HomeMy WebLinkAboutAIA Agreement with Wright Brothers for Storey Park Development - Bid Package No. 4: Prime Bid PackageInit.
#AIA Document A132rn —2009
Standard Form ofAgreement Between Ownerand ContractorConstructionManageras
Adviser Edition
Bid Package No. 4— Prime Bid Package
ADDITIONS AND DELETIONS:
AGREEMENT made as of the Twenty-second day of December in the year Two Thousand
The author of this document has
Fourteen
added information needed for Its
(in words, indicate day, month and year.)
completion. The author may also
have revised the text of the original
BETWEEN the Owner:
AIA standard form, An Additions and
(Name,. legal slants, address and other information)
Deletions Report that notes added
information as well as revisions to the
City of Meridian -
standard form text is available from
33 East Broadway Avenue
the author and should be reviewed. A
Meridian, Idaho 83642
vertical line in the left margin of this
document Indicates where the author
and the Contractor:
has added necessary Information
(Name, legal status,address and other information)
and where the a. or
t.
-
AIA lentadded
deleted from the original .
Wright Brothers, The Building Company, Eagle LLC
This document hes important legal
PO Boz 877
consequences; Consultation with an
Eagle, Idaho 83616 -
attorney is encouraged with respect
Telephone Number: 208-938-6000
to Its completion or modification.
Fax Number: 208-938-6069
This document Is Intended to be used
In conjunction with AIA Documents
for the following. Project:
A232--2009, General Conditions of
(Name, location and detailed description) -
the Contract for. Construction,
-
Construction Manager as Adviser
Storey Park: Development -
Edition; B132--2009, Standard
I. 430 East WatertowerLane
Form of Agreement Between Owner
Meridian, Idaho 83642
and Architect, Construction Manager
as Adviser Edition; and
The Construction Manager:
C132--2009, Standard Form of
(Name, -legal stalus, address and other it1formalion)
Agreement Between Owner and
Construction Manager as Adviser.
Kreizenbeck, LLC DBA Kreizenbeck Constructors,
AIA Document A232r —2009 is
1.1724 West Executive Drive
adopted in this document by
Boise, Idaho 83713'. -
reference. Do not use with other
Telephone Number: (208).336-9500
general conditions unless this
Fax Number:. (208) 336-7444
document is modified.
The Architect:
(Name, legal statils, address and other information)
Insight Architects, P.A.
2238 South: Broadway Avenue
Boise, Idaho 83706
Telephone Number: (208) 338-9080
The Owner and Contractor agree as follows.
TABLE OF ARTICLES
THE CONTRACT DOCUMENTS
THE WORK OF THIS CONTRACT
DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
10 INSURANCE AND BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other
Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed
in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are
as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract, together with the
performance bond and payment bond, if any, represent the entire and integrated agreement between the parties hereto
and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the
Contract Documents,. other than Modifications, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The. Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in
the Contract Documents to be the responsibility of others.
Contract Requirements: Provide all labor, material and equipment to complete the restroom building and
shade shelters per the listed specification Divisions/Sections in their entirety, as noted in the construction
documents: and per the following: -
Division 'I'—General Requirements, Complete Division 9 —Finishes, Complete
Division — Masonry, Complete Division 10 -Specialties, Complete
Division 6— Plastic and Composites,. Complete Division 22— Plumbing, Complete
Division 7—Thermal and Moisture Protection, Complete Division 23 -Heating, Ventilating & Air Conditioning
Division.8 —Openings, Complete ** As applicable to this scope of work
This contract specifically includes but is not limited to:
• Provide `lifting and hoisting of materials and equipment as required to complete work in this work package.
• Remove and dispose of all refuse and debris generated by work in this work package to construction
dumpsters provided by Construction Manager unless noted otherwise.
+ Provide and install all anchors and fasteners required to attach work within this work package. This includes
miscellaneous materials, clips or tabs in addition to anchors and fasteners that might be required to complete
attachment of the required work.
• Drilling and epoxy as required to complete all work as noted above.
• Famish and install blocking and backing as required for all work in this work package.
• Provide all temporary protection, masking and cleanup of adjacent surfaces while performing work in this
work package.
• Repair adjacent surfaces if damaged through work performed in this work package.
AIA Document A102^ — 2009 `formerly A101 -CMB— 1992). Copyright m 1975, 1980. 1992 and 2009 by The Amedll d
cen Institute of Archlteole. Ag
Init• ....... a w..Ymn• ihle EIA nn.•umnnl Is nmlanlaA by II R. Cnnudnhr Ln and Intamaannal Tmallaa nnaulhodind nonmd.etion mi letrlr
an uvutmulo, ena 15. not rar
(608666155)
• Include excavation and backfill for own work.
• Provide all labor, material and equipment to furnish and install all CMU as indicated by the construction
documents.
• Provide and install all masonry rebar and grouting as indicated by the construction documents.
• Furnish and install all rough carpentry in accordance with the construction documents.
• Furnish and install FRP panels as indicated by the construction documents.
• Furnish and install all building insulation in accordance with the construction documents.
• Furnish and install all joint sealants as applicable to work in this work package.
• Furnish and install penetrating fire stopping sealants as applicable to work in this work package.
• Furnish and install all hollow metal frames, wood doors and door hardware in accordance with the
constructiondocuments.
• Final. adjustment of doors as necessary to meet approval of Owner, Architect and Construction Manager.
• Provide construction and permanent cylinders and keying in accordance with construction documents.
• Prep all hollow metal door frames as required to receive electronic hardware. Coordinate with electrical.
• Provide .labor, material and equipment to complete all painting in accordance with the construction
documents.
• Provide and install anti-graffitti coating on all exterior masonry surfaces.
• Furnish and install all shade shelters in accordance with the construction documents. Structures and concrete
foundations shall -be designed as part of this package. Foundations shall be placed by the site contractor.
Anchor bolts shall be provided by this package and installed by site contractor.
• Complete all building plumbing and extend 5' from building foundation
• Complete :all HVAC in accordance with construction documents.
• Provide temporary: power and lighting as required to complete this scope of work.
• Provide weather protection and temporary heat as required to complete work scope.
• Provide. final cleaning of restroom building and shade shelters at substantial completion.
This contract specifically excludes:
• Site and building electrical
-
•-Siteutilities
• Excavation, backfill; concrete foundations, underslab vapor barriers, underslabrigid insulation and concrete
slab on grade for restroom building and shade shelters.
• Installation or finishing of pipe bollards in parking lot.
• Parking lot signage.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§; 3.1 The date of commencement of the Work shall be the dale of this Agreement unless a different date is stated
below or provision is made for the date to be fixed in a notice to proceed issued by the Owner.
(Insert the date ofcommencement, ifit dgersfrom the dale ofthisAgreement or, ifapplicable, state that the date will
he fixed in a notice lo proceed.).
The commencement date will be fixed in a notice to proceed.
If, prior to the commencement of the Work, the Owner requires time to file mortgages, mechanics' liens and other
security interests, the Owner's time requirement shall be as follows:
§,3.2 The Contract Time shall be measured from the date of commencement.
§ 3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than ( ) days from the date
of commencement, or as follows:
(Insert number ofcalendar days. Alternatively, a calendar date may be used when coordinated with the date of
commencement. Ifappropriate, insert requirementsfor earlier Substantial Completion ofeer9ain portions ofthe
AIA Document A132 - 2009rm
: roeriy A101 wCMa-1992). Copyright m 1975,1980, 1992 and 2009 by The Amencen Institute of Architects. All rights
]nit. AIA reserved. WARNING: This AIA Document le protected by U.S. Copyright Lew and International Trestles. Unauthorized reproduction or dletrlbulion
this AIA° Document, or any portion or It, may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent possible un
1 the law. This documenlwas produced by AIA software at 09:24:39 on 12/3112014 under Order No,6527595385_7 which expires on 0110712016, and is not for
resale.
User Notes: (909666166)
The work shall be substantially complete by July 2, 2015.
(Table deleted)
subject to adjustments of this Contract Time as provided in the Contract Documents.
(Insert provisions, Ifany, for liquidated damages relating tofailur a to achieve Substantial Completion on time orfor
bonus payments for early completion of the Work.)
In the event the Contractor, without excuse, fails to achieve Substantial Completion within the Contract Time, the
Contractor shall pay to. the Owner as liquidated damages, and not as a penalty, the sum of One Thousand Dollars
($1,000.00) or V4% the Contract Value (whichever is greater) for each and every calendar day following the end of
the Contract Time until Substantial Completion is achieved; provided that the Contractor shall not be liable for
liquidated damages for aday, or days of the excusable delay occurring during such period following the end of the
Contract Time.
ARTICLE 4 CONTRACT SUM
§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the
Contract. The Contract Sum shall be one of the following:
(Check the appropriate box.)
[ X:]:. Stipulated Sum, in accordance with Section 4.2 below
-[ ] Cost of the Work plus the Contractor's Fee without a Guaranteed Maximum Price, in accordance
with Section 4.3 below
- [ ] Cost of the. Work plus the Contractor's Fee with a Guaranteed Maximum Price, in accordance with
Section 4.4'below
(Based on the selection above, complete Section 4.2, 4.3 or 4.4 below. Based on the selection above, also complete_
either Section 5.1.4, 5. 1.5 or 5.1.6 below)
§ 4.2 Stipulated Sum
§ 4.2.1 The Stipulated Sum shall be One Hundred Twenty-six Thousand One Hundred Twenty-six Dollars and Zero
Cents ($126,126.00 ), subject to additions and deletions as provided in the Contract Documents.
Base Bid $0,00
Alternate No.I _ NOT ACCEPTED
Alternate No. 2 $0.00
Alternate No. 3 $86,707.00
- Alternate No. 4 $39,419.00
Alternate No. 5 $0.00
Alternate No 6 $0.00
TotalContract Amount $126,126.00
§ 4.2.2 The Stipulated Sum is based on the following alternates, if any, which are described in the Contract Documents
and are hereby accepted by the Owner:
(State the numbers or other identification ofacceptedalternates. Ifthe bidding orp•oposal documents permit the
- Ownerto accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other
alternates sholving the amount for each and the date when that amount expires.)
Alternate No. 2 - (toad Connection with Additional Parking: Refer to Sheets L1.3, GD.2.2, GD.3.1, and SO. LL
Alternate No. 3 - Restroom Building: Refer to Sheets LI A, A1.1, A2.1, A2.2, A2.3, A3.1, A4.1, MG0.0, MG0.1, M1.0,
M2.0, M3.0, EG0.0, E0.1, El. 1, E1.2, and E2.0.
Alternate No. 4 - Large Shelters: Refer to Sheet LI.1 and Spec Section 107300 Shade Shelters.
Alternate No. 5 - Synthetic Turf: Refer to Sheet LI.I and Spec Section 321813 Synthetic Turf Surfacing.
AIA Document A132-- 2009. foneerly A10"CMa-1992). Capydght ®1975. 1960, 1992 and 2009 by The Amedwn Institute of Architects. All rights
lull• reserved. WARNING: This AIA Document Is protected by U.S. Copyright Lew and International Trestles. Unauthorized reproduction ordletribullon of 4
this Ale Document, or any portion of It, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under
the law. This document was produced by AIA saftwere at 09:24:39 on 12/31/2014 under Order N%65275953851 which expires on 0110712015, and is not for
resale.
User Notes: (606666155)
Alternate No. 6 -.Irrigation Pipeline Replacement: Refer to Sheet GiRR.I.
§.4.2.3 Unit prices, if any:
(/dentfy and state the rmil price, and slate the quanfily limitations, ifany, to which the emit price will be applicabk.)
Item Units and Limitations Price per Unit ($0.00)
§, 4.2.4 Allowances included in the Stipulated Sum, if any:
(Identify allenvance and state exclusions, if any, from the allowance price.)
Item
Allowance
(Paragraphs deleted)
(Table deleted)
(Paragraphs deleted). -
(Table deleted)
(Paragraphs deleted)
(Table deleted)
(Paragraphsdeleted)
ARTICLE 5 PAYMENTS
§ 5.1 Progress Payments
§ 5.1.1 Based upon: Applications for Payment properly submitted to the Construction Manager by the Contractor, and
upon certification of the Project Application and Project Certificate for Payment or Application for Payment and
Certificate for Payment by the Construction Manager and Architect and issuance by the Architect, the Owner shall
make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the
Contract Documents.
§. 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the
month, or as follows:
§. 5.1.3 Provided that an Application for Payment is received by the Construction Manager not later than the
Twenty-fifth day of a month, the Owner shall make payment of the certified amount in the Application for Payment to
the Contractor not later than the Twenty-fifth day of the following month. If an Application for Payment is received
by the Construction Manager afterthe application date fixed above, payment shall be made bythe Owner not later than
Thirty ( 30 ). days after the Construction Manager receives the Application for Payment.
(Federal, state or local laws: may require payment within a certain period of time)
§ 5.1.4 Progress Payments Where the Contract Sum is Based on a Stipulated Sum
§ 5.1.4.1 Each Application for Payment shall be based on the most recent schedule of values submitted by the
Contractor and approved in writing by the Construction Manager and Architect in accordance with the Contract
Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work and
be prepared in such form and supported by such data to substantiate its accuracy as the Construction Manager and
Architect may require. This schedule, when, and only when, approved in writing by the Construction Manager or
Architect, shall .be used as a basis for reviewing the Contractor's Applications for Payment.
§`5.1.4.2 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end
of the -period rcovered by the Application for Payment.
§ 5.1.4.3 Subject to the provisions ofthe Contract Documents, the amount of each progress payment shall be computed
as follows:
AIA Document A132--20081formerly A10"Clde-1992).Copyright 01975.1980,1992and 2009 by The Amedcan lns6tute of Architects.. Ail rights
toll• reserved. WARNING: This AIAp. Document Is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution
this AJAs Document, or any portion of It, may result In severe civil and criminal penalties, and will he prosecuted to the maximum extent possible um
the law. This document was produced by AIA software at 00:24:39 on 12/3112014 under Order No.6527595385_7 which explres an 0110712015, and Is not for
resale..
UserNotes: 808666155)
.1 Take that portion of the Contract Sum properly allocable to completed Work as determined by
multiplying the percentage completion of each portion of the Work by the share of the total Contract
Sum allocated to that portion of the Work in the approved schedule of values, less retainage of Five
percent ( 5.00 %). Pending final determination of cost to the Owner of changes in the Work, amounts
not in dispute may be included as provided in Section 7.3.9 of the General Conditions, as modified;
.2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and
suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in
writing in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less
retainage. of Five percent ( 5.00 %);
.3 .Subtract the aggregate of previous payments made by the Owner;
.4 Subtract amounts, if any, for which the Construction Manager or Architect has withheld or nullified a
Certificate for Payment as provided in Section 9.5 of the General Conditions, as modified; and
.5 Subtract amounts, if any, being withheld by the Owner or Construction Manager as provided in the
Contract Documents.
§ 5.1.4.4 The progress payment amount determined in accordance with Section 5.1.4.3 shall be further modified under
the following circumstances:
.1 Add,:: upon Substantial Completion of the Work, a sum sufficient to increase the total payments to
Ninety-five percent ( 95.00 °/s) of the Contract Sum, less such amounts as the Construction Manager
recommends and the Architect determines for incomplete or defective Work, or both and unsettled
claims; and
.2 Add, iffinal completion ofthe Work is thereafter materially delayed through no fault of the Contractor,
any additional amounts payable in accordance with Section 9.10.3 of the General Conditions, as
modified.
§ 5,1.4.5 Reduction or limitation of retainage, if any, shall be as follows:
(Ifitis intended,prior to Substantial Completion ofthe entire Work to reduce or limit the retainage resullingfrom the
percentages inserted in Sections 5.1.4.3.1 and 5.1.4.3.2 above, and this Is not explained elsewhere in the Contract
Documents, insert here provisions for such redaction or limitation.)
Noreduction in retainage will be allowed prior to final completion without written approval of the Owner.
(Paragraphs deleted)
§ 5.1.4.6 A condition will be included forbidding more retainage from a contractor or supplier than retained from their
portion ofthe Work..
§ 5.2 Final Payment
§ :5.2.1: Final payment,constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the
Contractor when
_I the Contractor has fully performed the Contract except for the Contractor's responsibility to correct
Work as provided in Section 12.2 of AIA Document A232-2009 as modified, and to satisfy other
requirements, if any, which extend beyond final payment;
.2 the Contractor has submitted a final accounting for the Cost of the Work, pursuant to Exhibit A,
Determination of the Cost of the Work when payment is on the basis of the Cost of the Work, with or
without a Guaranteed Maximum payment; and
3 a final Certificate for Payment or Project Certificate for Payment has been issued by the Architect; such
final payment shall be made by the Owner not more than 30 days after (1) the Contractor has fully
performed the Contract and (2) the issuance of the final Certificate for Payment or Project Certificate
for Payment, or as follows:
ARTICLE 6 DISPUTE RESOLUTION
§ 6.1 Initial Decision Maker
The Architect will serve as In itial Decision Maker pursuant to Section 15.2 of AIA Document A232-2009 as
modified, unless the parties appoint below another individual, not a party to this Agreement, to serve as Initial
Decision Maker.
AIA Document A132m — 2009.Vonnedy A101-Clis-1992). Copyright 01975, 1980, 1992 and 2009 by The American Institute of Architects. All Fights
InIL reserved:. WARNING: This AIADocument Is protected by. U.S. Copyright Lew and International Trestles. Unauthorized reproduction ordletdbutlon of 6
the law. This document was produced by AIA software at 09:24:39 an 1213112014 under Order No.8527696385 1 which ezplres an 011072016, and Is not for
resale.
User Notes: (606666166)
(If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if
other than the Architect.)
§ 6.2 Binding Dispute Resolution
For any Claim subject to, but not resolved by, mediation pursuant to Section 15.3 of AIA Document A232-2009 as
For
the method of binding dispute resolution shall be as follows:
(Check the appropriate box. If the awter and Contractor do not select a method of binding dispute resolution below,
or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be
resolved by litigation in a court of competent jurisdiction.)
[ ] Arbitration pursuant to Section 15.4 of AIA Document A232-2009.
JX] Litigation in a court of competent jurisdiction.
[ ] Other: (Specify)
ARTICLE 7 TERMINATION OR SUSPENSION
§ 7.1 Where the Contract Sum Is a Stipulated Sum
§ 7.1.1 The Contract maybe terminated by the Owner or the Contractor as provided in Article 14 of AIA Document
A232-2009 as modified.
§ 7.1.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A232-2009 as
modified.
(Paragraphs deleted)
ARTICLE 8 MISCELLANEOUS PROVISIONS
§ 8.1 Where reference is made. in this Agreement to a provision of AIA Document A232-2009 as modified or another
Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the
Contract Documents.
§ 8.2 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated
below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.
(Insert rateofinterest agreed upon, (f any.)
-3/4 of 10/e per month .
§ 8.3 The Owner's representative:
(Name, address and other information)._
Keith Watts, Purchasing Manager
- City of Meridian
Purchasing Department_
33 East Broadway Avenue -
Meridian, Idaho 83642
§' 8.4 The Contractor's. representative:
(Name, address and other information)
Tom Andrews
Telephone Number: 208-938-6000
Mobile Number: --208-353-4535
Email Address: tandrews@wbtbc.com
§ 8.5 Neither the Owner's nor the Contractor's representative shall be changed without ten days written notice to the
other party.
§ 8.6 Other provisions:
AIA Document A132TM-2009 formerly AIOI-CMa-1992).Copydghl01975,1900. 1992 and 2009 by The American Institute of Architects. All rights
IOIL reserved. WARNING: This AIAt Document Is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of 7
this AIA? Document, or any portion of it, may reeult In severe civil and criminal penalties, and will be prosecuted to the maximum extentposslbie under
r
the law. This document was produced by AIA software at 09:24:39 on 12131/2014 under Order No.65275953861 which expires on 0110712015; and is not for
(808666166)
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
§ 9.1 no Contract Documents, except for Modifications issued after execution ofthis Agreement, are enumerated in
the sections below.
§ 9.1.1 The Agreement is this executed AIA Document A132-2009 as modified, Standard Form of Agreement
Between Owner and Contractor, Construction Manager as Adviser Edition.
§ 9.1.2 The General Conditions are, AIA Document A232-2009 as modified, General Conditions of the Contract for
Construction, Construction Manager as Adviser Edition.
§ 9.1.3 The Supplementary and other Conditions of the Contract:
Document Title Date Pages
Exhibit A Contract Document Schedule 12/22/2014 2
§ 9.1.4 The Specifications: -
(Either list the Specifications here or refer to an exhibit attached to this Agreement.)
Title of Specifications exhibit:. Contract Document Schedule, Exhibit A, dated December 22, 2014
(Table deleted)
§ 9.1.5 The Drawings:.
(Either list the Drawings here oi-referto an exhibit attached to this Agreement)
I: Title of Drawings exhibit: Contract Document Schedule, Exhibit A, dated December 22, 2014
(Table deleted)
§ 9.1.6 The Addenda, if any:
Number Date Pages
One 12/15/2014 2
Portions. of Addenda relating to bidding requirements are not part of the Contract Documents unless the bidding
requirements are also enumerated in this Article 9.
§ 9.1.7 Additional documents, if any, forming part of the Contract Documents are:
.1 AIA DocumentA132Tm-2009, Exhibit A, Determination of the Cost of the Work, if applicable.
.2 AIA Document E201T —2007, Digital Data Protocol Exhibit, if completed, or the following:
N/A
.3 ATA Document E202Tm-2008, Building Information Modeling Protocol Exhibit, if completed, or the
following:
N/A
.4 Other documents, if any, listed below:
( (List here any additional documents which are intended to form pail of the Contract Documents. AIA
Document A232-2009 provides that bidding requirements such as advertisement or invitation to bid,
Insh7ictions to Bidders, sample forms and the Contractor's bid are not part of the Contract Documents
c intless enumerated in this Agreement They should be listed here only if intended to be part of the
Contact Documents.)
AIA Document A132-- 2009 formerly A101 -Clue —1992). Copyright m 1975, 1980, 1992 and 2009 by The Amedcon Institute of Architects. All rights
Init reserved,. WARNING: This AIA Document Is protected by U.S. Copyright Law and International Tissues. Unauthorized reproduction or distribution of 8
This AIA° Document, or any portion of It, may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under
the law. This document was Droduced by, AIA software at 09:24:39 on 1213172014 under Order No.6527695385_1 which expires on 0110712015, and Is not For
(608666166)
All binding documents including the Invitation to Bid, Instructions to Bidders, Supplemental
Instructions to Bidders, Bid Proposal Forms, and the Project Schedule are intended to be part of the
Contract Documents.
ALA Document A232-2009 General Conditions
Exhibit A, Contract Document Schedule dated 12/22/2014
ARTICLE 10 INSURANCE AND BONDS
The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 11 of AIA Document
A232-2009 as modified
Refer to Supplemental Conditions modifying AIA Document A232-2009 for changes and additions to Article l I
"Insurance and Bonds".
Contractor is required to provide 100% Payment and Performance Bonds.
(State bonding requirements, if any, and limits of liabilityfor insurance required in Article 11 of AIA Document
A232-2009.)
Type of Insurance or Bond Limit of Liability or Bond Amount ($0.00)
Thisto as of the day and year first written above.
0 7WO, ro-�,
r lt-e
OWNER 'Signo/ CO TRACTOR (Signature)
Tammy de Weerd , Mayor >% �� "Stir'✓ p �'ti J'P/`
(Printed name and title) (Printed name and title)
AIA Document At 32TM-2009 formerly Al 01-CMa— 1992). Copyright ®1975,1980, 1992 and 2009 by The American Institute of Architects. All rights
Init. reserved. WARNING: This AIA Document Is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of 9
this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under
/ the law. This document was produced by AIA software at 09:24:39 on 12/31/2014 under Order No.6527595385_1 which expires on 01/07/2015, and is not for
resale
User Notes: (808666155)
CONTRACT DOCUMENT SCHEDULE (EXHIBIT A)
City of Meridian
Storey Park Development
430 E Watertower Street
Meridian, Idaho 83642
KC PROJECT NO. 14.085
December 22, 2014
PROJECT DOCUMENTS as issued by Insight Architects, P.A. and prepared by the following
project team:
Architect - Insight Architects, P.A.
Structural Engineer -AHJ Engineers, PC
Civil Engineer -Erickson Civil
Landscape Architect - Jensen Belts Associates
Mechanical Engineer- Musgrove Engineering, P.A.
Electrical Engineer - Musgrove Engineering, P.A.
Construction Manager- Krelzenbeck Constructors
PROJECT MANUALS
Instructions to Bidders, Complete- Dated November 21, 2014
Project Manual, Complete - Dated November 21, 2014
ADDENDUMS
Addendum No. One- Dated December 15, 2014
DRAWINGS - Dated November 21, 2014
A.01 Cover Sheet
Civil
C1.0 Cover Sheet
C1.1
Notes
C1.2 Topographic Survey
GD.0
Overall Grading Plan & Earthwork Req.
GDA Grading & Drainage Plan -Area 1
GD.2.0
Grading & Drainage Plan -Area 2
GD.2.1 Grading & Drainage Plan -Area 2 (Ail #1)
GD.2.2
Grading & Drainage Plan -Area 2 (Alt #2)
GD.3.0 Section Views (Base Bid)
GD.3.1
Section Views (Alt #1 W Alt #2)
GD.3.2 Internal Pathway Alignments
GD.3.3
Internal Pathway Proflles -1
GD.3.4 Internal Pathway Profiles -2
GDA
Roadway Profile&Details -1
GD.5 Details -2
GD.6
Details -3
SDA Storm Drain Base Bid & Alt #1)
SD.1.1
Storm Drain (Alt #2)
SD.2 Storrs Drain Details -1
SD.3
Storm Drain Details -2
GIRRA Gravity Irrigation (Alt #6)
UTA
Utility Plan
SPA SWPPP- Cover Sheet
SP.2
SWPPP Plan Sheet
SP.3 SWPPP-Details
Landscape
L1.1 Site Plan - Areal
L1.2
Site Plan -Area 2
L1.3 Site Plan -Area 2
L2.1
Landscape Plan -Areal
L2.2 Landscape Plan -Area 2
L2.3
Landscape Plan -Area 2
L3.1 Irrigation Plan -Area 1
L3.2
Irrigation Plan -Area 2
L3.3 Irrigation Plan -Area 2
Architectural
A1.1 Floor Plan, Roof Plan, Roof Framing Plan, Reflected Calling Plan, Foundation
Plan
A2.1 Building Sections, Details
A2.2
Details
A2.3 Details
A3.1
Exterior Elevations, Interior Elevations
A4.1 General Structural Notes / Schedules
Mechanical
MG0.0 Mechanical Cover Sheet
MG0.1
Energy Code Compliance
M1.0 Mechanical Plans
M2.0
Mechanical Details
M3.0 Mechanical Schedules
Storey Park Development
Page 1 of 2
December 22, 2014
Electrical
EG0.0 Electrical Cover Sheet $ Details EG7.0 Lighting Compliance Forms
E1.1 Electrical Site Plan —Area 1 E1.2 Electrical Site Plan—Area 2
E2.0 Electrical Plans $ Schedules
Storey Park Development
Page 2 of 2
December 22, 2014