Loading...
HomeMy WebLinkAboutChange Order No. 01 with Civil Survey Consultants for Linder Pine Water Line ImprovementsCITY OF MERIDIAN 33 EAST IDAHO MERIDIAN, ID 83642 CONTRACT CHANGE ORDER Change Order No.: 1 Project Number: 10170 Date: 711412011 Effective Date: 7/14/2011 CONTRACTOR: Civil Survey Consultants PROJECT: Linder/Pine Water Line Improvements The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Desciption: 1) Additional design and investigation tasks. 2) Additional design and consultant duties regarding property easements. 3) 4) 5) Reason for Change Order: Change in Scope of work due to additional ACHD construction duties. Attachments: Letter of Request from Civil Survey Consultants CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: $10,955.00 Original Contract Completion Date: Original Contract Completion Days: Net changes from previous C.O.'s.: Net Days change form previous C.O.'s: No. 0 to 0 No. 0 to 0 $0.00 Contract Price Prior to this C.O.: Contract Completion Date before this C.O.: $10,955.00 Net Increase (decrease) of this C O.: Net Days Increase (decrease) of this C.O.: $5,904.00 Contract Price with all Approved C.O.'s: Contract Completion Date with all Approved C.O.'s: $16,859.00 RECOMMENDED: (CONSTRUCTION MAN ER) ACCEPTED (CONTRACTOR) By: By: Date: 7 Date: APPROVED: (CITY PURCHASING A T) COUNCIL APPROVAL By: Ke th Watts Date: — er Date: APPROVED: (CITY) � ATTEST: / By: Mayor Tammy de Weerd • / ► By: City Clerk, Jaycee Holman Date: Date: Civil Survey Consultants, Inc. Glenn K. Bennett, P.L.S. (208)8884312 President 1400 E. Watertower Street Fax 888-0323 Suite 100 Timothy A. Burgess, P.E. Meridian, Idaho 83642 Vice President July 12, 2011 Brent Blake City of Meridian 33 E. Broadway Avenue, Ste. 200 Meridian, ID 83642 Re: Pine Street and Linder Road Intersection - Additional Services Task Order No. 10170 Dear Brent: The following additional services are required for the Pine Street and Linder Road intersection water and sewer improvement project: I. An additional six potholes by Circle H Construction were required to locate the existing water mains and sewer services. 6 each @ $250::ea = $1500 2. Additional time to coordinate, stake, and map additional potholes Engineer 1 - 2 hrs @ $110/hr = $220 Survey Crew -- 1 hr @ $140/hr = $140 3. In conjunction with City Staff it was determined that some existing sewer service lines will need to be reconstructed due to a conflict with the new 36" RCP Irrigation line to be constructed underneath the sidewalk by ACHD. This required reviewing CCTV provided by the City and locating the existing sewer services. Reconstruction of the sewer services was added to the project plans, specifications, and cost estimate. Engineer 1 - 24 hrs @ $110/hr = $2,640 4. The City has requested that we prepare descriptions and maps for six easements and assist the City in obtaining property owner signatures. Easements are required for fire hydrants and water meters that must be placed on private property due to an insufficient amount of right-of-way behind the sidewalk. Engineer 1 - 7 hrs @ $110/hr = $770 Survey Crew 2 hr @ $140/hr = $280 Chief of Surveys — 3 hr @ $118/hr = $354 We are requesting $5,904.00 to cover the additional services. The revised total contract amount will be $16,859.00. Sincerely, CIVIL RV Y ONSULTANTS, INC. Corey Peacock, P.E.