HomeMy WebLinkAboutTask Order 10268 with SPF Water Engineers for Reuse Tank Mixing and Disinfection Improvements Project WWTPTASK ORDER NO. 10268
Under the
MASTER AGREEMENT FOR PROFESSIONAL SERVICES
BETWEEN
CITY OF MERIDIAN (OWNER) AND SPF WATER ENGINEERING (ENGINEER)
This Task Order is issued by Owner and accepted by the Engineer pursuant to the mutual
promises, covenant and conditions contained in the Master Agreement (Category 2A) between the
above named parties dated April 13, 2010.
WASTEWATER TREATMENT PLANT
Reuse Tank Mixing and Disinfection Improvement Project
PURPOSE
Engineer shall prepare a preliminary engineering report and construction plans and specifications
to install a new tank mixing and disinfection control system for the reuse facility at the City's
Wastewater Treatment Plant (WWTP). The tank mixing and disinfection control system shall
provide operational control over the reuse disinfection scheme and monitoring and meet permit
conditions.
The preliminary engineering report will discuss tank mixing and disinfection control alternatives and
summarize the recommended improvements and associated estimated costs. After City review
and approval of the recommendations, Engineer shall prepare a final preliminary engineering
report for DEQ review and approval. Following the preliminary engineering report approval from
DEQ, Engineer shall submit construction plans and specifications to DEQ for review and approval.
Engineer shall assist the City through the construction bidding process.
Project Deliverables include:
• Draft Preliminary Engineering Report for City Review
• Final Preliminary Engineering Report for DEQ Review and Approval
• Construction Plans and Specifications (DEQ Review and Final Bid Package)
• As-Builts
The Anticipated Project Schedule:
• Draft Preliminary Engineering Report — completed within 21 days of notice to proceed
• Final Preliminary Engineering Report — completed within 7 days of receiving City comments
(anticipate 4 to 6 weeks for DEQ review and approval)
• Construction Plans and Specifications — completed within 21 days of Final Preliminary
Engineering Report (anticipate 4 to 6 weeks for DEQ review and approval)
1 OF 2
Engineer shall prepare the construction plans and specifications concurrently with the preliminary
engineering report review period by DEQ. Immediately after DEQ approval of the preliminary
engineering report, the plans and specifications will be submitted to DEQ.
Exclusions — Electrical and control design or programming services are not included in this Task
Order. After the preferred alternative is identified by the City, and City has acquired a firm to
provide necessary electrical and control design for project bidding purposes, Engineer will
coordinate with the selected engineering firm to incorporate their construction documents into the
project bid package.
COMPENSATION
The Not -to -Exceed amount for the engineering services to complete this Task Order No. 10268 is
fifteen thousand dollars ($15,000.00).
Costs will be billed for actual time services are rendered up to the Not -to -Exceed amount. The hourly
rate for services and direct expenses are per the Master Agreement, and by this reference made a part
hereof. No compensation will be paid over the Not -to -Exceed amount without prior written approval by
the City in the form of a Change Order.
CITY OF MERIDIAN
BY:
KEIT ATTS,PURCHASING MANAGER
Dated: _. r'
Department Approval
BY: C� �
�' l�
Clint Dolsby, Assistant City Engineer
Dated: -71111.,
SPF WATER ENGINEER
BY:
Dated:
CATI-�Y OORER, MANAGER
2OF2