provide an exterior hose bib (HB-2) within the bulk storage tank enclosure near the emergency eye wash shower location. See attached sketches. Purpose of Work Change Directive: Allows for a more convenient wash -down water source for the enclosure. If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change order based thereon will involve one or more of the following methods of determining the effect of the change(s). Method of determining change in Contract Price: Method of determining change in Contract Times: ❑ Unit Prices ❑ Contractor's records ❑ Lump Sum ❑ Engineer's records ❑ Other ❑ Other Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times: $ Substantial Completion: 0 days; Ready If the change involves an increase, the estimated amount for final payment: 0 days. If the change is not to be exceeded without further authorization. involves an increase, the estimated times are not to be exceeded without further authorization. RECOMMEND by ENGINEER: AUTHORIZED by OWNER: By: By: (Authorized Signature) (Authorized Signature) A oM®eTsreoinm OLS f'� OIIaV AY -PR I- .n NR d Irr.N �. .NW ��Nrpo x�whou3w�°N�cr�wju!I�\ R. r NOHUAW 3LY0 'ON �L*'�"F° �111H�NV sP efi a �yl Q) J it la A 395 11 w o Ila� 8� alo!11, 11 1 , 1 0 Jill HIPM1�, >�_ a11, 1 1°11 E � ° g W 12 1 g $ 'gill mv, � � ' � 411, go U11n11 IN LZ E [ Ri N mom, 0 4 m � O bl4 66� C i0 i � 7 �t gg 3 h ► s a O O LL J Q U z Q U W e lit $ kk§ sL 7 Ni�lP�Wl P��11.�.n a. wn : s3lnoaH3s OW STV130 uBIMIP4D TI�WMG3,I ONQYIi '11IHWZHO e z w w s z Z 0 mtt 0 01 81 e U o A �i -j£ : = p�Fy�B 3R rr.�:wrwwI!E- `. 6:. b dFe e 5, 17 1t. W H Z U. a < CONSTRUCTION • DESIGN BUILD • COMPANIES LAS VEGAs • PHOENIX •GREAT FALLS • BOISE • COOY COST PROPOSAL NO: 134250-05 City of Meridian Date: 10-Mar-15 33 East Broadway Avenue Meridian, Idaho 83642 DOCUMENT REFERENCE: WCD 00s Att: Clint Worthington Date: 23-Feb-15 Project: Well 21 Iron and Manganese Removal Facility SCC Project No.134250 cc: Field / File DESCRIPTION: Please find below and attached the costs associated with the hypochlorite piping revisions requested in WCD 006. Description Qt Unit Labor MH Type Rate Cost Mat7/Expense/Rental Unit Rate Cost Subcontractor Costs _ Challenger Construction I I $449.39 Piping revisions 1 ( LS i I I I i I I i I I I I ! I I I I I I I ! I SUBTOTALS Labor,Mat'I,Sub 5449,39 L.M= I 50.00 I 0.00 *Due to this Change The Contract Time wl# be increased decreased `X . unchanged to be determined by ( j days Subtotal OH @ 10 % Profit ® 5% Bonds & Insurance ® 2% COST PROPOSAL TOTAL $449.39 $44.94 $24.72 $10.38 $529.43 MCA= rYCVICYV AMU bMtV MCLVYV i LJK IlV blVN7 I V Ili NEAT VWNER UHANGE VHVEH. Sletlen Companies X Dated: 314�i5` 6202 W Gowen Road Ron Hagen- P negar Boise ID83709 Phone 208-668-9888 Fax 208-668.8626 X X Dated: Dated: Challenger Companies Change Order cost estimate Project: Well # 21, Meridian new three-way valves and fittings Change 1" to 2" suction line of delivery pump MATERIAL. Material costs total cuan0ty cost oer materials CO#2 Reference WCD#6 Labor costs hours total Path hminct 1/2" Three-way valve 21 80 160.00 0.00 1/2" Tee sch 80 PVC Fitting 4 8.6 34.40 0.00 1/2" MI sch 80 PVC Fitting 61 9.5 57.00 0.00 2" PVC bail valve 2 60 120.00 0.00 3/8" to V4" tubing and 1" PVC to 2" PVC 0 0 0.00 0.00 Was a wash for restocking 0.001 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.001 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 sub total 1 371.40I hours total 0.00 cost per hr 62.00 total labor 0.00 Owners signature Date Contractors signature Date Sub Contractors Signature Date This Change Order becomes part of and In conformance with existing contract WORK CHANGE DIRECTIVE No. 006 PROJECT: WELL 21 IRON AND MANGANESE REMOVAL PROJECT DATE OF ISSUANCE: February 23, 2015 EFFECTIVE DATE: February 23, 2015 OWNER: City of Meridian Project No. CONTRACTOR: Sletten Construction ENGINEER: CH2M HILL You are directed to provide a price quotation for the following change(s): 1) Change Sodium Hypochlorite Transfer Pump (WWL21-PMP-102) suction piping and vent line (all pipe between bulk storage tank (WWL2]-TNK-101) and transfer pump to 2" diameter SHC instead of 1" diameter as shown in the Contract Documents (see attached drawing redlines). Modify heat tracing and insulation to reflect the change in pipe diameter. Note that Keynote 14 on PR- 101 applies to 2" transfer pump suction line only. 2) Replace Detail 2 on sheet PR-401 with attached Figure 1 to add a 3-way ball valve on the inlet to WWL21- PMP-104 and WWL21-PMP-105 (see attached cut sheet for 3-way valve order information) to allow sodium hypochlorite to be taken from either the calibration column or the sodium hypochlorite supply line. 3) Install W WL21-PMP-104 and 105 inlet and outlet tubing with no loops or slack in order to prevent intermediate high and low points. 4) Change Keynote 2 on PR-101 and Keynote 18 on PR-301 to require 1/4" SHC tubing instead of the 3/8"tubing as shown (see attached drawing redline). Purpose of Work Change Directive: Proposed changes will enhance sodium hypochlorite system operation and reduce likelihood for operational issues. If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change order based thereon will involve one or more of the following methods of determining the effect of the change(s). Method of determining change in Contract Price: Method of determining change in Contract Times: ❑ Unit Prices ❑ Contractor's records ❑ Lump Sum ❑ Engineer's records ❑ Other ❑ Other Estimated increase (decrease) in Contract Price If the change involves an increase, the estimated amount is not to be exceeded without further authorization. RECOMMEND by ENGINEER: Estimated increase (decrease) in Contract Times: Substantial Completion: 0 days; Ready for final payment: 0 days. If the change involves an increase, the estimated times are not to be exceeded without further authorization. By: By: (Authorized Signature) AUTHORIZED by OWNER: (Authorized Signature) Sol ml RM.�+.� ,„ ■= rmnvi aw oM awP�iP�wwvP.w &ZFM 6ZE9� UMMPAD tit gi a Z � 6 Y " i lit LLI g i gi ui R� w d v O N M ♦ d / w 1 i ¢ 0 0 1 f f ti J a 0 011 � lII ICI 4 r .. .. _ WId SS3001dd sa�oua "11IHIMEM 01 UN Z 5 a w p.4 a. 8 �ir+w.�trd.u.�r.nww Kww SNOLLOSS U.P l P417 68330Md s �Jill s � via, 1i It M aWR �M11 aw ae namn� RVO +w� awa.wri�au«.+�mv+w RPM BZ6S L U°"A"p A"' Z M W 01 SNOLL33S GF=ua "T1IHUMHO OI- a 4 . a . : a muo�rwsinv TM� pr�eomxaumanmriuraumwwm� un�w�Mnnawrmnwui. �oannxmxa � wm'wNn RII s8I �gg we no�nae azva a+ Ana...w�i �nwu �nw.w S-IItl130 � Ey E e 8 7 8 BZBSL u�.np4� • ac�oba i�l ui g W EE F � Z 6 T co 4� SO S i 2d o a H S k OZ p '6 as uunuuuuuuuu s 3 u, oe = N g � V U- cn N ¢ �N a S S m a o WILLU r ~w g o:LL oz o � a � Q a. =Y nit MZ Ex M C-P1O1AN wccc d-1 wc0 - O©6 Fi GuRE 2 v NOTES: 1. MIRRORAS APPROPRIATE FOR PUMP LOCATION Z PRESSURE RELIEF VALVE NOT KNOWN. Tp6/Nt— (SEE PLANS AND weD-404 pot SIZE TNSrAlJ"P .7N"r *0 tu1'd6T ri alme- TO PREVENT-ArTC-jzmvp14rr. FI [ bH of1 WO PDINr5 ti SODIUM HYPOCHLORITE 2 METERING PUMP INSTALLATION DETAIL miol V Valves Product Guide & Engineering Specifications True Union 2000 Industrial 3-Way Ball Valves wick -View Valve Selection Cha ay Vertical Ball Valve Val 0-ring PVC Part Numberl, 2, 3, 4 A F 0 Pressure Socket SR Threaded Flanged Spig9f Size Itaterial Rating 112 E M 47221-1-005 47211-1-005SR 4723L1-005 4721 -005 FK 17321.1.005 47311.1-005SR 4733L1.005 L1-005 314 EPDM 2L1-007 4721Ll-007SR 4723L1.007 4727L1-007 FKM 473 1-007 4731Ll-007SR 47331-1- 47371-1-D07 235 psi Non 1 4722L1 0 4721L1-010SR 472 -010 4727LI.010 -Shock Water LFKM 4732L1-01 731L1.010SR 3L1-010 4737L1-010 @ 73-F 1-114 EPDM 47221-1-012 4 Lt-012S 4723L1-012 47271.1-012 (Flanged 150 FKM 47321-1-012 4731 0 R 47331.1-012 47371.1-012 psi Non -Shock) 1-112 EPDM 4722L1-015 4721E R 47230-015 47271-1-015 Water @ 73-F FKM 4732L1-015 47 1-01 4733L1-015 47371.1-015 2 EPDM 4722L1-020 21L1-020SR 31-1-020 47271.1.020 FKM 47321-1 47311-1-020SR 47 1-020 47371.1.020 2-1/2 EPDM 4722 25 47211.1.025SR 4723L1 5 47271-1-025 FKM 4 L1-025 47311-1-025SR 47331-1-02 47371_1.025 150 psi 3 EPDM 722L1-030 4721L1-030SR 4723L1-030N4727L1- Non-Shock F 4732L1-030 4731LI.030SR 4733L1-030 Water @73'F 4 DM 47221-1-040 4721L1-040SR 4723L1.040 FKM 47321-1 040 4731L1-040SR 4733L1 040 4737L1-040 1: r CPVC valve, add the letter'C" to the part number (e.g 4722L1-005 or D:b a L-Port, add the number "2" to the part number (e.g 47221-2.00 For Triple L-Port, add the number'3'to the part number (e,g, 4722L3-005) 4.. For T-Port, add the tatter "T1" to the part number (e.g 4722T1-005) Quick -View Valve Selection Chart 3-Way Horizontal Diverter Valve (no branch shutoff) Valve Size 0-ring Material PVC Part Numberl,2 Pressure Rating Socket SR Threaded Flanged Spigot 112 EPDM 5022L1-M 5021L1.005SR 5023L1-005 5027L1-005 FKM 50321-1-005 50311-1-005SR 50331-1-005 50371.1.005 EPDM 50221-1-007 5021Ll-007SR 50231-1-007 50271-1- FKM 50321.1-007 50311.1.007SR 50331-1.007 50JA007 235 psi Non 1 M 50221.1-010 50211.1.010SR 50231-1-010 271-1-010 -Shock Water FKM 32L1-010 50311-1-010SR 5033L1 50371-1-010 @ 73-F 1-114 EPDM ON1012 5021LI.012SR 50 1-012 50271-1-012 (Flanged 150 FKM 5032L1• 5031L1.0125 33L1.012 5037L1-012 psi Non -Shock) 1-112 EPDM 50221-1-015 1L1-0 R 50231-1-015 5027L1-015 Water @ 73'F FKM 50321-1-015 503kX5SR 50331-1-015 50371.1-015 2 EPDM 5022L1-020 1L1-0 50231-1-020 50271-1-020 FKM 50321-1- 5031Ll-020SR L1.020 50371-1-020 2-112 EPDM 50 -025 50211-1-025SR 5023L 5 50271.1-025 FKM 321.1.025 50311.1.025SR 50331.1.025 37L1-025 3 EP 5022L1-030 5021L1-030SR 5023L1-030 502 30 150 Psi Non -Shock OOFKM 5032L1-030 5031L1-030SR 5033L1-030 5037L1-0 Water 73'F EPDM 50221-1-M 50211.1.040SR 50231.1-040 50271-1-040 FKM 50321.1-040 50311-1-040SR 50331.1-040 50371-1-040 Pa a 1463 Sultable for 011-Free air handling to 25 psi, not for distribution of compressed air or gas Spears® Manufacturing Company g Due to Material Cost Variations, Prices Subject to Change. Check On-line Catalog @ www.spearsmfg.com Valves Product Guide & Engineering Specifications True Union 2000 Industrial 3-Way Ball Valves Feature PVC, CPVC Versatile design— prove es multiple port and configuration options for controlling flow distribution in industrial and chemical processing applications. Choose Vertical 3-Way (L-Port Diverter, T-Port Off) or Horizontal Diverter configurations with open branch (no shutoff) design. Valves are available in IPS sizes 1/2" through 4" with socket, SR threaded (Special Reinforced), flanged or spigot end connectors. Venturied 6" (4" valves with 4 x 6 reducers) are also available with socket or flanged valve end connections. • Chemical & Corrosion Resista PVC r CPVC Construction • Vertical 3-Way or Horizontal Diverter Design no branch shutoff) L-Port, Multi L-Port & T-Port Ball Configuration Options • Interchangeable with all True Union 2000 Valves, Mates with Union 2000 Pipe Unions • High Impact Polypropylene Handle • Built-in Handle Lockout • Strong, Buttress Thread Union Nuts • Spears'�,' Double 0-ring Safe-T Shears' Stem Design • EPDM or FKM O-rings 3-Way Port Options Diverter Valves have no shut-off on branch. Vertical3-wayHorizontal Single I Double I Triple L-Port L-Port L-Port T Port Ball Port Options viewed from top of valve. ttta • Spears' Safe-T-Blocked8 Seal Carrier • Self Adjusting PTFE Floating Seat Design • Fully Serviceable, Replaceable Components • Sizes 1/2" - 2" pressure rated to 235 psi @ 73°F Sizes 2-1/2" - 4" and all Flanged to 150 psi @ 73°F • EPDM Valves NSF, Certified for Potable Water use • Suitable for Vacuum Service • Assembled with Silicone -Free, Water Soluble Lubricants • Manufactured to ASTM F 1970 • Metric Socket and BSP Thread Available L-Port I I T Port Sample Engineering Specification Optional Accessories* • Retro-Fit End Connector Sets for Valve Replacement • Split -Nut Repair Kits for Union Nut Replacement • Supplemental End Connectors • Stem Extension Kits • Square Operator Nuts • Multi Mount Valve/Actuation Mounting Kits 'See "BALL VALVE ACCESSORIES" section for data Is of individual products. All thermoplastic ball valves shall be True Union 2000 3-Way [specify horizontal or vertical] type with [specify port option] manufactured to ASTM F 1970 and constructed from PVC Type 1, ASTM D 1784 Cell Classification 12454, or CPVC Type IV, ASTM D 1784 Cell Classification 23447. All O-rings shall be EPDM or FILM. All valves shall have Safe-T-Sheat' stem with double O-ring stem seals. All valve handles shall be polypropylene with built-in lockout mechanism. All valve union nuts shall have Buttress threads. All seal carriers shall be Safe-T-Blocked". All valve components shall be replaceable. All EPDM valves shall be certified by NSF International for use in potable water service. All PVC and CPVC 112" through 2" valves shall be pressure rated to 235 psi, all 2-1/2" through 4" and all flanged valves shall be pressure rated to 150 psi for water at 73°F as manufactured by Spears" Manufacturing Company. Made in the U.S.A. Suitable for Oil -Free air handling to 25 psi, not for distribution of compressed air or gas Pa a 1464 Due to Material Cost Variations, Prices Subject to Change. Check On-line Catalog @ www.spearsmfg.com g E=a Valves Product Guide & Engineering Specifications True Union 2000 Industrial 3-Way Ball Valves Replacement Parts No. Component Qty. Material 1 End Connector 3 PVC/CPVC 2 End Connector 0-ring 3 EPDM/FKM 3 Union Nut 3 PVC/CPVC 4 Handle Lock 1 PP 5 Handle 1 PP 6 Stem 1 PVC/CPVC 7 Screw 1 Stainless Steel 8 Handle Cover 1 PP 9 Stem 0-ring 2 EPDM/FKM 10 Stem Bearing' 1 PTFE 11 Body 1 PVC/CPVC 12 Ball 1 PVC/CPVC 13 End Connector Collar 3 Stainless Steel 14 Seat 2 PTFE 15 Carrier 0-ring 1 EPDM/FKM 16 Seal Carrier 1 PVC/CPVC RFote: Applies to both Vertical and Honzontal configurations. For sizes 2-112, 3 & 4 only NOTE: Diverter style valve has no shutoff on branch. Vertical 3-Way Ball Valves — Dimensions & Operating Torque Vertical 3 Way Ball Valve Oper.2 Nominal Size A B1 C D E F G H Torque in. lbs.) Soc/SR Thd Spigot Socket SR Thd Spigot Socket SR Thread Spigot Soc/SR Thd Spigot 1/2 1-7/8 2-7/16 2-15116 4-1/4 3-27/32 4-3/4 2-9/16 2-13/16 2-3/4 2-9/16 2-13/16 1-11/16 2 3-1/2 12 3/4 2-1/4 2-3/4 3-5116 4-3/4 4-1/4 5-3/8 2-7/8 3-5116 3 2-3/4 3-5/16 2 2-5/16 3-7/8 12 1 2-1/2 2-718 3-1/2 5-1/8 4-11/16 5-3/4 3-1/8 3-7/16 3-1/4 3 3-9/16 2-1/8 2-7/16 4-1/4 20 1-1/4 3-1/16 3-1/4 3-13/16 5-3/4 5-3/16 6-5116 3-5/8 3-13/16 3-3/4 3-3/8 4-1/16 2-3/8 2-13/16 4-5/8 25 1-1/2 3-1/2 3-1/2 4 6-1/4 5-7/16 6-3/4 4 4-3/16 4-3/16 3-13/16 4-1/2 2-3/16 3-1/8 5 40 2 4-1/4 4-3/4 5-3/16 7-3/4 6-3/4 8-1/4 4-1/2 5-1/8 5 4-1/2 5-5/16 3-1/2 3-3/4 6 67 2-1/2 5-3/8 5-7/8 7-13/16 9-5116 8-1/2 11-3/8 5-1/8 6-1/4 5-7/8 5-1/2 6-7/16 4-1/8 5-5/16 7-112 120 3 6-3/16 6-7/8 7-13/16 10-11/16 9-3/4 1 11-9/16 5-7/8 7-5/8 6-11/16 6-3/16 7-3/16 4-3/4 5-5/16 7-1/2 120 4 1 7-1/2 7-1/4 8-1/4 11-13116 1 10-1/4 12-13116 6-3/4 1 9-3/16 7-1/8 6-3/4 8-3/4 5-7/8 6-1/2 9 336 1• Valve Lay Length 2 Torque required at valve maximum internal pressure rating., 5f /sec.. Flow velocity: due to adjustment differences during installation,. actual values may vary. Pa a 1465 Suitable for Oil -Free air handling to 25 psi, not for distribution of compressed air or gas SpearsS Manuractunng Company g Due to Material Cost Variations, Prices Subject to Change. Check On-line Catalog @ www.spearsmfg.com Valves Product Guide & Engineering Specifications True Union 2000 Industrial 3-Way Ball Valves NOTE: Diverter style valve has no shutoff on branch 11 Horizontal Diverter 3-Way Ball Valves Dimensions & Operating Torque Nominal Size A B1 C D E F G H Oper.z Torque (in. lbs.) SocISR Thread Spigot Socket SR Thread Spigot Socket SR Thread Spigot S SR Thread Spigot 1/2 1-3116 2-7/16 2-15/16 4-3/16 3.13116 4-3/4 2-9/16 2-13/16 2-9/16 2-3/8 2-13/16 1-11/16 2 3-1/2 12 3/4 2-1/4 2-3/4 3-15/16 4-3/4 4-1/4 5-3/8 2-7/8 3-5116 3 2-3/4 3-5/16 2 2-5/16 3-718 12 1 2-1/2 2-7/8 3-1/2 5-1/8 4-11/16 5-3/4 3-1/8 1 3-7/16 3.1/4 3 3-9116 2-1/8 2-7116 4-1/4 20 1-1/4 3-1/16 3.1/4 3-13/16 5-3/4 5.3116 6-5/16 3.5/8 3-13/16 3-3/4 3-3/8 4-1/16 2-3/8 2-13116 4-5/8 25 1-1/2 3-1/2 3.1/2 4 6-1/4 5.7116 6-3/4 4 4-3/16 4-3/16 1 3-13/16 4-1/2 2-3/16 3-1/8 5 40 2 4-1/4 4-3/4 5-3116 7-3/4 6-3/4 B-1/4 4-1/2 5-1/8 5 4-1/2 5-5/16 3-1/2 3.3/4 6 67 2-1/2 5-3/8 5.7/8 7-13/16 9-5/16 8112 11-3/8 5.1/8 6-1/4 5-7/8 5-1/2 6.7/16 4-1/8 5-5/16 7-1/2 120 3 6-3/16 6.7/8 7-13/16 10-11116 9.3/4 11-9116 5718 7-5/8 6-11/16 6-3/16 7-3/16 4-3/4 5-5/16 7-1/2 120 4 7-1/2 7-1/4 8-1/4 1 11-13116 10-1/4 12-13/16 1 6-3/4 1 9-3/16 7-1/8 6-3/4 8-3/4 5-7/8 6.1/2 9 336 1: Vatve Lay Length 2. Torque required at valve maximum internal pressure rating, 5ft/sec. Flow velocty, due to adjustment differences during installation, actual values may vary Temperature Pressure Rating System Operating 100 110 120 130 140 150 160 170 180 190 200 210 Temperature °F (°C) (38) (43) (49) (54) (60) (66) (71) (77) (82) (88) (93) (99) PVC 235 211 150 75 50 -0- -0- -0- -0- -0- -0- -0- 1/2" 2" (1.62) (1.45) (1.03) (.52) (.34) (-0-) (-0-) (-0-) (-0-) (-0-) (-0-) (-0-) Valve Pressure - CPVC 235 219 170 145 130 110 90 80 70 60 50 -0- Rating (162) (1.51) (1.17) (1.00) (.90) (.76) (.62) (.55) (.48) (.41) (.34) (-0-) psi PVC 150 135 110 75 50 -0- -0- -0- -0- -0- -0- -0- (MPa) 2-1/2" 4" (1.03) (.93) (.76) (.52) (.34) (-0-) (-0-) (-0-) (-0-) (-0-) (-0-) (-0-) - CPVC 150 140 130 120 110 100 90 80 70 60 50 -0- (1.03) (.97) (.90) (.83) (.76) (.70) (.62) (.55) 1 (.48) (.41) (.34) (-0-) NOTE: Flanged Valves have a base pressure rating of 150 psi Made in the U S A Suitable for Oil -Free air handling to 25 psi, not for distribution of compressed air or gas Pa a 1466 Due to Material Cost Variations, Prices Subject to Change. Check On-line Catalog @ www.spearsmfg,com 9 CONSTRUCTION - DESIGN BUILD COMPAN/SS LASVEGAs •PHOENIX •GREAT FALLS • eOiSE • CODY COST PROPOSAL NO; 134250-07 City of Meridian Date: 18-Mar-15 33 East Broadway Avenue Meridian, Idaho 83642 DOCUMENT REFERENCE: Perrin Email Aft: Clint Worthington Date: 27-Feb-15 Project: Well 21 Iron and Manganese Removal Facility SCC Project No.134250 cc: Feld / File DESCRIPTION: Per conversation with Jerry & Perrin, this quote Is for the addition of a 20" x 24" access panel in the ceiling of the existing building to allow access to the attic fan and thermostat that are being installed in the overbuild space. Labor MafflExpense/Aental Subcontractor Descri tion Oty Unit MH Type Rate Cost Unit Rate Cost Costs Add_celligR access panel In 1 LS $306.00 existing ceiling - per Y_ MC ugyote _ I Paint allowance 1 LS _ _ ! $50.00 SUBTOTALS (Labor,Mat'I,Sub) $ - S J S 356.00 Subtotal $356.00 -Due to this Change The Contract Tlme WIN be Increased OH ® 10 % $35.60 decreased Profit ® 5% $19.58 _X_ unchanged Bonds & Insurance ® 2% $8.22 to be determined by ( ) days COST PROPOSAL TOTAL $419.4; • PLEASE REVIEW AND SIGN BELOW FOR IN USION 1 O EXT OWNER CHANGE ORDER Steffen Companies X Dated: 3 /i4? (� 6202 W. Gowen Road Ron Hagen - Project aneger eoise, 0 53709 X Dated: Phone 20B-655-98N Fax 20B-658-8626 X Dated: 3117015 iff ,, C MECHANICAL C AmUCr734 To: Date: Sletten owner. Sob No.: Request No., ttn: Iffy Nine 0edwp pAttached ❑Not Requked 2075 LANARK 5T MER101AN 10 63047 2ua 00 "99 FAX ®incense ❑Decease the cost of fhe project by $306 wM defaced esthnate Itfadwd XrFdbw Requbedt Required ❑X hrcroese ❑ Decease the coorpietlon time of the project by 1 working dap after reeelpt of Mal appne+at We reserve the right to datm hrlpacts on cost and/or schedule at a later data. Prepared By: 66 Graham Data: (PNaia1 borarpu n " Approved by: Date: cow ees�.ex+e�.) WMI 362015 Pape 2