CC - Phasing Plan NarrativePhasing Plan for Rackham Subdivision/Eagle View Landing
The following description sets forth the phasing of the various elements for Rackham Subdivision/Eagle
View Landing. Each phase will satisfy the requirements of the Meridian UDC when it is constructed.
Due to the significant amount of perimeter frontage of the Property, we are proposing phased
completion of the buffer areas and perimeter improvements corresponding to each phase when that
phase is undertaken. It is the Applicant's intention to make the CZC, Design Review and Building Permit
submittals for Phase 1 immediately upon approval of the Development Agreement, and then shortly
thereafter on Phase 1A. The Phase 2 elements will follow, although the actual order of development
within Phase 2 will depend upon the requirements of its users and tenants. Phase 3 will commence
once the anchor medical users are committed and may proceed contemporaneously with elements of
Phase 2. Phase 4 will be included and addressed in future supplemental applications addressing the
elements of the seven acre parcel. We believe that this phasing plan will permit the Applicant to
undertake development activities for various elements of the project in a sequential manner that will
provide construction efficiencies and which will permit the sequential opening of various elements.
Phase 1 and 1A development would be contemplated to commence in the Summer of 2019 and other
phases to follow thereafter.
Phase 1— ICCU Building — initial office building
Entrance drive improvements
Buffer and improvements on parcel adjacent to Interstate
Phase 1A— East Building—second office building
Will be commenced after Phase 1 begins
Buffer and improvements on parcel adjacent to Interstate
Required improvements to shared access drive between Rackham and Silverstone
Phase 2 — Retail, Entertainment, and Hospitality Elements (actual order of elements to be determined)
Phase 2A — Commercial and retail elements east and west of entrance drive
Buffer along southern boundary of Phases to be improved
Phase 2B — Outdoor entertainment entity
Buffer and improvements on parcel adjacent to Interstate
Improvements along eastern boundary of Phase adjacent to property to east
Phase 2C— Hospitality element
Buffer along southern boundary of Phases to be improved
Phase 3 — Medical Office and Office
Buffer and improvements on parcel adjacent to Interstate
Phase 4 — Future Multifamily/Commercial/Office Use parcel
Improvements along eastern and southern boundary will be constructed adjacent to property to
east and south when Phase is developed