CONTRACT CHANGE ORDER
CHANGE ORDER NO.
2
PROJECT NO.
10191
DATE:
3/10/2011
EFFECTIVE DATE:
3/10/2011
CONTRACTOR: BROWN CONSTRUCTION
PROJECT: VICTORY ROAD SEWER CONNECTOR
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description:
REIMBURSE BROWN CONSTRUCTION (BCI) FOR IDAHO POWER ENGINEERING FEES
Reason for Change Order:
MOVING EXISTING POWER POLES REQUIRED ENGINEERING PRIOR TO BEING BE MOVED.
CITY AGREED TO REIMBURSE BCI THE FEES IF THEY PAID THEM SO IDAHO POWER WOULD
PROCEED WITH THE ENGINEERING.
Attachments:
P.O. REQUISITION FORM
IDAHO POWER INVOICE TO BCI
IDAHO POWER RECEIPT TO BCI FOR PAYMENT
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price $ $ 365,115.75
Original Contract Times: 90
Net changes form previous Change Orders
Net changes form previous Change Orders
No._— to ,
No._ to ._ _ (calendar days)
$
0
Contract Price Prior to this Change Order:
Contract Times prior to this Change Order:
(calendar days)
$ 365,115.75
90
Net Increase (decrease) of this Change Order:
Net Increase (decrease) of this Change Order:
(calendar days)
$ 1,800.00
0
Contract Price with all Approved Change Orders:
Contract Times with all Approved Change Orders:
(calendar days)
$ 366,915.75
90
APPROVED: {CITY PURC)IAS►NGGE T)
ACCEPTED: ra r)
By: Keith Watts lowl
Date:,3 Z $ it
Date:
RECOMMENDED: ( struction Manager) _
DATE APPROVED BY COUNCIL
By: John Boyd
NO SIGNATURE REQUIRED
Date:3 /Z 3/V -':z0 I
DATE: