CONTRACT CHANGE ORDER
CHANGE ORDER NO. 1
PROJECT NO.
DATE: 3/3/2011
EFFECTIVE DATE: 3/3/2011
CONTRACTOR: BROWN CONSTRUCTION, INC.
PROJECT: VICTORY ROAD SEWER CONNECTOR TRUNK -
The Contractor is hereby directed to make the following changes from the Contract Documents and
Plans.
Description: #1. Remove the requirement of the Contractor to pay Idaho Power for
temporarily relocating the power poles and seek reimbursement from the City. The City
will pay Idaho Power directly. #2 The City pay CabieOne directly for their share of the
costs for temporarily relocating the power poles. All other terms and conditions of
the Agreement remain in full force and effect, including but not limited to all scheduling
and coordination of all work including the above mentioned power pole relocation.
Reason for Change Order: To expedite Idaho Powers' temporary relocation of the power
poles.
Attachements: NONE
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price $ 365.115.75
Original Contract Times:
Net changes form previous Change Orders
Net changes form previous Change Orders
No._ to _
No._ to _ (calendar days)
$0.00
NONE
Contract Price Prior to this Change Order:
Contract Times prior to this Change Order:
(calendar days)
$365,115.75
90 Days
Net Increase (decrease) of this Change Order:
Net Increase (decrease) of this Change Order.
(calendar days)
$0.00
NONE
Contract Price with all Approved Change Orders:
Contract Times with all Approved Change Orders
(calendar days)
$365,115.75
90 Days
APPROVED: CITY PURCHASING MANA E