HomeMy WebLinkAboutChange Order No. 01 with Schmidt Construction Ten Mile Cherry to Ustick Reclaimed Water ProjectCITY OF MERIDIAN 33 EAST BROADWAY MERIDIAN, ID 83642 CONTRACT CHANGE ORDER CHANGE ORDER NO. 1 PROJECT NO. 06428 DATE: 4/25/2011 EFFECTIVE DATE: 4/25/2011 CONTRACTOR: SCHMIDT CONSTRUCTION PROJECT: TEN MILE - CHERRY TO USTICK - RECLAIMED WATER PROJECT The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Description: Compensation for extra work required to install the revised reclaimed water alignment. Reason for Change Order: Fiber optic cable was encountered when excavating for the bore pit to cross the Five Mile Creek. This cable was not marked by Westel during the design of the project. This made it impossible to install the bore pit anywhere to enable crossing the Five Mile Drain as originally planned. A re -design was accomplished which required more material and effort to be installed. Attachments: 1. Change Order #1 from Schmidt Construction showing an increase to contract price. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $ $ 520,236.00 Original Contract Times: 90 Net changes form previous Change Orders Net changes form previous Change Orders NONE No.— to _ (calendar days) $ - 0 Contract Price Prior to this Change Order: Contract Times prior to this Change Order: {calendar days) $ 520,236.00 90 Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order: (calendar days) $ 28,599.59 0 Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders: (calendar days) $ 548,835.59 90 APPROVED: (CITY PURCHAG 'ENT ACCEPT /Onttor) By: Keith Watts Date: 2 G ! Date: RECOMMENDED: 0 DATE APPROVED BY COUNCIL By: Clint Dotsby, Assistant City Engineer NO SIGNATURE REQUIRED Date: HhZ ) ( I i DATE: rsex�atr�s�rs►s�.r�sx�ar�xoxs�wF�xcr,�7��;:r�arrKk,:„��.c:�.rx;�:ni.�a.�:av,�����r=:+�cz•:.'«Y7 ritkLtC!-_�'7��C4Y!.NCAL�pfiFtiu7YetuFS7i#�IY�ti74St:s(�6751b�ifl7r# Ten Mile ReUse Pipeline 4/22/2011 PJW Chane Order #1 Pub. Works #16406 -AAA -1 LINE QUANT. UNIT DESCRIPTION UNIT PRICE AMOUNT Bid Items and Additions 1 318 SY Type P Repair $ 19.55 $ 6,216.90 2 60 LF Bore & Jack $ 338.00 $ 20,280.00 3 396 LF 16" PVC ReUse Main $ 50.50 $ 19,998.00 4 119 LF 16" PVC ReUse Main $ 30.00 $ 3,570.00 5 1 LS Traffic Control $ 1,995.00 $ 1,995.00 6 600 LF Silt Fence $ 3.00 $ 1,800.00 T 1 LS H droSeed $ 2,215.00 $ 2,215.00 8 1 LS Install Bends $ 6,826.70 $ 6,826.70 9 1 EA Install 24" x 16" MJ xFL T $ 6,015.00 $ 6,015.00 10 1 EA I R & R EAsting Valve $ 1,518.00 $ 1,518.00 11 5 Day Downtime $ 1,210.00 $ 6,050.00 12 13 Subtotal $ 76,484.60 14 Ad mstments 15 SY Type P Surface Repair $ 19.55 $ 3,088.90 16E.126 LF Bore & Jack $ 338.00 $ 42,588.00 15883 Robber Pi. Caldwell, 1D 83607 ph: 208-459-2461 fax: 208-453-4968 17 -119 LF 16" PVC ReUse Main $ 30.00 $ 3,570.00 18 191 Adjustments $ 49,246.90 20 21 Adjusted Total $ 27,237.70 22 23 1 EA 5% Administration f=ee $ 1,361.89 $ 1,361.89 24 25 Total $ 28,599.59 26 r. 27 28 29 Submitted 8y: Schmidt Construct' Pete Wilson Date: 30 31 32 33 34 35 Accepted 8y: � �� City of Meridian Date: y rLsr I I 36 37 38 39 40 41 42 43 44 45 Clarifications: 46 JAII Items will be final billed at unit price for actual completed units 47 Another change will occur when the bore contractor determines if he can or can't utilize the 48 extra steel casing on a different project 49 50