Loading...
HomeMy WebLinkAboutTask Order No. 10460.F with Brown and Caldwell for Meridian Upgrade Alternatives AnalysisTASK ORDER NO. 10460.E Under the MASTER AGREEMENT FOR PROFESSIONAL SERVICES BETWEEN CITY OF MERIDIAN (CITY) AND NAME OF CONSULTANT (ENGINEER) This Task Order is made this 10th day of March, 2015 and entered into by and between the City of Meridian, a municipal corporation organized under the laws of the State of Idaho, hereinafter referred to as "City", and accepted by Brown & Caldwell, hereinafter referred to as "Engineer" pursuant to the mutual promises, covenant and conditions contained in the Master Agreement (Category 2a) between the above mentioned parties dated October 1, 2014. The Project Name for this Task Order 10460.E is as follows: CITY OF MERIDIAN MERIDIAN UPGRADE ALTERATIVES ANALYSIS PROJECT UNDERSTANDING The primary objective of this investigation is to evaluate alternatives for upgrading the Plant to achieve the proposed permit limits at the maximum month flow capacity of 14.2 million gallons per day (mgd). The project analysis and recommendations will be a collaborative effort between the City operations and engineering staff and Brown and Caldwell (BC). SCOPE OF SERVICES Scope of Work Task 10 — Project Management Objective. To manage, administer, and provide ongoing coordination for utilization of resources for the project. This task includes technical and financial management of the contract and liaison with the City, operational staff, and project team. Approach 1. All communication from the consultant regarding the project will include the City project manager (PM) or designee. The City PM will be responsible for coordinating and providing all review comments and the resolution of all issues to the consultant in a timely manner (typically 14 calendar days for design review); all other decisions will be provided to the consultant within 7 calendar days or less. The consultant PM will be responsible for drafting meeting minutes. 2. The consultant will document any and all requested changes to the scope of work using a Project Change Request form. The consultant PM will collaborate with the City PM to develop an approach for addressing the change(s). The City PM will review all changes for approval and provide the consultant Task Order 10460.E MERIDIAN UPGRADE ALTERNATICES ANALYSIS Page 1 of 7 BROWN & COLDWELL with written approval prior to modifying the existing scope, schedule, or budget and prior to proceeding with any new or un -scoped work activities. 3. Attend project kickoff meeting with City staff via conference call. 4. Attend up to four coordination meetings with City staff via conference call. City Responsibilities. Provide the following: 1. Identification of a PM with final authority for City decisions. 2. Timely review of products and decisions on issues critical to scheduled progress. 3. Identification and involvement of appropriate City staff. 4. Coordination of collected comments and resolution of any conflicting comments from all City reviewers prior to returning to the Consultant. Work Products. Deliverables for the tasks listed above include the following items: 1. Monthly progress reports and invoices 2. Meeting minutes, as required. Task 20 — Main Stream Process Screening Evaluation and Workshop Objective. To evaluate the existing process and up to three alternatives for expansion of the main stream processes at the Plant to meet proposed permit requirements and a design maximum month flow rate of 14.2 mgd and to include preliminary sizing of options and development of rough capital cost estimates for screening of alternatives; the screening to be conducted in a workshop setting to reduce the number of main stream treatment alternatives for evaluation in conjunction with add-on processes to one. Approach 1. BC will use modeling to determine preliminary sizing of alternatives (presented in approach item 2) for meeting the following requirements: a. Maximum month flow and load capacity of 14.2 mgd as developed for the Sidestream N Removal Evaluation project. Winter conditions will be evaluated, as these were found to be most restrictive from Sidestream project. b. Various combinations of effluent requirements, depending on the alternative, as developed and reported in the Sidestream N Removal Evaluation project. 1. Evaluate the following proposed alternatives (including reasons why they are proposed): a. Evaluate expansion of existing system as -is (AZO/Johannesburg), with expansion of process likely to occur on City -owned property adjacent to existing Plant site ("back 40") due to site constraints. b. Evaluate expansion of modified process configuration optimized for N and P removal such as the 5 - Stage Bardenpho type process, with expansion of the process to be completed on "back 40" (proposed as a conventional means of meeting stringent permit limits). c. Evaluate short-cut N removal technology (nitritation to denitritation) (proposed as a potential means of saving tank size and chemical cost versus conventional expansion). d. Evaluate technology for N removal only, such as the MLE process, assuming year-round reclaimed water discharge/groundwater percolation (proposed to eliminate need for P removal and stringent ammonia limits as reclaimed water production is limited only by total N). 2. Produce rough (for screening purposes only) capital construction costs and basic operating costs (chemical, aeration) for each alternative. 3. Produce draft TM of results of evaluations for City review. 4. Hold a workshop to discuss the results of the TM and reduce alternatives for evaluation to the best for further screening with add-on processes. During this workshop, present the recommended add-on Task Order 10460.F MERIDIAN UPGRADE ALTERNATICES ANALYSIS Page 2 of 7 BROWN & COLDWELL alternatives (up to eight combinations of those listed in Task 30) to be evaluated in conjunction with the recommended main stream treatment process. 5. Provide quality assurance/quality control (QA/QC) for all technical work (including memorandum). City Responsibilities 1. Provide review and comments on draft TM (one round). 2. Provide review and comments on meeting minutes. 3. Participate in the review workshop, provide feedback. Work Products 1. Electronic copy (in MS Word 2010) of the draft Main Stream Alternatives Screening Evaluation TM. 2. Electronic copy (in PDF) of the final Main Stream Alternatives Screening Evaluation TM. 3. Electronic copy of workshop meeting minutes, if deemed necessary by the City. Task 30 — Add -On Processes Screening Evaluation Objective. To evaluate up to eight add-on alternatives for expansion of the mainstream process recommended from Task 20 and to include preliminary sizing of options and development of rough capital cost estimates for screening of add-on alternatives; reduction of these alternatives to be reduced to three for detailed evaluation in conjunction with the recommended main stream process. Approach 1. BC will use modeling to determine preliminary sizing of alternatives (presented in approach item 2) for meeting the following requirements: a. Maximum month flow and load capacity of 14.2 mgd as developed for the Sidestream N Removal Evaluation project. Winter conditions will be evaluated, as these were found to be most restrictive from Sidestream project. b. Various combinations of effluent requirements, depending on the alternative, as developed and reported in the Sidestream N Removal Evaluation project. 2. Evaluate up to eight combinations of the following proposed add-on alternatives in conjunction with the selected main stream process from Task 20 (including reasons why they are proposed). The add-on combinations to be evaluated will be discussed during the workshop from Task 20: a. Tertiary chemical phosphorus removal process sizing and cost for tertiary membrane process to remove phosphorus from -0.5 mg/L down to 0.07 mg/L. This option will be common to all other options with the exception of MBR technology. b. Tertiary nitrification process (likely biological aerated filter) and denitrification filters (proposed as means to reduce level of nitrification in the main process and eliminate the need to denitrify in the existing tankage). c. Add influent flow equalization to existing system in conjunction with sidestream treatment (proposed to improve nitrification performance and reduce size of system expansion). d. Add additional centrate load equalization in conjunction with sidestream treatment (proposed to improve nitrification and performance and reduce size of system expansion). e. Use Biomag in conjunction with existing system (proposed to reduce footprint of expansion by allowing for higher operating MLSS and SRT). f. Use MBR technology to reduce footprint and to reduce need for tertiary phosphorus removal system. g. Confirm that the IFAS technology in the configuration proposed in the facility plan is still a viable alternative. Task Order 10460.1' MERIDIAN UPGRADE ALTERNATICES ANALYSIS Page 3 of 7 BROWN & COLDWELL 3. Produce rough capital construction costs and basic operating costs (chemical, aeration) for each alternative. 4. Produce draft TM of results of evaluations, including preliminary recommendations for final 3 alternatives to review, for City review. 5. Set final 3 alternatives for detailed evaluation in Task 40 based on City comments to TM. 6. Provide QA/QC for all technical work (including memorandum). City Responsibilities 1. Provide review and comments on draft TM (one round). Work Products 1. Electronic copy (in MS Word 2010) of the draft Add -On Screening Evaluation TM. 2. Electronic copy (in PDF) of the final Add -On Alternatives Screening Evaluation TM. Task 40 — Final Alternatives Evaluation and Workshop Objective. Determine the most appropriate process for expansion of the Plant based on initial screening results. Approach 1. Refine Task 30 analysis for the three selected alternatives. As with Task 30, BC will use modeling to determine preliminary sizing of alternatives for meeting the following requirements: a. Maximum month flow and maximum day flow and load conditions, as developed for the Sidestream N Removal Evaluation project. Both winter and summer conditions will be evaluated. 2. Develop planning level (AACE Class 5) capital cost estimates as well as chemical use costs, aeration costs, and anticipated labor costs for each alternative. 3. Provide a recommendation for expansion alternative based on capital and operational cost estimates. 4. Conduct a workshop with the City to review findings and collect comments from the City's review of the developed report (Task 50). City Responsibilities 1. Participate in the review workshop, provide feedback. 2. Provide review and comments on meeting minutes. Work Products None, report under separate Task. Task 50 — Report Development Objective. Combine the information from all above tasks to form an integrated report summarizing alternatives analysis and recommendations for plant expansion. Approach 1. Prepare draft Upgrade Alternatives Analysis and Recommendations Report (up to 80 pages) based on results from previous tasks. 2. Review results and the draft report with City staff at a workshop. 3. Amend report based on City comments and prepare a final report. City Responsibilities 1. Review and comment on the draft Upgrade Alternatives Analysis and Recommendations Report (one round). Task Order 10460.F MERIDIAN UPGRADE ALTERNATICES ANALYSIS Page 4 of 7 BROWN & COLDWELL Work Products 1. Electronic copy (in MS Word 2010) of the draft Upgrade Alternatives Analysis and Recommendations Report. 2. Electronic copy (in PDF) and 5 hard copies of the final Upgrade Alternatives Analysis and Recommendations Report. Task 60 — Update Sidestream Evaluation TM Objective. Update the Sidestream N Removal Evaluation TM based on comments from the City. Approach 1. Amend TM based on City comments and prepare a final Sidestream N Removal Evaluation TM. City Responsibilities 1. Provide comments to draft Sidestream N Removal TM. Work Products 1. Electronic copy (in PDF) of the final Sidestream N Removal Evaluation TM. Task 70 — Calibrate Biological Model for the Capacity Assessment Objective. The original scope for the Capacity Assessment project assumed that the existing calibrated model would be used to complete the evaluation. Based on the December 16, 2014 meeting with the City, it was determined that a full wastewater characterization would be completed to re -do model calibration, if needed. Results of this wastewater characterization have indicated that an update to the model calibration is warranted. This task is proposed to update the calibrated model based on the new wastewater characterization for completing the capacity assessment Approach 1. Update BioW in model calibration of Meridian plant based on January wastewater characterization. City Responsibilities None Work Products None It is assumed this project will be completed by June 30, 2015. Tasks 20, 30 and 40 will be completed and ready for presentation to the City by June 1, 2015. The estimated travel expenses are based on the following: Tasks 20 and 40 Travel — Airfare: two people @ $400 per roundtrip ticket — Meals and incidentals: two people at per person per diem rate for two days ($46/day, $34.50/day on travel days) — Lodging: two people for one night at per person per diem rate ($83/night) — Rental car + gas = $80/day — Airport parking and other travel incidentals ($15/day per person) Task Order 10460.F MERIDIAN UPGRADE ALTERNATICES ANALYSIS Page 5 of 7 BROWN & COLDWELL TIME OF COMPLETION and COMPENSATION SCHEDULE The following schedule is based on a Notice to Proceed (NTP) from the City by March 2015 and resulting in Final Design/Report being completed by June 30, 2015. A NTP issued on a different date will change the schedule accordingly. The Not -To -Exceed amount to complete all services listed above for this Task Order No. 10460.F is two hundred thirty-six thousand two hundred thirty-four dollars ($236,234.00). No compensation will be paid over the Not -to -Exceed amount without prior written approval by the City in the form of a Change Order. Monthly invoices shall be billed as a percentage of work completed. Any and all travel will only be reimbursed if pre -approved by the Project Manager, and only per the City of Meridian Travel Policy. Reimbursable expenses will be paid at cost and only if pre -approved by the Project Manager, and accompanied by an itemized receipt. Any travel and/or reimbursables paid will be paid as part of the Not -To -Exceed Task Order Total per the Compensation and Completion Schedule above. CITY OF MERIDIAN Dated: 3_/o,,S Approved by Council: 3�/y / Task Order 10460.F MERIDIAN UPGRADE BROWN & COLDWELL z')1 "WN CALDWELL 1911314 14ELPY Lb BF-RrbecT Dated: Page 6 of 7 COMPENSATION AND COMPLETION SCHEDULE Description Due Date Compensation Project Management 6/30/2015 $16,500 P40 Main Stream Screening Evaluation and Workshop 6/1/2015 $42,687 Add -On Screening Evaluation 6/1/2015 $62,060 Final Alternatives Evaluation and Workshop 6/1/2015 $80;437 Report Development 6/30/2015 $23,530 60 ' 70 Update Sidestream Evaluation TM Calibrate Biological Model 6/30/2015 1 6/30/2015 $940 $10,080 NOT -TO -EXCEED TASK ORDER TOTAL $236,234.00 The Not -To -Exceed amount to complete all services listed above for this Task Order No. 10460.F is two hundred thirty-six thousand two hundred thirty-four dollars ($236,234.00). No compensation will be paid over the Not -to -Exceed amount without prior written approval by the City in the form of a Change Order. Monthly invoices shall be billed as a percentage of work completed. Any and all travel will only be reimbursed if pre -approved by the Project Manager, and only per the City of Meridian Travel Policy. Reimbursable expenses will be paid at cost and only if pre -approved by the Project Manager, and accompanied by an itemized receipt. Any travel and/or reimbursables paid will be paid as part of the Not -To -Exceed Task Order Total per the Compensation and Completion Schedule above. CITY OF MERIDIAN Dated: 3_/o,,S Approved by Council: 3�/y / Task Order 10460.F MERIDIAN UPGRADE BROWN & COLDWELL z')1 "WN CALDWELL 1911314 14ELPY Lb BF-RrbecT Dated: Page 6 of 7 Purchasing App oval BY: KEIT ATTS, Pu chasing Manager City Project Manager Clint Dolsbv Department,A WARREN STEWAFVF, Engineering Manager Dated: -?. S�, / S' /3vswess ods /027 Task Order 10460.F MERIDIAN UPGRADE ALTERNATICES ANALYSIS Page 7 of 7 BROWN & COLDWELL .w C Q d w E _ z W c o N N F 11 N p � f �aC Li L � � a � LL } a o N 1� r N I N U � t v v o Uce) ayi o P Q y m m o m n (D W 0 mrnCL7 0 w wC� 0 C9 ch M > N M N � .w 0 a I 0 o 0 i M M > N M N M rc :' � 04 oz � t op D � C � r U o 0 a 0 o � � w N p Q Q N'. !. M W K F Z . O J 2 O RYA o Vi N J rtL rc O Q j�.�LT • i �S� ,02 a) ,f m tyl� ; MR r i � Q " � w -o a ae ., ' 0 1 • 'v_ 5t �: .1 N '2 w, C ❑ Y E Y� C City Of Meridian Detailed Statement of Revenues and Expenditures - Rev and Exp Report - Keith - Unposted Transactions Included In Report 3500 - WW - Admin 60 - Enterprise Fund From 10/1/2014 Through 9/30/2015 U te: 3/5/15 03:33:42 PM page: 1 Percent of Budget with Current Year Budget Budget Amendments Actual Remaining Remaining OPERATING COSTS 55000 Professional Services 52,881.81 0.00 52,881.81 100.00% 0000 NON -DEPARTMENTAL 0.00 660.00 (660.00) 0.00% 10023 Sewer Master Plan 924,998.96 0.00 924,998.96 100.00% 10264.b NPDES Financial Plan 99,999.96 0.00 99,999.96 100.00% Development 10264.c NPDES PERMIT STRATEGY AND 0.00 329,009.00 (329,009.00) 0.00% TECHNICAL ASSISTANCE RFQ 10353 WWTP Prelim Eval for 300,000.00 0.00 300,000.00 100.00% Infiltration Suitability 10353.b Infiltration Evaluation 0.00 291,710.00 (291,710.00) 0.00% for Wastewater Effluent Management - 10460.e WWTP Capacity Assessment 0.00 72,183.00 (72,183.00) 0.00% 1047... 2014 Annual Reuse Report 0.00 7,500.00 (7,500.00) 0.00% 10507.a WWTP Safety Upgrades - 0.00 14,422.50 (14,422.50) 0.00% Design 10507.£ WWTP Safety Upgrades - 0.00 6,500.00 (61500.00) 0.00% Clarifier 3 Control Panel Upgrade 10542 WWTP Air Permit Revisions 0.00 4,000.00 (4,000.00) 0.00% 10543 WWTP Spill Prevention, 0.00 5,000.00 (51000.00) 0.00% Control and Countermeasure (SPCC) Pla Total OPERATING COSTS 1,377,880.73 730,984.50 646,896.23 46.95% TOTAL EXPENDITURES 1,377,880.73 730,984.50 646,896.23 46.95% U te: 3/5/15 03:33:42 PM page: 1