HomeMy WebLinkAboutChange Order No. 09 with Brown Construction for Victory Road Sewer ConnectionCITY OF MERIDIAN 33 EAST BROADWAY MERIDIAN, ID 83642 CONTRACT CHANGE ORDER CHANGE ORDER NO. 9 PROJECT NO. 10191 DATE: 5/4/2011 EFFECTIVE DATE: 5/4/2011 CONTRACTOR: BROWN CONSTRUCTION PROJECT: VICTORY ROAD SEWER CONNECTOR The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Description: The area of asphalt was more than calculated due to unstable material. Reason for Change Order: Upon excavating for the sewer installation the material was very sandy and unstable causing more roadway to be replaced than originally anticipated. Attachments: 1. CO #9 from Brown Construction showing the Increase in area and pricing for Asphalt 2. Purchase Order Requisition Form CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $ $ 365,115.75 Original Contract Times: 90 Net changes form previous Change Orders Net changes form previous Change Orders No._j_ to _8.. No. —to _ (calendar days) $ 3,480.81 0 Contract Price Prior to this Change Order: Contract Times prior to this Change Order: (calendar days) $ 368,596.56 90 Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order: (calendar days) $ 4,590.00 0 Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders: (calendar days) $ 373,186.56 90 APPROVED: {CIN Pl! HAS[N ENT ACCEPTED- o raco ff By: Keith Watts Date: , /' Date: 5 RECOMMENDED: (Assislant City Engineer) DATE APPROVED BY COUNCIL By: Clint Dolsby NO SIGNATURE REQUIRED Date: 5A I I, t DATE: