CHANGE ORDER NO. 1
33 EAST BROADWAY
PROJECT NO. 10382.E
MERIDIAN, ID 83642
DATE: 3/20/2015
EFFECTIVE DATE: 3/16/2015
CONTRACT ORDER CHANGE ORDER
CONTRACTOR: Circle H Construction, Inc.
PROJECT: Fiber Optic Construction - City Hall to Water & Wastewater
The Engineer/Consultant is hereby directed to make the following changes from the Task Order Documents.
Description: The City has requested to change the product from Tight
Buffered to Loose Tube Fiber.
Reason for Change Order: Cost difference between Tight Buffered and Loose Tube Fiber
CHANGE IN TASK ORDER PRICE:
CHANGE IN TASK ORDER TIMES:
Original Task Order Price $229,111.13
Original Task Order Times: 150
Net changes form previous Change Orders
Net changes form previous Change Orders
No.—O— to _0
No._0_ to _0 (calendar days)
$0.00
0
Task Order Price Prior to this Change Order:
Task Order Times prior to this Change Order:
(calendar days)
$229,111.13
150
Net Increase (decrease) of this Change Order:
Net Increase (decrease) of this Change Order:
(calendar days)
-$3,000.00
15
Task Order Price with all Approved Change Orders:
Task Order Times with all Approved Change Orders:
(calendar days)
$226,111.13
165
RECOMMENDED: (Project Manager)
ACCEPTED: CIRCLE ONSTRUCTION, INC
By: Clint Dolsby
By: A��y/ Clapi�
Date: / 6
Date: / si �5
APPROVED: (CITU PURCHA51 G MA G
COUNCIL APPROVAL DATE:
By: Keith Welts
AU`'LS�
Date: A� �/� �S
`e4Qp0.Arao
Date:
APPROV) „
ATTESM°
TDIAN-
By: Mayor Tammy de�
\ /Dano
By: City Clerk, Jaycee HoE
EAL'-�1-\
Date:
Dale:
"!Ae IR F PSV°
/S G? J, -;p3/